2. Tutorial Goal
Create Bill of Material (BOM) Redline
Add BOM Redline to Engineering Record (ER)
Assign Object Status and Change Relevance
Display Change Number (CN) and Validity Date on BOM Redline
Complete BOM Redline
Process Route: Send BOM Redline for review
21 October 2013
2
Copyrighted 2013 by LeverX, Inc.
3. BOM Redline:
Built-in support for review and approval process for redlines
Electronic method of proposing changes to the BOM
Includes color coded visual indication of changes to the BOM
21 October 2013
3
Copyrighted 2013 by LeverX, Inc.
4. Create BOM Redline:
Login SAP NWBC
Click Material BOM
Select Display Material
BOMs
Enter
Material, Plant, Usage
and Alternative
Click Continue
21 October 2013
4
Copyrighted 2013 by LeverX, Inc.
5. Create BOM Redline: Contd.
On Display
Material BOM
screen, click
Redlining
Click Create
Enter Name and
Description
Click Ok and click
Save
21 October 2013
5
Copyrighted 2013 by LeverX, Inc.
6. Assign BOM Redline to ER:
Click Add to
Engineering Record
Enter Existing
Engineering Record
Click Ok
Click Save
21 October 2013
6
Copyrighted 2013 by LeverX, Inc.
7. Assign Status and Chg. Relevance:
Enter INPR (In Process)
for Status and CHG
(Change) for Chg.
Relevance on the ER
Click Save
21 October 2013
7
Copyrighted 2013 by LeverX, Inc.
8. Display CN and Validity Date:
View CN and Validity
Date copied from the
ER
The CN allows the
user to track
changes made to the
BOM
21 October 2013
8
Copyrighted 2013 by LeverX, Inc.
9. Complete BOM Redline:
Change component quantity
(Green), add a new component
(Yellow), delete an existing
component (Red)
View color coded
representation of changes
Set redline status to Completed
Click Save
Perform Redline approval
process
21 October 2013
9
Copyrighted 2013 by LeverX, Inc.
10. Process Routes:
Process Route task is
created to send a
notification out to the
user to review and
approve BOM redline
Click Add Sequential
Task
Fill in required fields
and click Ok
Click Start Workflow
and click Save
21 October 2013
10
Copyrighted 2013 by LeverX, Inc.
11. Conclusion:
Easy to implement changes on a desired validity date
Simple method to update changes to the BOM
The electronic color coded review and approval process enables
users to track changes easily
Puts an end to manual paper based BOM Redlining techniques
21 October 2013
11
Copyrighted 2013 by LeverX, Inc.
12. Contact Information
Please contact us for more information about our services or solutions available.
LeverX, Inc.
800 West El Camino Real, Suite 180
Mountain View, CA 94040 USA
Tel: (650) 625 – 8347
Web Site: www.LeverX.com
21 October 2013
12
Copyrighted 2013 by LeverX, Inc.