SESSION CODE: SC544
At the end of this session, you should be able to understand:
 Scheduling Challenges in Process Industry
 Ways to address scheduling challenges using SAP PP/DS
 Key Areas of Improvements required in SAP PP/DS
Learning Points
 About DuPont
 Detailed Scheduling in Integrated Business Planning
 Differences between Process and Discrete Manufacturing
 Scheduling Challenges in Process Industry
 Key Concerns
 Solution Review in SAP
 Key Areas of Improvements in SAP PP/DS
 Key Learnings
Agenda
© National Geographic image
DuPont is a Science Company
We work collaboratively to find sustainable, innovative, market-driven
solutions to solve some of the world’s biggest challenges, making lives
better, safer, and healthier for people everywhere.
Our Purpose
We are applying our science to find solutions to some really BIG
challenges…
FOOD ENERGY PROTECTION
FEEDING THE
WORLD
REDUCING OUR
DEPENDENCE ON
FOSSIL FUELS
KEEPING PEOPLE & THE
ENVIRONMENT SAFE
About DuPont
+
+
Improve
Customer
Experience
Reduce
Cost to Serve
Reduce
Inventory
From …
 High inventory
 Misaligned policies
 Non-productive inventory
 High complexity
 Manual interventions
 Numerous work around
 Significant expediting
 Inconsistent delivery
performance
 Difficulty meeting promises
 Significant churn and effort
To …
 Automated, streamlined,
rules based processes
 Reduced manufacturing
costs
 Reduced expediting costs
 Advantaged working
capital productivity
 Aligned E2E performance
 Capital available to re-
invest
 Reliable Supply
 Competitive LeadTimes
 Differentiated service
levels
DuPont’s Transformational Approach For Digital DuPont
 About DuPont
 Detailed Scheduling in Integrated Business Planning
 Differences between Process and Discrete Manufacturing
 Scheduling Challenges in Process Industry
 Key Concerns
 Solution Review in SAP
 Key Areas of Improvements in SAP PP/DS
 Key Learnings
Agenda
 To determine what to make, when to make, on which equipment to make
in a production facility
 Aims to maximize the efficiency of the operation at lowest possible costs
 The major inputs for Detailed Scheduling are:
 Master Production Schedule
 Demand Forecasts
 Sales
 Manufacturing
 Distribution
 Purchasing
What is Detailed Scheduling?
Goals of Detailed Scheduling
Detailed Scheduling in Integrated Business Planning
 About DuPont
 Detailed Scheduling in Integrated Business Planning
 Differences between Process and Discrete Manufacturing
 Scheduling Challenges in Process Industry
 Key Concerns
 Solution Review in SAP
 Key Areas of Improvements in SAP PP/DS
 Key Learnings
Agenda
Chemical, Food, and Beverage manufacturing processes are different from
automobile production!
Process Manufacturing vs. Discrete Manufacturing
Process Industry Discrete Industry
Production Product is manufactured by mixing,
blending and transforming chemicals,
liquids or food stuffs
Product is manufactured by assembly
of distinct items
Breaks or Stoppages Difficult and costly to Start & Stop.
Dependent on Production Sequence.
Easy to Start and Stop.
Independent of Production sequence.
Shortage of Input
Component
More Flexibility in altering production
lot size (above minimum) to continue
production
If sufficient quantity of components is
not available to assemble then
production must be halted.
Inventory Mainly maintained at Finished
Product level
Lot of Work-In-Progress inventory
Example Pharma, Food, Chemicals Automobile, High Tech
Material Flows are different in Process Industry and Discrete Industry requiring
different approach in Planning, Scheduling and Execution.
Process Manufacturing vs. Discrete Manufacturing
Discrete Industry
Forecast
Process Industry
Forecast Forecast Forecast
 About DuPont
 Detailed Scheduling in Integrated Business Planning
 Differences between Process and Discrete Manufacturing
 Scheduling Challenges in Process Industry
 Key Concerns
 Solution Review in SAP
 Key Areas of Improvements in SAP PP/DS
 Key Learnings
Agenda
Major Scheduling Challenges discussed are:
 Dealing with Uncertainties
 Setup optimization
 Production Quantity Constraints
 Multiple Stage Synchronization
 Resource (Machine) Constraints
Scheduling Challenges in Process Industry
Changes in Detailed Schedule are inevitable.
 Customers cancels or changes orders
 Suppliers have problems and miss delivery dates
 Machines break down or new machines are added, changing capacity
 Processes create more scrap than expected.
 Key Concerns:
 How to keep detailed schedule in sync
with planning and execution?
 How to balance competing goals?
 How to deal with uncertainties?
Dealing with Uncertainties in Detailed Scheduling
Scheduling Horizons – Aid to Decision Making
 Scheduling Horizons define artificial time boundaries used to separate periods
for planning or scheduling purposes.
 Used to establish policies to stabilize Detailed Schedule and Planning
Dealing with Uncertainties in Detailed Scheduling
 Frozen Horizon: Changes to DS are kept to a
minimum to avoid disruption to the production
schedule.
 Slushy Horizon: Changes to the detailed
schedule along with minor manual quantity
adjustment allowed.
 Liquid Horizon: Free to make changes in
detailed schedule as long as the schedule
remains within the production plan constraints
Dealing with Uncertainties in Detailed Scheduling
Horizon Purpose Where How
Frozen Schedule changes kept to a
minimum
Resource Detailed Scheduling Firming
Heuristics
Slushy Order in Slushy Horizon are
not changed by SNP
Product
Master
SNP Horizon Field
PP/DS Conversion of SNP Orders to
PP/DS Orders
Product
Master
PP/DS Horizon Field
Liquid MPS creates new orders to
respond to demand changes
Product
Master
Deletion job to delete the
orders beyond slushy horizon
Solution in SAP
Scope for improvements in SAP PP/DS
 If production is running behind, then detailed schedule must be updated to reflect
the new expected completion times. Current detailed scheduling heuristics does
not allow adjustment of backlog orders containing different phases within
operation.
Dealing with Uncertainties in Detailed Scheduling
Backlog Order
 A transition between products on a machine can incur a high cost or loss of large
amount of production time in setup.
 Sequence of manufacturing product influences production costs, setup times and
inventory levels and the goal is to balance the costs against inventory levels
while meeting demand.
Scheduling Challenge: Setup Optimization
 Key Concerns: How to create
a detailed schedule which
 Reduces setup cost
 Reduces setup time
 Meets customer demand
 Minimizes Inventory
Solution in SAP PP/DS
 SAP provides PPDS Optimization tool which can consider various trade offs
such as setup cost, setup time, delays and demand priority
 PP/DS Optimizer can create a schedule considering competing goals
 Automatic pickup of setup time based on predecessor product being
manufactured is supported in Detailed Scheduling Board
Scheduling Challenge: Setup Optimization
PP/DS Optimization profile for
Scheduling Trade Offs
Detailed Scheduling Board showing setup transition
Scope for Improvements in SAP
 Detailed Schedule prepared considering various trade offs is not aligned with
SNP planning as SNP optimization supports setup sequencing to a limited
extent.
 Transition materials produced during setup transition in process industry are not
supported in PP/DS.
 Modelling of costs in PP/DS Optimization to achieve the desired schedule is
challenging.
Scheduling Challenge: Setup Optimization
Sequencing of products at
regular interval.
A C B B A C SNP Orders
A A B B C C DS Order
(Current)
A B C A B C DS Order
( Expected)
Week 2
Modeling of PP/DS Optimization Costs is challening
Week 2
Week 2
Week 1
Week 1
Week 1
 Many factors affect quantity of product that can be produced at one time (Batch
Size, minimum campaign size, etc.)
 Process Industry have a lot of variation of production processes.
Key Concerns
 Batch Size: Consider minimum and maximum capacity requirements and align
with package size (increments of standard package).
 Intermittent Output: Product is produced in a continuous process with output at
regular time intervals. (e.g. 100 Gal every Hr)
 Minimum Input Quantity: A Product is produced in a continuous process and
order can not be started unless a minimum quantity (e.g. 200 Gal) of component
is available.
 Campaign lengths: Creating a campaign considering inter-dependency of semi-
finished product and finished product. (e.g. If semi-finished product order size
increased to meet lot size requirement then adjust the finished product order.)
Scheduling Challenge: Production Quantity Constraints
Scheduling Challenge: Production Quantity Constraints
Intermittent Output & Minimum Input Component Quantity
 Finished Good is produced in a continuous process.
 Finished Good order can not be started unless a minimum quantity (e.g. 200
Gal) of Semi-Finished Good is available.
 SFG is produced in an intermittent process with output at regular time intervals
Solution in SAP PP/DS
 SAP PP/DS supports scheduling of
continuous production with intermittent
output.
 PP/DS Optimizer can be used for
scheduling of continuous production.
Scheduling Challenge: Production Quantity Constraints
A10111000: Raw Material
B10111000: Semi-Finished
D10111000: Finished
After Scheduling main order output quantity is
spilt equivalent to required intermittent output.
FG Orders are scheduled based on continuous
production considering availability of minimum
input component quantity.
Scope for Improvements in SAP
Lot Size integration of Detailed Scheduling with SNP:
 In SNP optimization, its not possible to address lot size constraints if the input
data volume is large.
 Plan generated in SNP may be feasible but not always executable.
 If lot size is addressed in detailed scheduling, it may create infeasible plan
downstream.
 GR time is not supported in continuous output production which create
inconsistencies in execution and planning.
Scheduling Challenge: Production Quantity Constraints
Scheduling Challenge: Multiple Stage Synchronization
 The conversion of raw materials to finished products often consists of multiple
distinct manufacturing stages, either within a single site or across multiple
sites.
 When planning and scheduling these operations, synchronization between
stages and across multiple assets within the same stage must occur.
Key Concerns
 There is a scheduling dependencies between different levels of the BOM.
 Ideally, such products should be the part of the same manufacturing order but
due to the need to sell them differently, separate manufacturing orders are
required.
 Schedule operations on different orders in a way that they are a part of the
same manufacturing order.
Synchronization within order is supported
 First two operations start together but finish at
different times. Third operation starts 2 hours after
the start of the second operation
Scope for Improvement in SAP PP/DS
Synchronization across order is not supported:
 Adjust the finished product orders to meet lot size
requirement of semi-finished products
 If finished good order is rescheduled, then
reschedule semi-finished good order.
 Maintain a minimum and maximum duration
between finished good order and semi-finished good
order.
Scheduling Challenge: Multiple Stage Synchronization
 In order to generate feasible schedules and plans, it is important to understand
the capacity of the resources used in production.
Key Concerns
 Capacity / Rates / BOM changes over time
 Machine Downtime
 Resources to process multiple orders/products:
 Resource Network
 Labor Availability
Scheduling Challenge: Resource Constraints
Resources to Process multiple orders/products
 Example: Oven/Dryer
 Used for drying of multiple products.
 Can only be loaded or unloaded all at once.
 Should be filled with Products that require the
same temperature and duration.
Solution in SAP
 Resource can be defined to process multiple products
at the same time.
 Synchronization on the resource is activated to
process products with similar properties together.
 Products are grouped together so that they can be
heated/processed at the same time
Scheduling Challenge: Resource Constraints
Oven with Multiple
Sections
Alternate Resources
 Production rates may be limited due to available capacity of
machines.
 In such cases, production capacity is increased by the addition
of multiple machines.
 Asset Schedulers should have the flexibility to schedule production
on these multiple machines.
 A specific machine is preferable due to factors like higher
production rate, ease of operation, proximity to work area, etc.
Solution in SAP
 Alternate resource can be added in master data.
 Resource priorities and differential production rates can be
achieved using development
 Optimizer will try to schedule the order on preferred resource
(resource with high priority).
 If capacity is not available on preferred resource, then order is
scheduled on alternate resource (resource with low priority).
Scheduling Challenge: Resource Constraints
Before Scheduling
After Scheduling
Resource Network
 Manufacturing a product requires several steps
 Limited set of successor resources can be used
for the successor operation
Solution in SAP
 An additional master data called as Resource
Network can be used to define allowed
physical connections between resources.
 Resource Network can be used to define the
flow within an order or across orders
 PP/DS Optimizer can remove capacity overload
while respecting Resource Network constraints.
Scheduling Challenge: Resource Constraints
Scheduling Challenge: Resource Constraints
Labor Constraint
 Labor: Limited availability of labor to run
multiple resources.
 Specific Time: Requirement of Labor at the
start or end of operation.
Solution in SAP PP/DS
 A shared labor resource can be mapped as a
secondary resource and can be added to a
specific operation or phase.
 PP/DS Optimization considers the capacity of
secondary resource while scheduling on
primary resource.
Scheduling Challenge: Resource Constraints
Scope for improvements
 SAP design to support alternate resources
is not consistent in SNP and PP/DS.
 Results in maintenance of additional
master data to support alternate resource
functionality in SNP and PP/DS .
 Creates inconsistency in planning and
scheduling.
In PP/DS, alternate resources should be a part of the
same production data structure support alternate
resource selection in case of capacity overload.
In SNP, alternate resources within the same PDS
is not supported. Separate production data
structure is required in order to ensure that
capacity overload can be resolved.
 About DuPont
 Detailed Scheduling in Integrated Business Planning
 Differences between Process and Discrete Manufacturing
 Scheduling Challenges in Process Industry
 Key Concerns
 Solution Review in SAP
 Key Areas of Improvements in SAP PP/DS
 Key Learnings
Agenda
 Scheduling Processes in Process industry are complex due to the
nature of manufacturing processes.
 Standard SAP PP/DS solution delivers value to meet scheduling
requirement in process industry
 SAP should improve integration of PP/DS with other modules to
better suit process industry scheduling requirements.
Key Learnings
STAY INFORMED
Follow the ASUGNews team:
Tom Wailgum: @twailgum
Chris Kanaracus: @chriskanaracus
Craig Powers: @Powers_ASUG
THANK YOU FOR PARTICIPATING
Please provide feedback on this session by completing
a short survey via the event mobile application.
SESSION CODE: SC544
For ongoing education on this area of focus,
visit www.ASUG.com

More Related Content

What's hot

SAP Automatic batch determination
SAP Automatic batch determinationSAP Automatic batch determination
SAP Automatic batch determinationAmit Pandey
 
SAP ATP check for Sales Order
SAP ATP check for Sales OrderSAP ATP check for Sales Order
SAP ATP check for Sales OrderLee Scott
 
SAP PP MRP Guide for Beginners
SAP PP MRP Guide for BeginnersSAP PP MRP Guide for Beginners
SAP PP MRP Guide for Beginnerssapdocs. info
 
SAP PP Certification Overview (mindmap edition)
SAP PP Certification Overview (mindmap edition)SAP PP Certification Overview (mindmap edition)
SAP PP Certification Overview (mindmap edition)Benedict Yong (杨腾翔)
 
Multiple Work Center/Resource Selection and Classification in Master Recipe f...
Multiple Work Center/Resource Selection and Classification in Master Recipe f...Multiple Work Center/Resource Selection and Classification in Master Recipe f...
Multiple Work Center/Resource Selection and Classification in Master Recipe f...Ankit Sharma
 
SAP SOP process flow for production process
SAP SOP process flow for production processSAP SOP process flow for production process
SAP SOP process flow for production processAasif001234
 
SAP PP Case study by Murali Krishna Nookella
SAP PP Case study by Murali Krishna NookellaSAP PP Case study by Murali Krishna Nookella
SAP PP Case study by Murali Krishna Nookellamuralikrishnanookella
 
Project Systems: Materials
Project Systems: MaterialsProject Systems: Materials
Project Systems: Materialsvnhardik
 
SAP-ECM and PPPI Integration-Solution
SAP-ECM and PPPI Integration-SolutionSAP-ECM and PPPI Integration-Solution
SAP-ECM and PPPI Integration-SolutionVijay Pisipaty
 
Sap power point presentation download from
Sap power point presentation download fromSap power point presentation download from
Sap power point presentation download fromSomnath Ghose
 
240935187-Handling-Unit-Management-in-SAP-Packing-During-Outbound-Process.pptx
240935187-Handling-Unit-Management-in-SAP-Packing-During-Outbound-Process.pptx240935187-Handling-Unit-Management-in-SAP-Packing-During-Outbound-Process.pptx
240935187-Handling-Unit-Management-in-SAP-Packing-During-Outbound-Process.pptxManibudhSankasem
 
Sales and Operation Planning in SAP
Sales and Operation Planning in SAPSales and Operation Planning in SAP
Sales and Operation Planning in SAPAnkit Sharma
 
sap-ps-project-systems
 sap-ps-project-systems sap-ps-project-systems
sap-ps-project-systemshollabackgirl1
 
Master Data in Material Management
Master Data in Material ManagementMaster Data in Material Management
Master Data in Material ManagementGanesh Padala
 

What's hot (20)

MRP Overview
MRP OverviewMRP Overview
MRP Overview
 
SAP Automatic batch determination
SAP Automatic batch determinationSAP Automatic batch determination
SAP Automatic batch determination
 
Pp interview questions
Pp interview questionsPp interview questions
Pp interview questions
 
SAP PP Routing
SAP PP RoutingSAP PP Routing
SAP PP Routing
 
SAP ATP check for Sales Order
SAP ATP check for Sales OrderSAP ATP check for Sales Order
SAP ATP check for Sales Order
 
SAP PS overview
SAP PS overviewSAP PS overview
SAP PS overview
 
SAP PP MRP Guide for Beginners
SAP PP MRP Guide for BeginnersSAP PP MRP Guide for Beginners
SAP PP MRP Guide for Beginners
 
SAP PP Certification Overview (mindmap edition)
SAP PP Certification Overview (mindmap edition)SAP PP Certification Overview (mindmap edition)
SAP PP Certification Overview (mindmap edition)
 
Multiple Work Center/Resource Selection and Classification in Master Recipe f...
Multiple Work Center/Resource Selection and Classification in Master Recipe f...Multiple Work Center/Resource Selection and Classification in Master Recipe f...
Multiple Work Center/Resource Selection and Classification in Master Recipe f...
 
SAP SOP process flow for production process
SAP SOP process flow for production processSAP SOP process flow for production process
SAP SOP process flow for production process
 
SAP PP Case study by Murali Krishna Nookella
SAP PP Case study by Murali Krishna NookellaSAP PP Case study by Murali Krishna Nookella
SAP PP Case study by Murali Krishna Nookella
 
Project Systems: Materials
Project Systems: MaterialsProject Systems: Materials
Project Systems: Materials
 
SAP-ECM and PPPI Integration-Solution
SAP-ECM and PPPI Integration-SolutionSAP-ECM and PPPI Integration-Solution
SAP-ECM and PPPI Integration-Solution
 
Sap power point presentation download from
Sap power point presentation download fromSap power point presentation download from
Sap power point presentation download from
 
240935187-Handling-Unit-Management-in-SAP-Packing-During-Outbound-Process.pptx
240935187-Handling-Unit-Management-in-SAP-Packing-During-Outbound-Process.pptx240935187-Handling-Unit-Management-in-SAP-Packing-During-Outbound-Process.pptx
240935187-Handling-Unit-Management-in-SAP-Packing-During-Outbound-Process.pptx
 
SAP MM Standard Business Processes
SAP MM Standard Business ProcessesSAP MM Standard Business Processes
SAP MM Standard Business Processes
 
Sales and Operation Planning in SAP
Sales and Operation Planning in SAPSales and Operation Planning in SAP
Sales and Operation Planning in SAP
 
sap-ps-project-systems
 sap-ps-project-systems sap-ps-project-systems
sap-ps-project-systems
 
Consumable Materials
Consumable MaterialsConsumable Materials
Consumable Materials
 
Master Data in Material Management
Master Data in Material ManagementMaster Data in Material Management
Master Data in Material Management
 

Viewers also liked

Fmc Vision 2015
Fmc Vision 2015Fmc Vision 2015
Fmc Vision 2015Tom Matys
 
SAP Global Available to Promise (gATP) 101: Global Visibility vs. Global Avai...
SAP Global Available to Promise (gATP) 101: Global Visibility vs. Global Avai...SAP Global Available to Promise (gATP) 101: Global Visibility vs. Global Avai...
SAP Global Available to Promise (gATP) 101: Global Visibility vs. Global Avai...Plan4Demand
 
Supply Chain Planning and SAP APO Overview
Supply Chain Planning and SAP APO OverviewSupply Chain Planning and SAP APO Overview
Supply Chain Planning and SAP APO OverviewSap Ides
 

Viewers also liked (6)

FMC and SAP
FMC and SAPFMC and SAP
FMC and SAP
 
Does APO Really Work? - An APO Case Study
Does APO Really Work? - An APO Case StudyDoes APO Really Work? - An APO Case Study
Does APO Really Work? - An APO Case Study
 
Fmc Vision 2015
Fmc Vision 2015Fmc Vision 2015
Fmc Vision 2015
 
SAP Global Available to Promise (gATP) 101: Global Visibility vs. Global Avai...
SAP Global Available to Promise (gATP) 101: Global Visibility vs. Global Avai...SAP Global Available to Promise (gATP) 101: Global Visibility vs. Global Avai...
SAP Global Available to Promise (gATP) 101: Global Visibility vs. Global Avai...
 
Supply Chain Planning and SAP APO Overview
Supply Chain Planning and SAP APO OverviewSupply Chain Planning and SAP APO Overview
Supply Chain Planning and SAP APO Overview
 
SAP Production Planning
SAP Production PlanningSAP Production Planning
SAP Production Planning
 

Similar to SC544_544_Scheduling Challenges in PPDS

Zero Wait-State Agile EC MCAD Implementation Quick Start Presentation
Zero Wait-State Agile EC MCAD Implementation Quick Start PresentationZero Wait-State Agile EC MCAD Implementation Quick Start Presentation
Zero Wait-State Agile EC MCAD Implementation Quick Start PresentationZero Wait-State
 
Capacity-Planning-Report - Measurement of Capacity
Capacity-Planning-Report - Measurement of CapacityCapacity-Planning-Report - Measurement of Capacity
Capacity-Planning-Report - Measurement of CapacityJoanRachelCalansingi
 
Zws Corporate Presentation Agile Implementation Approach
Zws Corporate Presentation  Agile Implementation ApproachZws Corporate Presentation  Agile Implementation Approach
Zws Corporate Presentation Agile Implementation ApproachZero Wait-State
 
CV_AVINASH B. WADASKAR-2016-08-23
CV_AVINASH B. WADASKAR-2016-08-23CV_AVINASH B. WADASKAR-2016-08-23
CV_AVINASH B. WADASKAR-2016-08-23Avinash Wadaskar
 
Product and process design
Product and process designProduct and process design
Product and process designRajThakuri
 
AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING Aqib ali
 
The Reality of Affordable and Scalable Digital Transformation.pptx
The Reality of Affordable and Scalable Digital Transformation.pptxThe Reality of Affordable and Scalable Digital Transformation.pptx
The Reality of Affordable and Scalable Digital Transformation.pptxSafetyChain Software
 
Process-Driven SAP Management for successful SAP Projects
Process-Driven SAP Management for successful SAP ProjectsProcess-Driven SAP Management for successful SAP Projects
Process-Driven SAP Management for successful SAP ProjectsSoftware AG
 
Job description factory services engineer
Job description   factory services engineerJob description   factory services engineer
Job description factory services engineerBabatunde Sofoluwe
 
Process & Capacity 2
Process & Capacity 2Process & Capacity 2
Process & Capacity 2knksmart
 
Thiru CV 15 02 2016-FRP
Thiru CV 15 02 2016-FRPThiru CV 15 02 2016-FRP
Thiru CV 15 02 2016-FRPThirumurugan B
 
Make green go green by going lean
Make green go green by going leanMake green go green by going lean
Make green go green by going leanbwu.nl
 
Production Planning In Manufacturing Industry
Production Planning In Manufacturing IndustryProduction Planning In Manufacturing Industry
Production Planning In Manufacturing IndustryPolestarsolutions
 
Pagerinkite užsakymų įvykdymą laiku naudodami šiuolaikinius gamybos planavimo...
Pagerinkite užsakymų įvykdymą laiku naudodami šiuolaikinius gamybos planavimo...Pagerinkite užsakymų įvykdymą laiku naudodami šiuolaikinius gamybos planavimo...
Pagerinkite užsakymų įvykdymą laiku naudodami šiuolaikinius gamybos planavimo...Columbus Lietuva
 
Paranda ettevõtte tulemusi targa tootmise planeerimise ja operatiivjuhtimisega
Paranda ettevõtte tulemusi targa tootmise planeerimise ja operatiivjuhtimisegaParanda ettevõtte tulemusi targa tootmise planeerimise ja operatiivjuhtimisega
Paranda ettevõtte tulemusi targa tootmise planeerimise ja operatiivjuhtimisegaColumbus Eesti AS
 
LECTURE 6 - PROCESS & CAPACITY DESIGN.ppt
LECTURE 6 - PROCESS & CAPACITY DESIGN.pptLECTURE 6 - PROCESS & CAPACITY DESIGN.ppt
LECTURE 6 - PROCESS & CAPACITY DESIGN.pptMehrNawaz1
 

Similar to SC544_544_Scheduling Challenges in PPDS (20)

Zero Wait-State Agile EC MCAD Implementation Quick Start Presentation
Zero Wait-State Agile EC MCAD Implementation Quick Start PresentationZero Wait-State Agile EC MCAD Implementation Quick Start Presentation
Zero Wait-State Agile EC MCAD Implementation Quick Start Presentation
 
Capacity-Planning-Report - Measurement of Capacity
Capacity-Planning-Report - Measurement of CapacityCapacity-Planning-Report - Measurement of Capacity
Capacity-Planning-Report - Measurement of Capacity
 
Zws Corporate Presentation Agile Implementation Approach
Zws Corporate Presentation  Agile Implementation ApproachZws Corporate Presentation  Agile Implementation Approach
Zws Corporate Presentation Agile Implementation Approach
 
CV_AVINASH B. WADASKAR-2016-08-23
CV_AVINASH B. WADASKAR-2016-08-23CV_AVINASH B. WADASKAR-2016-08-23
CV_AVINASH B. WADASKAR-2016-08-23
 
Product and process design
Product and process designProduct and process design
Product and process design
 
AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING
 
Jit And Lean
Jit And LeanJit And Lean
Jit And Lean
 
PPC.pdf
PPC.pdfPPC.pdf
PPC.pdf
 
The Reality of Affordable and Scalable Digital Transformation.pptx
The Reality of Affordable and Scalable Digital Transformation.pptxThe Reality of Affordable and Scalable Digital Transformation.pptx
The Reality of Affordable and Scalable Digital Transformation.pptx
 
Design Sample
Design SampleDesign Sample
Design Sample
 
Process-Driven SAP Management for successful SAP Projects
Process-Driven SAP Management for successful SAP ProjectsProcess-Driven SAP Management for successful SAP Projects
Process-Driven SAP Management for successful SAP Projects
 
Job description factory services engineer
Job description   factory services engineerJob description   factory services engineer
Job description factory services engineer
 
What is six sigma
What is six sigmaWhat is six sigma
What is six sigma
 
Process & Capacity 2
Process & Capacity 2Process & Capacity 2
Process & Capacity 2
 
Thiru CV 15 02 2016-FRP
Thiru CV 15 02 2016-FRPThiru CV 15 02 2016-FRP
Thiru CV 15 02 2016-FRP
 
Make green go green by going lean
Make green go green by going leanMake green go green by going lean
Make green go green by going lean
 
Production Planning In Manufacturing Industry
Production Planning In Manufacturing IndustryProduction Planning In Manufacturing Industry
Production Planning In Manufacturing Industry
 
Pagerinkite užsakymų įvykdymą laiku naudodami šiuolaikinius gamybos planavimo...
Pagerinkite užsakymų įvykdymą laiku naudodami šiuolaikinius gamybos planavimo...Pagerinkite užsakymų įvykdymą laiku naudodami šiuolaikinius gamybos planavimo...
Pagerinkite užsakymų įvykdymą laiku naudodami šiuolaikinius gamybos planavimo...
 
Paranda ettevõtte tulemusi targa tootmise planeerimise ja operatiivjuhtimisega
Paranda ettevõtte tulemusi targa tootmise planeerimise ja operatiivjuhtimisegaParanda ettevõtte tulemusi targa tootmise planeerimise ja operatiivjuhtimisega
Paranda ettevõtte tulemusi targa tootmise planeerimise ja operatiivjuhtimisega
 
LECTURE 6 - PROCESS & CAPACITY DESIGN.ppt
LECTURE 6 - PROCESS & CAPACITY DESIGN.pptLECTURE 6 - PROCESS & CAPACITY DESIGN.ppt
LECTURE 6 - PROCESS & CAPACITY DESIGN.ppt
 

SC544_544_Scheduling Challenges in PPDS

  • 1.
  • 2. Scheduling Challenges in Process Industry & Solution Using PP/DS in SAP Software: DuPont Case Study Chintesh Chopkar Kevin Bunn Bristlecone DuPont SESSION CODE: SC544
  • 3. At the end of this session, you should be able to understand:  Scheduling Challenges in Process Industry  Ways to address scheduling challenges using SAP PP/DS  Key Areas of Improvements required in SAP PP/DS Learning Points
  • 4.  About DuPont  Detailed Scheduling in Integrated Business Planning  Differences between Process and Discrete Manufacturing  Scheduling Challenges in Process Industry  Key Concerns  Solution Review in SAP  Key Areas of Improvements in SAP PP/DS  Key Learnings Agenda
  • 5. © National Geographic image DuPont is a Science Company We work collaboratively to find sustainable, innovative, market-driven solutions to solve some of the world’s biggest challenges, making lives better, safer, and healthier for people everywhere. Our Purpose
  • 6. We are applying our science to find solutions to some really BIG challenges… FOOD ENERGY PROTECTION FEEDING THE WORLD REDUCING OUR DEPENDENCE ON FOSSIL FUELS KEEPING PEOPLE & THE ENVIRONMENT SAFE About DuPont
  • 7. + + Improve Customer Experience Reduce Cost to Serve Reduce Inventory From …  High inventory  Misaligned policies  Non-productive inventory  High complexity  Manual interventions  Numerous work around  Significant expediting  Inconsistent delivery performance  Difficulty meeting promises  Significant churn and effort To …  Automated, streamlined, rules based processes  Reduced manufacturing costs  Reduced expediting costs  Advantaged working capital productivity  Aligned E2E performance  Capital available to re- invest  Reliable Supply  Competitive LeadTimes  Differentiated service levels DuPont’s Transformational Approach For Digital DuPont
  • 8.  About DuPont  Detailed Scheduling in Integrated Business Planning  Differences between Process and Discrete Manufacturing  Scheduling Challenges in Process Industry  Key Concerns  Solution Review in SAP  Key Areas of Improvements in SAP PP/DS  Key Learnings Agenda
  • 9.  To determine what to make, when to make, on which equipment to make in a production facility  Aims to maximize the efficiency of the operation at lowest possible costs  The major inputs for Detailed Scheduling are:  Master Production Schedule  Demand Forecasts  Sales  Manufacturing  Distribution  Purchasing What is Detailed Scheduling? Goals of Detailed Scheduling
  • 10. Detailed Scheduling in Integrated Business Planning
  • 11.  About DuPont  Detailed Scheduling in Integrated Business Planning  Differences between Process and Discrete Manufacturing  Scheduling Challenges in Process Industry  Key Concerns  Solution Review in SAP  Key Areas of Improvements in SAP PP/DS  Key Learnings Agenda
  • 12. Chemical, Food, and Beverage manufacturing processes are different from automobile production! Process Manufacturing vs. Discrete Manufacturing Process Industry Discrete Industry Production Product is manufactured by mixing, blending and transforming chemicals, liquids or food stuffs Product is manufactured by assembly of distinct items Breaks or Stoppages Difficult and costly to Start & Stop. Dependent on Production Sequence. Easy to Start and Stop. Independent of Production sequence. Shortage of Input Component More Flexibility in altering production lot size (above minimum) to continue production If sufficient quantity of components is not available to assemble then production must be halted. Inventory Mainly maintained at Finished Product level Lot of Work-In-Progress inventory Example Pharma, Food, Chemicals Automobile, High Tech
  • 13. Material Flows are different in Process Industry and Discrete Industry requiring different approach in Planning, Scheduling and Execution. Process Manufacturing vs. Discrete Manufacturing Discrete Industry Forecast Process Industry Forecast Forecast Forecast
  • 14.  About DuPont  Detailed Scheduling in Integrated Business Planning  Differences between Process and Discrete Manufacturing  Scheduling Challenges in Process Industry  Key Concerns  Solution Review in SAP  Key Areas of Improvements in SAP PP/DS  Key Learnings Agenda
  • 15. Major Scheduling Challenges discussed are:  Dealing with Uncertainties  Setup optimization  Production Quantity Constraints  Multiple Stage Synchronization  Resource (Machine) Constraints Scheduling Challenges in Process Industry
  • 16. Changes in Detailed Schedule are inevitable.  Customers cancels or changes orders  Suppliers have problems and miss delivery dates  Machines break down or new machines are added, changing capacity  Processes create more scrap than expected.  Key Concerns:  How to keep detailed schedule in sync with planning and execution?  How to balance competing goals?  How to deal with uncertainties? Dealing with Uncertainties in Detailed Scheduling
  • 17. Scheduling Horizons – Aid to Decision Making  Scheduling Horizons define artificial time boundaries used to separate periods for planning or scheduling purposes.  Used to establish policies to stabilize Detailed Schedule and Planning Dealing with Uncertainties in Detailed Scheduling  Frozen Horizon: Changes to DS are kept to a minimum to avoid disruption to the production schedule.  Slushy Horizon: Changes to the detailed schedule along with minor manual quantity adjustment allowed.  Liquid Horizon: Free to make changes in detailed schedule as long as the schedule remains within the production plan constraints
  • 18. Dealing with Uncertainties in Detailed Scheduling Horizon Purpose Where How Frozen Schedule changes kept to a minimum Resource Detailed Scheduling Firming Heuristics Slushy Order in Slushy Horizon are not changed by SNP Product Master SNP Horizon Field PP/DS Conversion of SNP Orders to PP/DS Orders Product Master PP/DS Horizon Field Liquid MPS creates new orders to respond to demand changes Product Master Deletion job to delete the orders beyond slushy horizon Solution in SAP
  • 19. Scope for improvements in SAP PP/DS  If production is running behind, then detailed schedule must be updated to reflect the new expected completion times. Current detailed scheduling heuristics does not allow adjustment of backlog orders containing different phases within operation. Dealing with Uncertainties in Detailed Scheduling Backlog Order
  • 20.  A transition between products on a machine can incur a high cost or loss of large amount of production time in setup.  Sequence of manufacturing product influences production costs, setup times and inventory levels and the goal is to balance the costs against inventory levels while meeting demand. Scheduling Challenge: Setup Optimization  Key Concerns: How to create a detailed schedule which  Reduces setup cost  Reduces setup time  Meets customer demand  Minimizes Inventory
  • 21. Solution in SAP PP/DS  SAP provides PPDS Optimization tool which can consider various trade offs such as setup cost, setup time, delays and demand priority  PP/DS Optimizer can create a schedule considering competing goals  Automatic pickup of setup time based on predecessor product being manufactured is supported in Detailed Scheduling Board Scheduling Challenge: Setup Optimization PP/DS Optimization profile for Scheduling Trade Offs Detailed Scheduling Board showing setup transition
  • 22. Scope for Improvements in SAP  Detailed Schedule prepared considering various trade offs is not aligned with SNP planning as SNP optimization supports setup sequencing to a limited extent.  Transition materials produced during setup transition in process industry are not supported in PP/DS.  Modelling of costs in PP/DS Optimization to achieve the desired schedule is challenging. Scheduling Challenge: Setup Optimization Sequencing of products at regular interval. A C B B A C SNP Orders A A B B C C DS Order (Current) A B C A B C DS Order ( Expected) Week 2 Modeling of PP/DS Optimization Costs is challening Week 2 Week 2 Week 1 Week 1 Week 1
  • 23.  Many factors affect quantity of product that can be produced at one time (Batch Size, minimum campaign size, etc.)  Process Industry have a lot of variation of production processes. Key Concerns  Batch Size: Consider minimum and maximum capacity requirements and align with package size (increments of standard package).  Intermittent Output: Product is produced in a continuous process with output at regular time intervals. (e.g. 100 Gal every Hr)  Minimum Input Quantity: A Product is produced in a continuous process and order can not be started unless a minimum quantity (e.g. 200 Gal) of component is available.  Campaign lengths: Creating a campaign considering inter-dependency of semi- finished product and finished product. (e.g. If semi-finished product order size increased to meet lot size requirement then adjust the finished product order.) Scheduling Challenge: Production Quantity Constraints
  • 24. Scheduling Challenge: Production Quantity Constraints Intermittent Output & Minimum Input Component Quantity  Finished Good is produced in a continuous process.  Finished Good order can not be started unless a minimum quantity (e.g. 200 Gal) of Semi-Finished Good is available.  SFG is produced in an intermittent process with output at regular time intervals
  • 25. Solution in SAP PP/DS  SAP PP/DS supports scheduling of continuous production with intermittent output.  PP/DS Optimizer can be used for scheduling of continuous production. Scheduling Challenge: Production Quantity Constraints A10111000: Raw Material B10111000: Semi-Finished D10111000: Finished After Scheduling main order output quantity is spilt equivalent to required intermittent output. FG Orders are scheduled based on continuous production considering availability of minimum input component quantity.
  • 26. Scope for Improvements in SAP Lot Size integration of Detailed Scheduling with SNP:  In SNP optimization, its not possible to address lot size constraints if the input data volume is large.  Plan generated in SNP may be feasible but not always executable.  If lot size is addressed in detailed scheduling, it may create infeasible plan downstream.  GR time is not supported in continuous output production which create inconsistencies in execution and planning. Scheduling Challenge: Production Quantity Constraints
  • 27. Scheduling Challenge: Multiple Stage Synchronization  The conversion of raw materials to finished products often consists of multiple distinct manufacturing stages, either within a single site or across multiple sites.  When planning and scheduling these operations, synchronization between stages and across multiple assets within the same stage must occur. Key Concerns  There is a scheduling dependencies between different levels of the BOM.  Ideally, such products should be the part of the same manufacturing order but due to the need to sell them differently, separate manufacturing orders are required.  Schedule operations on different orders in a way that they are a part of the same manufacturing order.
  • 28. Synchronization within order is supported  First two operations start together but finish at different times. Third operation starts 2 hours after the start of the second operation Scope for Improvement in SAP PP/DS Synchronization across order is not supported:  Adjust the finished product orders to meet lot size requirement of semi-finished products  If finished good order is rescheduled, then reschedule semi-finished good order.  Maintain a minimum and maximum duration between finished good order and semi-finished good order. Scheduling Challenge: Multiple Stage Synchronization
  • 29.  In order to generate feasible schedules and plans, it is important to understand the capacity of the resources used in production. Key Concerns  Capacity / Rates / BOM changes over time  Machine Downtime  Resources to process multiple orders/products:  Resource Network  Labor Availability Scheduling Challenge: Resource Constraints
  • 30. Resources to Process multiple orders/products  Example: Oven/Dryer  Used for drying of multiple products.  Can only be loaded or unloaded all at once.  Should be filled with Products that require the same temperature and duration. Solution in SAP  Resource can be defined to process multiple products at the same time.  Synchronization on the resource is activated to process products with similar properties together.  Products are grouped together so that they can be heated/processed at the same time Scheduling Challenge: Resource Constraints Oven with Multiple Sections
  • 31. Alternate Resources  Production rates may be limited due to available capacity of machines.  In such cases, production capacity is increased by the addition of multiple machines.  Asset Schedulers should have the flexibility to schedule production on these multiple machines.  A specific machine is preferable due to factors like higher production rate, ease of operation, proximity to work area, etc. Solution in SAP  Alternate resource can be added in master data.  Resource priorities and differential production rates can be achieved using development  Optimizer will try to schedule the order on preferred resource (resource with high priority).  If capacity is not available on preferred resource, then order is scheduled on alternate resource (resource with low priority). Scheduling Challenge: Resource Constraints Before Scheduling After Scheduling
  • 32. Resource Network  Manufacturing a product requires several steps  Limited set of successor resources can be used for the successor operation Solution in SAP  An additional master data called as Resource Network can be used to define allowed physical connections between resources.  Resource Network can be used to define the flow within an order or across orders  PP/DS Optimizer can remove capacity overload while respecting Resource Network constraints. Scheduling Challenge: Resource Constraints
  • 33. Scheduling Challenge: Resource Constraints Labor Constraint  Labor: Limited availability of labor to run multiple resources.  Specific Time: Requirement of Labor at the start or end of operation. Solution in SAP PP/DS  A shared labor resource can be mapped as a secondary resource and can be added to a specific operation or phase.  PP/DS Optimization considers the capacity of secondary resource while scheduling on primary resource.
  • 34. Scheduling Challenge: Resource Constraints Scope for improvements  SAP design to support alternate resources is not consistent in SNP and PP/DS.  Results in maintenance of additional master data to support alternate resource functionality in SNP and PP/DS .  Creates inconsistency in planning and scheduling. In PP/DS, alternate resources should be a part of the same production data structure support alternate resource selection in case of capacity overload. In SNP, alternate resources within the same PDS is not supported. Separate production data structure is required in order to ensure that capacity overload can be resolved.
  • 35.  About DuPont  Detailed Scheduling in Integrated Business Planning  Differences between Process and Discrete Manufacturing  Scheduling Challenges in Process Industry  Key Concerns  Solution Review in SAP  Key Areas of Improvements in SAP PP/DS  Key Learnings Agenda
  • 36.  Scheduling Processes in Process industry are complex due to the nature of manufacturing processes.  Standard SAP PP/DS solution delivers value to meet scheduling requirement in process industry  SAP should improve integration of PP/DS with other modules to better suit process industry scheduling requirements. Key Learnings
  • 37. STAY INFORMED Follow the ASUGNews team: Tom Wailgum: @twailgum Chris Kanaracus: @chriskanaracus Craig Powers: @Powers_ASUG
  • 38. THANK YOU FOR PARTICIPATING Please provide feedback on this session by completing a short survey via the event mobile application. SESSION CODE: SC544 For ongoing education on this area of focus, visit www.ASUG.com