6. Enterprise Resource Planning
A system of interconnected data tables
(usually using the general ledger as its
‘backbone’) driven by an MRP/MRPII
calculation engine.
admission.edhole.com
7. Material Requirements Planning
A system for determining the quantity and
timing requirements for materials used in
a production operation.
admission.edhole.com
8. Manufacturing Resource Planning
An expanded system for determining
manufacturing resource requirements and
for scheduling production.
admission.edhole.com
9. Just-in-Time
A system for producing and delivering the right
items at the right time in the right amounts
Key elements of Just-in-Time are flow, pull,
standard work, and takt time
admission.edhole.com
10. A precise description of each work activity
specifying cycle time, takt time, the work
sequence of specific tasks, and the minimum
inventory of parts on hand needed to conduct
the activity.
admission.edhole.com
11. An important concept in pacing operations
The “heartbeat” of a lean system
Takt time = (available
production time) / (rate of customer
demand)
Example: Customer demand is eight widgets per
day. The plant operates 16 hours per day. Takt
time is two hours (16/8 = 2).
admission.edhole.com
12. A card attached to boxes of parts that regulates pull
in the Lean System by signaling upstream
production and delivery.
admission.edhole.com
14. A system of cascading production and delivery
instructions from downstream to upstream
activities in which nothing is produced by the
upstream supplier until the downstream
customer signals a need.
Nothing is produced without a signal from the
next station in the line.
admission.edhole.com
15. Single piece flow
Eliminate bureaucracy, departmentalization
Eliminate batch and queue
admission.edhole.com
16. Tear out conveyors (moving warehouses)
Adopt a just-do-it mindset
Focus on value
admission.edhole.com
17. Created by the producer
May be hard for producers to define
Can only be defined by the final customer
admission.edhole.com
18. The irreducible minimum set of activities
needed to design, order, and make a machine –
flowing smoothly, continuously, and rapidly
admission.edhole.com
19. Raw material to finished good
Order to delivery
Concept to launch
admission.edhole.com
20. Any activity that consumes resources but creates
no value is waste (muda)
admission.edhole.com
22. Arrange production by specific products
Identify the value stream for each product
Make value flow without interruptions
Let the customer pull value from the producer
Pursue perfection
admission.edhole.com
23. Don’t make anything until it is needed and
then make it very quickly.
Schedule changes may be made almost
instantaneously upon order receipt.
Quality improves as pull thinking is
introduced.
admission.edhole.com
24. Don’t build inventory
Right size tools to fit product lines
Reduce set-up times
Use statistical process control to achieve zero
defects
Implement planned maintenance
Get frequent deliveries from suppliers
admission.edhole.com
25. While periodic review of Kanban lot size is
necessary and desirable, resizing lots to meet
large fluctuations - highly variable demand
and/or rapidly shifting supply chain
uncertainty is difficult
Kanban doesn’t work well when there in a
highly variable system
admission.edhole.com
26. Forecast
Customer orders
MPS
Exploded BOM
MRP calculation
“X”% Leadtime*units-netable-on order
Purchase analysis
Order generation (PO) & order tracking
admission.edhole.com
27. Replenishment
a non-value activity
a gating factor to manufacturing
a significant factor in cash flow management
directly impacts profits
admission.edhole.com
28. ERP/MRP II
MRP engine
Push system
Reorder Point
Kanban
Market signal driven
Pull system
admission.edhole.com
29. Positives
Quick, efficient
recalculation of
requirements
Vendor & lot tracking
Enterprise visibility
Auto updates
financial records
Negatives
High overall effort
and maintenance
Plan driven vs. direct
market input driven
Susceptible to
forecast error
MRPII machine
centers scheduled in
series
admission.edhole.com
30. Positives
Reduces point-of-use
effort
Highly visible to
production
Negatives
Creates need for
system entries in other
areas of company
Reduced visibility
throughout
organization
admission.edhole.com
31. MRP
Complex
Fluctuating Demand
Auto adjusts req’s
Robust system
reporting and analysis
Kanban
Simple
Linear Demand
Kanban size adjusted
manually
No system reporting
admission.edhole.com
32. Uncouple the MRP engine from the ERP
system using Kanban practices in place of
MRP/MRPII to:
trigger production
move materials through plant
Continue to use ERP to:
track vendors and/or lots
update financials
provide enterprise visibility
make particular calculations
admission.edhole.com
33. Install/Configure ERP Kanban module
To resize Kanban lots
To calculate order quantities
Use ERP
To print Kanban cards
To auto update financials, material movement and
production status using barcode scans, RFID, etc.
To update vendor files
admission.edhole.com
35. Massive inventories
Large batches
Long machine changeovers
Push production system
Slow response to customers (long lead times)
admission.edhole.com
37. Welding booth is given the daily schedule
Empty parts tub with Kanban (signal card)
slides to stamping press from welding booth
When stamping press uses up blanks, empty
parts tub is sent down the slide to the blanking
press
admission.edhole.com
38. Blanking Stamping Welding FG
Blue Arrows = Movement of parts
Green Arrows = Circulation of
Kanban
Circles = Machines/
Work Cell
Triangles = Buffers
Finished Goods Inventory
admission.edhole.com
39. MRP system had sent orders to every machine
but expediting was always needed
WIP inventories used to get out of balance (e.g.,
Blanking would run to schedule even if
Welding was down)
MRP system is no longer required to drive the
system and becomes a calculation tool
admission.edhole.com
40. Shipping schedule drives production
Takt time paces the lines
Right sizing of equipment
admission.edhole.com
41. Long lead times
Complex production processes
Product variety
Batch production
Large WIP and finished inventories
admission.edhole.com
42. Master Schedule worked out by the Scheduling
Dept. based on sales forecasts
Ever changing demands from the Sales Dept.
intent on pleasing customers
admission.edhole.com
43. Sales tries to beat the system and enters orders
based on speculation
Sales alters options requested when the real
order is received
Expediters move through the plant with a “hot
list” for overdue orders
admission.edhole.com
44. Company made money despite its weaknesses
•Suddenly, low priced competition
entered the market
admission.edhole.com
45. Reorganization by standards or specials
Team orientation
Customer focus
MRP system with real time data input
admission.edhole.com
46. Conversion from a batch and queue system to a
flow organization
Single piece flow (no buffer stock)
Value stream
One machine, one design, one order at a time
The Result:
Production lead time reduced
from 16 weeks to 14 hours
admission.edhole.com
47. MRP system retained for long-term ordering of
materials
Day-to-day scheduling now run off a large
whiteboard
Production day divided into slots by takt times
Orders written on the whiteboard as they are
confirmed
admission.edhole.com
48. Nothing produced without a confirmed order
Management Information Systems department
was eliminated
Parts within the plant are pulled to the next
station automatically
Product and information are combined
admission.edhole.com
49. People missed the excitement of fire fighting
Lean operations revealed problems that had
been covered up by high inventory levels
Deliveries of purchased components to the cells
were not dependable
admission.edhole.com
50. Will the company honor its commitment to
retain excess workers?
Will contributions to improvement activities be
recognized and rewarded?
People ask, “What will the changes mean for
my career?”
admission.edhole.com
51. Large inventories
Enormous batches
MRP system with 50% extra margin added to
safety stocks
Machine maintenance neglected
admission.edhole.com
52. MPS used forecasts to ensure finished goods
were on hand in a huge warehouse
Orders were processed in a batch mode
Few orders were shipped complete
Large customer service department was
required to keep track and expedite orders
Many potential sources for errors
admission.edhole.com
53. Implementation not understood
Didn’t know how to reduce changeover times
Difficulty creating to a level schedule
Large inventories had glossed over problems
Express freight to make deliveries
Added customer service staff to explain later
deliveries
admission.edhole.com
54. Value creating jobs
Non-value creating jobs – but currently
necessary to run the business
Non-value creating and unnecessary jobs
admission.edhole.com
55. Fear of job loss can derail the conversion
to lean – taking away fear of job loss is at
the core of a lean conversion.
admission.edhole.com
56. Manager’s should personally lead the
implementation activities
Manager’s need to go out to the shop floor to
work hands-on making improvements
The more senior the better - They need to see
the waste and understand where change is
needed
admission.edhole.com
57. Assembly activity no longer dependent upon a
department for material
Before, the master schedule generated by the
MRP system might schedule other material
than that needed by the line
admission.edhole.com
58. Order-receipt-to-ship time reduced from more
that a week to less than a day
As shipper withdrew parts from finished stock
racks, this became the signal to make more of a
given part
Fewer people & fewer errors
Instead of one month batches, parts
were produced every day
admission.edhole.com
59. Formerly kept track of the movements of
individual parts
Now given the smaller task of long-term
capacity planning
Also required to order parts from suppliers not
yet on pull systems
admission.edhole.com
60. Just-do-it mind set
Kaizen philosophy
Group technology (cells)
Work with HR
Management involvement
Improved maintenance
Blend systems when & where appropriate
admission.edhole.com
61. Lean manufacturing can:
simplify operations and improve control
reduce inventories and improve cash flow
reduce lead times
Set-up times must be reduced for lean to work
to be able to reduce lot sizes
As internal issues are addresses – look to
include vendors
admission.edhole.com
62. Lean manufacturing:
offers greater responsiveness and therefore better
customer satisfaction
identifies mistakes quickly
helps to identify muda (waste)
is applicable to other areas of the firm in addition to
production
MRP still may be used to maintain inventories,
but in a reduced role
admission.edhole.com
MRP is the scheduling and inventory management portion of the ERP system.
MRP is the scheduling and inventory management portion of the ERP system.
MRP II includes capacity planning tools, a financial interface to translate operations planning into financial terms, and a simulation tool to assess alternative production plans.
JIT is part of the lean manufacturing system
Three typical areas for lean.
The antidote to muda: lean thinking
Product groups – group technology.
Outdated thinking about economics of scale.
The Kanban drives the pull system. Welding gets the schedule and sends the Kanban with the parts tub back to the stamping press. The stamping press sends the empty parts tub to the blanking press.
Machines should be available for production about 90% of the time and down for change-over 10% of the time, according to Toyota.
Patents were circumvented.
Chronological list of interventions designed to meet the low cost competition.
MRP with data entry in real time was “muda to the people.”
New computer, large data entry department.
Distributors and buyers of industrial equipment were unaccustomed to getting deliveries quickly.
There is a rush that comes from having to meet a deadline. Quality problems are especially hidden by high inventories. There was a touchup department that fixed up the nicks and scratches that are incurred during movement and storage.
Lean but not mean.
A manufacturer of electrical building materials used an MRP system. The large inventories masked quality problems and maintenance issues such as worn cutting tools, etc.
Three types of jobs
You can’t expect cooperation if people are concerned about their job security. Who will work to eliminate their own job?
Department means a shared functional department, e.g., fabrication.
Other areas for lean include order entry and design processes.