SlideShare a Scribd company logo
1 of 13
Download to read offline
Mustang Wind Farm Collector System
Centerville, WA
EE 456
Project 1 Final Report
April 24, 2015
Prepared by:
Yussuf Roble
Bayu Halim
Ki Hei Chan
for
Mr. John Smith
VP of Resource Development
Renewable Power Corporation, inc.
Executive Summary
Figure 1
After analyzing different design options, we have decided to build the collector system for
Mustang Wind Farm using an overhead implementation of the design shown in Figure 1. This
design has a total construction cost of $4,073,913.56 with a total annualized cost of $381,862.54/
year (total annualized cost includes the annualized cost of equipment, cost of unreliability, and
annual energy loss). In comparison with other design options that we have considered (different
designs will be further analyzed in the later sections), this design is relatively reliable, and the
cheapest to build.
Although underground transmission lines may prove to be more reliable than overhead
transmission lines, the difference in the cost of unreliability between overhead and underground
lines does not outweigh the difference in the total construction costs. Therefore, we have decided
to build overhead transmission lines using the above design for the Mustang Wind Farm collector
system.
Design Consideration
Figure 2
1st
Design Figure 3
2nd
Design
In choosing our design for the collector system, we have considered two designs which are shown
above (refer to Figure 2 and Figure 3). For the purpose of this comparison, we are going to compare
the two designs by connecting them through overhead lines. The 1st
design involves connecting
two rows of 20 wind turbines and having a thicker conductor running from two connected rows to
the substation. The 2nd
design has each row connected straight up to the substation. There are 2
main differences: 1st
design requires two types of wire (refer to Table 6 in the appendix) and three
circuit breakers on each line that runs into the substation, and 2nd
design requires only one type of
wires (first row of Table 6 in the appendix) for all the connections, but four circuit breakers are
required on each line that runs into the substation.
We have decided to go with the 1st
design because it is cheaper compared to the second design.
The total construction cost for the 1st
design is $4,073,913.56 with a total annualized cost of
$381,862.54 (this includes the annualized cost of equipment, cost of unreliability, and annual
energy loss). The 2nd
design costs more to construct. The total construction cost is $4,174,311.977
with a total annualized cost of $399,009.23. It is evident from these numbers that the 1st
design is
cheaper to build. This is mainly because the 1st
design requires shorter conductors which greatly
reduces the construction cost. The 1st
design requires approximately 22.6 km of conductors while
the 2nd
design requires approximately 25.75 km. Furthermore, the 1st
design requires only three
circuit breakers while the 2nd
design requires four circuit breakers on each line that runs to the
substation. Table 1 summarizes the cost comparison between the two designs.
1st
design 2nd
design Cost difference
Total Construction Cost $4,073,913.56 $4,174,311.977 ($100,398.417)
Annualized cost $198,582.72/year $202,385.42/year ($3,802.7)
Cost of unreliability $6,568.38 /year $7,484.25 /year ($915.87)
Annual energy loss $176,711.44/year $189,139.56/year ($12,428.12)
Total annualized cost $381,862.54/year $399,009.23/year ($17,146.69)
Table 1
Besides its cheaper overall cost, 1st
design is more favorable because it is more reliable. As shown
in Table 1, the cost of unreliability of the 1st
design is $6,568.38 /year while the cost of unreliability
of the 2nd
design is $7,484.25 /year. Although having four circuit breakers may seem to be more
reliable than just three, the length of conductors is a more important factor in this case. Having
longer conductors translates to more occurrences of fault, and thus increasing the expected outage
time. Having shorter conductors, however, is more reliable. The expected outage time (EOT) for
the 1st
design was calculated to be approximately 50.55 hours/year while the EOT for the 2nd
design
was calculated to be approximately 57.6 hours/year. Therefore, the 1st
design is more reliable.
Overhead vs underground
We have analyzed two designs in the previous section and justified that the first design is by far
the best option. In this section, we are comparing between overhead and underground
implementations of the 1st
design.
Overhead Underground Difference
Total Construction Cost $4,073,913.56 $16,236,483.391 ($12,162,569.83)
Annualized cost $198,582.72/year $216,501.29/year ($17,918.57)
Cost of unreliability $6,568.38 /year $5,254.70/year $1,313.68
Annual energy loss $176,711.44/year $176,711.44/year $0.00
Total Annualized cost $381,862.54/year $398,467.43/year ($16,605.03)
Table 2
Table 2 above summarizes the total construction and annualized cost for overhead and
underground implementations of the 1st
design. The total construction cost of underground lines is
significantly more expensive than overhead lines because underground conductors are more
expensive. The price of an overhead conductor is $1.62/lb. while the price of an underground
conductor is $8.46/lb. Furthermore, underground transmission lines require conduits. These
conduits are $55/foot. These prices contribute to high cost of underground lines construction. The
difference in annualized cost is mainly due to the lifetime of underground lines. The lifetime of
underground conductors is 20 years while the lifetime of overhead conductors is 40 years. This
means that underground lines will require more maintenance than overhead lines.
In terms of cost of unreliability, underground lines are more reliable than overhead lines.
According to Table 2 above, the cost difference in terms of unreliability is approximately
$1,313.68. Even though underground lines are proven to be more reliable, the cost difference in
terms of unreliability does not outweigh the difference in annualized cost which is approximately
$17,918.57. Thus, it is cheaper to go with overhead lines implementation of the 1st
design.
Note: The detailed calculation of cost, reliability, and energy lost can be found in the appendix
Reliability
Process
Reliability analysis is one of the significant parts because we have to make sure our project design
are able to deal with unpredictable things occur and consider how much potential money would
loss when the power output doesn’t achieve the ideal prediction. We have to know which model
has the less annual reliability cost in order to choose the best transmission circuit design. In this
process, we have to realize two parts. The first part is the value of the worst fault current occur in
each of the models, and the second part is the money loss because of some fault current occur and
normal power loss during the process of energy transmission.
In the first part, we have to compare the largest fault current—line to ground fault in these three
models. According to the cost sheet file, we know the per unit impedance of a transformer and a
generator in the base 100 MVA apparent power. Therefore, in order to find the fault current, we
have to convert all the per unit value into 31.579MVA (total power in one conductor line = 30MW
and power factor = 0.95). Next, we find the total line resistance in each conductor by consulting
the ACSR table. Finally, we can sum all the impedance and use the apparent power to calculate
line to ground fault current.
In the second case, we have to calculate and compare the annual unreliability cost of these three
models. In this process, we have to find the cost by total fault current (permanent and temporary),
the cost by permanent fault only. We have to find out the voltage drop, and power loss due to
current transmission in order to calculate the annual value loss.
Result:
Fault Current Analysis
1st
design overhead 2nd
design overhead 1st
design underground
Line 1 720 A 720 A 720 A
Line 2 720 A 720 A 720 A
Line 3 2629 A 707 A 2629 A
Line 4 2629 A 694 A 2629 A
Table 3
As we didn’t do any changing in Line 1 and Line 2 which are the two upper Lines connect to the
left and right of the substation, all the models supposed to receive at most 720A fault current in
each line. In overhead implementation of the 1st
design, we can see the way that we combine two
lines will have to be considered some of the impedance in parallel circuit. We calculated the total
impedance in this way will be less than the overhead implementations of the 2nd
design, which all
the conductors are lined to substation separately. Therefore, we expect the fault current of the 1st
design to be larger than the 2nd
design and we estimate the fault current in 1st
design to be four
times higher than 2nd
design. For underground implementations of the 1st
design, although we
change all the conductors in the 1st
design from overhead into underground, we use the same length
and size of aluminum to make the conductor. Hence, the fault current is the same as the 1st
design.
Unreliability Loss
Total energy loss
(MWh/year)
Total energy loss
due to permanent
fault
(MWh/year)
Voltage
Drop (V)
Power Loss
(MW)
1st
design overhead 1501 375 6227 1.15
2nd
design overhead 1710 427.7 7373 1.23
1st
design underground 300 300 6227 1.15
Table 4
Cost of Unreliability
Total fault
($/year)
Permanent fault
($/year)
Annual Value
Loss ($k/year)
1st
design overhead 8.758 6,568.38 176.7
2nd
design overhead 9.937 7,484.25 189.1
1st
design underground 1.752 5,254.70 176.7
Table 5
According to Table 4, the total energy loss in overhead implementations of 1st
and 2nd
design is
five times larger than the underground implementation of the 1st
design. The reason is there are no
temporary fault current occur in underground. Thus, we decided to build circuit breakers in each
of the conductors. As the circuit breakers are able to deal with the temporary fault current in a
very short period (around 1 minute), temporary fault current doesn’t seem affect the whole system
operation seriously. Thus, we can just compare the cost by permanent fault only.
According to Table 4, we can see that the way that combine line 3 and line 4 are able to reduce the
power by fault and the power loss during the normal operation as well. Also, the voltage drop of
the 1st
design is lower than the 2nd
design. Afterward, when we estimate the cost of these power
loss, we conclude that although the fault current will increase if we combine line 3 and line 4, we
still can save some money for the unreliability cost by fault current. Moreover, we can save more
than $10,000 in power loss during the normal operation. Finally, underground implementation
seems have better reliability, yet the difference in cost of unreliability does not seem to outweigh
the difference in annualized cost of the two designs.
Standards
Impact of Global Warming on our Design
Conclusion
Appendix
Conductor type Weight (lbs/mile) Current Carrying Capacity (A)
336400 cmils ACSR 2442 530
954000 cmils ACSR 6479 1010
Table 6
Ro
w
Dis
tan
ce
No.
of
pol
es
and
ins
ulat
or
Cost of
poles
and
insulato
r
A of
poles
and
insulat
or
XFMR
cost
A of a
XFMR
Price
of
condu
ctor
per lb
Conductor
cost for a
single
turbine
A of a
conducto
r
Connection
Cost for a
single turbine
Total A
1 &
4
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
1 13 $32,808 $1,419 $37,500 $1,913 $1.62 $7,417.575 $320.902 $77,725.975 $3,653.49
Total cost
for 3 phase
$943,084.68 $46,617.75
2 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
3.2 41
$103,74
9
$4,488 $37,500 $1,913 $1.62 $23,456.432
$1,014.7
81
$164,705.702 $7,416.44
Total cost
for 3 phase
$1,030,064.4
1
$50,380.70
3 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
2.2 29 $73,362 $3,174 $37,500 $1,913 $1.62 $16,586.202 $717.559 $127,448.015 $5,804.59
Total cost
for 3 phase
$992,806.72 $48,768.84
Table 7
Overhead 1st
Design Cost Calculation
Ro
w
Dis
tan
ce
No.
of
pol
es
and
ins
ulat
or
Cost of
poles
and
insulato
r
A of
poles
and
insulat
or
XFMR
cost
A of a
XFMR
Price
of
condu
ctor
per lb
Conductor
cost for a
turbine
A of a
conductor
Connection
Cost for a
turbine Total A
1 &
4 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
1 13 $32,808 $1,419 $37,500 $1,913 $1.62 $7,417.575 $320.902 $77,725.975 $3,653.49
Total cost
for 3 phase $943,084.68 $46,617.75
2 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
3.1
623 41
$103,74
9 $4,488 $37,500 $1,913 $1.62 $23,456.432 $1,014.781 $164,705.702 $7,416.44
Total cost
for 3 phase $1,030,064.41 $50,380.70
3 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
5.3
852 71
$176,67
9 $7,644 $37,500 $1,913 $1.62 $39,944.864 $1,728.110 $254,123.505 $11,284.87
Total cost
for 3 phase $1,119,482.21 $54,249.12
Table 8
Overhead 2nd
Design Cost Calculation
Row Distance
XFMR
cost
A of a
XMFR
Price of
conductor
per lb
Conductor
cost for a
turbine
A of
conductor
Cost of
conduits and
ditching per
km
Connection
Cost for a
turbine Total A
1&4 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
1 $37,500 $1,913 $8.46 $38,736.225 $2,603.683 $180,446.200 $617,574.83 $4,516.90
Total cost for
3 phase $3,534,359.160 $50,762.12
2 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
3.2 $37,500 $1,913 $8.46 $122,494.699 $8,233.568 $180,446.200 $1,871,857.66 $10,146.79
Total cost for
3 phase $4,788,641.995 $56,392.01
3 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
2.2 $37,500 $1,913 $8.46 $86,616.832 $5,822.012 $180,446.200 $1,334,586.74 $7,735.23
Total cost for
3 phase $4,251,371.076 $53,980.45
Table 9
Underground 1st
Design cost calculation
overhead
(permanent fault) length(m) length(mile)
EF
(faults/year) EOT (hours/year)
Production lost
(MWh/year)
Line 1 4800 2.9825808 1.78954848 2.68432272 26.57479493
Line 2 4800 2.9825808 1.78954848 2.68432272 26.57479493
Lines 3 & 4 (2lines
together) 9836 6.111805156 3.667083094 5.50062464 54.45618394
Lines 3 & 4 to sub 3162 1.964775102 1.178865061 1.768297592 17.50614616
Total production
lost (MWh/year) 375.3357599
cost of unreliability $6,568.38
Table 10
Overhead 1st Design Cost of unreliability calculation
overhead
(permanent fault) length(m) length(mile) EF(faults/year) EOT(hours/year)
Production Lost
(MWh/year)
Line 1 4800 2.9825808 1.78954848 2.68432272 26.57479493
Line 2 4800 2.9825808 1.78954848 2.68432272 26.57479493
Lines 3 & 4 (2lines
together) 6963 4.326606273 2.595963764 3.893945646 38.55006189
Lines 3 & 4 to sub 9186 5.707914006 3.424748404 5.137122605 50.85751379
Total Production lost
(MWh/year) 427.6714966
cost of unreliability $7,484.25
Table 11
Overhead 2ND Design Cost of unreliability calculation
Underground
(permanent fault) length(m) length(mile) EF(faults/year) EOT(hours/year)
Production
lost(MWh/year)
Line 1 4800 2.9825808 0.178954848 2.147458176 21.25983594
Line 2 4800 2.9825808 0.178954848 2.147458176 21.25983594
Lines 3 & 4 (2lines
together) 9836 6.111805156 0.366708309 4.400499712 43.56494715
Lines 3 & 4 to
substation 3162 1.964775102 0.117886506 1.414638073 14.00491693
Total production
lost(MWh/year) 300.2686079
cost of unreliability $5,254.70
Table 12
Underground 1st Design Cost of unreliability calculation

More Related Content

What's hot

Design and analysis of boost converter with cld cell
Design and analysis of boost converter with cld cellDesign and analysis of boost converter with cld cell
Design and analysis of boost converter with cld celleSAT Journals
 
Rlc circuits and differential equations1
Rlc circuits and differential equations1Rlc circuits and differential equations1
Rlc circuits and differential equations1Ghanima Eyleeuhs
 
A New Single-Stage Multilevel Type Full-Bridge Converter Applied to closed lo...
A New Single-Stage Multilevel Type Full-Bridge Converter Applied to closed lo...A New Single-Stage Multilevel Type Full-Bridge Converter Applied to closed lo...
A New Single-Stage Multilevel Type Full-Bridge Converter Applied to closed lo...IOSR Journals
 
An Active Input Current Waveshaping with Zero Switching Losses for Three-Phas...
An Active Input Current Waveshaping with Zero Switching Losses for Three-Phas...An Active Input Current Waveshaping with Zero Switching Losses for Three-Phas...
An Active Input Current Waveshaping with Zero Switching Losses for Three-Phas...IDES Editor
 
Circuit theory 1 finals
Circuit theory 1 finalsCircuit theory 1 finals
Circuit theory 1 finalsjerbor
 
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...IJERD Editor
 
Rectifiers Simulation
Rectifiers SimulationRectifiers Simulation
Rectifiers SimulationZunAib Ali
 
Power converter report
Power converter reportPower converter report
Power converter reportZunAib Ali
 
Two Stage Amplifier
Two Stage AmplifierTwo Stage Amplifier
Two Stage AmplifierJacob Ramey
 
PF correction using SEPIC
PF correction using SEPICPF correction using SEPIC
PF correction using SEPICSoumya Dash
 
12 11jan17 24 oct16 13127 28779-1-ed(edit-new)
12 11jan17 24 oct16 13127 28779-1-ed(edit-new)12 11jan17 24 oct16 13127 28779-1-ed(edit-new)
12 11jan17 24 oct16 13127 28779-1-ed(edit-new)IAESIJEECS
 
Rc and rl differentiator and integrator circuit
Rc and rl differentiator and integrator circuitRc and rl differentiator and integrator circuit
Rc and rl differentiator and integrator circuittaranjeet10
 
Efficiency and Power Factor improvement of Bridgeless Soft-switched PWM Cuk C...
Efficiency and Power Factor improvement of Bridgeless Soft-switched PWM Cuk C...Efficiency and Power Factor improvement of Bridgeless Soft-switched PWM Cuk C...
Efficiency and Power Factor improvement of Bridgeless Soft-switched PWM Cuk C...IOSR Journals
 
A comparison of soft switched dc to dc converters for electrolyzer application
 A comparison of soft switched dc to dc converters for electrolyzer application A comparison of soft switched dc to dc converters for electrolyzer application
A comparison of soft switched dc to dc converters for electrolyzer applicationAsoka Technologies
 
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...IRJET Journal
 

What's hot (20)

Design and analysis of boost converter with cld cell
Design and analysis of boost converter with cld cellDesign and analysis of boost converter with cld cell
Design and analysis of boost converter with cld cell
 
Rlc circuits and differential equations1
Rlc circuits and differential equations1Rlc circuits and differential equations1
Rlc circuits and differential equations1
 
A New Single-Stage Multilevel Type Full-Bridge Converter Applied to closed lo...
A New Single-Stage Multilevel Type Full-Bridge Converter Applied to closed lo...A New Single-Stage Multilevel Type Full-Bridge Converter Applied to closed lo...
A New Single-Stage Multilevel Type Full-Bridge Converter Applied to closed lo...
 
An Active Input Current Waveshaping with Zero Switching Losses for Three-Phas...
An Active Input Current Waveshaping with Zero Switching Losses for Three-Phas...An Active Input Current Waveshaping with Zero Switching Losses for Three-Phas...
An Active Input Current Waveshaping with Zero Switching Losses for Three-Phas...
 
Circuit theory 1 finals
Circuit theory 1 finalsCircuit theory 1 finals
Circuit theory 1 finals
 
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
 
Rectifiers Simulation
Rectifiers SimulationRectifiers Simulation
Rectifiers Simulation
 
K010337787
K010337787K010337787
K010337787
 
Ripple theorem
Ripple theoremRipple theorem
Ripple theorem
 
Power converter report
Power converter reportPower converter report
Power converter report
 
Two Stage Amplifier
Two Stage AmplifierTwo Stage Amplifier
Two Stage Amplifier
 
PF correction using SEPIC
PF correction using SEPICPF correction using SEPIC
PF correction using SEPIC
 
12 11jan17 24 oct16 13127 28779-1-ed(edit-new)
12 11jan17 24 oct16 13127 28779-1-ed(edit-new)12 11jan17 24 oct16 13127 28779-1-ed(edit-new)
12 11jan17 24 oct16 13127 28779-1-ed(edit-new)
 
Rc and rl differentiator and integrator circuit
Rc and rl differentiator and integrator circuitRc and rl differentiator and integrator circuit
Rc and rl differentiator and integrator circuit
 
Efficiency and Power Factor improvement of Bridgeless Soft-switched PWM Cuk C...
Efficiency and Power Factor improvement of Bridgeless Soft-switched PWM Cuk C...Efficiency and Power Factor improvement of Bridgeless Soft-switched PWM Cuk C...
Efficiency and Power Factor improvement of Bridgeless Soft-switched PWM Cuk C...
 
M1028993
M1028993M1028993
M1028993
 
Flyback Converters v4
Flyback Converters v4Flyback Converters v4
Flyback Converters v4
 
A comparison of soft switched dc to dc converters for electrolyzer application
 A comparison of soft switched dc to dc converters for electrolyzer application A comparison of soft switched dc to dc converters for electrolyzer application
A comparison of soft switched dc to dc converters for electrolyzer application
 
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...
 
PES'16 poster
PES'16 posterPES'16 poster
PES'16 poster
 

Similar to Mustang Wind Farm Collector System Design Report

Influence choice of the injection nodes of energy source on on-line losses of...
Influence choice of the injection nodes of energy source on on-line losses of...Influence choice of the injection nodes of energy source on on-line losses of...
Influence choice of the injection nodes of energy source on on-line losses of...IJMER
 
Novel Global Elmore Delay Optimized Model with Improved Elmore Delay Estimati...
Novel Global Elmore Delay Optimized Model with Improved Elmore Delay Estimati...Novel Global Elmore Delay Optimized Model with Improved Elmore Delay Estimati...
Novel Global Elmore Delay Optimized Model with Improved Elmore Delay Estimati...IRJET Journal
 
IRJET- Comparative Analysis of Concrete Filled Steel Tubular Truss Bridge wit...
IRJET- Comparative Analysis of Concrete Filled Steel Tubular Truss Bridge wit...IRJET- Comparative Analysis of Concrete Filled Steel Tubular Truss Bridge wit...
IRJET- Comparative Analysis of Concrete Filled Steel Tubular Truss Bridge wit...IRJET Journal
 
Analysis of rc bridge decks for selected national a nd internationalstandard ...
Analysis of rc bridge decks for selected national a nd internationalstandard ...Analysis of rc bridge decks for selected national a nd internationalstandard ...
Analysis of rc bridge decks for selected national a nd internationalstandard ...eSAT Journals
 
Analysis of rc bridge decks for selected national a nd internationalstandard ...
Analysis of rc bridge decks for selected national a nd internationalstandard ...Analysis of rc bridge decks for selected national a nd internationalstandard ...
Analysis of rc bridge decks for selected national a nd internationalstandard ...eSAT Journals
 
Analysis of rc bridge decks for selected national a nd internationalstandard ...
Analysis of rc bridge decks for selected national a nd internationalstandard ...Analysis of rc bridge decks for selected national a nd internationalstandard ...
Analysis of rc bridge decks for selected national a nd internationalstandard ...eSAT Journals
 
Analysis of rc bridge decks for selected national a nd internationalstandard ...
Analysis of rc bridge decks for selected national a nd internationalstandard ...Analysis of rc bridge decks for selected national a nd internationalstandard ...
Analysis of rc bridge decks for selected national a nd internationalstandard ...eSAT Journals
 
Analysis of rc bridge decks for selected national and internationalstandard l...
Analysis of rc bridge decks for selected national and internationalstandard l...Analysis of rc bridge decks for selected national and internationalstandard l...
Analysis of rc bridge decks for selected national and internationalstandard l...eSAT Publishing House
 
Review: Potential Ecodesign regulation for economic cable conductor sizing in...
Review: Potential Ecodesign regulation for economic cable conductor sizing in...Review: Potential Ecodesign regulation for economic cable conductor sizing in...
Review: Potential Ecodesign regulation for economic cable conductor sizing in...Leonardo ENERGY
 
Electric Field Analysis and Impact Study with Shrubbery on the 11 kV Distribu...
Electric Field Analysis and Impact Study with Shrubbery on the 11 kV Distribu...Electric Field Analysis and Impact Study with Shrubbery on the 11 kV Distribu...
Electric Field Analysis and Impact Study with Shrubbery on the 11 kV Distribu...IRJET Journal
 
Parametric investigation of cable stayed bridge using macro based program
Parametric investigation of cable stayed bridge using macro based programParametric investigation of cable stayed bridge using macro based program
Parametric investigation of cable stayed bridge using macro based programeSAT Journals
 
A Self-Balancing Switched Capacitor Multilevel Inverter Structure with Six-fo...
A Self-Balancing Switched Capacitor Multilevel Inverter Structure with Six-fo...A Self-Balancing Switched Capacitor Multilevel Inverter Structure with Six-fo...
A Self-Balancing Switched Capacitor Multilevel Inverter Structure with Six-fo...IRJET Journal
 
A bridgeless cuk converter based induction motor drive for pfc applications
A bridgeless cuk converter based induction motor drive for pfc applicationsA bridgeless cuk converter based induction motor drive for pfc applications
A bridgeless cuk converter based induction motor drive for pfc applicationsIAEME Publication
 
STUDY OF HARPS PERIPHERAL AND PERIMETRAL BRACINGS PATTERN SHAPE IN PRE ENGINE...
STUDY OF HARPS PERIPHERAL AND PERIMETRAL BRACINGS PATTERN SHAPE IN PRE ENGINE...STUDY OF HARPS PERIPHERAL AND PERIMETRAL BRACINGS PATTERN SHAPE IN PRE ENGINE...
STUDY OF HARPS PERIPHERAL AND PERIMETRAL BRACINGS PATTERN SHAPE IN PRE ENGINE...IRJET Journal
 
IRJET- A Novel High Speed Power Efficient Double Tail Comparator in 180nm...
IRJET-  	  A Novel High Speed Power Efficient Double Tail Comparator in 180nm...IRJET-  	  A Novel High Speed Power Efficient Double Tail Comparator in 180nm...
IRJET- A Novel High Speed Power Efficient Double Tail Comparator in 180nm...IRJET Journal
 

Similar to Mustang Wind Farm Collector System Design Report (20)

Influence choice of the injection nodes of energy source on on-line losses of...
Influence choice of the injection nodes of energy source on on-line losses of...Influence choice of the injection nodes of energy source on on-line losses of...
Influence choice of the injection nodes of energy source on on-line losses of...
 
Murali base
Murali baseMurali base
Murali base
 
Murali base
Murali baseMurali base
Murali base
 
Novel Global Elmore Delay Optimized Model with Improved Elmore Delay Estimati...
Novel Global Elmore Delay Optimized Model with Improved Elmore Delay Estimati...Novel Global Elmore Delay Optimized Model with Improved Elmore Delay Estimati...
Novel Global Elmore Delay Optimized Model with Improved Elmore Delay Estimati...
 
IRJET- Comparative Analysis of Concrete Filled Steel Tubular Truss Bridge wit...
IRJET- Comparative Analysis of Concrete Filled Steel Tubular Truss Bridge wit...IRJET- Comparative Analysis of Concrete Filled Steel Tubular Truss Bridge wit...
IRJET- Comparative Analysis of Concrete Filled Steel Tubular Truss Bridge wit...
 
Analysis of rc bridge decks for selected national a nd internationalstandard ...
Analysis of rc bridge decks for selected national a nd internationalstandard ...Analysis of rc bridge decks for selected national a nd internationalstandard ...
Analysis of rc bridge decks for selected national a nd internationalstandard ...
 
Analysis of rc bridge decks for selected national a nd internationalstandard ...
Analysis of rc bridge decks for selected national a nd internationalstandard ...Analysis of rc bridge decks for selected national a nd internationalstandard ...
Analysis of rc bridge decks for selected national a nd internationalstandard ...
 
Analysis of rc bridge decks for selected national a nd internationalstandard ...
Analysis of rc bridge decks for selected national a nd internationalstandard ...Analysis of rc bridge decks for selected national a nd internationalstandard ...
Analysis of rc bridge decks for selected national a nd internationalstandard ...
 
Analysis of rc bridge decks for selected national a nd internationalstandard ...
Analysis of rc bridge decks for selected national a nd internationalstandard ...Analysis of rc bridge decks for selected national a nd internationalstandard ...
Analysis of rc bridge decks for selected national a nd internationalstandard ...
 
Analysis of rc bridge decks for selected national and internationalstandard l...
Analysis of rc bridge decks for selected national and internationalstandard l...Analysis of rc bridge decks for selected national and internationalstandard l...
Analysis of rc bridge decks for selected national and internationalstandard l...
 
Review: Potential Ecodesign regulation for economic cable conductor sizing in...
Review: Potential Ecodesign regulation for economic cable conductor sizing in...Review: Potential Ecodesign regulation for economic cable conductor sizing in...
Review: Potential Ecodesign regulation for economic cable conductor sizing in...
 
Electric Field Analysis and Impact Study with Shrubbery on the 11 kV Distribu...
Electric Field Analysis and Impact Study with Shrubbery on the 11 kV Distribu...Electric Field Analysis and Impact Study with Shrubbery on the 11 kV Distribu...
Electric Field Analysis and Impact Study with Shrubbery on the 11 kV Distribu...
 
Group 1,6
Group 1,6Group 1,6
Group 1,6
 
Group 1,6
Group 1,6Group 1,6
Group 1,6
 
Parametric investigation of cable stayed bridge using macro based program
Parametric investigation of cable stayed bridge using macro based programParametric investigation of cable stayed bridge using macro based program
Parametric investigation of cable stayed bridge using macro based program
 
A Self-Balancing Switched Capacitor Multilevel Inverter Structure with Six-fo...
A Self-Balancing Switched Capacitor Multilevel Inverter Structure with Six-fo...A Self-Balancing Switched Capacitor Multilevel Inverter Structure with Six-fo...
A Self-Balancing Switched Capacitor Multilevel Inverter Structure with Six-fo...
 
report
reportreport
report
 
A bridgeless cuk converter based induction motor drive for pfc applications
A bridgeless cuk converter based induction motor drive for pfc applicationsA bridgeless cuk converter based induction motor drive for pfc applications
A bridgeless cuk converter based induction motor drive for pfc applications
 
STUDY OF HARPS PERIPHERAL AND PERIMETRAL BRACINGS PATTERN SHAPE IN PRE ENGINE...
STUDY OF HARPS PERIPHERAL AND PERIMETRAL BRACINGS PATTERN SHAPE IN PRE ENGINE...STUDY OF HARPS PERIPHERAL AND PERIMETRAL BRACINGS PATTERN SHAPE IN PRE ENGINE...
STUDY OF HARPS PERIPHERAL AND PERIMETRAL BRACINGS PATTERN SHAPE IN PRE ENGINE...
 
IRJET- A Novel High Speed Power Efficient Double Tail Comparator in 180nm...
IRJET-  	  A Novel High Speed Power Efficient Double Tail Comparator in 180nm...IRJET-  	  A Novel High Speed Power Efficient Double Tail Comparator in 180nm...
IRJET- A Novel High Speed Power Efficient Double Tail Comparator in 180nm...
 

Mustang Wind Farm Collector System Design Report

  • 1. Mustang Wind Farm Collector System Centerville, WA EE 456 Project 1 Final Report April 24, 2015 Prepared by: Yussuf Roble Bayu Halim Ki Hei Chan for Mr. John Smith VP of Resource Development Renewable Power Corporation, inc.
  • 2. Executive Summary Figure 1 After analyzing different design options, we have decided to build the collector system for Mustang Wind Farm using an overhead implementation of the design shown in Figure 1. This design has a total construction cost of $4,073,913.56 with a total annualized cost of $381,862.54/ year (total annualized cost includes the annualized cost of equipment, cost of unreliability, and annual energy loss). In comparison with other design options that we have considered (different designs will be further analyzed in the later sections), this design is relatively reliable, and the cheapest to build. Although underground transmission lines may prove to be more reliable than overhead transmission lines, the difference in the cost of unreliability between overhead and underground lines does not outweigh the difference in the total construction costs. Therefore, we have decided to build overhead transmission lines using the above design for the Mustang Wind Farm collector system.
  • 3. Design Consideration Figure 2 1st Design Figure 3 2nd Design In choosing our design for the collector system, we have considered two designs which are shown above (refer to Figure 2 and Figure 3). For the purpose of this comparison, we are going to compare the two designs by connecting them through overhead lines. The 1st design involves connecting two rows of 20 wind turbines and having a thicker conductor running from two connected rows to the substation. The 2nd design has each row connected straight up to the substation. There are 2 main differences: 1st design requires two types of wire (refer to Table 6 in the appendix) and three circuit breakers on each line that runs into the substation, and 2nd design requires only one type of wires (first row of Table 6 in the appendix) for all the connections, but four circuit breakers are required on each line that runs into the substation. We have decided to go with the 1st design because it is cheaper compared to the second design. The total construction cost for the 1st design is $4,073,913.56 with a total annualized cost of $381,862.54 (this includes the annualized cost of equipment, cost of unreliability, and annual energy loss). The 2nd design costs more to construct. The total construction cost is $4,174,311.977 with a total annualized cost of $399,009.23. It is evident from these numbers that the 1st design is cheaper to build. This is mainly because the 1st design requires shorter conductors which greatly reduces the construction cost. The 1st design requires approximately 22.6 km of conductors while the 2nd design requires approximately 25.75 km. Furthermore, the 1st design requires only three circuit breakers while the 2nd design requires four circuit breakers on each line that runs to the substation. Table 1 summarizes the cost comparison between the two designs. 1st design 2nd design Cost difference Total Construction Cost $4,073,913.56 $4,174,311.977 ($100,398.417) Annualized cost $198,582.72/year $202,385.42/year ($3,802.7) Cost of unreliability $6,568.38 /year $7,484.25 /year ($915.87) Annual energy loss $176,711.44/year $189,139.56/year ($12,428.12) Total annualized cost $381,862.54/year $399,009.23/year ($17,146.69) Table 1 Besides its cheaper overall cost, 1st design is more favorable because it is more reliable. As shown in Table 1, the cost of unreliability of the 1st design is $6,568.38 /year while the cost of unreliability of the 2nd design is $7,484.25 /year. Although having four circuit breakers may seem to be more reliable than just three, the length of conductors is a more important factor in this case. Having longer conductors translates to more occurrences of fault, and thus increasing the expected outage
  • 4. time. Having shorter conductors, however, is more reliable. The expected outage time (EOT) for the 1st design was calculated to be approximately 50.55 hours/year while the EOT for the 2nd design was calculated to be approximately 57.6 hours/year. Therefore, the 1st design is more reliable. Overhead vs underground We have analyzed two designs in the previous section and justified that the first design is by far the best option. In this section, we are comparing between overhead and underground implementations of the 1st design. Overhead Underground Difference Total Construction Cost $4,073,913.56 $16,236,483.391 ($12,162,569.83) Annualized cost $198,582.72/year $216,501.29/year ($17,918.57) Cost of unreliability $6,568.38 /year $5,254.70/year $1,313.68 Annual energy loss $176,711.44/year $176,711.44/year $0.00 Total Annualized cost $381,862.54/year $398,467.43/year ($16,605.03) Table 2 Table 2 above summarizes the total construction and annualized cost for overhead and underground implementations of the 1st design. The total construction cost of underground lines is significantly more expensive than overhead lines because underground conductors are more expensive. The price of an overhead conductor is $1.62/lb. while the price of an underground conductor is $8.46/lb. Furthermore, underground transmission lines require conduits. These conduits are $55/foot. These prices contribute to high cost of underground lines construction. The difference in annualized cost is mainly due to the lifetime of underground lines. The lifetime of underground conductors is 20 years while the lifetime of overhead conductors is 40 years. This means that underground lines will require more maintenance than overhead lines. In terms of cost of unreliability, underground lines are more reliable than overhead lines. According to Table 2 above, the cost difference in terms of unreliability is approximately $1,313.68. Even though underground lines are proven to be more reliable, the cost difference in terms of unreliability does not outweigh the difference in annualized cost which is approximately $17,918.57. Thus, it is cheaper to go with overhead lines implementation of the 1st design. Note: The detailed calculation of cost, reliability, and energy lost can be found in the appendix
  • 5. Reliability Process Reliability analysis is one of the significant parts because we have to make sure our project design are able to deal with unpredictable things occur and consider how much potential money would loss when the power output doesn’t achieve the ideal prediction. We have to know which model has the less annual reliability cost in order to choose the best transmission circuit design. In this process, we have to realize two parts. The first part is the value of the worst fault current occur in each of the models, and the second part is the money loss because of some fault current occur and normal power loss during the process of energy transmission. In the first part, we have to compare the largest fault current—line to ground fault in these three models. According to the cost sheet file, we know the per unit impedance of a transformer and a generator in the base 100 MVA apparent power. Therefore, in order to find the fault current, we have to convert all the per unit value into 31.579MVA (total power in one conductor line = 30MW and power factor = 0.95). Next, we find the total line resistance in each conductor by consulting the ACSR table. Finally, we can sum all the impedance and use the apparent power to calculate line to ground fault current. In the second case, we have to calculate and compare the annual unreliability cost of these three models. In this process, we have to find the cost by total fault current (permanent and temporary), the cost by permanent fault only. We have to find out the voltage drop, and power loss due to current transmission in order to calculate the annual value loss. Result: Fault Current Analysis 1st design overhead 2nd design overhead 1st design underground Line 1 720 A 720 A 720 A Line 2 720 A 720 A 720 A Line 3 2629 A 707 A 2629 A Line 4 2629 A 694 A 2629 A Table 3 As we didn’t do any changing in Line 1 and Line 2 which are the two upper Lines connect to the left and right of the substation, all the models supposed to receive at most 720A fault current in each line. In overhead implementation of the 1st design, we can see the way that we combine two lines will have to be considered some of the impedance in parallel circuit. We calculated the total impedance in this way will be less than the overhead implementations of the 2nd design, which all the conductors are lined to substation separately. Therefore, we expect the fault current of the 1st design to be larger than the 2nd design and we estimate the fault current in 1st design to be four times higher than 2nd design. For underground implementations of the 1st design, although we change all the conductors in the 1st design from overhead into underground, we use the same length and size of aluminum to make the conductor. Hence, the fault current is the same as the 1st design.
  • 6. Unreliability Loss Total energy loss (MWh/year) Total energy loss due to permanent fault (MWh/year) Voltage Drop (V) Power Loss (MW) 1st design overhead 1501 375 6227 1.15 2nd design overhead 1710 427.7 7373 1.23 1st design underground 300 300 6227 1.15 Table 4 Cost of Unreliability Total fault ($/year) Permanent fault ($/year) Annual Value Loss ($k/year) 1st design overhead 8.758 6,568.38 176.7 2nd design overhead 9.937 7,484.25 189.1 1st design underground 1.752 5,254.70 176.7 Table 5 According to Table 4, the total energy loss in overhead implementations of 1st and 2nd design is five times larger than the underground implementation of the 1st design. The reason is there are no temporary fault current occur in underground. Thus, we decided to build circuit breakers in each of the conductors. As the circuit breakers are able to deal with the temporary fault current in a very short period (around 1 minute), temporary fault current doesn’t seem affect the whole system operation seriously. Thus, we can just compare the cost by permanent fault only. According to Table 4, we can see that the way that combine line 3 and line 4 are able to reduce the power by fault and the power loss during the normal operation as well. Also, the voltage drop of the 1st design is lower than the 2nd design. Afterward, when we estimate the cost of these power loss, we conclude that although the fault current will increase if we combine line 3 and line 4, we still can save some money for the unreliability cost by fault current. Moreover, we can save more than $10,000 in power loss during the normal operation. Finally, underground implementation seems have better reliability, yet the difference in cost of unreliability does not seem to outweigh the difference in annualized cost of the two designs. Standards Impact of Global Warming on our Design Conclusion
  • 7. Appendix Conductor type Weight (lbs/mile) Current Carrying Capacity (A) 336400 cmils ACSR 2442 530 954000 cmils ACSR 6479 1010 Table 6 Ro w Dis tan ce No. of pol es and ins ulat or Cost of poles and insulato r A of poles and insulat or XFMR cost A of a XFMR Price of condu ctor per lb Conductor cost for a single turbine A of a conducto r Connection Cost for a single turbine Total A 1 & 4 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 1 13 $32,808 $1,419 $37,500 $1,913 $1.62 $7,417.575 $320.902 $77,725.975 $3,653.49 Total cost for 3 phase $943,084.68 $46,617.75 2 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
  • 8. 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 3.2 41 $103,74 9 $4,488 $37,500 $1,913 $1.62 $23,456.432 $1,014.7 81 $164,705.702 $7,416.44 Total cost for 3 phase $1,030,064.4 1 $50,380.70 3 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 2.2 29 $73,362 $3,174 $37,500 $1,913 $1.62 $16,586.202 $717.559 $127,448.015 $5,804.59 Total cost for 3 phase $992,806.72 $48,768.84 Table 7 Overhead 1st Design Cost Calculation
  • 9. Ro w Dis tan ce No. of pol es and ins ulat or Cost of poles and insulato r A of poles and insulat or XFMR cost A of a XFMR Price of condu ctor per lb Conductor cost for a turbine A of a conductor Connection Cost for a turbine Total A 1 & 4 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 1 13 $32,808 $1,419 $37,500 $1,913 $1.62 $7,417.575 $320.902 $77,725.975 $3,653.49 Total cost for 3 phase $943,084.68 $46,617.75 2 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28
  • 10. 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 3.1 623 41 $103,74 9 $4,488 $37,500 $1,913 $1.62 $23,456.432 $1,014.781 $164,705.702 $7,416.44 Total cost for 3 phase $1,030,064.41 $50,380.70 3 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 0.2 3 $6,562 $284 $37,500 $1,913 $1.62 $1,483.515 $64.180 $45,545.195 $2,261.28 5.3 852 71 $176,67 9 $7,644 $37,500 $1,913 $1.62 $39,944.864 $1,728.110 $254,123.505 $11,284.87 Total cost for 3 phase $1,119,482.21 $54,249.12 Table 8 Overhead 2nd Design Cost Calculation
  • 11. Row Distance XFMR cost A of a XMFR Price of conductor per lb Conductor cost for a turbine A of conductor Cost of conduits and ditching per km Connection Cost for a turbine Total A 1&4 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 1 $37,500 $1,913 $8.46 $38,736.225 $2,603.683 $180,446.200 $617,574.83 $4,516.90 Total cost for 3 phase $3,534,359.160 $50,762.12 2 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96
  • 12. 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 3.2 $37,500 $1,913 $8.46 $122,494.699 $8,233.568 $180,446.200 $1,871,857.66 $10,146.79 Total cost for 3 phase $4,788,641.995 $56,392.01 3 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 0.2 $37,500 $1,913 $8.46 $7,747.245 $520.737 $180,446.200 $153,514.97 $2,433.96 2.2 $37,500 $1,913 $8.46 $86,616.832 $5,822.012 $180,446.200 $1,334,586.74 $7,735.23 Total cost for 3 phase $4,251,371.076 $53,980.45 Table 9 Underground 1st Design cost calculation
  • 13. overhead (permanent fault) length(m) length(mile) EF (faults/year) EOT (hours/year) Production lost (MWh/year) Line 1 4800 2.9825808 1.78954848 2.68432272 26.57479493 Line 2 4800 2.9825808 1.78954848 2.68432272 26.57479493 Lines 3 & 4 (2lines together) 9836 6.111805156 3.667083094 5.50062464 54.45618394 Lines 3 & 4 to sub 3162 1.964775102 1.178865061 1.768297592 17.50614616 Total production lost (MWh/year) 375.3357599 cost of unreliability $6,568.38 Table 10 Overhead 1st Design Cost of unreliability calculation overhead (permanent fault) length(m) length(mile) EF(faults/year) EOT(hours/year) Production Lost (MWh/year) Line 1 4800 2.9825808 1.78954848 2.68432272 26.57479493 Line 2 4800 2.9825808 1.78954848 2.68432272 26.57479493 Lines 3 & 4 (2lines together) 6963 4.326606273 2.595963764 3.893945646 38.55006189 Lines 3 & 4 to sub 9186 5.707914006 3.424748404 5.137122605 50.85751379 Total Production lost (MWh/year) 427.6714966 cost of unreliability $7,484.25 Table 11 Overhead 2ND Design Cost of unreliability calculation Underground (permanent fault) length(m) length(mile) EF(faults/year) EOT(hours/year) Production lost(MWh/year) Line 1 4800 2.9825808 0.178954848 2.147458176 21.25983594 Line 2 4800 2.9825808 0.178954848 2.147458176 21.25983594 Lines 3 & 4 (2lines together) 9836 6.111805156 0.366708309 4.400499712 43.56494715 Lines 3 & 4 to substation 3162 1.964775102 0.117886506 1.414638073 14.00491693 Total production lost(MWh/year) 300.2686079 cost of unreliability $5,254.70 Table 12 Underground 1st Design Cost of unreliability calculation