SlideShare a Scribd company logo
1 of 13
Destressing of LWR
Definition
• Destressing is the operation undertaken with or without rail
tensor to secure stress free conditions in the LWR/CWR at the
desired/specified rail temperature.
• Destressing Temperature (td) is the average rail temperature
during the period of fastening the rails to the sleepers after
destressing LWR without the use of rail tensor.
• Range of td :-
o Temperature zone I,II,III
i) All sections tm to tm + 5C
o Temperature zone IV
i) 52kg & heavier tm+5C to tm+10C
ii) Others tm to tm+5 C
Need for destressing?
1) On initial laying of LWR
2) During maintenance of LWR
i) Gaps at SEJ
a) Gap between the reference mark and tongue rail
tip/stock rail corner at various rail temperatures
shall not differ by more than +/- 10 mm from
the theoretical range as shown in Annexure-V
b) Gap exceeds maximum designed gap of SEJ
c) Tongue/Stock rail crosses mean position
Need for destressing?
ii) After special track maintenance operations
namely TFR, D/S, Lifting of track, major
reliagnment of curves, TSR etc.
iii) After restoration of track following an
unusual occurance namely rail fracture,
buckling, accidents, breaches etc
iv) If number of repairs where temporary repairs
have been done exeed 3 per km
Need for destressing?
3) If rail temp is likely to fall outside td+10 & td-
20 C during special maintenance activities like
D/S, TSR, lifting etc then 1 round of temporary
destressing is essential
Practice
• Once in 3 years, all LWRs shall preferably with
destressed.
LWR destressing operation
• Under supervision of JE/SSE Pway during traffic
block of adequate duration at appropriate rail
temperature
• SR of 30 kmph before traffic block shall be availed
to loosen rail fastenings on alternate sleepers
• Impediments to free movement of rail shall be
removed such as rail anchor, guard rail, check rail
etc
• During destressing operation, rail is required to
be lifted and placed on rollers at every 15th
sleeper to permit free movement of rail
LWR destressing operation
• During destressing following activities shall
also be done:-
a) Fitting renewal namely damaged rubber pad,
ERC, liners.
b) Shifting of liner biting zone shall be done,
wherever required
c) Greasing on leg of pandrol clip ,inside of
inserts, below liners & liner sealing
d) LC overhauling
Destressing methods
• Without tensor
o Conventional practice
o Do not require skilled supervision
o Can be used only tp is within range
• With tensor
o Used when prevailing temperature tp is below to
o Require skilled supervision, more number of supervisors
o More block time is required
Procedure (without tensor)
• Approximately 1 km patch of LWR is
destressed in single block of 2/2.5 hrs which
involves 2-3 welds. Minimum 30-40 nos
labour, 2 supervisors required during block
• Pre block activities:-
o SR of 30 kmph is imposed
o ERCs are removed every alternate sleeper
o LC check rail is removed if any LC is coming in
destressed portion
Procedure (without tensor)
• Cut is made in central portion and rails made out of
alignment to permit free expansion/contraction.
• Fittings are unfastened from centre cut towards LWR
on either side with placing of rollers on every 15th
sleeper & tapping with wooden hammer to facilitate
free movement of rail
• Fastening is then started from either side of LWR
portion towards central cut.
• If less than 2.5 hours block is permitted then welds are
not done during this block & caution persists till next
block is granted.
Procedure (with tensor)
• Para 5.7.3 of LWR manual
THANKS

More Related Content

What's hot

Signalling and Interlocking
Signalling and InterlockingSignalling and Interlocking
Signalling and Interlockingsrinivas2036
 
SCHEDULE OF DIMENSIONS.ppt
SCHEDULE OF DIMENSIONS.pptSCHEDULE OF DIMENSIONS.ppt
SCHEDULE OF DIMENSIONS.pptzubersana
 
Station and Yards in Indian Railway
Station and Yards in Indian RailwayStation and Yards in Indian Railway
Station and Yards in Indian RailwayArbaz Kazi
 
MODULE-I INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-I INFRASTRUCTURE ENGINEERING BTCVC702MODULE-I INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-I INFRASTRUCTURE ENGINEERING BTCVC702Dr. BASWESHWAR JIRWANKAR
 
modern methods of railway track maintanence
modern methods of railway track maintanencemodern methods of railway track maintanence
modern methods of railway track maintanencekrishnacp
 
cc ppt Transportation engg poly unit 4(4)
cc ppt Transportation engg poly unit 4(4)cc ppt Transportation engg poly unit 4(4)
cc ppt Transportation engg poly unit 4(4)Coomarasamy Chidambaram
 
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...Hossam Shafiq I
 
highway engineering
 highway engineering highway engineering
highway engineeringGowtham Raja
 
Railway signalling
Railway signallingRailway signalling
Railway signallingkarthikdishu
 
Stations and Yards of Railway
Stations and Yards of RailwayStations and Yards of Railway
Stations and Yards of RailwaySouvik Mondal
 
Wind Rose.pdf
Wind Rose.pdfWind Rose.pdf
Wind Rose.pdfWhUllahWa
 
Maintenance & repair of steel bridges
Maintenance & repair of steel bridgesMaintenance & repair of steel bridges
Maintenance & repair of steel bridgesnaveen kumar
 
Monorail vs Metrorail
Monorail vs MetrorailMonorail vs Metrorail
Monorail vs MetrorailSuresh7862
 
11.track junctions and layouts
11.track junctions and layouts11.track junctions and layouts
11.track junctions and layoutsMani Vel
 
chapter-4 Railway Station.pptx
chapter-4   Railway Station.pptxchapter-4   Railway Station.pptx
chapter-4 Railway Station.pptxMamushLeta
 

What's hot (20)

Signalling and Interlocking
Signalling and InterlockingSignalling and Interlocking
Signalling and Interlocking
 
SCHEDULE OF DIMENSIONS.ppt
SCHEDULE OF DIMENSIONS.pptSCHEDULE OF DIMENSIONS.ppt
SCHEDULE OF DIMENSIONS.ppt
 
Station and Yards in Indian Railway
Station and Yards in Indian RailwayStation and Yards in Indian Railway
Station and Yards in Indian Railway
 
MODULE-I INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-I INFRASTRUCTURE ENGINEERING BTCVC702MODULE-I INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-I INFRASTRUCTURE ENGINEERING BTCVC702
 
equipments at railway station
equipments at railway stationequipments at railway station
equipments at railway station
 
modern methods of railway track maintanence
modern methods of railway track maintanencemodern methods of railway track maintanence
modern methods of railway track maintanence
 
Railway Track Maintenance
Railway Track  MaintenanceRailway Track  Maintenance
Railway Track Maintenance
 
Airport lighting
Airport lightingAirport lighting
Airport lighting
 
Railway signal
Railway signalRailway signal
Railway signal
 
Signals on Railway
Signals on RailwaySignals on Railway
Signals on Railway
 
cc ppt Transportation engg poly unit 4(4)
cc ppt Transportation engg poly unit 4(4)cc ppt Transportation engg poly unit 4(4)
cc ppt Transportation engg poly unit 4(4)
 
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
 
highway engineering
 highway engineering highway engineering
highway engineering
 
Railway signalling
Railway signallingRailway signalling
Railway signalling
 
Stations and Yards of Railway
Stations and Yards of RailwayStations and Yards of Railway
Stations and Yards of Railway
 
Wind Rose.pdf
Wind Rose.pdfWind Rose.pdf
Wind Rose.pdf
 
Maintenance & repair of steel bridges
Maintenance & repair of steel bridgesMaintenance & repair of steel bridges
Maintenance & repair of steel bridges
 
Monorail vs Metrorail
Monorail vs MetrorailMonorail vs Metrorail
Monorail vs Metrorail
 
11.track junctions and layouts
11.track junctions and layouts11.track junctions and layouts
11.track junctions and layouts
 
chapter-4 Railway Station.pptx
chapter-4   Railway Station.pptxchapter-4   Railway Station.pptx
chapter-4 Railway Station.pptx
 

Similar to LWR Destressing Methods and Procedures

Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and detailsMahesh Sontyal
 
Traction distribution
Traction distribution Traction distribution
Traction distribution Amit Kumar
 
Rig Operations & Equipment
Rig Operations & EquipmentRig Operations & Equipment
Rig Operations & EquipmentM.T.H Group
 
Offshore platform slot recovery process
Offshore platform slot recovery processOffshore platform slot recovery process
Offshore platform slot recovery processKamel Elsayed
 
Tower crane safety
Tower crane safetyTower crane safety
Tower crane safetyShiva Kaveri
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976Southern Railway
 
PNGE 310Class 21Overbalanced Drilling• Mos.docx
PNGE 310Class 21Overbalanced Drilling• Mos.docxPNGE 310Class 21Overbalanced Drilling• Mos.docx
PNGE 310Class 21Overbalanced Drilling• Mos.docxstilliegeorgiana
 
Presentation on coal handling systems
Presentation on coal handling systemsPresentation on coal handling systems
Presentation on coal handling systemsArnab Chakraborty
 
RUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCHRUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCHApoorv Dhawan
 
Dismantling of existing ROB, CSB Nagpur, AFCONS
Dismantling of existing ROB, CSB Nagpur, AFCONSDismantling of existing ROB, CSB Nagpur, AFCONS
Dismantling of existing ROB, CSB Nagpur, AFCONSSaritaJoshi5
 
Coiled Tubing Introduction and Basics.pdf
Coiled Tubing Introduction and Basics.pdfCoiled Tubing Introduction and Basics.pdf
Coiled Tubing Introduction and Basics.pdfsalem123gmaal
 
Behaviour of the track in hot weather. Rail thermal forces for jointed and CW...
Behaviour of the track in hot weather. Rail thermal forces for jointed and CW...Behaviour of the track in hot weather. Rail thermal forces for jointed and CW...
Behaviour of the track in hot weather. Rail thermal forces for jointed and CW...Constantin Ciobanu
 
Post Tensioning Review Session for Installers
Post Tensioning Review Session for InstallersPost Tensioning Review Session for Installers
Post Tensioning Review Session for InstallersAMSYSCO Inc.
 
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)coderweb
 
Best practices day 4 am new
Best practices day 4 am newBest practices day 4 am new
Best practices day 4 am newAhmed Radwan
 
Areva "Manufacturing of transformer, uses & it’s accessories"
Areva "Manufacturing of transformer, uses & it’s accessories"Areva "Manufacturing of transformer, uses & it’s accessories"
Areva "Manufacturing of transformer, uses & it’s accessories"Harshit Srivastava
 

Similar to LWR Destressing Methods and Procedures (20)

Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and details
 
Traction distribution
Traction distribution Traction distribution
Traction distribution
 
Rig Operations & Equipment
Rig Operations & EquipmentRig Operations & Equipment
Rig Operations & Equipment
 
Offshore platform slot recovery process
Offshore platform slot recovery processOffshore platform slot recovery process
Offshore platform slot recovery process
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
 
Track
TrackTrack
Track
 
Tower crane safety
Tower crane safetyTower crane safety
Tower crane safety
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976
 
PNGE 310Class 21Overbalanced Drilling• Mos.docx
PNGE 310Class 21Overbalanced Drilling• Mos.docxPNGE 310Class 21Overbalanced Drilling• Mos.docx
PNGE 310Class 21Overbalanced Drilling• Mos.docx
 
Presentation on coal handling systems
Presentation on coal handling systemsPresentation on coal handling systems
Presentation on coal handling systems
 
RUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCHRUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCH
 
Dismantling of existing ROB, CSB Nagpur, AFCONS
Dismantling of existing ROB, CSB Nagpur, AFCONSDismantling of existing ROB, CSB Nagpur, AFCONS
Dismantling of existing ROB, CSB Nagpur, AFCONS
 
Coiled Tubing Introduction and Basics.pdf
Coiled Tubing Introduction and Basics.pdfCoiled Tubing Introduction and Basics.pdf
Coiled Tubing Introduction and Basics.pdf
 
Behaviour of the track in hot weather. Rail thermal forces for jointed and CW...
Behaviour of the track in hot weather. Rail thermal forces for jointed and CW...Behaviour of the track in hot weather. Rail thermal forces for jointed and CW...
Behaviour of the track in hot weather. Rail thermal forces for jointed and CW...
 
Post Tensioning Review Session for Installers
Post Tensioning Review Session for InstallersPost Tensioning Review Session for Installers
Post Tensioning Review Session for Installers
 
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
 
Best practices day 4 am new
Best practices day 4 am newBest practices day 4 am new
Best practices day 4 am new
 
Areva "Manufacturing of transformer, uses & it’s accessories"
Areva "Manufacturing of transformer, uses & it’s accessories"Areva "Manufacturing of transformer, uses & it’s accessories"
Areva "Manufacturing of transformer, uses & it’s accessories"
 
Presentation on Highwall Mining
Presentation on Highwall MiningPresentation on Highwall Mining
Presentation on Highwall Mining
 
Drilling engineering zaidi
Drilling engineering zaidiDrilling engineering zaidi
Drilling engineering zaidi
 

Recently uploaded

Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 

Recently uploaded (20)

Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 

LWR Destressing Methods and Procedures

  • 2. Definition • Destressing is the operation undertaken with or without rail tensor to secure stress free conditions in the LWR/CWR at the desired/specified rail temperature. • Destressing Temperature (td) is the average rail temperature during the period of fastening the rails to the sleepers after destressing LWR without the use of rail tensor. • Range of td :- o Temperature zone I,II,III i) All sections tm to tm + 5C o Temperature zone IV i) 52kg & heavier tm+5C to tm+10C ii) Others tm to tm+5 C
  • 3. Need for destressing? 1) On initial laying of LWR 2) During maintenance of LWR i) Gaps at SEJ a) Gap between the reference mark and tongue rail tip/stock rail corner at various rail temperatures shall not differ by more than +/- 10 mm from the theoretical range as shown in Annexure-V b) Gap exceeds maximum designed gap of SEJ c) Tongue/Stock rail crosses mean position
  • 4. Need for destressing? ii) After special track maintenance operations namely TFR, D/S, Lifting of track, major reliagnment of curves, TSR etc. iii) After restoration of track following an unusual occurance namely rail fracture, buckling, accidents, breaches etc iv) If number of repairs where temporary repairs have been done exeed 3 per km
  • 5. Need for destressing? 3) If rail temp is likely to fall outside td+10 & td- 20 C during special maintenance activities like D/S, TSR, lifting etc then 1 round of temporary destressing is essential
  • 6. Practice • Once in 3 years, all LWRs shall preferably with destressed.
  • 7. LWR destressing operation • Under supervision of JE/SSE Pway during traffic block of adequate duration at appropriate rail temperature • SR of 30 kmph before traffic block shall be availed to loosen rail fastenings on alternate sleepers • Impediments to free movement of rail shall be removed such as rail anchor, guard rail, check rail etc • During destressing operation, rail is required to be lifted and placed on rollers at every 15th sleeper to permit free movement of rail
  • 8. LWR destressing operation • During destressing following activities shall also be done:- a) Fitting renewal namely damaged rubber pad, ERC, liners. b) Shifting of liner biting zone shall be done, wherever required c) Greasing on leg of pandrol clip ,inside of inserts, below liners & liner sealing d) LC overhauling
  • 9. Destressing methods • Without tensor o Conventional practice o Do not require skilled supervision o Can be used only tp is within range • With tensor o Used when prevailing temperature tp is below to o Require skilled supervision, more number of supervisors o More block time is required
  • 10. Procedure (without tensor) • Approximately 1 km patch of LWR is destressed in single block of 2/2.5 hrs which involves 2-3 welds. Minimum 30-40 nos labour, 2 supervisors required during block • Pre block activities:- o SR of 30 kmph is imposed o ERCs are removed every alternate sleeper o LC check rail is removed if any LC is coming in destressed portion
  • 11. Procedure (without tensor) • Cut is made in central portion and rails made out of alignment to permit free expansion/contraction. • Fittings are unfastened from centre cut towards LWR on either side with placing of rollers on every 15th sleeper & tapping with wooden hammer to facilitate free movement of rail • Fastening is then started from either side of LWR portion towards central cut. • If less than 2.5 hours block is permitted then welds are not done during this block & caution persists till next block is granted.
  • 12. Procedure (with tensor) • Para 5.7.3 of LWR manual