SlideShare a Scribd company logo
1 of 25
Download to read offline
Governance in public sector projects 1
25 February 2015
Governance in public sector projects
Lessons from welfare reform programmes
Max Tse, National Audit Office
APM Governance SIG presentation
Governance in public sector projects 2
About us
Yvonne Gallagher
 Digital expert
 Former CIO in two
govt. departments
 Expert in IT, cyber,
business change
Max Tse
 Director (VFM)
 Work & pensions
 Former consultant
and economist
Geraldine Barker
 Director, Project
Delivery
 Programme expert
 Recently VFM
audit director for
transport
Alison Hood
 Audit Manager
 Programme lead
 Expert in project
and programme
management
Some of the (many) people in the NAO interested in governance and programmes
Governance in public sector projects 3
Today’s discussion
 Why welfare reform?
 Learning lessons from welfare reform programmes
 Wider NAO work on programme management and governance
Governance in public sector projects 4
Today’s discussion
 Why welfare reform?
 Learning lessons from welfare reform programmes
 Wider NAO work on programme management and governance
Governance in public sector projects 5
Welfare reform has had some challenges…
Source: NAO, Universal Credit: progress update, December 2014
 Combining 6 benefits
into 1 payment
 Originally aimed to
complete by 2017
 Agile approach
aimed to tackle past
programme failings
 Reset in early 2013
 Currently twin track
roll-out with revised
completion date
Governance in public sector projects 6
…experienced costly delays…
Source: NAO, Personal Independence Payment: early progress, February 2014
 Replacing Disability Living Allowance
with greater assessment of needs
 2 contractors (Atos and Capita)
 Early development of backlogs
 Initial expectation of large savings,
but delays to roll-out and savings
 Currently recovering from backlogs
and slowly expanding roll-out
Governance in public sector projects 7
…and exposed failings in contracts
Source: NAO, Contract management of medical services, October 2012
 Replacing Incapacity Benefit
with work capability
assessment
 Problems with backlogs,
then quality led to Atos
exiting contract
 Savings not achieved as
expected
Governance in public sector projects 8
On the other hand some things have gone better
Source: NAO, Child maintenance 2012 scheme: early progress, June 2014
 Long history of troubled CM
systems (1993, 2003)
 Phased reform with new
system and then introduction
of charging and case closure
 Early performance of phase
1 encouraging
Governance in public sector projects 9
Governance has been a focus in welfare reform…
Source: NAO, Child maintenance 2012 scheme: early progress, June 2014, Appendix Three
Comparison of aspects of governance of welfare reforms
Governance in public sector projects 10
…echoing many existing principles of governance
APM’s Directing Change principles
Governance in public sector projects 11
So what have we learnt from recent experience?
NAO work in progress notice
Governance in public sector projects 12
Today’s discussion
 Why welfare reform?
 Learning lessons from welfare reform programmes
 Wider NAO work on programme management and governance
Governance in public sector projects 13
Lessons from implementing welfare reform
The irreducible obligation to
be informed
The centrality of an operating
model perspective
The illusion of control over
specification
The elusive capacity question
The (apparent) paradox of
time
Phasing and learning: redux
The gradualist reactive default
Management information: the
poor cousin
Some lessons from welfare reform (preliminary)
Governance in public sector projects 14
Lesson 1: The irreducible obligation to
be informed
Programme aims need to take account of wider departmental responsibilities and trade-offs. Trying to define
aims too narrowly can lead to unanticipated consequential costs and issues in defining performance criteria.
Directing Change principles include clear differentiation between project and non-project activities (1) and
clearly defined roles, responsibilities and performance criteria for governing the project (3).
Governance in public sector projects 15
Lesson 2: The centrality of an
operating model perspective
Departments must align transformation with overall view of business model, including how people will use
the service, and how sustainable internal processes will be in supporting the service.
Directing Change principles include the need for a coherent relationship between overall business strategy
and portfolio (5).
Universal Credit, predicted channel use Child maintenance, cost sensitivities
Governance in public sector projects 16
Lesson 3: The illusion of control over
specification
Departments are limited in their ability to specify how services will work. They need to understand end users
and delivery partners, as well as the constraints they face in serving wider public objectives.
Directing Change principles include need for engagement with stakeholders to foster trust (12) and clear
relationship with business policies on ethics and sustainability (5).
Changes in minimum service standards
on the Work Programme
Housing Benefit fraud and error
The Department has had to change its
approach to maintaining minimum levels of
service…The Department originally allowed
contractors to set their own minimum service
standards. Contractors set 212 standards and
the Department could not monitor these
effectively…
NAO, The Work Programme, July 2014
Governance in public sector projects 17
Lesson 4: The elusive capacity
question
With programme vacancies, and limited information about portfolio capacity and risk, programmes are
particularly dependent on a small number of senior programme leaders for direction and oversight.
Directing Change principles include need for disciplined governance arrangements and a project sponsor
for each project (4).
High turnover in Universal Credit Stable leadership in child maintenance
 SROs since 2010: 6
 Programme directors since 2010: 6
 Multiple changes in CIO/CTO
Governance in public sector projects 18
Lesson 5: The (apparent) paradox of
time
Programmes struggle with setting specific (but not certain) timetables and being clear about the trade-offs
involved. Departments need to judge risk and make decisions openly throughout a programme.
Directing Change principles include frank internal disclosure of information and progress (11), and relevant
and realistic information supporting decisions (8).
Shift in Universal Credit caseload projections Planned acceleration of PIP savings
Governance in public sector projects 19
Lesson 6: Phasing and learning: redux
Lessons about avoiding ‘big bang’ are widely accepted, but the detail of how to phase implementation or
manage agile development is still challenging, as is the need to recognise learning curves in early stages.
Directing Change principles clear criteria for escalating concerns and risks (10) and realistic information for
authorising decisions (8).
Original phasing profile in PIP Learning curves in the Work Programme
Governance in public sector projects 20
Lesson 7: The gradualist reactive
default
Departments can often react well to shocks in core businesses, and some programmes may be most
comfortable introducing change in a similar reactive or gradualist way. Risks arise in new approaches.
Directing Change principles include need for governance arrangements to be supported by appropriate
cultures (4) and matching competence and resources to delegated authorities (7).
Adjusting FTEs in jobcentres in downturn Impact assessments in Housing Benefit
Governance in public sector projects 21
Lesson 8: Management information:
the poor cousin
Programmes often treat management information as a dimension of flexibility when under pressure, or fail to
set clear requirements for information that is needed. This is compounded by lack of end-to-end oversight.
Directing Change principles include relevant and realistic information (8), clearly defined criteria for reporting
project status and escalating risks (10).
Limited MI at the start of PIP… …and the Work Programme
Management information at the start of the
programme was limited. The Department did not
complete initial work on its new management
information tool in April 2013, as planned,
despite discussing this risk regularly since
January 2013. The Department now expects to
complete all work by the end of 2014. It has
adopted an interim solution …
NAO, Personal Independence Payment:
early progress, February 2014
The IT project to support the Programme was
not fully functional when the Work Programme
was launched…The Department will also not be
able to use its IT support to generate
management information on how many job and
sustainment outcomes the Work Programme, or
individual providers, are delivering until
September 2012 at the earliest.
NAO, The Work Programme, July 2014
Governance in public sector projects 22
Today’s discussion
 Why welfare reform?
 Learning lessons from welfare reform programmes
 Wider NAO work on programme management and governance
Governance in public sector projects 23
We are developing wider work on project and
programme management
Governance in public sector projects 24
Thank you
Max Tse
Max.Tse@nao.gsi.gov.uk
For all reports mentioned
www.nao.org.uk
Governance in public sector projects 25
This presentation was delivered
at an APM event
To find out more about
upcoming events please visit our
website www.apm.org.uk/events

More Related Content

What's hot

Developments in performance budgeting - Andrew Blazey, OECD Secretariat
Developments in performance budgeting - Andrew Blazey, OECD SecretariatDevelopments in performance budgeting - Andrew Blazey, OECD Secretariat
Developments in performance budgeting - Andrew Blazey, OECD SecretariatOECD Governance
 
Getting a Federal ICT department to listen to the Voice of its Customers
Getting a Federal ICT department to listen to the Voice of its CustomersGetting a Federal ICT department to listen to the Voice of its Customers
Getting a Federal ICT department to listen to the Voice of its CustomersMielabelo
 
The Challenges of Pulling Together 10,000 Lessons Learned and What Has Been L...
The Challenges of Pulling Together 10,000 Lessons Learned and What Has Been L...The Challenges of Pulling Together 10,000 Lessons Learned and What Has Been L...
The Challenges of Pulling Together 10,000 Lessons Learned and What Has Been L...Martin Paver
 
Day 2 1230 - 1315 - pearl 1 - vineet jain v1.1
Day 2   1230 - 1315 - pearl 1 - vineet jain v1.1Day 2   1230 - 1315 - pearl 1 - vineet jain v1.1
Day 2 1230 - 1315 - pearl 1 - vineet jain v1.1PMI2011
 
Module 1rev
Module 1revModule 1rev
Module 1revcomesa15
 
1 a. introduction to project management
1 a. introduction to project management1 a. introduction to project management
1 a. introduction to project managementDr.R. SELVAM
 
Information Technology Project Management - part 12
Information Technology Project Management - part 12Information Technology Project Management - part 12
Information Technology Project Management - part 12Rizwan Khurram
 
From Grant Dependent to Profit Centre
From Grant Dependent to Profit CentreFrom Grant Dependent to Profit Centre
From Grant Dependent to Profit CentreNaseha Sameen
 
LSI - PMP - Training material
LSI - PMP - Training materialLSI - PMP - Training material
LSI - PMP - Training materialKrishna Sujeer
 
Information Technology Project Management - part 02
Information Technology Project Management - part 02Information Technology Project Management - part 02
Information Technology Project Management - part 02Rizwan Khurram
 
Information Technology Project Management - part 01
Information Technology Project Management - part 01Information Technology Project Management - part 01
Information Technology Project Management - part 01Rizwan Khurram
 

What's hot (16)

Developments in performance budgeting - Andrew Blazey, OECD Secretariat
Developments in performance budgeting - Andrew Blazey, OECD SecretariatDevelopments in performance budgeting - Andrew Blazey, OECD Secretariat
Developments in performance budgeting - Andrew Blazey, OECD Secretariat
 
Getting a Federal ICT department to listen to the Voice of its Customers
Getting a Federal ICT department to listen to the Voice of its CustomersGetting a Federal ICT department to listen to the Voice of its Customers
Getting a Federal ICT department to listen to the Voice of its Customers
 
The Challenges of Pulling Together 10,000 Lessons Learned and What Has Been L...
The Challenges of Pulling Together 10,000 Lessons Learned and What Has Been L...The Challenges of Pulling Together 10,000 Lessons Learned and What Has Been L...
The Challenges of Pulling Together 10,000 Lessons Learned and What Has Been L...
 
Day 2 1230 - 1315 - pearl 1 - vineet jain v1.1
Day 2   1230 - 1315 - pearl 1 - vineet jain v1.1Day 2   1230 - 1315 - pearl 1 - vineet jain v1.1
Day 2 1230 - 1315 - pearl 1 - vineet jain v1.1
 
Module 1rev
Module 1revModule 1rev
Module 1rev
 
1 a. introduction to project management
1 a. introduction to project management1 a. introduction to project management
1 a. introduction to project management
 
How to pass cobit exam
How to pass cobit exam   How to pass cobit exam
How to pass cobit exam
 
Information Technology Project Management - part 12
Information Technology Project Management - part 12Information Technology Project Management - part 12
Information Technology Project Management - part 12
 
From Grant Dependent to Profit Centre
From Grant Dependent to Profit CentreFrom Grant Dependent to Profit Centre
From Grant Dependent to Profit Centre
 
LSI - PMP - Training material
LSI - PMP - Training materialLSI - PMP - Training material
LSI - PMP - Training material
 
Information Technology Project Management - part 02
Information Technology Project Management - part 02Information Technology Project Management - part 02
Information Technology Project Management - part 02
 
Software project management
Software project managementSoftware project management
Software project management
 
Cobit 5 - An Overview
Cobit 5 - An OverviewCobit 5 - An Overview
Cobit 5 - An Overview
 
Rest assured - the role of programme and project assurance
Rest assured - the role of programme and project assuranceRest assured - the role of programme and project assurance
Rest assured - the role of programme and project assurance
 
Information Technology Project Management - part 01
Information Technology Project Management - part 01Information Technology Project Management - part 01
Information Technology Project Management - part 01
 
Facts on Public Finance Management
Facts on Public Finance ManagementFacts on Public Finance Management
Facts on Public Finance Management
 

Similar to National Audit Office: Lessons from welfare reform programmes, 25th feb

APM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challengesAPM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challengesAssociation for Project Management
 
Benefits Management in Health and Care part 1: Identify and map target benefits
Benefits Management in Health and Care part 1: Identify and map target benefitsBenefits Management in Health and Care part 1: Identify and map target benefits
Benefits Management in Health and Care part 1: Identify and map target benefitsAssociation for Project Management
 
Evaluation Report - The Many Faces of Collaboration
Evaluation Report - The Many Faces of CollaborationEvaluation Report - The Many Faces of Collaboration
Evaluation Report - The Many Faces of CollaborationAssociation of Colleges
 
APM Benefits Summit 2017 - Implementing a benefits-led approach to portfolio ...
APM Benefits Summit 2017 - Implementing a benefits-led approach to portfolio ...APM Benefits Summit 2017 - Implementing a benefits-led approach to portfolio ...
APM Benefits Summit 2017 - Implementing a benefits-led approach to portfolio ...Association for Project Management
 
UCISA Toolkit - Effective Benefits Management for Business Change and IT Proj...
UCISA Toolkit - Effective Benefits Management for Business Change and IT Proj...UCISA Toolkit - Effective Benefits Management for Business Change and IT Proj...
UCISA Toolkit - Effective Benefits Management for Business Change and IT Proj...Mark Ritchie
 
Pfm Measure 2008
Pfm Measure 2008Pfm Measure 2008
Pfm Measure 2008euweben01
 
Pfm Measure 2008
Pfm Measure 2008Pfm Measure 2008
Pfm Measure 2008euwebsc01
 
Pfm Measure 2008
Pfm Measure 2008Pfm Measure 2008
Pfm Measure 2008euwebtc01
 
An introductory guide to implementation (ces)
An introductory guide to implementation (ces)An introductory guide to implementation (ces)
An introductory guide to implementation (ces)Nazila Hana
 
MEAL WORKSHOP ON ETH1224-draft.pptx
MEAL WORKSHOP ON ETH1224-draft.pptxMEAL WORKSHOP ON ETH1224-draft.pptx
MEAL WORKSHOP ON ETH1224-draft.pptxAbraham Lebeza
 
Epidemiology & Community Optometry-8,9,10,11.pptx
Epidemiology & Community Optometry-8,9,10,11.pptxEpidemiology & Community Optometry-8,9,10,11.pptx
Epidemiology & Community Optometry-8,9,10,11.pptxssuser22cc61
 
USER GUIDE M&E 2014 LENNY HIDAYAT
USER GUIDE M&E 2014 LENNY HIDAYATUSER GUIDE M&E 2014 LENNY HIDAYAT
USER GUIDE M&E 2014 LENNY HIDAYATLenny Hidayat
 
How to Achieve Measurable Benefits Through Project and Organizational Change
How to Achieve Measurable Benefits Through Project and Organizational ChangeHow to Achieve Measurable Benefits Through Project and Organizational Change
How to Achieve Measurable Benefits Through Project and Organizational ChangePactera_US
 
Project Management
Project ManagementProject Management
Project ManagementMayanSardana
 
FuturePMO 2017 - Susan Palmer-Trew, The Open University: Do Less. Do it Better.
FuturePMO 2017 - Susan Palmer-Trew, The Open University: Do Less. Do it Better.FuturePMO 2017 - Susan Palmer-Trew, The Open University: Do Less. Do it Better.
FuturePMO 2017 - Susan Palmer-Trew, The Open University: Do Less. Do it Better.Wellingtone
 
Commissioning - Principles v5.1
Commissioning - Principles v5.1Commissioning - Principles v5.1
Commissioning - Principles v5.1Julian Ingram
 

Similar to National Audit Office: Lessons from welfare reform programmes, 25th feb (20)

APM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challengesAPM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challenges
 
How to successfully deliver business change
How to successfully deliver business changeHow to successfully deliver business change
How to successfully deliver business change
 
Benefits Management in Health and Care part 1: Identify and map target benefits
Benefits Management in Health and Care part 1: Identify and map target benefitsBenefits Management in Health and Care part 1: Identify and map target benefits
Benefits Management in Health and Care part 1: Identify and map target benefits
 
Evaluation Report - The Many Faces of Collaboration
Evaluation Report - The Many Faces of CollaborationEvaluation Report - The Many Faces of Collaboration
Evaluation Report - The Many Faces of Collaboration
 
Performance Evaluation in Public Service.
Performance Evaluation in Public Service.Performance Evaluation in Public Service.
Performance Evaluation in Public Service.
 
APM Benefits Summit 2017 - Implementing a benefits-led approach to portfolio ...
APM Benefits Summit 2017 - Implementing a benefits-led approach to portfolio ...APM Benefits Summit 2017 - Implementing a benefits-led approach to portfolio ...
APM Benefits Summit 2017 - Implementing a benefits-led approach to portfolio ...
 
UCISA Toolkit - Effective Benefits Management for Business Change and IT Proj...
UCISA Toolkit - Effective Benefits Management for Business Change and IT Proj...UCISA Toolkit - Effective Benefits Management for Business Change and IT Proj...
UCISA Toolkit - Effective Benefits Management for Business Change and IT Proj...
 
Pfm Measure 2008
Pfm Measure 2008Pfm Measure 2008
Pfm Measure 2008
 
Pfm Measure 2008
Pfm Measure 2008Pfm Measure 2008
Pfm Measure 2008
 
Pfm Measure 2008
Pfm Measure 2008Pfm Measure 2008
Pfm Measure 2008
 
An introductory guide to implementation (ces)
An introductory guide to implementation (ces)An introductory guide to implementation (ces)
An introductory guide to implementation (ces)
 
MEAL WORKSHOP ON ETH1224-draft.pptx
MEAL WORKSHOP ON ETH1224-draft.pptxMEAL WORKSHOP ON ETH1224-draft.pptx
MEAL WORKSHOP ON ETH1224-draft.pptx
 
Program-for-Results - An Overview and experiences in results-based funding
Program-for-Results - An Overview and experiences in results-based fundingProgram-for-Results - An Overview and experiences in results-based funding
Program-for-Results - An Overview and experiences in results-based funding
 
Epidemiology & Community Optometry-8,9,10,11.pptx
Epidemiology & Community Optometry-8,9,10,11.pptxEpidemiology & Community Optometry-8,9,10,11.pptx
Epidemiology & Community Optometry-8,9,10,11.pptx
 
USER GUIDE M&E 2014 LENNY HIDAYAT
USER GUIDE M&E 2014 LENNY HIDAYATUSER GUIDE M&E 2014 LENNY HIDAYAT
USER GUIDE M&E 2014 LENNY HIDAYAT
 
How to Achieve Measurable Benefits Through Project and Organizational Change
How to Achieve Measurable Benefits Through Project and Organizational ChangeHow to Achieve Measurable Benefits Through Project and Organizational Change
How to Achieve Measurable Benefits Through Project and Organizational Change
 
Good governance of the project portfolio
Good governance of the project portfolioGood governance of the project portfolio
Good governance of the project portfolio
 
Project Management
Project ManagementProject Management
Project Management
 
FuturePMO 2017 - Susan Palmer-Trew, The Open University: Do Less. Do it Better.
FuturePMO 2017 - Susan Palmer-Trew, The Open University: Do Less. Do it Better.FuturePMO 2017 - Susan Palmer-Trew, The Open University: Do Less. Do it Better.
FuturePMO 2017 - Susan Palmer-Trew, The Open University: Do Less. Do it Better.
 
Commissioning - Principles v5.1
Commissioning - Principles v5.1Commissioning - Principles v5.1
Commissioning - Principles v5.1
 

More from Association for Project Management

Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Association for Project Management
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Association for Project Management
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...Association for Project Management
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Association for Project Management
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...Association for Project Management
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Association for Project Management
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Association for Project Management
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Association for Project Management
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Association for Project Management
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...Association for Project Management
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024Association for Project Management
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Association for Project Management
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...Association for Project Management
 

More from Association for Project Management (20)

Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
 

Recently uploaded

Buy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From SeosmmearthBuy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From SeosmmearthBuy Verified Binance Account
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfwill854175
 
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow ChallengesFalcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow Challengeshemanthkumar470700
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in OmanMifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Omaninstagramfab782445
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptxnandhinijagan9867
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Adnet Communications
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1kcpayne
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon investment
 
Over the Top (OTT) Market Size & Growth Outlook 2024-2030
Over the Top (OTT) Market Size & Growth Outlook 2024-2030Over the Top (OTT) Market Size & Growth Outlook 2024-2030
Over the Top (OTT) Market Size & Growth Outlook 2024-2030tarushabhavsar
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon investment
 
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdfTVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdfbelieveminhh
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizharallensay1
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannaBusinessPlans
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 

Recently uploaded (20)

Buy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From SeosmmearthBuy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From Seosmmearth
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow ChallengesFalcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in OmanMifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
Over the Top (OTT) Market Size & Growth Outlook 2024-2030
Over the Top (OTT) Market Size & Growth Outlook 2024-2030Over the Top (OTT) Market Size & Growth Outlook 2024-2030
Over the Top (OTT) Market Size & Growth Outlook 2024-2030
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdfTVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 Updated
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 

National Audit Office: Lessons from welfare reform programmes, 25th feb

  • 1. Governance in public sector projects 1 25 February 2015 Governance in public sector projects Lessons from welfare reform programmes Max Tse, National Audit Office APM Governance SIG presentation
  • 2. Governance in public sector projects 2 About us Yvonne Gallagher  Digital expert  Former CIO in two govt. departments  Expert in IT, cyber, business change Max Tse  Director (VFM)  Work & pensions  Former consultant and economist Geraldine Barker  Director, Project Delivery  Programme expert  Recently VFM audit director for transport Alison Hood  Audit Manager  Programme lead  Expert in project and programme management Some of the (many) people in the NAO interested in governance and programmes
  • 3. Governance in public sector projects 3 Today’s discussion  Why welfare reform?  Learning lessons from welfare reform programmes  Wider NAO work on programme management and governance
  • 4. Governance in public sector projects 4 Today’s discussion  Why welfare reform?  Learning lessons from welfare reform programmes  Wider NAO work on programme management and governance
  • 5. Governance in public sector projects 5 Welfare reform has had some challenges… Source: NAO, Universal Credit: progress update, December 2014  Combining 6 benefits into 1 payment  Originally aimed to complete by 2017  Agile approach aimed to tackle past programme failings  Reset in early 2013  Currently twin track roll-out with revised completion date
  • 6. Governance in public sector projects 6 …experienced costly delays… Source: NAO, Personal Independence Payment: early progress, February 2014  Replacing Disability Living Allowance with greater assessment of needs  2 contractors (Atos and Capita)  Early development of backlogs  Initial expectation of large savings, but delays to roll-out and savings  Currently recovering from backlogs and slowly expanding roll-out
  • 7. Governance in public sector projects 7 …and exposed failings in contracts Source: NAO, Contract management of medical services, October 2012  Replacing Incapacity Benefit with work capability assessment  Problems with backlogs, then quality led to Atos exiting contract  Savings not achieved as expected
  • 8. Governance in public sector projects 8 On the other hand some things have gone better Source: NAO, Child maintenance 2012 scheme: early progress, June 2014  Long history of troubled CM systems (1993, 2003)  Phased reform with new system and then introduction of charging and case closure  Early performance of phase 1 encouraging
  • 9. Governance in public sector projects 9 Governance has been a focus in welfare reform… Source: NAO, Child maintenance 2012 scheme: early progress, June 2014, Appendix Three Comparison of aspects of governance of welfare reforms
  • 10. Governance in public sector projects 10 …echoing many existing principles of governance APM’s Directing Change principles
  • 11. Governance in public sector projects 11 So what have we learnt from recent experience? NAO work in progress notice
  • 12. Governance in public sector projects 12 Today’s discussion  Why welfare reform?  Learning lessons from welfare reform programmes  Wider NAO work on programme management and governance
  • 13. Governance in public sector projects 13 Lessons from implementing welfare reform The irreducible obligation to be informed The centrality of an operating model perspective The illusion of control over specification The elusive capacity question The (apparent) paradox of time Phasing and learning: redux The gradualist reactive default Management information: the poor cousin Some lessons from welfare reform (preliminary)
  • 14. Governance in public sector projects 14 Lesson 1: The irreducible obligation to be informed Programme aims need to take account of wider departmental responsibilities and trade-offs. Trying to define aims too narrowly can lead to unanticipated consequential costs and issues in defining performance criteria. Directing Change principles include clear differentiation between project and non-project activities (1) and clearly defined roles, responsibilities and performance criteria for governing the project (3).
  • 15. Governance in public sector projects 15 Lesson 2: The centrality of an operating model perspective Departments must align transformation with overall view of business model, including how people will use the service, and how sustainable internal processes will be in supporting the service. Directing Change principles include the need for a coherent relationship between overall business strategy and portfolio (5). Universal Credit, predicted channel use Child maintenance, cost sensitivities
  • 16. Governance in public sector projects 16 Lesson 3: The illusion of control over specification Departments are limited in their ability to specify how services will work. They need to understand end users and delivery partners, as well as the constraints they face in serving wider public objectives. Directing Change principles include need for engagement with stakeholders to foster trust (12) and clear relationship with business policies on ethics and sustainability (5). Changes in minimum service standards on the Work Programme Housing Benefit fraud and error The Department has had to change its approach to maintaining minimum levels of service…The Department originally allowed contractors to set their own minimum service standards. Contractors set 212 standards and the Department could not monitor these effectively… NAO, The Work Programme, July 2014
  • 17. Governance in public sector projects 17 Lesson 4: The elusive capacity question With programme vacancies, and limited information about portfolio capacity and risk, programmes are particularly dependent on a small number of senior programme leaders for direction and oversight. Directing Change principles include need for disciplined governance arrangements and a project sponsor for each project (4). High turnover in Universal Credit Stable leadership in child maintenance  SROs since 2010: 6  Programme directors since 2010: 6  Multiple changes in CIO/CTO
  • 18. Governance in public sector projects 18 Lesson 5: The (apparent) paradox of time Programmes struggle with setting specific (but not certain) timetables and being clear about the trade-offs involved. Departments need to judge risk and make decisions openly throughout a programme. Directing Change principles include frank internal disclosure of information and progress (11), and relevant and realistic information supporting decisions (8). Shift in Universal Credit caseload projections Planned acceleration of PIP savings
  • 19. Governance in public sector projects 19 Lesson 6: Phasing and learning: redux Lessons about avoiding ‘big bang’ are widely accepted, but the detail of how to phase implementation or manage agile development is still challenging, as is the need to recognise learning curves in early stages. Directing Change principles clear criteria for escalating concerns and risks (10) and realistic information for authorising decisions (8). Original phasing profile in PIP Learning curves in the Work Programme
  • 20. Governance in public sector projects 20 Lesson 7: The gradualist reactive default Departments can often react well to shocks in core businesses, and some programmes may be most comfortable introducing change in a similar reactive or gradualist way. Risks arise in new approaches. Directing Change principles include need for governance arrangements to be supported by appropriate cultures (4) and matching competence and resources to delegated authorities (7). Adjusting FTEs in jobcentres in downturn Impact assessments in Housing Benefit
  • 21. Governance in public sector projects 21 Lesson 8: Management information: the poor cousin Programmes often treat management information as a dimension of flexibility when under pressure, or fail to set clear requirements for information that is needed. This is compounded by lack of end-to-end oversight. Directing Change principles include relevant and realistic information (8), clearly defined criteria for reporting project status and escalating risks (10). Limited MI at the start of PIP… …and the Work Programme Management information at the start of the programme was limited. The Department did not complete initial work on its new management information tool in April 2013, as planned, despite discussing this risk regularly since January 2013. The Department now expects to complete all work by the end of 2014. It has adopted an interim solution … NAO, Personal Independence Payment: early progress, February 2014 The IT project to support the Programme was not fully functional when the Work Programme was launched…The Department will also not be able to use its IT support to generate management information on how many job and sustainment outcomes the Work Programme, or individual providers, are delivering until September 2012 at the earliest. NAO, The Work Programme, July 2014
  • 22. Governance in public sector projects 22 Today’s discussion  Why welfare reform?  Learning lessons from welfare reform programmes  Wider NAO work on programme management and governance
  • 23. Governance in public sector projects 23 We are developing wider work on project and programme management
  • 24. Governance in public sector projects 24 Thank you Max Tse Max.Tse@nao.gsi.gov.uk For all reports mentioned www.nao.org.uk
  • 25. Governance in public sector projects 25 This presentation was delivered at an APM event To find out more about upcoming events please visit our website www.apm.org.uk/events