Ziztel ZTL350 PAGA loudspeaker
network test set
The Requirement …..
• The site PAGA [Public Address and
General Alarm] is one of the
biggest systems within the entire
Telecom package.
• The system is required to provide
acoustic coverage to all potential
listening positions on the site.
• Field cabling and associated field
devices is a major installation
overhead.
The Requirement …..
• By far the greatest overhead in
setting the PAGA system to work is
the commissioning of the field
loudspeaker networks which
account for 90% of the overall
installation.
• Consequently the majority of site
time is consumed in fault finding
on loudspeaker installation wiring.
• This activity can only be executed
upon completion of the entire
PAGA installation works.
The Requirement …..
• Only when the loudspeaker
networks and associated central
equipment racks are
commissioned satisfactorily can
the acoustic performance of the
PAGA system be verified.
• As a consequence verification and
validation of the acoustic design is
only usually possible at an
advance stage in the project hand
over plan.
The Requirement …..
• Changes to loudspeaker
assignment as a result of
installation failures or acoustic
design anomalies are only totally
evident during the critical phase of
hand over.
The Requirement …..
• Re work is exceedingly costly
at this stage of the schedule
and also exposes the installer
to possible penalties for
potential delays to the project
execution.
The solution ….
The Ziztel ZTL350
loudspeaker
network test set
The solution ….
The ZTL350 Test Set
• A complete PAGA system in a small
brief case.
• Light weight – only 7Kg.
• Tiny size – 300 x 200 x 120mm.
• Robust – designed to survive
transportation world wide.
• Rugged – designed to operate in wide
range of service conditions – eg high
ambient temperatures +50C
ZTL350 Benefits
• Enables checking of the loudspeaker
termination cable connectivity as
installation proceeds thereby eliminating
exceedingly costly re work.
• Enables checking of the acoustic
performance of the system at an early
stage of the project plan enabling
modifications to be actioned at minimal
cost / schedule impact.
ZTL350 Simple use
• The installer connects the
speaker circuit cable pair
to the Ziztel portable
tester via a quick
termination block.
• The installer can now
switch on an alarm tone
or make a speech
announcement and verify
operation of all the
loudspeakers connected
on the circuit under test.
ZTL350 Benefits
• The installer can check the
acoustic coverage of the system
by switching on a selected
alarm tone signal and then
measuring broadcast Sound
Pressure Level [SPL] with a
sound pressure level meter.
• Speech intelligibility can also be
checked by making live speech
broadcasts and ensuring that
speech is both audible, clear
and intelligible.
ZTL350 Benefits
• All loudspeaker networks can be
checked electrically / acoustically and
signed off in advance of central PAGA
rack commissioning.
• Specialist PAGA vendor site attendance
is limited only to commissioning the
rack and ancillaries, and as such can be
carefully monitored to contain day work
costs.
ZTL350 Benefits
• Massive reduction in specialist day work
costs.
• No delays at hand over due to possible
acoustic coverage issues.
• No project delays due to installation
errors.
• Massive reduction in remedial / re work
labour costs.
• Reduced exposure to project liquidated
damages.
ZTL350 Test Set Amplifier
• Incorporates a powerful no
compromise integral PAGA
amplifier module type 350A.
• 350 Watts output capability.
• Industry standard 100 Volt
line output.
• Can be used to verify PAGA
system networks supplied by
other PAGA vendors.
ZTL350 Test Set Amplifier
• Unconditionally stable,
electronically protected
against abnormal
loudspeaker network
conditions including Open /
Short circuit, overloaded
lines, earth faults.
• Over Temperature protected.
ZTL350 Test Set Amplifier
• Test set 350A amplifier
under going elevated
factory heat testing.
ZTL350 Test Set Alarm tones
• Integral alarm tone
generator sub system
delivers a range of alarm
cadences / frequencies
according to International or
project specific standards.
• Alarm tone set can be
altered by simple file down
load.
ZTL350 Test Set Alarm tones
• Four alarm tones embedded,
standard Alarm tone sets
include :-
• SOLAS IMO compliant
• NORSOK compliant
• PFEER compliant
ZTL350 Test Set Speech
broadcasts
• Live voice broadcast
capability from an
integral microphone
input.
• Fist microphone or
optional goose neck
microphone input.
ZTL350 Test Set Speech
broadcasts
• Fist microphone or optional plug in goose neck
microphone input.
ZTL350 Test Set
Auxiliary input broadcasts
• Auxiliary input XLR
connector fitted
allowing external
program to be
broadcast by the
system.
ZTL350 Test Set
• Low level test ‘Tick Tone’ enables
convenient walk down check of entire site
installation without full volume alarm tone
broadcasts.
ZTL350 Test Set
• Automatic earth fault
detection – provides
rapid unambiguous
indication of leakage
current from either
field cable line
conductor to earth.
• Resolution is better
than 0.5 mA
ZTL350 Test Set
• Universal mains power
supply input.
• Operates from 90 to 254 VAC
50 / 60 Hz.
• Connection by industry
standard IEE plug / socket.
ZTL350 Test Set
• Also operates from
optional maintenance
free industry standard
VRLA valve regulated
sealed lead acid battery
pile to provide one hour
continuous service.
ZTL350 with Battery back up set
ZTL350 Test Set
• All controls are rugged toggle
type power switches designed
to provide long service life
under aggressive site
conditions.
• Connections are robust
industrial metal XLR type plug /
sockets.
ZTL350 Test Set
ZTL350 Test Set
• Target Loudspeaker Line is
connected to the ZTL350 by
a special ‘Safe Block’ quick
connect / disconnect unit
which eliminates the electric
shock hazard risk possible
with other temporary
connection schemes.
ZTL350 Test Set
• Unit incorporates 100 Volt
line isolation switch for rapid
disconnection of amplifier
100V drive to the connected
speaker network.
• Warning Status indications
fitted to show presence of
source input program on 100
Volt line drive output.
ZTL350 Test Set Conclusion
• Early verification and validation of :-
• A] Correct loudspeaker network
connectivity - freedom from cable
earth faults, short circuit and open
circuit lines.
• B] Acoustic performance / coverage
for both audibility and intelligibility.
• C] Correct loudspeaker tap
assignment.
ZTL350 Test Set
• The investment in a Ziztel ZTL350
test set will repay it self many
hundreds of times over.
• The only question is:-
How did we manage to
commission a PAGA system
before we had a ZTL350 test
set!

More Related Content

What's hot

Aruba products and solutions brochure 2019
Aruba products and solutions brochure 2019Aruba products and solutions brochure 2019
Aruba products and solutions brochure 2019
Pierre Beckers
 
Vodaworld - As-built documentation
Vodaworld - As-built documentationVodaworld - As-built documentation
Vodaworld - As-built documentation
hannese
 
Ap 300 access port internal antenna model
Ap 300 access port   internal antenna modelAp 300 access port   internal antenna model
Ap 300 access port internal antenna model
Advantec Distribution
 

What's hot (17)

ComNet NWK7 Data Sheet
ComNet NWK7 Data SheetComNet NWK7 Data Sheet
ComNet NWK7 Data Sheet
 
6600ingles
6600ingles6600ingles
6600ingles
 
IGS-4215-4P4T Industrial Managed Switch
IGS-4215-4P4T Industrial Managed SwitchIGS-4215-4P4T Industrial Managed Switch
IGS-4215-4P4T Industrial Managed Switch
 
IGS-604HPT-RJ Industrial Managed Ethernet Switch
IGS-604HPT-RJ Industrial Managed Ethernet SwitchIGS-604HPT-RJ Industrial Managed Ethernet Switch
IGS-604HPT-RJ Industrial Managed Ethernet Switch
 
Aruba products and solutions brochure 2019
Aruba products and solutions brochure 2019Aruba products and solutions brochure 2019
Aruba products and solutions brochure 2019
 
Overview: Principles of Full Matrix Capture (FMC) and Total Focusing Method (...
Overview: Principles of Full Matrix Capture (FMC) and Total Focusing Method (...Overview: Principles of Full Matrix Capture (FMC) and Total Focusing Method (...
Overview: Principles of Full Matrix Capture (FMC) and Total Focusing Method (...
 
Vodaworld - As-built documentation
Vodaworld - As-built documentationVodaworld - As-built documentation
Vodaworld - As-built documentation
 
Fuji tu dong hoa renic ehvaccatalog-dienhathe.org
Fuji tu dong hoa renic ehvaccatalog-dienhathe.orgFuji tu dong hoa renic ehvaccatalog-dienhathe.org
Fuji tu dong hoa renic ehvaccatalog-dienhathe.org
 
Sp80
Sp80Sp80
Sp80
 
Optoacoplador 817a
Optoacoplador  817aOptoacoplador  817a
Optoacoplador 817a
 
Industrial EN50155 Ethernet Switch
Industrial EN50155 Ethernet SwitchIndustrial EN50155 Ethernet Switch
Industrial EN50155 Ethernet Switch
 
Aruba 3810 Switch Series Data Sheet
Aruba 3810 Switch Series Data SheetAruba 3810 Switch Series Data Sheet
Aruba 3810 Switch Series Data Sheet
 
Ap 300 access port internal antenna model
Ap 300 access port   internal antenna modelAp 300 access port   internal antenna model
Ap 300 access port internal antenna model
 
Power distribution solutions
Power distribution solutionsPower distribution solutions
Power distribution solutions
 
GSW-2824P Combo Ethernet Switch
GSW-2824P Combo Ethernet SwitchGSW-2824P Combo Ethernet Switch
GSW-2824P Combo Ethernet Switch
 
RS_insert
RS_insertRS_insert
RS_insert
 
Aruba 2930F Switch Series Datasheet
Aruba 2930F Switch Series DatasheetAruba 2930F Switch Series Datasheet
Aruba 2930F Switch Series Datasheet
 

Similar to ZTL350 Network Test Set

OneGear SMC 15kV Soft Starter
OneGear SMC 15kV Soft StarterOneGear SMC 15kV Soft Starter
OneGear SMC 15kV Soft Starter
Paul Plavicheanu
 
PLC Based Annunciation System
PLC Based Annunciation SystemPLC Based Annunciation System
PLC Based Annunciation System
Fasih Ahmed
 
Profinet network qualification - Peter Thomas
Profinet network qualification - Peter ThomasProfinet network qualification - Peter Thomas
Profinet network qualification - Peter Thomas
PROFIBUS and PROFINET InternationaI - PI UK
 
C5269 Case Study - Acoustically Insulated Test Chamber for a `Rotor Spin Rig ...
C5269 Case Study - Acoustically Insulated Test Chamber for a `Rotor Spin Rig ...C5269 Case Study - Acoustically Insulated Test Chamber for a `Rotor Spin Rig ...
C5269 Case Study - Acoustically Insulated Test Chamber for a `Rotor Spin Rig ...
Christian Senior
 

Similar to ZTL350 Network Test Set (20)

electrical-wiring_WHY DO WE NEED ALL THIS COPPER
electrical-wiring_WHY DO WE NEED ALL THIS COPPERelectrical-wiring_WHY DO WE NEED ALL THIS COPPER
electrical-wiring_WHY DO WE NEED ALL THIS COPPER
 
Gis4
Gis4Gis4
Gis4
 
OneGear SMC 15kV Soft Starter
OneGear SMC 15kV Soft StarterOneGear SMC 15kV Soft Starter
OneGear SMC 15kV Soft Starter
 
Thomson electrak pro_specsheet
Thomson electrak pro_specsheetThomson electrak pro_specsheet
Thomson electrak pro_specsheet
 
Thomson Linear Electrak Pro Series
Thomson Linear Electrak Pro SeriesThomson Linear Electrak Pro Series
Thomson Linear Electrak Pro Series
 
Copper connecivity
Copper connecivityCopper connecivity
Copper connecivity
 
Wago io brochure
Wago io brochureWago io brochure
Wago io brochure
 
Fibaro System
Fibaro SystemFibaro System
Fibaro System
 
Wago xtr brochure
Wago xtr brochureWago xtr brochure
Wago xtr brochure
 
Philips eColor Cove EC Powercore Product Guide
Philips eColor Cove EC Powercore Product GuidePhilips eColor Cove EC Powercore Product Guide
Philips eColor Cove EC Powercore Product Guide
 
PROFINET network qualification Peter Thomas - oct 2015
PROFINET network qualification   Peter Thomas - oct 2015PROFINET network qualification   Peter Thomas - oct 2015
PROFINET network qualification Peter Thomas - oct 2015
 
Multi-Link Product Line Card 2016 *Revised
Multi-Link Product Line Card 2016 *RevisedMulti-Link Product Line Card 2016 *Revised
Multi-Link Product Line Card 2016 *Revised
 
PLC Based Annunciation System
PLC Based Annunciation SystemPLC Based Annunciation System
PLC Based Annunciation System
 
Profinet network qualification - Peter Thomas
Profinet network qualification - Peter ThomasProfinet network qualification - Peter Thomas
Profinet network qualification - Peter Thomas
 
Philiips eColor Cove MX Powercore Product Guide
Philiips eColor Cove MX Powercore Product GuidePhiliips eColor Cove MX Powercore Product Guide
Philiips eColor Cove MX Powercore Product Guide
 
Ruggedcom mx5000 re
Ruggedcom mx5000 reRuggedcom mx5000 re
Ruggedcom mx5000 re
 
Antiference
AntiferenceAntiference
Antiference
 
C5269 Case Study - Acoustically Insulated Test Chamber for a `Rotor Spin Rig ...
C5269 Case Study - Acoustically Insulated Test Chamber for a `Rotor Spin Rig ...C5269 Case Study - Acoustically Insulated Test Chamber for a `Rotor Spin Rig ...
C5269 Case Study - Acoustically Insulated Test Chamber for a `Rotor Spin Rig ...
 
Siae Company Overview
Siae Company OverviewSiae Company Overview
Siae Company Overview
 
36kV high voltage drawout VCB type switchgear
36kV high voltage drawout VCB type switchgear36kV high voltage drawout VCB type switchgear
36kV high voltage drawout VCB type switchgear
 

Recently uploaded

Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
HenryBriggs2
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 

Recently uploaded (20)

A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic Marks
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 

ZTL350 Network Test Set

  • 1. Ziztel ZTL350 PAGA loudspeaker network test set
  • 2. The Requirement ….. • The site PAGA [Public Address and General Alarm] is one of the biggest systems within the entire Telecom package. • The system is required to provide acoustic coverage to all potential listening positions on the site. • Field cabling and associated field devices is a major installation overhead.
  • 3. The Requirement ….. • By far the greatest overhead in setting the PAGA system to work is the commissioning of the field loudspeaker networks which account for 90% of the overall installation. • Consequently the majority of site time is consumed in fault finding on loudspeaker installation wiring. • This activity can only be executed upon completion of the entire PAGA installation works.
  • 4. The Requirement ….. • Only when the loudspeaker networks and associated central equipment racks are commissioned satisfactorily can the acoustic performance of the PAGA system be verified. • As a consequence verification and validation of the acoustic design is only usually possible at an advance stage in the project hand over plan.
  • 5. The Requirement ….. • Changes to loudspeaker assignment as a result of installation failures or acoustic design anomalies are only totally evident during the critical phase of hand over.
  • 6. The Requirement ….. • Re work is exceedingly costly at this stage of the schedule and also exposes the installer to possible penalties for potential delays to the project execution.
  • 7. The solution …. The Ziztel ZTL350 loudspeaker network test set
  • 9. The ZTL350 Test Set • A complete PAGA system in a small brief case. • Light weight – only 7Kg. • Tiny size – 300 x 200 x 120mm. • Robust – designed to survive transportation world wide. • Rugged – designed to operate in wide range of service conditions – eg high ambient temperatures +50C
  • 10. ZTL350 Benefits • Enables checking of the loudspeaker termination cable connectivity as installation proceeds thereby eliminating exceedingly costly re work. • Enables checking of the acoustic performance of the system at an early stage of the project plan enabling modifications to be actioned at minimal cost / schedule impact.
  • 11.
  • 12. ZTL350 Simple use • The installer connects the speaker circuit cable pair to the Ziztel portable tester via a quick termination block. • The installer can now switch on an alarm tone or make a speech announcement and verify operation of all the loudspeakers connected on the circuit under test.
  • 13. ZTL350 Benefits • The installer can check the acoustic coverage of the system by switching on a selected alarm tone signal and then measuring broadcast Sound Pressure Level [SPL] with a sound pressure level meter. • Speech intelligibility can also be checked by making live speech broadcasts and ensuring that speech is both audible, clear and intelligible.
  • 14. ZTL350 Benefits • All loudspeaker networks can be checked electrically / acoustically and signed off in advance of central PAGA rack commissioning. • Specialist PAGA vendor site attendance is limited only to commissioning the rack and ancillaries, and as such can be carefully monitored to contain day work costs.
  • 15. ZTL350 Benefits • Massive reduction in specialist day work costs. • No delays at hand over due to possible acoustic coverage issues. • No project delays due to installation errors. • Massive reduction in remedial / re work labour costs. • Reduced exposure to project liquidated damages.
  • 16. ZTL350 Test Set Amplifier • Incorporates a powerful no compromise integral PAGA amplifier module type 350A. • 350 Watts output capability. • Industry standard 100 Volt line output. • Can be used to verify PAGA system networks supplied by other PAGA vendors.
  • 17. ZTL350 Test Set Amplifier • Unconditionally stable, electronically protected against abnormal loudspeaker network conditions including Open / Short circuit, overloaded lines, earth faults. • Over Temperature protected.
  • 18. ZTL350 Test Set Amplifier • Test set 350A amplifier under going elevated factory heat testing.
  • 19. ZTL350 Test Set Alarm tones • Integral alarm tone generator sub system delivers a range of alarm cadences / frequencies according to International or project specific standards. • Alarm tone set can be altered by simple file down load.
  • 20. ZTL350 Test Set Alarm tones • Four alarm tones embedded, standard Alarm tone sets include :- • SOLAS IMO compliant • NORSOK compliant • PFEER compliant
  • 21. ZTL350 Test Set Speech broadcasts • Live voice broadcast capability from an integral microphone input. • Fist microphone or optional goose neck microphone input.
  • 22. ZTL350 Test Set Speech broadcasts • Fist microphone or optional plug in goose neck microphone input.
  • 23. ZTL350 Test Set Auxiliary input broadcasts • Auxiliary input XLR connector fitted allowing external program to be broadcast by the system.
  • 24. ZTL350 Test Set • Low level test ‘Tick Tone’ enables convenient walk down check of entire site installation without full volume alarm tone broadcasts.
  • 25. ZTL350 Test Set • Automatic earth fault detection – provides rapid unambiguous indication of leakage current from either field cable line conductor to earth. • Resolution is better than 0.5 mA
  • 26. ZTL350 Test Set • Universal mains power supply input. • Operates from 90 to 254 VAC 50 / 60 Hz. • Connection by industry standard IEE plug / socket.
  • 27. ZTL350 Test Set • Also operates from optional maintenance free industry standard VRLA valve regulated sealed lead acid battery pile to provide one hour continuous service.
  • 28. ZTL350 with Battery back up set
  • 29. ZTL350 Test Set • All controls are rugged toggle type power switches designed to provide long service life under aggressive site conditions. • Connections are robust industrial metal XLR type plug / sockets.
  • 31. ZTL350 Test Set • Target Loudspeaker Line is connected to the ZTL350 by a special ‘Safe Block’ quick connect / disconnect unit which eliminates the electric shock hazard risk possible with other temporary connection schemes.
  • 32. ZTL350 Test Set • Unit incorporates 100 Volt line isolation switch for rapid disconnection of amplifier 100V drive to the connected speaker network. • Warning Status indications fitted to show presence of source input program on 100 Volt line drive output.
  • 33. ZTL350 Test Set Conclusion • Early verification and validation of :- • A] Correct loudspeaker network connectivity - freedom from cable earth faults, short circuit and open circuit lines. • B] Acoustic performance / coverage for both audibility and intelligibility. • C] Correct loudspeaker tap assignment.
  • 34. ZTL350 Test Set • The investment in a Ziztel ZTL350 test set will repay it self many hundreds of times over. • The only question is:- How did we manage to commission a PAGA system before we had a ZTL350 test set!