The following are the deliverables that will be expected in this project:
1. Inception Report (grade A) - this is the very first deliverable of the assignment, it is a very important deliverable and it should have a high grade (A) because it sets the first phase of the project. This report will provide the following: the outline of the final report, the methodology of the assignment and the initial budget estimates.
2. First Interim Report (grade B) – this is the second deliverable; it is graded relatively lower than the first deliverable. This report will provide: Finalized budget, the proposed team of professionals and a stakeholders analysis.
3. Second Interim report (grade A) - this is an important deliverable because it is crucial in monitoring the progress of the project. It will clearly outline the communication plan for this project in order to ensure that all team members understand their roles and the chain of protocol.
4. Design Report (grade A) – this is a crucial deliverable that requires serious work to avoid compromising the quality of the desired products such as uniforms, apparel and the gear; the report has a higher grade due to its importance and relevance to this project. The design report will clearly show the design and engineering aspects of the products.
5. Draft Report (grade B) – this is a reflection of the final report; it has a lower grade than the final report since there is time for incorporation of comments from stakeholders and the team members. This deliverable will be based on the outline that was discussed during the inception meeting along with the proposed final report outline that was documented in the inception report
6. Final report (grade A) - This is a very important deliverable that marks the end of the entire project in order to determine if the project was a success or failure, that is why it earns the top grade. The report will be an improvement of the Draft Report that was discussed in the presentation during a stakeholders’ workshop.
Running Head: 18 ft. HORN PROJECT
18 ft. Horn Project
Tania Amador
18 ft. HORN PROJECT
UMUC BMGT 487 7980
18 ft. Horn Project
This is a civil engineering project with interesting artistic works that is spearheaded by Edouard Steinhaue. The project involves construction of an 18 ft. structure that resembles a horn, in Socrates Sculpture Park, located in New York City. Edourard is soliciting for funds from donors to enable him to complete the project, considering all the legal and safety standards he must abide by.
The following table shows the risk management plan for various risks that are associated with this project
Table 1: Risk Management Plan
Risk Name
Definition of the Risk
Probability of occurrence
(High/Low)
Impact of the Risk
(High/Low)
Description of the Impact (in terms of cost, time, and quality)
Response Strategy (with explanation)
Lack of enough funds
The proponent is looking for external financial support; therefore the ...
The following are the deliverables that will be expected in this p.docx
1. The following are the deliverables that will be expected in this
project:
1. Inception Report (grade A) - this is the very first deliverable
of the assignment, it is a very important deliverable and it
should have a high grade (A) because it sets the first phase of
the project. This report will provide the following: the outline
of the final report, the methodology of the assignment and the
initial budget estimates.
2. First Interim Report (grade B) – this is the second
deliverable; it is graded relatively lower than the first
deliverable. This report will provide: Finalized budget, the
proposed team of professionals and a stakeholders analysis.
3. Second Interim report (grade A) - this is an important
deliverable because it is crucial in monitoring the progress of
the project. It will clearly outline the communication plan for
this project in order to ensure that all team members understand
their roles and the chain of protocol.
4. Design Report (grade A) – this is a crucial deliverable that
requires serious work to avoid compromising the quality of the
desired products such as uniforms, apparel and the gear; the
report has a higher grade due to its importance and relevance to
this project. The design report will clearly show the design and
engineering aspects of the products.
5. Draft Report (grade B) – this is a reflection of the final
report; it has a lower grade than the final report since there is
time for incorporation of comments from stakeholders and the
team members. This deliverable will be based on the outline
that was discussed during the inception meeting along with the
proposed final report outline that was documented in the
inception report
6. Final report (grade A) - This is a very important deliverable
that marks the end of the entire project in order to determine if
2. the project was a success or failure, that is why it earns the top
grade. The report will be an improvement of the Draft Report
that was discussed in the presentation during a stakeholders’
workshop.
Running Head: 18 ft. HORN PROJECT
18 ft. Horn Project
Tania Amador
18 ft. HORN PROJECT
UMUC BMGT 487 7980
18 ft. Horn Project
This is a civil engineering project with interesting artistic works
that is spearheaded by Edouard Steinhaue. The project involves
construction of an 18 ft. structure that resembles a horn, in
Socrates Sculpture Park, located in New York City. Edourard is
soliciting for funds from donors to enable him to complete the
project, considering all the legal and safety standards he must
abide by.
The following table shows the risk management plan for various
risks that are associated with this project
Table 1: Risk Management Plan
Risk Name
Definition of the Risk
3. Probability of occurrence
(High/Low)
Impact of the Risk
(High/Low)
Description of the Impact (in terms of cost, time, and
quality)
Response Strategy (with explanation)
Lack of enough funds
The proponent is looking for external financial support;
therefore there was a possibility of funds running out in the
course of construction.
High – Because there is no guarantee that donors will fund the
project
High - because the project will not be completed
· Time will be lost if the project will not be completed
· Poor quality will result if the funds are not enough
· Money will be wasted is the project stops
The project proponent should look for promising donors
Legal challenges
The project may fail to meet the legal standards that have been
established by the municipality
Low – the proponent will cooperate with the local authorities
High – because the construction will be illegal
· Time will be wasted because the project will not take place
· Money will be wasted because the project will have aborted
Comply with the local laws and regulations
Lack of team unity
There may be lack of cooperation among members of the team
that is proposing the project
High – because human being is a social animal and conflicts are
bound to happen when working as a team
High – because the project may fail to take place as planned
· Time will be wasted because the mission will not be
4. accomplished
· Funds may not be adequate because conflicts among team
members may turn donors away
Ensure that a professional sociologist intervenes whenever there
is a conflict
Negative environmental impacts
There is likelihood that the project will interfere with the
environment since the construction will take place in an outdoor
open space
High – because environment is sensitive to construction projects
High – because environmental lobbyist may take legal action to
stop the project.
· Time will be wasted if the project is stropped
· Money will be lost if the project is stopped
An environmental impact assessment study should be conducted
to propose appropriate mitigation measures
Political interference
Considering that this is a project that deals with the aesthetics
of the park; therefore, local politicians may take interest and
interfere with the project.
High – because politics are part of developments
High – because politicians may influence civil society groups to
demonstrate in order to stop the project
· Money will be lost if the project is stopped
· Time will be lost if the project will not be implemented
· Donors may withdraw money due to the politically charged
environment- This will lead to poor quality due to lack of funds
Consult all Stakeholders including the politicians to minimize
future conflicts during project implementation.
References
A guide to the project management body of knowledge (PMBOK
guide) (3rd ed.). (2004). Newtown Square, Pa.: Project
Management Institute.
Saladis, F., & Kerzner, H. (2011). Bringing the PMBOK Guide
to Life a Companion for the Practicing Project Manager.
5. Hoboken: John Wiley & Sons.
Risk Management Plan
Risk Name
Define Risk
Probability
High/Low (with explanation)
Impact
High/Low (with explanation)
Describe Impact (in terms of cost, time, and quality)
Response Strategy (with explanation)
Lack of unity among team members
There may be some internal conflicts among team members due
to social the nature of human beings
Low- because there is a project coordinator
High - because the whole project will be delayed
· Millions of dollars will be lost.
· The project will take longer time due to the delay
· Quality will be compromised
The project coordinator should ensure that there is the spirit of
team work among the professionals
Disagreement among the stakeholders
Issues that can cause disagreement of the key stakeholders may
arise
· High- because this is a giant project that will involve millions
of dollars.
· Stakeholders are keen to see how they can influence decisions
or even benefit from the project
6. High – because stakeholders play a major role in
implementation of a project especially in the sports sector
· Funding may be delayed because some donors may be
influenced to withdraw their support
· The project may not be implemented to lack of funds
· If funding will not be sufficient, the quality will be low
· The project manager should organize for stakeholders
workshops in order to discuss issues the that may arise
· This will lead to a consensus, hence the project will proceed
as planned
In accurate budget estimate
The budget may be overestimated or underestimated
Low – because a trained and an experienced professional will be
in charge
High – because if the budget is over estimated, donors may be
suspicious of corruption. On the other hand if the budget is
underestimated the products will be of poor quality
· Quality will be compromised
· The project implementation may be jeopardized
· Money will be wasted if there are delays
The financial experts should work on the possible errors in the
budget in order to fix them
Communication gaps
The project team may misunderstand what is required of them
Low- because a sociologist and the project manager will be in
charge to ensure that all team members are updated and know
what is expected of them
High-because there may inconsistency in deliverables
The quality of the uniforms and sport gears will be
compromised
· The sociologist and the project manager should always review
the communication plan whenever there are lapses
7. · Appropriate measures should be put in place to address the
communication lapses
Experts turn over
Some of the key experts may resign due to internal or external
factors
High – because employees are always looking for greener
pastures. If they are offered better package else where they may
decide to quit their current job
High – This will lead to project delay
· High cost will be incurred in recruiting new employees. This
will be inconsistent with the estimated budget
· The project will take longer time than expected
· Quality of the uniforms, apparels and the sport gear may be
compromised
· The project manager should put ensure that there are measures
to address the welfare of the employees whenever issues arise
· A good cost efficient plan for hiring new employees should be
put in place to mitigate this
Task_Table1WBSName1ABC University Project
Iniation1.1Gather Requirements1.1.1Identify
Sponsor1.1.2Identify Sponsor Approval Process1.1.3Identify
Due Date1.1.4Identify School Teams1.1.5View Apparel
Options1.1.6View Footwear Options1.1.7Finalize Apparel
Selection1.1.8Finalize Footwear Selection1.1.9Identify
Ordering Options1.1.10Estimate Budget1.2Budget1.2.1Review
Budget Estimate1.2.2Identify Budget Risk1.2.3Budget Risk
Mitigation1.2.4Finalize Budget1.3Develop Project
Team1.3.1Identify Roles Needed1.3.2Select Team
Members1.3.3Provide Project Overview1.3.4View Lesson
Learned(Previous Projects)1.3.5Identify Project
POCs1.3.6Identify Charging Procedures1.3.7Communication
Plan1.3.8Identify Documentation Requierements1.4Project
8. Charter1.4.1Document Objective1.4.2Document
Budget1.4.3List Stakeholders1.4.4Document Scope1.4.5Develop
Statement of Work1.5Stakeholder Roles1.5.1Identify
Stakeholders1.5.2Survey Stakeholder Suggestions1.5.3Review
Surveys1.5.4Document Surveys Feedback1.5.5Present Feedback
to Sponsor1.6Communication Plan1.6.1Acknowledge
Acceptable Forms of Communication1.6.1a.Email, Web-cam,
Face-to Face, Speaker Conference1.6.2Schedule PreDesign
Meeting(Stakeholders)1.6.3Schedule Meeting Manufacturing
Team1.6.4Schedule Supplier Meeting1.6.5Schedule Project
Team Meeting1.6.6Schedule Progress Meeting1.7Design
1.7.1Identify Color1.7.2Identify Logo1.7.3Identify Size
Options1.7.4Spreadsheet to track size requirements/uniform
set1.7.5Meet with UA to receive approval of prototype
expectations1.7.6.Design Apparel Prototype1.7.7Ensure
prototype against safety
requirements1.8Manufacture1.8.1Manufacture
Prototype1.8.2Present Prototype to Sponsor1.8.3Sponsor
Prototype Approval1.8.4Coordinate manufacturer schedule with
vendors1.8.5Meeting to determine delivery options1.8.6weekly
progress meetings with vendors1.9Supplier/Order1.9.1Compare
suppliers1.9.2Select supplier1.9.3Meet with
supplier1.9.4Provide requirements to supplier1.9.5Finalize
supplier requirements1.9.6Identify ordering
options1.9.7Document internet order process1.9.8Document
phone order process1.9.9Document mail order
process1.9.10Test internet order process1.9.11Tes phone order
process1.9.12Test mail order process1.9.13Identify teams
ordering POC's1.9.14Schedule Prdering Process Meeting-Team
POC's1.10.Shipment/Delivery1.10.1Review Schedule with
Sponsor1.10.2Document Sponsor Schedule Feedback1.10.3Make
Necessary Schedule Changes1.10.4Notify Supplier of
Changes1.10.5Document Supplier Acceptance of
Changes1.10.6Meet with vendors/stakeholders to make
changes1.10.7Initial Product quality Inspection
meeting1.10.8Coordinate final delivery plan1.10.9Ensure
9. QA/QC with department team heads1.10.10Scehdule media
releases announcing ABC new team design per
UA1.10.11Maintain project plan in client's
file1.11Finalize1.11.1Compile initial milestones/deliverables
into project plan document1.11.2Review project plan with
SHE's1.11.3Incorporate any necessary changes to
document1.11.4Distribute project plan to ABC, UA Team
members, stakeholders1.11.5Schedule Meeting with
stakeholders for plan deliverables review1.11.6Make changesor
updates for formal review1.11.7Finalize project
deliverables1.11.8Gain final approval/signatures from
stakeholders and designees1.11.9Transition project to UA
Account manager1.12Project Finished
UMUC - Project Management I
4/12/2015
Presented By:
Wanjiru Chege
Sugeiri Ruiz
Tania Amador
Waliyyud-Deen Shakir
Shelley Cotten
Tempest Davis
UMUC - Project Management I
4/12/2015
10. Presented By:
Wanjiru Chege
Sugeiri Ruiz
Tania Amador
Waliyyud-Deen Shakir
Shelley Cotten
Tempest Davis
Artifact 3 Group Assignment
Tania Amador-Project Manager
Shelley Cotton
Wanjiru Chege
Su Ruiz
Tempest Davis
Waliyyud-Deen Shakir
WBS 1
ABC University Athletic Gear Project
13. Milestone 2: budget
2.1. Review Budget Estimate
2.2. Identify Budget Risk
2.3. Budget Risk Mitigation
2.4. Finalize Budget
Milestone 3: Develop Project Team
3.1. Identify Roles Needed
3.2. Select Team Members
3.3. Provide Project Overview
3.4. View Lesson Learned (from previous projects)
3.5. Identify Project POCs
3.6. Identify Charging Procedures
3.7. Communication Plan
3.8. Identify Documentation Requirements
Milestone 4: Project Charter
4.1. Identify Objective
4.2. List Budget
4.3. List Stakeholders
4.4. List Budget
4.5. List Scope
4.6. Develop Statement of Work
Milestone 5: Stakeholder Roles
5.1. Identify Stakeholders
5.2. Survey Stakeholder Suggestions
14. 5.3. Review Surveys
5.4. Document Surveys Feedback
5.5. Present Feedback to Sponsor
Milestone 6: Communication Plan
6.1. Acknowledge Acceptable Forms of Communication
6.1A. Email, Web-Cam, Face-to-Face, Speaker Conference
6.2. Schedule Pre-Design Meeting with Stakeholders
6.3. Schedule Meeting with Manufacturing Team
6.4. Schedule Supplier Meeting
6.5. Schedule Project Team Meeting
6.6. Implement Initial Progress Meeting Schedules with all
Teams/Stakeholders
Milestone 7: design
7.1. Identify Color
7.2. Identify Logo
7.3. Identify Size Options
7.4. Spreadsheet to track each team’s specific sizes, function,
color requirement for each set of uniforms
7.5 .Meet with UA Design team to receive approved mockup
designs.
7.6. Design Apparel Prototype
7.7. Ensure Prototype will meet Safety Commission Standards
Milestone 8: manufacture
8.1. Manufacture Apparel Prototype based upon approved
designs
8.2. Present Apparel Prototype to Sponsor
15. 8.3. Sponsor Approves Apparel Prototype
8.4. Coordinate manufacturing schedule and realistic turnaround
time based upon inventory information from UA and outside
vendors.
8.5. Meet with ABC University to determine expected delivery
dates for each set of team uniforms.
8.6. Set up weekly progress meetings with vendors and UA
manufacturing based upon the delivery schedule for each set of
team uniforms and footwear.
8.7. Set up a weekly conference call to keep ABC apprised of
the manufacturing progress.
8.8. Schedule initial quality inspections of the uniforms with
Stakeholders as soon as they become available to UA
8.9. Document any issues with the product, such as size or
quality inconsistencies
1.8.1 Review Ordering Requierements 1.8.2 Test Internet Order
Process 1.8.3 Document Internet Order Process 1.8.4 Test Phone
Order Process 1.8.5 Document Phone Order Process 1.8.6 Test
mail order process 1.8.7 Document mail order process 1.8.8
Identify Teams Ordering POCs 1.8.9 Schedule Ordering Process
Meeting-Team POCs
11
Milestone 9: Supplier/order
9.1. Compare Suppliers
9.2. Select Supplier
9.3. Meet with Supplier
9.4. Provide Requirements to Supplier
9.5. Finalize Supplier Requirements
9.6. Identify Ordering Options
16. 9.7. Document Internet Order Process
9.8. Document Phone Order Process
9.9. Document Mail Order Process
9.10. Test Internet Order Process
9.11. Test Phone Order Process
9.12. Test Mail Order Process
9.13. Identify Teams Ordering POC
9.14. Schedule Ordering Process Meeting-Team POCs
12
Milestone 10: shipment/Delivery
10.1. Review Schedule with Sponsor
10.2. Document Sponsor Schedule Feedback
10.3. Make Necessary Schedule Changes
10.4. Notify Supplier of Changes
10.5. Document Supplier Acceptance of Changes
10.6. Meet with vendors and UA manufacturing team to take
delivery of products.
10.7. Coordinate initial product quality inspection with vendor
present.
10.8. Coordinate delivery schedule for each team with the ABC
Athletic Director and team staff.
10.9. Coordinate follow up meetings with each ABC team head
representative to ensure products are in line with the quality and
specifications put forth in the project charter.
10.10. Schedule media releases to announce successful delivery
of new Athletic Uniforms for ABC University.
10.11. Maintain the project plan document in the client’s file.
17. Review Schedule with Sponsor Document Sponsor Schedule
Feedback Make Necessary Schedule Changes Notify Supplier of
Changes Document Supplier Acceptance of Changes Schedule
Prototype QA Document Prototype QA Issues Resolve QA
Issues
13
Milestone 11: finalize
11.1. Compile all ABC University milestones/deliverables from
all the Planning Stage activities into a project plan document.
11.2. Review the project plan document with various Subject
Matter Experts (SMEs).
11.3. Incorporate any necessary changes to the document.
11.4. Distribute the project plan to the Project Sponsor and
other appropriate ABC University stakeholders.
11.5. Schedule a meeting with Project Sponsor and other
relevant ABC University stakeholders to review the project plan
deliverables.
11.6. Make any changes and or updates from the formal review.
11.7. Finalize the project plan milestones/deliverables.
11.8. Gain final approval/ signatures from the Project Sponsor
and any other designated stakeholder.
11.9. Transition Project to UA Account Manager
14
Project plan approval signatures
Project Manager:
___________________________
18. __________________________ _________
(Name/Signature) Organization Date
Project Sponsor:
________________________---___
__________________________ _________
(Name/Signature) Organization Date
Project Customer:
___________________________
__________________________ _________
(Name/Signature) Organization (Date)
DoIT Project Management Advisor, www.pma.doit.wisc.edu,
(2007). How to: Finalize Project Plan & Gain Approvals.
Retrieved on April 10, 2015 from
http://www.pma.doit.wisc.edu/plan/4/how.html
reference
Communication Management
As shown in my Communication Management Plan, my first
plan of action would be a (pre-Con) as I know it, or pre-
construction meeting, where we (all parties involved,) would
discuss:
· Expectations,
· Scheduling,
19. · Sequence of events
· Which uniforms would be required first or if in a lump sum
quantity
· Documentation the stakeholders would require
· Go over a list of approved vendors
I scheduled this for 1-2 hours, which would all depend on how
in depth the meeting would go, as well as allow for discussion
time amongst us all.
Next, I have listed monthly progress meetings, which ideally
should be face-to-face depending upon scheduling and
availability. This would allows us to go over any project
concerns, milestones, or tasks as well as, the ability to discuss
the actual progression of the project. I feel the main team
members involved in the project, as well as, the stakeholder
and/or representatives should make it a point to be at these
meetings in order to get a grasp of the rate at which the project
is moving along. This would also allow adequate time for
implementing changes if need be.
I inputted a section for (RFI’s) or request for information, and
this can come from any member involved in the project, in order
to clarify or address concerns, along with offering advice. I feel
email and fax would work best for this type of communication
as it is formally documented.
Next, I would like to conduct vendor design supply meetings, in
which the PM as well as merchandising teams, team leaders and
stakeholders, would attend bi-weekly web cam conferences, in
order to see how the vendors are incorporating the teams ideas,
as well as the availability of the merchandise and production
deadlines.
Lastly, I have assigned a monthly meeting to go over strategies
for marketing the products, dealing with public relations, as
well as setting a cost for the product. I believe the CEO, and
stakeholders should be the main contributors in this meeting,
and then pass down the information discussed to the varying
underlying agencies.
According to PMBOK, 2013., mu communication management
20. plan would all utilize familiar terminology so tat every audience
member is able to thoroughly understand matters being
addressed. Also, a major key to a success of a project is clear,
concise, reliable and informative information that can be
presented on a regular schedule or basis; not just when issues
arise. The ability to communicate steadily, gives everyone
involved in the project the ability to foresee any issues, and
remedy them before they happen.
Reference
Project Management/PMBOK/Communications Management.
(2013, March 3).
Wikibooks, The Free Textbook Project. Retrieved 02:34, April
9, 2015 from
http://en.wikibooks.org/w/index.php?title=Project_Management/
PMBOK/Communications_Management&oldid=2496417.
Comm. Name
Frequency
Method
Audience
Key Messages
Sender
Duration
Pre-Con
Initial meeting/does not repeat
Face-to face
PM, teamleaders, Stakeholder s and Representatives
Premliminary sequencing of events, expectations, budget
review, timeline, documentation requirements, vendors
Project Manager
1-2 hours
21. Progress Meeting
Monthly
Face-to Face
PM, teamleaders, Stakeholder s and Representatives
Schedule, budget, completion status, obstacles,
Team Admisinstrator
1 hour
RFI’s
Daily/weekly
/as needed
Email/fax
PM, Team leaders, stakeholder
Request for more information
Any initiator requiring more info or clarififcation
Varies however response
Should be given
with 24 hours
Vendor design supply
Bi-Weekly
Web cam
Stakeholders, team leaders, PM, merchandising team
Availability, shipping/
production time
Stakeholder/
PM
1-2 hours
Marketing/Merchandising
Team, Public Relations
Monthly
Web cam
Stakeholders, CEO, PM, Public Relations Team
Advertising schedule, price per unit, objective, revenue, stock
22. Stakeholder, CEO
1-2 hours
Statement of Work Template
www.ProjectManagementDocs.com
Statement of Work Template
This Statement of Work Template is free for you to copy and
use on your project
and within your organization. We hope that you find this
template useful and
welcome your comments. Public distribution of this document is
only permitted
from the Project Management Docs official website at:
www.ProjectManagementDocs.com
Statement of Work (SOW)
Under Armour, Inc.
1020 Hull Street
Baltimore, Maryland 21230
March 29, 2015
Table of Contents
2Introduction/Background
2Scope of Work
2Period of Performance
3Place of Performance
3Work Requirements
4Schedule/Milestones
23. 5Acceptance Criteria
5Other Requirements
Introduction/Background
Under Armour has been commissioned by ABC University along
with the college’s 25 athletic teams, to design, manufacture and
implement new performance sporting gear, equipment and
footwear. The improved athletic gear and redesigned collegiate
uniforms for our client is an exceptional opportunity not only to
improve the image of ABC University’s athletic programs, but
for Under Armour to gain free marketing exposure from the fans
and televised broadcasts of the sports teams. It is a necessity
that Under Armour approaches the re-design in such a manner
as to maintain the University’s approval, but also incorporating
performance technology with a mainstream design that will
allow the athletes to feel successful and empowered. In
consulting with ABC University, Under Armour understands the
importance of interacting and interpreting the elements required
in new gear, and performance equipment, while striving to
implement and accomplish the goals set fourth by ABC, as well
as, the standards within Under Armour itself. The new uniforms
must be mainstream and designed with the collegiate athlete in
mind. Equipment should be light, yet strong and footwear
should be supportive, breathable and comfortable for long hours
of wear. Under Armour plans to utilize innovative technologies,
new fabrics and successful branding, to produce bold, on trend
uniforms that will be reflective of Under Armour’s mission, as
well as, ABC University’s vision. Under Armour believes that
this approach will not only increase sales from the everyday
athlete, but also be successful in the recruitment of new
sponsorships.
Scope of Work
The scope of work for the equipment, gear and performance
footwear contract includes all research, planning, design,
manufacturing and implementation into everyday use by the
collegiate athletes. Under Armour will consort with ABC on all
design elements of the new uniforms, and will implement
24. changes based upon their feedback. Each stage of the project
will require approval from ABC’s Board of Directors’ before
proceeding to the next step. Physical samples of material, along
with design elements, will be provided to ABC for approval
before production. Under Armour has the authority to choose
it’s own vendors, as well as, other resources, which will be
needed in order to produce the required uniforms, gear and
footwear.Period of Performance
As per the contract, Under Armour has 6 months (180) days
from February 1, 2015 in order to gain approval for all
materials and designs that will be used in the manufacturing of
the new uniforms, gear and equipment. Any delays due to
indecision from ABC’s Board of Directors will be reflected as a
time modification and added to the original contract deadline
and initiated by Under Armour. Once design and equipment is
approved, Under Armour has 6 months (180) days from August
3, 2015 to produce the entirety of ABC’s order to the college
directly in order to begin implementation. Under Armour, will
provide enough personnel in order to distribute all the new
items to the college coaches, for delivery to the students. The
duration of the contract is 1 year, beginning February 1, 2015
(365 days) as long as there are no modifications or special
requests. All special requests must be in writing, from ABC’s
Board of Directors, to Under Armour. Under Armour then
reserves the right to extend the contract in reflection of the new
requests.Place of Performance
Under Armour will utilize it’s own vendors along with their
own facilities for the manufacturing and development of the
gear, uniforms and footwear. Under Armour will request on site
meetings with ABC’s Board of Directors, as a stage ends and
approval is needed from them in order to continue. Under
Armour will request in writing at least 1 week in advance for a
meeting to move forward. All efforts should be made by both
parties to come to an agreeable time that will not hinder the
production or flow of the schedule.Work Requirements
As part of the Uniform Redesign, and new Equipment
25. Implementation Project, Under Armour will be responsible for
performing tasks throughout various stages of this project. The
following is a list of these tasks, which will result in the
successful completion of this project:
Kickoff:
· Vendor will design, create and present a project plan including
schedule, location facilities, equipment test results, fabric
samples and implementation plan
· Under Armour will present the project plan to ABC Board of
Directors’ for review and approval before proceeding
Design Phase:
· Work with ABC to gather requirements, ideas and
functionality
· Create a mock up design based on collected requirements and
overall University vision
· Present weekly progress reports using video conferencing or
on site meeting
Build Phase:
· Under Armour will implement all approved design’s into gear,
footwear, and uniforms
· Under Armour will provide ABC with physical mock up’s of
the footwear and uniforms as they become available in order to
be approved for final manufacturing
· ABC will only include approved concepts into the re-design of
the gear, footwear and equipment
· ABC will resolve any issues as required by ABC
· Present weekly progress reports using video conferencing or
on site meeting
Implementation Phase:
· Under Armour will coordinate with ABC University within the
allotted contract guidelines, in order to implement the gear,
26. footwear, and uniforms into the collegiate programs
· Under Armour will serve as sole liaison for delivery of the
redesigned items to the college directly.
· Under Armour will conduct weekly video conferencing when
implementation is 30 days or less away.
Project Handoff/Closure:
· Under Armour will provide ABC with all documentation in
accordance with the approved project plan
· Under Armour will present a project closure report to ABC for
review and approval
· Under Armour will complete all guidelines as required by the
contract and implement all approved specs into the redesign of
the equipment, gear and uniforms
· Under Armour will sign off of the project following
implementation day, after all deliverables have been assigned to
their proper organizations
· Under Armour’s contract will conclude on or before 11:59
p.m. on February 3, 2016 post delivery of merchandise, unless a
modification has been implemented. At which time, the day of
delivery will conclude UA’s further involvement with
ABC.Schedule/Milestones
The below list consists of the initial milestones identified for
the Uniform Redesign, and New Equipment Implementation
Project:
RFP/SOW Release
February 2, 2015
27. Under Armour product Design/Review
March 1-28, 2015
ABC Board approval of prelim-design
May 1, 2015
Period of Mock up design Begins
June 1, 2015
Mock up design presented to ABC
June 21, 2015
ABC Final Approval
July 10, 2015
Manufacturing Begins
July 15, 2015
Implementation Complete
28. November 1, 2015
Project Completion Review
November 2, 2015
Project Closure/Archives Complete
November 2, 2015Acceptance Criteria
For the Uniform Redesign, and new Equipment Implementation
Project, the acceptance of all deliverables will reside with
ABC’s Board of Director’s or assigned Representatives. The
Board, or Representatives, will ensure that the uniforms,
footwear, and equipment are of approved design and quality,
thereby maintaining that the project scope was met. Under
Armour suggests that an agreed upon day, once manufacturing
has been completed, and before implementation day, that ABC’s
Board of Directors or Representatives, schedule a review of the
equipment, footwear, and uniforms which are to be presented to
the college on implementation day. By scheduling this ahead of
time, both parties can agree in advance as to the final products’
quality and design. This should allow the project closure to flow
easier, as the quality assurance will have already been agreed
upon. Once ABC approves the new products, Under Armour
will provide and submit their signoff/project closure report, as
well as, a checklist for review. At which time the Board, or
Representatives, will sign off on the project closure request
and document any changes they need remedied before
finalization.
The acceptance of this documentation by ABC’s Board of
Directors or Representatives, will acknowledge acceptance of
29. all project deliverables and that Under Armour has met all
assigned tasks.
Any discrepancies involving completion of project tasks or
disagreements between ABC and Under Armour, will be
referred to both organizations’ contracting offices for review
and discussion.
Other Requirements
None at this time
Acceptance
Approved by:
Date:
<Tania Amador>
<Project Manager>
This free Statement of Work Template is brought to you by
www.ProjectManagementDocs.com
PAGE
1
TEMPLATE: PROJECT PURPOSE AND JUSTIFICATION
(The justification and validity of the project needs to be
confirmed before the project proceeds. This document is used to
clarify the project purpose and justification and to gain approval
to proceed to the next phase.)
Project Title
Working Title:
Develop, manufacture and distribute Under Armour branded
30. collegiate apparel, and performance footwear for ABC’s 25
athletic teams, for a duration of seven years 2015-2022
(completed by Tania Amador)
UTS File Title:
Marketing Sponsorship Proposal for ABC University
(Completed by Tania Amador)
Reference
Anderson, T. (March 25, 2009). [email protected] Guide to
Project Management.
Retrieved from
www.projects.uts.edu.au/resources/pdfs/StepbyStepGuide2009.p
df
Project Purpose
(Describe the purpose / need / rationale / feasibility for the
project)
Background and Strategic Context
(Explain the background to the project and how it relates to the
key strategic plans.)
Priority
Related Projects
Project Client/Owner
(The person who requires the project to be undertaken)
Project Sponsor
(The person who is providing the funds and has the ultimate
authority over the project)
Project Manager
(The person who has the authority to manage the project on a
day-to-day basis).
Project Status
(What has already been decided about the project? What
decisions have already been made? What work has already been
done in relation to the project? Any assumptions or
constraints?)
Special Provisions
(Special regulations, ethical considerations etc.)
31. · Under Armour to be exclusive outfitter of uniform apparel and
footwear to ABC University’s 25 Collegiate athletic teams
· Under Armour apparel contract defined as 3.5M in apparel &
3.5M as a monetary donation annually for the term of 7 years
· Varsity athletes will be unable to wear outside outfitters
during games
· Varsity apparel from outside outfitters may be worn during
athletes recreational time as well as any practices
· Under Armour retains the ability to market and promote it’s
brand in a matter that does not conflict with ABC University’s
Commitment to Excellence Statement
· ABC University’s official outfitter agreement will include
“entitlements that will complement Under Armour’s marketing
campaign through venue presence and advertising at the
University (UMBC retrievers, 2012).
· Under Armour agrees to refrain from promoting or enforcing
endorsement of products that could inadvertently affect ABC
University’s values or mission. (Completed by Tania Amador)
Reference
UMBC retrievers. (December 3, 2012). UMBC announces Under
Armour as official outfitter of Retriever Athletics.
Retrieved from
www.umbcretrievers.com/Sports/general/2014_AE_Commission
er-s_Cup/12-3-2012
Project Approvals
Add any signatures that are required for approval to proceed to
the next phase
__________________________________ Project Manager
__________________________________ Project Client/Owner
____________________ Project Sponsor
____________________
Other