FINAL PROJECT
MANAGEMENT REPORT
The Social Album, City Lobby
A Documentation of A Medium-Sized Project
Tutor: Ar. Sateerah Hassan
Ho Yen Liang 0326660
1
1.0 Project Introduction / 3
1.1 Project Brief
1.2 Project Objectives
1.3 Project Goals
1.4 Organisation Structure
1.5 Client & Stakeholders
2.0 Site Information & Studies / 6
2.1 Site Introduction
2.2 S.W.O.T Analysis
2.3 PESTLE Analysis
3.0 Project Viability / 26
3.1 Programme Viability
3.2 Design Suitability
3.3 Schedule of Accommodation - Tabulation of Spaces
3.4 Economic Feasibility - Budget Calculation
4.0 Project Procurement & Resource Planning / 91
4.1 Procurement Process
4.2 Resource Planning
Content
2
5.0 Risk Analysis & Management / 96
5.1 Risk Analysis
6.0 Project Delivery /
6.1 Success Criteria
6.2 Work Breakdown Structure (WBS)
6.3 Gantt Chart
1.0 Project Introduction: The Social Album
1.1 Project Brief
The proposed project calls for designing a ‘City Lobby’, which will engage and re-engage the city’s local
population and visiting tourists from other towns or countries. A quality public place and building where its
architecture can create great opportunities to build and strengthen the people’s connection. The project
addresses earlier studies and researches on the socio-cultural issues related to the architecture of Johor
Bahru, namely: Ethnicity (segregation of multi-racial community), Demography (segregation based on age
and social status) and Identity (urban landscape is homogenous and contiguous).
1.2 Objectives
The City Lobby is used as a gathering place for people in the city and it offers a wide range of disparate
activities, which can be non-to-profit type.
● To promote the common interests or ‘neutral spaces’ of the public where specific dialogues and
activities are encouraged and expected to happen.
● To showcase cultural events, public activities, recreational activities and public programmes which
is not present in the popular weekend destinations for locals and tourists such as theme parks and
urban lifestyle centres.
1.3 Goals
● To create a platform for collaboration between different age classes, interests and social
background to create a healthy environment for appreciation of difference and similarities.
● To provide healthy interaction between local city dwellers, tourists, visitors and transient users.
● To allow people to stamp their own identity leading to ‘personalization’ of the space and the place
● To blur the boundary between the division of the multicultural communities on site.
● To celebrate the diversity of multicultural coexistence of Johor Bahru, expressing the spirit of
“Bangsa Johor”.
3
1.0 Project Introduction
Figure 1.1.1 Aerial View to Site (Ho, 2019)
1.4 Organisation Structure
1.4.1 Project Team
Client: Johor Bahru City Council, also known as Majlis Bandaraya Johor Bahru (MBJB)
Consultants:-
● Architect: HOArchitects Sdn Bhd.
● Civil & Structural Engineer: CYS Jurutera Sdn Bhd.
● Mechanical & Electrical Engineer: Perunding BCP Sdn Bhd.
● Quantity Surveyor: Alpha Omega Matrix Sdn Bhd.
● Landscape Architect: HODA Design Sdn Bhd.
● Interior Designer: J&V Interior Design Sdn Bhd.
Lead Consultant
HOArchitects Sdn Bhd.
Main Consultants
Contractors
Architect
HOArchitects Sdn Bhd.
M&E Engineer
Perunding BCP Sdn Bhd.
Landscape Architect
HODA Sdn Bhd.
C&S Engineer
CYS Jurutera Sdn Bhd.
Quantity Surveyor
Alpha Omega Matrix Sdn
Bhd.
Interior Designer
J&V Interior Design Sdn
Bhd.
Figure 1.4.1 Organization Chart of Project (Ho, 2019)
Main Contractor
Sub-Contractor
4
Client (Johor Bahru)
MBJB
Main Consultants
1.0 Project Introduction
Specialists
Suppliers
1.5 Client & Stakeholders
1.5.1 Client
Majlis Bandaraya Johor Bahru (MBJB)
Majlis Bandaraya Johor Bahru or Johor Bahru City Council (MBJB) is a local authority which administers Johor Bahru city centre. MBJB are responsible
for 12 major roles, and two of them are fostering a stronger sense of community and sustaining the environmental quality of Johor Bahru landscape.
Therefore, the city lobby project is proposed to be a community-based project which MBJB has the opportunity to achieve their roles and objectives.
1.0 Project Introduction
5
Jabatan Kebudayaan & Kesenian Negara (JKKN)
JKKM aims to plan and coordinate art and cultural activities in
the city lobby by promoting local arts and crafts development
on site. Their main role is to encourage the growth of arts and
cultural activities through effective collaboration between arts
and cultural organizations, government agencies,
non-governmental organizations and arts and cultural activists
from within and outside the country.
Ministry of Tourism, Art & Culture Malaysia (MOTAC)
MOTAC is responsible to preserve and promote the art and
culture of Johor Bahru as well. The organization helps with
providing conducive infrastructure for arts and culture and
advisory services to the Johor Bahru community.
ThinkCity
A community-focused urban regeneration organisation that
aims to create better, more sustainable cities in Malaysia by
supporting community-driven initiatives through the public
grants programme. ThinkCity will be proposing some of the
innovative work spaces in the city lobby to encourage different
communities to experience the co-working environment as a
community sharing initiative.
1.5.2 External Stakeholders
Senso Art Gallery & Cafe
Senso Art Gallery is a gallery owned by Ms. Katherine,
located at Jalan Tan Hiok Nee, it is a art platform for
the local artists and crafters to display their work and
also there is art workshops for public to take part in.
Thus, Senso will be providing an art studio for anyone
who is interested in local arts and crafts activities to
use the space.
Persatuan Hainan Johor Bahru
Persatuan Hainan Johor Bahru is an organization
responsible to preserve and promote the Chinese
heritage of the town, their mainly responsible for
documenting the historical artifacts and proposing
seasonal cultural activities on site. The information
lobby and archiving library would be funded by the
organisation to promote the heritage and cultural
values of Johor Bahru.
2.1 Site Introduction
The project is located at the City of Johor Bahru, one of Malaysia’s premier
city and urban destination because of its highly modernized infrastructure.
Based on the current feel of the place, Johor Bahru City can be both busy
at day and night time. The site sits among four streets, which are Jalan
Trus, Jalan Tan Hiok Nee, Jalan Dhoby and Jalan Segget. The site is a
vibrant town, heavily emphasizing on the food, art and market (Bazaar
Karat) cultural aspects. It can be observe that the old shophouse typology
are enveloped within the new taller developments that shades the lower
buildings below. Both coexist at the same place, cultured at different time.
The activities differ by time by expanding the usage of the streets.
Morning where people stroll through the pedestrian walkway, while at night
the gathering of people beside the stalls in Bazaar Karat. This transition of
time shows prominent differences of assembling and dispersing of people
during different time zones daily.
6
2.0 Site Analysis
Figure 2.1.1 Site Plan (Ho, 2019)
2.0 Site Information: Johor Bahru Heritage Town
● Total Land Area: 3335.5 m2
● Plinth area : <60%
Including car parks, walking pavement, loading bay, rubbish
collection, & utilities
● Setback: -Front: 6m + 2m (greenery)
-Sides and back: 6m
● Height control: ≤4 storeys
● Parking requirement: (site area - 30% for utilities) ÷ standard
size of carpark lots = 30 parking lots
2.2 S.W.O.T Analysis
7
● High permeability and
accessibility by vehicular
and foot to site.
● Variety and diverse of
socio-cultural and historical
value on site.
● Greeneries and high rises
shades the site, providing
comfort to users.
● Public or open spaces are left
unused and attracts homeless
people to utilise.
● High rises around the site has
shadowed the fine grain
shophouses on site, creating
visual barrier.
● Time gap on site where there
is no activities happening
during the evening session
● Lost interest on the culture of
the mundane town
● Promoting cultural
awareness whilst
preserving the historical
and socio-cultural value
on site.
● Celebrating the vibrancy
and diversity on site
through providing a
platform for people to
collaborate and connect.
● The increase presence of
homeless people may caused
a high risk of security on site
● Presence of illegal parking on
site affect the traffic flow and
safety of pedestrians
● Division between the
multicultural communities due
to misinterpreted boundaries
and understandings
WeaknessStrength
Opportunity Threat
2.0 Site Analysis
2.3 PESTLE Analysis
8
The proposed scheme has the intention to encourage
positive engagement between the local dwellers, the
tourists and transient users, therefore the collaborative
and cultural activities are introduced and initiated
through some of the government agencies, like Jabatan
Kebudayaan & Kesenian Negara (JKKN) and Ministry
of Tourism, Art & Culture (MOTAC). Bazaar Karat is also
administered by the client MBJB and any morning or
night market activities introduced in the scheme should
be liaised with the client.
Some of the proposed programmes like the artisan retail
spaces and art gallery are funded by the external
stakeholder Senso Art Gallery Cafe, offering to provide a
platform for artist to showcase their work. The archive
library and information lobby will also be funded by the
Persatuan Hainan Johor Bahru, which initiated the
heritage museum of the site itself. Some of the
shophouses on site are purchased by Singaporeans but
they are left vacant and unused.
The heritage site is rich in cultural activities expressed
in the form of food, artisan crafts, exhibitions and a mix
of all above. Bazaar Karat, the open street market and
live performances at night such as street busking helps
brighten up the site.
The development of urban infrastructure is on a fast
paced track, aligning their growth triangle with
Indonesia and Singapore, ensuring the strong
connections and trade on both sides. The city is one of
the fastest-growing cities in Malaysia after Kuala
Lumpur due to its modernized infrastructure.
The proposed building setback to be 8m along the street
Jalan segget, and 6m along other sides. 10% greeneries
must be included for the surrounding landscape and
minimum 30 parkings to be provided.
There are other law enforcement such as Night/Day
Markets (MBJB) By-Laws 2003 to make sure the vendors
for the night market or bazaar comply to the requirements
from the authority. The Heritage Walk of Jalan Tan Hiok
Nee cannot be demolished or build any high-rise buildings
that will affect the condition of the site.
The well-paved roads on cultural streets allowed a
comfortable walking experience. The ongoing urban
planning strategies proposed by ThinkCity to
rejuvenate and pedestrianise Jalan Dhoby to enhance
pedestrian connectivity to the cultural street, Jalan Tan
Hiok Nee. The alleys are rejuvenated into vibrant
paths via mural art and streetscapes lighting. Most
importantly the streets are well shaded with greens.
Politic Economic Sociological
LegalTechnology Environment
2.0 Site Analysis
3.1 Program Viability
The city lobby played a role in fostering a symbiotic relationship called interdependency, between the multiracial community through creating
permeable boundaries, which allowed people to communicate, collaborate and connects.
9
3.0 Project Viability
Figure 3.1.1 Conceptual Diagrams (Ho, 2019)
3.0 Project Viability
Communicate Connect Collaborate
Design articulation of spaces revolved around a ‘common ground’ for the communities to share, shared spaces of common interests articulate
through path-space relationship and overlapping of spatial identities. It’s the foundation of the unintentional meetups with different people of
different cultural background, and that the spaces could house a sharing atmosphere of local city dwellers, tourists, visitors and transient users.
The programmatic spaces overlapped each other to form shared spaces of the city lobby. These shared spaces are articulate through the
in-between spaces like courtyards, pocket and breakout spaces and collaboratories.
3.2 Design Suitability
10
3.0 Project Viability
3.2.1 Contextual Response
The design of the city lobby takes into consideration of the site itself being entitled as
the heritage site of Johor Bahru Old Town. The site has an enriching blend of food, art
and market culture, with a multicultural community locating at the heart of the town. The
city lobby responses to the issue regarding human and cultural aspect, which are the
lack of human activities due to the cause of a time gap issue; the lack of authenticity
due to the tourism economic culture on site; and lastly lacking a proper platform and
common ground for the locals to express their artistic sensibilities.
TIME GAP?
Figure 3.2.1 Contextual Intangible Elements (Ho, 2019)
Figure 3.2.2 Temporal Study of Different Communities at Kin Hua Kopitiam (Ho, 2019)
TIME
GAP?
3.2 Design Suitability
11
3.0 Project Viability
3.2.2 Programmatic Response - Social Feasibility
The programs proposed in the city lobby are mostly food, art and market based activities
and events as these three aspects has the most prominent identity of the Johor Bahru
heritage town. These objectives of these programs are suitable for different ethnic group at
all ages as they allow the engagement of the people from this diverse community. The
visitors get to experience and engage with different age group via different programmatic
aspects and common spaces provided for these various user groups to come together to
have fun and interact with each other which subsequently will diminish the intangible barrier
between the people of Johor Bahru, achieving the infamous “Bangsa Johor” concept.
Figure 3.2.4 Programmatic Diagram of Local Public Spaces & Events in Johor Bahru (Ho, 2019)
Figure 3.2.3 Programmatic Aspects of the City Lobby - The Social Album (Ho, 2019)
3.3 Schedule of Accommodation - Tabulation of Spaces
12
3.0 Project Viability
Floor Gross Floor Area (m²)
Basement Floor 2108.7
Ground Floor 1650.8
First Floor 696.5
Second Floor 843.9
Third Floor 521.4
Total 5821.3
3.3.1 Economic Feasibility - Budget Calculation
5821.3m² = 62660 ft²
Estimated construction cost at RM 200 per sqft,
Gross construction cost
= 62600 X RM 200
= RM 12,532,000
Consultant fee at 10% of construction cost
= RM 12,532,000 X 10%
= RM 1,253,200
Table 3.3.1 Gross Floor Area Tabulation (Ho, 2019)
Contribution Fees for TNB & IWK (5%)
= RM 12,532,000 X 5%
= RM 626,600
Contingency of budget (5%)
= RM 12,532,000 X 5%
= RM 626,600
Total Estimated Building Cost
= RM 12,532,000+ RM 1,253,200 +
RM 626,600 + RM 626,600
= RM 15,038,400
3.3.2 Technical Feasibility
The construction method used for the city lobby will be reinforced concrete (RC) slab
and steel post and beam construction. The construction will be featuring a few steel
columns which protrude out from the basement, to allow natural daylight into the
basement space, and supporting the large overhangs of the building, also representing
the three communities of the site itself. The facade will be constructed with U Channel
Glass Profile, which are very durable and it can be self-supported without any external
framing. The glass will be manipulated with different openings to allow adequate
natural daylighting into the building. The configuration of the U Channel Glass will be
arranged in a double-glazed pattern to block direct sunlight from the West Sun during
the evening.
3.3.3 Legal Feasibility
The proposed building fully comply the legal requirements as stated within the Uniform Building
By-Law 1994 (UBBL) and the guidelines provided from Majlis Perbandaran Johor Bahru (MBJB).
The proposed building is sat in between a row of shophouses and a high rise public bank. Since the
building is facing Jalan Segget, Jalan Dhoby, Jalan Trus and Jalan Tan Hiok Nee, which has a
pedestrianised pavement wider than a five foot walkway, the setback of the building follows
according to this.
Besides, fire escape with a dead-limit of not more than 30m is provided, as well as adequate lighting
and ventilation to floor area ratio is adopted. There are 30 parking, 2 disabled parking and services
provided on the lower ground floor of this building as the decision of creating a basement is omitted.
The building also comply to the MS 1525 and MS 1184 (disabled) guideline.
13
4.0 Project Procurement & Resource Planning
4.0 Project Procurement & Resource Planning
4.1 Procurement Method
Public Works Department Method (P.W.D Form of Contract 203/203A)
As well as referred as Jabatan Kerja Raya (JKR). PWD is the federal government department in Malaysia under Ministry of
Works Malaysia (MOW) which is responsible for construction and maintenance of public works in Malaysia.
4.1.1 Procurement Suitability
Majlis Perbandaran Johor Bahru (MBJB) acts as the government agency on behalf of the goods, services and construction acting as a public authority. As the City Lobby aims to
serve for the public for communal and cultural activities, PWD is the most suitable form of contract as the client is represented under a government body despite it
being a medium scale project.
Objective of Using this Method :
● To ensure the realization of policies and deliver services through
smart partnership strategy.
● To ensure consistency in services it procures, JKR established
processes and systems that must be adhered to by contractors.
Contract Conditions :
● Contractor allowed to claim contract period extension for various
circumstances deemed the government’s risks.
● Majority funded by contractor - as is a separation between the
construction and design team,therefore contractor holds most
responsibility.
● No retention money is withheld from payments.
● Bill of payment are in a lump sum.
P.W.D Form of Contract 203/203A (Revised 2007)
These are the traditional forms of contract based on drawings and specification (203)
or bill of quantities (203A) produced for use in public sector or government projects in
both building and engineering contracts. In this latest 2007 version remains where it
said majority of the risk has been transferred to the contractor.
PWD 203A
Standards Form of
Building Contract is
in use at many
public project where
the government is
the main client.
4.2 Resource Planning
No. Task/ Deliverables Resource Types Quantity Skills Required Equipment/ Medium
A. Schematic Design
1. Site Visit and Survey
Client, Consultants, Land
Surveyor Site Observation and Analysis done
with professional analytical results
or conclusion
Manual Tools and Equipment for Site Analysis
2. Site Documentation & Analysis Client, Consultants
3. Conceptual Sketches Architect 1 -
4. M&E and Landscape Planning
M&E Engineer, Landscape
Architect
2
Ability to plan mechanical and
electrical connection; landscape to
plan according to the site context
Proficiency in using digital softwares such as
Autodesk CFD, AutoCAD, ArcGIS, Revit
5. Cost Estimation Quantity Surveyor 1
Taught individual in producing cost
estimation schedules and able to
preparare of Bill of Quantities
Skilled Microsoft Excel user in producing
spreadsheets of schedules
6. Visualization Architect, Draftsmen 1,2
Able to showcase the overall form,
appearance and visualisation of the
3-Dimensional model of the building
Any modelling software, for example, Autodesk
Revit, AutoCAD
4.0 Project Procurement & Resource Planning
14
No. Task/ Deliverables Resource Types Quantity Skills Required Equipment/ Medium
2. Design Development
1. Detailed Design Drawings Architect, Draftsmen 1,2
Able to produce all submission
drawings to authority (MBJB) to get
building approval
Skilled profession to use digital drawing
tool that can produce proper detailed
drawings like Autodesk AutoCAD
2. Detailed Project Budget Quantity Surveyor 1
Continuation of producing the all cost
with detailed schedule
Using Microsoft Excel to produce schedules
and cost calculation
3. Local Authority Submission Architect 1
Liaise with different departments of
authority in MBJB in submission of
drawings
Printouts of submission drawings to
requirement of MBJB
3. Contract Documentation
1. Preparation of Bill of Quantities Quantity Surveyor 1
Required skills and knowledge in
producing Bill of Quantities
Using the software of WinQS, Microsoft
Excel
2. Tender Period (Open Tender) Architect, Project Manager 2
3. Tender Evaluation Client
4. Award of Contract Architect 2
Certified architect to award the
contractor the official letter of award to
the contractor
Microsoft Word
4.0 Project Procurement & Resource Planning
15
No. Task/ Deliverables Resource Types Quantity Skills Required Equipment/ Medium
4. Contract Implementation
1. Initial Project Meeting
Client and all parties are
involved
-
- Ability to communicate effectively and
efficiently
- Ability to solve issues effectively and
promptly
- Experienced in site and personnel
management
-
2.
Monitor on Site Work & Construction
Progress
Architect 1 - -
3. Monitor Civil Works on Site Civil Engineer 1 - -
4. Monitor Structural Works on Site Structural Engineer 1 - -
5. Monitor M&E Works on Site
Mechanical & Electrical
Engineer
2 - -
6. Monitor Landscape Works on Site Landscape Architect 1 - -
7. Monitor on Site Works
Site Manager & Clerk of
Work
2 - -
8. Conduct On Site Construction Work Contractor & Site Workers 2 - -
9.
Inspection of Building Services on
Site Works
Facilities Manager 1 - -
4.0 Project Procurement & Resource Planning
16
No. Task/ Deliverables Resource Types Quantity Skills Required Equipment/ Medium
5. Final Completion (Handing Over)
1.
Testing, commissioning and
Inspection
Client and all parties are
involved.
- - -
2. Issuance of CCC Architect 1
Certified architect to issue the CCC
Certificate to the consultants and
contractor
Using the software of Microsoft Word or
Adobe PDF
3. Preparation of Final Account
Architect, Quantity
Surveyor
2
Certified architect to issue the consultant
final account (contractor) and contractual
final account (closing file)
Using the software of Microsoft Excel
4.0 Project Procurement & Resource Planning
17
5.1 Risk Analysis
Risk Likelihood Severity Impact Mitigation Strategy Contingency Plan
Client reduces budget without warning Medium Low/Medium
Minor changes such as the
material choice to major changes
such as project scope.
Create several design options that vary
in scope and materials.
Meet with client to discuss the
possibilities to raise funds to
meet objectives.
Client frequently changes design High Low/Medium
Change in quality, delays in
construction and planning.
Ensure constant communication
between consultants and clients to
prevent miscommunications.
Utilize contractual agreements
to prevent changes in design.
Change in government Low Medium/High
Possibility of cancellation of
project or change in scope.
Publicly emphasize the apolitical
nature of the project and highlight its
benefit to the nation regardless of
politics.
Meet with the leaders of the
new government to persuade
them of the merits of the
proposal.
Client loses faith in experimental
programmes
Medium Medium/High
Change in scope to outright the
cancellation of project.
Hosts prior events to showcase the
viability of the programmes.
Compromise and present a
more familiar programmes.
Site users demonstrates and show
displeasure at proposed development
Low Medium/ High
Change in scope to outright the
cancellation of project.
Hosts talks and discussions to
persuade and change public’s
conception.
Appeal to the greater good of
the nation.
5.1.1 Pre- Construction Phase
5.0 Risk Analysis & Management
5.0 Risk Analysis & Management
18
Risk Likelihood Severity Impact Mitigation Strategy Contingency Plan
Error in installation Low Low/ High
Construction will be on hold
leading to project delay.
PM should delegate a task for quality
check to ensure no error happen
throughout the construction phase.
Make regular visits on site to
check on the updated
progress.
Change in design Low Medium/High
Delays in construction process,
destruction of design vision, and
violation of contractual agreement.
Ensure contract agreed limits and
controls the amount and scope of
changes.
Utilize legal means to ensure
design is not unnecessarily
changed.
Construction related accidents involving the
public
Medium Medium/High
Corrodes public sentiment and
support for the project, which can
lead to project cancellation.
Ensure strict adherence to safety
standards as set by law.
Personally visit and impact site
to ensure compliance and
utilize legal means if
necessary.
Insufficient storage on site for building
materials
Medium Medium/High
Authorities can get in the way to
stop the operation on site .
Ensure that storage size is capable
enough to hold enough materials.
5.1.2 Construction Phase
5.0 Risk Analysis & Management
19
Risk Likelihood Severity Impact Mitigation Strategy Contingency Plan
The programmes do not attract the targeted
user according to plan
Low Medium/High
With the lack of attraction from the
users, the building will be shut
down and put up for sale.
Have multiple programmes and neutral
spaces to give variety of options to the
user.
Poor maintenance of facilities Medium Medium/High
The unmaintained and unpleasant
look will prevent users from going
into the building.
To have maintenance strategy for each
possible elements.
5.1.3 Building Operation Phase
6.1 Success Criteria
6.0 Project Delivery
20
A project’s success criteria refers to measurable terms of what should be the outcome of the project that is acceptable to
the end user, customer and the stakeholders. Thus, Melwood, OnePark project team emphasises on three main
objectives that they aim to achieve throughout the project phases, including the quality of work, being on time and
keeping within budget to ensure client satisfaction and a smooth workflow. This triangular model circulates and form a
conclusion which is the quality of the project. In certain projects, priorities may be given to two out of the three
parameters, especially relating to the cost and time. This would cause an imbalance of the triangular model, affecting
the quality of the project managed.
SCOPE TIME COST
The scope of the project depends on the amount of work
that needs to be done to complete the project.
1) Using the WBS to outline and define the scope
of work.
2) Visualizing the duration and quantity of work
with the aid of the Gantt Chart.
3) Coordinating meetings between consultants and
clients to update on the project scope.
4) Minimizing changes during construction phase
towards the design
5) Decreasing risk factor of failing project and
proper management of construction.
6) Design to achieve the requirements (progress,
standards, finance, and time)
The time frame to complete the project within the
estimated 35 months which is starting from December
2019 to October 2022.
1) Using the Gantt Chart to plan out the time frame
and to highlight the critical periods of the
project.
2) Adhering to the workflow programme to
complete tasks to ensure that there is no delay
which will affect the critical path.
The total estimated cost for the completion of the project
is RM 15,038,400.
1) Using a proper fee planning structure to ensure
that the project is completed within the budget.
2) The consideration of materials to be done
according to the project budget while ensuring a
quality selection.
6.0 Project Deliveries
6.2 Work Breakdown Structure (WBS)
The Social Album, Johor Bahru City Lobby
Pre-construction stage Post-Construction stage
Construction Stage -
Contract Administration & Implementation Stage
1.1 Inception - Site Studies
1.1.1 Client Briefing
1.1.2 Design Requirements
1.1.3 Site Investigation
1.1.4 Feasibility Studies
1.2 Schematic Design
1.2.1 Soil Investigation
1.2.2 Conceptual Sketches
1.2.3 Spaces Planning
1.2.4 M&E Planning
1.2.5 Landscape Planning
1.2.6 Material Proposal
1.2.7 Design Visualization
1.2.8 Cost Estimation
1.3 Design Development
1.3.1 Detailed Design Drawings
1.3.2 Detailed Landscape Drawings
1.3.3 Authority Submission
1.3.4 Revised Cost Estimate & Project
Schedule
1.4 Contract Documentation
1.4.1 Tender Documentation
1.4.2 Tender Review & Award
1.4.3 Project Planning & Schedule
1.4.4 Stakeholder Notification
2.1 Preliminary
2.1.1 Mobilization & Site Establishment
2.1.2 Dilapidation Survey
2.1.3 Setting Out
2.2 Foundation
2.2.1 Land excavation
2.2.2 Piling & Footing
2.2.3 Basement Slab & Wall
2.3 Superstructure
2.3.1 R.C. Slab & Landing
2.3.2 R.C. Beam, Column & Flooring
2.3.3 Internal & External R.C Wall
2.3.4 Lift & Fire Staircase
2.3.5 U Channel Glass Wall - Facade
2.3.6 Glass Curtain System
2.4 Roofing
2.4.1 Roof Construction
2.4.2 Gutter & Drainage System
2.5 M&E Services Installation
2.7.1 Fire Protection System
2.7.2 M&E Fixture Installations
2.7 External & Landscape
2.7.1 Surface Water Drainage
2.7.2 External M&E Work
2.7.3 Installation of Softscape & Hardscape
2.7.4 Turfing
2.7.5 Outdoor Lighting
2.6 Architectural Finish
2.9.1 Door & Window Frame & Panels
2.9.2 Tiling Works
2.9.3 Wall, Ceiling & Floor Finishing
2.9.4 Staircase & Handrail Finishing
3.1 Final Completion
3.1.1 Final Clearing & Testing
3.1.2 Inspection
3.1.3 Issuance of Certificate of Practical
of Completion (C.P.C)
3.1.4 Issuance Certificate of Completion
& Compliance (C.C.C)
3.1.5 Issuance of Certificate of Making
Good Defects (C.M.G.D)
3.1.4 Preparation of Final Accounts of
Contract
21
6.0 Project Deliveries
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
PRE-CONSTRUCTION STAGE
1. Schematic Design Phase
1.1 Project Briefing 1
1.2 Site Visit 1
1.3 Site Investigation 1
1.4 Soil Investigation 3
1.5 Feasibility Studies 1
1.6 Spatial Planning & Tabulation 1
1.7 Preliminary Design Proposal 2
1.8 Building Structure Proposal 2
1.9 Building Services Proposal 2
1.10 Landscape Design Proposal 2
1.11 Initial Estimation Cost 2
1.12 Planning Submission for DO Authorities 4
1.13 DO Authority Submission for Town Planning Approval 12
2. Design Development Phase
2.1 Detailed Architectural Drawings 20
2.2 Detailed Civil & Structure Drawings 18
2.3 Detailed M&E Drawings 18
2.4 Detailed Landsacpe Drawings 8
2.5 Pre-tender Cost Estimation 4
2.6 Building Plans Submission to MBJB 15
2.7 Other Authotities Submission
2.7.1 Passive Bomba 6
2.7.2 Active Bomba 6
2.7.3 Syarikat Air Johor 3
2.7.4 Road & Drains 3
2.7.5 IWK 3
2.7.6 Earthwork (Jabatan Kejuruteraan) 3
2.7.7 Multimedia 2
2.7.8 Streetlighting 2
2.7.9 DOE 2
2.7.10 Pos Malaysia 2
2.7.11 Transport (carpark) 2
2.7.12 Heritage 2
2.7.13 Landscape 2
3. Contract Documentation Phase
3.1 Finalize & Complete Architectural Tender Drawings 10
3.2 Complete Structural Tender Drawings 8
3.3 Complete M&E Tender Drawings 8
3.4 Tender Estimate 6
3.4 Preparation of Bill of Quantities 4
3.5 Call Tender 1
3.6 Tender Period 4
3.7 Opening of Tender 1
3.8 Review & Evaluation 4
3.9 Tender Report & Recommendation 3
3.10 Client's Approval & Award 2
CONSTRUCTION STAGE
4. Contract Implementation Phase
4.1 Preliminaries
4.1.1 Site Handover 1
4.1.2 Mobilization 3
4.1.3 Site Clearing & Levelling 2
4.1.4 Building setting out 1
4.2 Substructure
4.2.1 Excavation 4
4.2.2 Piling 10
4.2.3 RC Retaining Wall 4
4.2.4 Basement Columns, Beams & Slabs 12
4.2.5 Ramps 2
4.2.6 Lift pit 2
4.3 Superstructure
4.3.1 Beams 16 GF 1F 2F 3F
4.3.2 Columns 16 GF 1F 2F 3F
4.3.3 Slabs 16 GF 1F 2F 3F
4.3.4 Walls & Openings 16 GF 1F 2F 3F
4.3.5 Concrete Roof Slab, Steel Roof Truss & Corrugated Metal Decking 14
4.3.6 Installation of Gutter & Drainage System 2
4.4 Services Installation
4.4.1 Active Fire Protection Systems 12
4.4.2 M&E Fixtures Installations 12
4.5 Architectural Finishes
4.5.1 Door & Window Panels 4
4.5.2 Ceiling, Wall & Floor Finishes 4
4.5.3 Built-In Installation Works - Furnitures 8
4.6 Landscaping & Civil works
4.6.1 External Landscaping Works 12
4.6.2 Road & Drainage Works 12
POST-CONSTRUCTION STAGE
5.0 Final Completion Phase
5.1 Testing and commissioning 4
5.2 Cleaning 2
5.3 Inspection by consultants 2
5.4 Pre-CCC inspection by authorities (clearance letters) 2
5.5 Certifying as built drawings, warranties and guarantees, etc. 8
5.6 Issuance of CPC 1
5.7 Issuance of CCC 1
5.8 Defects Liability Period (Handing Over) 96 (2years)
5.9 Issuance of CMGD 1
5.9 Final Accounts Certificate 2
6.3 Gantt Chart
2019
Dec Jan FebTask/Deliverables Duration (Weeks)
2020
Mar Apr May June July Aug Oct Nov Dec Aug Sep Oct Oct
2 Years
20242021
Mar Apr May June
2022
Sep Aug Sep JulyOctJan Mar Apr May JuneJuly Nov Dec Jan FebFeb
DOApproval
BPApproval
LetterofAward
IssuanceofCPC
IssuanceofCCC
FinalAccountCertificate

More Related Content

What's hot

Final wisma lee rubber compilation (new)
Final wisma lee rubber compilation (new)Final wisma lee rubber compilation (new)
Final wisma lee rubber compilation (new)WC Yan
 
Comprehensive design report 2 To create a Social Hub Center that reflect the ...
Comprehensive design report 2 To create a Social Hub Center that reflect the ...Comprehensive design report 2 To create a Social Hub Center that reflect the ...
Comprehensive design report 2 To create a Social Hub Center that reflect the ...Weng Chuan
 
Project management report project 1
Project management report project 1Project management report project 1
Project management report project 1Afiq Knick
 
Research Report on Menara Maybank
Research Report on Menara MaybankResearch Report on Menara Maybank
Research Report on Menara MaybankSheau Hui Tan
 
NATIONAL MOSQUE - CULTURE AND HISTORY 2 REPORT
NATIONAL MOSQUE - CULTURE AND HISTORY 2 REPORTNATIONAL MOSQUE - CULTURE AND HISTORY 2 REPORT
NATIONAL MOSQUE - CULTURE AND HISTORY 2 REPORTAtiqah Ghazali
 
Adaptive Re-use of Melaka Stamp Museum
Adaptive Re-use of Melaka Stamp MuseumAdaptive Re-use of Melaka Stamp Museum
Adaptive Re-use of Melaka Stamp MuseumFakhrul Afifi
 
Ar Mun Inn's Group - Taman Tasik Titiwangsa Site Analysis
Ar Mun Inn's Group - Taman Tasik Titiwangsa Site AnalysisAr Mun Inn's Group - Taman Tasik Titiwangsa Site Analysis
Ar Mun Inn's Group - Taman Tasik Titiwangsa Site AnalysisJoe Onn Lim
 
BSC (H) IN ARCHITECTURE DEGREE SEM 6 PROJECT MANAGEMENT FINAL REPORT
BSC (H) IN ARCHITECTURE DEGREE SEM 6 PROJECT MANAGEMENT FINAL REPORT BSC (H) IN ARCHITECTURE DEGREE SEM 6 PROJECT MANAGEMENT FINAL REPORT
BSC (H) IN ARCHITECTURE DEGREE SEM 6 PROJECT MANAGEMENT FINAL REPORT jolynnTJL
 
Stadium negara report history2
Stadium negara report history2Stadium negara report history2
Stadium negara report history2ForestedTiger
 
Project Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectProject Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectNekumi Kida
 
URBAN TRAIL OF PENANG: Georgetown and Bandar Perda
URBAN TRAIL OF PENANG: Georgetown and Bandar PerdaURBAN TRAIL OF PENANG: Georgetown and Bandar Perda
URBAN TRAIL OF PENANG: Georgetown and Bandar PerdaAida Nesa
 
Building setback & service road
Building setback & service roadBuilding setback & service road
Building setback & service roadAriff Abe
 
Cnh2 petaling jaya civic centre
Cnh2   petaling jaya civic centreCnh2   petaling jaya civic centre
Cnh2 petaling jaya civic centre杉 江紫
 
History & culture of lumut, perak
History & culture of lumut, perakHistory & culture of lumut, perak
History & culture of lumut, perakEraz
 
Conservation
Conservation Conservation
Conservation hongbinng
 
Redefining Malaysian Terrace Residential Architecture by Introducing Passive ...
Redefining Malaysian Terrace Residential Architecture by Introducing Passive ...Redefining Malaysian Terrace Residential Architecture by Introducing Passive ...
Redefining Malaysian Terrace Residential Architecture by Introducing Passive ...Ong Seng Peng Jeff
 
ARCHITECT ACT 1967 (ACT 117) & RULES
ARCHITECT ACT 1967 (ACT 117) & RULESARCHITECT ACT 1967 (ACT 117) & RULES
ARCHITECT ACT 1967 (ACT 117) & RULESZhao Wei Kim
 
Architecture Culture & History II : Project 2 -report
Architecture Culture & History II : Project 2 -reportArchitecture Culture & History II : Project 2 -report
Architecture Culture & History II : Project 2 -reportLee Wan Xuan
 

What's hot (20)

Final wisma lee rubber compilation (new)
Final wisma lee rubber compilation (new)Final wisma lee rubber compilation (new)
Final wisma lee rubber compilation (new)
 
Comprehensive design report 2 To create a Social Hub Center that reflect the ...
Comprehensive design report 2 To create a Social Hub Center that reflect the ...Comprehensive design report 2 To create a Social Hub Center that reflect the ...
Comprehensive design report 2 To create a Social Hub Center that reflect the ...
 
Project management report project 1
Project management report project 1Project management report project 1
Project management report project 1
 
UBBL 1984 pdf
UBBL 1984 pdfUBBL 1984 pdf
UBBL 1984 pdf
 
Research Report on Menara Maybank
Research Report on Menara MaybankResearch Report on Menara Maybank
Research Report on Menara Maybank
 
NATIONAL MOSQUE - CULTURE AND HISTORY 2 REPORT
NATIONAL MOSQUE - CULTURE AND HISTORY 2 REPORTNATIONAL MOSQUE - CULTURE AND HISTORY 2 REPORT
NATIONAL MOSQUE - CULTURE AND HISTORY 2 REPORT
 
Jalan Ampang Case Study
Jalan Ampang Case StudyJalan Ampang Case Study
Jalan Ampang Case Study
 
Adaptive Re-use of Melaka Stamp Museum
Adaptive Re-use of Melaka Stamp MuseumAdaptive Re-use of Melaka Stamp Museum
Adaptive Re-use of Melaka Stamp Museum
 
Ar Mun Inn's Group - Taman Tasik Titiwangsa Site Analysis
Ar Mun Inn's Group - Taman Tasik Titiwangsa Site AnalysisAr Mun Inn's Group - Taman Tasik Titiwangsa Site Analysis
Ar Mun Inn's Group - Taman Tasik Titiwangsa Site Analysis
 
BSC (H) IN ARCHITECTURE DEGREE SEM 6 PROJECT MANAGEMENT FINAL REPORT
BSC (H) IN ARCHITECTURE DEGREE SEM 6 PROJECT MANAGEMENT FINAL REPORT BSC (H) IN ARCHITECTURE DEGREE SEM 6 PROJECT MANAGEMENT FINAL REPORT
BSC (H) IN ARCHITECTURE DEGREE SEM 6 PROJECT MANAGEMENT FINAL REPORT
 
Stadium negara report history2
Stadium negara report history2Stadium negara report history2
Stadium negara report history2
 
Project Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectProject Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A Project
 
URBAN TRAIL OF PENANG: Georgetown and Bandar Perda
URBAN TRAIL OF PENANG: Georgetown and Bandar PerdaURBAN TRAIL OF PENANG: Georgetown and Bandar Perda
URBAN TRAIL OF PENANG: Georgetown and Bandar Perda
 
Building setback & service road
Building setback & service roadBuilding setback & service road
Building setback & service road
 
Cnh2 petaling jaya civic centre
Cnh2   petaling jaya civic centreCnh2   petaling jaya civic centre
Cnh2 petaling jaya civic centre
 
History & culture of lumut, perak
History & culture of lumut, perakHistory & culture of lumut, perak
History & culture of lumut, perak
 
Conservation
Conservation Conservation
Conservation
 
Redefining Malaysian Terrace Residential Architecture by Introducing Passive ...
Redefining Malaysian Terrace Residential Architecture by Introducing Passive ...Redefining Malaysian Terrace Residential Architecture by Introducing Passive ...
Redefining Malaysian Terrace Residential Architecture by Introducing Passive ...
 
ARCHITECT ACT 1967 (ACT 117) & RULES
ARCHITECT ACT 1967 (ACT 117) & RULESARCHITECT ACT 1967 (ACT 117) & RULES
ARCHITECT ACT 1967 (ACT 117) & RULES
 
Architecture Culture & History II : Project 2 -report
Architecture Culture & History II : Project 2 -reportArchitecture Culture & History II : Project 2 -report
Architecture Culture & History II : Project 2 -report
 

Similar to Final Project Management Report

Final Project Management Report
Final Project Management ReportFinal Project Management Report
Final Project Management Reportzerospaces_
 
Project management final - KSHV SZ
Project management final - KSHV SZProject management final - KSHV SZ
Project management final - KSHV SZKeshav Seewraz
 
Project management
Project management Project management
Project management Jing Fan Koh
 
Project management report document a medium size project.
Project management report document a medium size project. Project management report document a medium size project.
Project management report document a medium size project. Weng Chuan
 
Final Project Management Report
Final Project Management ReportFinal Project Management Report
Final Project Management ReportDavidJPCChai
 
Project management (3)
Project management (3)Project management (3)
Project management (3)Benjamin Tan
 
Final Project Management Report
Final Project Management ReportFinal Project Management Report
Final Project Management ReportCarmen Chan
 
Project Management (Individual)
Project Management (Individual)Project Management (Individual)
Project Management (Individual)FabienFoo
 
Finalstudio final report
Finalstudio final reportFinalstudio final report
Finalstudio final reportJing Fan Koh
 
Project management Project 2 report
Project management Project 2 reportProject management Project 2 report
Project management Project 2 reportHong Wei Teo
 
Project 2 : Documentation For A Medium-Sized Project
Project 2 : Documentation For A Medium-Sized ProjectProject 2 : Documentation For A Medium-Sized Project
Project 2 : Documentation For A Medium-Sized ProjectBryan Yeoh
 
FUNCTION OF THE PERFORMING ARTS STUDENT IN CULTURAL TOURISM IN THE CITY OF BU...
FUNCTION OF THE PERFORMING ARTS STUDENT IN CULTURAL TOURISM IN THE CITY OF BU...FUNCTION OF THE PERFORMING ARTS STUDENT IN CULTURAL TOURISM IN THE CITY OF BU...
FUNCTION OF THE PERFORMING ARTS STUDENT IN CULTURAL TOURISM IN THE CITY OF BU...AJHSSR Journal
 
Santa Monica Civic Center Mixed Use Arts & Cultural District
Santa Monica Civic Center Mixed Use Arts & Cultural DistrictSanta Monica Civic Center Mixed Use Arts & Cultural District
Santa Monica Civic Center Mixed Use Arts & Cultural DistrictHR&A Advisors
 
CPS Retail EOI 2015 Mar
CPS Retail EOI 2015 MarCPS Retail EOI 2015 Mar
CPS Retail EOI 2015 MarJohnny Hanson
 
project management
project managementproject management
project managementWC Yan
 
Project management final
Project management finalProject management final
Project management finalAidiel Azhar
 
Project 2: Documentation of a Medium-Sized Project
Project 2: Documentation of a Medium-Sized ProjectProject 2: Documentation of a Medium-Sized Project
Project 2: Documentation of a Medium-Sized Projectkimberleyee95
 

Similar to Final Project Management Report (20)

Final Project Management Report
Final Project Management ReportFinal Project Management Report
Final Project Management Report
 
Project management final - KSHV SZ
Project management final - KSHV SZProject management final - KSHV SZ
Project management final - KSHV SZ
 
Final ADP Report
Final ADP ReportFinal ADP Report
Final ADP Report
 
Project management
Project management Project management
Project management
 
Project management report document a medium size project.
Project management report document a medium size project. Project management report document a medium size project.
Project management report document a medium size project.
 
Project 2 report
Project 2 reportProject 2 report
Project 2 report
 
Final Project Management Report
Final Project Management ReportFinal Project Management Report
Final Project Management Report
 
Project management (3)
Project management (3)Project management (3)
Project management (3)
 
Final Project Management Report
Final Project Management ReportFinal Project Management Report
Final Project Management Report
 
Project Management (Individual)
Project Management (Individual)Project Management (Individual)
Project Management (Individual)
 
Finalstudio final report
Finalstudio final reportFinalstudio final report
Finalstudio final report
 
Sem 6 studio report
Sem  6 studio reportSem  6 studio report
Sem 6 studio report
 
Project management Project 2 report
Project management Project 2 reportProject management Project 2 report
Project management Project 2 report
 
Project 2 : Documentation For A Medium-Sized Project
Project 2 : Documentation For A Medium-Sized ProjectProject 2 : Documentation For A Medium-Sized Project
Project 2 : Documentation For A Medium-Sized Project
 
FUNCTION OF THE PERFORMING ARTS STUDENT IN CULTURAL TOURISM IN THE CITY OF BU...
FUNCTION OF THE PERFORMING ARTS STUDENT IN CULTURAL TOURISM IN THE CITY OF BU...FUNCTION OF THE PERFORMING ARTS STUDENT IN CULTURAL TOURISM IN THE CITY OF BU...
FUNCTION OF THE PERFORMING ARTS STUDENT IN CULTURAL TOURISM IN THE CITY OF BU...
 
Santa Monica Civic Center Mixed Use Arts & Cultural District
Santa Monica Civic Center Mixed Use Arts & Cultural DistrictSanta Monica Civic Center Mixed Use Arts & Cultural District
Santa Monica Civic Center Mixed Use Arts & Cultural District
 
CPS Retail EOI 2015 Mar
CPS Retail EOI 2015 MarCPS Retail EOI 2015 Mar
CPS Retail EOI 2015 Mar
 
project management
project managementproject management
project management
 
Project management final
Project management finalProject management final
Project management final
 
Project 2: Documentation of a Medium-Sized Project
Project 2: Documentation of a Medium-Sized ProjectProject 2: Documentation of a Medium-Sized Project
Project 2: Documentation of a Medium-Sized Project
 

More from Ho Yen Liang

ADP FINAL SITE ANALYSIS 2019
ADP FINAL SITE ANALYSIS 2019 ADP FINAL SITE ANALYSIS 2019
ADP FINAL SITE ANALYSIS 2019 Ho Yen Liang
 
Project Management Project 1
Project Management Project 1Project Management Project 1
Project Management Project 1Ho Yen Liang
 
SS2 Local Markets & Community - Food & Culture
SS2 Local Markets & Community - Food & CultureSS2 Local Markets & Community - Food & Culture
SS2 Local Markets & Community - Food & CultureHo Yen Liang
 
Research Proposal for Food and Culture
Research Proposal for Food and CultureResearch Proposal for Food and Culture
Research Proposal for Food and CultureHo Yen Liang
 
Urban Comparative Analysis Essay
Urban Comparative Analysis EssayUrban Comparative Analysis Essay
Urban Comparative Analysis EssayHo Yen Liang
 
Project 1B Synopsis
Project 1B Synopsis Project 1B Synopsis
Project 1B Synopsis Ho Yen Liang
 

More from Ho Yen Liang (6)

ADP FINAL SITE ANALYSIS 2019
ADP FINAL SITE ANALYSIS 2019 ADP FINAL SITE ANALYSIS 2019
ADP FINAL SITE ANALYSIS 2019
 
Project Management Project 1
Project Management Project 1Project Management Project 1
Project Management Project 1
 
SS2 Local Markets & Community - Food & Culture
SS2 Local Markets & Community - Food & CultureSS2 Local Markets & Community - Food & Culture
SS2 Local Markets & Community - Food & Culture
 
Research Proposal for Food and Culture
Research Proposal for Food and CultureResearch Proposal for Food and Culture
Research Proposal for Food and Culture
 
Urban Comparative Analysis Essay
Urban Comparative Analysis EssayUrban Comparative Analysis Essay
Urban Comparative Analysis Essay
 
Project 1B Synopsis
Project 1B Synopsis Project 1B Synopsis
Project 1B Synopsis
 

Recently uploaded

Industrialised data - the key to AI success.pdf
Industrialised data - the key to AI success.pdfIndustrialised data - the key to AI success.pdf
Industrialised data - the key to AI success.pdfLars Albertsson
 
RA-11058_IRR-COMPRESS Do 198 series of 1998
RA-11058_IRR-COMPRESS Do 198 series of 1998RA-11058_IRR-COMPRESS Do 198 series of 1998
RA-11058_IRR-COMPRESS Do 198 series of 1998YohFuh
 
Data Science Jobs and Salaries Analysis.pptx
Data Science Jobs and Salaries Analysis.pptxData Science Jobs and Salaries Analysis.pptx
Data Science Jobs and Salaries Analysis.pptxFurkanTasci3
 
DBA Basics: Getting Started with Performance Tuning.pdf
DBA Basics: Getting Started with Performance Tuning.pdfDBA Basics: Getting Started with Performance Tuning.pdf
DBA Basics: Getting Started with Performance Tuning.pdfJohn Sterrett
 
VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...
VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...
VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...Suhani Kapoor
 
dokumen.tips_chapter-4-transient-heat-conduction-mehmet-kanoglu.ppt
dokumen.tips_chapter-4-transient-heat-conduction-mehmet-kanoglu.pptdokumen.tips_chapter-4-transient-heat-conduction-mehmet-kanoglu.ppt
dokumen.tips_chapter-4-transient-heat-conduction-mehmet-kanoglu.pptSonatrach
 
Call Us ➥97111√47426🤳Call Girls in Aerocity (Delhi NCR)
Call Us ➥97111√47426🤳Call Girls in Aerocity (Delhi NCR)Call Us ➥97111√47426🤳Call Girls in Aerocity (Delhi NCR)
Call Us ➥97111√47426🤳Call Girls in Aerocity (Delhi NCR)jennyeacort
 
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Callshivangimorya083
 
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130Suhani Kapoor
 
How we prevented account sharing with MFA
How we prevented account sharing with MFAHow we prevented account sharing with MFA
How we prevented account sharing with MFAAndrei Kaleshka
 
Schema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfSchema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfLars Albertsson
 
Call Girls In Mahipalpur O9654467111 Escorts Service
Call Girls In Mahipalpur O9654467111  Escorts ServiceCall Girls In Mahipalpur O9654467111  Escorts Service
Call Girls In Mahipalpur O9654467111 Escorts ServiceSapana Sha
 
INTERNSHIP ON PURBASHA COMPOSITE TEX LTD
INTERNSHIP ON PURBASHA COMPOSITE TEX LTDINTERNSHIP ON PURBASHA COMPOSITE TEX LTD
INTERNSHIP ON PURBASHA COMPOSITE TEX LTDRafezzaman
 
Brighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingBrighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingNeil Barnes
 
Consent & Privacy Signals on Google *Pixels* - MeasureCamp Amsterdam 2024
Consent & Privacy Signals on Google *Pixels* - MeasureCamp Amsterdam 2024Consent & Privacy Signals on Google *Pixels* - MeasureCamp Amsterdam 2024
Consent & Privacy Signals on Google *Pixels* - MeasureCamp Amsterdam 2024thyngster
 
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改atducpo
 
Call Girls in Defence Colony Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Defence Colony Delhi 💯Call Us 🔝8264348440🔝Call Girls in Defence Colony Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Defence Colony Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
GA4 Without Cookies [Measure Camp AMS]
GA4 Without Cookies [Measure Camp AMS]GA4 Without Cookies [Measure Camp AMS]
GA4 Without Cookies [Measure Camp AMS]📊 Markus Baersch
 
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...Suhani Kapoor
 

Recently uploaded (20)

VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...
VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...
VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...
 
Industrialised data - the key to AI success.pdf
Industrialised data - the key to AI success.pdfIndustrialised data - the key to AI success.pdf
Industrialised data - the key to AI success.pdf
 
RA-11058_IRR-COMPRESS Do 198 series of 1998
RA-11058_IRR-COMPRESS Do 198 series of 1998RA-11058_IRR-COMPRESS Do 198 series of 1998
RA-11058_IRR-COMPRESS Do 198 series of 1998
 
Data Science Jobs and Salaries Analysis.pptx
Data Science Jobs and Salaries Analysis.pptxData Science Jobs and Salaries Analysis.pptx
Data Science Jobs and Salaries Analysis.pptx
 
DBA Basics: Getting Started with Performance Tuning.pdf
DBA Basics: Getting Started with Performance Tuning.pdfDBA Basics: Getting Started with Performance Tuning.pdf
DBA Basics: Getting Started with Performance Tuning.pdf
 
VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...
VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...
VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...
 
dokumen.tips_chapter-4-transient-heat-conduction-mehmet-kanoglu.ppt
dokumen.tips_chapter-4-transient-heat-conduction-mehmet-kanoglu.pptdokumen.tips_chapter-4-transient-heat-conduction-mehmet-kanoglu.ppt
dokumen.tips_chapter-4-transient-heat-conduction-mehmet-kanoglu.ppt
 
Call Us ➥97111√47426🤳Call Girls in Aerocity (Delhi NCR)
Call Us ➥97111√47426🤳Call Girls in Aerocity (Delhi NCR)Call Us ➥97111√47426🤳Call Girls in Aerocity (Delhi NCR)
Call Us ➥97111√47426🤳Call Girls in Aerocity (Delhi NCR)
 
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call
 
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
 
How we prevented account sharing with MFA
How we prevented account sharing with MFAHow we prevented account sharing with MFA
How we prevented account sharing with MFA
 
Schema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfSchema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdf
 
Call Girls In Mahipalpur O9654467111 Escorts Service
Call Girls In Mahipalpur O9654467111  Escorts ServiceCall Girls In Mahipalpur O9654467111  Escorts Service
Call Girls In Mahipalpur O9654467111 Escorts Service
 
INTERNSHIP ON PURBASHA COMPOSITE TEX LTD
INTERNSHIP ON PURBASHA COMPOSITE TEX LTDINTERNSHIP ON PURBASHA COMPOSITE TEX LTD
INTERNSHIP ON PURBASHA COMPOSITE TEX LTD
 
Brighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingBrighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data Storytelling
 
Consent & Privacy Signals on Google *Pixels* - MeasureCamp Amsterdam 2024
Consent & Privacy Signals on Google *Pixels* - MeasureCamp Amsterdam 2024Consent & Privacy Signals on Google *Pixels* - MeasureCamp Amsterdam 2024
Consent & Privacy Signals on Google *Pixels* - MeasureCamp Amsterdam 2024
 
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
 
Call Girls in Defence Colony Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Defence Colony Delhi 💯Call Us 🔝8264348440🔝Call Girls in Defence Colony Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Defence Colony Delhi 💯Call Us 🔝8264348440🔝
 
GA4 Without Cookies [Measure Camp AMS]
GA4 Without Cookies [Measure Camp AMS]GA4 Without Cookies [Measure Camp AMS]
GA4 Without Cookies [Measure Camp AMS]
 
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
 

Final Project Management Report

  • 1. FINAL PROJECT MANAGEMENT REPORT The Social Album, City Lobby A Documentation of A Medium-Sized Project Tutor: Ar. Sateerah Hassan Ho Yen Liang 0326660 1
  • 2. 1.0 Project Introduction / 3 1.1 Project Brief 1.2 Project Objectives 1.3 Project Goals 1.4 Organisation Structure 1.5 Client & Stakeholders 2.0 Site Information & Studies / 6 2.1 Site Introduction 2.2 S.W.O.T Analysis 2.3 PESTLE Analysis 3.0 Project Viability / 26 3.1 Programme Viability 3.2 Design Suitability 3.3 Schedule of Accommodation - Tabulation of Spaces 3.4 Economic Feasibility - Budget Calculation 4.0 Project Procurement & Resource Planning / 91 4.1 Procurement Process 4.2 Resource Planning Content 2 5.0 Risk Analysis & Management / 96 5.1 Risk Analysis 6.0 Project Delivery / 6.1 Success Criteria 6.2 Work Breakdown Structure (WBS) 6.3 Gantt Chart
  • 3. 1.0 Project Introduction: The Social Album 1.1 Project Brief The proposed project calls for designing a ‘City Lobby’, which will engage and re-engage the city’s local population and visiting tourists from other towns or countries. A quality public place and building where its architecture can create great opportunities to build and strengthen the people’s connection. The project addresses earlier studies and researches on the socio-cultural issues related to the architecture of Johor Bahru, namely: Ethnicity (segregation of multi-racial community), Demography (segregation based on age and social status) and Identity (urban landscape is homogenous and contiguous). 1.2 Objectives The City Lobby is used as a gathering place for people in the city and it offers a wide range of disparate activities, which can be non-to-profit type. ● To promote the common interests or ‘neutral spaces’ of the public where specific dialogues and activities are encouraged and expected to happen. ● To showcase cultural events, public activities, recreational activities and public programmes which is not present in the popular weekend destinations for locals and tourists such as theme parks and urban lifestyle centres. 1.3 Goals ● To create a platform for collaboration between different age classes, interests and social background to create a healthy environment for appreciation of difference and similarities. ● To provide healthy interaction between local city dwellers, tourists, visitors and transient users. ● To allow people to stamp their own identity leading to ‘personalization’ of the space and the place ● To blur the boundary between the division of the multicultural communities on site. ● To celebrate the diversity of multicultural coexistence of Johor Bahru, expressing the spirit of “Bangsa Johor”. 3 1.0 Project Introduction Figure 1.1.1 Aerial View to Site (Ho, 2019)
  • 4. 1.4 Organisation Structure 1.4.1 Project Team Client: Johor Bahru City Council, also known as Majlis Bandaraya Johor Bahru (MBJB) Consultants:- ● Architect: HOArchitects Sdn Bhd. ● Civil & Structural Engineer: CYS Jurutera Sdn Bhd. ● Mechanical & Electrical Engineer: Perunding BCP Sdn Bhd. ● Quantity Surveyor: Alpha Omega Matrix Sdn Bhd. ● Landscape Architect: HODA Design Sdn Bhd. ● Interior Designer: J&V Interior Design Sdn Bhd. Lead Consultant HOArchitects Sdn Bhd. Main Consultants Contractors Architect HOArchitects Sdn Bhd. M&E Engineer Perunding BCP Sdn Bhd. Landscape Architect HODA Sdn Bhd. C&S Engineer CYS Jurutera Sdn Bhd. Quantity Surveyor Alpha Omega Matrix Sdn Bhd. Interior Designer J&V Interior Design Sdn Bhd. Figure 1.4.1 Organization Chart of Project (Ho, 2019) Main Contractor Sub-Contractor 4 Client (Johor Bahru) MBJB Main Consultants 1.0 Project Introduction Specialists Suppliers
  • 5. 1.5 Client & Stakeholders 1.5.1 Client Majlis Bandaraya Johor Bahru (MBJB) Majlis Bandaraya Johor Bahru or Johor Bahru City Council (MBJB) is a local authority which administers Johor Bahru city centre. MBJB are responsible for 12 major roles, and two of them are fostering a stronger sense of community and sustaining the environmental quality of Johor Bahru landscape. Therefore, the city lobby project is proposed to be a community-based project which MBJB has the opportunity to achieve their roles and objectives. 1.0 Project Introduction 5 Jabatan Kebudayaan & Kesenian Negara (JKKN) JKKM aims to plan and coordinate art and cultural activities in the city lobby by promoting local arts and crafts development on site. Their main role is to encourage the growth of arts and cultural activities through effective collaboration between arts and cultural organizations, government agencies, non-governmental organizations and arts and cultural activists from within and outside the country. Ministry of Tourism, Art & Culture Malaysia (MOTAC) MOTAC is responsible to preserve and promote the art and culture of Johor Bahru as well. The organization helps with providing conducive infrastructure for arts and culture and advisory services to the Johor Bahru community. ThinkCity A community-focused urban regeneration organisation that aims to create better, more sustainable cities in Malaysia by supporting community-driven initiatives through the public grants programme. ThinkCity will be proposing some of the innovative work spaces in the city lobby to encourage different communities to experience the co-working environment as a community sharing initiative. 1.5.2 External Stakeholders Senso Art Gallery & Cafe Senso Art Gallery is a gallery owned by Ms. Katherine, located at Jalan Tan Hiok Nee, it is a art platform for the local artists and crafters to display their work and also there is art workshops for public to take part in. Thus, Senso will be providing an art studio for anyone who is interested in local arts and crafts activities to use the space. Persatuan Hainan Johor Bahru Persatuan Hainan Johor Bahru is an organization responsible to preserve and promote the Chinese heritage of the town, their mainly responsible for documenting the historical artifacts and proposing seasonal cultural activities on site. The information lobby and archiving library would be funded by the organisation to promote the heritage and cultural values of Johor Bahru.
  • 6. 2.1 Site Introduction The project is located at the City of Johor Bahru, one of Malaysia’s premier city and urban destination because of its highly modernized infrastructure. Based on the current feel of the place, Johor Bahru City can be both busy at day and night time. The site sits among four streets, which are Jalan Trus, Jalan Tan Hiok Nee, Jalan Dhoby and Jalan Segget. The site is a vibrant town, heavily emphasizing on the food, art and market (Bazaar Karat) cultural aspects. It can be observe that the old shophouse typology are enveloped within the new taller developments that shades the lower buildings below. Both coexist at the same place, cultured at different time. The activities differ by time by expanding the usage of the streets. Morning where people stroll through the pedestrian walkway, while at night the gathering of people beside the stalls in Bazaar Karat. This transition of time shows prominent differences of assembling and dispersing of people during different time zones daily. 6 2.0 Site Analysis Figure 2.1.1 Site Plan (Ho, 2019) 2.0 Site Information: Johor Bahru Heritage Town ● Total Land Area: 3335.5 m2 ● Plinth area : <60% Including car parks, walking pavement, loading bay, rubbish collection, & utilities ● Setback: -Front: 6m + 2m (greenery) -Sides and back: 6m ● Height control: ≤4 storeys ● Parking requirement: (site area - 30% for utilities) ÷ standard size of carpark lots = 30 parking lots
  • 7. 2.2 S.W.O.T Analysis 7 ● High permeability and accessibility by vehicular and foot to site. ● Variety and diverse of socio-cultural and historical value on site. ● Greeneries and high rises shades the site, providing comfort to users. ● Public or open spaces are left unused and attracts homeless people to utilise. ● High rises around the site has shadowed the fine grain shophouses on site, creating visual barrier. ● Time gap on site where there is no activities happening during the evening session ● Lost interest on the culture of the mundane town ● Promoting cultural awareness whilst preserving the historical and socio-cultural value on site. ● Celebrating the vibrancy and diversity on site through providing a platform for people to collaborate and connect. ● The increase presence of homeless people may caused a high risk of security on site ● Presence of illegal parking on site affect the traffic flow and safety of pedestrians ● Division between the multicultural communities due to misinterpreted boundaries and understandings WeaknessStrength Opportunity Threat 2.0 Site Analysis
  • 8. 2.3 PESTLE Analysis 8 The proposed scheme has the intention to encourage positive engagement between the local dwellers, the tourists and transient users, therefore the collaborative and cultural activities are introduced and initiated through some of the government agencies, like Jabatan Kebudayaan & Kesenian Negara (JKKN) and Ministry of Tourism, Art & Culture (MOTAC). Bazaar Karat is also administered by the client MBJB and any morning or night market activities introduced in the scheme should be liaised with the client. Some of the proposed programmes like the artisan retail spaces and art gallery are funded by the external stakeholder Senso Art Gallery Cafe, offering to provide a platform for artist to showcase their work. The archive library and information lobby will also be funded by the Persatuan Hainan Johor Bahru, which initiated the heritage museum of the site itself. Some of the shophouses on site are purchased by Singaporeans but they are left vacant and unused. The heritage site is rich in cultural activities expressed in the form of food, artisan crafts, exhibitions and a mix of all above. Bazaar Karat, the open street market and live performances at night such as street busking helps brighten up the site. The development of urban infrastructure is on a fast paced track, aligning their growth triangle with Indonesia and Singapore, ensuring the strong connections and trade on both sides. The city is one of the fastest-growing cities in Malaysia after Kuala Lumpur due to its modernized infrastructure. The proposed building setback to be 8m along the street Jalan segget, and 6m along other sides. 10% greeneries must be included for the surrounding landscape and minimum 30 parkings to be provided. There are other law enforcement such as Night/Day Markets (MBJB) By-Laws 2003 to make sure the vendors for the night market or bazaar comply to the requirements from the authority. The Heritage Walk of Jalan Tan Hiok Nee cannot be demolished or build any high-rise buildings that will affect the condition of the site. The well-paved roads on cultural streets allowed a comfortable walking experience. The ongoing urban planning strategies proposed by ThinkCity to rejuvenate and pedestrianise Jalan Dhoby to enhance pedestrian connectivity to the cultural street, Jalan Tan Hiok Nee. The alleys are rejuvenated into vibrant paths via mural art and streetscapes lighting. Most importantly the streets are well shaded with greens. Politic Economic Sociological LegalTechnology Environment 2.0 Site Analysis
  • 9. 3.1 Program Viability The city lobby played a role in fostering a symbiotic relationship called interdependency, between the multiracial community through creating permeable boundaries, which allowed people to communicate, collaborate and connects. 9 3.0 Project Viability Figure 3.1.1 Conceptual Diagrams (Ho, 2019) 3.0 Project Viability Communicate Connect Collaborate Design articulation of spaces revolved around a ‘common ground’ for the communities to share, shared spaces of common interests articulate through path-space relationship and overlapping of spatial identities. It’s the foundation of the unintentional meetups with different people of different cultural background, and that the spaces could house a sharing atmosphere of local city dwellers, tourists, visitors and transient users. The programmatic spaces overlapped each other to form shared spaces of the city lobby. These shared spaces are articulate through the in-between spaces like courtyards, pocket and breakout spaces and collaboratories.
  • 10. 3.2 Design Suitability 10 3.0 Project Viability 3.2.1 Contextual Response The design of the city lobby takes into consideration of the site itself being entitled as the heritage site of Johor Bahru Old Town. The site has an enriching blend of food, art and market culture, with a multicultural community locating at the heart of the town. The city lobby responses to the issue regarding human and cultural aspect, which are the lack of human activities due to the cause of a time gap issue; the lack of authenticity due to the tourism economic culture on site; and lastly lacking a proper platform and common ground for the locals to express their artistic sensibilities. TIME GAP? Figure 3.2.1 Contextual Intangible Elements (Ho, 2019) Figure 3.2.2 Temporal Study of Different Communities at Kin Hua Kopitiam (Ho, 2019) TIME GAP?
  • 11. 3.2 Design Suitability 11 3.0 Project Viability 3.2.2 Programmatic Response - Social Feasibility The programs proposed in the city lobby are mostly food, art and market based activities and events as these three aspects has the most prominent identity of the Johor Bahru heritage town. These objectives of these programs are suitable for different ethnic group at all ages as they allow the engagement of the people from this diverse community. The visitors get to experience and engage with different age group via different programmatic aspects and common spaces provided for these various user groups to come together to have fun and interact with each other which subsequently will diminish the intangible barrier between the people of Johor Bahru, achieving the infamous “Bangsa Johor” concept. Figure 3.2.4 Programmatic Diagram of Local Public Spaces & Events in Johor Bahru (Ho, 2019) Figure 3.2.3 Programmatic Aspects of the City Lobby - The Social Album (Ho, 2019)
  • 12. 3.3 Schedule of Accommodation - Tabulation of Spaces 12 3.0 Project Viability Floor Gross Floor Area (m²) Basement Floor 2108.7 Ground Floor 1650.8 First Floor 696.5 Second Floor 843.9 Third Floor 521.4 Total 5821.3 3.3.1 Economic Feasibility - Budget Calculation 5821.3m² = 62660 ft² Estimated construction cost at RM 200 per sqft, Gross construction cost = 62600 X RM 200 = RM 12,532,000 Consultant fee at 10% of construction cost = RM 12,532,000 X 10% = RM 1,253,200 Table 3.3.1 Gross Floor Area Tabulation (Ho, 2019) Contribution Fees for TNB & IWK (5%) = RM 12,532,000 X 5% = RM 626,600 Contingency of budget (5%) = RM 12,532,000 X 5% = RM 626,600 Total Estimated Building Cost = RM 12,532,000+ RM 1,253,200 + RM 626,600 + RM 626,600 = RM 15,038,400 3.3.2 Technical Feasibility The construction method used for the city lobby will be reinforced concrete (RC) slab and steel post and beam construction. The construction will be featuring a few steel columns which protrude out from the basement, to allow natural daylight into the basement space, and supporting the large overhangs of the building, also representing the three communities of the site itself. The facade will be constructed with U Channel Glass Profile, which are very durable and it can be self-supported without any external framing. The glass will be manipulated with different openings to allow adequate natural daylighting into the building. The configuration of the U Channel Glass will be arranged in a double-glazed pattern to block direct sunlight from the West Sun during the evening. 3.3.3 Legal Feasibility The proposed building fully comply the legal requirements as stated within the Uniform Building By-Law 1994 (UBBL) and the guidelines provided from Majlis Perbandaran Johor Bahru (MBJB). The proposed building is sat in between a row of shophouses and a high rise public bank. Since the building is facing Jalan Segget, Jalan Dhoby, Jalan Trus and Jalan Tan Hiok Nee, which has a pedestrianised pavement wider than a five foot walkway, the setback of the building follows according to this. Besides, fire escape with a dead-limit of not more than 30m is provided, as well as adequate lighting and ventilation to floor area ratio is adopted. There are 30 parking, 2 disabled parking and services provided on the lower ground floor of this building as the decision of creating a basement is omitted. The building also comply to the MS 1525 and MS 1184 (disabled) guideline.
  • 13. 13 4.0 Project Procurement & Resource Planning 4.0 Project Procurement & Resource Planning 4.1 Procurement Method Public Works Department Method (P.W.D Form of Contract 203/203A) As well as referred as Jabatan Kerja Raya (JKR). PWD is the federal government department in Malaysia under Ministry of Works Malaysia (MOW) which is responsible for construction and maintenance of public works in Malaysia. 4.1.1 Procurement Suitability Majlis Perbandaran Johor Bahru (MBJB) acts as the government agency on behalf of the goods, services and construction acting as a public authority. As the City Lobby aims to serve for the public for communal and cultural activities, PWD is the most suitable form of contract as the client is represented under a government body despite it being a medium scale project. Objective of Using this Method : ● To ensure the realization of policies and deliver services through smart partnership strategy. ● To ensure consistency in services it procures, JKR established processes and systems that must be adhered to by contractors. Contract Conditions : ● Contractor allowed to claim contract period extension for various circumstances deemed the government’s risks. ● Majority funded by contractor - as is a separation between the construction and design team,therefore contractor holds most responsibility. ● No retention money is withheld from payments. ● Bill of payment are in a lump sum. P.W.D Form of Contract 203/203A (Revised 2007) These are the traditional forms of contract based on drawings and specification (203) or bill of quantities (203A) produced for use in public sector or government projects in both building and engineering contracts. In this latest 2007 version remains where it said majority of the risk has been transferred to the contractor. PWD 203A Standards Form of Building Contract is in use at many public project where the government is the main client.
  • 14. 4.2 Resource Planning No. Task/ Deliverables Resource Types Quantity Skills Required Equipment/ Medium A. Schematic Design 1. Site Visit and Survey Client, Consultants, Land Surveyor Site Observation and Analysis done with professional analytical results or conclusion Manual Tools and Equipment for Site Analysis 2. Site Documentation & Analysis Client, Consultants 3. Conceptual Sketches Architect 1 - 4. M&E and Landscape Planning M&E Engineer, Landscape Architect 2 Ability to plan mechanical and electrical connection; landscape to plan according to the site context Proficiency in using digital softwares such as Autodesk CFD, AutoCAD, ArcGIS, Revit 5. Cost Estimation Quantity Surveyor 1 Taught individual in producing cost estimation schedules and able to preparare of Bill of Quantities Skilled Microsoft Excel user in producing spreadsheets of schedules 6. Visualization Architect, Draftsmen 1,2 Able to showcase the overall form, appearance and visualisation of the 3-Dimensional model of the building Any modelling software, for example, Autodesk Revit, AutoCAD 4.0 Project Procurement & Resource Planning 14
  • 15. No. Task/ Deliverables Resource Types Quantity Skills Required Equipment/ Medium 2. Design Development 1. Detailed Design Drawings Architect, Draftsmen 1,2 Able to produce all submission drawings to authority (MBJB) to get building approval Skilled profession to use digital drawing tool that can produce proper detailed drawings like Autodesk AutoCAD 2. Detailed Project Budget Quantity Surveyor 1 Continuation of producing the all cost with detailed schedule Using Microsoft Excel to produce schedules and cost calculation 3. Local Authority Submission Architect 1 Liaise with different departments of authority in MBJB in submission of drawings Printouts of submission drawings to requirement of MBJB 3. Contract Documentation 1. Preparation of Bill of Quantities Quantity Surveyor 1 Required skills and knowledge in producing Bill of Quantities Using the software of WinQS, Microsoft Excel 2. Tender Period (Open Tender) Architect, Project Manager 2 3. Tender Evaluation Client 4. Award of Contract Architect 2 Certified architect to award the contractor the official letter of award to the contractor Microsoft Word 4.0 Project Procurement & Resource Planning 15
  • 16. No. Task/ Deliverables Resource Types Quantity Skills Required Equipment/ Medium 4. Contract Implementation 1. Initial Project Meeting Client and all parties are involved - - Ability to communicate effectively and efficiently - Ability to solve issues effectively and promptly - Experienced in site and personnel management - 2. Monitor on Site Work & Construction Progress Architect 1 - - 3. Monitor Civil Works on Site Civil Engineer 1 - - 4. Monitor Structural Works on Site Structural Engineer 1 - - 5. Monitor M&E Works on Site Mechanical & Electrical Engineer 2 - - 6. Monitor Landscape Works on Site Landscape Architect 1 - - 7. Monitor on Site Works Site Manager & Clerk of Work 2 - - 8. Conduct On Site Construction Work Contractor & Site Workers 2 - - 9. Inspection of Building Services on Site Works Facilities Manager 1 - - 4.0 Project Procurement & Resource Planning 16
  • 17. No. Task/ Deliverables Resource Types Quantity Skills Required Equipment/ Medium 5. Final Completion (Handing Over) 1. Testing, commissioning and Inspection Client and all parties are involved. - - - 2. Issuance of CCC Architect 1 Certified architect to issue the CCC Certificate to the consultants and contractor Using the software of Microsoft Word or Adobe PDF 3. Preparation of Final Account Architect, Quantity Surveyor 2 Certified architect to issue the consultant final account (contractor) and contractual final account (closing file) Using the software of Microsoft Excel 4.0 Project Procurement & Resource Planning 17
  • 18. 5.1 Risk Analysis Risk Likelihood Severity Impact Mitigation Strategy Contingency Plan Client reduces budget without warning Medium Low/Medium Minor changes such as the material choice to major changes such as project scope. Create several design options that vary in scope and materials. Meet with client to discuss the possibilities to raise funds to meet objectives. Client frequently changes design High Low/Medium Change in quality, delays in construction and planning. Ensure constant communication between consultants and clients to prevent miscommunications. Utilize contractual agreements to prevent changes in design. Change in government Low Medium/High Possibility of cancellation of project or change in scope. Publicly emphasize the apolitical nature of the project and highlight its benefit to the nation regardless of politics. Meet with the leaders of the new government to persuade them of the merits of the proposal. Client loses faith in experimental programmes Medium Medium/High Change in scope to outright the cancellation of project. Hosts prior events to showcase the viability of the programmes. Compromise and present a more familiar programmes. Site users demonstrates and show displeasure at proposed development Low Medium/ High Change in scope to outright the cancellation of project. Hosts talks and discussions to persuade and change public’s conception. Appeal to the greater good of the nation. 5.1.1 Pre- Construction Phase 5.0 Risk Analysis & Management 5.0 Risk Analysis & Management 18
  • 19. Risk Likelihood Severity Impact Mitigation Strategy Contingency Plan Error in installation Low Low/ High Construction will be on hold leading to project delay. PM should delegate a task for quality check to ensure no error happen throughout the construction phase. Make regular visits on site to check on the updated progress. Change in design Low Medium/High Delays in construction process, destruction of design vision, and violation of contractual agreement. Ensure contract agreed limits and controls the amount and scope of changes. Utilize legal means to ensure design is not unnecessarily changed. Construction related accidents involving the public Medium Medium/High Corrodes public sentiment and support for the project, which can lead to project cancellation. Ensure strict adherence to safety standards as set by law. Personally visit and impact site to ensure compliance and utilize legal means if necessary. Insufficient storage on site for building materials Medium Medium/High Authorities can get in the way to stop the operation on site . Ensure that storage size is capable enough to hold enough materials. 5.1.2 Construction Phase 5.0 Risk Analysis & Management 19 Risk Likelihood Severity Impact Mitigation Strategy Contingency Plan The programmes do not attract the targeted user according to plan Low Medium/High With the lack of attraction from the users, the building will be shut down and put up for sale. Have multiple programmes and neutral spaces to give variety of options to the user. Poor maintenance of facilities Medium Medium/High The unmaintained and unpleasant look will prevent users from going into the building. To have maintenance strategy for each possible elements. 5.1.3 Building Operation Phase
  • 20. 6.1 Success Criteria 6.0 Project Delivery 20 A project’s success criteria refers to measurable terms of what should be the outcome of the project that is acceptable to the end user, customer and the stakeholders. Thus, Melwood, OnePark project team emphasises on three main objectives that they aim to achieve throughout the project phases, including the quality of work, being on time and keeping within budget to ensure client satisfaction and a smooth workflow. This triangular model circulates and form a conclusion which is the quality of the project. In certain projects, priorities may be given to two out of the three parameters, especially relating to the cost and time. This would cause an imbalance of the triangular model, affecting the quality of the project managed. SCOPE TIME COST The scope of the project depends on the amount of work that needs to be done to complete the project. 1) Using the WBS to outline and define the scope of work. 2) Visualizing the duration and quantity of work with the aid of the Gantt Chart. 3) Coordinating meetings between consultants and clients to update on the project scope. 4) Minimizing changes during construction phase towards the design 5) Decreasing risk factor of failing project and proper management of construction. 6) Design to achieve the requirements (progress, standards, finance, and time) The time frame to complete the project within the estimated 35 months which is starting from December 2019 to October 2022. 1) Using the Gantt Chart to plan out the time frame and to highlight the critical periods of the project. 2) Adhering to the workflow programme to complete tasks to ensure that there is no delay which will affect the critical path. The total estimated cost for the completion of the project is RM 15,038,400. 1) Using a proper fee planning structure to ensure that the project is completed within the budget. 2) The consideration of materials to be done according to the project budget while ensuring a quality selection. 6.0 Project Deliveries
  • 21. 6.2 Work Breakdown Structure (WBS) The Social Album, Johor Bahru City Lobby Pre-construction stage Post-Construction stage Construction Stage - Contract Administration & Implementation Stage 1.1 Inception - Site Studies 1.1.1 Client Briefing 1.1.2 Design Requirements 1.1.3 Site Investigation 1.1.4 Feasibility Studies 1.2 Schematic Design 1.2.1 Soil Investigation 1.2.2 Conceptual Sketches 1.2.3 Spaces Planning 1.2.4 M&E Planning 1.2.5 Landscape Planning 1.2.6 Material Proposal 1.2.7 Design Visualization 1.2.8 Cost Estimation 1.3 Design Development 1.3.1 Detailed Design Drawings 1.3.2 Detailed Landscape Drawings 1.3.3 Authority Submission 1.3.4 Revised Cost Estimate & Project Schedule 1.4 Contract Documentation 1.4.1 Tender Documentation 1.4.2 Tender Review & Award 1.4.3 Project Planning & Schedule 1.4.4 Stakeholder Notification 2.1 Preliminary 2.1.1 Mobilization & Site Establishment 2.1.2 Dilapidation Survey 2.1.3 Setting Out 2.2 Foundation 2.2.1 Land excavation 2.2.2 Piling & Footing 2.2.3 Basement Slab & Wall 2.3 Superstructure 2.3.1 R.C. Slab & Landing 2.3.2 R.C. Beam, Column & Flooring 2.3.3 Internal & External R.C Wall 2.3.4 Lift & Fire Staircase 2.3.5 U Channel Glass Wall - Facade 2.3.6 Glass Curtain System 2.4 Roofing 2.4.1 Roof Construction 2.4.2 Gutter & Drainage System 2.5 M&E Services Installation 2.7.1 Fire Protection System 2.7.2 M&E Fixture Installations 2.7 External & Landscape 2.7.1 Surface Water Drainage 2.7.2 External M&E Work 2.7.3 Installation of Softscape & Hardscape 2.7.4 Turfing 2.7.5 Outdoor Lighting 2.6 Architectural Finish 2.9.1 Door & Window Frame & Panels 2.9.2 Tiling Works 2.9.3 Wall, Ceiling & Floor Finishing 2.9.4 Staircase & Handrail Finishing 3.1 Final Completion 3.1.1 Final Clearing & Testing 3.1.2 Inspection 3.1.3 Issuance of Certificate of Practical of Completion (C.P.C) 3.1.4 Issuance Certificate of Completion & Compliance (C.C.C) 3.1.5 Issuance of Certificate of Making Good Defects (C.M.G.D) 3.1.4 Preparation of Final Accounts of Contract 21 6.0 Project Deliveries
  • 22. 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 PRE-CONSTRUCTION STAGE 1. Schematic Design Phase 1.1 Project Briefing 1 1.2 Site Visit 1 1.3 Site Investigation 1 1.4 Soil Investigation 3 1.5 Feasibility Studies 1 1.6 Spatial Planning & Tabulation 1 1.7 Preliminary Design Proposal 2 1.8 Building Structure Proposal 2 1.9 Building Services Proposal 2 1.10 Landscape Design Proposal 2 1.11 Initial Estimation Cost 2 1.12 Planning Submission for DO Authorities 4 1.13 DO Authority Submission for Town Planning Approval 12 2. Design Development Phase 2.1 Detailed Architectural Drawings 20 2.2 Detailed Civil & Structure Drawings 18 2.3 Detailed M&E Drawings 18 2.4 Detailed Landsacpe Drawings 8 2.5 Pre-tender Cost Estimation 4 2.6 Building Plans Submission to MBJB 15 2.7 Other Authotities Submission 2.7.1 Passive Bomba 6 2.7.2 Active Bomba 6 2.7.3 Syarikat Air Johor 3 2.7.4 Road & Drains 3 2.7.5 IWK 3 2.7.6 Earthwork (Jabatan Kejuruteraan) 3 2.7.7 Multimedia 2 2.7.8 Streetlighting 2 2.7.9 DOE 2 2.7.10 Pos Malaysia 2 2.7.11 Transport (carpark) 2 2.7.12 Heritage 2 2.7.13 Landscape 2 3. Contract Documentation Phase 3.1 Finalize & Complete Architectural Tender Drawings 10 3.2 Complete Structural Tender Drawings 8 3.3 Complete M&E Tender Drawings 8 3.4 Tender Estimate 6 3.4 Preparation of Bill of Quantities 4 3.5 Call Tender 1 3.6 Tender Period 4 3.7 Opening of Tender 1 3.8 Review & Evaluation 4 3.9 Tender Report & Recommendation 3 3.10 Client's Approval & Award 2 CONSTRUCTION STAGE 4. Contract Implementation Phase 4.1 Preliminaries 4.1.1 Site Handover 1 4.1.2 Mobilization 3 4.1.3 Site Clearing & Levelling 2 4.1.4 Building setting out 1 4.2 Substructure 4.2.1 Excavation 4 4.2.2 Piling 10 4.2.3 RC Retaining Wall 4 4.2.4 Basement Columns, Beams & Slabs 12 4.2.5 Ramps 2 4.2.6 Lift pit 2 4.3 Superstructure 4.3.1 Beams 16 GF 1F 2F 3F 4.3.2 Columns 16 GF 1F 2F 3F 4.3.3 Slabs 16 GF 1F 2F 3F 4.3.4 Walls & Openings 16 GF 1F 2F 3F 4.3.5 Concrete Roof Slab, Steel Roof Truss & Corrugated Metal Decking 14 4.3.6 Installation of Gutter & Drainage System 2 4.4 Services Installation 4.4.1 Active Fire Protection Systems 12 4.4.2 M&E Fixtures Installations 12 4.5 Architectural Finishes 4.5.1 Door & Window Panels 4 4.5.2 Ceiling, Wall & Floor Finishes 4 4.5.3 Built-In Installation Works - Furnitures 8 4.6 Landscaping & Civil works 4.6.1 External Landscaping Works 12 4.6.2 Road & Drainage Works 12 POST-CONSTRUCTION STAGE 5.0 Final Completion Phase 5.1 Testing and commissioning 4 5.2 Cleaning 2 5.3 Inspection by consultants 2 5.4 Pre-CCC inspection by authorities (clearance letters) 2 5.5 Certifying as built drawings, warranties and guarantees, etc. 8 5.6 Issuance of CPC 1 5.7 Issuance of CCC 1 5.8 Defects Liability Period (Handing Over) 96 (2years) 5.9 Issuance of CMGD 1 5.9 Final Accounts Certificate 2 6.3 Gantt Chart 2019 Dec Jan FebTask/Deliverables Duration (Weeks) 2020 Mar Apr May June July Aug Oct Nov Dec Aug Sep Oct Oct 2 Years 20242021 Mar Apr May June 2022 Sep Aug Sep JulyOctJan Mar Apr May JuneJuly Nov Dec Jan FebFeb DOApproval BPApproval LetterofAward IssuanceofCPC IssuanceofCCC FinalAccountCertificate