SlideShare a Scribd company logo
1 of 74
Download to read offline
Resolution Institute:
Construction Contracts Act 2004 (WA)
– recent case review
Greg Nairn
Partner, Construction & Infrastructure
21 June 2017
INTRODUCTION AND CONTEXT
2
Period covered: from 15 August 2016 to June 2017
Amendments to the CCA yet to fully filter through
Case law continues to develop – and continues to offer up
surprises
3
CASE REVIEW
4
CH2M Hill Australia v ABB Australia
[2016] NTSC 42 (15 August 2016)
KEY TOPICS: REPEAT APPLICATIONS
(s25 CCA) + ABUSE OF PROCESS +
COMPLEXITY + REASONS FOR
DECISION
Overview
– Defendant agreed to supply equipment to plaintiff for power plant at
Ichthys
– Payment claim #1 lodged by defendant – plaintiff’s certificate for a
substantially lower amount – became subject of Adjudication #1
– Payment claim #2 lodged by defendant – became subject of
Adjudication #2
– Adjudication #1 was dismissed for being out of time
– Adjudication #2 was allowed in defendant’s favour
– Plaintiff sought to set aside Adjudication #2
6
Duplicate application point
– Under CCA (WA s25), a party cannot adjudicate where an application
has previously been made
– Plaintiff argued that the second claim (in Adjudication #2) was a
“repeat” of the claim in Adjudication #1
– Plaintiff’s argument was that s25(a) operated where the subject
matter was repeated across two applications – ie not just where the
very same payment claim was agitated
– Rejected – found that to offend s25(a), the applicant has to be
adjudicating the very same payment dispute as a dispute the
subject of another application (at [30])
7
Abuse of process point
– Plaintiff further argued that there was such a substantial overlap
between the claims the subject of Adjudication #1 and #2, that #2
amounted to an abuse of process.
– It was accepted that the principles of abuse of process and related
principles such as issue estoppel could apply to CCA matters
– However, the two applications were not the same, and gave rise to
different issues – hence no relevant abuse/issue estoppel (at [36])
despite extensive overlap of issues (particularly on the question of
whether the defendant was entitled to an EOT) (at [37])
– Also in Adjudication #1 there was no determination on the merits
anyway (at [38])
8
Complexity point
– Plaintiff argued that adjudicator should have dismissed on complexity
grounds
– Rejected (at [49]-[51]):
– Although there were more than 12 lever arch files, “I do not think
that the volume of the material is a necessary indicator …”
– The legal issues were not particularly complex and did not
necessarily require a lawyer to resolve them
– There were at least as many factual issues as legal
9
Reasons for decision point
– Reasons found to be “fundamentally inadequate” (at [88])
– Decision was set aside on that basis (at [117])
– Adjudicator must show he/she has turned mind to the issues raised by
the parties in support and opposition to the claim (at [92])
– The determination failed to give reasons to support the finding that the
defendant was entitled to an EOT (which was a critical point) (at [96])
10
– Not sufficient for the adjudicator to say:
– that he has “considered everything” (at [99]);
– merely that he was satisfied why the relevant contractual notice
provisions (time bars) had been satisfied (at [97])
– merely that he found the defendant’s case more persuasive than
the plaintiff’s case (at [98])
– merely that he found the defendant’s expert delay analysis
preferable or more persuasive than the plaintiff’s expert delay
analysis (at [100])
– The adjudicator must give the reasons why
11
M+W Singapore Pte Ltd -v- Anstee-Brook
[2016] WASC 310 (27 September 2016)
KEY TOPICS: PAYMENT DISPUTE
ARISES ON INFORMAL DISPUTING +
INABILITY TO SEVER DETERMINATION
INFECTED BY JURISDICTIONAL
ERROR
Overview
– Unusual case – by consent
– Pritchard J was satisfied that, for 2 of the 3 payment claims captured
in the determination, the application was brought out of time and that
adjudicator’s failure to dismiss on that basis was jurisdictional error (at
[39])
– This was on the basis of clear evidence of informal disputation of
those payment claims, which triggered the 28 day time limit earlier
than the adjudicator thought
– 3rd payment claim may have been in time, but given there is no ability
to sever that portion of the determination, the determination was
wholly set aside (at [43]-[44])
13
MRCN Pty Ltd and Pindan Contracting Pty
Ltd [2016] WASAT 114 (20 September
2016)
KEY TOPICS: PAY WHEN PAID
CLAUSES + RELEVANCE OF PRIOR
ADJUDICATIONS
Pay when paid clause
– SAT not satisfied that a clause in a subcontract that made the return
of retention by head contractor (Pindan) contingent upon a
Superintendent certifying completion of broader works (head contract)
offended “pay when paid” prohibition in s9 CCA (at [24]-[28])
– Evidence didn’t establish that return of retention to Pindan was
contingent on Pindan getting its retentions back from the
Owner/Principal
15
Relevance of prior adjudication
– There was an earlier determination of another adjudicator in which the
a finding had been made as to when PC was achieved, which led to
the release of a tranche of the retention
– MRCN argued in effect that:
– earlier determination meant that second tranche of retention was
now due for release
– the current adjudicator could not overturn the earlier determination
finding on this point
– Rejected by SAT - current adjudicator was not bound by previous
determination, and was entitled to take a different approach as to
when final tranche was due for release, and in any event no actual
inconsistency (at [63]-[67]) 16
Samsung C&T Corporation -v- Loots
[2016] WASC 330 (24 October 2016)
KEY TOPICS: JURISDICTIONAL
ERROR + SCOPE OF PAYMENT
DISPUTES + DEALING WITH SET-OFFS
+ MINING EXCEPTION
18
Errors in contractual construction
– Found: it could not amount to jurisdictional error for the adjudicators
in that case to make a finding that, as a matter of contractual
construction, certain contractual milestones (related to Samsung’s
asserted right to LDs) were not applicable
– “There is no doubt … that an adjudicator has jurisdiction to err in the
construction of a contract” (at [137])
19
Whether an amount certified but not
claimed is part of a payment dispute
– One of the payment disputes (and adjudications) arose out of Duro’s
December 2015 payment claim for some $64m
– In the prior month’s certificate (November 2015 certificate), Samsung
had set off $32.4m for defective works
– In assessing Duro’s December 2015 claim, Samsung reversed that
set off of $32.4m in “good faith”
– This was in effect happening independently of what Duro was
claiming in its December claim (it arising out of what had happened
the month prior)
– By time of adjudication application, Duro made a $49m claim, which
included (in effect) the $32.4m which was the subject of Samsung’s
reversal – adjudicator in effect granted that in favour of Duro
20
– An argument arose before Beech J as to whether it was open for the
adjudicator handling the payment dispute arising out of Duro’s
December 2015 claim to make any finding about whether this $32.4m
was due
– Samsung argued in effect that the adjudicator could NOT make any
determination on the $32.4m because:
– That $32.4m was not part of Duro’s December 2015 claim (it
arose out of a reversal of Samsung’s earlier position);
– Alternatively, Duro was out of time to adjudicate on the $32.4m,
since any dispute arose out of the November 2015 certificate
21
– Beech J agreed with Samsung’s arguments and set aside the
determination on basis of jurisdictional error
– Duro’s December 2015 claim did not include the $32.4m and that was
the only payment claim that could give rise to the dispute (at [210])
– The $32.4m was in substance unrelated to that claim (at [212])
– Adjudicator misunderstood his role, which was to adjudicate solely on
the payment dispute arising out of the December claim (at [215])
– Adjudicator also failed to engage/respond to Samsung’s arguments
on the $32.4m and that amounted to a denial of procedural fairness
(at [226])
22
Considering merits of a set-off
– Samsung also alleged that in one of the adjudications (#2), the
adjudicator erred in failing to give credit for a $7m payment it had
made to Duro “on account” for variations (still $6.6m in credit as at
relevant date)
– In effect, adjudicator #2 denied it on the basis that Samsung had (in
an earlier payment certificate) applied illegitimate set-offs which in
substance captured/exceeded the $6.6m (at [273])
– Beech J found that this was a jurisdictional error (at [274])
– The adjudicator’s function is not to determine amounts payable at
large, but is confined by the payment claim that gave rise to the
payment dispute (at [276]) – adjudicator is to determine what is owing
in respect of that payment claim only (at [277])
23
– That involves consideration of merits of an asserted set-off – here the
adjudicator found that it was (on its face) valid set-off in response to
Duro’s payment claim
– It was wrong for the adjudicator to go beyond that, and examine
earlier payment claims/certificates and determine the amounts
otherwise owing between the parties
– “It is not open to an adjudicator to find that the amount payable by a
party in relation to the payment claim before the adjudicator is to be
increased (or decreased) on the ground that the adjudicator considers
that a party wrongfully denied liability (or wrongfully made a claim) in
relation to an earlier, different payment claim” (at [281])
24
Effect if no payment claim or dispute
– In obiter remarks, Beech J expressed the view ([at [295]) that a finding
by an adjudicator that there was no payment dispute because there
was no payment claim does not enliven the dismissal power in
s31(2)(a) (regarding preparation and service in accordance with s26)
– At [303], Beech J expressed view that lack of a claim/dispute was
relevant only to the merits part of the adjudication (s31(2)(b))
– This is potentially significant as query whether a disappointed
applicant in a case where adjudicator found no claim/dispute could
access a SAT review under s46 (review right restricted to decisions to
dismiss under s31(2)(a))
25
Effect if payment claim is made for
work outside CCA scope
– Beech J found (at [309], [311]-[318]) that:
– the scope of a payment dispute is limited by the scope of a
payment claim;
– it is only a claim for payment of an amount in relation to the
performance of obligations within paragraphs (a) to (d) of the
definition of 'construction contract' in s 3 that gives rise to a
payment claim under the CCA;
– only that component of the claim that related to construction
obligations could be adjudicated
26
– Beech J (at [315]-[316]):
– A construction contract need not be wholly or primarily for
performance of the relevant construction obligations to be a
construction contract under the CCA;
– However, many parts of the Act only operates on a construction
contract to the extent it relates to the relevant construction
obligations (and not other types of obligations)
– Some aspects of CCA do apply generally
– Beech J rejected (at [319]-[347]) Samsung argument that a payment
claim must be confined to a claim for payment of an amount in relation
to the performance of construction work or related obligations, and
that if it was not so confined lost its ability to be adjudicated
27
– Beech J found (at [336]) that each of the adjudicators honoured this
approach, restricting their adjudications to claims for relevant
construction work – this was evidenced by the exclusion of works that
were the subject of the s4(3) exception
28
Mining/processing plant exception
– Obiter comments of Beech J (at [349]-[412])
– In determining application of the exception, it is necessary to view
the works in the contractual context, including whether it forms
part of a broader package or works (at [354])
– The character and purpose of the works packages may reveal the
character and purpose of the component item of work in question
– Duro’s provision of a “Data Centre” to mine processing plant was
excluded work – “the Data Centre is one of many elements of the
integrated mine process plant” (at [363])
– Duro’s provision of electrical switch-rooms (even those not
connected directly to the mine processing equipment) were also
“properly seen as a component of the mine process plant, and are
constructed for the purpose of processing iron ore” (at [370])
29
– So were certain “belt feeders” that transported ore from bins to
crushers (at [374])
– So was work done by Duro to commission the control systems at
the mine process plant (at [383])
– So too were a mine pit laboratory and a mine process plant
laboratory – formed an element of integrated processing plant (at
[392])
– So too was work done in relation to certain stackers and reclaims
at the site of the mine process plant, but not stackers and
reclaimers and loaders at the port (remote from the processing
plant) (at [401])
– Note: s4(3)(c) CCA has since been amended
30
Inability to sever erroneous portions
of adjudication
– Beech J confirmed (at [414]) that as soon as a determination is found
to be infected with jurisdictional error, it is not possible to “sever” the
erroneous part, leaving the balance to stand – thus the error infects
and voids the entire determination
Cooper & Oxley Builders Pty Ltd v
Steensma [2016] WASC 386 (30 November
2016)
KEY TOPICS: SET-OFFS + NATURE OF
LIABILITY BEING DETERMINED + CCA
IMPLIED TERMS
Overview
– Subcontractor made progress claims against C&O
– In assessing each claim, C&O applied set-offs for liquidated damages
and rectification work (defective works)
– Adjudication #1: adjudicator declined to have regard to C&O’s set-
offs on the basis the set-off was separate and outside his jurisdiction
– Adjudication #2: set-off not available and adjudicator found implied
terms (when and how to respond to payment claim) applied
– C&O sought judicial review of both adjudications on basis of
jurisdictional errors
32
Nature of liability being determined
– Le Miere J (at [33]) accepted that adjudicator’s function was to
determine current contractual liability, not whether, at some time in
past, the contractor was entitled to be paid
– Accordingly, an adjudicator cannot ignore events which occur after the
payment dispute arose and before date of determination, such as:
– payment of whole or part of claim;
– compromise of the claim;
– the accrual of a claim for liquidated damages
33
Set-off point (Adjudication #1)
– Le Miere J found adjudicator was wrong to exclude consideration of
C&O’s set-off – while a set-off may itself give rise to a separate
payment claim and dispute (as per Alliance Contracting [2014] WASC
212), this does meant that the adjudicator can overlook the merits of
the claim against which the set-off is raised (at [22])
– “The adjudicator is required to take into account the respondent’s
response, including the merits or any counterclaim or set off, in
reaching his determination …” (at [22])
– Adjudication #1 was set aside
34
Implied terms point (Adjudication #2)
– Le Miere J found adjudicator was wrong to imply Sch 1 Div 5 implied
terms (when and how to respond) – basis of reasoning:
– Adjudicator needs to form a view whether the contract has a written provision about
when and how to respond to a payment claim
– That is a simple inquiry – it is wrong to instead consider (as the adjudicator did)
whether the contract has a “written provision about each element of the provisions in
div 5 about when and how a party is to respond to claim for payment. That is not
what s 17 … says or means” (at [38])
– The only “matter” about which the contract needs a written provision to avoid the
implied terms implication is “when and how a party is to respond to a claim for
payment” (at [39])
– What is sufficient in that regard may be informed by Sch 1 Div 5 implied terms, but
s17 does not require the adjudicator to perform an elaborate comparison between the
contract and the implied terms, and imply the implied terms to the extent the contract
does not replicate the implied terms (at [39])
35
Southern Han Breakfast Point Pty Ltd v
Lewence Construction Pty Ltd [2016] HCA
52 (21 December 2016)
KEY TOPICS: EFFECT OF A “TAKING
OUT” + EFFECT OF TERMINATION
37
Scope of valid payment claims
– In essence, High Court found that requirements of NSW Act that
claims for payment be for work carried out under a construction
contract meant that adjudication has a limited purpose – covers
claims for contractual entitlements only (at [66])
– [Note wording differs to CCA]
– High Court stated (at [66])
the Act is concerned to provide a statutory mechanism for securing payment of an amount claimed to
be payable in partial or total discharge of an obligation to pay for work (or for goods and services
supplied) imposed by the contractual force of a construction contract. The Act is not concerned to
provide security for payment of an amount claimed by way of damages for breach of a construction
contract. Nor is the Act concerned to provide security for payment of an amount which … might be
claimed as an alternative to damages by way of restitution for work carried out (or goods and services
supplied) in the event of the construction contract terminating on acceptance of repudiation.
38
Effect of taking out/termination
– Relevant facts - parties’ contract had:
– standard monthly progress claim provisions (clause 37.1)
– right (in event of substantial breach) to take work out of hands and
“suspend payment” in interim, or terminate (clause 39.4)
– On 27 October 2014, Southern Han purported to take all of remaining
work out of Lewence’s hands
– Lewence treated that action as a repudiation and on 28 October 2014
purported to terminate
– On 4 December 2014, Lewence submitted payment claim for work up
to 27 October 2014 – became the subject of an adjudication
39
Taking out/payment suspension
– If Southern Han had validly taken work out of the builder’s hands, then:
– Lewence’s rights to payment for all work was suspended until the works
(and take out process) were completed (clause 39.4)
– The suspension of payment was a form of “security” in favour of Southern
Han
– That being so, payment suspension applied not just for work taken out of
hands, but all work, otherwise that security would be undermined (at [76])
– “The suspension of payment was a suspension of the totality of the rights
conferred and obligations imposed in relation to payment by cl 37”,
including the right to make the November progress claim for work done up
to point of take out (at [78])
– In other words, the builder’s November progress claim was contractually
invalid as the right to submit it was suspended
40
– Query whether same approach would be taken under cl 44 AS2124
which is more particular refers to suspension of “further” payment in
respect of work taken out of hands – has been held as not suspending
contractor’s rights to be done for work done up to (and therefore not
included in) take out: see Queensland University of Technology v
Project Constructions (Aust) P/L (In Liq) & Anor [2002] QCA 224
– However it pays to read the payment suspension carefully as if as
broad as in Southern Han it is likely to prejudice right to claim (and
adjudicate)
41
Termination
– If on the other hand Lewence had validly terminated, then:
– Both parties were discharged from further performance of the contract;
– Lewence’s rights were restricted to rights which had already accrued;
– Lewence’s rights to submit progress claim had not yet accrued (claims
were to be made 8th day of each month and Lewence’s claim was 4 days
early) (at [79])
– Further, no sufficient basis to conclude that cl 37 (progress claim right)
survived termination – contract indicated that parties would be left to
common law damages remedies (at [80])
– Claims for common law damages are outside scope of legislation (ie
Lewence has no adjudication right)
Bocol Constructions v Keslake [2017]
WASAT 15 (17 January 2017)
KEY TOPICS: NAMING OF PARTIES +
TYPES OF PAYMENT CLAIMS THAT
CAN BE MADE “UNDER” A CONTRACT
+ COMPLEXITY
43
Overview
– Bocol (as main contractor) engaged Keslake as a subcontractor to do
some works in relation to a road construction project
– Bocol alleged Keslake performed those works defectively (in breach
of implied workmanship term) and sought recovery of damages for
breach
– Bocol submitted a payment claim for those damages, relying on the
implied terms
– That payment claim became the subject of an adjudication, which was
dismissed on the basis that (1) Keslake had been incorrectly named;
(2) claim for damages was not able to be adjudicated under CCA
– Bocol sought a SAT review (hearing de novo)
44
Naming issue
– Bocol had in effect referred to Keslake as:
– Bitumen Surfacing (which was Keslake’s trading name)
– “The Trustee for the Complete Road Services trust”
– Hadn’t used the formal legal name “Keslake Group Pty Ltd”
– SAT found it didn’t matter:
– “the meaning of 'name' is the nomenclature used to accurately describe a
person or entity” (at [60])
– Reg 5 of CC Regs is not to be read narrowly – not the case that any error
or misdescription is fatal
– No relevant misdescription in any event – it was clear who the respondent
was
– At any rate s74 of Interpretation Act allows SAT to overlook immaterial
non-compliances with statutory forms and that could be applied here
45
Damages claim issue
– SAT rejected Bocol’s arguments that CCA, both on its express terms
and via the implied terms, permitted a “principal” in the shoes of Bocol
to make a contractual claim for damages against a “contractor” in the
shoes of Keslake
– A claim for damages is not a claim “under” a construction contract –
“there has to be a term in the construction contract that provides the
right to make the claim not that the claim is 'referable to' or 'a genus of
claim provided for by that contract' or 'by reason of the existence of
the contract'.” (at [114])
– Here there was no such right (there was no contractual right to claim
damages for breach)
– What about the implied terms? SAT found they applied but it made
no difference …
46
Complexity issue
– SAT found the matter was too complex (at [137])
– There was competing expert evidence
– Liability was not factually or legally clear
– Quantum of damages not straightforward
– Contrast approach in NT in ABB v CH2M (August 2016 decision
addressed above)
ABB Australia v CH2M Hill Australia (No
1) [2017] NTSC 1 (13 January 2017)
KEY TOPIC: CONTRACTUALLY NON-
CONFORMING PAYMENT CLAIMS
Overview
– Subcontractor submitted a payment claim (Claim #1) to main contractor,
purporting it to be under the contract
– However, payment claim did not comply with contractual requirements for
making of the claim (subcontractor had not provided security which was a
condition precedent to valid payment claim)
– Main contractor asked subcontractor to re-submit after relevant security
given
– Subcontractor did so, and lodged Claim #2 and main contractor issued
payment certificate in response for less than amount claimed
– Subcontractor took claim to adjudication – adjudicator dismissed on basis
that rejection of Claim #1 had triggered time limit
– HELD: Claim #1 did not trigger time limit as it was not contractually valid
48
Reasoning
– Kelly J applied K & J Burns Electrical Pty Ltd v GRD Group (NT) Pty
Ltd & Anor [2011] NTCA 1
– In order to determine whether there is a payment dispute, the
adjudicator must determine whether the contractor has made a claim
for payment under the contract
– “This necessarily entails the adjudicator going to the terms of the
contract and asking whether what purports to be a payment claim is
capable of giving rise to a liability on the part of the principal to pay. If
not, then there is no “payment dispute” [and the application must be
dismissed]” (at [30])
– The payment claim must be capable of giving rise to a liability to pay
under the contract (at [32])
49
Reasoning (cont’d)
– A dispute about the contractual validity of a payment claim is not in
itself a payment dispute (at [33]), but is a matter which the adjudicator
must making a finding on when the adjudicator makes the initial
decision whether or not to dismiss (at [34])
– Given the above, on facts of this case, Claim #1 was contractually
non-conforming, and its rejection could not trigger a payment dispute
within the meaning of the CCA
50
ABB Australia v CH2M Hill Australia (No
2) [2017] NTSC 11 (14 Feb 2017)
KEY TOPIC: CONTRACTUALLY NON-
CONFORMING PAYMENT CLAIMS
52
Overview
– Applicant submitted a “non-conforming” payment claim. Respondent
issued a payment certificate. Payment claim was adjudicated.
– Respondent claimed that fact that the payment claim did not comply
with contract meant a “payment dispute” could not arise under NT
CCA.
– HELD: fact that payment claim was contractually defective was not
fatal to creation of payment dispute, since on the facts the recipient
didn’t reject the payment claim on that basis.
53
Reasoning in ABB v CH2M
– In determining whether a payment dispute exists, adjudicator must
first determine whether contractor has made a payment claim under
the contract
– This requires consideration of the purported payment claim and
whether it is “capable of giving rise to a liability on the part of the
principal to pay” (at [38]).
– Here the respondent failed to reject the claim, but instead issued a
payment certificate. Under the terms of the parties’ contract, this
certificate itself triggered an obligation to pay (at [39]).
– Didn’t matter contractually that claim was non-conforming, therefore it
didn’t matter to the adjudication
54
Implications …
– Fact that a payment claim may be contractually non-compliant will not
necessarily be fatal
– Look at contract – if contract on its terms permits certification of non-
conforming claims, and attaches a liability to pay to such certification,
a non-conforming claim
– Query where ABB decisions leave the “broader” approach, found in
earlier SAT decisions such as Blackadder Scaffolding v Mirvac
Homes (WA) [2009] WASAT 133, at [68] – suggested, particularly
when read in conjunction with SAT not adopting the majority view in
K&J Burns (see Georgiou Group and MCC Mining [2011] WASAT
120, at [64]) that, so long as payment claim could in a general sense
be described as a payment claim under the contract, it didn’t matter it
if did not strictly comply
Total Eden Pty Ltd -v- ECA Systems Pty
Ltd [2017] WASC 58 (9 February 2017)
KEY TOPICS: SET-OFFS +
DETERMINATION OF CURRENT
LIABILITY + IMPLIED TERMS + COSTS
56
Context
– Total Eden sought an order (under Civil Judgments Enforcement Act)
suspending enforcement of judgment pending the outcome of judicial
review of a determination – resolution of that application required
Pritchard J to express preliminary views on merits of the judicial
review application
– Total Eden was granted a suspension order including on basis that
the judicial review application had reasonable prospects of success
57
Observations made – set-offs,
implied terms
– Determination reasons did not make it clear that the adjudicator had
considered a set-off raised by Total Eden against ECA – against that
background it was fairly arguable that adjudicator had made an error
in making a determination of Total Eden’s liability as at the date the
payment to ECA was due, rather than the date of the determination
(at [20])
– It was also reasonably arguable that the implied terms (cl 7, Sch 1) re
responding to a payment claim did not exclude Total Eden’s common
law rights to set-off (at [21]) – this on the basis that court would be
slow to infer that established common law rights are excluded
58
Observations made - costs
– Pritchard J also indicated she felt it was arguable that there was a
reviewable error in the adjudicator awarding costs against Total Eden,
on the basis that Total Eden had not acted frivolously or vexatiously
(at [23])
Parkview Construction v Total Lifestyle
[2017] NSWSC 194 (7 March 2017)
KEY TOPIC: SERVICE OF ELECTRONIC
DOCUMENTS
60
Overview
– FACTS:
– Adjudication application was uploaded to nominating authority on
a cloud service (Hightail)
– Applicant pasted same files across to a USB stick
– The respondent was served with the USB stick
– HELD: service of USB stick was not effective service under the NSW
security of payment legislation
61
Reasoning in Parkview:
– Key point: “service” under the NSW security of payment legislation
requires service of a written copy of the application (at [73])
– Findings (at [75]-[81]):
– Generally, service will be effective where the party served has become
aware of the contents of a document
– In case of an email, or upload to cloud, service will not be effected until the
transmission or upload is actually accessed by the recipient
– Service of the USB stick is NOT the same as service of the writing stored
on the USB stick:
– USB does not represent or reproduce words visibly;
– Delivery of a USB is not transmission in writing just as delivering a CD
is not aural transmission of the recording embedded upon it
INPEX Operations Australia Pty Ltd v JKC
Australia LNG Pty Ltd [2017] NTSC 45
(15 June 2017)
KEY TOPICS: JURISDICTIONAL
ERROR + DENIAL OF NATURAL
JUSTICE + PAYMENT DISPUTE +
IMPLIED TERMS
63
Facts
– JKC lodged payment claim against Inpex, which Inpex disputed in part
– JKC brought an application seeking to adjudicate part of the dispute
– 34 volumes of material in the application
– Importantly, JKC’s application didn’t contend that Inpex was
contractually precluded from disputing the merits of JKC’s claims
– The adjudicator sought submissions from the parties as to whether
the implied provisions of the CCA applied to the EPC contract based
on a deficiency he perceived in the way the payment terms operated
– Both parties filed submissions to the effect that the implied provisions
did NOT apply
64
Adjudicator’s finding
– The implied terms applied
– As there was no evidence as to prove that Inpex had issued a notice
of dispute within the 14 day period set out in the implied terms, there
was a deemed acceptance and Inpex became liable to pay the full
amount
– Inpex applied to Supreme Court (NT) for judicial review
65
Reviewable/jurisdictional error
– Kelly J
[28] An error of law in construing provisions of the Act which give the
adjudicator his jurisdiction to make a determination will render a
determination a nullity reviewable by this Court. However, non-
jurisdictional errors of law or fact made by an adjudicator in the process of
making a bona fide attempt to carry out the functions conferred on him or
her by the Act are not amenable to review by this Court. If the only
complaint were that the Adjudicator had misconstrued the EPC Contract,
then that would not, of itself, render the Determination a nullity,
reviewable by the Court … unless it could be shown that the Adjudicator’s
decision was unreasonable (in the Wednesbury sense) or that there was
a substantial failure to comply with the requirements of procedural
fairness in the circumstances.
66
Denial of natural justice
– Kelly J found a denial of natural justice had been made out
– Relevantly:
– [30] Procedural fairness required that the Adjudicator notify the parties of
“proposed conclusions that were not put forward by the parties and could
not be easily anticipated.” The Court will set aside a purported
determination by an adjudicator where there has been a failure by an
adjudicator to provide such procedural fairness and, as a result, a party
has been deprived of the possibility of a successful outcome.
– Here the adjudicator needed to do more than ask for submissions on
whether the implied terms applied
67
– Adjudicator failed to warn parties that he was considering making a
determination on the basis of the “deemed acceptance” operation of
the implied terms
– Inpex was denied opportunity to put submissions on that issue,
including on the basis that:
– JKC’s payment claim was not compliant with the contract; or
– there was some estoppel or waiver which prevented JKC relying
on 14 day response time; or
– even if the implied terms applied, an adjudicator was still obliged
to be satisfied that the work was done and money owing
68
– Kelly J didn’t accept that it was apparent from asking for submissions
on the implied terms that the adjudicator was flagging he might make
a determination based on the implied terms – this was because the
adjudicator had made it clear that the parties’ submissions on the
implied terms issue had to be restricted to whether the implied terms
applied (at [38])
– Not necessary to assess the merits of Inpex’s arguments on implied
terms – was satisfied that a different outcome may have eventuated
(at [41])
– Kelly J in effect warned adjudicators from making a determination on
a basis not contended for by either party, without first giving the
parties to make submissions on that basis – see [44]
69
Scope of a payment dispute
– Inpex alternatively argued that by determining the matter on a basis
not argued by the parties, the adjudicator had gone beyond his
powers, which were confined to analysing the specific payment
dispute that gave rise to the application
– Inpex’s argument sought to distinguish between payment disputes
arising due to an actual dispute, as opposed to disputes arising due to
mere non-payment
– Kelly J rejected this alternative argument
70
Operation of implied terms
– Inpex further argued that adjudicator had erred in blindly applying the
implied terms “deemed acceptance”, and that he ought to have turned
his mind to the underlying merits of JKC’s claim
– Kelly J rejected this (at [58]):
As has been said many times in cases connected with this Act, the focus
of the Act is on the contract. If the contract between the parties provides
for a claim to be paid in full if not disputed within a given time, then there
is no reason why an adjudicator ought not give effect to that provision in
making a determination on the merits under s 33(1)(b), and every reason
why he should.
TAKEAWAYS
71
Takeaways
Parties must be given full opportunity to be heard on what will
underpin adjudicator’s decision
Reasons must explain the “why” behind adjudicator’s key
findings (why party A expert preferred over party B)
A single jurisdictional error on a minor point (eg costs)
could lead to entire determination being void
Cannot make a determination to pay on amounts not claimed
in the original payment claim
72
Takeaways
Determinations must be for contractual entitlements only and
be for work covered by the CCA
Do you make a merits dismissal if no payment
claim/dispute?
Set offs cannot be ignored or overlooked – need to
determine current liability to pay
Ground continues to shift on when the implied terms apply
73
Questions?
Follow us on Twitter: @LavanTweets
Follow us on LinkedIn: Lavan
74

More Related Content

Similar to Resolution Institute: Construction Contracts Act 2004 (WA) – recent case review

A Little Light Relief? A summary of the post-Mitchell landscape
A Little Light Relief? A summary of the post-Mitchell landscapeA Little Light Relief? A summary of the post-Mitchell landscape
A Little Light Relief? A summary of the post-Mitchell landscapeRachel Tandy
 
SPIRIT OF CIVIL PROCEDURE REFORMS BITES
SPIRIT OF CIVIL PROCEDURE REFORMS BITESSPIRIT OF CIVIL PROCEDURE REFORMS BITES
SPIRIT OF CIVIL PROCEDURE REFORMS BITESCameron Ford
 
Blake lapthorn new Construction Act seminar
Blake lapthorn new Construction Act seminarBlake lapthorn new Construction Act seminar
Blake lapthorn new Construction Act seminarBlake Morgan
 
DIGITAL-SECURITY-SERVICES-LTD-AND-MICHAEL-PEETS-vs-NEVIS-INTERNATIONAL-BANK-T...
DIGITAL-SECURITY-SERVICES-LTD-AND-MICHAEL-PEETS-vs-NEVIS-INTERNATIONAL-BANK-T...DIGITAL-SECURITY-SERVICES-LTD-AND-MICHAEL-PEETS-vs-NEVIS-INTERNATIONAL-BANK-T...
DIGITAL-SECURITY-SERVICES-LTD-AND-MICHAEL-PEETS-vs-NEVIS-INTERNATIONAL-BANK-T...HRBExposed
 
BoyarMiller – Things Every Associate Should Know
BoyarMiller – Things Every Associate Should Know BoyarMiller – Things Every Associate Should Know
BoyarMiller – Things Every Associate Should Know BoyarMiller
 
SMALL CLAIM TRACK
SMALL CLAIM TRACK SMALL CLAIM TRACK
SMALL CLAIM TRACK ACID_SLIDES
 
Bintai Kindenko Pte Ltd v Samsung C&T Corp [2018] SGCA 39 – Principles Govern...
Bintai Kindenko Pte Ltd v Samsung C&T Corp [2018] SGCA 39 – Principles Govern...Bintai Kindenko Pte Ltd v Samsung C&T Corp [2018] SGCA 39 – Principles Govern...
Bintai Kindenko Pte Ltd v Samsung C&T Corp [2018] SGCA 39 – Principles Govern...Abraham Vergis
 
Dishonour of cheque priyanka agarwal bvdu_pune
Dishonour of cheque priyanka agarwal bvdu_puneDishonour of cheque priyanka agarwal bvdu_pune
Dishonour of cheque priyanka agarwal bvdu_punePriyanka Agarwal
 
USEFUL JUDGMENT ON 138
USEFUL JUDGMENT ON 138USEFUL JUDGMENT ON 138
USEFUL JUDGMENT ON 138arjun randhir
 
Enforcing Adjudication Determinations
Enforcing Adjudication DeterminationsEnforcing Adjudication Determinations
Enforcing Adjudication DeterminationsResolution Institute
 
Issues under the Arbitration and Conciliation (Amendment) Act, 2015
Issues under the Arbitration and Conciliation (Amendment) Act, 2015Issues under the Arbitration and Conciliation (Amendment) Act, 2015
Issues under the Arbitration and Conciliation (Amendment) Act, 2015Agnish Aditya
 
How To Protect Your Construction Business and Legal Interests
How To Protect Your Construction Business and Legal InterestsHow To Protect Your Construction Business and Legal Interests
How To Protect Your Construction Business and Legal InterestsPalecek & Palecek, PLLC
 
Tutorial4 presentation ver.3
Tutorial4 presentation ver.3Tutorial4 presentation ver.3
Tutorial4 presentation ver.3Thia Chiong Wei
 
Patrick O'Sullivan Dispute Resolution Boards
Patrick O'Sullivan Dispute Resolution BoardsPatrick O'Sullivan Dispute Resolution Boards
Patrick O'Sullivan Dispute Resolution BoardsResolution Institute
 
Hoffenberg v. commissioner
Hoffenberg v. commissionerHoffenberg v. commissioner
Hoffenberg v. commissionerjrbampfield
 
Federal Discovery Plan2.pdf
Federal Discovery Plan2.pdfFederal Discovery Plan2.pdf
Federal Discovery Plan2.pdfHectorEsquivel23
 

Similar to Resolution Institute: Construction Contracts Act 2004 (WA) – recent case review (20)

A Little Light Relief? A summary of the post-Mitchell landscape
A Little Light Relief? A summary of the post-Mitchell landscapeA Little Light Relief? A summary of the post-Mitchell landscape
A Little Light Relief? A summary of the post-Mitchell landscape
 
SPIRIT OF CIVIL PROCEDURE REFORMS BITES
SPIRIT OF CIVIL PROCEDURE REFORMS BITESSPIRIT OF CIVIL PROCEDURE REFORMS BITES
SPIRIT OF CIVIL PROCEDURE REFORMS BITES
 
UK Adjudicators March 2018 newsletter
UK Adjudicators March 2018 newsletterUK Adjudicators March 2018 newsletter
UK Adjudicators March 2018 newsletter
 
UK Adjudicators July 2018 newsletter
UK  Adjudicators July 2018 newsletterUK  Adjudicators July 2018 newsletter
UK Adjudicators July 2018 newsletter
 
Blake lapthorn new Construction Act seminar
Blake lapthorn new Construction Act seminarBlake lapthorn new Construction Act seminar
Blake lapthorn new Construction Act seminar
 
DIGITAL-SECURITY-SERVICES-LTD-AND-MICHAEL-PEETS-vs-NEVIS-INTERNATIONAL-BANK-T...
DIGITAL-SECURITY-SERVICES-LTD-AND-MICHAEL-PEETS-vs-NEVIS-INTERNATIONAL-BANK-T...DIGITAL-SECURITY-SERVICES-LTD-AND-MICHAEL-PEETS-vs-NEVIS-INTERNATIONAL-BANK-T...
DIGITAL-SECURITY-SERVICES-LTD-AND-MICHAEL-PEETS-vs-NEVIS-INTERNATIONAL-BANK-T...
 
BoyarMiller – Things Every Associate Should Know
BoyarMiller – Things Every Associate Should Know BoyarMiller – Things Every Associate Should Know
BoyarMiller – Things Every Associate Should Know
 
SMALL CLAIM TRACK
SMALL CLAIM TRACK SMALL CLAIM TRACK
SMALL CLAIM TRACK
 
Bintai Kindenko Pte Ltd v Samsung C&T Corp [2018] SGCA 39 – Principles Govern...
Bintai Kindenko Pte Ltd v Samsung C&T Corp [2018] SGCA 39 – Principles Govern...Bintai Kindenko Pte Ltd v Samsung C&T Corp [2018] SGCA 39 – Principles Govern...
Bintai Kindenko Pte Ltd v Samsung C&T Corp [2018] SGCA 39 – Principles Govern...
 
Dishonour of cheque priyanka agarwal bvdu_pune
Dishonour of cheque priyanka agarwal bvdu_puneDishonour of cheque priyanka agarwal bvdu_pune
Dishonour of cheque priyanka agarwal bvdu_pune
 
USEFUL JUDGMENT ON 138
USEFUL JUDGMENT ON 138USEFUL JUDGMENT ON 138
USEFUL JUDGMENT ON 138
 
Enforcing Adjudication Determinations
Enforcing Adjudication DeterminationsEnforcing Adjudication Determinations
Enforcing Adjudication Determinations
 
UK Adjudicators October 2020 Newsletter
UK Adjudicators  October 2020 NewsletterUK Adjudicators  October 2020 Newsletter
UK Adjudicators October 2020 Newsletter
 
Issues under the Arbitration and Conciliation (Amendment) Act, 2015
Issues under the Arbitration and Conciliation (Amendment) Act, 2015Issues under the Arbitration and Conciliation (Amendment) Act, 2015
Issues under the Arbitration and Conciliation (Amendment) Act, 2015
 
How To Protect Your Construction Business and Legal Interests
How To Protect Your Construction Business and Legal InterestsHow To Protect Your Construction Business and Legal Interests
How To Protect Your Construction Business and Legal Interests
 
Tutorial4 presentation ver.3
Tutorial4 presentation ver.3Tutorial4 presentation ver.3
Tutorial4 presentation ver.3
 
Patrick O'Sullivan Dispute Resolution Boards
Patrick O'Sullivan Dispute Resolution BoardsPatrick O'Sullivan Dispute Resolution Boards
Patrick O'Sullivan Dispute Resolution Boards
 
Hoffenberg v. commissioner
Hoffenberg v. commissionerHoffenberg v. commissioner
Hoffenberg v. commissioner
 
Rule 37 38-41
Rule 37 38-41Rule 37 38-41
Rule 37 38-41
 
Federal Discovery Plan2.pdf
Federal Discovery Plan2.pdfFederal Discovery Plan2.pdf
Federal Discovery Plan2.pdf
 

More from Resolution Institute

The importance of the preliminary conference: An opportunity for the parties ...
The importance of the preliminary conference: An opportunity for the parties ...The importance of the preliminary conference: An opportunity for the parties ...
The importance of the preliminary conference: An opportunity for the parties ...Resolution Institute
 
Should Australia sign the Singapore Convention on Mediation?
Should Australia sign the Singapore Convention on Mediation?Should Australia sign the Singapore Convention on Mediation?
Should Australia sign the Singapore Convention on Mediation?Resolution Institute
 
Should Australia sign the Singapore Convention on Mediation?
Should Australia sign the Singapore Convention on Mediation?Should Australia sign the Singapore Convention on Mediation?
Should Australia sign the Singapore Convention on Mediation?Resolution Institute
 
Government approaches to Alternative Dispute Resolution
Government approaches to Alternative Dispute ResolutionGovernment approaches to Alternative Dispute Resolution
Government approaches to Alternative Dispute ResolutionResolution Institute
 
The voice of children in family law: The child centred continuum approach
The voice of children in family law: The child centred continuum approachThe voice of children in family law: The child centred continuum approach
The voice of children in family law: The child centred continuum approachResolution Institute
 
Expert evidence in building and construction
Expert evidence in building and constructionExpert evidence in building and construction
Expert evidence in building and constructionResolution Institute
 
2019 Changes in Security of Payment legislation in NSW
2019 Changes in Security of Payment legislation in NSW2019 Changes in Security of Payment legislation in NSW
2019 Changes in Security of Payment legislation in NSWResolution Institute
 
Latent conditions and the experienced contractor test
Latent conditions and the experienced contractor testLatent conditions and the experienced contractor test
Latent conditions and the experienced contractor testResolution Institute
 
The sins of the preparer: the adjudicator’s view
The sins of the preparer: the adjudicator’s viewThe sins of the preparer: the adjudicator’s view
The sins of the preparer: the adjudicator’s viewResolution Institute
 
2018 michael klug award and luminary award night - photos
2018 michael klug award and luminary award night - photos2018 michael klug award and luminary award night - photos
2018 michael klug award and luminary award night - photosResolution Institute
 
2018 michael klug award and luminary award night - photos
2018 michael klug award and luminary award night - photos2018 michael klug award and luminary award night - photos
2018 michael klug award and luminary award night - photosResolution Institute
 
Dispute resolution in family law - April 2018
Dispute resolution in family law - April 2018Dispute resolution in family law - April 2018
Dispute resolution in family law - April 2018Resolution Institute
 
Partings - the application of grief theory in mediation
Partings - the application of grief theory in mediationPartings - the application of grief theory in mediation
Partings - the application of grief theory in mediationResolution Institute
 
Adjudication discussion evening (6 Sep, Sydney) - 3/3
Adjudication discussion evening (6 Sep, Sydney) - 3/3Adjudication discussion evening (6 Sep, Sydney) - 3/3
Adjudication discussion evening (6 Sep, Sydney) - 3/3Resolution Institute
 
Adjudication discussion evening (6 Sep, Sydney) - 1/3
Adjudication discussion evening (6 Sep, Sydney) - 1/3Adjudication discussion evening (6 Sep, Sydney) - 1/3
Adjudication discussion evening (6 Sep, Sydney) - 1/3Resolution Institute
 
Men's lived experience and the implications for mediation services
Men's lived experience and the implications for mediation servicesMen's lived experience and the implications for mediation services
Men's lived experience and the implications for mediation servicesResolution Institute
 

More from Resolution Institute (20)

Remedium
RemediumRemedium
Remedium
 
The importance of the preliminary conference: An opportunity for the parties ...
The importance of the preliminary conference: An opportunity for the parties ...The importance of the preliminary conference: An opportunity for the parties ...
The importance of the preliminary conference: An opportunity for the parties ...
 
Should Australia sign the Singapore Convention on Mediation?
Should Australia sign the Singapore Convention on Mediation?Should Australia sign the Singapore Convention on Mediation?
Should Australia sign the Singapore Convention on Mediation?
 
Should Australia sign the Singapore Convention on Mediation?
Should Australia sign the Singapore Convention on Mediation?Should Australia sign the Singapore Convention on Mediation?
Should Australia sign the Singapore Convention on Mediation?
 
Government approaches to Alternative Dispute Resolution
Government approaches to Alternative Dispute ResolutionGovernment approaches to Alternative Dispute Resolution
Government approaches to Alternative Dispute Resolution
 
The voice of children in family law: The child centred continuum approach
The voice of children in family law: The child centred continuum approachThe voice of children in family law: The child centred continuum approach
The voice of children in family law: The child centred continuum approach
 
Report writing
Report writingReport writing
Report writing
 
Expert evidence in building and construction
Expert evidence in building and constructionExpert evidence in building and construction
Expert evidence in building and construction
 
2019 Changes in Security of Payment legislation in NSW
2019 Changes in Security of Payment legislation in NSW2019 Changes in Security of Payment legislation in NSW
2019 Changes in Security of Payment legislation in NSW
 
Latent conditions and the experienced contractor test
Latent conditions and the experienced contractor testLatent conditions and the experienced contractor test
Latent conditions and the experienced contractor test
 
The sins of the preparer: the adjudicator’s view
The sins of the preparer: the adjudicator’s viewThe sins of the preparer: the adjudicator’s view
The sins of the preparer: the adjudicator’s view
 
Support people in mediation
Support people in mediationSupport people in mediation
Support people in mediation
 
2018 michael klug award and luminary award night - photos
2018 michael klug award and luminary award night - photos2018 michael klug award and luminary award night - photos
2018 michael klug award and luminary award night - photos
 
2018 michael klug award and luminary award night - photos
2018 michael klug award and luminary award night - photos2018 michael klug award and luminary award night - photos
2018 michael klug award and luminary award night - photos
 
Dispute resolution in family law - April 2018
Dispute resolution in family law - April 2018Dispute resolution in family law - April 2018
Dispute resolution in family law - April 2018
 
Partings - the application of grief theory in mediation
Partings - the application of grief theory in mediationPartings - the application of grief theory in mediation
Partings - the application of grief theory in mediation
 
Constructive conversations
Constructive conversationsConstructive conversations
Constructive conversations
 
Adjudication discussion evening (6 Sep, Sydney) - 3/3
Adjudication discussion evening (6 Sep, Sydney) - 3/3Adjudication discussion evening (6 Sep, Sydney) - 3/3
Adjudication discussion evening (6 Sep, Sydney) - 3/3
 
Adjudication discussion evening (6 Sep, Sydney) - 1/3
Adjudication discussion evening (6 Sep, Sydney) - 1/3Adjudication discussion evening (6 Sep, Sydney) - 1/3
Adjudication discussion evening (6 Sep, Sydney) - 1/3
 
Men's lived experience and the implications for mediation services
Men's lived experience and the implications for mediation servicesMen's lived experience and the implications for mediation services
Men's lived experience and the implications for mediation services
 

Recently uploaded

“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...Christina Parmionova
 
call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...
call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...
call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...saminamagar
 
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012rehmti665
 
Club of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationClub of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationEnergy for One World
 
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service MumbaiHigh Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbaisonalikaur4
 
Take action for a healthier planet and brighter future.
Take action for a healthier planet and brighter future.Take action for a healthier planet and brighter future.
Take action for a healthier planet and brighter future.Christina Parmionova
 
Call Girls Near Surya International Hotel New Delhi 9873777170
Call Girls Near Surya International Hotel New Delhi 9873777170Call Girls Near Surya International Hotel New Delhi 9873777170
Call Girls Near Surya International Hotel New Delhi 9873777170Sonam Pathan
 
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls ServiceCall Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Servicenarwatsonia7
 
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdf
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdfMonastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdf
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdfCharlynTorres1
 
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…nishakur201
 
Start Donating your Old Clothes to Poor People kurnool
Start Donating your Old Clothes to Poor People kurnoolStart Donating your Old Clothes to Poor People kurnool
Start Donating your Old Clothes to Poor People kurnoolSERUDS INDIA
 
How to design healthy team dynamics to deliver successful digital projects.pptx
How to design healthy team dynamics to deliver successful digital projects.pptxHow to design healthy team dynamics to deliver successful digital projects.pptx
How to design healthy team dynamics to deliver successful digital projects.pptxTechSoupConnectLondo
 
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...narwatsonia7
 
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...ResolutionFoundation
 
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...narwatsonia7
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27JSchaus & Associates
 
13875446-Ballistic Missile Trajectories.ppt
13875446-Ballistic Missile Trajectories.ppt13875446-Ballistic Missile Trajectories.ppt
13875446-Ballistic Missile Trajectories.pptsilvialandin2
 

Recently uploaded (20)

“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
 
call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...
call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...
call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...
 
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
 
Club of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationClub of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological Civilization
 
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service MumbaiHigh Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
 
Take action for a healthier planet and brighter future.
Take action for a healthier planet and brighter future.Take action for a healthier planet and brighter future.
Take action for a healthier planet and brighter future.
 
Call Girls Near Surya International Hotel New Delhi 9873777170
Call Girls Near Surya International Hotel New Delhi 9873777170Call Girls Near Surya International Hotel New Delhi 9873777170
Call Girls Near Surya International Hotel New Delhi 9873777170
 
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls ServiceCall Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
 
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdf
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdfMonastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdf
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdf
 
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
 
Start Donating your Old Clothes to Poor People kurnool
Start Donating your Old Clothes to Poor People kurnoolStart Donating your Old Clothes to Poor People kurnool
Start Donating your Old Clothes to Poor People kurnool
 
The Federal Budget and Health Care Policy
The Federal Budget and Health Care PolicyThe Federal Budget and Health Care Policy
The Federal Budget and Health Care Policy
 
How to design healthy team dynamics to deliver successful digital projects.pptx
How to design healthy team dynamics to deliver successful digital projects.pptxHow to design healthy team dynamics to deliver successful digital projects.pptx
How to design healthy team dynamics to deliver successful digital projects.pptx
 
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
 
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
 
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27
 
13875446-Ballistic Missile Trajectories.ppt
13875446-Ballistic Missile Trajectories.ppt13875446-Ballistic Missile Trajectories.ppt
13875446-Ballistic Missile Trajectories.ppt
 

Resolution Institute: Construction Contracts Act 2004 (WA) – recent case review

  • 1. Resolution Institute: Construction Contracts Act 2004 (WA) – recent case review Greg Nairn Partner, Construction & Infrastructure 21 June 2017
  • 3. Period covered: from 15 August 2016 to June 2017 Amendments to the CCA yet to fully filter through Case law continues to develop – and continues to offer up surprises 3
  • 5. CH2M Hill Australia v ABB Australia [2016] NTSC 42 (15 August 2016) KEY TOPICS: REPEAT APPLICATIONS (s25 CCA) + ABUSE OF PROCESS + COMPLEXITY + REASONS FOR DECISION
  • 6. Overview – Defendant agreed to supply equipment to plaintiff for power plant at Ichthys – Payment claim #1 lodged by defendant – plaintiff’s certificate for a substantially lower amount – became subject of Adjudication #1 – Payment claim #2 lodged by defendant – became subject of Adjudication #2 – Adjudication #1 was dismissed for being out of time – Adjudication #2 was allowed in defendant’s favour – Plaintiff sought to set aside Adjudication #2 6
  • 7. Duplicate application point – Under CCA (WA s25), a party cannot adjudicate where an application has previously been made – Plaintiff argued that the second claim (in Adjudication #2) was a “repeat” of the claim in Adjudication #1 – Plaintiff’s argument was that s25(a) operated where the subject matter was repeated across two applications – ie not just where the very same payment claim was agitated – Rejected – found that to offend s25(a), the applicant has to be adjudicating the very same payment dispute as a dispute the subject of another application (at [30]) 7
  • 8. Abuse of process point – Plaintiff further argued that there was such a substantial overlap between the claims the subject of Adjudication #1 and #2, that #2 amounted to an abuse of process. – It was accepted that the principles of abuse of process and related principles such as issue estoppel could apply to CCA matters – However, the two applications were not the same, and gave rise to different issues – hence no relevant abuse/issue estoppel (at [36]) despite extensive overlap of issues (particularly on the question of whether the defendant was entitled to an EOT) (at [37]) – Also in Adjudication #1 there was no determination on the merits anyway (at [38]) 8
  • 9. Complexity point – Plaintiff argued that adjudicator should have dismissed on complexity grounds – Rejected (at [49]-[51]): – Although there were more than 12 lever arch files, “I do not think that the volume of the material is a necessary indicator …” – The legal issues were not particularly complex and did not necessarily require a lawyer to resolve them – There were at least as many factual issues as legal 9
  • 10. Reasons for decision point – Reasons found to be “fundamentally inadequate” (at [88]) – Decision was set aside on that basis (at [117]) – Adjudicator must show he/she has turned mind to the issues raised by the parties in support and opposition to the claim (at [92]) – The determination failed to give reasons to support the finding that the defendant was entitled to an EOT (which was a critical point) (at [96]) 10
  • 11. – Not sufficient for the adjudicator to say: – that he has “considered everything” (at [99]); – merely that he was satisfied why the relevant contractual notice provisions (time bars) had been satisfied (at [97]) – merely that he found the defendant’s case more persuasive than the plaintiff’s case (at [98]) – merely that he found the defendant’s expert delay analysis preferable or more persuasive than the plaintiff’s expert delay analysis (at [100]) – The adjudicator must give the reasons why 11
  • 12. M+W Singapore Pte Ltd -v- Anstee-Brook [2016] WASC 310 (27 September 2016) KEY TOPICS: PAYMENT DISPUTE ARISES ON INFORMAL DISPUTING + INABILITY TO SEVER DETERMINATION INFECTED BY JURISDICTIONAL ERROR
  • 13. Overview – Unusual case – by consent – Pritchard J was satisfied that, for 2 of the 3 payment claims captured in the determination, the application was brought out of time and that adjudicator’s failure to dismiss on that basis was jurisdictional error (at [39]) – This was on the basis of clear evidence of informal disputation of those payment claims, which triggered the 28 day time limit earlier than the adjudicator thought – 3rd payment claim may have been in time, but given there is no ability to sever that portion of the determination, the determination was wholly set aside (at [43]-[44]) 13
  • 14. MRCN Pty Ltd and Pindan Contracting Pty Ltd [2016] WASAT 114 (20 September 2016) KEY TOPICS: PAY WHEN PAID CLAUSES + RELEVANCE OF PRIOR ADJUDICATIONS
  • 15. Pay when paid clause – SAT not satisfied that a clause in a subcontract that made the return of retention by head contractor (Pindan) contingent upon a Superintendent certifying completion of broader works (head contract) offended “pay when paid” prohibition in s9 CCA (at [24]-[28]) – Evidence didn’t establish that return of retention to Pindan was contingent on Pindan getting its retentions back from the Owner/Principal 15
  • 16. Relevance of prior adjudication – There was an earlier determination of another adjudicator in which the a finding had been made as to when PC was achieved, which led to the release of a tranche of the retention – MRCN argued in effect that: – earlier determination meant that second tranche of retention was now due for release – the current adjudicator could not overturn the earlier determination finding on this point – Rejected by SAT - current adjudicator was not bound by previous determination, and was entitled to take a different approach as to when final tranche was due for release, and in any event no actual inconsistency (at [63]-[67]) 16
  • 17. Samsung C&T Corporation -v- Loots [2016] WASC 330 (24 October 2016) KEY TOPICS: JURISDICTIONAL ERROR + SCOPE OF PAYMENT DISPUTES + DEALING WITH SET-OFFS + MINING EXCEPTION
  • 18. 18 Errors in contractual construction – Found: it could not amount to jurisdictional error for the adjudicators in that case to make a finding that, as a matter of contractual construction, certain contractual milestones (related to Samsung’s asserted right to LDs) were not applicable – “There is no doubt … that an adjudicator has jurisdiction to err in the construction of a contract” (at [137])
  • 19. 19 Whether an amount certified but not claimed is part of a payment dispute – One of the payment disputes (and adjudications) arose out of Duro’s December 2015 payment claim for some $64m – In the prior month’s certificate (November 2015 certificate), Samsung had set off $32.4m for defective works – In assessing Duro’s December 2015 claim, Samsung reversed that set off of $32.4m in “good faith” – This was in effect happening independently of what Duro was claiming in its December claim (it arising out of what had happened the month prior) – By time of adjudication application, Duro made a $49m claim, which included (in effect) the $32.4m which was the subject of Samsung’s reversal – adjudicator in effect granted that in favour of Duro
  • 20. 20 – An argument arose before Beech J as to whether it was open for the adjudicator handling the payment dispute arising out of Duro’s December 2015 claim to make any finding about whether this $32.4m was due – Samsung argued in effect that the adjudicator could NOT make any determination on the $32.4m because: – That $32.4m was not part of Duro’s December 2015 claim (it arose out of a reversal of Samsung’s earlier position); – Alternatively, Duro was out of time to adjudicate on the $32.4m, since any dispute arose out of the November 2015 certificate
  • 21. 21 – Beech J agreed with Samsung’s arguments and set aside the determination on basis of jurisdictional error – Duro’s December 2015 claim did not include the $32.4m and that was the only payment claim that could give rise to the dispute (at [210]) – The $32.4m was in substance unrelated to that claim (at [212]) – Adjudicator misunderstood his role, which was to adjudicate solely on the payment dispute arising out of the December claim (at [215]) – Adjudicator also failed to engage/respond to Samsung’s arguments on the $32.4m and that amounted to a denial of procedural fairness (at [226])
  • 22. 22 Considering merits of a set-off – Samsung also alleged that in one of the adjudications (#2), the adjudicator erred in failing to give credit for a $7m payment it had made to Duro “on account” for variations (still $6.6m in credit as at relevant date) – In effect, adjudicator #2 denied it on the basis that Samsung had (in an earlier payment certificate) applied illegitimate set-offs which in substance captured/exceeded the $6.6m (at [273]) – Beech J found that this was a jurisdictional error (at [274]) – The adjudicator’s function is not to determine amounts payable at large, but is confined by the payment claim that gave rise to the payment dispute (at [276]) – adjudicator is to determine what is owing in respect of that payment claim only (at [277])
  • 23. 23 – That involves consideration of merits of an asserted set-off – here the adjudicator found that it was (on its face) valid set-off in response to Duro’s payment claim – It was wrong for the adjudicator to go beyond that, and examine earlier payment claims/certificates and determine the amounts otherwise owing between the parties – “It is not open to an adjudicator to find that the amount payable by a party in relation to the payment claim before the adjudicator is to be increased (or decreased) on the ground that the adjudicator considers that a party wrongfully denied liability (or wrongfully made a claim) in relation to an earlier, different payment claim” (at [281])
  • 24. 24 Effect if no payment claim or dispute – In obiter remarks, Beech J expressed the view ([at [295]) that a finding by an adjudicator that there was no payment dispute because there was no payment claim does not enliven the dismissal power in s31(2)(a) (regarding preparation and service in accordance with s26) – At [303], Beech J expressed view that lack of a claim/dispute was relevant only to the merits part of the adjudication (s31(2)(b)) – This is potentially significant as query whether a disappointed applicant in a case where adjudicator found no claim/dispute could access a SAT review under s46 (review right restricted to decisions to dismiss under s31(2)(a))
  • 25. 25 Effect if payment claim is made for work outside CCA scope – Beech J found (at [309], [311]-[318]) that: – the scope of a payment dispute is limited by the scope of a payment claim; – it is only a claim for payment of an amount in relation to the performance of obligations within paragraphs (a) to (d) of the definition of 'construction contract' in s 3 that gives rise to a payment claim under the CCA; – only that component of the claim that related to construction obligations could be adjudicated
  • 26. 26 – Beech J (at [315]-[316]): – A construction contract need not be wholly or primarily for performance of the relevant construction obligations to be a construction contract under the CCA; – However, many parts of the Act only operates on a construction contract to the extent it relates to the relevant construction obligations (and not other types of obligations) – Some aspects of CCA do apply generally – Beech J rejected (at [319]-[347]) Samsung argument that a payment claim must be confined to a claim for payment of an amount in relation to the performance of construction work or related obligations, and that if it was not so confined lost its ability to be adjudicated
  • 27. 27 – Beech J found (at [336]) that each of the adjudicators honoured this approach, restricting their adjudications to claims for relevant construction work – this was evidenced by the exclusion of works that were the subject of the s4(3) exception
  • 28. 28 Mining/processing plant exception – Obiter comments of Beech J (at [349]-[412]) – In determining application of the exception, it is necessary to view the works in the contractual context, including whether it forms part of a broader package or works (at [354]) – The character and purpose of the works packages may reveal the character and purpose of the component item of work in question – Duro’s provision of a “Data Centre” to mine processing plant was excluded work – “the Data Centre is one of many elements of the integrated mine process plant” (at [363]) – Duro’s provision of electrical switch-rooms (even those not connected directly to the mine processing equipment) were also “properly seen as a component of the mine process plant, and are constructed for the purpose of processing iron ore” (at [370])
  • 29. 29 – So were certain “belt feeders” that transported ore from bins to crushers (at [374]) – So was work done by Duro to commission the control systems at the mine process plant (at [383]) – So too were a mine pit laboratory and a mine process plant laboratory – formed an element of integrated processing plant (at [392]) – So too was work done in relation to certain stackers and reclaims at the site of the mine process plant, but not stackers and reclaimers and loaders at the port (remote from the processing plant) (at [401]) – Note: s4(3)(c) CCA has since been amended
  • 30. 30 Inability to sever erroneous portions of adjudication – Beech J confirmed (at [414]) that as soon as a determination is found to be infected with jurisdictional error, it is not possible to “sever” the erroneous part, leaving the balance to stand – thus the error infects and voids the entire determination
  • 31. Cooper & Oxley Builders Pty Ltd v Steensma [2016] WASC 386 (30 November 2016) KEY TOPICS: SET-OFFS + NATURE OF LIABILITY BEING DETERMINED + CCA IMPLIED TERMS
  • 32. Overview – Subcontractor made progress claims against C&O – In assessing each claim, C&O applied set-offs for liquidated damages and rectification work (defective works) – Adjudication #1: adjudicator declined to have regard to C&O’s set- offs on the basis the set-off was separate and outside his jurisdiction – Adjudication #2: set-off not available and adjudicator found implied terms (when and how to respond to payment claim) applied – C&O sought judicial review of both adjudications on basis of jurisdictional errors 32
  • 33. Nature of liability being determined – Le Miere J (at [33]) accepted that adjudicator’s function was to determine current contractual liability, not whether, at some time in past, the contractor was entitled to be paid – Accordingly, an adjudicator cannot ignore events which occur after the payment dispute arose and before date of determination, such as: – payment of whole or part of claim; – compromise of the claim; – the accrual of a claim for liquidated damages 33
  • 34. Set-off point (Adjudication #1) – Le Miere J found adjudicator was wrong to exclude consideration of C&O’s set-off – while a set-off may itself give rise to a separate payment claim and dispute (as per Alliance Contracting [2014] WASC 212), this does meant that the adjudicator can overlook the merits of the claim against which the set-off is raised (at [22]) – “The adjudicator is required to take into account the respondent’s response, including the merits or any counterclaim or set off, in reaching his determination …” (at [22]) – Adjudication #1 was set aside 34
  • 35. Implied terms point (Adjudication #2) – Le Miere J found adjudicator was wrong to imply Sch 1 Div 5 implied terms (when and how to respond) – basis of reasoning: – Adjudicator needs to form a view whether the contract has a written provision about when and how to respond to a payment claim – That is a simple inquiry – it is wrong to instead consider (as the adjudicator did) whether the contract has a “written provision about each element of the provisions in div 5 about when and how a party is to respond to claim for payment. That is not what s 17 … says or means” (at [38]) – The only “matter” about which the contract needs a written provision to avoid the implied terms implication is “when and how a party is to respond to a claim for payment” (at [39]) – What is sufficient in that regard may be informed by Sch 1 Div 5 implied terms, but s17 does not require the adjudicator to perform an elaborate comparison between the contract and the implied terms, and imply the implied terms to the extent the contract does not replicate the implied terms (at [39]) 35
  • 36. Southern Han Breakfast Point Pty Ltd v Lewence Construction Pty Ltd [2016] HCA 52 (21 December 2016) KEY TOPICS: EFFECT OF A “TAKING OUT” + EFFECT OF TERMINATION
  • 37. 37 Scope of valid payment claims – In essence, High Court found that requirements of NSW Act that claims for payment be for work carried out under a construction contract meant that adjudication has a limited purpose – covers claims for contractual entitlements only (at [66]) – [Note wording differs to CCA] – High Court stated (at [66]) the Act is concerned to provide a statutory mechanism for securing payment of an amount claimed to be payable in partial or total discharge of an obligation to pay for work (or for goods and services supplied) imposed by the contractual force of a construction contract. The Act is not concerned to provide security for payment of an amount claimed by way of damages for breach of a construction contract. Nor is the Act concerned to provide security for payment of an amount which … might be claimed as an alternative to damages by way of restitution for work carried out (or goods and services supplied) in the event of the construction contract terminating on acceptance of repudiation.
  • 38. 38 Effect of taking out/termination – Relevant facts - parties’ contract had: – standard monthly progress claim provisions (clause 37.1) – right (in event of substantial breach) to take work out of hands and “suspend payment” in interim, or terminate (clause 39.4) – On 27 October 2014, Southern Han purported to take all of remaining work out of Lewence’s hands – Lewence treated that action as a repudiation and on 28 October 2014 purported to terminate – On 4 December 2014, Lewence submitted payment claim for work up to 27 October 2014 – became the subject of an adjudication
  • 39. 39 Taking out/payment suspension – If Southern Han had validly taken work out of the builder’s hands, then: – Lewence’s rights to payment for all work was suspended until the works (and take out process) were completed (clause 39.4) – The suspension of payment was a form of “security” in favour of Southern Han – That being so, payment suspension applied not just for work taken out of hands, but all work, otherwise that security would be undermined (at [76]) – “The suspension of payment was a suspension of the totality of the rights conferred and obligations imposed in relation to payment by cl 37”, including the right to make the November progress claim for work done up to point of take out (at [78]) – In other words, the builder’s November progress claim was contractually invalid as the right to submit it was suspended
  • 40. 40 – Query whether same approach would be taken under cl 44 AS2124 which is more particular refers to suspension of “further” payment in respect of work taken out of hands – has been held as not suspending contractor’s rights to be done for work done up to (and therefore not included in) take out: see Queensland University of Technology v Project Constructions (Aust) P/L (In Liq) & Anor [2002] QCA 224 – However it pays to read the payment suspension carefully as if as broad as in Southern Han it is likely to prejudice right to claim (and adjudicate)
  • 41. 41 Termination – If on the other hand Lewence had validly terminated, then: – Both parties were discharged from further performance of the contract; – Lewence’s rights were restricted to rights which had already accrued; – Lewence’s rights to submit progress claim had not yet accrued (claims were to be made 8th day of each month and Lewence’s claim was 4 days early) (at [79]) – Further, no sufficient basis to conclude that cl 37 (progress claim right) survived termination – contract indicated that parties would be left to common law damages remedies (at [80]) – Claims for common law damages are outside scope of legislation (ie Lewence has no adjudication right)
  • 42. Bocol Constructions v Keslake [2017] WASAT 15 (17 January 2017) KEY TOPICS: NAMING OF PARTIES + TYPES OF PAYMENT CLAIMS THAT CAN BE MADE “UNDER” A CONTRACT + COMPLEXITY
  • 43. 43 Overview – Bocol (as main contractor) engaged Keslake as a subcontractor to do some works in relation to a road construction project – Bocol alleged Keslake performed those works defectively (in breach of implied workmanship term) and sought recovery of damages for breach – Bocol submitted a payment claim for those damages, relying on the implied terms – That payment claim became the subject of an adjudication, which was dismissed on the basis that (1) Keslake had been incorrectly named; (2) claim for damages was not able to be adjudicated under CCA – Bocol sought a SAT review (hearing de novo)
  • 44. 44 Naming issue – Bocol had in effect referred to Keslake as: – Bitumen Surfacing (which was Keslake’s trading name) – “The Trustee for the Complete Road Services trust” – Hadn’t used the formal legal name “Keslake Group Pty Ltd” – SAT found it didn’t matter: – “the meaning of 'name' is the nomenclature used to accurately describe a person or entity” (at [60]) – Reg 5 of CC Regs is not to be read narrowly – not the case that any error or misdescription is fatal – No relevant misdescription in any event – it was clear who the respondent was – At any rate s74 of Interpretation Act allows SAT to overlook immaterial non-compliances with statutory forms and that could be applied here
  • 45. 45 Damages claim issue – SAT rejected Bocol’s arguments that CCA, both on its express terms and via the implied terms, permitted a “principal” in the shoes of Bocol to make a contractual claim for damages against a “contractor” in the shoes of Keslake – A claim for damages is not a claim “under” a construction contract – “there has to be a term in the construction contract that provides the right to make the claim not that the claim is 'referable to' or 'a genus of claim provided for by that contract' or 'by reason of the existence of the contract'.” (at [114]) – Here there was no such right (there was no contractual right to claim damages for breach) – What about the implied terms? SAT found they applied but it made no difference …
  • 46. 46 Complexity issue – SAT found the matter was too complex (at [137]) – There was competing expert evidence – Liability was not factually or legally clear – Quantum of damages not straightforward – Contrast approach in NT in ABB v CH2M (August 2016 decision addressed above)
  • 47. ABB Australia v CH2M Hill Australia (No 1) [2017] NTSC 1 (13 January 2017) KEY TOPIC: CONTRACTUALLY NON- CONFORMING PAYMENT CLAIMS
  • 48. Overview – Subcontractor submitted a payment claim (Claim #1) to main contractor, purporting it to be under the contract – However, payment claim did not comply with contractual requirements for making of the claim (subcontractor had not provided security which was a condition precedent to valid payment claim) – Main contractor asked subcontractor to re-submit after relevant security given – Subcontractor did so, and lodged Claim #2 and main contractor issued payment certificate in response for less than amount claimed – Subcontractor took claim to adjudication – adjudicator dismissed on basis that rejection of Claim #1 had triggered time limit – HELD: Claim #1 did not trigger time limit as it was not contractually valid 48
  • 49. Reasoning – Kelly J applied K & J Burns Electrical Pty Ltd v GRD Group (NT) Pty Ltd & Anor [2011] NTCA 1 – In order to determine whether there is a payment dispute, the adjudicator must determine whether the contractor has made a claim for payment under the contract – “This necessarily entails the adjudicator going to the terms of the contract and asking whether what purports to be a payment claim is capable of giving rise to a liability on the part of the principal to pay. If not, then there is no “payment dispute” [and the application must be dismissed]” (at [30]) – The payment claim must be capable of giving rise to a liability to pay under the contract (at [32]) 49
  • 50. Reasoning (cont’d) – A dispute about the contractual validity of a payment claim is not in itself a payment dispute (at [33]), but is a matter which the adjudicator must making a finding on when the adjudicator makes the initial decision whether or not to dismiss (at [34]) – Given the above, on facts of this case, Claim #1 was contractually non-conforming, and its rejection could not trigger a payment dispute within the meaning of the CCA 50
  • 51. ABB Australia v CH2M Hill Australia (No 2) [2017] NTSC 11 (14 Feb 2017) KEY TOPIC: CONTRACTUALLY NON- CONFORMING PAYMENT CLAIMS
  • 52. 52 Overview – Applicant submitted a “non-conforming” payment claim. Respondent issued a payment certificate. Payment claim was adjudicated. – Respondent claimed that fact that the payment claim did not comply with contract meant a “payment dispute” could not arise under NT CCA. – HELD: fact that payment claim was contractually defective was not fatal to creation of payment dispute, since on the facts the recipient didn’t reject the payment claim on that basis.
  • 53. 53 Reasoning in ABB v CH2M – In determining whether a payment dispute exists, adjudicator must first determine whether contractor has made a payment claim under the contract – This requires consideration of the purported payment claim and whether it is “capable of giving rise to a liability on the part of the principal to pay” (at [38]). – Here the respondent failed to reject the claim, but instead issued a payment certificate. Under the terms of the parties’ contract, this certificate itself triggered an obligation to pay (at [39]). – Didn’t matter contractually that claim was non-conforming, therefore it didn’t matter to the adjudication
  • 54. 54 Implications … – Fact that a payment claim may be contractually non-compliant will not necessarily be fatal – Look at contract – if contract on its terms permits certification of non- conforming claims, and attaches a liability to pay to such certification, a non-conforming claim – Query where ABB decisions leave the “broader” approach, found in earlier SAT decisions such as Blackadder Scaffolding v Mirvac Homes (WA) [2009] WASAT 133, at [68] – suggested, particularly when read in conjunction with SAT not adopting the majority view in K&J Burns (see Georgiou Group and MCC Mining [2011] WASAT 120, at [64]) that, so long as payment claim could in a general sense be described as a payment claim under the contract, it didn’t matter it if did not strictly comply
  • 55. Total Eden Pty Ltd -v- ECA Systems Pty Ltd [2017] WASC 58 (9 February 2017) KEY TOPICS: SET-OFFS + DETERMINATION OF CURRENT LIABILITY + IMPLIED TERMS + COSTS
  • 56. 56 Context – Total Eden sought an order (under Civil Judgments Enforcement Act) suspending enforcement of judgment pending the outcome of judicial review of a determination – resolution of that application required Pritchard J to express preliminary views on merits of the judicial review application – Total Eden was granted a suspension order including on basis that the judicial review application had reasonable prospects of success
  • 57. 57 Observations made – set-offs, implied terms – Determination reasons did not make it clear that the adjudicator had considered a set-off raised by Total Eden against ECA – against that background it was fairly arguable that adjudicator had made an error in making a determination of Total Eden’s liability as at the date the payment to ECA was due, rather than the date of the determination (at [20]) – It was also reasonably arguable that the implied terms (cl 7, Sch 1) re responding to a payment claim did not exclude Total Eden’s common law rights to set-off (at [21]) – this on the basis that court would be slow to infer that established common law rights are excluded
  • 58. 58 Observations made - costs – Pritchard J also indicated she felt it was arguable that there was a reviewable error in the adjudicator awarding costs against Total Eden, on the basis that Total Eden had not acted frivolously or vexatiously (at [23])
  • 59. Parkview Construction v Total Lifestyle [2017] NSWSC 194 (7 March 2017) KEY TOPIC: SERVICE OF ELECTRONIC DOCUMENTS
  • 60. 60 Overview – FACTS: – Adjudication application was uploaded to nominating authority on a cloud service (Hightail) – Applicant pasted same files across to a USB stick – The respondent was served with the USB stick – HELD: service of USB stick was not effective service under the NSW security of payment legislation
  • 61. 61 Reasoning in Parkview: – Key point: “service” under the NSW security of payment legislation requires service of a written copy of the application (at [73]) – Findings (at [75]-[81]): – Generally, service will be effective where the party served has become aware of the contents of a document – In case of an email, or upload to cloud, service will not be effected until the transmission or upload is actually accessed by the recipient – Service of the USB stick is NOT the same as service of the writing stored on the USB stick: – USB does not represent or reproduce words visibly; – Delivery of a USB is not transmission in writing just as delivering a CD is not aural transmission of the recording embedded upon it
  • 62. INPEX Operations Australia Pty Ltd v JKC Australia LNG Pty Ltd [2017] NTSC 45 (15 June 2017) KEY TOPICS: JURISDICTIONAL ERROR + DENIAL OF NATURAL JUSTICE + PAYMENT DISPUTE + IMPLIED TERMS
  • 63. 63 Facts – JKC lodged payment claim against Inpex, which Inpex disputed in part – JKC brought an application seeking to adjudicate part of the dispute – 34 volumes of material in the application – Importantly, JKC’s application didn’t contend that Inpex was contractually precluded from disputing the merits of JKC’s claims – The adjudicator sought submissions from the parties as to whether the implied provisions of the CCA applied to the EPC contract based on a deficiency he perceived in the way the payment terms operated – Both parties filed submissions to the effect that the implied provisions did NOT apply
  • 64. 64 Adjudicator’s finding – The implied terms applied – As there was no evidence as to prove that Inpex had issued a notice of dispute within the 14 day period set out in the implied terms, there was a deemed acceptance and Inpex became liable to pay the full amount – Inpex applied to Supreme Court (NT) for judicial review
  • 65. 65 Reviewable/jurisdictional error – Kelly J [28] An error of law in construing provisions of the Act which give the adjudicator his jurisdiction to make a determination will render a determination a nullity reviewable by this Court. However, non- jurisdictional errors of law or fact made by an adjudicator in the process of making a bona fide attempt to carry out the functions conferred on him or her by the Act are not amenable to review by this Court. If the only complaint were that the Adjudicator had misconstrued the EPC Contract, then that would not, of itself, render the Determination a nullity, reviewable by the Court … unless it could be shown that the Adjudicator’s decision was unreasonable (in the Wednesbury sense) or that there was a substantial failure to comply with the requirements of procedural fairness in the circumstances.
  • 66. 66 Denial of natural justice – Kelly J found a denial of natural justice had been made out – Relevantly: – [30] Procedural fairness required that the Adjudicator notify the parties of “proposed conclusions that were not put forward by the parties and could not be easily anticipated.” The Court will set aside a purported determination by an adjudicator where there has been a failure by an adjudicator to provide such procedural fairness and, as a result, a party has been deprived of the possibility of a successful outcome. – Here the adjudicator needed to do more than ask for submissions on whether the implied terms applied
  • 67. 67 – Adjudicator failed to warn parties that he was considering making a determination on the basis of the “deemed acceptance” operation of the implied terms – Inpex was denied opportunity to put submissions on that issue, including on the basis that: – JKC’s payment claim was not compliant with the contract; or – there was some estoppel or waiver which prevented JKC relying on 14 day response time; or – even if the implied terms applied, an adjudicator was still obliged to be satisfied that the work was done and money owing
  • 68. 68 – Kelly J didn’t accept that it was apparent from asking for submissions on the implied terms that the adjudicator was flagging he might make a determination based on the implied terms – this was because the adjudicator had made it clear that the parties’ submissions on the implied terms issue had to be restricted to whether the implied terms applied (at [38]) – Not necessary to assess the merits of Inpex’s arguments on implied terms – was satisfied that a different outcome may have eventuated (at [41]) – Kelly J in effect warned adjudicators from making a determination on a basis not contended for by either party, without first giving the parties to make submissions on that basis – see [44]
  • 69. 69 Scope of a payment dispute – Inpex alternatively argued that by determining the matter on a basis not argued by the parties, the adjudicator had gone beyond his powers, which were confined to analysing the specific payment dispute that gave rise to the application – Inpex’s argument sought to distinguish between payment disputes arising due to an actual dispute, as opposed to disputes arising due to mere non-payment – Kelly J rejected this alternative argument
  • 70. 70 Operation of implied terms – Inpex further argued that adjudicator had erred in blindly applying the implied terms “deemed acceptance”, and that he ought to have turned his mind to the underlying merits of JKC’s claim – Kelly J rejected this (at [58]): As has been said many times in cases connected with this Act, the focus of the Act is on the contract. If the contract between the parties provides for a claim to be paid in full if not disputed within a given time, then there is no reason why an adjudicator ought not give effect to that provision in making a determination on the merits under s 33(1)(b), and every reason why he should.
  • 72. Takeaways Parties must be given full opportunity to be heard on what will underpin adjudicator’s decision Reasons must explain the “why” behind adjudicator’s key findings (why party A expert preferred over party B) A single jurisdictional error on a minor point (eg costs) could lead to entire determination being void Cannot make a determination to pay on amounts not claimed in the original payment claim 72
  • 73. Takeaways Determinations must be for contractual entitlements only and be for work covered by the CCA Do you make a merits dismissal if no payment claim/dispute? Set offs cannot be ignored or overlooked – need to determine current liability to pay Ground continues to shift on when the implied terms apply 73
  • 74. Questions? Follow us on Twitter: @LavanTweets Follow us on LinkedIn: Lavan 74