Contents
1. Project Management Proposal
2. Business Case
3. Project charter
4. Work breakdown structure
5. Project Status Report
6. Work Breakdown Structure & Schedules
7. Work Breakdown Structure & Budget

©Md. Asif Sultanul Arefeen
American International University-Bangladesh
WEB Design Project Proposal
I. Short description about our project

Develop an Internet Site for the City online Shopping Mall. Create a Customer interactive
web page design. Develop a consistent theme with the city logo, headings, and buttons.
Provide a product list and their prices which is displayed on the Internet. Provide an
"Interactive Form" where people can leave messages and receive replies.

II. Budget


Total estimate cost of this project is $ 10000.

III. Time estimate


Estimate time limit is 6 months.

IV. Site Name Registration
A. Registering the Domain Name

We recommends reserving the top level domain name "cityshopping.org" which is available
at this time. The often used "ci.city.ca.us" can be pointed in to the main site so users familiar
with this name can still find the site. Having the name of the city, with an .org extension is
good situation and should be reserved immediately. This is a similar web presence we
established for the city of New York.
B. Email Addressing

Top level domain names allows you to use your domain name in your email. In this case it
may be administration@cityshopping.org. Domain level email addressing gives a consistent
professional look in the Internet community.

V. Webcam Site Design
A. Site Design

The site will contain the information from the existing site as well as additional information
from the city. In the case of Cypress we divided the site along city departments. Internet
sites for cities are an excellent opportunity to provide often requested information on the
web. Typically a city web site will be divided approximately six major sections with 8 to 10
pages per section.
B. Design Methodology

It is essential to establish a polished and professional look. Mills Group Multimedia will
establish a temporary area, out of view from the general public, to post design concepts for
©Md. Asif Sultanul Arefeen
American International University-Bangladesh
client approval. We will begin by creating three versions of the site main page. Upon
approval of the strongest concept we will develop a consistent look for section headings,
logo, footers and buttons.
C. Site Content

With an approved consistent look established the next step is to add content to the site.
Generally clients will gather existing materials (pamphlets, forms, papers, photographs) and
send them to us. We take the materials and ready them for the site. The content is then
parsed out into individual web pages and assembled in a hierarchy which is easy to
understand and to navigate. Site content is added to pages which have a consistent theme
and look in terms of headers, footers and accent graphics like buttons and bullets.
D. Developing the Site

Upon name registration we will establish the site. Generally we will put up an "under
construction" page which announces the site will be coming soon. Then we begin to post
the site pages behind the scenes so only we and our client can see the pages. This allows the
client to see the progress as we build the site. Together we review the site on the phone
during the building process. When the site is complete we remove the "under construction"
page and insert the site main page in its place and the site becomes open to the public.
Throughout the process the client is involved in the design process.
E. User Accounts

We will provide our each of the customer a user accounts where they will keep their
shopping history. The user of the site will open their account by email and social media also.

F. Interactive Form

Internet technology allows for communication forums. We will provide an interactive form
(often called a guest book) which allows for an open exchange of information between the
city and its citizens. The interactive form will act as an on line meeting area to develop a
sense of community using Internet communication.
City shopping website retested user will be able to make comment with a username and
password for the interactive form. City shopping website user will also be able to access the
form and add, delete, and modify messages.

VI. Web Site Hosting
A. Internet Software

We own co-located servers that resides at Mexico. We maintain a small group of selected
clients on our server. Owning our server allows us to offer high end software systems on the
web. Features such as on line calendars require significant server side programming and
knowledge.
©Md. Asif Sultanul Arefeen
American International University-Bangladesh
B. Benefits of Hosting

Web hosting clients take advantage of a range of Internet technologies not available
through other hosting services. We are Internet programming specialists. The systems
require server side programming. Because we own the platform we routinely deploy these
systems for our hosting clients.

VII. Compensation and Terms (Site Design)
A. Compensation

We agree to design and install the web site and administrative functions described above
for the fee of $10000 inclusive of the following:
1. All Design and Layout described above
2. All Programming described above
3. Installation of web pages and programs on target web server.
4. Marketing the Site with Search Engine Listing
B. Terms

1. Deposit - 50% prior to starting work
2. Progress Payment - 20% upon site completion and buy off
3. Final Payment - 30% thirty days after site completion

VIII. Compensation and Terms (Hosting)
A. Hosting Compensation

1. Site Name Registration and Set Up: 2 day (one time)
2. Internet Corporate Web Hosting: 1 month
3. Pointer for second domain name: 2 month
B. Hosting Terms

1. Payable 6 months in advance by check, or
2. Payable monthly by credit card

©Md. Asif Sultanul Arefeen
American International University-Bangladesh
Business Case
September 29, 2013
1.0 Introduction/ Background

City online Shopping Mall is a new concept of online shopping store in Mexico. It is a
new business and run by two owners. The main concept of this business is give a new
experience in online shopping that fulfill your demand in a real cost. This online business
need a new site for their customer which is more attractive and easy to use. The design is
include with an “Interactive Form” that help to connect the customer with the website
admin. The form will use for customer feedback purpose.
2.0 Business objective

City online Shopping Mall business objective is increase the profit and make the business
in number one position in Mexico and also make a top class online store. Their goals is
continuing growth of the business and make it internationally.
3.0 Current Situation and Problems/ Opportunity Statement

City online Shopping Mall is a new business. There is also more five companies is
available in the Mexico market. So the completion is hard. But City’s main competitor
will be in the Mexico’s third biggest online shopping website buynsell.com. All the
current shopping website is now use oldest version web security HTML. But we will Use
HTML5. That is more secured and more customer attractive. In the world market
“amazon.com”, “ebay.com” use HTML5 and they are successfully run their business.
Day by day Mexican customer is dependent on the online shopping because of its save
their time. So it is easy to realize that the day is come it’s demand will increase.

4.0 Critical Assumptions and Constraints

This project need a customer attractive, easy to maintain, easy to shopping and easy to
updatable webpage template. The template will work in flash and HTML5 language. The
template will also increase the level of online shopping experience. The Web design is
make simple but unique. The design will also help to increase the SEO. The Webpage
make satisfied our sponsor as well as their customer.
5.0 Analysis of Options and Recommendation

We will recommendation some options that will increase the attractiveness of this project.
That is:
I.
II.

The website design is include the SEO then the project is fully pleased by its
maker.
If the project is introduced in the global then the design might be more attractive.
©Md. Asif Sultanul Arefeen
American International University-Bangladesh
III.

If the time of the project is one year then it might be made more creative.

6.0 Preliminary Project Requirements
The main requirements of this project include the following:






Need to make a plan for design, time, money and quality ensure management.
We need an e-marketing template for Web page design.
Need a critical analysis for sponsor demand.
Make sure the design is approved by the sponsor.
Make a team for the project.

7.0 Budget Estimate and Financial Analysis

Our Total Budget for the project is $10000. The preliminary estimate of costs for the
entire projects is $5000. Half of the Costs is for Web Template buy and registration of the
website. Another Half of the Costs is for Web Hosting and Web place buy. We will use
our Rest of the money is for SEO purpose. We Use 2000 dollar for increase the rank of
website. 500 dollar for Facebook marketing. 1000 dollar for submit the website in Search
engine like Google, yahoo, Bing etc. And another 1500 dollar will be used for testing
purpose.

8.0 Schedule Estimate

Our total time for this project is six months. Project will be started from 1st January and it
will be completed in 30th June. We work 1 st month for selecting the Template and then
within 10 days we completed our registration process. Then we work for design and
modification and it will continue one month. Then we will submit our website in the
search engines. Then we will tasted our website as a pilot case in 3 months. That time we
monitoring our website to identify our design errors.
9.0 Potential Risks

There are several risks involved with this projects. The foremost risk is complete the
project in the limited budget and duration time schedule. The design will not accepted by
the sponsor and their customers. Misunderstanding between the sponsor and the designer
because of poor communication.

©Md. Asif Sultanul Arefeen
American International University-Bangladesh
PROJECT CHARTER
1. General Information
Date:

01-10-2013

Project Title:

Website Design Project

Project Sponsor:

Karl Louis Armstrong

Start / Finish Date:

01-11-2013

Budget Allocation:

The developers of the project has allocated $1000 for this project.
Approximately half of the costs will be for design materials, whereas the other
half will be for developed the design purpose.

31-04-2014

2. Stakeholders
SL

ID

Name

Project Manager:

Karl Louis Armstrong

Business Leader:

Atique Ullah

Technical Leader:

Md. Asif Sultanul Arefeen

Key Team Member:

Muhammad Ziaul Kader

Key Team Member:

Miss Susmita

3. Project / Service Description
* Project Objectives / Business Justification Describe the product or service that this project will produce (e.g., “This
project will manage relocation to a new headquarters location for ABC Corporation.”) Measurable business outcomes of the
project. Business Objectives typically deal with cost, time, and quality (e.g., reduce the cost of delivery of this service by 30%).
Describe the business problem or need being addressed (e.g., “ABC Corporations is currently at risk for interruption of essential
services due to lack of space in its current location”).

Develop a new site for the new online Shopping business. The business is totally doing i
n online by using the website. So this website is the main way to do the business. Their a
ll success is depend on this website. They need a customer’s friendly design. That is ea
sy to use and secured filling to use the website. The website design must be simple but
unique. The design will be also help to increase the business.
* Project Deliverables List the high-level project, sub-products or project phases whose satisfactory delivery mark
completion of the project (e.g., site selection, vendor selection, installation of office equipment and furniture, opening session).

We are designing the small elements of the website like buttons, plugin, Interactive Form a
nd the front flash menu.
* Project Exclusion (Will Not be Include) (Example: Phase 1 of the Headquarters Relocation project will not
include the planned employee fitness center.)

In the project will not be included coding of the website development languages and the SEO.

©Md. Asif Sultanul Arefeen
American International University-Bangladesh
3. Project / Service Description
* Project Milestones Proposed start and end dates for Project Phases (e.g., Inception, Planning, Design,
Development, Testing, and Rollout) and other major milestones.

1. Selecting the Template for the design.
2. Selecting the way of the design.
3. Estimate the cost of the project
4. Estimate the time of the project
5. Divided the works between team members.
* Project Approaches Describe primary plans briefly on the following (Will the project have formal written plans – i.e.,
Project Schedule, Budget, and Resource? How will project issues be dealt with? List any scheduled project team
meetings, planned status reports)

We have to complite the project within six months. Time is short but enough if we do all the work
perfectly and timely. Our budget for this project is $1000. We will develop a design template in Adobe
Phothoshop and Illustrator then we make a unique but a simple design. We will also adjust our flash
button, plugin and other templet elements. Then we are write our content in the website. After that we run
our design as pailot case and mesurement our quility with beanch marking way. If we will setisfied then
monitoring the process. If it is error free then we submit our project to the project sponser. He will be
justified our design. If any chage or modification is needed then we will do this. After that if he is said
“ok” then our project phase is completed, but the project is not fully completed, because it is not running
in the real business. If the design is perfect for the real business then the project is completed.

* Assumption & Constraints List any conditions that may limit the project team’s options with respect to resources,
personnel, or schedule (e.g., predetermined budget or project end date, limit on number of staff that may be assigned to
the project). Include both internal risks and external risks. (e.g., Internal Risk – Move In date may be in jeopardy if
decisions about office furniture are not made on time. External Risk – Office Furniture vendor has a poor track record of
on-time delivery).

There is saveral risk involve to this project. The devided the risk in two kinds. One is internal and another
is external.
Internal Risk1. Conflict between project manager, technical advisor and the designer
2. Lack of knowledge about the programming language.
3. If the time is not maintain then cost of budget will increase.
External Risk1. The Design might not be unique due to lack of knowledge
2. Design element like plugin, button, flash etc might not be avabile in the internet
3. Internet connect might be problem due to slow speed.

* Project Success Criteria Define what must be done in order for this project to be considered a success by its
stakeholders.

We will use latest type of design element, flash and plugin. We also use google customized search engine
that will help to the user of this website.It is also considered a success by its stakeholders. Our design will
also help to make the SEO incress. So it is also a sucees by its stakeholders.

©Md. Asif Sultanul Arefeen
American International University-Bangladesh
4. Sign-off
Name
Project Sponsor:

Pater Louis Armstrong

Project Manager

Date(dd-mon-yy)

Karl Louis Armstrong

Co-Sponsor

Signature

Karl Louis Armstrong

5. Comments (Handwritten or typed comments from above stakeholders, if applicable)
“If the contact menu is more upgradable and include the social media box the it look
more attractive”--- Karl Louis Armstrong, project manager and Sponsor

©Md. Asif Sultanul Arefeen
American International University-Bangladesh
PROJECT WORK BREAKDOWN STRUCTURE
1. General Information
Date:
Project Title:
Project Sponsor:
Start / Finish Date:
Budget Allocation:

1-10-2013
website design project
Karl Louis Armstrong
1-11-2013
31-4-2014
The developers of the project has allocated $10000 for this project. Approximately half of
the costs will be for design materials, whereas the
other half will
be for developed the design purpose.

2. Project Deliverable:
S/L

Deliverable Name

1.0

Buttons

2.0

Plugin

3.0

Interactive formant the front flash menu

3. Work Breakdown Structure
Deliverable Name
S/L

WBS Element Name
.1

Initiating
1.1 Prepare stakeholder analysis
1.2 Create project charter
1.3 Prepare business case
1.4 Prepare preliminary scope statement

©Md. Asif Sultanul Arefeen
American International University-Bangladesh
3. Work Breakdown Structure
.2

Planning

2.1 Project integration management
2.1.1
2.1.2

Create team contract

Develop project management plan

2.2 Project time management

2.3 project cost management
2.3.1 web template buy and registration of the website
2.3.2 web hosting and web place buy
2.3.3 SEO purpose
2.3.4 Facebook marketing
2.3.5 Submit the website in search engine
2.4 project communication management
2.5 project risk management
2.5.1 Time
2.5.2 Budget
2.5.3 Communication
2.5.4 Technical problem
2.5.5 Lack knowledge about programming language
.3

Executing

3.1 create design

3.1.1
3.1.2
3.1.3
3.1.4

Design creation
Color matching
Web widgets matching
Web buttons creation

3.2 Implementation
3.2.1 Design and coding match
3.2.2 Adding button and widgets in the main design

©Md. Asif Sultanul Arefeen
American International University-Bangladesh
3. Work Breakdown Structure
.4

Monitoring and controlling
4.1
4.2
4.3
4.4
4.5

.5

Time

Cost
Design
SEO
Size of fonts

Closing
5.1 Finalize the design
5.2 Make a simple closing of the project

5. Comments (Handwritten or typed comments from above stakeholders, if applicable)
“It is pretty cool and handsome work break down structure”
- Karl Louis Armstrong, Project Sponsor.

©Md. Asif Sultanul Arefeen
American International University-Bangladesh
Project Status Report
1. General Information
Date:

01/11/2013

Project Title:

website design project

Project Manager:

Karl Louis Armstrong

Reporting Period:

2 Month

2. Summary
Overall Status:
Green 1

Yellow 2

Red 3

(Controlled)

(Caution)

(Critical)

Budget:

[ ]

[ √]

[ ]

Schedule:

[ ]

[ ]

[√]

Scope:

[√ ]

[ ]

[ ]

Quality:

[ √]

[ ]

[ ]

1 Project
2

Reason for Deviation

Due to some unavoidable situation we need more time to complete
our project.

is within budget, scope and on schedule.

Project has deviated slightly from the plan but should recover

3

Project has fallen significantly behind schedule, is forecast to be significantly over budget, and/or has taken on tasks
that are out of scope.

3. Scheduled Milestones / Deliverables
List any Project Milestones that are late as well as Milestones due in the next 4 to 6 weeks.

Milestone

Approved
Schedule

Actual
Completion

Current
Forecast

Status
(%)

Facebook marketing

5 Day

15/11/13

20/11/13

O%

Submit the website in search engine

2 Day

21/11/13

23/11/13

0%

Web buttons creation

8 Days

24/11/13

1/1/14

60%

Adding button and widgets in the main design

4 Days

02/01/14

05/01/14

20%

SEO

5 Days

05/01/14

09/01/14

50%

Web widgets matching

2 Days

10/01/14

12/01/14

50%

2 Days

13/01/14

15/01/14

80%

Lack knowledge about programming language

©Md. Asif Sultanul Arefeen
American International University-Bangladesh
4. Accomplishments / Plans
.1 Accomplishments during this Reporting Period (Should relate to milestones):











Create project charter
Prepare business case
Prepare preliminary scope statement
project integration management
create team contract
develop project management plan
project time management
project cost management
web template buy and registration of the website
web hosting and web place buy

.2 Plans during the next Reporting Period (Should relate to milestones):












web hosting and web place buy
SEO purpose
Facebook marketing
Submit the website in search engine
project communication management
project risk management
Time
Budget
Communication
Technical problem
Lack knowledge about programming language

.3 What went well during this Reporting Period (Should relate to milestones):









create design
Design creation
Color matching
Web widgets matching
Web buttons creation
Implementation
Design and coding match
Adding button and widgets in the main design

.4 What did not go well during this Reporting Period (Should relate to milestones):

©Md. Asif Sultanul Arefeen
American International University-Bangladesh
4. Accomplishments / Plans






Time
Cost
Design
SEO
Size of fonts

5. Controls
.1 Issue Status (Issues requiring resolution by Project Team or Executive Committee):

This is the landing status for new issues. Issues stay in this status until they are assigned,
acknowledged, confirmed or resolved. The next status can be "acknowledged", "confirmed",
"assigned" or "resolved"

.2 Recommendation (Recommendation on corrective actions executed or planned to resolve plan project issues
incurred and risk identified and project changes from baseline which would require approval by the Project Sponsor and
possibly the Executive Committee):

This status is used by the development team to reflect their agreement to the suggested feature
request. Or to agree with what the project is suggesting in an issue project, although they didn't
yet attempt to reproduce what the project is referring to. The next status is typically "assigned"
or "confirmed"

.3 Project Change (Changes raised for consideration that change the approved project baselines. Would require
approval by the Project Sponsor and possibly the Executive Committee):

This status is used to reflect that the issue has been resolved. An issue can be resolved with one
of many resolutions (customizable). For example, an issue can be resolved as "fixed",
"duplicate", "won't fix", "no change required", etc.

.4 Comments

This status reflects that the issue is completely closed and no further actions are required on it. It
also typically hides the issue from the View Issues page. Some teams use "closed" to reflect
sign-off by the reporter and others use it to reflect the fact that the fix has been released to
customers

©Md. Asif Sultanul Arefeen
American International University-Bangladesh

More Related Content

What's hot

Project charter - website design
Project charter - website designProject charter - website design
Project charter - website designDave Jones
 
E Commerce Project Charter
E Commerce Project CharterE Commerce Project Charter
E Commerce Project Charterbrianbish10795
 
Ecommerce Online Store Developer Proposal PowerPoint Presentation Slides
Ecommerce Online Store Developer Proposal PowerPoint Presentation SlidesEcommerce Online Store Developer Proposal PowerPoint Presentation Slides
Ecommerce Online Store Developer Proposal PowerPoint Presentation SlidesSlideTeam
 
Ecommerce Website Design Proposal PowerPoint Presentation Slides
Ecommerce Website Design Proposal PowerPoint Presentation SlidesEcommerce Website Design Proposal PowerPoint Presentation Slides
Ecommerce Website Design Proposal PowerPoint Presentation SlidesSlideTeam
 
Agile Product Roadmaps
Agile Product RoadmapsAgile Product Roadmaps
Agile Product RoadmapsRoman Pichler
 
Web Design Proposal Powerpoint Presentation Slides
Web Design Proposal Powerpoint Presentation SlidesWeb Design Proposal Powerpoint Presentation Slides
Web Design Proposal Powerpoint Presentation SlidesSlideTeam
 
E Commerce Website Design Proposal PowerPoint Presentation Slides
E Commerce Website Design Proposal PowerPoint Presentation SlidesE Commerce Website Design Proposal PowerPoint Presentation Slides
E Commerce Website Design Proposal PowerPoint Presentation SlidesSlideTeam
 
Web Design Proposal PowerPoint Presentation Slides
Web Design Proposal PowerPoint Presentation Slides Web Design Proposal PowerPoint Presentation Slides
Web Design Proposal PowerPoint Presentation Slides SlideTeam
 
Rocket Internet Company Presentation
Rocket Internet Company PresentationRocket Internet Company Presentation
Rocket Internet Company PresentationNishan Bose
 
How to Create a Product Vision by Dropbox PM
How to Create a Product Vision by Dropbox PMHow to Create a Product Vision by Dropbox PM
How to Create a Product Vision by Dropbox PMProduct School
 
Practical Product Management for new Product Managers
Practical Product Management for new Product ManagersPractical Product Management for new Product Managers
Practical Product Management for new Product ManagersAmarpreet Kalkat
 
Rocket Internet Overview 2014
Rocket Internet Overview 2014Rocket Internet Overview 2014
Rocket Internet Overview 2014Joerg Strotmann
 
Front-end development introduction (HTML, CSS). Part 1
Front-end development introduction (HTML, CSS). Part 1Front-end development introduction (HTML, CSS). Part 1
Front-end development introduction (HTML, CSS). Part 1Oleksii Prohonnyi
 
Proposal bull hotel website design & development
Proposal bull hotel website design & developmentProposal bull hotel website design & development
Proposal bull hotel website design & developmentmikerogerhexagon
 
User Story Mapping in Practice
User Story Mapping in PracticeUser Story Mapping in Practice
User Story Mapping in PracticeSteve Rogalsky
 
Agile Product Manager/Product Owner Dilemma (PMEC)
Agile Product Manager/Product Owner Dilemma (PMEC)Agile Product Manager/Product Owner Dilemma (PMEC)
Agile Product Manager/Product Owner Dilemma (PMEC)Enthiosys Inc
 

What's hot (20)

Project charter - website design
Project charter - website designProject charter - website design
Project charter - website design
 
E Commerce Project Charter
E Commerce Project CharterE Commerce Project Charter
E Commerce Project Charter
 
Ecommerce Online Store Developer Proposal PowerPoint Presentation Slides
Ecommerce Online Store Developer Proposal PowerPoint Presentation SlidesEcommerce Online Store Developer Proposal PowerPoint Presentation Slides
Ecommerce Online Store Developer Proposal PowerPoint Presentation Slides
 
Product Roadmap
Product RoadmapProduct Roadmap
Product Roadmap
 
Ecommerce Website Design Proposal PowerPoint Presentation Slides
Ecommerce Website Design Proposal PowerPoint Presentation SlidesEcommerce Website Design Proposal PowerPoint Presentation Slides
Ecommerce Website Design Proposal PowerPoint Presentation Slides
 
Sample Website Proposal Presentation
Sample Website Proposal PresentationSample Website Proposal Presentation
Sample Website Proposal Presentation
 
Agile Product Roadmaps
Agile Product RoadmapsAgile Product Roadmaps
Agile Product Roadmaps
 
Product roadmap strategy
Product roadmap strategyProduct roadmap strategy
Product roadmap strategy
 
Web Design Proposal Powerpoint Presentation Slides
Web Design Proposal Powerpoint Presentation SlidesWeb Design Proposal Powerpoint Presentation Slides
Web Design Proposal Powerpoint Presentation Slides
 
Sample proposal
Sample proposalSample proposal
Sample proposal
 
E Commerce Website Design Proposal PowerPoint Presentation Slides
E Commerce Website Design Proposal PowerPoint Presentation SlidesE Commerce Website Design Proposal PowerPoint Presentation Slides
E Commerce Website Design Proposal PowerPoint Presentation Slides
 
Web Design Proposal PowerPoint Presentation Slides
Web Design Proposal PowerPoint Presentation Slides Web Design Proposal PowerPoint Presentation Slides
Web Design Proposal PowerPoint Presentation Slides
 
Rocket Internet Company Presentation
Rocket Internet Company PresentationRocket Internet Company Presentation
Rocket Internet Company Presentation
 
How to Create a Product Vision by Dropbox PM
How to Create a Product Vision by Dropbox PMHow to Create a Product Vision by Dropbox PM
How to Create a Product Vision by Dropbox PM
 
Practical Product Management for new Product Managers
Practical Product Management for new Product ManagersPractical Product Management for new Product Managers
Practical Product Management for new Product Managers
 
Rocket Internet Overview 2014
Rocket Internet Overview 2014Rocket Internet Overview 2014
Rocket Internet Overview 2014
 
Front-end development introduction (HTML, CSS). Part 1
Front-end development introduction (HTML, CSS). Part 1Front-end development introduction (HTML, CSS). Part 1
Front-end development introduction (HTML, CSS). Part 1
 
Proposal bull hotel website design & development
Proposal bull hotel website design & developmentProposal bull hotel website design & development
Proposal bull hotel website design & development
 
User Story Mapping in Practice
User Story Mapping in PracticeUser Story Mapping in Practice
User Story Mapping in Practice
 
Agile Product Manager/Product Owner Dilemma (PMEC)
Agile Product Manager/Product Owner Dilemma (PMEC)Agile Product Manager/Product Owner Dilemma (PMEC)
Agile Product Manager/Product Owner Dilemma (PMEC)
 

Viewers also liked

Business Case template for LavaCon "Creating a Content Strategy Ecosystem" wo...
Business Case template for LavaCon "Creating a Content Strategy Ecosystem" wo...Business Case template for LavaCon "Creating a Content Strategy Ecosystem" wo...
Business Case template for LavaCon "Creating a Content Strategy Ecosystem" wo...Andrea L. Ames
 
The business case for SaaS HR workforce management HCM software technology
The business case for SaaS HR workforce management HCM software technologyThe business case for SaaS HR workforce management HCM software technology
The business case for SaaS HR workforce management HCM software technologyCharles Bedard
 
Business Case - Project Management template
Business Case - Project Management template Business Case - Project Management template
Business Case - Project Management template Simon Misiewicz
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)Anand Subramaniam
 
Project 5 Flowchart - Publix Wines Website
Project 5 Flowchart - Publix Wines WebsiteProject 5 Flowchart - Publix Wines Website
Project 5 Flowchart - Publix Wines WebsiteOrlandoMagic14
 
Hanrahan power point business proposal week 6
Hanrahan power point business proposal week 6Hanrahan power point business proposal week 6
Hanrahan power point business proposal week 6allstarmax13
 
Final presentation power point
Final presentation power pointFinal presentation power point
Final presentation power pointOrlandoMagic14
 
Hanrahan power point business proposal week 6 revised
Hanrahan power point business proposal week 6 revisedHanrahan power point business proposal week 6 revised
Hanrahan power point business proposal week 6 revisedallstarmax13
 
State fair project ( Remote Car Parking System)
State fair project ( Remote Car Parking System)State fair project ( Remote Car Parking System)
State fair project ( Remote Car Parking System)akash veerappan
 
Hanrahan power point business proposal
Hanrahan power point business proposalHanrahan power point business proposal
Hanrahan power point business proposalallstarmax13
 
Final Report Project Presentation
Final Report Project Presentation Final Report Project Presentation
Final Report Project Presentation Christian Pratts
 
Project Management Slides
Project Management Slides Project Management Slides
Project Management Slides Christian Pratts
 
Business Proposal - IT Project
Business Proposal - IT ProjectBusiness Proposal - IT Project
Business Proposal - IT ProjectSharad Srivastava
 
Alpha Case Study - Contract Administration Sample
Alpha Case Study - Contract Administration SampleAlpha Case Study - Contract Administration Sample
Alpha Case Study - Contract Administration SampleAgatha Maia Duarte de Assis
 
Project Business Case
Project Business CaseProject Business Case
Project Business CaseNader Jarmooz
 

Viewers also liked (20)

Business Case template for LavaCon "Creating a Content Strategy Ecosystem" wo...
Business Case template for LavaCon "Creating a Content Strategy Ecosystem" wo...Business Case template for LavaCon "Creating a Content Strategy Ecosystem" wo...
Business Case template for LavaCon "Creating a Content Strategy Ecosystem" wo...
 
The business case for SaaS HR workforce management HCM software technology
The business case for SaaS HR workforce management HCM software technologyThe business case for SaaS HR workforce management HCM software technology
The business case for SaaS HR workforce management HCM software technology
 
Project charter j
Project charter jProject charter j
Project charter j
 
Business Case - Project Management template
Business Case - Project Management template Business Case - Project Management template
Business Case - Project Management template
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)
 
Project 5 Flowchart - Publix Wines Website
Project 5 Flowchart - Publix Wines WebsiteProject 5 Flowchart - Publix Wines Website
Project 5 Flowchart - Publix Wines Website
 
Hanrahan power point business proposal week 6
Hanrahan power point business proposal week 6Hanrahan power point business proposal week 6
Hanrahan power point business proposal week 6
 
Final presentation power point
Final presentation power pointFinal presentation power point
Final presentation power point
 
Powerpoint
Powerpoint Powerpoint
Powerpoint
 
Pictures
PicturesPictures
Pictures
 
Hanrahan power point business proposal week 6 revised
Hanrahan power point business proposal week 6 revisedHanrahan power point business proposal week 6 revised
Hanrahan power point business proposal week 6 revised
 
State fair project ( Remote Car Parking System)
State fair project ( Remote Car Parking System)State fair project ( Remote Car Parking System)
State fair project ( Remote Car Parking System)
 
Hanrahan power point business proposal
Hanrahan power point business proposalHanrahan power point business proposal
Hanrahan power point business proposal
 
Untitled 2
Untitled 2Untitled 2
Untitled 2
 
Final Report Project Presentation
Final Report Project Presentation Final Report Project Presentation
Final Report Project Presentation
 
Project Management Slides
Project Management Slides Project Management Slides
Project Management Slides
 
Business Proposal - IT Project
Business Proposal - IT ProjectBusiness Proposal - IT Project
Business Proposal - IT Project
 
Project Charter
Project CharterProject Charter
Project Charter
 
Alpha Case Study - Contract Administration Sample
Alpha Case Study - Contract Administration SampleAlpha Case Study - Contract Administration Sample
Alpha Case Study - Contract Administration Sample
 
Project Business Case
Project Business CaseProject Business Case
Project Business Case
 

Similar to Webpage design full project of project management

Cd chasedaddy-web-proposal
Cd chasedaddy-web-proposalCd chasedaddy-web-proposal
Cd chasedaddy-web-proposalChase Daddy
 
Plan it now safe boxes
Plan it now  safe boxesPlan it now  safe boxes
Plan it now safe boxesHenry Stafford
 
Best Digital Marketing Services
Best Digital Marketing Services Best Digital Marketing Services
Best Digital Marketing Services Pinacle Web India
 
Web Designing Training in Ambala ! Batra Computer Centre
Web Designing Training in Ambala ! Batra Computer CentreWeb Designing Training in Ambala ! Batra Computer Centre
Web Designing Training in Ambala ! Batra Computer Centrejatin batra
 
How Much Does Website Development Cost?
How Much Does Website Development Cost?How Much Does Website Development Cost?
How Much Does Website Development Cost?EngineerBabu
 
Website Development Proposal For Corporate PowerPoint Presentation Slides
Website Development Proposal For Corporate PowerPoint Presentation SlidesWebsite Development Proposal For Corporate PowerPoint Presentation Slides
Website Development Proposal For Corporate PowerPoint Presentation SlidesSlideTeam
 
Website design and development company
Website design and development  companyWebsite design and development  company
Website design and development companyMtoag Technologies
 
Webigence Credentials - showcasing technically complex bespoke ASP.NET projects
Webigence Credentials - showcasing technically complex bespoke ASP.NET projectsWebigence Credentials - showcasing technically complex bespoke ASP.NET projects
Webigence Credentials - showcasing technically complex bespoke ASP.NET projectsWebigence
 
“Inchem Cooperation Website”
“Inchem Cooperation Website”“Inchem Cooperation Website”
“Inchem Cooperation Website”IRJET Journal
 
Corporate Presentation - WebonRetail
Corporate Presentation - WebonRetailCorporate Presentation - WebonRetail
Corporate Presentation - WebonRetaile_nitin
 
Geoxis iHub Pvt Ltd Profile
Geoxis iHub Pvt Ltd ProfileGeoxis iHub Pvt Ltd Profile
Geoxis iHub Pvt Ltd ProfileGeoxis
 
Tisfleet.com SEO Project Portfolio by Holistic eCommerce.pptx
Tisfleet.com SEO Project Portfolio by Holistic eCommerce.pptxTisfleet.com SEO Project Portfolio by Holistic eCommerce.pptx
Tisfleet.com SEO Project Portfolio by Holistic eCommerce.pptxholisticommercesolut
 
What is the Importance of Responsive Web Design for Business Development?
What is the Importance of Responsive Web Design for Business Development?What is the Importance of Responsive Web Design for Business Development?
What is the Importance of Responsive Web Design for Business Development?Versatile Mobitech
 
What is the Importance of Responsive Web Design for Business Development_.pptx
What is the Importance of Responsive Web Design for Business Development_.pptxWhat is the Importance of Responsive Web Design for Business Development_.pptx
What is the Importance of Responsive Web Design for Business Development_.pptxVersatile Mobitech
 

Similar to Webpage design full project of project management (20)

Kamran Ali CV
Kamran Ali CVKamran Ali CV
Kamran Ali CV
 
ka info
ka infoka info
ka info
 
Cd chasedaddy-web-proposal
Cd chasedaddy-web-proposalCd chasedaddy-web-proposal
Cd chasedaddy-web-proposal
 
Plan it now safe boxes
Plan it now  safe boxesPlan it now  safe boxes
Plan it now safe boxes
 
Best Digital Marketing Services
Best Digital Marketing Services Best Digital Marketing Services
Best Digital Marketing Services
 
Web Designing Training in Ambala ! Batra Computer Centre
Web Designing Training in Ambala ! Batra Computer CentreWeb Designing Training in Ambala ! Batra Computer Centre
Web Designing Training in Ambala ! Batra Computer Centre
 
How Much Does Website Development Cost?
How Much Does Website Development Cost?How Much Does Website Development Cost?
How Much Does Website Development Cost?
 
Website Development Proposal For Corporate PowerPoint Presentation Slides
Website Development Proposal For Corporate PowerPoint Presentation SlidesWebsite Development Proposal For Corporate PowerPoint Presentation Slides
Website Development Proposal For Corporate PowerPoint Presentation Slides
 
Website design and development company
Website design and development  companyWebsite design and development  company
Website design and development company
 
Webigence Credentials - showcasing technically complex bespoke ASP.NET projects
Webigence Credentials - showcasing technically complex bespoke ASP.NET projectsWebigence Credentials - showcasing technically complex bespoke ASP.NET projects
Webigence Credentials - showcasing technically complex bespoke ASP.NET projects
 
Web design 3
Web design 3Web design 3
Web design 3
 
Website Presentation for Corporate
Website Presentation for Corporate Website Presentation for Corporate
Website Presentation for Corporate
 
“Inchem Cooperation Website”
“Inchem Cooperation Website”“Inchem Cooperation Website”
“Inchem Cooperation Website”
 
GLAM COLLECTION.pptx
GLAM COLLECTION.pptxGLAM COLLECTION.pptx
GLAM COLLECTION.pptx
 
Website Development vs Web App Development.pptx
Website Development vs Web App Development.pptxWebsite Development vs Web App Development.pptx
Website Development vs Web App Development.pptx
 
Corporate Presentation - WebonRetail
Corporate Presentation - WebonRetailCorporate Presentation - WebonRetail
Corporate Presentation - WebonRetail
 
Geoxis iHub Pvt Ltd Profile
Geoxis iHub Pvt Ltd ProfileGeoxis iHub Pvt Ltd Profile
Geoxis iHub Pvt Ltd Profile
 
Tisfleet.com SEO Project Portfolio by Holistic eCommerce.pptx
Tisfleet.com SEO Project Portfolio by Holistic eCommerce.pptxTisfleet.com SEO Project Portfolio by Holistic eCommerce.pptx
Tisfleet.com SEO Project Portfolio by Holistic eCommerce.pptx
 
What is the Importance of Responsive Web Design for Business Development?
What is the Importance of Responsive Web Design for Business Development?What is the Importance of Responsive Web Design for Business Development?
What is the Importance of Responsive Web Design for Business Development?
 
What is the Importance of Responsive Web Design for Business Development_.pptx
What is the Importance of Responsive Web Design for Business Development_.pptxWhat is the Importance of Responsive Web Design for Business Development_.pptx
What is the Importance of Responsive Web Design for Business Development_.pptx
 

Recently uploaded

Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
The Future of Software Development - Devin AI Innovative Approach.pdf
The Future of Software Development - Devin AI Innovative Approach.pdfThe Future of Software Development - Devin AI Innovative Approach.pdf
The Future of Software Development - Devin AI Innovative Approach.pdfSeasiaInfotech2
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clashcharlottematthew16
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...Fwdays
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr LapshynFwdays
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024Lorenzo Miniero
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piececharlottematthew16
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubKalema Edgar
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsRizwan Syed
 

Recently uploaded (20)

Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
The Future of Software Development - Devin AI Innovative Approach.pdf
The Future of Software Development - Devin AI Innovative Approach.pdfThe Future of Software Development - Devin AI Innovative Approach.pdf
The Future of Software Development - Devin AI Innovative Approach.pdf
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clash
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piece
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding Club
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL Certs
 

Webpage design full project of project management

  • 1.
  • 2. Contents 1. Project Management Proposal 2. Business Case 3. Project charter 4. Work breakdown structure 5. Project Status Report 6. Work Breakdown Structure & Schedules 7. Work Breakdown Structure & Budget ©Md. Asif Sultanul Arefeen American International University-Bangladesh
  • 3. WEB Design Project Proposal I. Short description about our project Develop an Internet Site for the City online Shopping Mall. Create a Customer interactive web page design. Develop a consistent theme with the city logo, headings, and buttons. Provide a product list and their prices which is displayed on the Internet. Provide an "Interactive Form" where people can leave messages and receive replies. II. Budget  Total estimate cost of this project is $ 10000. III. Time estimate  Estimate time limit is 6 months. IV. Site Name Registration A. Registering the Domain Name We recommends reserving the top level domain name "cityshopping.org" which is available at this time. The often used "ci.city.ca.us" can be pointed in to the main site so users familiar with this name can still find the site. Having the name of the city, with an .org extension is good situation and should be reserved immediately. This is a similar web presence we established for the city of New York. B. Email Addressing Top level domain names allows you to use your domain name in your email. In this case it may be administration@cityshopping.org. Domain level email addressing gives a consistent professional look in the Internet community. V. Webcam Site Design A. Site Design The site will contain the information from the existing site as well as additional information from the city. In the case of Cypress we divided the site along city departments. Internet sites for cities are an excellent opportunity to provide often requested information on the web. Typically a city web site will be divided approximately six major sections with 8 to 10 pages per section. B. Design Methodology It is essential to establish a polished and professional look. Mills Group Multimedia will establish a temporary area, out of view from the general public, to post design concepts for ©Md. Asif Sultanul Arefeen American International University-Bangladesh
  • 4. client approval. We will begin by creating three versions of the site main page. Upon approval of the strongest concept we will develop a consistent look for section headings, logo, footers and buttons. C. Site Content With an approved consistent look established the next step is to add content to the site. Generally clients will gather existing materials (pamphlets, forms, papers, photographs) and send them to us. We take the materials and ready them for the site. The content is then parsed out into individual web pages and assembled in a hierarchy which is easy to understand and to navigate. Site content is added to pages which have a consistent theme and look in terms of headers, footers and accent graphics like buttons and bullets. D. Developing the Site Upon name registration we will establish the site. Generally we will put up an "under construction" page which announces the site will be coming soon. Then we begin to post the site pages behind the scenes so only we and our client can see the pages. This allows the client to see the progress as we build the site. Together we review the site on the phone during the building process. When the site is complete we remove the "under construction" page and insert the site main page in its place and the site becomes open to the public. Throughout the process the client is involved in the design process. E. User Accounts We will provide our each of the customer a user accounts where they will keep their shopping history. The user of the site will open their account by email and social media also. F. Interactive Form Internet technology allows for communication forums. We will provide an interactive form (often called a guest book) which allows for an open exchange of information between the city and its citizens. The interactive form will act as an on line meeting area to develop a sense of community using Internet communication. City shopping website retested user will be able to make comment with a username and password for the interactive form. City shopping website user will also be able to access the form and add, delete, and modify messages. VI. Web Site Hosting A. Internet Software We own co-located servers that resides at Mexico. We maintain a small group of selected clients on our server. Owning our server allows us to offer high end software systems on the web. Features such as on line calendars require significant server side programming and knowledge. ©Md. Asif Sultanul Arefeen American International University-Bangladesh
  • 5. B. Benefits of Hosting Web hosting clients take advantage of a range of Internet technologies not available through other hosting services. We are Internet programming specialists. The systems require server side programming. Because we own the platform we routinely deploy these systems for our hosting clients. VII. Compensation and Terms (Site Design) A. Compensation We agree to design and install the web site and administrative functions described above for the fee of $10000 inclusive of the following: 1. All Design and Layout described above 2. All Programming described above 3. Installation of web pages and programs on target web server. 4. Marketing the Site with Search Engine Listing B. Terms 1. Deposit - 50% prior to starting work 2. Progress Payment - 20% upon site completion and buy off 3. Final Payment - 30% thirty days after site completion VIII. Compensation and Terms (Hosting) A. Hosting Compensation 1. Site Name Registration and Set Up: 2 day (one time) 2. Internet Corporate Web Hosting: 1 month 3. Pointer for second domain name: 2 month B. Hosting Terms 1. Payable 6 months in advance by check, or 2. Payable monthly by credit card ©Md. Asif Sultanul Arefeen American International University-Bangladesh
  • 6. Business Case September 29, 2013 1.0 Introduction/ Background City online Shopping Mall is a new concept of online shopping store in Mexico. It is a new business and run by two owners. The main concept of this business is give a new experience in online shopping that fulfill your demand in a real cost. This online business need a new site for their customer which is more attractive and easy to use. The design is include with an “Interactive Form” that help to connect the customer with the website admin. The form will use for customer feedback purpose. 2.0 Business objective City online Shopping Mall business objective is increase the profit and make the business in number one position in Mexico and also make a top class online store. Their goals is continuing growth of the business and make it internationally. 3.0 Current Situation and Problems/ Opportunity Statement City online Shopping Mall is a new business. There is also more five companies is available in the Mexico market. So the completion is hard. But City’s main competitor will be in the Mexico’s third biggest online shopping website buynsell.com. All the current shopping website is now use oldest version web security HTML. But we will Use HTML5. That is more secured and more customer attractive. In the world market “amazon.com”, “ebay.com” use HTML5 and they are successfully run their business. Day by day Mexican customer is dependent on the online shopping because of its save their time. So it is easy to realize that the day is come it’s demand will increase. 4.0 Critical Assumptions and Constraints This project need a customer attractive, easy to maintain, easy to shopping and easy to updatable webpage template. The template will work in flash and HTML5 language. The template will also increase the level of online shopping experience. The Web design is make simple but unique. The design will also help to increase the SEO. The Webpage make satisfied our sponsor as well as their customer. 5.0 Analysis of Options and Recommendation We will recommendation some options that will increase the attractiveness of this project. That is: I. II. The website design is include the SEO then the project is fully pleased by its maker. If the project is introduced in the global then the design might be more attractive. ©Md. Asif Sultanul Arefeen American International University-Bangladesh
  • 7. III. If the time of the project is one year then it might be made more creative. 6.0 Preliminary Project Requirements The main requirements of this project include the following:      Need to make a plan for design, time, money and quality ensure management. We need an e-marketing template for Web page design. Need a critical analysis for sponsor demand. Make sure the design is approved by the sponsor. Make a team for the project. 7.0 Budget Estimate and Financial Analysis Our Total Budget for the project is $10000. The preliminary estimate of costs for the entire projects is $5000. Half of the Costs is for Web Template buy and registration of the website. Another Half of the Costs is for Web Hosting and Web place buy. We will use our Rest of the money is for SEO purpose. We Use 2000 dollar for increase the rank of website. 500 dollar for Facebook marketing. 1000 dollar for submit the website in Search engine like Google, yahoo, Bing etc. And another 1500 dollar will be used for testing purpose. 8.0 Schedule Estimate Our total time for this project is six months. Project will be started from 1st January and it will be completed in 30th June. We work 1 st month for selecting the Template and then within 10 days we completed our registration process. Then we work for design and modification and it will continue one month. Then we will submit our website in the search engines. Then we will tasted our website as a pilot case in 3 months. That time we monitoring our website to identify our design errors. 9.0 Potential Risks There are several risks involved with this projects. The foremost risk is complete the project in the limited budget and duration time schedule. The design will not accepted by the sponsor and their customers. Misunderstanding between the sponsor and the designer because of poor communication. ©Md. Asif Sultanul Arefeen American International University-Bangladesh
  • 8. PROJECT CHARTER 1. General Information Date: 01-10-2013 Project Title: Website Design Project Project Sponsor: Karl Louis Armstrong Start / Finish Date: 01-11-2013 Budget Allocation: The developers of the project has allocated $1000 for this project. Approximately half of the costs will be for design materials, whereas the other half will be for developed the design purpose. 31-04-2014 2. Stakeholders SL ID Name Project Manager: Karl Louis Armstrong Business Leader: Atique Ullah Technical Leader: Md. Asif Sultanul Arefeen Key Team Member: Muhammad Ziaul Kader Key Team Member: Miss Susmita 3. Project / Service Description * Project Objectives / Business Justification Describe the product or service that this project will produce (e.g., “This project will manage relocation to a new headquarters location for ABC Corporation.”) Measurable business outcomes of the project. Business Objectives typically deal with cost, time, and quality (e.g., reduce the cost of delivery of this service by 30%). Describe the business problem or need being addressed (e.g., “ABC Corporations is currently at risk for interruption of essential services due to lack of space in its current location”). Develop a new site for the new online Shopping business. The business is totally doing i n online by using the website. So this website is the main way to do the business. Their a ll success is depend on this website. They need a customer’s friendly design. That is ea sy to use and secured filling to use the website. The website design must be simple but unique. The design will be also help to increase the business. * Project Deliverables List the high-level project, sub-products or project phases whose satisfactory delivery mark completion of the project (e.g., site selection, vendor selection, installation of office equipment and furniture, opening session). We are designing the small elements of the website like buttons, plugin, Interactive Form a nd the front flash menu. * Project Exclusion (Will Not be Include) (Example: Phase 1 of the Headquarters Relocation project will not include the planned employee fitness center.) In the project will not be included coding of the website development languages and the SEO. ©Md. Asif Sultanul Arefeen American International University-Bangladesh
  • 9. 3. Project / Service Description * Project Milestones Proposed start and end dates for Project Phases (e.g., Inception, Planning, Design, Development, Testing, and Rollout) and other major milestones. 1. Selecting the Template for the design. 2. Selecting the way of the design. 3. Estimate the cost of the project 4. Estimate the time of the project 5. Divided the works between team members. * Project Approaches Describe primary plans briefly on the following (Will the project have formal written plans – i.e., Project Schedule, Budget, and Resource? How will project issues be dealt with? List any scheduled project team meetings, planned status reports) We have to complite the project within six months. Time is short but enough if we do all the work perfectly and timely. Our budget for this project is $1000. We will develop a design template in Adobe Phothoshop and Illustrator then we make a unique but a simple design. We will also adjust our flash button, plugin and other templet elements. Then we are write our content in the website. After that we run our design as pailot case and mesurement our quility with beanch marking way. If we will setisfied then monitoring the process. If it is error free then we submit our project to the project sponser. He will be justified our design. If any chage or modification is needed then we will do this. After that if he is said “ok” then our project phase is completed, but the project is not fully completed, because it is not running in the real business. If the design is perfect for the real business then the project is completed. * Assumption & Constraints List any conditions that may limit the project team’s options with respect to resources, personnel, or schedule (e.g., predetermined budget or project end date, limit on number of staff that may be assigned to the project). Include both internal risks and external risks. (e.g., Internal Risk – Move In date may be in jeopardy if decisions about office furniture are not made on time. External Risk – Office Furniture vendor has a poor track record of on-time delivery). There is saveral risk involve to this project. The devided the risk in two kinds. One is internal and another is external. Internal Risk1. Conflict between project manager, technical advisor and the designer 2. Lack of knowledge about the programming language. 3. If the time is not maintain then cost of budget will increase. External Risk1. The Design might not be unique due to lack of knowledge 2. Design element like plugin, button, flash etc might not be avabile in the internet 3. Internet connect might be problem due to slow speed. * Project Success Criteria Define what must be done in order for this project to be considered a success by its stakeholders. We will use latest type of design element, flash and plugin. We also use google customized search engine that will help to the user of this website.It is also considered a success by its stakeholders. Our design will also help to make the SEO incress. So it is also a sucees by its stakeholders. ©Md. Asif Sultanul Arefeen American International University-Bangladesh
  • 10. 4. Sign-off Name Project Sponsor: Pater Louis Armstrong Project Manager Date(dd-mon-yy) Karl Louis Armstrong Co-Sponsor Signature Karl Louis Armstrong 5. Comments (Handwritten or typed comments from above stakeholders, if applicable) “If the contact menu is more upgradable and include the social media box the it look more attractive”--- Karl Louis Armstrong, project manager and Sponsor ©Md. Asif Sultanul Arefeen American International University-Bangladesh
  • 11. PROJECT WORK BREAKDOWN STRUCTURE 1. General Information Date: Project Title: Project Sponsor: Start / Finish Date: Budget Allocation: 1-10-2013 website design project Karl Louis Armstrong 1-11-2013 31-4-2014 The developers of the project has allocated $10000 for this project. Approximately half of the costs will be for design materials, whereas the other half will be for developed the design purpose. 2. Project Deliverable: S/L Deliverable Name 1.0 Buttons 2.0 Plugin 3.0 Interactive formant the front flash menu 3. Work Breakdown Structure Deliverable Name S/L WBS Element Name .1 Initiating 1.1 Prepare stakeholder analysis 1.2 Create project charter 1.3 Prepare business case 1.4 Prepare preliminary scope statement ©Md. Asif Sultanul Arefeen American International University-Bangladesh
  • 12. 3. Work Breakdown Structure .2 Planning 2.1 Project integration management 2.1.1 2.1.2 Create team contract Develop project management plan 2.2 Project time management 2.3 project cost management 2.3.1 web template buy and registration of the website 2.3.2 web hosting and web place buy 2.3.3 SEO purpose 2.3.4 Facebook marketing 2.3.5 Submit the website in search engine 2.4 project communication management 2.5 project risk management 2.5.1 Time 2.5.2 Budget 2.5.3 Communication 2.5.4 Technical problem 2.5.5 Lack knowledge about programming language .3 Executing 3.1 create design 3.1.1 3.1.2 3.1.3 3.1.4 Design creation Color matching Web widgets matching Web buttons creation 3.2 Implementation 3.2.1 Design and coding match 3.2.2 Adding button and widgets in the main design ©Md. Asif Sultanul Arefeen American International University-Bangladesh
  • 13. 3. Work Breakdown Structure .4 Monitoring and controlling 4.1 4.2 4.3 4.4 4.5 .5 Time Cost Design SEO Size of fonts Closing 5.1 Finalize the design 5.2 Make a simple closing of the project 5. Comments (Handwritten or typed comments from above stakeholders, if applicable) “It is pretty cool and handsome work break down structure” - Karl Louis Armstrong, Project Sponsor. ©Md. Asif Sultanul Arefeen American International University-Bangladesh
  • 14. Project Status Report 1. General Information Date: 01/11/2013 Project Title: website design project Project Manager: Karl Louis Armstrong Reporting Period: 2 Month 2. Summary Overall Status: Green 1 Yellow 2 Red 3 (Controlled) (Caution) (Critical) Budget: [ ] [ √] [ ] Schedule: [ ] [ ] [√] Scope: [√ ] [ ] [ ] Quality: [ √] [ ] [ ] 1 Project 2 Reason for Deviation Due to some unavoidable situation we need more time to complete our project. is within budget, scope and on schedule. Project has deviated slightly from the plan but should recover 3 Project has fallen significantly behind schedule, is forecast to be significantly over budget, and/or has taken on tasks that are out of scope. 3. Scheduled Milestones / Deliverables List any Project Milestones that are late as well as Milestones due in the next 4 to 6 weeks. Milestone Approved Schedule Actual Completion Current Forecast Status (%) Facebook marketing 5 Day 15/11/13 20/11/13 O% Submit the website in search engine 2 Day 21/11/13 23/11/13 0% Web buttons creation 8 Days 24/11/13 1/1/14 60% Adding button and widgets in the main design 4 Days 02/01/14 05/01/14 20% SEO 5 Days 05/01/14 09/01/14 50% Web widgets matching 2 Days 10/01/14 12/01/14 50% 2 Days 13/01/14 15/01/14 80% Lack knowledge about programming language ©Md. Asif Sultanul Arefeen American International University-Bangladesh
  • 15. 4. Accomplishments / Plans .1 Accomplishments during this Reporting Period (Should relate to milestones):           Create project charter Prepare business case Prepare preliminary scope statement project integration management create team contract develop project management plan project time management project cost management web template buy and registration of the website web hosting and web place buy .2 Plans during the next Reporting Period (Should relate to milestones):            web hosting and web place buy SEO purpose Facebook marketing Submit the website in search engine project communication management project risk management Time Budget Communication Technical problem Lack knowledge about programming language .3 What went well during this Reporting Period (Should relate to milestones):         create design Design creation Color matching Web widgets matching Web buttons creation Implementation Design and coding match Adding button and widgets in the main design .4 What did not go well during this Reporting Period (Should relate to milestones): ©Md. Asif Sultanul Arefeen American International University-Bangladesh
  • 16. 4. Accomplishments / Plans      Time Cost Design SEO Size of fonts 5. Controls .1 Issue Status (Issues requiring resolution by Project Team or Executive Committee): This is the landing status for new issues. Issues stay in this status until they are assigned, acknowledged, confirmed or resolved. The next status can be "acknowledged", "confirmed", "assigned" or "resolved" .2 Recommendation (Recommendation on corrective actions executed or planned to resolve plan project issues incurred and risk identified and project changes from baseline which would require approval by the Project Sponsor and possibly the Executive Committee): This status is used by the development team to reflect their agreement to the suggested feature request. Or to agree with what the project is suggesting in an issue project, although they didn't yet attempt to reproduce what the project is referring to. The next status is typically "assigned" or "confirmed" .3 Project Change (Changes raised for consideration that change the approved project baselines. Would require approval by the Project Sponsor and possibly the Executive Committee): This status is used to reflect that the issue has been resolved. An issue can be resolved with one of many resolutions (customizable). For example, an issue can be resolved as "fixed", "duplicate", "won't fix", "no change required", etc. .4 Comments This status reflects that the issue is completely closed and no further actions are required on it. It also typically hides the issue from the View Issues page. Some teams use "closed" to reflect sign-off by the reporter and others use it to reflect the fact that the fix has been released to customers ©Md. Asif Sultanul Arefeen American International University-Bangladesh