SlideShare a Scribd company logo
1 of 16
Deadline 6 PM Friday September 27, 2013
10 Project Management Questions with sub-questions under
each question. A word document is provided with all questions
and directions.
Problem 1
The following data were obtained from a project to create a new
portable electronic.
Activity
Duration
Predecessors
A
5 Days
---
B
6 Days
---
C
8 Days
---
D
4 Days
A, B
E
3 Days
C
F
5 Days
D
G
5 Days
E, F
H
9 Days
D
I
12 Days
G
Step 1: Construct a network diagram for the project.
Step 2: Answer the following questions:
a)
What is the Scheduled Completion of the Project?
b)
What is the Critical Path of the Project?
c)
What is the ES for Activity D?
d)
What is the LS for Activity G?
e)
What is the EF for Activity B?
f)
What is the LF for Activity H?
g)
What is the float for Activity I?
Problem 2
The following data were obtained from a project to build a
pressure vessel:
Activity
Duration
Predecessors
A
6 weeks
---
B
6 weeks
---
C
5 weeks
B
D
4 weeks
A, C
E
5 weeks
B
F
7 weeks
D, E, G
G
4 weeks
B
H
8 weeks
F
I
5 weeks
G
J
3 week
I
Step 1: Construct a network diagram for the project.
Step 2: Answer the following questions:
a)
Calculate the scheduled completion time.
b)
Identify the critical path
c)
What is the slack time (float) for activity A?
d)
What is the slack time (float) for activity D?
e) What is the slack time (float) for activity E?
f) What is the slack time (float) for activity G?
Problem 3
The following data were obtained from a project to design a
new software package:
Activity
Duration
Predecessors
A
5 Days
---
B
8 Days
---
C
6 Days
A
D
4 Days
C, B
E
5 Days
A
F
4 Days
D, E, G
G
4 Days
B, C
H
3 Day
G
Step 1: Construct a network diagram for the project.
Step 2: Answer the following questions:
a)
Calculate the scheduled completion time.
b)
Identify the critical path(s)
c)
What is the slack time (float) for activity B?
d)
What is the slack time (float) for activity D?
e) What is the slack time (float) for activity E?
f) What is the slack time (float) for activity G?
Problem 4
The following data were obtained from an in-house MIS project:
Activity
Duration
Predecessors
A
5 Days
---
B
8 Days
---
C
5 Days
A
D
4 Days
B
E
5 Days
B
F
3 Day
C, D
G
7 Days
C, D
H
6 Days
E, F, G
I
9 Days
E, F
Step 1: Construct a network diagram for the project.
Step 2: Answer the following questions:
a)
Calculate the scheduled completion time.
b)
Identify the critical path
c)
What is the slack time (float) for activity A?
d)
What is the slack time (float) for activity D?
e)
What is the slack time (float) for activity E?
f)
What is the slack time (float) for activity F?
PROBLEM 5
Use the network diagram below and the additional information
provided to answer the corresponding questions.
a) Give the crash cost per day per activity.
b) Which activities should be crashed to meet a project deadline
of 10 days at minimum cost? What is the cost impact of
crashing these activities?
c) Find the new budget (or cost of the project).
PROBLEM 6
Use the network diagram below and the additional information
provided to answer the corresponding questions.
a) Give the crash cost per day per activity.
b) Which activities should be crashed to meet a project deadline
of 13 days at minimum cost? What is the cost impact of
crashing these activities?
PROBLEM 7
Month
AC
PV
EV
22
$540
$523
$535
a)
Calculate the cost variance (CV).
b)
Is the CV over or under budget?
c)
Calculate the schedule variance (SV).
d)
Is the SV ahead of or behind schedule?
PROBLEM 8
Month
AC
PV
EV
5
$34
$42
$39
a)
Calculate the cost performance index (CPI).
b)
Is the project cost efficient or not efficient?
c)
Calculate the schedule performance index (SPI).
d)
Is the schedule efficient or not efficient?
PROBLEM 9 [8 points]
Day
AC
PV
EV
65
$550
$735
$678
a)
Calculate the cost variance (CV).
b)
Calculate the cost performance index (CPI).
c)
Calculate the schedule variance (SV).
d)
Calculate the schedule performance index (SPI).
e)
Given these data, what should a project manager do with respect
to this project?
PROBLEM 10
Day
AC
PV
EV
65
$760
$735
$678
a)
Calculate the cost variance (CV).
b)
Calculate the cost performance index (CPI).
c)
Calculate the schedule variance (SV).
d)
Calculate the schedule performance index (SPI).
e)
Explain the project performance in terms of efficiency, budget,
and schedule. What should the project manager do for the
project?
Deadline 6 PM Friday September 27, 201310 Project Management Que.docx

More Related Content

Similar to Deadline 6 PM Friday September 27, 201310 Project Management Que.docx

Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project managementShadina Shah
 
Your university is holding a fund-raiser and will be hiring a band t.docx
Your university is holding a fund-raiser and will be hiring a band t.docxYour university is holding a fund-raiser and will be hiring a band t.docx
Your university is holding a fund-raiser and will be hiring a band t.docxransayo
 
Conveyor belt project
Conveyor belt projectConveyor belt project
Conveyor belt projectSamehTeleb
 
Question 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docxQuestion 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docxIRESH3
 
OPM101Chapter16_001 (2).ppt
OPM101Chapter16_001 (2).pptOPM101Chapter16_001 (2).ppt
OPM101Chapter16_001 (2).pptMarkNaguibElAbd
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newKatherineJack1
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newSarajacobe
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newEmmaJack2018
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newlizabonilla
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newemmywatson2017
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newLillieDickey
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newsarahlazeto
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newsweetsour2017
 
Devry proj 586 final exam set 2 new
Devry proj 586 final exam set 2 newDevry proj 586 final exam set 2 new
Devry proj 586 final exam set 2 newuopassignment
 
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docxdrennanmicah
 
Devry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newDevry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newuopassignment
 
College of Computing and Informatics Name ### .docx
College of Computing and Informatics Name ### .docxCollege of Computing and Informatics Name ### .docx
College of Computing and Informatics Name ### .docxmccormicknadine86
 
LectureProjectPlanning.ppt
LectureProjectPlanning.pptLectureProjectPlanning.ppt
LectureProjectPlanning.pptanhdbh
 

Similar to Deadline 6 PM Friday September 27, 201310 Project Management Que.docx (20)

Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
 
MGT-Ch07.ppt
MGT-Ch07.pptMGT-Ch07.ppt
MGT-Ch07.ppt
 
Your university is holding a fund-raiser and will be hiring a band t.docx
Your university is holding a fund-raiser and will be hiring a band t.docxYour university is holding a fund-raiser and will be hiring a band t.docx
Your university is holding a fund-raiser and will be hiring a band t.docx
 
Pmp6
Pmp6Pmp6
Pmp6
 
Conveyor belt project
Conveyor belt projectConveyor belt project
Conveyor belt project
 
Question 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docxQuestion 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docx
 
OPM101Chapter16_001 (2).ppt
OPM101Chapter16_001 (2).pptOPM101Chapter16_001 (2).ppt
OPM101Chapter16_001 (2).ppt
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Devry proj 586 final exam set 2 new
Devry proj 586 final exam set 2 newDevry proj 586 final exam set 2 new
Devry proj 586 final exam set 2 new
 
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
 
Devry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newDevry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 new
 
College of Computing and Informatics Name ### .docx
College of Computing and Informatics Name ### .docxCollege of Computing and Informatics Name ### .docx
College of Computing and Informatics Name ### .docx
 
LectureProjectPlanning.ppt
LectureProjectPlanning.pptLectureProjectPlanning.ppt
LectureProjectPlanning.ppt
 

More from edwardmarivel

deadline 6 hours 7.3 y 7.47.4.docx
deadline  6 hours 7.3 y 7.47.4.docxdeadline  6 hours 7.3 y 7.47.4.docx
deadline 6 hours 7.3 y 7.47.4.docxedwardmarivel
 
DEADLINE 15 HOURS6 PAGES UNDERGRADUATECOURSEWORKHARV.docx
DEADLINE 15 HOURS6 PAGES UNDERGRADUATECOURSEWORKHARV.docxDEADLINE 15 HOURS6 PAGES UNDERGRADUATECOURSEWORKHARV.docx
DEADLINE 15 HOURS6 PAGES UNDERGRADUATECOURSEWORKHARV.docxedwardmarivel
 
De nada.El gusto es mío.Encantada.Me llamo Pepe.Muy bien, grac.docx
De nada.El gusto es mío.Encantada.Me llamo Pepe.Muy bien, grac.docxDe nada.El gusto es mío.Encantada.Me llamo Pepe.Muy bien, grac.docx
De nada.El gusto es mío.Encantada.Me llamo Pepe.Muy bien, grac.docxedwardmarivel
 
DDBA 8307 Week 4 Assignment TemplateJohn DoeDDBA 8.docx
DDBA 8307 Week 4 Assignment TemplateJohn DoeDDBA 8.docxDDBA 8307 Week 4 Assignment TemplateJohn DoeDDBA 8.docx
DDBA 8307 Week 4 Assignment TemplateJohn DoeDDBA 8.docxedwardmarivel
 
DDL 24 hours reading the article and writing a 1-page doubl.docx
DDL 24 hours reading the article and writing a 1-page doubl.docxDDL 24 hours reading the article and writing a 1-page doubl.docx
DDL 24 hours reading the article and writing a 1-page doubl.docxedwardmarivel
 
DCF valuation methodSuper-normal growth modelApplicatio.docx
DCF valuation methodSuper-normal growth modelApplicatio.docxDCF valuation methodSuper-normal growth modelApplicatio.docx
DCF valuation methodSuper-normal growth modelApplicatio.docxedwardmarivel
 
DDBA 8307 Week 2 Assignment ExemplarJohn Doe[footnoteRef1] .docx
DDBA 8307 Week 2 Assignment ExemplarJohn Doe[footnoteRef1] .docxDDBA 8307 Week 2 Assignment ExemplarJohn Doe[footnoteRef1] .docx
DDBA 8307 Week 2 Assignment ExemplarJohn Doe[footnoteRef1] .docxedwardmarivel
 
DBM380 v14Create a DatabaseDBM380 v14Page 2 of 2Create a D.docx
DBM380 v14Create a DatabaseDBM380 v14Page 2 of 2Create a D.docxDBM380 v14Create a DatabaseDBM380 v14Page 2 of 2Create a D.docx
DBM380 v14Create a DatabaseDBM380 v14Page 2 of 2Create a D.docxedwardmarivel
 
DBA CAPSTONE TEMPLATEThe pages in this template are correctl.docx
DBA CAPSTONE TEMPLATEThe pages in this template are correctl.docxDBA CAPSTONE TEMPLATEThe pages in this template are correctl.docx
DBA CAPSTONE TEMPLATEThe pages in this template are correctl.docxedwardmarivel
 
DB3.1 Mexico corruptionDiscuss the connection between pol.docx
DB3.1 Mexico corruptionDiscuss the connection between pol.docxDB3.1 Mexico corruptionDiscuss the connection between pol.docx
DB3.1 Mexico corruptionDiscuss the connection between pol.docxedwardmarivel
 
DB2Pepsi Co and Coke American beverage giants, must adhere to th.docx
DB2Pepsi Co and Coke American beverage giants, must adhere to th.docxDB2Pepsi Co and Coke American beverage giants, must adhere to th.docx
DB2Pepsi Co and Coke American beverage giants, must adhere to th.docxedwardmarivel
 
DB1 What Ive observedHave you ever experienced a self-managed .docx
DB1 What Ive observedHave you ever experienced a self-managed .docxDB1 What Ive observedHave you ever experienced a self-managed .docx
DB1 What Ive observedHave you ever experienced a self-managed .docxedwardmarivel
 
DB Response 1I agree with the decision to search the house. Ther.docx
DB Response 1I agree with the decision to search the house. Ther.docxDB Response 1I agree with the decision to search the house. Ther.docx
DB Response 1I agree with the decision to search the house. Ther.docxedwardmarivel
 
DB Response prompt ZAKChapter 7, Q1.Customers are expecting.docx
DB Response prompt  ZAKChapter 7, Q1.Customers are expecting.docxDB Response prompt  ZAKChapter 7, Q1.Customers are expecting.docx
DB Response prompt ZAKChapter 7, Q1.Customers are expecting.docxedwardmarivel
 
DB Topic of Discussion Information-related CapabilitiesAnalyze .docx
DB Topic of Discussion Information-related CapabilitiesAnalyze .docxDB Topic of Discussion Information-related CapabilitiesAnalyze .docx
DB Topic of Discussion Information-related CapabilitiesAnalyze .docxedwardmarivel
 
DB Instructions Each reply must be 250–300 words with a minim.docx
DB Instructions Each reply must be 250–300 words with a minim.docxDB Instructions Each reply must be 250–300 words with a minim.docx
DB Instructions Each reply must be 250–300 words with a minim.docxedwardmarivel
 
DB Defining White Collar CrimeHow would you define white co.docx
DB Defining White Collar CrimeHow would you define white co.docxDB Defining White Collar CrimeHow would you define white co.docx
DB Defining White Collar CrimeHow would you define white co.docxedwardmarivel
 
DAVID H. ROSENBLOOMSECOND EDITIONAdministrative Law .docx
DAVID H. ROSENBLOOMSECOND EDITIONAdministrative Law .docxDAVID H. ROSENBLOOMSECOND EDITIONAdministrative Law .docx
DAVID H. ROSENBLOOMSECOND EDITIONAdministrative Law .docxedwardmarivel
 
DB ASSIGNMENTFor this Discussion Board you will be developing a th.docx
DB ASSIGNMENTFor this Discussion Board you will be developing a th.docxDB ASSIGNMENTFor this Discussion Board you will be developing a th.docx
DB ASSIGNMENTFor this Discussion Board you will be developing a th.docxedwardmarivel
 

More from edwardmarivel (20)

deadline 6 hours 7.3 y 7.47.4.docx
deadline  6 hours 7.3 y 7.47.4.docxdeadline  6 hours 7.3 y 7.47.4.docx
deadline 6 hours 7.3 y 7.47.4.docx
 
DEADLINE 15 HOURS6 PAGES UNDERGRADUATECOURSEWORKHARV.docx
DEADLINE 15 HOURS6 PAGES UNDERGRADUATECOURSEWORKHARV.docxDEADLINE 15 HOURS6 PAGES UNDERGRADUATECOURSEWORKHARV.docx
DEADLINE 15 HOURS6 PAGES UNDERGRADUATECOURSEWORKHARV.docx
 
De nada.El gusto es mío.Encantada.Me llamo Pepe.Muy bien, grac.docx
De nada.El gusto es mío.Encantada.Me llamo Pepe.Muy bien, grac.docxDe nada.El gusto es mío.Encantada.Me llamo Pepe.Muy bien, grac.docx
De nada.El gusto es mío.Encantada.Me llamo Pepe.Muy bien, grac.docx
 
DDBA 8307 Week 4 Assignment TemplateJohn DoeDDBA 8.docx
DDBA 8307 Week 4 Assignment TemplateJohn DoeDDBA 8.docxDDBA 8307 Week 4 Assignment TemplateJohn DoeDDBA 8.docx
DDBA 8307 Week 4 Assignment TemplateJohn DoeDDBA 8.docx
 
DDL 24 hours reading the article and writing a 1-page doubl.docx
DDL 24 hours reading the article and writing a 1-page doubl.docxDDL 24 hours reading the article and writing a 1-page doubl.docx
DDL 24 hours reading the article and writing a 1-page doubl.docx
 
DCF valuation methodSuper-normal growth modelApplicatio.docx
DCF valuation methodSuper-normal growth modelApplicatio.docxDCF valuation methodSuper-normal growth modelApplicatio.docx
DCF valuation methodSuper-normal growth modelApplicatio.docx
 
ddr-.docx
ddr-.docxddr-.docx
ddr-.docx
 
DDBA 8307 Week 2 Assignment ExemplarJohn Doe[footnoteRef1] .docx
DDBA 8307 Week 2 Assignment ExemplarJohn Doe[footnoteRef1] .docxDDBA 8307 Week 2 Assignment ExemplarJohn Doe[footnoteRef1] .docx
DDBA 8307 Week 2 Assignment ExemplarJohn Doe[footnoteRef1] .docx
 
DBM380 v14Create a DatabaseDBM380 v14Page 2 of 2Create a D.docx
DBM380 v14Create a DatabaseDBM380 v14Page 2 of 2Create a D.docxDBM380 v14Create a DatabaseDBM380 v14Page 2 of 2Create a D.docx
DBM380 v14Create a DatabaseDBM380 v14Page 2 of 2Create a D.docx
 
DBA CAPSTONE TEMPLATEThe pages in this template are correctl.docx
DBA CAPSTONE TEMPLATEThe pages in this template are correctl.docxDBA CAPSTONE TEMPLATEThe pages in this template are correctl.docx
DBA CAPSTONE TEMPLATEThe pages in this template are correctl.docx
 
DB3.1 Mexico corruptionDiscuss the connection between pol.docx
DB3.1 Mexico corruptionDiscuss the connection between pol.docxDB3.1 Mexico corruptionDiscuss the connection between pol.docx
DB3.1 Mexico corruptionDiscuss the connection between pol.docx
 
DB2Pepsi Co and Coke American beverage giants, must adhere to th.docx
DB2Pepsi Co and Coke American beverage giants, must adhere to th.docxDB2Pepsi Co and Coke American beverage giants, must adhere to th.docx
DB2Pepsi Co and Coke American beverage giants, must adhere to th.docx
 
DB1 What Ive observedHave you ever experienced a self-managed .docx
DB1 What Ive observedHave you ever experienced a self-managed .docxDB1 What Ive observedHave you ever experienced a self-managed .docx
DB1 What Ive observedHave you ever experienced a self-managed .docx
 
DB Response 1I agree with the decision to search the house. Ther.docx
DB Response 1I agree with the decision to search the house. Ther.docxDB Response 1I agree with the decision to search the house. Ther.docx
DB Response 1I agree with the decision to search the house. Ther.docx
 
DB Response prompt ZAKChapter 7, Q1.Customers are expecting.docx
DB Response prompt  ZAKChapter 7, Q1.Customers are expecting.docxDB Response prompt  ZAKChapter 7, Q1.Customers are expecting.docx
DB Response prompt ZAKChapter 7, Q1.Customers are expecting.docx
 
DB Topic of Discussion Information-related CapabilitiesAnalyze .docx
DB Topic of Discussion Information-related CapabilitiesAnalyze .docxDB Topic of Discussion Information-related CapabilitiesAnalyze .docx
DB Topic of Discussion Information-related CapabilitiesAnalyze .docx
 
DB Instructions Each reply must be 250–300 words with a minim.docx
DB Instructions Each reply must be 250–300 words with a minim.docxDB Instructions Each reply must be 250–300 words with a minim.docx
DB Instructions Each reply must be 250–300 words with a minim.docx
 
DB Defining White Collar CrimeHow would you define white co.docx
DB Defining White Collar CrimeHow would you define white co.docxDB Defining White Collar CrimeHow would you define white co.docx
DB Defining White Collar CrimeHow would you define white co.docx
 
DAVID H. ROSENBLOOMSECOND EDITIONAdministrative Law .docx
DAVID H. ROSENBLOOMSECOND EDITIONAdministrative Law .docxDAVID H. ROSENBLOOMSECOND EDITIONAdministrative Law .docx
DAVID H. ROSENBLOOMSECOND EDITIONAdministrative Law .docx
 
DB ASSIGNMENTFor this Discussion Board you will be developing a th.docx
DB ASSIGNMENTFor this Discussion Board you will be developing a th.docxDB ASSIGNMENTFor this Discussion Board you will be developing a th.docx
DB ASSIGNMENTFor this Discussion Board you will be developing a th.docx
 

Recently uploaded

Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
The byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxThe byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxShobhayan Kirtania
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajanpragatimahajan3
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 

Recently uploaded (20)

Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
The byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxThe byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptx
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajan
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 

Deadline 6 PM Friday September 27, 201310 Project Management Que.docx

  • 1. Deadline 6 PM Friday September 27, 2013 10 Project Management Questions with sub-questions under each question. A word document is provided with all questions and directions. Problem 1 The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days
  • 2. A, B E 3 Days C F 5 Days D G 5 Days E, F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: a) What is the Scheduled Completion of the Project? b)
  • 3. What is the Critical Path of the Project? c) What is the ES for Activity D? d) What is the LS for Activity G? e) What is the EF for Activity B? f) What is the LF for Activity H? g) What is the float for Activity I? Problem 2 The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A
  • 4. 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G
  • 5. 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: a) Calculate the scheduled completion time. b) Identify the critical path c) What is the slack time (float) for activity A?
  • 6. d) What is the slack time (float) for activity D? e) What is the slack time (float) for activity E? f) What is the slack time (float) for activity G? Problem 3 The following data were obtained from a project to design a new software package: Activity Duration Predecessors A 5 Days --- B 8 Days --- C 6 Days
  • 7. A D 4 Days C, B E 5 Days A F 4 Days D, E, G G 4 Days B, C H 3 Day G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: a)
  • 8. Calculate the scheduled completion time. b) Identify the critical path(s) c) What is the slack time (float) for activity B? d) What is the slack time (float) for activity D? e) What is the slack time (float) for activity E? f) What is the slack time (float) for activity G? Problem 4 The following data were obtained from an in-house MIS project: Activity Duration Predecessors A
  • 9. 5 Days --- B 8 Days --- C 5 Days A D 4 Days B E 5 Days B F 3 Day C, D
  • 10. G 7 Days C, D H 6 Days E, F, G I 9 Days E, F Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: a) Calculate the scheduled completion time. b) Identify the critical path c) What is the slack time (float) for activity A? d)
  • 11. What is the slack time (float) for activity D? e) What is the slack time (float) for activity E? f) What is the slack time (float) for activity F? PROBLEM 5 Use the network diagram below and the additional information provided to answer the corresponding questions. a) Give the crash cost per day per activity. b) Which activities should be crashed to meet a project deadline of 10 days at minimum cost? What is the cost impact of crashing these activities? c) Find the new budget (or cost of the project). PROBLEM 6 Use the network diagram below and the additional information provided to answer the corresponding questions.
  • 12. a) Give the crash cost per day per activity. b) Which activities should be crashed to meet a project deadline of 13 days at minimum cost? What is the cost impact of crashing these activities? PROBLEM 7 Month AC PV EV 22 $540 $523 $535 a) Calculate the cost variance (CV). b) Is the CV over or under budget? c) Calculate the schedule variance (SV). d)
  • 13. Is the SV ahead of or behind schedule? PROBLEM 8 Month AC PV EV 5 $34 $42 $39 a) Calculate the cost performance index (CPI). b) Is the project cost efficient or not efficient? c) Calculate the schedule performance index (SPI). d) Is the schedule efficient or not efficient? PROBLEM 9 [8 points]
  • 14. Day AC PV EV 65 $550 $735 $678 a) Calculate the cost variance (CV). b) Calculate the cost performance index (CPI). c) Calculate the schedule variance (SV). d) Calculate the schedule performance index (SPI). e) Given these data, what should a project manager do with respect to this project?
  • 15. PROBLEM 10 Day AC PV EV 65 $760 $735 $678 a) Calculate the cost variance (CV). b) Calculate the cost performance index (CPI). c) Calculate the schedule variance (SV). d) Calculate the schedule performance index (SPI). e) Explain the project performance in terms of efficiency, budget, and schedule. What should the project manager do for the project?