SlideShare a Scribd company logo
1 of 3
Download to read offline
August 2010, Kathmandu


                                                                                    Surakshit Samudaya II
                                                                                    Building Disaster Resilient Communities, Nepal

                                                          Second Review Meeting Report
                                                                                                                                 13-14 August 2010

                                                                                                                       ActionAid Nepal DIPECHO Project Publication



PROJECT AT A GLANCE                                   The Context
        Project Area:                                 ActionAid has been implementing            As a continuous process of Review and
            Banke                                     the project titled Surakshit               Reflection, the Second Review Meeting
           Sunsari                                    Samudaya II: Building disaster-            for ActionAid and its partners under
          Udayapur
                                                                                                                                                   Disaster
                                                      resilient communities, Nepal in            DIPECHO project was held during 13-14
                                                                                                                                               Management is
                                                      three districts of Nepal aiming to         August 2010 in Hotel Royal Century,
     Partner NGOs:                                                                                                                           one and only issue
                                                      increase disaster resilience of the        Chitwan. All the DIPECHO team and
       BEE Group                                                                                                                               on which there
                                                      target communities through                 PNGO heads attended the meeting.
      UPCA Nepal
                                                      awareness, capacity building,                                                             must not be
        NP Nepal                                                                                                                                rivalries. DM
                                                      enabling policy environment and            The review meeting is done as a part of
    Co-Action Nepal                                                                                                                          requires initiatives
                                                      vulnerability reduction.                   the approach of ActionAid to undergo a
                                                                                                 cycle of Action-Reflection-Action. The       of multi-sectors
       Beneficiaries:
                                                      AAN received funding from                  meeting is one of the key activities of          and thus,
       13,854 people
                                                      European Commission Humanitarian           the DIPECHO project towards reviewing        multi-institutions
          Budget:                                     Aid department to implement the            the partners program and financial               including
        441,330 Euro                                  17 months project. The project is          performance, drawing key lessons,              government,
                                                      co-financed by Australian                  building team spirit and revisit the         non-government
          Start Date:                                 Government through AusAid and              planning with enhanced commitments.           and the private
          01 July 2009                                implemented by ActionAid in Nepal                                                            sectors.
                                                      in partnership with local NGOs.
            Duration:
            17 months

For more details, contact:                            Objectives, Methodology & Expected Outcome
    ActionAid Nepal
     Ph: 01-4436477
    Fax: 01-4419718                                   Objective of the meeting              Expected outcome                      Enough room was provided to
                                                      The overall objective of the                                                each participants for personal
                                                                                            Participants will have the            as well as project reflections.
                                                      meeting was to enhance                collective learning and sharing
   The Second Review Meet (SRM) of AAN DIPECHO V




                                                      culture of shared learning and        experience. Learning from the         Facilitators
                                                      team building.
      Project was intended to take stock of project




                                                                                            field application will be shared      The workshop was jointly
                                                                                            and documented. The meeting           facilitated by AAN DIPECHO
                                                      The specific objectives were:         will also finalize revised targets
                                                      a) To report progress made                                                  team: P. V. Krishnan, Shyam
                                                                                            for remaining period. Also the
              performance for the period




                                                          by the project, share and                                               Sunder Jnavaly, Ashok Raj
                                                                                            case studies will be prepared
                (July 2009 to July 2010)




                                                          analyse the key outcomes                                                Pokharel, Shaurabh Sharma &
                                                                                            and documented.                       Ms. Pratima Shrestha
                                                          and results
                                                      b) To analyse the outputs vs.         Meeting Methodology
                                                          outcomes till the period of
                                                          the project and make              The review meeting applied               Key outcome of the SRM
                                                          necessary adjustments in          various methodologies
                                                          implementation methods            including lecture, anticipatory       PROJECT PROGRESS
                                                          to ensure that quality and        group discussion and                  REVIEWED AND STOCK WAS
                                                                                                                                  TAKEN
                                                          efficiency are maintained         presentation, power point
                                                      c) To review and re-schedule          presentation, case study write        CASE STUDIES PREPARED
                                                          the targets for the final         shop, individual reflection and
                                                          quarter                           interactive planning sessions.        PLANNED FOR REMAINDER
                                                                                            The meeting was organized to          PERIOD & WAY FORWARD
                                                                                            in such a way to make able all
                                                                                            the participants take part.
Surakshit Samudaya II: Building Disaster Resilient Communities, Nepal

Participants




UPCA: Mr. Yash Prasad Subba, Mr. Shiva Hari Khatiwada, Mr. Dev Narayan Sharma, Ms. Manmaya Niraula, Ms. Parbati Limbu, Ms. Khadga K.
Magar, Ms. Kamali Chaudhary, Ms. Rita Chaudhary, Ms. Sarita, Mr. Sultan Alam, Mr. Keshav Neupane, Ms. Ranjana K. Yadav, Ms. Anita Gupta
NP: Mr. Durga Nanda Chaudhary, Mr. Santosh Singh, Ms. Krishna Raut, Ms. Nirmala Budhathoki, Ms. Sarita Chaudhary Co-Action: Mr. Deepak
Acharya, Mr. Bishnu Hari Wagle BEE Group: Mr. Gopal Nath Yogi, Mr. Dillu Ram Ghimire, Mr. Dinesh Chaudhary, Mr. Ram Yadav, Mr.
Makbool Mukeri, Mr. Man Bahadur Rana, Ms. Ajita Godiya, Ms. Haseena Bano Mukeri, Ms. Shanti Devi Mourya, Ms. Ramkumari Harijan
AAN: Mr. P.V.Krishnan, Mr. Shyam S. Jnavaly, Mr. Ashok Raj Pokharel, Ms. Pratima Shrestha, Mr. Saurav Sharma, Mr. Surendara B. Bam, Mr.
Suresh Raut, Mr. Binod K. Timilsena, and Mr. Nanda Kandangwa


Meeting procedure and outcome
The meeting objectives, agendas and         financial performance along with the          were discussed. The presentation made
structure were prepared in the advance      project target exercise was also carried      clarity to the participants on gauzing the
for efficient execution of the meeting.     out.                                          project performance with the HFA
Hence, the meeting followed a               Citing the changes made by the project        priorities. In the meantime, international
structured agenda. The sessions were        The review meeting also tried to assess       scenario of increased disaster events and
divided logically so as to draw             the changes the project has been making       humanitarian challenges were also
achievement in both qualitative and         to people’s lives. In this session, a short   discussed.
quantitative terms. Apart from the          discussion on writing good case study
review, a knowledge session on HFA                                                        Way forward
                                            was held. All the Reflect facilitators who    Based on discussions and deliberations, the
was also discussed to enhance               brought their one story of change they
knowledge and capacity of staffs on it.                                                   PNGOs prepared the work plan for
                                            have witnessed, with detailed evidence        remainder of the project period aiming to
Project & Financial Performance             on the impact the project has made on         effectively accomplish objectives was one of
Review                                      the lives of people has to be edited by       the key way forward.
The first day was focused on to present     their own. A total of 12 stories were
and discuss on achievements against set     generated.                                    It was agreed that building linkages of
project milestones. The 7 crucial                                                         disaster management committee with local
                                            Hyogo Framework for Action                    government planning, and district/national
questions were asked to discuss in the
groups. The presentation was followed       A session was taken to discuss on how         networks are utmost important in coming
by discussions, seeking clarifications on   we internalize HFA in our projects. A         days for exit and sustainability of the
the achievements, and learning. The         brief introduction to HFA, HFA five           project.
                                            priorities and indicators to the priorities
Surakshit Samudaya II: Building Disaster Resilient Communities, Nepal


Key project achievements
1. Project communities are aware about hazards, vulnerability, and risk of disasters. And their
   perception and belief on disaster preparedness is changed positively
        Examples: People are aware on safe place inside and outside home, regular discussion and update on vulnerability
        map, local youth mobilized in street drama, women reaching to different service providers/VDCs etc


2. Family level disaster preparedness is in place
        Examples: Important documents like citizenship, land registration, birth registration, mark-sheet etc are kept in
        plastic folders, preparedness according to monthly calendar, one bucket of water storage, ensure extinguishing
        fire after use etc.

3. Collective initiatives for coping with upcoming disasters
        Examples: Disaster management committees and task forces are active during recent flood; used early warning
        system; community level search and rescue operation; first aid work in the community; constructed safe exits, rice
        grain collection as a campaign; established disaster relief fund; prepared contingency plans etc.

4. Government and other stakeholders are informed and supportive
        Examples: MOHA/MOLD/NPC are working together with AAN; DDC and DWIDP join hands to make bio-dyke; VDC
        allocated resources to community level DM fund; A VDC allocated DRM fund; Two VDCs requested PNGOs to
        prepare VDC level contingency plan; clustered response in recent Sunsari flood;


5. Substantive progress towards enabling DRM policies
        Examples: National Disaster Risk Management Strategy 2009 enforced; commitment of government officials and
        constituent assembly members to bill the proposed Disaster Management Act; provision of disaster focal persons in
        concerned line ministries and line agencies; VDC secretaries trained on DRR in project districts; joint initiatives of
        DRM stakeholders in making DRR tool kit



Key learning
                                                                        Apart from informing CA members/government
                                                                     officials/NGOs/journalist, the DRR policies have to be
                                                                          informed and discussed in the community for
  It is very good initiative to orient the VDC secretaries in                strengthening community led advocacy
       DRR so that it will help to mainstream DRR into
     development planning. However orientation is also
  required to VDC level political parties representatives to
   internalize mainstreaming the DRR into development.                Formalizing DRR in education sector is important to
                                                                       sustain child/parents learning in DRR. We need to
                                                                     develop local curriculum on DRR jointly with resource
                                                                             centers for modeling it in district level.
   Youth street drama group formation, DMC and task
    force mobilization, calendar, government resource
   mobilization in mitigation works are some of the good
                         practices.
                                                                     Our project works are based upon HFA principles and
  It is utmost important to give priority for local resource          priorities. We have been contributing the country in
      mobilization: human, material, skills etc in DRR                 achieving HFA, however we need to reflect upon
                                                                                    ourselves, where we are.

More Related Content

Similar to Srm brief report dipecho

Aan dipecho5 project brief july aug 09
Aan dipecho5 project brief july aug 09Aan dipecho5 project brief july aug 09
Aan dipecho5 project brief july aug 09DIPECHO Nepal
 
Dipecho v aan project brief july aug 09
Dipecho v aan  project brief july aug 09Dipecho v aan  project brief july aug 09
Dipecho v aan project brief july aug 09edmnepal
 
Aan dipecho v mtr report.doc
Aan dipecho v mtr report.docAan dipecho v mtr report.doc
Aan dipecho v mtr report.docedmnepal
 
Aan dipecho v mtr report.doc
Aan dipecho v mtr report.docAan dipecho v mtr report.doc
Aan dipecho v mtr report.docDIPECHO Nepal
 
D2 01 reca for resilience meeting_prasad_07_feb2013 [repaired]
D2 01 reca for resilience meeting_prasad_07_feb2013 [repaired]D2 01 reca for resilience meeting_prasad_07_feb2013 [repaired]
D2 01 reca for resilience meeting_prasad_07_feb2013 [repaired]RiskSquare
 
Dipecho v news letter 6th edition- april10
Dipecho v news letter  6th edition- april10Dipecho v news letter  6th edition- april10
Dipecho v news letter 6th edition- april10edmnepal
 
Dipecho5 news letter 6th edition- april10
Dipecho5 news letter  6th edition- april10Dipecho5 news letter  6th edition- april10
Dipecho5 news letter 6th edition- april10DIPECHO Nepal
 
Dipecho v aan reflect tot summary report
Dipecho v aan  reflect tot summary reportDipecho v aan  reflect tot summary report
Dipecho v aan reflect tot summary reportedmnepal
 
Amakuru ki i Rubavu Day 2
Amakuru ki i Rubavu Day 2Amakuru ki i Rubavu Day 2
Amakuru ki i Rubavu Day 2UNDP
 
Dipecho4 project summary
Dipecho4 project summaryDipecho4 project summary
Dipecho4 project summaryDIPECHO Nepal
 
Dipecho iv project summary
Dipecho iv project summaryDipecho iv project summary
Dipecho iv project summaryedmnepal
 
Dipecho drr managers meet 2009 report
Dipecho drr managers meet 2009 reportDipecho drr managers meet 2009 report
Dipecho drr managers meet 2009 reportDIPECHO Nepal
 
T L C Phil Newsletter
T L C  Phil  NewsletterT L C  Phil  Newsletter
T L C Phil NewsletterPsdmn Phil
 
Nepal final report echo evaluation
Nepal final report echo evaluationNepal final report echo evaluation
Nepal final report echo evaluationDIPECHO Nepal
 
Dipecho4 newsletter3rd oct08
Dipecho4 newsletter3rd oct08Dipecho4 newsletter3rd oct08
Dipecho4 newsletter3rd oct08DIPECHO Nepal
 
Csedu 2012 re act presentation v1
Csedu 2012 re act presentation v1Csedu 2012 re act presentation v1
Csedu 2012 re act presentation v1Pieter De Vries
 
Dipecho aan evaluation final report
Dipecho aan evaluation final reportDipecho aan evaluation final report
Dipecho aan evaluation final reportDIPECHO Nepal
 

Similar to Srm brief report dipecho (20)

Aan dipecho5 project brief july aug 09
Aan dipecho5 project brief july aug 09Aan dipecho5 project brief july aug 09
Aan dipecho5 project brief july aug 09
 
Dipecho v aan project brief july aug 09
Dipecho v aan  project brief july aug 09Dipecho v aan  project brief july aug 09
Dipecho v aan project brief july aug 09
 
Aan dipecho v mtr report.doc
Aan dipecho v mtr report.docAan dipecho v mtr report.doc
Aan dipecho v mtr report.doc
 
Aan dipecho v mtr report.doc
Aan dipecho v mtr report.docAan dipecho v mtr report.doc
Aan dipecho v mtr report.doc
 
D2 01 reca for resilience meeting_prasad_07_feb2013 [repaired]
D2 01 reca for resilience meeting_prasad_07_feb2013 [repaired]D2 01 reca for resilience meeting_prasad_07_feb2013 [repaired]
D2 01 reca for resilience meeting_prasad_07_feb2013 [repaired]
 
Dipecho v news letter 6th edition- april10
Dipecho v news letter  6th edition- april10Dipecho v news letter  6th edition- april10
Dipecho v news letter 6th edition- april10
 
Dipecho5 news letter 6th edition- april10
Dipecho5 news letter  6th edition- april10Dipecho5 news letter  6th edition- april10
Dipecho5 news letter 6th edition- april10
 
Aan pva
Aan pvaAan pva
Aan pva
 
Dipecho v aan reflect tot summary report
Dipecho v aan  reflect tot summary reportDipecho v aan  reflect tot summary report
Dipecho v aan reflect tot summary report
 
Amakuru ki i Rubavu Day 2
Amakuru ki i Rubavu Day 2Amakuru ki i Rubavu Day 2
Amakuru ki i Rubavu Day 2
 
Dipecho4 project summary
Dipecho4 project summaryDipecho4 project summary
Dipecho4 project summary
 
Dipecho iv project summary
Dipecho iv project summaryDipecho iv project summary
Dipecho iv project summary
 
Dipecho drr managers meet 2009 report
Dipecho drr managers meet 2009 reportDipecho drr managers meet 2009 report
Dipecho drr managers meet 2009 report
 
T L C Phil Newsletter
T L C  Phil  NewsletterT L C  Phil  Newsletter
T L C Phil Newsletter
 
TEEB in the ASEAN context - ASEAN Center for Biodiversity
TEEB in the ASEAN context - ASEAN Center for BiodiversityTEEB in the ASEAN context - ASEAN Center for Biodiversity
TEEB in the ASEAN context - ASEAN Center for Biodiversity
 
Nepal final report echo evaluation
Nepal final report echo evaluationNepal final report echo evaluation
Nepal final report echo evaluation
 
CFP Evaluation 2016
CFP Evaluation 2016CFP Evaluation 2016
CFP Evaluation 2016
 
Dipecho4 newsletter3rd oct08
Dipecho4 newsletter3rd oct08Dipecho4 newsletter3rd oct08
Dipecho4 newsletter3rd oct08
 
Csedu 2012 re act presentation v1
Csedu 2012 re act presentation v1Csedu 2012 re act presentation v1
Csedu 2012 re act presentation v1
 
Dipecho aan evaluation final report
Dipecho aan evaluation final reportDipecho aan evaluation final report
Dipecho aan evaluation final report
 

More from DIPECHO Nepal

0.1 disaster development
0.1 disaster development0.1 disaster development
0.1 disaster developmentDIPECHO Nepal
 
0.01 concept of dm may 2011
0.01 concept of dm may 20110.01 concept of dm may 2011
0.01 concept of dm may 2011DIPECHO Nepal
 
South asia women speak out on cca
South asia women speak out on ccaSouth asia women speak out on cca
South asia women speak out on ccaDIPECHO Nepal
 
Ids child no bleed nepali
Ids child no bleed nepaliIds child no bleed nepali
Ids child no bleed nepaliDIPECHO Nepal
 
Final report acorab drr programme
Final report  acorab drr programmeFinal report  acorab drr programme
Final report acorab drr programmeDIPECHO Nepal
 
Small scale mitigation report
Small scale mitigation reportSmall scale mitigation report
Small scale mitigation reportDIPECHO Nepal
 
Early warning system
Early warning systemEarly warning system
Early warning systemDIPECHO Nepal
 
Communication channel
Communication channelCommunication channel
Communication channelDIPECHO Nepal
 
Case study dipecho v upca
Case study dipecho v upcaCase study dipecho v upca
Case study dipecho v upcaDIPECHO Nepal
 
11 children and drr april 2010 english
11  children and drr april 2010 english11  children and drr april 2010 english
11 children and drr april 2010 englishDIPECHO Nepal
 
Nepal disaster risk_case_study
Nepal disaster risk_case_studyNepal disaster risk_case_study
Nepal disaster risk_case_studyDIPECHO Nepal
 
Mercy corps mc-cba-report-final-2010
Mercy corps mc-cba-report-final-2010Mercy corps mc-cba-report-final-2010
Mercy corps mc-cba-report-final-2010DIPECHO Nepal
 
Understanding disaster-management-in-practice
Understanding disaster-management-in-practiceUnderstanding disaster-management-in-practice
Understanding disaster-management-in-practiceDIPECHO Nepal
 
National platform on drr bidhan 2065 52
National platform on drr bidhan 2065 52National platform on drr bidhan 2065 52
National platform on drr bidhan 2065 52DIPECHO Nepal
 

More from DIPECHO Nepal (20)

0.1 disaster development
0.1 disaster development0.1 disaster development
0.1 disaster development
 
0.01 concept of dm may 2011
0.01 concept of dm may 20110.01 concept of dm may 2011
0.01 concept of dm may 2011
 
0.0 dev and drr
0.0 dev and drr0.0 dev and drr
0.0 dev and drr
 
South asia women speak out on cca
South asia women speak out on ccaSouth asia women speak out on cca
South asia women speak out on cca
 
Ids child no bleed nepali
Ids child no bleed nepaliIds child no bleed nepali
Ids child no bleed nepali
 
Final report acorab drr programme
Final report  acorab drr programmeFinal report  acorab drr programme
Final report acorab drr programme
 
School renovation
School renovationSchool renovation
School renovation
 
Small scale mitigation report
Small scale mitigation reportSmall scale mitigation report
Small scale mitigation report
 
Rambati case
Rambati caseRambati case
Rambati case
 
Early warning system
Early warning systemEarly warning system
Early warning system
 
Communication channel
Communication channelCommunication channel
Communication channel
 
Case study dipecho v upca
Case study dipecho v upcaCase study dipecho v upca
Case study dipecho v upca
 
Biodyke
BiodykeBiodyke
Biodyke
 
11 children and drr april 2010 english
11  children and drr april 2010 english11  children and drr april 2010 english
11 children and drr april 2010 english
 
Mason ort report
Mason ort reportMason ort report
Mason ort report
 
Inee nepal
Inee nepalInee nepal
Inee nepal
 
Nepal disaster risk_case_study
Nepal disaster risk_case_studyNepal disaster risk_case_study
Nepal disaster risk_case_study
 
Mercy corps mc-cba-report-final-2010
Mercy corps mc-cba-report-final-2010Mercy corps mc-cba-report-final-2010
Mercy corps mc-cba-report-final-2010
 
Understanding disaster-management-in-practice
Understanding disaster-management-in-practiceUnderstanding disaster-management-in-practice
Understanding disaster-management-in-practice
 
National platform on drr bidhan 2065 52
National platform on drr bidhan 2065 52National platform on drr bidhan 2065 52
National platform on drr bidhan 2065 52
 

Srm brief report dipecho

  • 1. August 2010, Kathmandu Surakshit Samudaya II Building Disaster Resilient Communities, Nepal Second Review Meeting Report 13-14 August 2010 ActionAid Nepal DIPECHO Project Publication PROJECT AT A GLANCE The Context Project Area: ActionAid has been implementing As a continuous process of Review and Banke the project titled Surakshit Reflection, the Second Review Meeting Sunsari Samudaya II: Building disaster- for ActionAid and its partners under Udayapur Disaster resilient communities, Nepal in DIPECHO project was held during 13-14 Management is three districts of Nepal aiming to August 2010 in Hotel Royal Century, Partner NGOs: one and only issue increase disaster resilience of the Chitwan. All the DIPECHO team and BEE Group on which there target communities through PNGO heads attended the meeting. UPCA Nepal awareness, capacity building, must not be NP Nepal rivalries. DM enabling policy environment and The review meeting is done as a part of Co-Action Nepal requires initiatives vulnerability reduction. the approach of ActionAid to undergo a cycle of Action-Reflection-Action. The of multi-sectors Beneficiaries: AAN received funding from meeting is one of the key activities of and thus, 13,854 people European Commission Humanitarian the DIPECHO project towards reviewing multi-institutions Budget: Aid department to implement the the partners program and financial including 441,330 Euro 17 months project. The project is performance, drawing key lessons, government, co-financed by Australian building team spirit and revisit the non-government Start Date: Government through AusAid and planning with enhanced commitments. and the private 01 July 2009 implemented by ActionAid in Nepal sectors. in partnership with local NGOs. Duration: 17 months For more details, contact: Objectives, Methodology & Expected Outcome ActionAid Nepal Ph: 01-4436477 Fax: 01-4419718 Objective of the meeting Expected outcome Enough room was provided to The overall objective of the each participants for personal Participants will have the as well as project reflections. meeting was to enhance collective learning and sharing The Second Review Meet (SRM) of AAN DIPECHO V culture of shared learning and experience. Learning from the Facilitators team building. Project was intended to take stock of project field application will be shared The workshop was jointly and documented. The meeting facilitated by AAN DIPECHO The specific objectives were: will also finalize revised targets a) To report progress made team: P. V. Krishnan, Shyam for remaining period. Also the performance for the period by the project, share and Sunder Jnavaly, Ashok Raj case studies will be prepared (July 2009 to July 2010) analyse the key outcomes Pokharel, Shaurabh Sharma & and documented. Ms. Pratima Shrestha and results b) To analyse the outputs vs. Meeting Methodology outcomes till the period of the project and make The review meeting applied Key outcome of the SRM necessary adjustments in various methodologies implementation methods including lecture, anticipatory PROJECT PROGRESS to ensure that quality and group discussion and REVIEWED AND STOCK WAS TAKEN efficiency are maintained presentation, power point c) To review and re-schedule presentation, case study write CASE STUDIES PREPARED the targets for the final shop, individual reflection and quarter interactive planning sessions. PLANNED FOR REMAINDER The meeting was organized to PERIOD & WAY FORWARD in such a way to make able all the participants take part.
  • 2. Surakshit Samudaya II: Building Disaster Resilient Communities, Nepal Participants UPCA: Mr. Yash Prasad Subba, Mr. Shiva Hari Khatiwada, Mr. Dev Narayan Sharma, Ms. Manmaya Niraula, Ms. Parbati Limbu, Ms. Khadga K. Magar, Ms. Kamali Chaudhary, Ms. Rita Chaudhary, Ms. Sarita, Mr. Sultan Alam, Mr. Keshav Neupane, Ms. Ranjana K. Yadav, Ms. Anita Gupta NP: Mr. Durga Nanda Chaudhary, Mr. Santosh Singh, Ms. Krishna Raut, Ms. Nirmala Budhathoki, Ms. Sarita Chaudhary Co-Action: Mr. Deepak Acharya, Mr. Bishnu Hari Wagle BEE Group: Mr. Gopal Nath Yogi, Mr. Dillu Ram Ghimire, Mr. Dinesh Chaudhary, Mr. Ram Yadav, Mr. Makbool Mukeri, Mr. Man Bahadur Rana, Ms. Ajita Godiya, Ms. Haseena Bano Mukeri, Ms. Shanti Devi Mourya, Ms. Ramkumari Harijan AAN: Mr. P.V.Krishnan, Mr. Shyam S. Jnavaly, Mr. Ashok Raj Pokharel, Ms. Pratima Shrestha, Mr. Saurav Sharma, Mr. Surendara B. Bam, Mr. Suresh Raut, Mr. Binod K. Timilsena, and Mr. Nanda Kandangwa Meeting procedure and outcome The meeting objectives, agendas and financial performance along with the were discussed. The presentation made structure were prepared in the advance project target exercise was also carried clarity to the participants on gauzing the for efficient execution of the meeting. out. project performance with the HFA Hence, the meeting followed a Citing the changes made by the project priorities. In the meantime, international structured agenda. The sessions were The review meeting also tried to assess scenario of increased disaster events and divided logically so as to draw the changes the project has been making humanitarian challenges were also achievement in both qualitative and to people’s lives. In this session, a short discussed. quantitative terms. Apart from the discussion on writing good case study review, a knowledge session on HFA Way forward was held. All the Reflect facilitators who Based on discussions and deliberations, the was also discussed to enhance brought their one story of change they knowledge and capacity of staffs on it. PNGOs prepared the work plan for have witnessed, with detailed evidence remainder of the project period aiming to Project & Financial Performance on the impact the project has made on effectively accomplish objectives was one of Review the lives of people has to be edited by the key way forward. The first day was focused on to present their own. A total of 12 stories were and discuss on achievements against set generated. It was agreed that building linkages of project milestones. The 7 crucial disaster management committee with local Hyogo Framework for Action government planning, and district/national questions were asked to discuss in the groups. The presentation was followed A session was taken to discuss on how networks are utmost important in coming by discussions, seeking clarifications on we internalize HFA in our projects. A days for exit and sustainability of the the achievements, and learning. The brief introduction to HFA, HFA five project. priorities and indicators to the priorities
  • 3. Surakshit Samudaya II: Building Disaster Resilient Communities, Nepal Key project achievements 1. Project communities are aware about hazards, vulnerability, and risk of disasters. And their perception and belief on disaster preparedness is changed positively Examples: People are aware on safe place inside and outside home, regular discussion and update on vulnerability map, local youth mobilized in street drama, women reaching to different service providers/VDCs etc 2. Family level disaster preparedness is in place Examples: Important documents like citizenship, land registration, birth registration, mark-sheet etc are kept in plastic folders, preparedness according to monthly calendar, one bucket of water storage, ensure extinguishing fire after use etc. 3. Collective initiatives for coping with upcoming disasters Examples: Disaster management committees and task forces are active during recent flood; used early warning system; community level search and rescue operation; first aid work in the community; constructed safe exits, rice grain collection as a campaign; established disaster relief fund; prepared contingency plans etc. 4. Government and other stakeholders are informed and supportive Examples: MOHA/MOLD/NPC are working together with AAN; DDC and DWIDP join hands to make bio-dyke; VDC allocated resources to community level DM fund; A VDC allocated DRM fund; Two VDCs requested PNGOs to prepare VDC level contingency plan; clustered response in recent Sunsari flood; 5. Substantive progress towards enabling DRM policies Examples: National Disaster Risk Management Strategy 2009 enforced; commitment of government officials and constituent assembly members to bill the proposed Disaster Management Act; provision of disaster focal persons in concerned line ministries and line agencies; VDC secretaries trained on DRR in project districts; joint initiatives of DRM stakeholders in making DRR tool kit Key learning Apart from informing CA members/government officials/NGOs/journalist, the DRR policies have to be informed and discussed in the community for It is very good initiative to orient the VDC secretaries in strengthening community led advocacy DRR so that it will help to mainstream DRR into development planning. However orientation is also required to VDC level political parties representatives to internalize mainstreaming the DRR into development. Formalizing DRR in education sector is important to sustain child/parents learning in DRR. We need to develop local curriculum on DRR jointly with resource centers for modeling it in district level. Youth street drama group formation, DMC and task force mobilization, calendar, government resource mobilization in mitigation works are some of the good practices. Our project works are based upon HFA principles and It is utmost important to give priority for local resource priorities. We have been contributing the country in mobilization: human, material, skills etc in DRR achieving HFA, however we need to reflect upon ourselves, where we are.