1. Which of the following is more reflective of managerial task?
a. creating vision and strategies
b. problem-solving
c. long-term risk-taking
d. communication by word and deed
2. Which of the following is more reflective of a leader’s task?
a. efficiency of operations
b. delegation and maintaining
c. motivation and inspiration
d. marshalling resources
3. A more apt title for a project manager is ______________.
a. controller
b. comptroller
c. project director
d. project leader
4. Friendliness with a purpose describes ______________.
a. empathy
b. self-regulation
c. obsequiousness
d. social skill
5. Project management is first and foremost a ______________
challenge.
a. people management
b. customer service
c. perception management
d. budget management
6. The ability to cognitively bring the past and future closer
together is ______________.
a. creating future vision
b. time warping
c. time compressing
d. tesseracting
7. A project manager should have the ability to generate
estimates of what will occur in the
future, which is termed ______________.
a. time warping
b. creating future vision
c. predicting
d. chunking time
8. The organizational structure for the project team, including
policies and procedures, is the
_______________.
a. work breakdown structure
b. rules statement
c. scope statement
d. management plan
9. Which of these scope statement steps create the all-important
bureaucracy for a project?
a. the management plan
b. the work breakdown structure
c. the scope baseline
d. the project goal criteria
10. In the case of projects developed for external clients, work
authorization typically addresses
______________.
a. budget linkage
b. audit trail establishment
c. resource requirements
d. contractual obligations
11. All projects are promised in terms of the specific
functionality or performance criteria they will
meet. The key feature of the contractual documentation that
specifies this functionality or
criteria is the ______________.
a. contractual requirements
b. valid consideration
c. contracted terms
d. contractual performance
12. The exchange that is specified by the contractual
documentation is ______________.
a. the terms
b. valid consideration
c. reciprocity
d. fair and unencumbered
13. The status accounting step of configuration management
functions primarily as
_____________.
a. a hierarchy
b. binding arbitration
c. cost control
d. memory
14. If viewed from a flow standpoint, the stage of configuration
management that has provision
for variable routing to the next step, depending on outcome at
this stage, is _______________.
a. configuration control
b. configuration reviews
c. status accounting
d. configuration identification
15. Your first project team meeting got off to a bad start when
the functional manager for your
team’s physician refused to allow her to attend the meeting.
This ______________.
a. goal-oriented conflict threatened the project’s success.
b. administrative conflict posed a serious threat to the project’s
success.
c. interpersonal conflict was devastating to the project’s chance
for success.
d. interactionist conflict meant there would be no project
completion party in your future.
16. The husband in the marriage project meekly apologized and
hid in the garage while the other
project team member rampaged through the house. The husband
holds the ______________
view of conflict.
a. behavioral
b. interactionist
c. traditional
d. attributional
17. Some of the team members took great delight in stirring the
pot at team meetings. They knew
just how to get each team member agitated and then sat back
and enjoyed the show. These
trouble-makers defended their actions by claiming that they
took the _______________ view of
conflict.
a. traditional
b. behavioral
c. the high reliability
d. the interactionist
18. When a project manager imposes a judgment on warring
parties, he is involved in
______________.
a. mediation
b. elimination
c. arbitration
d. acceptance
19. Principled negotiation is the art of ______________.
a. getting agreement with the other party while maintaining a
win-win attitude
b. refusing to compromise your principles for the sake of a
business deal
c. creating conflict to test for an adversary’s weakness and
reducing conflict once the
weakness has been exposed
d. dividing your resources in the face of superior numbers
20. An excellent starting point in negotiations is to
______________.
a. deduce their intentions from your fears
b. identify the person that is the source of the problem
c. deduce their fears from your intentions
d. put yourself in their shoes
21. The greatest project risk occurs when the probability of the
event is _______________ and the
consequences of the event are ______________.
a. high; high
b. high; low
c. low; high
d. low; low
22. The greatest project opportunity occurs when the project is
in the _______________ phase.
a. concept
b. development
c. implementation
d. termination
23. The amount a company has at stake in a project rises above
the dollar value of opportunity in
the ______________ phase.
a. implementation
b. development
c. concept
d. termination
24. The mouse executive board meeting was drawing to a
conclusion; the only way they would be
able to detect the presence of the cat was to tie a bell around its
tail. Under their risk
management identification scheme, this would fall under
_______________ risk.
a. commercial
b. execution
c. financial
d. technical
25. A method for conducting risk factor identification that
consolidates the judgments of isolated,
anonymous respondents is _______________.
a. a brainstorming meeting
b. the Delphi method
c. past history
d. multiple assessments
*****************************************************
*
UNIT 4
*****************************************************
*
1. All five members of a project team add 15% to their
individual serial activities as a safety
margin and submit their time estimates to the project manager.
The manager adds the activity
length estimates together and adds 10% for his personal safety
margin. Then, anticipating a cut
by top management, adds another 10% to his final project
estimate. Much to his surprise, top
management cuts 30% off his time estimate. How much of a
cushion is now built into the
project?
a 13%
b. 7%
c. 5%
d. -3%
2. All five members of a project team add 20% to their
individual serial activities as a safety
margin and submit their time estimates to the project manager.
The manager adds the activity
length estimates together and adds 20% for his personal safety
margin. Then, anticipating a cut
by top management, adds another 20% to his final project
estimate. The executive level of the
organization just completed a retreat where they read The One
Minute Manager, Who Moved My
Cheese and Critical Chain. They return from their retreat both
energized and much wiser in the
ways of project management. They know that everyone has
been routinely adding 20% and
want to scale the project back to an unpadded estimate. How
much should they cut?
a. 42%
b. 60%
c. 33%
d. 27%
3. The student syndrome of wasting extra safety time can be
described as ______________.
a. lack of motivation
b. procrastination
c. failure to communicate
d. lack of comprehension
4. Which of the following statements about CCPM activity
networks is correct?
a. Project workers are more likely to meet a deadline for their
activity than miss it.
b. There are no milestones in the CCPM activity network.
c. Project workers are more likely to miss a deadline for their
activity than meet it.
d. There is no project delivery deadline in the CCPM activity
network
5. Subcontractor deliveries are difficult to schedule with the
critical chain project methodology
because ____________.
a. the project manager cannot force subcontractors to use this
project management
approach
b. the feeder buffers for a subcontractor are as much as 50%
shorter than for an employee
or internal team
c. subcontractors routinely operate according to calendar
delivery dates
d. the corporate culture of “no blame” does not naturally extend
to subcontractors
6. The buffers supplied to noncritical paths in critical chain
project management are called
_____________ buffers.
a. slack
b. drum
c. rope
d. feeder
7. The amounts of individual resources that a schedule requires
during a specific time period is
referred to as the resource’s ______________.
a. loading
b. capacity
c. constraint
d. drag
8. A resource loading form is also known as a(n)
______________.
a. load schedule
b. resource usage calendar
c. activity resource schedule
d. network resource profile
9. A resource loading chart displays the amount of
______________.
a. time needed as a function of resource limits
b. resources required as a function of time
c. time needed as a function of money
d. resources needed as a function of money
10. Splitting activities refers to _____________.
a. assigning the work to two or more workers
b. assigning the work to two or more days
c. starting an activity, interrupting it to use a resource
elsewhere and then returning to
work on the activity
d. breaking each noncritical activity into two or more
components and subdividing the
resources they use by a similar divisor
11. The Minimum Late Finish Time rule stipulates that the
_____________.
a. earliest late finishers are scheduled last
b. latest early finishers are scheduled first
c. earliest late finishers are scheduled first
d. latest late finishers are scheduled first
12. Mathematical programming is sometimes used to generate
optimal solutions to resource
constrained problems in a multi-project setting but suffers from
_____________.
a. an inability to model project and activity due dates
b. resource substitution
c. resource constraints
d. problem complexity
13. In earned value management, schedule variance is defined
as the difference
between the _____________.
a. earned value and the actual cost
b. earned value and the planned value
c. actual cost and the planned value
d. cost and schedule performance indices multiplied by the
budgeted cost at completion
14. The budget variance is calculated as _____________.
a. earned value minus planned value
b. planned value minus actual cost
c. earned value minus actual cost
d. cost minus planned value
15. In earned value management analysis, the cumulative
amount of the budget becomes the
_____________.
a. planned value
b. scheduled value
c. cost basis
d. cost driver
16. The project baseline is established by combining data from
the _____________.
a. work breakdown structure and the project budget
b. time-phased project budget and the PERT chart
c. S-curve and the project budget
d. time-phased project budget and the work breakdown structure
17. Take the factors considered by earned value analysis and
subtract those considered by project
S-curves. The factor(s) you have remaining are
_____________.
a. performance and cost
b. cost and schedule
c. time
d. performance
18. Knowing the correct steps to take once problems develop is
a function of a team’s ___________
ability.
a. communication
b. client acceptance
c. troubleshooting
d. technical task
19. Earned value management is also known as _____________.
a. the golden triangle method (GTM)
b. the achieved value method (AVM)
c. the program evaluation and review method (PERM)
d. earned value analysis (EVA)
20. All projects are unique _____________.
a. therefore all project management circumstances are equally
unique
b. so knowledge cannot be transferred
c. but they may have several common points
d. so knowledge should not be transferred to avoid bias in
future projects
21. Lessons learned analysis is best described as a(n)
______________ process.
a. bookkeeping
b. personnel reassignment
c. pressure relief
d. organizational learning
22. Which of these is not a consequence of a natural process for
project closeout?
a. Team members suffer a natural let-down and are de-motivated
to participate in future
projects.
b. Managers can create a database of lessons learned analyses.
c. Closeout can serve as an important source of information for
team members.
d. Structure for a systematic and complete project shut-down
arises.
23. Which of these statements about early termination decisions
is best?
a. The decision to pull the plug is usually clear-cut.
b. A project’s viability is usually a purely internal issue.
c. Projects that can fulfill a useful purpose in the marketplace
are not killed.
d. External reasons, such as a change in the organizations
environment, are often the
reasons for project termination.
24. A mainframe computer company decided to enter the
personal computer market with its
Floridian Project, but subsequently decided to leave the market
to focus on the mainframe
business. The decision rule that they probably applied was to
get out when ____________.
a. the project no longer meets strategic fit criteria
b. deadlines continue to be missed
c. project personnel turn over too rapidly
d. technology evolves beyond the project’s scope
25. The rapid evolution of technology and the need to freeze a
project’s scope can combine to
render a project ____________.
a. too costly to complete
b. obsolete before it can be finished
c. a poor fit with current company strategy
d. so complex that it will take too long to complete
UNIT1.docx

More Related Content

Similar to UNIT1.docx

ICFAI Projects and Operations Management - Solved assignments and case study ...
ICFAI Projects and Operations Management - Solved assignments and case study ...ICFAI Projects and Operations Management - Solved assignments and case study ...
ICFAI Projects and Operations Management - Solved assignments and case study ...smumbahelp
 
Chapter 2 Questionsand Answers1. There is a difference between t.docx
Chapter 2 Questionsand Answers1. There is a difference between t.docxChapter 2 Questionsand Answers1. There is a difference between t.docx
Chapter 2 Questionsand Answers1. There is a difference between t.docxwalterl4
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfMoncefMakni1
 
Project ManagementECE 326 Exam 2Description Exam 2 question.docx
Project ManagementECE 326 Exam 2Description Exam 2 question.docxProject ManagementECE 326 Exam 2Description Exam 2 question.docx
Project ManagementECE 326 Exam 2Description Exam 2 question.docxwkyra78
 
(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx
(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx
(Enter your answers on the enclosed answer sheet)1. A humanis an e.docxtienmixon
 
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management FrameworkProject Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management FrameworkD10iT
 
Liberty university busi 313 quiz 1 complete solutions correct answers key
Liberty university busi 313 quiz 1 complete solutions correct answers keyLiberty university busi 313 quiz 1 complete solutions correct answers key
Liberty university busi 313 quiz 1 complete solutions correct answers keyHarry White
 
Group 11. A ________ is an example of a first-line manager.a.docx
Group 11. A ________ is an example of a first-line manager.a.docxGroup 11. A ________ is an example of a first-line manager.a.docx
Group 11. A ________ is an example of a first-line manager.a.docxJeanmarieColbert3
 
PMI ACP Classroom Question Paper with Answers
PMI ACP Classroom Question Paper with AnswersPMI ACP Classroom Question Paper with Answers
PMI ACP Classroom Question Paper with AnswersThanh Nguyen
 
PMI ACP Classroom Question Paper
PMI ACP Classroom Question PaperPMI ACP Classroom Question Paper
PMI ACP Classroom Question PaperThanh Nguyen
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxalfred4lewis58146
 
PMP Certification Training Course Part-64
PMP Certification Training Course Part-64PMP Certification Training Course Part-64
PMP Certification Training Course Part-64Skillogic Solutions
 
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management examJamil Faraj , PMP
 
Question 1 According to the textbook, risk management plans ad.docx
Question 1 According to the textbook, risk management plans ad.docxQuestion 1 According to the textbook, risk management plans ad.docx
Question 1 According to the textbook, risk management plans ad.docxIRESH3
 
Mb0033 mb0049
Mb0033 mb0049Mb0033 mb0049
Mb0033 mb0049amitpr
 
2016 bookmatter ace_thepmi-acp_exam
2016 bookmatter ace_thepmi-acp_exam2016 bookmatter ace_thepmi-acp_exam
2016 bookmatter ace_thepmi-acp_examNguyen Hai
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bankBaskar El
 

Similar to UNIT1.docx (20)

ICFAI Projects and Operations Management - Solved assignments and case study ...
ICFAI Projects and Operations Management - Solved assignments and case study ...ICFAI Projects and Operations Management - Solved assignments and case study ...
ICFAI Projects and Operations Management - Solved assignments and case study ...
 
Chapter 2 Questionsand Answers1. There is a difference between t.docx
Chapter 2 Questionsand Answers1. There is a difference between t.docxChapter 2 Questionsand Answers1. There is a difference between t.docx
Chapter 2 Questionsand Answers1. There is a difference between t.docx
 
Pmp sample qa3
Pmp sample qa3Pmp sample qa3
Pmp sample qa3
 
Software engineering-quiz
Software engineering-quizSoftware engineering-quiz
Software engineering-quiz
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
 
Pmp test 05
Pmp test 05Pmp test 05
Pmp test 05
 
Project ManagementECE 326 Exam 2Description Exam 2 question.docx
Project ManagementECE 326 Exam 2Description Exam 2 question.docxProject ManagementECE 326 Exam 2Description Exam 2 question.docx
Project ManagementECE 326 Exam 2Description Exam 2 question.docx
 
(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx
(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx
(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx
 
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management FrameworkProject Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
 
Liberty university busi 313 quiz 1 complete solutions correct answers key
Liberty university busi 313 quiz 1 complete solutions correct answers keyLiberty university busi 313 quiz 1 complete solutions correct answers key
Liberty university busi 313 quiz 1 complete solutions correct answers key
 
Group 11. A ________ is an example of a first-line manager.a.docx
Group 11. A ________ is an example of a first-line manager.a.docxGroup 11. A ________ is an example of a first-line manager.a.docx
Group 11. A ________ is an example of a first-line manager.a.docx
 
PMI ACP Classroom Question Paper with Answers
PMI ACP Classroom Question Paper with AnswersPMI ACP Classroom Question Paper with Answers
PMI ACP Classroom Question Paper with Answers
 
PMI ACP Classroom Question Paper
PMI ACP Classroom Question PaperPMI ACP Classroom Question Paper
PMI ACP Classroom Question Paper
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docx
 
PMP Certification Training Course Part-64
PMP Certification Training Course Part-64PMP Certification Training Course Part-64
PMP Certification Training Course Part-64
 
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management exam
 
Question 1 According to the textbook, risk management plans ad.docx
Question 1 According to the textbook, risk management plans ad.docxQuestion 1 According to the textbook, risk management plans ad.docx
Question 1 According to the textbook, risk management plans ad.docx
 
Mb0033 mb0049
Mb0033 mb0049Mb0033 mb0049
Mb0033 mb0049
 
2016 bookmatter ace_thepmi-acp_exam
2016 bookmatter ace_thepmi-acp_exam2016 bookmatter ace_thepmi-acp_exam
2016 bookmatter ace_thepmi-acp_exam
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
 

More from gidmanmary

Using C#, write a program to find the nearest common parent of any t.docx
Using C#, write a program to find the nearest common parent of any t.docxUsing C#, write a program to find the nearest common parent of any t.docx
Using C#, write a program to find the nearest common parent of any t.docxgidmanmary
 
Using autoethnography in a qualitative research,consider a resid.docx
Using autoethnography in a qualitative research,consider a resid.docxUsing autoethnography in a qualitative research,consider a resid.docx
Using autoethnography in a qualitative research,consider a resid.docxgidmanmary
 
Using Earned Value to Determine StatusJennifer turned in her statu.docx
Using Earned Value to Determine StatusJennifer turned in her statu.docxUsing Earned Value to Determine StatusJennifer turned in her statu.docx
Using Earned Value to Determine StatusJennifer turned in her statu.docxgidmanmary
 
Using at least your textbook and a minimum of three additional sourc.docx
Using at least your textbook and a minimum of three additional sourc.docxUsing at least your textbook and a minimum of three additional sourc.docx
Using at least your textbook and a minimum of three additional sourc.docxgidmanmary
 
Using APA style format, write a 4-5 page paper describing the provis.docx
Using APA style format, write a 4-5 page paper describing the provis.docxUsing APA style format, write a 4-5 page paper describing the provis.docx
Using APA style format, write a 4-5 page paper describing the provis.docxgidmanmary
 
Use the organization you selected in Week One and the Security Ass.docx
Use the organization you selected in Week One and the Security Ass.docxUse the organization you selected in Week One and the Security Ass.docx
Use the organization you selected in Week One and the Security Ass.docxgidmanmary
 
Using DuPont analysis is a quick and relatively easy way to assess t.docx
Using DuPont analysis is a quick and relatively easy way to assess t.docxUsing DuPont analysis is a quick and relatively easy way to assess t.docx
Using DuPont analysis is a quick and relatively easy way to assess t.docxgidmanmary
 
Using APA style, prepare written research paper of 4 double spaced p.docx
Using APA style, prepare written research paper of 4 double spaced p.docxUsing APA style, prepare written research paper of 4 double spaced p.docx
Using APA style, prepare written research paper of 4 double spaced p.docxgidmanmary
 
Use the organization selected for your Managing Change Paper Part .docx
Use the organization selected for your Managing Change Paper Part .docxUse the organization selected for your Managing Change Paper Part .docx
Use the organization selected for your Managing Change Paper Part .docxgidmanmary
 
Use your knowledge to develop the circumstances and details involved.docx
Use your knowledge to develop the circumstances and details involved.docxUse your knowledge to develop the circumstances and details involved.docx
Use your knowledge to develop the circumstances and details involved.docxgidmanmary
 
Use the percentage method to compute the federal income taxes to w.docx
Use the percentage method to compute the federal income taxes to w.docxUse the percentage method to compute the federal income taxes to w.docx
Use the percentage method to compute the federal income taxes to w.docxgidmanmary
 
Use the textbook andor online sources to locate and capture three w.docx
Use the textbook andor online sources to locate and capture three w.docxUse the textbook andor online sources to locate and capture three w.docx
Use the textbook andor online sources to locate and capture three w.docxgidmanmary
 
Use the Web to conduct research on User Domain Security Policy and A.docx
Use the Web to conduct research on User Domain Security Policy and A.docxUse the Web to conduct research on User Domain Security Policy and A.docx
Use the Web to conduct research on User Domain Security Policy and A.docxgidmanmary
 
Use this Article to create the powerpoint slidesBrown, S. L., No.docx
Use this Article to create the powerpoint slidesBrown, S. L., No.docxUse this Article to create the powerpoint slidesBrown, S. L., No.docx
Use this Article to create the powerpoint slidesBrown, S. L., No.docxgidmanmary
 
use the work sheet format made available  but only to give brief, bu.docx
use the work sheet format made available  but only to give brief, bu.docxuse the work sheet format made available  but only to give brief, bu.docx
use the work sheet format made available  but only to give brief, bu.docxgidmanmary
 
Use these three sources to compose an annotated bibliography on Data.docx
Use these three sources to compose an annotated bibliography on Data.docxUse these three sources to compose an annotated bibliography on Data.docx
Use these three sources to compose an annotated bibliography on Data.docxgidmanmary
 
Use this outline to crete a four page essay. Guideline included and .docx
Use this outline to crete a four page essay. Guideline included and .docxUse this outline to crete a four page essay. Guideline included and .docx
Use this outline to crete a four page essay. Guideline included and .docxgidmanmary
 
Use the link provided to complete a self-assessment. After completin.docx
Use the link provided to complete a self-assessment. After completin.docxUse the link provided to complete a self-assessment. After completin.docx
Use the link provided to complete a self-assessment. After completin.docxgidmanmary
 
Use the SPSS software and the data set (2004)GSS.SAV (attached).docx
Use the SPSS software and the data set (2004)GSS.SAV (attached).docxUse the SPSS software and the data set (2004)GSS.SAV (attached).docx
Use the SPSS software and the data set (2004)GSS.SAV (attached).docxgidmanmary
 
Use the Internet to research functional systems that would contain a.docx
Use the Internet to research functional systems that would contain a.docxUse the Internet to research functional systems that would contain a.docx
Use the Internet to research functional systems that would contain a.docxgidmanmary
 

More from gidmanmary (20)

Using C#, write a program to find the nearest common parent of any t.docx
Using C#, write a program to find the nearest common parent of any t.docxUsing C#, write a program to find the nearest common parent of any t.docx
Using C#, write a program to find the nearest common parent of any t.docx
 
Using autoethnography in a qualitative research,consider a resid.docx
Using autoethnography in a qualitative research,consider a resid.docxUsing autoethnography in a qualitative research,consider a resid.docx
Using autoethnography in a qualitative research,consider a resid.docx
 
Using Earned Value to Determine StatusJennifer turned in her statu.docx
Using Earned Value to Determine StatusJennifer turned in her statu.docxUsing Earned Value to Determine StatusJennifer turned in her statu.docx
Using Earned Value to Determine StatusJennifer turned in her statu.docx
 
Using at least your textbook and a minimum of three additional sourc.docx
Using at least your textbook and a minimum of three additional sourc.docxUsing at least your textbook and a minimum of three additional sourc.docx
Using at least your textbook and a minimum of three additional sourc.docx
 
Using APA style format, write a 4-5 page paper describing the provis.docx
Using APA style format, write a 4-5 page paper describing the provis.docxUsing APA style format, write a 4-5 page paper describing the provis.docx
Using APA style format, write a 4-5 page paper describing the provis.docx
 
Use the organization you selected in Week One and the Security Ass.docx
Use the organization you selected in Week One and the Security Ass.docxUse the organization you selected in Week One and the Security Ass.docx
Use the organization you selected in Week One and the Security Ass.docx
 
Using DuPont analysis is a quick and relatively easy way to assess t.docx
Using DuPont analysis is a quick and relatively easy way to assess t.docxUsing DuPont analysis is a quick and relatively easy way to assess t.docx
Using DuPont analysis is a quick and relatively easy way to assess t.docx
 
Using APA style, prepare written research paper of 4 double spaced p.docx
Using APA style, prepare written research paper of 4 double spaced p.docxUsing APA style, prepare written research paper of 4 double spaced p.docx
Using APA style, prepare written research paper of 4 double spaced p.docx
 
Use the organization selected for your Managing Change Paper Part .docx
Use the organization selected for your Managing Change Paper Part .docxUse the organization selected for your Managing Change Paper Part .docx
Use the organization selected for your Managing Change Paper Part .docx
 
Use your knowledge to develop the circumstances and details involved.docx
Use your knowledge to develop the circumstances and details involved.docxUse your knowledge to develop the circumstances and details involved.docx
Use your knowledge to develop the circumstances and details involved.docx
 
Use the percentage method to compute the federal income taxes to w.docx
Use the percentage method to compute the federal income taxes to w.docxUse the percentage method to compute the federal income taxes to w.docx
Use the percentage method to compute the federal income taxes to w.docx
 
Use the textbook andor online sources to locate and capture three w.docx
Use the textbook andor online sources to locate and capture three w.docxUse the textbook andor online sources to locate and capture three w.docx
Use the textbook andor online sources to locate and capture three w.docx
 
Use the Web to conduct research on User Domain Security Policy and A.docx
Use the Web to conduct research on User Domain Security Policy and A.docxUse the Web to conduct research on User Domain Security Policy and A.docx
Use the Web to conduct research on User Domain Security Policy and A.docx
 
Use this Article to create the powerpoint slidesBrown, S. L., No.docx
Use this Article to create the powerpoint slidesBrown, S. L., No.docxUse this Article to create the powerpoint slidesBrown, S. L., No.docx
Use this Article to create the powerpoint slidesBrown, S. L., No.docx
 
use the work sheet format made available  but only to give brief, bu.docx
use the work sheet format made available  but only to give brief, bu.docxuse the work sheet format made available  but only to give brief, bu.docx
use the work sheet format made available  but only to give brief, bu.docx
 
Use these three sources to compose an annotated bibliography on Data.docx
Use these three sources to compose an annotated bibliography on Data.docxUse these three sources to compose an annotated bibliography on Data.docx
Use these three sources to compose an annotated bibliography on Data.docx
 
Use this outline to crete a four page essay. Guideline included and .docx
Use this outline to crete a four page essay. Guideline included and .docxUse this outline to crete a four page essay. Guideline included and .docx
Use this outline to crete a four page essay. Guideline included and .docx
 
Use the link provided to complete a self-assessment. After completin.docx
Use the link provided to complete a self-assessment. After completin.docxUse the link provided to complete a self-assessment. After completin.docx
Use the link provided to complete a self-assessment. After completin.docx
 
Use the SPSS software and the data set (2004)GSS.SAV (attached).docx
Use the SPSS software and the data set (2004)GSS.SAV (attached).docxUse the SPSS software and the data set (2004)GSS.SAV (attached).docx
Use the SPSS software and the data set (2004)GSS.SAV (attached).docx
 
Use the Internet to research functional systems that would contain a.docx
Use the Internet to research functional systems that would contain a.docxUse the Internet to research functional systems that would contain a.docx
Use the Internet to research functional systems that would contain a.docx
 

Recently uploaded

18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 

Recently uploaded (20)

18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 

UNIT1.docx

  • 1. ***************************************** UNIT1 **************************************** 1. Which of the following is more reflective of managerial task? a. creating vision and strategies b. problem-solving c. long-term risk-taking d. communication by word and deed 2. Which of the following is more reflective of a leader’s task? a. efficiency of operations b. delegation and maintaining c. motivation and inspiration d. marshalling resources 3. A more apt title for a project manager is ______________. a. controller b. comptroller c. project director d. project leader 4. Friendliness with a purpose describes ______________. a. empathy b. self-regulation c. obsequiousness d. social skill 5. Project management is first and foremost a ______________ challenge. a. people management b. customer service c. perception management d. budget management 6. The ability to cognitively bring the past and future closer together is ______________. a. creating future vision b. time warping c. time compressing d. tesseracting
  • 2. 7. A project manager should have the ability to generate estimates of what will occur in the future, which is termed ______________. a. time warping b. creating future vision c. predicting d. chunking time 8. The organizational structure for the project team, including policies and procedures, is the _______________. a. work breakdown structure b. rules statement c. scope statement d. management plan 9. Which of these scope statement steps create the all-important bureaucracy for a project? a. the management plan b. the work breakdown structure c. the scope baseline d. the project goal criteria 10. In the case of projects developed for external clients, work authorization typically addresses ______________. a. budget linkage b. audit trail establishment c. resource requirements d. contractual obligations 11. All projects are promised in terms of the specific functionality or performance criteria they will meet. The key feature of the contractual documentation that specifies this functionality or criteria is the ______________. a. contractual requirements b. valid consideration c. contracted terms d. contractual performance
  • 3. 12. The exchange that is specified by the contractual documentation is ______________. a. the terms b. valid consideration c. reciprocity d. fair and unencumbered 13. The status accounting step of configuration management functions primarily as _____________. a. a hierarchy b. binding arbitration c. cost control d. memory 14. If viewed from a flow standpoint, the stage of configuration management that has provision for variable routing to the next step, depending on outcome at this stage, is _______________. a. configuration control b. configuration reviews c. status accounting d. configuration identification 15. Your first project team meeting got off to a bad start when the functional manager for your team’s physician refused to allow her to attend the meeting. This ______________. a. goal-oriented conflict threatened the project’s success. b. administrative conflict posed a serious threat to the project’s success. c. interpersonal conflict was devastating to the project’s chance for success. d. interactionist conflict meant there would be no project completion party in your future. 16. The husband in the marriage project meekly apologized and hid in the garage while the other project team member rampaged through the house. The husband holds the ______________
  • 4. view of conflict. a. behavioral b. interactionist c. traditional d. attributional 17. Some of the team members took great delight in stirring the pot at team meetings. They knew just how to get each team member agitated and then sat back and enjoyed the show. These trouble-makers defended their actions by claiming that they took the _______________ view of conflict. a. traditional b. behavioral c. the high reliability d. the interactionist 18. When a project manager imposes a judgment on warring parties, he is involved in ______________. a. mediation b. elimination c. arbitration d. acceptance 19. Principled negotiation is the art of ______________. a. getting agreement with the other party while maintaining a win-win attitude b. refusing to compromise your principles for the sake of a business deal c. creating conflict to test for an adversary’s weakness and reducing conflict once the weakness has been exposed d. dividing your resources in the face of superior numbers 20. An excellent starting point in negotiations is to ______________. a. deduce their intentions from your fears b. identify the person that is the source of the problem
  • 5. c. deduce their fears from your intentions d. put yourself in their shoes 21. The greatest project risk occurs when the probability of the event is _______________ and the consequences of the event are ______________. a. high; high b. high; low c. low; high d. low; low 22. The greatest project opportunity occurs when the project is in the _______________ phase. a. concept b. development c. implementation d. termination 23. The amount a company has at stake in a project rises above the dollar value of opportunity in the ______________ phase. a. implementation b. development c. concept d. termination 24. The mouse executive board meeting was drawing to a conclusion; the only way they would be able to detect the presence of the cat was to tie a bell around its tail. Under their risk management identification scheme, this would fall under _______________ risk. a. commercial b. execution c. financial d. technical 25. A method for conducting risk factor identification that consolidates the judgments of isolated, anonymous respondents is _______________. a. a brainstorming meeting
  • 6. b. the Delphi method c. past history d. multiple assessments ***************************************************** * UNIT 4 ***************************************************** * 1. All five members of a project team add 15% to their individual serial activities as a safety margin and submit their time estimates to the project manager. The manager adds the activity length estimates together and adds 10% for his personal safety margin. Then, anticipating a cut by top management, adds another 10% to his final project estimate. Much to his surprise, top management cuts 30% off his time estimate. How much of a cushion is now built into the project? a 13% b. 7% c. 5% d. -3% 2. All five members of a project team add 20% to their individual serial activities as a safety margin and submit their time estimates to the project manager. The manager adds the activity length estimates together and adds 20% for his personal safety margin. Then, anticipating a cut by top management, adds another 20% to his final project estimate. The executive level of the organization just completed a retreat where they read The One Minute Manager, Who Moved My Cheese and Critical Chain. They return from their retreat both energized and much wiser in the ways of project management. They know that everyone has
  • 7. been routinely adding 20% and want to scale the project back to an unpadded estimate. How much should they cut? a. 42% b. 60% c. 33% d. 27% 3. The student syndrome of wasting extra safety time can be described as ______________. a. lack of motivation b. procrastination c. failure to communicate d. lack of comprehension 4. Which of the following statements about CCPM activity networks is correct? a. Project workers are more likely to meet a deadline for their activity than miss it. b. There are no milestones in the CCPM activity network. c. Project workers are more likely to miss a deadline for their activity than meet it. d. There is no project delivery deadline in the CCPM activity network 5. Subcontractor deliveries are difficult to schedule with the critical chain project methodology because ____________. a. the project manager cannot force subcontractors to use this project management approach b. the feeder buffers for a subcontractor are as much as 50% shorter than for an employee or internal team c. subcontractors routinely operate according to calendar delivery dates d. the corporate culture of “no blame” does not naturally extend to subcontractors 6. The buffers supplied to noncritical paths in critical chain
  • 8. project management are called _____________ buffers. a. slack b. drum c. rope d. feeder 7. The amounts of individual resources that a schedule requires during a specific time period is referred to as the resource’s ______________. a. loading b. capacity c. constraint d. drag 8. A resource loading form is also known as a(n) ______________. a. load schedule b. resource usage calendar c. activity resource schedule d. network resource profile 9. A resource loading chart displays the amount of ______________. a. time needed as a function of resource limits b. resources required as a function of time c. time needed as a function of money d. resources needed as a function of money 10. Splitting activities refers to _____________. a. assigning the work to two or more workers b. assigning the work to two or more days c. starting an activity, interrupting it to use a resource elsewhere and then returning to work on the activity d. breaking each noncritical activity into two or more components and subdividing the resources they use by a similar divisor 11. The Minimum Late Finish Time rule stipulates that the _____________.
  • 9. a. earliest late finishers are scheduled last b. latest early finishers are scheduled first c. earliest late finishers are scheduled first d. latest late finishers are scheduled first 12. Mathematical programming is sometimes used to generate optimal solutions to resource constrained problems in a multi-project setting but suffers from _____________. a. an inability to model project and activity due dates b. resource substitution c. resource constraints d. problem complexity 13. In earned value management, schedule variance is defined as the difference between the _____________. a. earned value and the actual cost b. earned value and the planned value c. actual cost and the planned value d. cost and schedule performance indices multiplied by the budgeted cost at completion 14. The budget variance is calculated as _____________. a. earned value minus planned value b. planned value minus actual cost c. earned value minus actual cost d. cost minus planned value 15. In earned value management analysis, the cumulative amount of the budget becomes the _____________. a. planned value b. scheduled value c. cost basis d. cost driver 16. The project baseline is established by combining data from the _____________. a. work breakdown structure and the project budget b. time-phased project budget and the PERT chart
  • 10. c. S-curve and the project budget d. time-phased project budget and the work breakdown structure 17. Take the factors considered by earned value analysis and subtract those considered by project S-curves. The factor(s) you have remaining are _____________. a. performance and cost b. cost and schedule c. time d. performance 18. Knowing the correct steps to take once problems develop is a function of a team’s ___________ ability. a. communication b. client acceptance c. troubleshooting d. technical task 19. Earned value management is also known as _____________. a. the golden triangle method (GTM) b. the achieved value method (AVM) c. the program evaluation and review method (PERM) d. earned value analysis (EVA) 20. All projects are unique _____________. a. therefore all project management circumstances are equally unique b. so knowledge cannot be transferred c. but they may have several common points d. so knowledge should not be transferred to avoid bias in future projects 21. Lessons learned analysis is best described as a(n) ______________ process. a. bookkeeping b. personnel reassignment c. pressure relief d. organizational learning 22. Which of these is not a consequence of a natural process for
  • 11. project closeout? a. Team members suffer a natural let-down and are de-motivated to participate in future projects. b. Managers can create a database of lessons learned analyses. c. Closeout can serve as an important source of information for team members. d. Structure for a systematic and complete project shut-down arises. 23. Which of these statements about early termination decisions is best? a. The decision to pull the plug is usually clear-cut. b. A project’s viability is usually a purely internal issue. c. Projects that can fulfill a useful purpose in the marketplace are not killed. d. External reasons, such as a change in the organizations environment, are often the reasons for project termination. 24. A mainframe computer company decided to enter the personal computer market with its Floridian Project, but subsequently decided to leave the market to focus on the mainframe business. The decision rule that they probably applied was to get out when ____________. a. the project no longer meets strategic fit criteria b. deadlines continue to be missed c. project personnel turn over too rapidly d. technology evolves beyond the project’s scope 25. The rapid evolution of technology and the need to freeze a project’s scope can combine to render a project ____________. a. too costly to complete b. obsolete before it can be finished c. a poor fit with current company strategy d. so complex that it will take too long to complete