SlideShare a Scribd company logo
1 of 6
Download to read offline
Nwankwojike, B. Nduka Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 4, Issue 12( Part 6), December 2014, pp.91-96
www.ijera.com 91|P a g e
Optimal Duration of Submersible Pump Equipped Deep Water
Borehole Project in Ikwuano, Nigeria
Nwankwojike, B. Nduka
Department of Mechanical Engineering, Michael Okpara University of Agriculture, Umudike. Nigeria
Abstract
Optimal duration for constructing a submersible pump equipped deep water borehole in Ikwuano and optimal
durations of distinct jobs in this project were determined to aid effective planning and implementation of
borehole projects in this area. The investigation was conducted and analyzed using network modeling
procedure. Results revealed 13days as the optimal duration of the borehole project when construction of
overhead water distribution tank stantion constitutes part of the contract and 12days when the overhead structure
is not involved. The optimal duration in hours for the distinct jobs involved in this borehole construction include
25.92 for site preparation/mobilization of geophysical survey team, 36 for geophysical analysis/selection of the
best water yielding point in the site, 72 for mobilizing labour and materials to the selected site, 168 for
constructing overhead water distribution tank stantion, 3.12 for placement of overhead tank(s) on its
stantion/installation of its water conveying pipes/accessories, 4.56 for casing/gravel packing/flushing materials
preparation, 19.44 for well drilling, 1.92 for casing, 1.92 for gravel packing, 1.2 for flushing, 25.92 for water
collection/analysis, 1.2 for water treatment, 13.44 for pumping test, 25.92 for platforming, 77.04 for pump
installation/integration of water conveying systems, 4.8 for test running and 0.96 for training end users/project
commission. Thus, a guide for effective planning to ensure adequate and timely implementation of deep
borehole water supply projects in Ikwuano is set.
Key Words: Construction, deep borehole, network modeling, optimal duration, planning, portable water
I. INTRODUCTION
Borehole water supply scheme have become a
frequent means of providing portable water in
Nigerian cities, city peripheries as well as rural areas
because its water does not require intensive
treatment before use [1]. In addition, the scheme is
best for optimal fulfillment of water required by
single populated residences, small group of sparsely
populated residences, schools and factories
because its initial and maintenance
costs/technology are within an average man’s budget
[1]. Borehole is the prevailing means of providing
portable water in Ikwuano Local Government Area
of Abia State, Nigeria, which hosts two federal
agricultural research based institutions; Michael
Okpara University of Agriculture, Umudike
(MOUAU) and National Root Crops Research
Institute, Umudike (NRCRI). Hence the
heterogeneous populace of this area comprising civil
servants, traders, indigenous peasant farmers,
artisans and ever increasing student’s population.
Ikwuano has an average flat topography of less than
140m above the sea level and adequate underground
clean water resources due to the presence of
watershed between Cross River and Kwa-Ibo River
basins in this area [2]. Thus, governments,
philanthropic individuals and non-governmental
organizations are taking advantage of this natural
gift of underground water deposit in their effort to
achieve millennium goal of water for all by
constructing boreholes for inhabitants of various
communities in this area. However, the achievement
of this millennium goal in Ikwuano may not be
possible as expected soon because most of
government funded boreholes constructed in this
area are either unproductive or suffer pump failure
while a good number of them were abandoned
without completion due to inadequate funding.
The major cause of this ugly phenomenon is
that some corrupt contractors are conspiring with
corrupt government officials to induce unnecessary
delay in implementing borehole projects awarded in
this area to enable them secure upward review
(increment) of the project costs with claim that costs
of materials and engineering services increases
significantly over the implementation period.
Consequences of this short practice in Ikwuano
borehole projects implementation include
abandonment of projects when additional fund
demanded is not readily approved/available and
hesitation for quick completion of the project earlier
than minimum possible duration especially when
commissioning date (the contractor must not fail) is
at hand. This hesitation also paves way for two most
costly technical faults/short practices in water
borehole development. The faults include improper
pump installation and non-drilling to the appropriate
depth required of a deep borehole, thereby providing
RESEARCH ARTICLE OPEN ACCESS
Nwankwojike, B. Nduka Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 4, Issue 12( Part 6), December 2014, pp.91-96
www.ijera.com 92|P a g e
shallow boreholes in place of deep ones. This is why
many boreholes funded by government in this area
are characterized with frequent failure/high
maintenance of water pumping systems and their
productivity drops in the dry season and with age.
Recall that shallow borehole is not reliable source of
water for all seasons because it draws water from the
earth uppermost pervious layer unlike deep ones that
gets its water from water bearing strata lying below
the earth impervious stratum [3], [4] and [5].
The direct economic effect of this corruption in
borehole project implementation in Ikwuano is that
fund that should have been enough for more projects
are presently used for few, thereby hindering quick
and equitable distribution of potable water to
communities in Ikwuano as anticipated. Hence, the
high cost of portable water in this area which is very
obvious in the average cost of ten naira (N10) for
twenty (20) litres of water while the same quantity
of water costs five naira (N5) in other areas of Niger
Delta and Eastern Nigeria. This is why low income
earners in Ikwuano still resort to the use of nearby
unimproved water sources such as streams and
rivers, thereby increasing health hazard in this area.
It is therefore of economic sense to establish optimal
durations of specific tasks involved in deep borehole
construction and of the entire project to serve as a
guide/model for effective project planning,
monitoring and evaluation in Ikwuano.
In a case like this where specific information
on earliest and latest start or finish dates of project
activities, activity floats, optimal duration and
critical jobs that need close monitoring are required
for successful projects planning and execution,
network modeling/analysis lends itself [6] and [7].
Network Analysis is a generic name of two major
practices, critical path method (CPM) and
programme evaluation and review technique
(PERT). CPM is deterministic and does not account
for uncertainties involved in a job (or activity) time
estimate while PERT, as a probabilistic model takes
care of this shortcoming of CPM. Hence, both are
usually applied to improve efficiency of project
execution within predetermined time and cost [7]
and [8]. Application of these techniques is most
appropriate for planning and execution of large
time/fund-bound projects which involve careful
coordination of complex and interrelated activities
and resources such as assembly works, installation,
maintenance and phasing out of facilities/plants,
research and developments, logistic management,
marketing, construction of building, estates,
factories, roads, ships, airplanes and water scheme
[8] and [9].
Application of network modeling in predicting
borehole water supply project duration is not new in
this nation. Ekwe [10], applied this technique in
predicting optimal cost and duration of UNICEF
assisted borehole projects in Enugu state. This
prediction is not adequately applicable in Ikwuano
because the network model developed/used in the
forecast is not specific to the borehole types.
Anosike [11], also predicted optimal duration of
hand pump equipped deep borehole project in Abia
State as 20-21 days using network techniques, but
this type of borehole has been phased out with
submersible pump equipped ones due to drudgery
involved in its operation. Hence, the objective of this
study is to determine the optimal duration of
submersible pump equipped deep water borehole
project in Ikwuano for effective planning and
implementation.
II. METHODOLOGY
The distinct jobs (activities) involved in the
construction of submersible pump equipped deep
borehole in Ikwuano and the activities precedence
order were determined from the experimental study
of thirty different functional deep boreholes
constructed in this community within the period of
this investigation (July, 2010 to June, 2013). The
optimistic (to), most likely (tm) and pessimistic (tp)
durations (multiple time estimates) of the activities
were determined by measuring the time used for
executing each of the tasks in all the thirty projects
investigated. The shortest and longest time used for
completing each job among the projects studied
were respectively taken as the optimistic and
pessimistic durations of the distinct job concerned
while the figure with the highest frequency in the
collated data as per each job was taken as the most
likely duration. The expected (optimal) duration, te
for each job was computed from the measured
multiple durations using Equation (1).
6
4 pmo
e
ttt
t

 (1)
Thereafter, the network model of submersible pump
equipped deep water borehole supply in Ikwuano
was developed and analyzed. In accordance with [8],
activities with zero slacks and floats were identified
from the model as critical activities while the total
duration of the critical activities constitutes the
optimal duration of the project since activity
crashing is not allowed in order to ensure adequate
accuracy in the execution of each job. The slack (SL)
and total float (TF) associated with each job/network
path were determined from the following relations
[8];
EFLFSL  (2)
etESLFTF  (3)
Where the earliest start dates (ES) for each of the
jobs were determined by adding up activities
durations successively from the beginning to end
nodes of the network, using the highest value for
Nwankwojike, B. Nduka Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 4, Issue 12( Part 6), December 2014, pp.91-96
www.ijera.com 93|P a g e
nodes with more than one possible dates, while the
jobs latest finish dates (LF) were obtained by
subtracting the activities durations successively from
the end of the network, where there were more than
one possible values, the lowest one was taken in
accordance with [8] and [9]. EF constitutes the
earliest finish date of each job.
III. RESULTS AND DISCUSSION
The identified distinct jobs involved in the
execution of submersible pump equipped deep water
borehole project in Ikwuano and their order of
precedence are presented in Table 1 while Table 2
shows the measured multiple time analysis for the
jobs. The optimal duration of this borehole project
was revealed as 12.95 days (≈13 days) from the
model analysis shown in Figures 1 and Table 3. This
Table revealed activities A, B, C, D, E, P and Q as
critical jobs while G, H, I, J, M, N and O are sub-
critical ones. Further analysis of the model shown in
Figure 2 revealed that the sub-critical jobs becomes
critical when construction of overhead water
distribution tank stantion is not part of the contract
(either not required or has been provided for). Figure
2 also revealed 11.69 days (≈12 days) as the optimal
deep borehole project duration in Ikwuano when
construction of overhead water distribution tank
stantion is not involved. The use of overhead water
distribution plastic tank was considered as an
optimal resource for this water scheme in Ikwuano
because it is not a corrosion prone object unlike
metallic tank that corrodes with age.
Table 1: Work Breakdown Structure of Deep Water Borehole Construction Project in Ikwuano
S/No Job Description Activity Symbol Preceding Activity
1 Site Preparation/Mobilization of geophysical survey team A -
2 Geophysical analysis/selection of the best water yielding point in
the site for well development
B A
3 Mobilization of labour and materials for well development, pump
installation and construction of overhead water distribution tank
stantion
C B
4 Construction of Overhead water distribution tank stantion D C
5 Placement of overhead plastic tank (s) on its stantion and
installation of its water conveying pipes/accessories
E D
6 Preparation of materials for casing, gravel packing and flushing F C
7 Well drilling G C
8 Casing H F, G
9 Gravel packing I H
10 Flushing J I
11 Collection and analysis of water samples from the well K J
12 Water treatment L K
13 Pumping test M J
14 Construction of pump platform N M
15 Pump installation and integration of all water
conveying/distribution systems
O N
16 Test running of the project P E, O
17 Training of the end users/ project commission Q L, P
Nwankwojike, B. Nduka Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 4, Issue 12( Part 6), December 2014, pp.91-96
www.ijera.com 94|P a g e
Table 2: Multiple Time Analysis of Distinct Jobs in Ikwuano Deep Water Borehole Project
Activity Duration (Days) Variance
Optimistic Most Likely Pessimistic Expected
A 0.50 1.00 2.00 1.08 0.25
B 1.00 1.50 2.00 1.50 0.17
C 2.00 3.00 4.00 3.00 0.33
D 5.00 7.00 9.00 7.00 0.67
E 0.08 0.13 0.17 0.13 0.02
F 0.12 0.17 0.33 0.19 0.04
G 0.33 0.50 2.50 0.81 0.36
H 0.04 0.08 0.13 0.08 0.02
I 0.04 0.08 0.13 0.08 0.02
J 0.03 0.04 0.08 0.05 0.01
K 0.50 1.00 2.00 1.08 0.25
L 0.01 0.02 0.21 0.05 0.03
M 0.33 0.50 1.00 0.56 0.11
N 0.50 1.00 2.00 1.08 0.25
O 2.25 3.00 5.00 3.21 0.46
P 0.02 0.04 1.00 0.20 0.16
Q 0.02 0.04 0.08 0.04 0.01
Figure 1: Network Model of Deep Water Borehole Project in Ikwuano (with overhead tank stantion)
Nwankwojike, B. Nduka Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 4, Issue 12( Part 6), December 2014, pp.91-96
www.ijera.com 95|P a g e
Figure 2: Network Model of Deep Water Borehole Project in Ikwuano (without the Overhead Structure)
Table 3: Analysis of Network Model of Deep Water Borehole Construction Project in Ikwuano
IV. CONCLUSION
The optimal duration for constructing
submersible pump equipped deep water borehole
with overhead water distribution tank stantion in
Ikwuano is 13days while 12days is required when
the overhead structure is not involved. The optimal
duration in hours for the distinct jobs involved in
this borehole project include 25.92 for site
preparation/geophysical survey team mobilization,
36 for geophysical analysis/selection of the best
water yielding point in the site, 72 for the mobilizing
labour and materials to the selected site, 168 for
constructing overhead water distribution tank
stantion, 3.12 for placing overhead plastic tank (s)
on its stantion/installation of its water conveying
pipes/accessories, 4.56 for casing/gravel packing/
Activity Duration
(Day)
Earliest Date
(Day)
Latest Date
(Day)
Slack
(Day)
Total Float
(Day)
Critical Jobs
Start Finish Start Finish
A 1.08 0.00 1.08 0.00 1.08 0.00 0.00 Critical
B 1.50 1.08 2.58 1.08 2.58 0.00 0.00 Critical
C 3.00 2.58 5.58 2.58 5.58 0.00 0.00 Critical
D 7.00 5.58 12.58 5.58 12.58 0.00 0.00 Critical
E 0.13 12.58 12.71 12.58 12.71 0.00 0.00 Critical
F 0.19 5.58 5.77 5.58 7.65 1.88 1.88 -
G 0.81 5.58 6.39 5.58 7.65 1.26 1.26 Sub-critical
H 0.08 6.39 6.47 7.65 7.73 1.26 1.26 Sub-critical
I 0.08 6.47 6.55 7.73 7.81 1.26 1.26 Sub-critical
J 0.05 6.55 6.60 7.81 7.86 1.26 1.26 Sub-critical
K 1.08 6.60 7.68 7.86 12.86 5.18 5.18 -
L 0.05 7.68 7.73 12.86 12.91 5.18 5.18 -
M 0.56 6.60 7.16 7.86 8.24 1.26 1.26 Sub-critical
N 1.08 7.16 8.24 8.24 9.50 1.26 1.26 Sub-critical
O 3.21 8.24 11.45 9.50 12.71 1.26 1.26 Sub-critical
P 0.20 12.71 12.91 12.71 12.91 0.00 0.00 Critical
Q 0.04 12.91 12.95 12.91 12.95 0.00 0.00 Critical
Nwankwojike, B. Nduka Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 4, Issue 12( Part 6), December 2014, pp.91-96
www.ijera.com 96|P a g e
flushing materials preparation, 19.44 for well
drilling, 1.92 for casing, 1.92 for gravel packing, 1.2
for flushing, 25.92 for water collection/analysis, 1.2
for water treatment, 13.44 for pumping test, 25.92
for platforming, 77.04 for pump
installation/integration of water conveying systems,
4.8 for test running and 0.96 for training end
users/project commission. The results of this
investigation are therefore recommended as a
model/guide for effective planning and execution of
deep borehole water supply scheme in Ikwuano to
ensure adequate and timely project execution.
REFERENCES
[1.] Agunwamba J. C. (1995), Rural Water Supply,
Successes and Failures. In E. C. Eboh, C. U.
Okoye and D. Ayichi edited Rural Development
in Nigeria. Concepts, Processes and Prospects.
Auto-century Publishing Company Limited,
Enugu Nigeria. pp. 103 -188.
[2.] Onwughara, I. J. (2010) Design and
Optimization of Water Treatment and
Distribution Scheme for Michael Okpara
University of Agriculture Umudike Campus”,
B. Eng. Degree Project, Department of
Mechanical Engineering, Michael Okpara
University of Agriculture, Umudike, 2010.
[3.] Singh G. and Singh J. (2003), Water Supply and
Sanitary Engineering. Standard Publisher
Distributors Naisarak Delhi.
[4.] Bell F.G. and Hamill L. (2004), Ground Water
Resources Development. British Library
Cataloguing Publications, London.
[5.] Arora K.R. (2005), Irrigation, Water Power
and Water Resources. Standard Publishers
Distributors, Naisark Delhi.
[6.] Imaga E. U. L. (2003). Theory and Practice of
Production and Operations Management.
Rhyce Kerex Publishers, Enugu, Nigeria, pp.
321-342,
[7.] Cheema D.S (2006), Operation Research.
Laxmi Publications (N) Ltd, Daryganj New
Delhi
[8.] Kapoor, V. K. (1993). Problems and Solutions
in Operation Research. 2nd
Revised Edition,
Sultan Chand and Sons, New Delhi, pp. 667-
746.
[9.] Benjamin, S. B. (2008). Logistics Engineering
and Management. 6th
Edition, Prentice-Hall of
India Private Limited, New Delhi, pp. 372-
431, 2008.
[10.] Ekwe, L. O. (2002) Application of
Optimization Technique in Borehole Water
Project (A Case Study of UNICEF Assisted
Borehole Water Projects in Enugu State). MBA
Degree Project, Department of Project
Management Technology. Federal University of
Technology, Owerri.
[11.] Anosike, M. (2008) Application of
Optimization Technique in Borehole Water
Supply Projects (A Case Study of Federal
Department of Rural Development Borehole
Projects in Abia State). B. Eng. Degree Project,
Department of Civil Engineering, Michael
Okpara University of Agriculture, Umudike.

More Related Content

What's hot

C5 council workshop 111128_final
C5 council workshop 111128_finalC5 council workshop 111128_final
C5 council workshop 111128_finalpublicinvolvement
 
IRJET- Train Impact Analysis on Prestressed Concrete Girder
IRJET- Train Impact Analysis on Prestressed Concrete GirderIRJET- Train Impact Analysis on Prestressed Concrete Girder
IRJET- Train Impact Analysis on Prestressed Concrete GirderIRJET Journal
 
LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1Theodore McNeal
 
March 9, 2011 City Council Workshop
March 9, 2011 City Council WorkshopMarch 9, 2011 City Council Workshop
March 9, 2011 City Council Workshoppublicinvolvement
 
Undertaking Modelling of Flooding due to Wave Overtopping using the MIKE by D...
Undertaking Modelling of Flooding due to Wave Overtopping using the MIKE by D...Undertaking Modelling of Flooding due to Wave Overtopping using the MIKE by D...
Undertaking Modelling of Flooding due to Wave Overtopping using the MIKE by D...Stephen Flood
 
Underground Wet Ponds for Stormwater Management in Wisconsin
Underground Wet Ponds for Stormwater Management in WisconsinUnderground Wet Ponds for Stormwater Management in Wisconsin
Underground Wet Ponds for Stormwater Management in WisconsinContech Engineered Solutions
 
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...Stephen Flood
 
MASEFinalReport (2)
MASEFinalReport (2)MASEFinalReport (2)
MASEFinalReport (2)Sunil Satish
 
Teaching and research with MIKE by DHI - Dr Björn Elsäßer (Queen’s University...
Teaching and research with MIKE by DHI - Dr Björn Elsäßer (Queen’s University...Teaching and research with MIKE by DHI - Dr Björn Elsäßer (Queen’s University...
Teaching and research with MIKE by DHI - Dr Björn Elsäßer (Queen’s University...Stephen Flood
 
PLANNING AND DESIGN OF PIPE DISTRIBUTION NETWORK (PDN).
PLANNING AND DESIGN OF PIPE DISTRIBUTION NETWORK (PDN).PLANNING AND DESIGN OF PIPE DISTRIBUTION NETWORK (PDN).
PLANNING AND DESIGN OF PIPE DISTRIBUTION NETWORK (PDN).Yatiraj Battul
 
Guidelines For Construction of Pipe Distribution Network (PDN) For Irrigation
Guidelines For Construction of Pipe Distribution Network (PDN) For IrrigationGuidelines For Construction of Pipe Distribution Network (PDN) For Irrigation
Guidelines For Construction of Pipe Distribution Network (PDN) For IrrigationIRJET Journal
 
Breach Brief Feb 2018, NWRR Symposium
Breach Brief Feb 2018, NWRR SymposiumBreach Brief Feb 2018, NWRR Symposium
Breach Brief Feb 2018, NWRR SymposiumJimWaddell4
 
water harvesting syatem
water harvesting syatemwater harvesting syatem
water harvesting syatemManish Singh
 
Oscillating water column and government regulation of ocean
Oscillating water column and government regulation of oceanOscillating water column and government regulation of ocean
Oscillating water column and government regulation of oceanArjun Puthusseri
 
2014 MIKE by DHI UK Symposium Flyer
2014 MIKE by DHI UK Symposium Flyer2014 MIKE by DHI UK Symposium Flyer
2014 MIKE by DHI UK Symposium FlyerStephen Flood
 
Final project for haydroulic engginering
Final project for haydroulic enggineringFinal project for haydroulic engginering
Final project for haydroulic enggineringkindu melese
 
ICE Flooding 2013 - MIKE by DHI Delegate Pack
ICE Flooding 2013 - MIKE by DHI Delegate PackICE Flooding 2013 - MIKE by DHI Delegate Pack
ICE Flooding 2013 - MIKE by DHI Delegate PackStephen Flood
 
Multifunctional Stormwater Projects - An Innovative Technical Design and Part...
Multifunctional Stormwater Projects - An Innovative Technical Design and Part...Multifunctional Stormwater Projects - An Innovative Technical Design and Part...
Multifunctional Stormwater Projects - An Innovative Technical Design and Part...Adam Berry
 

What's hot (20)

C5 council workshop 111128_final
C5 council workshop 111128_finalC5 council workshop 111128_final
C5 council workshop 111128_final
 
IRJET- Train Impact Analysis on Prestressed Concrete Girder
IRJET- Train Impact Analysis on Prestressed Concrete GirderIRJET- Train Impact Analysis on Prestressed Concrete Girder
IRJET- Train Impact Analysis on Prestressed Concrete Girder
 
LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1
 
March 9, 2011 City Council Workshop
March 9, 2011 City Council WorkshopMarch 9, 2011 City Council Workshop
March 9, 2011 City Council Workshop
 
Undertaking Modelling of Flooding due to Wave Overtopping using the MIKE by D...
Undertaking Modelling of Flooding due to Wave Overtopping using the MIKE by D...Undertaking Modelling of Flooding due to Wave Overtopping using the MIKE by D...
Undertaking Modelling of Flooding due to Wave Overtopping using the MIKE by D...
 
Underground Wet Ponds for Stormwater Management in Wisconsin
Underground Wet Ponds for Stormwater Management in WisconsinUnderground Wet Ponds for Stormwater Management in Wisconsin
Underground Wet Ponds for Stormwater Management in Wisconsin
 
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
 
MASEFinalReport (2)
MASEFinalReport (2)MASEFinalReport (2)
MASEFinalReport (2)
 
Saleh_Abdulrahman_Cv
Saleh_Abdulrahman_CvSaleh_Abdulrahman_Cv
Saleh_Abdulrahman_Cv
 
Teaching and research with MIKE by DHI - Dr Björn Elsäßer (Queen’s University...
Teaching and research with MIKE by DHI - Dr Björn Elsäßer (Queen’s University...Teaching and research with MIKE by DHI - Dr Björn Elsäßer (Queen’s University...
Teaching and research with MIKE by DHI - Dr Björn Elsäßer (Queen’s University...
 
INIO2014 Presentation
INIO2014 PresentationINIO2014 Presentation
INIO2014 Presentation
 
PLANNING AND DESIGN OF PIPE DISTRIBUTION NETWORK (PDN).
PLANNING AND DESIGN OF PIPE DISTRIBUTION NETWORK (PDN).PLANNING AND DESIGN OF PIPE DISTRIBUTION NETWORK (PDN).
PLANNING AND DESIGN OF PIPE DISTRIBUTION NETWORK (PDN).
 
Guidelines For Construction of Pipe Distribution Network (PDN) For Irrigation
Guidelines For Construction of Pipe Distribution Network (PDN) For IrrigationGuidelines For Construction of Pipe Distribution Network (PDN) For Irrigation
Guidelines For Construction of Pipe Distribution Network (PDN) For Irrigation
 
Breach Brief Feb 2018, NWRR Symposium
Breach Brief Feb 2018, NWRR SymposiumBreach Brief Feb 2018, NWRR Symposium
Breach Brief Feb 2018, NWRR Symposium
 
water harvesting syatem
water harvesting syatemwater harvesting syatem
water harvesting syatem
 
Oscillating water column and government regulation of ocean
Oscillating water column and government regulation of oceanOscillating water column and government regulation of ocean
Oscillating water column and government regulation of ocean
 
2014 MIKE by DHI UK Symposium Flyer
2014 MIKE by DHI UK Symposium Flyer2014 MIKE by DHI UK Symposium Flyer
2014 MIKE by DHI UK Symposium Flyer
 
Final project for haydroulic engginering
Final project for haydroulic enggineringFinal project for haydroulic engginering
Final project for haydroulic engginering
 
ICE Flooding 2013 - MIKE by DHI Delegate Pack
ICE Flooding 2013 - MIKE by DHI Delegate PackICE Flooding 2013 - MIKE by DHI Delegate Pack
ICE Flooding 2013 - MIKE by DHI Delegate Pack
 
Multifunctional Stormwater Projects - An Innovative Technical Design and Part...
Multifunctional Stormwater Projects - An Innovative Technical Design and Part...Multifunctional Stormwater Projects - An Innovative Technical Design and Part...
Multifunctional Stormwater Projects - An Innovative Technical Design and Part...
 

Viewers also liked

Trends in Wire Electrical Discharge Machining (WEDM): A Review
Trends in Wire Electrical Discharge Machining (WEDM): A ReviewTrends in Wire Electrical Discharge Machining (WEDM): A Review
Trends in Wire Electrical Discharge Machining (WEDM): A ReviewIJERA Editor
 
Anorthosite and Associated Rocks of Oddanchatram, Dindigul Anna District, Tam...
Anorthosite and Associated Rocks of Oddanchatram, Dindigul Anna District, Tam...Anorthosite and Associated Rocks of Oddanchatram, Dindigul Anna District, Tam...
Anorthosite and Associated Rocks of Oddanchatram, Dindigul Anna District, Tam...IJERA Editor
 
Generic conventions
Generic conventionsGeneric conventions
Generic conventionsHarry Wise
 
Hydrogeological Studies At Jalakandapuram Sub – Basin Of Sarabanga Minor Basi...
Hydrogeological Studies At Jalakandapuram Sub – Basin Of Sarabanga Minor Basi...Hydrogeological Studies At Jalakandapuram Sub – Basin Of Sarabanga Minor Basi...
Hydrogeological Studies At Jalakandapuram Sub – Basin Of Sarabanga Minor Basi...IJERA Editor
 
Альянсы для развития портфеля и бизнеса
Альянсы для развития портфеля и бизнесаАльянсы для развития портфеля и бизнеса
Альянсы для развития портфеля и бизнесаInfor-media
 
Modelling of The Properties of Sand Mould Made of Reclaimed Sand
Modelling of The Properties of Sand Mould Made of Reclaimed SandModelling of The Properties of Sand Mould Made of Reclaimed Sand
Modelling of The Properties of Sand Mould Made of Reclaimed SandIJERA Editor
 
Study and Analysis of K-Means Clustering Algorithm Using Rapidminer
Study and Analysis of K-Means Clustering Algorithm Using RapidminerStudy and Analysis of K-Means Clustering Algorithm Using Rapidminer
Study and Analysis of K-Means Clustering Algorithm Using RapidminerIJERA Editor
 
Assessment of sanitation levels of sources of water in Osun State Capital, Ni...
Assessment of sanitation levels of sources of water in Osun State Capital, Ni...Assessment of sanitation levels of sources of water in Osun State Capital, Ni...
Assessment of sanitation levels of sources of water in Osun State Capital, Ni...IJERA Editor
 
IIA Training (Beginning Auditor)
IIA Training (Beginning Auditor)IIA Training (Beginning Auditor)
IIA Training (Beginning Auditor)Victor Muto
 
195615892 personalitate-alfa-puterea-ta-interioara
195615892 personalitate-alfa-puterea-ta-interioara195615892 personalitate-alfa-puterea-ta-interioara
195615892 personalitate-alfa-puterea-ta-interioaraMihnevici Madalina
 
Designing instruction laying the foundation
Designing instruction laying the foundationDesigning instruction laying the foundation
Designing instruction laying the foundationKathleen Stone
 

Viewers also liked (14)

QS Al Baqarah 148
QS Al Baqarah 148QS Al Baqarah 148
QS Al Baqarah 148
 
Trends in Wire Electrical Discharge Machining (WEDM): A Review
Trends in Wire Electrical Discharge Machining (WEDM): A ReviewTrends in Wire Electrical Discharge Machining (WEDM): A Review
Trends in Wire Electrical Discharge Machining (WEDM): A Review
 
Anorthosite and Associated Rocks of Oddanchatram, Dindigul Anna District, Tam...
Anorthosite and Associated Rocks of Oddanchatram, Dindigul Anna District, Tam...Anorthosite and Associated Rocks of Oddanchatram, Dindigul Anna District, Tam...
Anorthosite and Associated Rocks of Oddanchatram, Dindigul Anna District, Tam...
 
белашов
белашовбелашов
белашов
 
Fais Credits 1
Fais Credits 1Fais Credits 1
Fais Credits 1
 
Generic conventions
Generic conventionsGeneric conventions
Generic conventions
 
Hydrogeological Studies At Jalakandapuram Sub – Basin Of Sarabanga Minor Basi...
Hydrogeological Studies At Jalakandapuram Sub – Basin Of Sarabanga Minor Basi...Hydrogeological Studies At Jalakandapuram Sub – Basin Of Sarabanga Minor Basi...
Hydrogeological Studies At Jalakandapuram Sub – Basin Of Sarabanga Minor Basi...
 
Альянсы для развития портфеля и бизнеса
Альянсы для развития портфеля и бизнесаАльянсы для развития портфеля и бизнеса
Альянсы для развития портфеля и бизнеса
 
Modelling of The Properties of Sand Mould Made of Reclaimed Sand
Modelling of The Properties of Sand Mould Made of Reclaimed SandModelling of The Properties of Sand Mould Made of Reclaimed Sand
Modelling of The Properties of Sand Mould Made of Reclaimed Sand
 
Study and Analysis of K-Means Clustering Algorithm Using Rapidminer
Study and Analysis of K-Means Clustering Algorithm Using RapidminerStudy and Analysis of K-Means Clustering Algorithm Using Rapidminer
Study and Analysis of K-Means Clustering Algorithm Using Rapidminer
 
Assessment of sanitation levels of sources of water in Osun State Capital, Ni...
Assessment of sanitation levels of sources of water in Osun State Capital, Ni...Assessment of sanitation levels of sources of water in Osun State Capital, Ni...
Assessment of sanitation levels of sources of water in Osun State Capital, Ni...
 
IIA Training (Beginning Auditor)
IIA Training (Beginning Auditor)IIA Training (Beginning Auditor)
IIA Training (Beginning Auditor)
 
195615892 personalitate-alfa-puterea-ta-interioara
195615892 personalitate-alfa-puterea-ta-interioara195615892 personalitate-alfa-puterea-ta-interioara
195615892 personalitate-alfa-puterea-ta-interioara
 
Designing instruction laying the foundation
Designing instruction laying the foundationDesigning instruction laying the foundation
Designing instruction laying the foundation
 

Similar to Optimal Duration of Submersible Pump Equipped Deep Water Borehole Project in Ikwuano, Nigeria

Internship Report
Internship ReportInternship Report
Internship ReportBala Murali
 
DSD-SEA 2018 Software Application in Integrated Water Resources Management in...
DSD-SEA 2018 Software Application in Integrated Water Resources Management in...DSD-SEA 2018 Software Application in Integrated Water Resources Management in...
DSD-SEA 2018 Software Application in Integrated Water Resources Management in...Deltares
 
Tc iv submited paper risk analysis and managements large epc projects
Tc iv submited paper risk analysis and managements  large epc projectsTc iv submited paper risk analysis and managements  large epc projects
Tc iv submited paper risk analysis and managements large epc projectsPALLA NARASIMHUDU
 
NESTLE ABAJI EIA PRESENTATION
NESTLE  ABAJI  EIA  PRESENTATIONNESTLE  ABAJI  EIA  PRESENTATION
NESTLE ABAJI EIA PRESENTATIONAdewunmi Okumodi
 
Pader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement ReportPader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement ReportFesto Wasukira
 
Dam Break Analysis of Peringalkuthu Dam, Thrissur Using HEC-RAS
Dam Break Analysis of Peringalkuthu Dam, Thrissur Using HEC-RASDam Break Analysis of Peringalkuthu Dam, Thrissur Using HEC-RAS
Dam Break Analysis of Peringalkuthu Dam, Thrissur Using HEC-RASIRJET Journal
 
Scheme for the construction of water channels
Scheme for the construction of water channelsScheme for the construction of water channels
Scheme for the construction of water channelsmirzaqadeer
 
Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Charles Abraham Scheck
 
I0313048051
I0313048051I0313048051
I0313048051theijes
 

Similar to Optimal Duration of Submersible Pump Equipped Deep Water Borehole Project in Ikwuano, Nigeria (20)

Cz32629632
Cz32629632Cz32629632
Cz32629632
 
Cz32629632
Cz32629632Cz32629632
Cz32629632
 
Ground water o&m_norms
Ground water o&m_normsGround water o&m_norms
Ground water o&m_norms
 
I1302024147
I1302024147I1302024147
I1302024147
 
road_map (1)
road_map (1)road_map (1)
road_map (1)
 
Internship Report
Internship ReportInternship Report
Internship Report
 
CV_Hazwan Updated
CV_Hazwan UpdatedCV_Hazwan Updated
CV_Hazwan Updated
 
Infusion of Standards in Water Drilling Rig Fabrication in Nigeria
Infusion of Standards in Water Drilling Rig Fabrication in NigeriaInfusion of Standards in Water Drilling Rig Fabrication in Nigeria
Infusion of Standards in Water Drilling Rig Fabrication in Nigeria
 
CV~PW~02-02-16 Opus
CV~PW~02-02-16 OpusCV~PW~02-02-16 Opus
CV~PW~02-02-16 Opus
 
DSD-SEA 2018 Software Application in Integrated Water Resources Management in...
DSD-SEA 2018 Software Application in Integrated Water Resources Management in...DSD-SEA 2018 Software Application in Integrated Water Resources Management in...
DSD-SEA 2018 Software Application in Integrated Water Resources Management in...
 
Tc iv submited paper risk analysis and managements large epc projects
Tc iv submited paper risk analysis and managements  large epc projectsTc iv submited paper risk analysis and managements  large epc projects
Tc iv submited paper risk analysis and managements large epc projects
 
Interface Consulting ltd projects
Interface Consulting ltd projectsInterface Consulting ltd projects
Interface Consulting ltd projects
 
NESTLE ABAJI EIA PRESENTATION
NESTLE  ABAJI  EIA  PRESENTATIONNESTLE  ABAJI  EIA  PRESENTATION
NESTLE ABAJI EIA PRESENTATION
 
Ugeshan Naidoo1
Ugeshan Naidoo1Ugeshan Naidoo1
Ugeshan Naidoo1
 
Pader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement ReportPader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement Report
 
Dam Break Analysis of Peringalkuthu Dam, Thrissur Using HEC-RAS
Dam Break Analysis of Peringalkuthu Dam, Thrissur Using HEC-RASDam Break Analysis of Peringalkuthu Dam, Thrissur Using HEC-RAS
Dam Break Analysis of Peringalkuthu Dam, Thrissur Using HEC-RAS
 
Scheme for the construction of water channels
Scheme for the construction of water channelsScheme for the construction of water channels
Scheme for the construction of water channels
 
Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...
 
I0313048051
I0313048051I0313048051
I0313048051
 
Philip Kachina CV
Philip Kachina CVPhilip Kachina CV
Philip Kachina CV
 

Recently uploaded

Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEarley Information Science
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Paola De la Torre
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...gurkirankumar98700
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 

Recently uploaded (20)

Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 

Optimal Duration of Submersible Pump Equipped Deep Water Borehole Project in Ikwuano, Nigeria

  • 1. Nwankwojike, B. Nduka Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 4, Issue 12( Part 6), December 2014, pp.91-96 www.ijera.com 91|P a g e Optimal Duration of Submersible Pump Equipped Deep Water Borehole Project in Ikwuano, Nigeria Nwankwojike, B. Nduka Department of Mechanical Engineering, Michael Okpara University of Agriculture, Umudike. Nigeria Abstract Optimal duration for constructing a submersible pump equipped deep water borehole in Ikwuano and optimal durations of distinct jobs in this project were determined to aid effective planning and implementation of borehole projects in this area. The investigation was conducted and analyzed using network modeling procedure. Results revealed 13days as the optimal duration of the borehole project when construction of overhead water distribution tank stantion constitutes part of the contract and 12days when the overhead structure is not involved. The optimal duration in hours for the distinct jobs involved in this borehole construction include 25.92 for site preparation/mobilization of geophysical survey team, 36 for geophysical analysis/selection of the best water yielding point in the site, 72 for mobilizing labour and materials to the selected site, 168 for constructing overhead water distribution tank stantion, 3.12 for placement of overhead tank(s) on its stantion/installation of its water conveying pipes/accessories, 4.56 for casing/gravel packing/flushing materials preparation, 19.44 for well drilling, 1.92 for casing, 1.92 for gravel packing, 1.2 for flushing, 25.92 for water collection/analysis, 1.2 for water treatment, 13.44 for pumping test, 25.92 for platforming, 77.04 for pump installation/integration of water conveying systems, 4.8 for test running and 0.96 for training end users/project commission. Thus, a guide for effective planning to ensure adequate and timely implementation of deep borehole water supply projects in Ikwuano is set. Key Words: Construction, deep borehole, network modeling, optimal duration, planning, portable water I. INTRODUCTION Borehole water supply scheme have become a frequent means of providing portable water in Nigerian cities, city peripheries as well as rural areas because its water does not require intensive treatment before use [1]. In addition, the scheme is best for optimal fulfillment of water required by single populated residences, small group of sparsely populated residences, schools and factories because its initial and maintenance costs/technology are within an average man’s budget [1]. Borehole is the prevailing means of providing portable water in Ikwuano Local Government Area of Abia State, Nigeria, which hosts two federal agricultural research based institutions; Michael Okpara University of Agriculture, Umudike (MOUAU) and National Root Crops Research Institute, Umudike (NRCRI). Hence the heterogeneous populace of this area comprising civil servants, traders, indigenous peasant farmers, artisans and ever increasing student’s population. Ikwuano has an average flat topography of less than 140m above the sea level and adequate underground clean water resources due to the presence of watershed between Cross River and Kwa-Ibo River basins in this area [2]. Thus, governments, philanthropic individuals and non-governmental organizations are taking advantage of this natural gift of underground water deposit in their effort to achieve millennium goal of water for all by constructing boreholes for inhabitants of various communities in this area. However, the achievement of this millennium goal in Ikwuano may not be possible as expected soon because most of government funded boreholes constructed in this area are either unproductive or suffer pump failure while a good number of them were abandoned without completion due to inadequate funding. The major cause of this ugly phenomenon is that some corrupt contractors are conspiring with corrupt government officials to induce unnecessary delay in implementing borehole projects awarded in this area to enable them secure upward review (increment) of the project costs with claim that costs of materials and engineering services increases significantly over the implementation period. Consequences of this short practice in Ikwuano borehole projects implementation include abandonment of projects when additional fund demanded is not readily approved/available and hesitation for quick completion of the project earlier than minimum possible duration especially when commissioning date (the contractor must not fail) is at hand. This hesitation also paves way for two most costly technical faults/short practices in water borehole development. The faults include improper pump installation and non-drilling to the appropriate depth required of a deep borehole, thereby providing RESEARCH ARTICLE OPEN ACCESS
  • 2. Nwankwojike, B. Nduka Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 4, Issue 12( Part 6), December 2014, pp.91-96 www.ijera.com 92|P a g e shallow boreholes in place of deep ones. This is why many boreholes funded by government in this area are characterized with frequent failure/high maintenance of water pumping systems and their productivity drops in the dry season and with age. Recall that shallow borehole is not reliable source of water for all seasons because it draws water from the earth uppermost pervious layer unlike deep ones that gets its water from water bearing strata lying below the earth impervious stratum [3], [4] and [5]. The direct economic effect of this corruption in borehole project implementation in Ikwuano is that fund that should have been enough for more projects are presently used for few, thereby hindering quick and equitable distribution of potable water to communities in Ikwuano as anticipated. Hence, the high cost of portable water in this area which is very obvious in the average cost of ten naira (N10) for twenty (20) litres of water while the same quantity of water costs five naira (N5) in other areas of Niger Delta and Eastern Nigeria. This is why low income earners in Ikwuano still resort to the use of nearby unimproved water sources such as streams and rivers, thereby increasing health hazard in this area. It is therefore of economic sense to establish optimal durations of specific tasks involved in deep borehole construction and of the entire project to serve as a guide/model for effective project planning, monitoring and evaluation in Ikwuano. In a case like this where specific information on earliest and latest start or finish dates of project activities, activity floats, optimal duration and critical jobs that need close monitoring are required for successful projects planning and execution, network modeling/analysis lends itself [6] and [7]. Network Analysis is a generic name of two major practices, critical path method (CPM) and programme evaluation and review technique (PERT). CPM is deterministic and does not account for uncertainties involved in a job (or activity) time estimate while PERT, as a probabilistic model takes care of this shortcoming of CPM. Hence, both are usually applied to improve efficiency of project execution within predetermined time and cost [7] and [8]. Application of these techniques is most appropriate for planning and execution of large time/fund-bound projects which involve careful coordination of complex and interrelated activities and resources such as assembly works, installation, maintenance and phasing out of facilities/plants, research and developments, logistic management, marketing, construction of building, estates, factories, roads, ships, airplanes and water scheme [8] and [9]. Application of network modeling in predicting borehole water supply project duration is not new in this nation. Ekwe [10], applied this technique in predicting optimal cost and duration of UNICEF assisted borehole projects in Enugu state. This prediction is not adequately applicable in Ikwuano because the network model developed/used in the forecast is not specific to the borehole types. Anosike [11], also predicted optimal duration of hand pump equipped deep borehole project in Abia State as 20-21 days using network techniques, but this type of borehole has been phased out with submersible pump equipped ones due to drudgery involved in its operation. Hence, the objective of this study is to determine the optimal duration of submersible pump equipped deep water borehole project in Ikwuano for effective planning and implementation. II. METHODOLOGY The distinct jobs (activities) involved in the construction of submersible pump equipped deep borehole in Ikwuano and the activities precedence order were determined from the experimental study of thirty different functional deep boreholes constructed in this community within the period of this investigation (July, 2010 to June, 2013). The optimistic (to), most likely (tm) and pessimistic (tp) durations (multiple time estimates) of the activities were determined by measuring the time used for executing each of the tasks in all the thirty projects investigated. The shortest and longest time used for completing each job among the projects studied were respectively taken as the optimistic and pessimistic durations of the distinct job concerned while the figure with the highest frequency in the collated data as per each job was taken as the most likely duration. The expected (optimal) duration, te for each job was computed from the measured multiple durations using Equation (1). 6 4 pmo e ttt t   (1) Thereafter, the network model of submersible pump equipped deep water borehole supply in Ikwuano was developed and analyzed. In accordance with [8], activities with zero slacks and floats were identified from the model as critical activities while the total duration of the critical activities constitutes the optimal duration of the project since activity crashing is not allowed in order to ensure adequate accuracy in the execution of each job. The slack (SL) and total float (TF) associated with each job/network path were determined from the following relations [8]; EFLFSL  (2) etESLFTF  (3) Where the earliest start dates (ES) for each of the jobs were determined by adding up activities durations successively from the beginning to end nodes of the network, using the highest value for
  • 3. Nwankwojike, B. Nduka Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 4, Issue 12( Part 6), December 2014, pp.91-96 www.ijera.com 93|P a g e nodes with more than one possible dates, while the jobs latest finish dates (LF) were obtained by subtracting the activities durations successively from the end of the network, where there were more than one possible values, the lowest one was taken in accordance with [8] and [9]. EF constitutes the earliest finish date of each job. III. RESULTS AND DISCUSSION The identified distinct jobs involved in the execution of submersible pump equipped deep water borehole project in Ikwuano and their order of precedence are presented in Table 1 while Table 2 shows the measured multiple time analysis for the jobs. The optimal duration of this borehole project was revealed as 12.95 days (≈13 days) from the model analysis shown in Figures 1 and Table 3. This Table revealed activities A, B, C, D, E, P and Q as critical jobs while G, H, I, J, M, N and O are sub- critical ones. Further analysis of the model shown in Figure 2 revealed that the sub-critical jobs becomes critical when construction of overhead water distribution tank stantion is not part of the contract (either not required or has been provided for). Figure 2 also revealed 11.69 days (≈12 days) as the optimal deep borehole project duration in Ikwuano when construction of overhead water distribution tank stantion is not involved. The use of overhead water distribution plastic tank was considered as an optimal resource for this water scheme in Ikwuano because it is not a corrosion prone object unlike metallic tank that corrodes with age. Table 1: Work Breakdown Structure of Deep Water Borehole Construction Project in Ikwuano S/No Job Description Activity Symbol Preceding Activity 1 Site Preparation/Mobilization of geophysical survey team A - 2 Geophysical analysis/selection of the best water yielding point in the site for well development B A 3 Mobilization of labour and materials for well development, pump installation and construction of overhead water distribution tank stantion C B 4 Construction of Overhead water distribution tank stantion D C 5 Placement of overhead plastic tank (s) on its stantion and installation of its water conveying pipes/accessories E D 6 Preparation of materials for casing, gravel packing and flushing F C 7 Well drilling G C 8 Casing H F, G 9 Gravel packing I H 10 Flushing J I 11 Collection and analysis of water samples from the well K J 12 Water treatment L K 13 Pumping test M J 14 Construction of pump platform N M 15 Pump installation and integration of all water conveying/distribution systems O N 16 Test running of the project P E, O 17 Training of the end users/ project commission Q L, P
  • 4. Nwankwojike, B. Nduka Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 4, Issue 12( Part 6), December 2014, pp.91-96 www.ijera.com 94|P a g e Table 2: Multiple Time Analysis of Distinct Jobs in Ikwuano Deep Water Borehole Project Activity Duration (Days) Variance Optimistic Most Likely Pessimistic Expected A 0.50 1.00 2.00 1.08 0.25 B 1.00 1.50 2.00 1.50 0.17 C 2.00 3.00 4.00 3.00 0.33 D 5.00 7.00 9.00 7.00 0.67 E 0.08 0.13 0.17 0.13 0.02 F 0.12 0.17 0.33 0.19 0.04 G 0.33 0.50 2.50 0.81 0.36 H 0.04 0.08 0.13 0.08 0.02 I 0.04 0.08 0.13 0.08 0.02 J 0.03 0.04 0.08 0.05 0.01 K 0.50 1.00 2.00 1.08 0.25 L 0.01 0.02 0.21 0.05 0.03 M 0.33 0.50 1.00 0.56 0.11 N 0.50 1.00 2.00 1.08 0.25 O 2.25 3.00 5.00 3.21 0.46 P 0.02 0.04 1.00 0.20 0.16 Q 0.02 0.04 0.08 0.04 0.01 Figure 1: Network Model of Deep Water Borehole Project in Ikwuano (with overhead tank stantion)
  • 5. Nwankwojike, B. Nduka Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 4, Issue 12( Part 6), December 2014, pp.91-96 www.ijera.com 95|P a g e Figure 2: Network Model of Deep Water Borehole Project in Ikwuano (without the Overhead Structure) Table 3: Analysis of Network Model of Deep Water Borehole Construction Project in Ikwuano IV. CONCLUSION The optimal duration for constructing submersible pump equipped deep water borehole with overhead water distribution tank stantion in Ikwuano is 13days while 12days is required when the overhead structure is not involved. The optimal duration in hours for the distinct jobs involved in this borehole project include 25.92 for site preparation/geophysical survey team mobilization, 36 for geophysical analysis/selection of the best water yielding point in the site, 72 for the mobilizing labour and materials to the selected site, 168 for constructing overhead water distribution tank stantion, 3.12 for placing overhead plastic tank (s) on its stantion/installation of its water conveying pipes/accessories, 4.56 for casing/gravel packing/ Activity Duration (Day) Earliest Date (Day) Latest Date (Day) Slack (Day) Total Float (Day) Critical Jobs Start Finish Start Finish A 1.08 0.00 1.08 0.00 1.08 0.00 0.00 Critical B 1.50 1.08 2.58 1.08 2.58 0.00 0.00 Critical C 3.00 2.58 5.58 2.58 5.58 0.00 0.00 Critical D 7.00 5.58 12.58 5.58 12.58 0.00 0.00 Critical E 0.13 12.58 12.71 12.58 12.71 0.00 0.00 Critical F 0.19 5.58 5.77 5.58 7.65 1.88 1.88 - G 0.81 5.58 6.39 5.58 7.65 1.26 1.26 Sub-critical H 0.08 6.39 6.47 7.65 7.73 1.26 1.26 Sub-critical I 0.08 6.47 6.55 7.73 7.81 1.26 1.26 Sub-critical J 0.05 6.55 6.60 7.81 7.86 1.26 1.26 Sub-critical K 1.08 6.60 7.68 7.86 12.86 5.18 5.18 - L 0.05 7.68 7.73 12.86 12.91 5.18 5.18 - M 0.56 6.60 7.16 7.86 8.24 1.26 1.26 Sub-critical N 1.08 7.16 8.24 8.24 9.50 1.26 1.26 Sub-critical O 3.21 8.24 11.45 9.50 12.71 1.26 1.26 Sub-critical P 0.20 12.71 12.91 12.71 12.91 0.00 0.00 Critical Q 0.04 12.91 12.95 12.91 12.95 0.00 0.00 Critical
  • 6. Nwankwojike, B. Nduka Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 4, Issue 12( Part 6), December 2014, pp.91-96 www.ijera.com 96|P a g e flushing materials preparation, 19.44 for well drilling, 1.92 for casing, 1.92 for gravel packing, 1.2 for flushing, 25.92 for water collection/analysis, 1.2 for water treatment, 13.44 for pumping test, 25.92 for platforming, 77.04 for pump installation/integration of water conveying systems, 4.8 for test running and 0.96 for training end users/project commission. The results of this investigation are therefore recommended as a model/guide for effective planning and execution of deep borehole water supply scheme in Ikwuano to ensure adequate and timely project execution. REFERENCES [1.] Agunwamba J. C. (1995), Rural Water Supply, Successes and Failures. In E. C. Eboh, C. U. Okoye and D. Ayichi edited Rural Development in Nigeria. Concepts, Processes and Prospects. Auto-century Publishing Company Limited, Enugu Nigeria. pp. 103 -188. [2.] Onwughara, I. J. (2010) Design and Optimization of Water Treatment and Distribution Scheme for Michael Okpara University of Agriculture Umudike Campus”, B. Eng. Degree Project, Department of Mechanical Engineering, Michael Okpara University of Agriculture, Umudike, 2010. [3.] Singh G. and Singh J. (2003), Water Supply and Sanitary Engineering. Standard Publisher Distributors Naisarak Delhi. [4.] Bell F.G. and Hamill L. (2004), Ground Water Resources Development. British Library Cataloguing Publications, London. [5.] Arora K.R. (2005), Irrigation, Water Power and Water Resources. Standard Publishers Distributors, Naisark Delhi. [6.] Imaga E. U. L. (2003). Theory and Practice of Production and Operations Management. Rhyce Kerex Publishers, Enugu, Nigeria, pp. 321-342, [7.] Cheema D.S (2006), Operation Research. Laxmi Publications (N) Ltd, Daryganj New Delhi [8.] Kapoor, V. K. (1993). Problems and Solutions in Operation Research. 2nd Revised Edition, Sultan Chand and Sons, New Delhi, pp. 667- 746. [9.] Benjamin, S. B. (2008). Logistics Engineering and Management. 6th Edition, Prentice-Hall of India Private Limited, New Delhi, pp. 372- 431, 2008. [10.] Ekwe, L. O. (2002) Application of Optimization Technique in Borehole Water Project (A Case Study of UNICEF Assisted Borehole Water Projects in Enugu State). MBA Degree Project, Department of Project Management Technology. Federal University of Technology, Owerri. [11.] Anosike, M. (2008) Application of Optimization Technique in Borehole Water Supply Projects (A Case Study of Federal Department of Rural Development Borehole Projects in Abia State). B. Eng. Degree Project, Department of Civil Engineering, Michael Okpara University of Agriculture, Umudike.