2. ● Educational building
was proposed to build
within Klang Valley.
● There are 2 blocks of
enclosed buildings
consists of 4 floors each
were proposed to build.
● There are a linked floor
between these 2
educational building at
3rd
floor
● The total area around
7500m2.
● The area occupied by
the 2 blocks are
4296.8m2.
3. Summary of the Problem
● Cost of the project is over budget.
● Failure in consideration of the future operation cost.
● Lack of Buildability
● Do not achieve the Green Certification
4. The 40 hour Value Management Workshop/Study
● 35% of design stage
● Value Management
Team Coordinator
● Period of 5 days
5. Workshop Process (Job Plan)
● Information Phase
● Function Analysis Phase
● Creativity Phase
● Evaluation Phase
● Development Phase
● Presentation Phase
6. Outcome of Value Management Workshop
❖ Function Analysis
➢ Defining the function as a whole (Project Concept)
➢ Defining the function of the spaces
20. 7. Conventional Construction Method to IBS
❖ VM team recommended
that the conventional
construction method is to
be replaced by IBS
method.
❖ IBS help to enhance the
efficiency of construction
process, allowing a higher
productivity, quality, time
and cost saving.
❖ It will serve as a better
alternative to increase
value and cut unnecessary
cos
21. 8. Propose Change of Conventional Slab to Hollow Slab
❖ Reasons:
➢ Eliminate amount use of concrete
➢ Reduce amount use of reinforcement bars
➢ Reduce deadweight of building
➢ Have long span 15m
➢ Eliminate the use of suspended ceiling
➢ Save materials cost such as ductwork
22. Whole life costing
1.
1. Change from Brick wall to Glazing wall at
Library
○ Glass wall has a higher initial capital
cost per square metre.
○ Brick wall will require repainting due
to the degradation of the surface
caused by prolonged exposure to the
sun.
○ Maintenance cost is higher leading to
greater total life cycle cost.
○ Glazing wall required minimum
maintenance such as cleaning smooth
glossy surface as it is dust proof and
can be easily cleaned.
23. 2. Change from Enclosed Space to Open Space at
Corridor and Study Area
● Able to save the quantity of the building
materials in terms of cost.
● Save the electricity and also provide good
ventilation.
● Furthermore, air conditioner need professional
for servicing and maintenance
● Without using air conditioner, we can also save
the maintenance fees which can save the whole
life cost and this also helps in improving the
building’s function efficiency and also energy
efficient.
27. Conclusion
● Net saving for the construction cost is RM 1,127,133.84.
● The cost has reduced from RM 4,687,275.92 (BEFORE
VM) to RM 3,560,142.08 (AFTER VM).
28. Recommendation
● Value Management should be implemented during the
early development stage and not introduced only when
problem arises.
● Teamwork is important, as everyone has the equal
responsibility for the quality and success of the project.