SlideShare a Scribd company logo
1 of 34
Download to read offline
Three Recent SoP Cases
• St Hilliers Property v ACT Projects and Wilson
[2017] ACTSC 177 (20 July 2017)
• Quasar (Constructions) Commercial v Trilla Group
[2017] NSWSC 860 (22 June 2017)
• Probuild Constructions (Aust) v DDI Group
[2017] NSWCA 151 (23 June 2017)
David Campbell-Williams
Resolution Institute Adjudicators Discussion Evening
6 September 2017
St Hilliers Property v ACT Projects and Wilson
[2017] ACTSC 177 (20 July 2017)
Void determination- Jurisdictional error and manifest error
Cost exposure for Adjudicator
• 9 July 2014 ACT Projects, contracted to perform structural works for St Hilliers on
a project in Gungahlin ACT
• Works completed before 29 April 2015
• Between 20 May 2015 and 20 April 2016 ACT Projects served 12 almost identical
payment claims each related to the same completed works
• 20 June 2016 ACT Projects lodged an adjudication application
• 27 June 2016 Adjudicator filed notice of acceptance
• 4 July 2016 St Hilliers lodged its adjudication response
• Submissions sought and extension agreed that the Determination had to be made
on or by 22 July 2016
• Date met but minor amendments made on 25 July, and published 26 July
determining that St Hilliers owed ACT Projects $222,260.53
St Hilliers Property v ACT Projects and Wilson
[2017] ACTSC 177
Appeal under Administrative Decisions (Judicial review)
Act 1989 and an appeal from the determination on the
basis of error of law (as provided for in s43 ACT SoP Act)
s43(4) The Supreme Court must not grant leave under subsection (3) (b)
unless it considers that—
(a) having regard to all the circumstances, the determination of the question of
law concerned could substantially affect the rights of 1 or more parties to the
adjudication decision; and
(b) there is—
(i) a manifest error of law on the face of the adjudication decision; or
(ii) strong evidence that the adjudicator made an error of law and that the
determination of the question may add, or may be likely to add, substantially to
the certainty of the law.
St Hilliers Property v ACT Projects and Wilson
[2017] ACTSC 177
Three bases:
• that the payment claim had been served too late
• that a ‘reference date’ was a necessary prerequisite
to its service, and was absent at the time of service,
and
• that the Adjudicator had, in effect, delegated the
preparation of his adjudication by having someone
else prepare it (or taken into account something other
than the ACT s24(2) items/ matters) (22(2) in NSW
Act)
The payment claim had been served too late
ACT Section 15(4) provides:
(4) A payment claim may be given only before
the later of—
(a) the end of the period worked out under
the construction contract; and
(b) the end of the period of 12 months after
the construction work to which the claim relates
was last carried out or the related goods and
services to which the claim relates were last
supplied.
• (cf NSW s13(4))
The payment claim had been served too late
Cl 16.9 The subcontractor agrees to execute a CVA containing confirmation of the
matters dealt with in Schedule G and a release in favour of St Hilliers as a
precondition of final payment to the Subcontractor. The Unpaid Substantial
Completion Retention Release amount identified in the CVA is payable on
Substantial Completion and the Unpaid Final Retention Release amount is payable
at the end of the Defects Liability Period or when all defects have been remedied to
St Hilliers’ satisfaction, whichever is the later. Any Payment Claim which the
Subcontractor may have which is not included in the CVA or notified in writing to St
Hilliers within 7 days of issue of the CVA or notified in writing to St Hilliers within 3
business days of the commencement of the events giving rise to the Claim
(whichever is the earlier) (other than any claim for the return of Security or Retention)
shall be absolutely barred and forever released and discharged. Nothing in this
clause shall restrict the Subcontractor from defending or bringing a cross claim
(provided the cross claim related to the subject matter of the claim against the
Subcontractor) or a claim for contribution with respect to, any claim, action, suit of
proceeding [sic] brought by the Head Contract Principal against the Subcontractor.
The payment claim had been served too late
[42] I consider the adjudicator erred in finding in cl 16.9 a period within which
ACT Projects could serve its claim.
[43] I cannot see any way in which it shows “the end of the period worked
out under the construction contract.”
[44] First, the clause says ACT Projects agrees to sign an agreement.
Secondly, it provides what is to happen with the retention sum referred to in
that agreement. Thirdly, it bars certain payment claims. Fourthly, it preserves
to ACT Projects the right to defend or cross claim in any case brought
against it by the head contractor.
[45] Nowhere does it create any rights to serve payment claims. Nowhere
does it contain a mechanism to work out “the end of the period under the
construction contract”.
No reference date
Para 43 of St Hilliers submissions quoted at [62]
43 Accordingly, on the proper construction of this contract, a (new)
reference date can only ever accrue in a month where no construction work
was performed, in circumstances where a valid payment claim was not
submitted in the previous month (and construction work was done in that
earlier month). Where a valid payment claim was submitted in the previous
month, no new reference date can arise. This is because there is no work
under the Contract which can be claimed. For that reason, on a proper
construction of the Contract, the Payment Claim was submitted in relation to
the same reference date as all previous 12 payment claims. No new
reference date ever arose for those subsequent months, as with the last
one.
No reference date
[77] Clause 16.1, although permitting monthly claims, must be construed as having
limits to its operation, including time limits. For example it would be absurd to construe
it as having continuous operation, beyond the end of construction and payment of the
final payment.
[78] If, as I am satisfied it does, the clause has a time limit for its operation, that must
have been, at the latest, to the time for claiming a final payment.
[79] On its face the clause contemplates ongoing work occurring in the month
immediately before lodgement, unless a claim previously lodged had failed to comply
with relevant preconditions: see cl 16.4. Where there has been such a failure, another
claim could be lodged for the work in that claim, which in cl 16.4 is called a “lapsed
claim.”
[80] It was not suggested here the claim lodged on 20 May 2016 was such a claim.
[81] Thus in the context of this case, I accept Mr Miller’s submission that the words “to
that time” in cl 16.3(a) must mean to the date immediately before the lodgement of the
claim. As no work was done in the month before 20 May 2016, the claim was not
served on a reference date, and was invalid.
Impermissible Delegation
[117] I accept Mr Miller’s submission that the use of singular words in s 22,
such as “an adjudicator” (s 22(1), shows that the job of adjudicator is
personal to the person who agrees to adjudicate.
[118] I do not consider s 24(2) requires that an adjudicator work alone,
with no clerical or other assistance. Clearly, adjudicators must have some
assistance. In the end, whether the assistance amounts to a usurpation of
the task of adjudication must be a matter of degree.
[119] However, as much as Mr Wilson sought to say all the work was his, I
infer most was that of Mr Turner, and that he adopted Mr Turner’s work to a
substantial degree and put forward the final product as his own.
The Appeal under ACT BCI(SoP)Act s.43
s43(1) Except as provided for in this part, a court does not have jurisdiction to
set aside or remit an adjudication decision on the ground of error of fact or law
on the face of the decision.
s43(4) The Supreme Court must not grant leave under subsection (3)(b)
unless it considers that—
(a) having regard to all the circumstances, the determination of the question of
law concerned could substantially affect the rights of 1 or more parties to the
adjudication decision; and
(b) there is—
(i) a manifest error of law on the face of the adjudication decision; or
(ii) strong evidence that the adjudicator made an error of law and that the
determination of the question may add, or may be likely to add, substantially
to the certainty of the law.
The Appeal under ACT BCI(SoP)Act s.43
[138] The appellant contended that two errors of law had been made,
and each warranted allowing the appeal. The first concerned an issue
of waiver. The second, which I have dealt with above, concerned
whether the payment claim had been served on a reference date.
[139] For the reasons set out above as to the reference date, the
appeal must succeed. I am satisfied that in finding the payment claim
was served on a reference date, the adjudicator made an error of law.
[140] However I shall also consider the plaintiff’s argument that [the
Adjudicator] made an error of law when finding St Hilliers had waived
its right to insist that ACT Projects comply with contractual time limits.
Exposure to costs
Because the Adjudicator became actively involved in the proceedings, he
became exposed to a costs order.
[220] Despite the general rule that no order for costs be made against an
adjudicator, here, because of his active involvement in defence of his
position, I consider he should share some of the costs liability: Fernando v
Medical Complaints Tribunal at [21]. As did the tribunal member there, the
second defendant had an indemnity under the Act: s 37(1). That is an
additional factor I take account of on this issue: Fernando at [22].
Quasar (Constructions) Commercial v Trilla Group
[2017] NSWSC 860 (22 June 2017)
Determination not void by reason of want of Natural Justice
Stay also refused
Trilla had obtained a Determination of $462,000 incl GST
Quasar claimed:
• a declaration that the adjudicator's determination is void, and
consequential relief restraining Trilla from enforcing it; or in the event
that the primary case failed-
• an order restraining Trilla from enforcing the determination until such
time as Quasar's claim can be heard and determined.
Quasar (Constructions) Commercial v Trilla Group
• Quasar submitted to the adjudicator that the date of practical
completion was delayed by some 192 days from the date for
practical completion, in circumstances where the date for
practical completion (Quasar said) had not been extended. At
the rate of $13,000 per day for liquidated damages, that led to
the claim of the order of $2.5 million
• Trilla submitted that time was at large, because of Quasar's acts
of prevention. Those asserted acts of prevention included, apart
from the matters to which I have referred, the asserted failure to
appoint a superintendent who would manage
Quasar (Constructions) Commercial v Trilla Group
Quasar responded by denying some of the matters of fact to which Trilla
had referred. However, the principal argument advanced by Quasar was
that the prevention principle had no application because the contract
specifically made provision for extension of time. It relied on the judgment of
Rolfe J in Turner Corporation Limited v Coordinated Industries Pty Limited .
His Honour there held, in substance, that usually at least, the prevention
principle would only apply where the contract did not itself provide for the
consequences of the acts that were said to be breaches and acts of
prevention.
Quasar (Constructions) Commercial v Trilla Group
• Quasar's submissions then turned to cl 34.3 of the contract which
provided that Trilla would be entitled to extensions of time if Trilla:
▫ would be delayed (or had been delayed) by a "qualifying cause of
delay" to which it had not contributed itself:
▫ had given written notice within three days of becoming aware of the
causal event;
▫ that "the delay claimed affects the critical path of the progress of the
WUC“ and
▫ had taken all reasonable steps to mitigate the effects of the delay.
Quasar (Constructions) Commercial v Trilla Group
Quasar's submissions canvassed cl 34.3 and its application asserting that
no claim for an EOT had been made by Trilla.
Quasar also disputed that it had any obligation to provide a construction
program (coherent or otherwise) to Trilla.
It reiterated its submission that the prevention principle had no relevance,
and said that whatever the superintendent did or did not do had nothing to
do with the case.
Quasar (Constructions) Commercial v Trilla Group
The adjudicator then turned his attention to the real dispute, which was the
impact of the prevention principle on Trilla's claimed entitlements to EOTs
in circumstances where the contract made express provisions for EOTs in
cl 34.3.
He noted the requirement that the delay claimed must affect the critical
path of the progress of the WUC. He then said that although there was no
requirement for Quasar to provide a construction program, where it had
not done so (or had not updated the program initially provided), Trilla could
not comply with the requirements of that sub-paragraph because it simply
could not know whether the delay had had any impact on the critical path
of its works.
Quasar (Constructions) Commercial v Trilla Group
[20] Accordingly, the adjudicator concluded, the prevention principle
was no answer to Trilla's answer to the claim for liquidated
damages. Since it was the claim for liquidated damages that was
the principal offset, that removed a substantial obstacle to Trilla's
success.
[21] Trilla had submitted to the adjudicator, in the alternative, that if it
were wrong as to the application of the prevention principle,
nonetheless he should conclude, in the alternative, that he was
unable to determine the quantum of any liquidated damages. The
adjudicator referred to that alternative submission, but expressed no
view as to whether or not he was satisfied that it had been made
good.
Quasar (Constructions) Commercial v Trilla Group
[22] In the end (on this aspect of the dispute) the adjudicator decided
that Quasar could not set off liquidated damages, because Trilla was
unable to request an EOT in accordance with the provisions of the
contract. That was so, he said, because Trilla could not assess if a
qualifying cause of delay would have any impact on the critical path,
because the critical path had not been defined in an updated
construction program.
[23] …[Quasar] submitted that by deciding the question in this
fashion, the Adjudicator had decided it on a basis for which neither
party contended. In those circumstances, he submitted, there was a
material or substantial denial of natural justice.
Quasar (Constructions) Commercial v Trilla Group
[24] In my view, there was no substantial or material denial of natural
justice. It was Quasar itself that put cl 34.3 into issue, as an answer
to Trilla's claim insofar as that claim relied on the prevention
principle. Trilla had no ability to respond to Quasar's submissions on
that point. It was up to the Adjudicator to wrestle with the issue as
best he could.
[25] The factual material that the adjudicator took into account,
including the absence of a current construction program and the
consequences of that, were in the evidence before him. Quasar was
in a position to answer those factual matters, and to the extent that it
wished to do so, it did.
Quasar (Constructions) Commercial v Trilla Group
[26] The legal issue that Quasar presented was whether cl 34.3
imposed an insuperable obstacle to Trilla's defence (an inaccurate
but sufficient term for present purposes) of Quasar's response to
the adjudication application based on its claimed entitlement to set
off liquidated damages. Neither party could anticipate in any real
detail the way in which that argument might work out. But it was an
argument that had been put before the adjudicator, and it was an
argument that he dealt with, as best he could in the very tight
timeframe allowed by the [Act]…
Quasar (Constructions) Commercial v Trilla Group
[28] In my view, the issue having been raised, it was incumbent upon the
adjudicator to deal with it as best he could on the material provided. That,
I think, is precisely what he did. He may have been right or wrong in his
interpretation of the contract. But if he were, that would be an error within
jurisdiction, and nothing more
Stay refused
[33] Although it may not be true as a statement of absolute application, it is
undoubtedly correct to note that most of the cases where a stay has been
granted are cases where the claimant before the adjudicator has been
insolvent, or is undergoing some form of administration in insolvency, and
no longer trading. In those cases, as the Court said in Facade Treatment
Engineering, the rationale for allowing the statutory shift of the risk of
insolvency to continue is no longer applicable.
Stay refused
42 …Even if it should be held that, apart from the cross-claim, Trilla
were entitled to the full amount of $861,000 claimed by it, the resulting
debt in favour of Quasar, assuming it proved its entire claim for
liquidated damages, would be of the order of $1.6 m. It does not seem
to me that there is any real prospect that Trilla could repay that if called
upon to do so.
43 However, to reason in that way is to ignore the policy of the Act, and
the relevant aspects of its operation in relation to solvent trading
companies, that have been referred to in the intermediate appellate
court decisions that I have summarised above. The mere fact that an
amount might not be repaid does not justify withholding it until the
entitlement to that amount can be determined on a final basis.
Probuild Constructions (Aust) v DDI Group
[2017] NSWCA 151 (23 June 2017)
Determination not void by reason of want of Natural Justice; Appeal
dismissed.
Beazley ACJ McColl JA Macfarlan JA
on appeal from Meagher JA [2016] NSWSC 462 (20 April 2016)
Primary Judgment McColl JA
Challenge to Determination of $475,716 in favour of DDI had been dismissed
by Meagher JA
Probuild contended that the determination was infected by a denial of
procedural fairness (natural justice) in that the adjudicator rejected its
liquidated damages claim on bases which neither party had notified to the
other or contended for, and which the adjudicator had not notified the parties.
Probuild also asserted that had the adjudicator intended to so act, he should
have invited the parties to make further submissions, as he was empowered
to do under s 21(4) of the SOP Act
Extract from para 185 of Determination (@ [51])
“…Based on the submissions it appears that 80% of the contract variations
(approximately $1.4m) were directed by [Probuild] and executed by [DDI] after 5 January
2015. As the bulk of the contract variations were approved by [Probuild] it is assumed
[DDI] performed the work as directed by [Probuild].
It appears totally inconsistent and unreasonable for [Probuild] to be directing [DDI] to
perform significant additional work under the Subcontract after the original Date for
Practical Completion and then making a claim for LDs against [DDI] for following
[Probuild’s] express directions.
[Probuild] also states:
‘DDI has not been granted nor is it entitled to any extension of time.’
Under the Subcontract [Probuild] has the ability to extend time for any reason. Based on
the significance of the volume of additional work being directed it is unreasonable of
[Probuild] not to [have] granted additional time.
Whilst there may have been [DDI] caused delays I am not satisfied [Probuild] is entitled
to a claim for the total 144 days.
In the absence of an alternative [Probuild] position I find in favour of [DDI].”
The Prevention Principle (@[114] to [129])
[114] In Spiers Earthworks Pty Ltd v Landtec Projects Corp Pty Ltd (No
2), McLure P (with whom Newnes JA agreed), by reference to Hudson’s
Building and Engineering Contracts, observed that “[t]he essence of the
prevention principle is that a party cannot insist on the performance of a
contractual obligation by the other party if it itself is the cause of the other
party’s non-performance”.
[115]…Ordering variations after the due date which must substantially delay
completion will, unless the contract provides otherwise, and in the absence of
an applicable extension of time clause, disable the proprietor from recovering
or retaining liquidated damages which might otherwise have accrued after the
giving of the order. In the context of delaying variations, whether ordered
before or after the due date for completion, the prevention principle “is
grounded upon considerations of fairness and reasonableness”.
The Prevention Principle
[117] The operation of the prevention principle can be modified or excluded by
contract. The manner in which this can be done, as relevant to the present
case, is by extension of time provisions such as cll 41.5 – 41.6. Those
clauses established a procedure by which, in the event of an actual or likely
delay caused as provided in cl 41.6(b)(i), DDI could advise Probuild of the
matters set out in cl 41.5, including whether it sought an extension of time to
the Date for Practical Completion.
[128] In my view, and contrary to Probuild’s submissions, Probuild was
obliged to exercise the reserve power to grant extensions conferred by cl 41.9
honestly and fairly having regard to the underlying rationale of the prevention
principle to which I have earlier referred or, if necessary, because there is an
implied duty of good faith in exercising the discretion cl 41.9 conferred.
Justice McColl’s conclusions
[130] …It is important in considering the content of the procedural fairness
requirement in the context of the SOP Act to bear in mind that a valid
payment claim may be made under the SOP Act “even though it may
ultimately be proved that no payment was due under the construction
contract”. This underscores the rough justice the adjudication procedure
entails. There is no, or little, time for fine arguments about legal principle.
Indeed, having regard to the fact that there is no requirement that
adjudicators have legal qualifications, and, again the constrained time period
for adjudications, it might be concluded the legislature intended such matters
are left to the courts to which the parties may in due course resort, after the
adjudication process is complete.
Justice McColl’s conclusions
[131] When the operation of the prevention principle is understood as I
have explained it, it is apparent in my view that its application was
squarely an issue in the adjudication process. Its inferential application by
the adjudicator could not, or should not, have come as a surprise to
Probuild.
Justice McColl’s conclusions
[137] …Probuild was clearly on notice of the following matters.
First, that the adjudicator was being asked to determine its liquidated
damages claim in the face of a strong claim by DDI that [Probuild’s] acts of
prevention had caused the performance of the Subcontract to be delayed past
the Date for Practical Completion.
Secondly, that it had abandoned the variation procedure in the Subcontract
such that it could not place reliance on assertions that DDI was not entitled to
extensions of time under those provisions by virtue of failing to comply with the
time periods they prescribed.
Thirdly… that there was a free standing, albeit discretionary, extension of time
provision which DDI had, or could arguably have been understood, to have
invoked.
Justice McColl’s conclusions
[140] In concluding that Probuild was not entitled to liquidated damages for
the period of 144 days as sought in its Payment Schedule Table, it is
apparent that the adjudicator did, as the primary judge found, deal “with
Probuild’s argument as made”. In short, the adjudicator found Probuild had
not made good its liquidated damages claim because, as it had anticipated
might be found, Probuild should have granted DDI an extension of time.

More Related Content

What's hot

What's hot (20)

TIME OF SUPPLY AND TAX INVOICE UNDER CGST ACT & RULES
TIME OF SUPPLY  AND  TAX INVOICE UNDER  CGST ACT & RULESTIME OF SUPPLY  AND  TAX INVOICE UNDER  CGST ACT & RULES
TIME OF SUPPLY AND TAX INVOICE UNDER CGST ACT & RULES
 
GST : Time and Place of Supply
GST : Time and Place of SupplyGST : Time and Place of Supply
GST : Time and Place of Supply
 
GST on Real Estate and Works Contract
GST on Real Estate and Works ContractGST on Real Estate and Works Contract
GST on Real Estate and Works Contract
 
Embargo on levy of service tax on flats under composite contracts - Dr Sanjiv...
Embargo on levy of service tax on flats under composite contracts - Dr Sanjiv...Embargo on levy of service tax on flats under composite contracts - Dr Sanjiv...
Embargo on levy of service tax on flats under composite contracts - Dr Sanjiv...
 
Insights into RERA by SBS
Insights into RERA by SBSInsights into RERA by SBS
Insights into RERA by SBS
 
Time of supply
Time of supplyTime of supply
Time of supply
 
Arizona Lien Law
Arizona Lien LawArizona Lien Law
Arizona Lien Law
 
RWY CIPAA 2012 - Scope and Applicability
RWY CIPAA 2012 - Scope and ApplicabilityRWY CIPAA 2012 - Scope and Applicability
RWY CIPAA 2012 - Scope and Applicability
 
Time of supply
Time of supplyTime of supply
Time of supply
 
CIPAA presentation
CIPAA presentationCIPAA presentation
CIPAA presentation
 
Vat on works contract
Vat on works contractVat on works contract
Vat on works contract
 
WA Chapter event: Determinative forum
WA Chapter event: Determinative forumWA Chapter event: Determinative forum
WA Chapter event: Determinative forum
 
Commercial aspects of civil construction
Commercial aspects of civil constructionCommercial aspects of civil construction
Commercial aspects of civil construction
 
2019 Changes in Security of Payment legislation in NSW
2019 Changes in Security of Payment legislation in NSW2019 Changes in Security of Payment legislation in NSW
2019 Changes in Security of Payment legislation in NSW
 
PP2 COMPILCATION
PP2 COMPILCATIONPP2 COMPILCATION
PP2 COMPILCATION
 
"SUPPLY OF GOODS & SERVICES IN GST" WRITTEN BY MAYANK SINGH
"SUPPLY OF GOODS & SERVICES IN GST" WRITTEN BY MAYANK SINGH"SUPPLY OF GOODS & SERVICES IN GST" WRITTEN BY MAYANK SINGH
"SUPPLY OF GOODS & SERVICES IN GST" WRITTEN BY MAYANK SINGH
 
Works contract tax issues-cma nswain)
Works contract tax   issues-cma nswain)Works contract tax   issues-cma nswain)
Works contract tax issues-cma nswain)
 
Time of supply of goods or service in GST- ca amit kumar
Time of supply of goods or service in GST- ca amit kumarTime of supply of goods or service in GST- ca amit kumar
Time of supply of goods or service in GST- ca amit kumar
 
Cases
CasesCases
Cases
 
S 10-Time and value of Supply
S 10-Time and value of SupplyS 10-Time and value of Supply
S 10-Time and value of Supply
 

Similar to Adjudication discussion evening (6 Sep, Sydney) - 2/3

11-27-13 ORDER GRANTING MOTION TO DISMISS SWAMY
11-27-13 ORDER GRANTING MOTION TO DISMISS SWAMY11-27-13 ORDER GRANTING MOTION TO DISMISS SWAMY
11-27-13 ORDER GRANTING MOTION TO DISMISS SWAMY
Richard Goren
 
STAY of collection of tax..........................................pptx
STAY of collection of tax..........................................pptxSTAY of collection of tax..........................................pptx
STAY of collection of tax..........................................pptx
ssuser510f6e
 

Similar to Adjudication discussion evening (6 Sep, Sydney) - 2/3 (20)

Colin Harris and Mark Kenney
Colin Harris and Mark KenneyColin Harris and Mark Kenney
Colin Harris and Mark Kenney
 
Construction Contracts Act WA 2004 - recent cases review
Construction Contracts Act WA 2004 - recent cases reviewConstruction Contracts Act WA 2004 - recent cases review
Construction Contracts Act WA 2004 - recent cases review
 
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
 
Slides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claimsSlides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claims
 
UK Adjudicators Newsletter November 2021
UK Adjudicators  Newsletter November 2021UK Adjudicators  Newsletter November 2021
UK Adjudicators Newsletter November 2021
 
101112016 panel-timetofileliens
101112016 panel-timetofileliens101112016 panel-timetofileliens
101112016 panel-timetofileliens
 
Limitation Act, Section 15 28
Limitation Act, Section 15 28Limitation Act, Section 15 28
Limitation Act, Section 15 28
 
Construction Meets Texas Law: Selected Statutory Overrides
Construction Meets Texas Law: Selected Statutory OverridesConstruction Meets Texas Law: Selected Statutory Overrides
Construction Meets Texas Law: Selected Statutory Overrides
 
Pp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyangPp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyang
 
Stay of Demand under Income Tax Act
Stay of Demand under Income Tax ActStay of Demand under Income Tax Act
Stay of Demand under Income Tax Act
 
11-27-13 ORDER GRANTING MOTION TO DISMISS SWAMY
11-27-13 ORDER GRANTING MOTION TO DISMISS SWAMY11-27-13 ORDER GRANTING MOTION TO DISMISS SWAMY
11-27-13 ORDER GRANTING MOTION TO DISMISS SWAMY
 
UK Adjudicators April 2019 newsletter
UK Adjudicators April 2019 newsletterUK Adjudicators April 2019 newsletter
UK Adjudicators April 2019 newsletter
 
Income Tax Appellate Tribunal has no power to stay prosecution of taxpayers i...
Income Tax Appellate Tribunal has no power to stay prosecution of taxpayers i...Income Tax Appellate Tribunal has no power to stay prosecution of taxpayers i...
Income Tax Appellate Tribunal has no power to stay prosecution of taxpayers i...
 
unit 5& 6.pptx
unit 5& 6.pptxunit 5& 6.pptx
unit 5& 6.pptx
 
The Small Business Reorganization Act of 2019
The Small Business Reorganization Act of 2019The Small Business Reorganization Act of 2019
The Small Business Reorganization Act of 2019
 
STAY of collection of tax..........................................pptx
STAY of collection of tax..........................................pptxSTAY of collection of tax..........................................pptx
STAY of collection of tax..........................................pptx
 
O. XXXVII OF CPC,1908 [SUMMARY PROCEDURE]
O. XXXVII OF CPC,1908 [SUMMARY PROCEDURE]O. XXXVII OF CPC,1908 [SUMMARY PROCEDURE]
O. XXXVII OF CPC,1908 [SUMMARY PROCEDURE]
 
Construction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aConstruction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 a
 
Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015
 
Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2
 

More from Resolution Institute

More from Resolution Institute (20)

Remedium
RemediumRemedium
Remedium
 
The importance of the preliminary conference: An opportunity for the parties ...
The importance of the preliminary conference: An opportunity for the parties ...The importance of the preliminary conference: An opportunity for the parties ...
The importance of the preliminary conference: An opportunity for the parties ...
 
Should Australia sign the Singapore Convention on Mediation?
Should Australia sign the Singapore Convention on Mediation?Should Australia sign the Singapore Convention on Mediation?
Should Australia sign the Singapore Convention on Mediation?
 
Should Australia sign the Singapore Convention on Mediation?
Should Australia sign the Singapore Convention on Mediation?Should Australia sign the Singapore Convention on Mediation?
Should Australia sign the Singapore Convention on Mediation?
 
Government approaches to Alternative Dispute Resolution
Government approaches to Alternative Dispute ResolutionGovernment approaches to Alternative Dispute Resolution
Government approaches to Alternative Dispute Resolution
 
The voice of children in family law: The child centred continuum approach
The voice of children in family law: The child centred continuum approachThe voice of children in family law: The child centred continuum approach
The voice of children in family law: The child centred continuum approach
 
Report writing
Report writingReport writing
Report writing
 
Expert evidence in building and construction
Expert evidence in building and constructionExpert evidence in building and construction
Expert evidence in building and construction
 
Latent conditions and the experienced contractor test
Latent conditions and the experienced contractor testLatent conditions and the experienced contractor test
Latent conditions and the experienced contractor test
 
The sins of the preparer: the adjudicator’s view
The sins of the preparer: the adjudicator’s viewThe sins of the preparer: the adjudicator’s view
The sins of the preparer: the adjudicator’s view
 
Support people in mediation
Support people in mediationSupport people in mediation
Support people in mediation
 
2018 michael klug award and luminary award night - photos
2018 michael klug award and luminary award night - photos2018 michael klug award and luminary award night - photos
2018 michael klug award and luminary award night - photos
 
2018 michael klug award and luminary award night - photos
2018 michael klug award and luminary award night - photos2018 michael klug award and luminary award night - photos
2018 michael klug award and luminary award night - photos
 
Dispute resolution in family law - April 2018
Dispute resolution in family law - April 2018Dispute resolution in family law - April 2018
Dispute resolution in family law - April 2018
 
Partings - the application of grief theory in mediation
Partings - the application of grief theory in mediationPartings - the application of grief theory in mediation
Partings - the application of grief theory in mediation
 
Constructive conversations
Constructive conversationsConstructive conversations
Constructive conversations
 
Adjudication discussion evening (6 Sep, Sydney) - 3/3
Adjudication discussion evening (6 Sep, Sydney) - 3/3Adjudication discussion evening (6 Sep, Sydney) - 3/3
Adjudication discussion evening (6 Sep, Sydney) - 3/3
 
Men's lived experience and the implications for mediation services
Men's lived experience and the implications for mediation servicesMen's lived experience and the implications for mediation services
Men's lived experience and the implications for mediation services
 
Construction Contracts Act (WA) - the past, present and future
Construction Contracts Act (WA) - the past, present and futureConstruction Contracts Act (WA) - the past, present and future
Construction Contracts Act (WA) - the past, present and future
 
Mediating personal injury claims
Mediating personal injury claimsMediating personal injury claims
Mediating personal injury claims
 

Recently uploaded

2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
MadhuKothuru
 

Recently uploaded (20)

Item ## 4a -- April 29, 2024 CCM Minutes
Item ## 4a -- April 29, 2024 CCM MinutesItem ## 4a -- April 29, 2024 CCM Minutes
Item ## 4a -- April 29, 2024 CCM Minutes
 
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
 
Our nurses, our future. The economic power of care.
Our nurses, our future. The economic power of care.Our nurses, our future. The economic power of care.
Our nurses, our future. The economic power of care.
 
PPT Item # 9 2ndQTR Financial & Inv. Report
PPT Item # 9 2ndQTR Financial & Inv. ReportPPT Item # 9 2ndQTR Financial & Inv. Report
PPT Item # 9 2ndQTR Financial & Inv. Report
 
2024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 312024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 31
 
NGO working for orphan children’s education
NGO working for orphan children’s educationNGO working for orphan children’s education
NGO working for orphan children’s education
 
"Plant health, safe trade and digital technology." International Day of Plant...
"Plant health, safe trade and digital technology." International Day of Plant..."Plant health, safe trade and digital technology." International Day of Plant...
"Plant health, safe trade and digital technology." International Day of Plant...
 
AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024
 
Spring 2024 Issue Punitive and Productive Suffering
Spring 2024 Issue Punitive and Productive SufferingSpring 2024 Issue Punitive and Productive Suffering
Spring 2024 Issue Punitive and Productive Suffering
 
ℂall Girls Ahmedabad Book Esha 6378878445 Top Class ℂall Girl Serviℂe Available
ℂall Girls Ahmedabad Book Esha 6378878445 Top Class ℂall Girl Serviℂe Availableℂall Girls Ahmedabad Book Esha 6378878445 Top Class ℂall Girl Serviℂe Available
ℂall Girls Ahmedabad Book Esha 6378878445 Top Class ℂall Girl Serviℂe Available
 
YHRGeorgetown Spring 2024 America should Take Her Share
YHRGeorgetown Spring 2024 America should Take Her ShareYHRGeorgetown Spring 2024 America should Take Her Share
YHRGeorgetown Spring 2024 America should Take Her Share
 
Electric Vehicle infrastructure planning in Rural Planning Organizations
Electric Vehicle infrastructure planning in Rural Planning OrganizationsElectric Vehicle infrastructure planning in Rural Planning Organizations
Electric Vehicle infrastructure planning in Rural Planning Organizations
 
tOld settlement register shouldnotaffect BTR
tOld settlement register shouldnotaffect BTRtOld settlement register shouldnotaffect BTR
tOld settlement register shouldnotaffect BTR
 
Item # 7-8 - 6900 Broadway P&Z Case # 438
Item # 7-8 - 6900 Broadway P&Z Case # 438Item # 7-8 - 6900 Broadway P&Z Case # 438
Item # 7-8 - 6900 Broadway P&Z Case # 438
 
2024: The FAR, Federal Acquisition Regulations, Part 32
2024: The FAR, Federal Acquisition Regulations, Part 322024: The FAR, Federal Acquisition Regulations, Part 32
2024: The FAR, Federal Acquisition Regulations, Part 32
 
Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019
 
Value, protect, respect and invest in our nuses for a sustainable future for ...
Value, protect, respect and invest in our nuses for a sustainable future for ...Value, protect, respect and invest in our nuses for a sustainable future for ...
Value, protect, respect and invest in our nuses for a sustainable future for ...
 
World Migratory Bird Day 2024 "Protect insects, Protect Birds"
World Migratory Bird Day  2024 "Protect insects, Protect Birds"World Migratory Bird Day  2024 "Protect insects, Protect Birds"
World Migratory Bird Day 2024 "Protect insects, Protect Birds"
 
POKKUVARAVU OF RR property-directions for mutation
POKKUVARAVU OF RR property-directions  for mutationPOKKUVARAVU OF RR property-directions  for mutation
POKKUVARAVU OF RR property-directions for mutation
 
Time, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie WhitehouseTime, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie Whitehouse
 

Adjudication discussion evening (6 Sep, Sydney) - 2/3

  • 1. Three Recent SoP Cases • St Hilliers Property v ACT Projects and Wilson [2017] ACTSC 177 (20 July 2017) • Quasar (Constructions) Commercial v Trilla Group [2017] NSWSC 860 (22 June 2017) • Probuild Constructions (Aust) v DDI Group [2017] NSWCA 151 (23 June 2017) David Campbell-Williams Resolution Institute Adjudicators Discussion Evening 6 September 2017
  • 2. St Hilliers Property v ACT Projects and Wilson [2017] ACTSC 177 (20 July 2017) Void determination- Jurisdictional error and manifest error Cost exposure for Adjudicator • 9 July 2014 ACT Projects, contracted to perform structural works for St Hilliers on a project in Gungahlin ACT • Works completed before 29 April 2015 • Between 20 May 2015 and 20 April 2016 ACT Projects served 12 almost identical payment claims each related to the same completed works • 20 June 2016 ACT Projects lodged an adjudication application • 27 June 2016 Adjudicator filed notice of acceptance • 4 July 2016 St Hilliers lodged its adjudication response • Submissions sought and extension agreed that the Determination had to be made on or by 22 July 2016 • Date met but minor amendments made on 25 July, and published 26 July determining that St Hilliers owed ACT Projects $222,260.53
  • 3. St Hilliers Property v ACT Projects and Wilson [2017] ACTSC 177 Appeal under Administrative Decisions (Judicial review) Act 1989 and an appeal from the determination on the basis of error of law (as provided for in s43 ACT SoP Act) s43(4) The Supreme Court must not grant leave under subsection (3) (b) unless it considers that— (a) having regard to all the circumstances, the determination of the question of law concerned could substantially affect the rights of 1 or more parties to the adjudication decision; and (b) there is— (i) a manifest error of law on the face of the adjudication decision; or (ii) strong evidence that the adjudicator made an error of law and that the determination of the question may add, or may be likely to add, substantially to the certainty of the law.
  • 4. St Hilliers Property v ACT Projects and Wilson [2017] ACTSC 177 Three bases: • that the payment claim had been served too late • that a ‘reference date’ was a necessary prerequisite to its service, and was absent at the time of service, and • that the Adjudicator had, in effect, delegated the preparation of his adjudication by having someone else prepare it (or taken into account something other than the ACT s24(2) items/ matters) (22(2) in NSW Act)
  • 5. The payment claim had been served too late ACT Section 15(4) provides: (4) A payment claim may be given only before the later of— (a) the end of the period worked out under the construction contract; and (b) the end of the period of 12 months after the construction work to which the claim relates was last carried out or the related goods and services to which the claim relates were last supplied. • (cf NSW s13(4))
  • 6. The payment claim had been served too late Cl 16.9 The subcontractor agrees to execute a CVA containing confirmation of the matters dealt with in Schedule G and a release in favour of St Hilliers as a precondition of final payment to the Subcontractor. The Unpaid Substantial Completion Retention Release amount identified in the CVA is payable on Substantial Completion and the Unpaid Final Retention Release amount is payable at the end of the Defects Liability Period or when all defects have been remedied to St Hilliers’ satisfaction, whichever is the later. Any Payment Claim which the Subcontractor may have which is not included in the CVA or notified in writing to St Hilliers within 7 days of issue of the CVA or notified in writing to St Hilliers within 3 business days of the commencement of the events giving rise to the Claim (whichever is the earlier) (other than any claim for the return of Security or Retention) shall be absolutely barred and forever released and discharged. Nothing in this clause shall restrict the Subcontractor from defending or bringing a cross claim (provided the cross claim related to the subject matter of the claim against the Subcontractor) or a claim for contribution with respect to, any claim, action, suit of proceeding [sic] brought by the Head Contract Principal against the Subcontractor.
  • 7. The payment claim had been served too late [42] I consider the adjudicator erred in finding in cl 16.9 a period within which ACT Projects could serve its claim. [43] I cannot see any way in which it shows “the end of the period worked out under the construction contract.” [44] First, the clause says ACT Projects agrees to sign an agreement. Secondly, it provides what is to happen with the retention sum referred to in that agreement. Thirdly, it bars certain payment claims. Fourthly, it preserves to ACT Projects the right to defend or cross claim in any case brought against it by the head contractor. [45] Nowhere does it create any rights to serve payment claims. Nowhere does it contain a mechanism to work out “the end of the period under the construction contract”.
  • 8. No reference date Para 43 of St Hilliers submissions quoted at [62] 43 Accordingly, on the proper construction of this contract, a (new) reference date can only ever accrue in a month where no construction work was performed, in circumstances where a valid payment claim was not submitted in the previous month (and construction work was done in that earlier month). Where a valid payment claim was submitted in the previous month, no new reference date can arise. This is because there is no work under the Contract which can be claimed. For that reason, on a proper construction of the Contract, the Payment Claim was submitted in relation to the same reference date as all previous 12 payment claims. No new reference date ever arose for those subsequent months, as with the last one.
  • 9. No reference date [77] Clause 16.1, although permitting monthly claims, must be construed as having limits to its operation, including time limits. For example it would be absurd to construe it as having continuous operation, beyond the end of construction and payment of the final payment. [78] If, as I am satisfied it does, the clause has a time limit for its operation, that must have been, at the latest, to the time for claiming a final payment. [79] On its face the clause contemplates ongoing work occurring in the month immediately before lodgement, unless a claim previously lodged had failed to comply with relevant preconditions: see cl 16.4. Where there has been such a failure, another claim could be lodged for the work in that claim, which in cl 16.4 is called a “lapsed claim.” [80] It was not suggested here the claim lodged on 20 May 2016 was such a claim. [81] Thus in the context of this case, I accept Mr Miller’s submission that the words “to that time” in cl 16.3(a) must mean to the date immediately before the lodgement of the claim. As no work was done in the month before 20 May 2016, the claim was not served on a reference date, and was invalid.
  • 10. Impermissible Delegation [117] I accept Mr Miller’s submission that the use of singular words in s 22, such as “an adjudicator” (s 22(1), shows that the job of adjudicator is personal to the person who agrees to adjudicate. [118] I do not consider s 24(2) requires that an adjudicator work alone, with no clerical or other assistance. Clearly, adjudicators must have some assistance. In the end, whether the assistance amounts to a usurpation of the task of adjudication must be a matter of degree. [119] However, as much as Mr Wilson sought to say all the work was his, I infer most was that of Mr Turner, and that he adopted Mr Turner’s work to a substantial degree and put forward the final product as his own.
  • 11. The Appeal under ACT BCI(SoP)Act s.43 s43(1) Except as provided for in this part, a court does not have jurisdiction to set aside or remit an adjudication decision on the ground of error of fact or law on the face of the decision. s43(4) The Supreme Court must not grant leave under subsection (3)(b) unless it considers that— (a) having regard to all the circumstances, the determination of the question of law concerned could substantially affect the rights of 1 or more parties to the adjudication decision; and (b) there is— (i) a manifest error of law on the face of the adjudication decision; or (ii) strong evidence that the adjudicator made an error of law and that the determination of the question may add, or may be likely to add, substantially to the certainty of the law.
  • 12. The Appeal under ACT BCI(SoP)Act s.43 [138] The appellant contended that two errors of law had been made, and each warranted allowing the appeal. The first concerned an issue of waiver. The second, which I have dealt with above, concerned whether the payment claim had been served on a reference date. [139] For the reasons set out above as to the reference date, the appeal must succeed. I am satisfied that in finding the payment claim was served on a reference date, the adjudicator made an error of law. [140] However I shall also consider the plaintiff’s argument that [the Adjudicator] made an error of law when finding St Hilliers had waived its right to insist that ACT Projects comply with contractual time limits.
  • 13. Exposure to costs Because the Adjudicator became actively involved in the proceedings, he became exposed to a costs order. [220] Despite the general rule that no order for costs be made against an adjudicator, here, because of his active involvement in defence of his position, I consider he should share some of the costs liability: Fernando v Medical Complaints Tribunal at [21]. As did the tribunal member there, the second defendant had an indemnity under the Act: s 37(1). That is an additional factor I take account of on this issue: Fernando at [22].
  • 14. Quasar (Constructions) Commercial v Trilla Group [2017] NSWSC 860 (22 June 2017) Determination not void by reason of want of Natural Justice Stay also refused Trilla had obtained a Determination of $462,000 incl GST Quasar claimed: • a declaration that the adjudicator's determination is void, and consequential relief restraining Trilla from enforcing it; or in the event that the primary case failed- • an order restraining Trilla from enforcing the determination until such time as Quasar's claim can be heard and determined.
  • 15. Quasar (Constructions) Commercial v Trilla Group • Quasar submitted to the adjudicator that the date of practical completion was delayed by some 192 days from the date for practical completion, in circumstances where the date for practical completion (Quasar said) had not been extended. At the rate of $13,000 per day for liquidated damages, that led to the claim of the order of $2.5 million • Trilla submitted that time was at large, because of Quasar's acts of prevention. Those asserted acts of prevention included, apart from the matters to which I have referred, the asserted failure to appoint a superintendent who would manage
  • 16. Quasar (Constructions) Commercial v Trilla Group Quasar responded by denying some of the matters of fact to which Trilla had referred. However, the principal argument advanced by Quasar was that the prevention principle had no application because the contract specifically made provision for extension of time. It relied on the judgment of Rolfe J in Turner Corporation Limited v Coordinated Industries Pty Limited . His Honour there held, in substance, that usually at least, the prevention principle would only apply where the contract did not itself provide for the consequences of the acts that were said to be breaches and acts of prevention.
  • 17. Quasar (Constructions) Commercial v Trilla Group • Quasar's submissions then turned to cl 34.3 of the contract which provided that Trilla would be entitled to extensions of time if Trilla: ▫ would be delayed (or had been delayed) by a "qualifying cause of delay" to which it had not contributed itself: ▫ had given written notice within three days of becoming aware of the causal event; ▫ that "the delay claimed affects the critical path of the progress of the WUC“ and ▫ had taken all reasonable steps to mitigate the effects of the delay.
  • 18. Quasar (Constructions) Commercial v Trilla Group Quasar's submissions canvassed cl 34.3 and its application asserting that no claim for an EOT had been made by Trilla. Quasar also disputed that it had any obligation to provide a construction program (coherent or otherwise) to Trilla. It reiterated its submission that the prevention principle had no relevance, and said that whatever the superintendent did or did not do had nothing to do with the case.
  • 19. Quasar (Constructions) Commercial v Trilla Group The adjudicator then turned his attention to the real dispute, which was the impact of the prevention principle on Trilla's claimed entitlements to EOTs in circumstances where the contract made express provisions for EOTs in cl 34.3. He noted the requirement that the delay claimed must affect the critical path of the progress of the WUC. He then said that although there was no requirement for Quasar to provide a construction program, where it had not done so (or had not updated the program initially provided), Trilla could not comply with the requirements of that sub-paragraph because it simply could not know whether the delay had had any impact on the critical path of its works.
  • 20. Quasar (Constructions) Commercial v Trilla Group [20] Accordingly, the adjudicator concluded, the prevention principle was no answer to Trilla's answer to the claim for liquidated damages. Since it was the claim for liquidated damages that was the principal offset, that removed a substantial obstacle to Trilla's success. [21] Trilla had submitted to the adjudicator, in the alternative, that if it were wrong as to the application of the prevention principle, nonetheless he should conclude, in the alternative, that he was unable to determine the quantum of any liquidated damages. The adjudicator referred to that alternative submission, but expressed no view as to whether or not he was satisfied that it had been made good.
  • 21. Quasar (Constructions) Commercial v Trilla Group [22] In the end (on this aspect of the dispute) the adjudicator decided that Quasar could not set off liquidated damages, because Trilla was unable to request an EOT in accordance with the provisions of the contract. That was so, he said, because Trilla could not assess if a qualifying cause of delay would have any impact on the critical path, because the critical path had not been defined in an updated construction program. [23] …[Quasar] submitted that by deciding the question in this fashion, the Adjudicator had decided it on a basis for which neither party contended. In those circumstances, he submitted, there was a material or substantial denial of natural justice.
  • 22. Quasar (Constructions) Commercial v Trilla Group [24] In my view, there was no substantial or material denial of natural justice. It was Quasar itself that put cl 34.3 into issue, as an answer to Trilla's claim insofar as that claim relied on the prevention principle. Trilla had no ability to respond to Quasar's submissions on that point. It was up to the Adjudicator to wrestle with the issue as best he could. [25] The factual material that the adjudicator took into account, including the absence of a current construction program and the consequences of that, were in the evidence before him. Quasar was in a position to answer those factual matters, and to the extent that it wished to do so, it did.
  • 23. Quasar (Constructions) Commercial v Trilla Group [26] The legal issue that Quasar presented was whether cl 34.3 imposed an insuperable obstacle to Trilla's defence (an inaccurate but sufficient term for present purposes) of Quasar's response to the adjudication application based on its claimed entitlement to set off liquidated damages. Neither party could anticipate in any real detail the way in which that argument might work out. But it was an argument that had been put before the adjudicator, and it was an argument that he dealt with, as best he could in the very tight timeframe allowed by the [Act]…
  • 24. Quasar (Constructions) Commercial v Trilla Group [28] In my view, the issue having been raised, it was incumbent upon the adjudicator to deal with it as best he could on the material provided. That, I think, is precisely what he did. He may have been right or wrong in his interpretation of the contract. But if he were, that would be an error within jurisdiction, and nothing more
  • 25. Stay refused [33] Although it may not be true as a statement of absolute application, it is undoubtedly correct to note that most of the cases where a stay has been granted are cases where the claimant before the adjudicator has been insolvent, or is undergoing some form of administration in insolvency, and no longer trading. In those cases, as the Court said in Facade Treatment Engineering, the rationale for allowing the statutory shift of the risk of insolvency to continue is no longer applicable.
  • 26. Stay refused 42 …Even if it should be held that, apart from the cross-claim, Trilla were entitled to the full amount of $861,000 claimed by it, the resulting debt in favour of Quasar, assuming it proved its entire claim for liquidated damages, would be of the order of $1.6 m. It does not seem to me that there is any real prospect that Trilla could repay that if called upon to do so. 43 However, to reason in that way is to ignore the policy of the Act, and the relevant aspects of its operation in relation to solvent trading companies, that have been referred to in the intermediate appellate court decisions that I have summarised above. The mere fact that an amount might not be repaid does not justify withholding it until the entitlement to that amount can be determined on a final basis.
  • 27. Probuild Constructions (Aust) v DDI Group [2017] NSWCA 151 (23 June 2017) Determination not void by reason of want of Natural Justice; Appeal dismissed. Beazley ACJ McColl JA Macfarlan JA on appeal from Meagher JA [2016] NSWSC 462 (20 April 2016) Primary Judgment McColl JA Challenge to Determination of $475,716 in favour of DDI had been dismissed by Meagher JA Probuild contended that the determination was infected by a denial of procedural fairness (natural justice) in that the adjudicator rejected its liquidated damages claim on bases which neither party had notified to the other or contended for, and which the adjudicator had not notified the parties. Probuild also asserted that had the adjudicator intended to so act, he should have invited the parties to make further submissions, as he was empowered to do under s 21(4) of the SOP Act
  • 28. Extract from para 185 of Determination (@ [51]) “…Based on the submissions it appears that 80% of the contract variations (approximately $1.4m) were directed by [Probuild] and executed by [DDI] after 5 January 2015. As the bulk of the contract variations were approved by [Probuild] it is assumed [DDI] performed the work as directed by [Probuild]. It appears totally inconsistent and unreasonable for [Probuild] to be directing [DDI] to perform significant additional work under the Subcontract after the original Date for Practical Completion and then making a claim for LDs against [DDI] for following [Probuild’s] express directions. [Probuild] also states: ‘DDI has not been granted nor is it entitled to any extension of time.’ Under the Subcontract [Probuild] has the ability to extend time for any reason. Based on the significance of the volume of additional work being directed it is unreasonable of [Probuild] not to [have] granted additional time. Whilst there may have been [DDI] caused delays I am not satisfied [Probuild] is entitled to a claim for the total 144 days. In the absence of an alternative [Probuild] position I find in favour of [DDI].”
  • 29. The Prevention Principle (@[114] to [129]) [114] In Spiers Earthworks Pty Ltd v Landtec Projects Corp Pty Ltd (No 2), McLure P (with whom Newnes JA agreed), by reference to Hudson’s Building and Engineering Contracts, observed that “[t]he essence of the prevention principle is that a party cannot insist on the performance of a contractual obligation by the other party if it itself is the cause of the other party’s non-performance”. [115]…Ordering variations after the due date which must substantially delay completion will, unless the contract provides otherwise, and in the absence of an applicable extension of time clause, disable the proprietor from recovering or retaining liquidated damages which might otherwise have accrued after the giving of the order. In the context of delaying variations, whether ordered before or after the due date for completion, the prevention principle “is grounded upon considerations of fairness and reasonableness”.
  • 30. The Prevention Principle [117] The operation of the prevention principle can be modified or excluded by contract. The manner in which this can be done, as relevant to the present case, is by extension of time provisions such as cll 41.5 – 41.6. Those clauses established a procedure by which, in the event of an actual or likely delay caused as provided in cl 41.6(b)(i), DDI could advise Probuild of the matters set out in cl 41.5, including whether it sought an extension of time to the Date for Practical Completion. [128] In my view, and contrary to Probuild’s submissions, Probuild was obliged to exercise the reserve power to grant extensions conferred by cl 41.9 honestly and fairly having regard to the underlying rationale of the prevention principle to which I have earlier referred or, if necessary, because there is an implied duty of good faith in exercising the discretion cl 41.9 conferred.
  • 31. Justice McColl’s conclusions [130] …It is important in considering the content of the procedural fairness requirement in the context of the SOP Act to bear in mind that a valid payment claim may be made under the SOP Act “even though it may ultimately be proved that no payment was due under the construction contract”. This underscores the rough justice the adjudication procedure entails. There is no, or little, time for fine arguments about legal principle. Indeed, having regard to the fact that there is no requirement that adjudicators have legal qualifications, and, again the constrained time period for adjudications, it might be concluded the legislature intended such matters are left to the courts to which the parties may in due course resort, after the adjudication process is complete.
  • 32. Justice McColl’s conclusions [131] When the operation of the prevention principle is understood as I have explained it, it is apparent in my view that its application was squarely an issue in the adjudication process. Its inferential application by the adjudicator could not, or should not, have come as a surprise to Probuild.
  • 33. Justice McColl’s conclusions [137] …Probuild was clearly on notice of the following matters. First, that the adjudicator was being asked to determine its liquidated damages claim in the face of a strong claim by DDI that [Probuild’s] acts of prevention had caused the performance of the Subcontract to be delayed past the Date for Practical Completion. Secondly, that it had abandoned the variation procedure in the Subcontract such that it could not place reliance on assertions that DDI was not entitled to extensions of time under those provisions by virtue of failing to comply with the time periods they prescribed. Thirdly… that there was a free standing, albeit discretionary, extension of time provision which DDI had, or could arguably have been understood, to have invoked.
  • 34. Justice McColl’s conclusions [140] In concluding that Probuild was not entitled to liquidated damages for the period of 144 days as sought in its Payment Schedule Table, it is apparent that the adjudicator did, as the primary judge found, deal “with Probuild’s argument as made”. In short, the adjudicator found Probuild had not made good its liquidated damages claim because, as it had anticipated might be found, Probuild should have granted DDI an extension of time.