SlideShare a Scribd company logo
1 of 18
The 4+1+1Introduction to the Construction Industry &
Introduction to Drawing
( Engineering)
PROJECT 1
Lim Wei Heng 0320148
Lim Jey Sheng 0319796
Lim Yang Kang 0320538
MarcoLeong Wong Ka Henn 0320026
Muhammad Irfaan Yadun 0319353
Ahmed Ali Karama Senan
Civil
engineer
Introduction to the
Construction Industry
& Introduction to Drawing
What is
Civil Engineer?
• Civil engineers create, improve and protect the environment in which we
live.
• They plan, design and oversee construction and maintenance of building
structures and facilities, such as roads, power plants, water, sewerage
systems and etc…
• They also design and build buildings and large structures that they can
last for hundreds of years and withstand all weather conditions.
Roles
- To maintain and stable and
secure buildings so that the
buildings will not deflect or
collapse.
Responsibilities
• To plan, design and oversee buildings.
• Design the foundation structures so that the building can
withstand pressure imposed through environmental
conditions and human use
• To advice on projects and design or contracting engineers
to suggest their plans into reality and maintain the
structure once they built
• To investigate the building structures and facilities.
Pre-Construction
• Obtaining site surveys and soil-engineering services, which include
test borings or pits, soil-bearing values to determine the conditions
of the soil and rock as they may impact the foundation design,
percolation tests, ground-water levels and also could recommend
quality geotechnical firms in the area.
• Secure any required technical tests during construction, such as
concrete strength tests.
• Find an on-site project representative and obtain the necessary legal,
auditing, and insurance counseling services needed to fulfill these
responsibilities, as outlined in AIA documents B141 and A201.
During Construction
• Ensuring that a project runs smoothly and that the structure is completed on time and within
budget
• Adopting all relevant requirements around issues such as building permits, environmental
regulations, sanitary design, good manufacturing practices and safety on all work assignments
• Attending public meetings to discuss projects, especially in
a senior role
• Scheduling material and equipment purchases and delivery
• Reviewing and approving project drawings
• Managing change, as the client may change their mind about the design, and ensuring relevant
parties are notified of changes in the project
• Thinking both creatively and logically to resolve design and development problems
Post Construction
• Our relationship with the client does not end when the construction
is complete. We continue to serve the client post construction.
• Execution of inspections, testing, and functional performance
procedures performed during commissioning process.
• Provide all equipment, tools, materials, and qualified
Commissioning Team personnel required to complete functional
performance tests.
• Make needed repairs, calibrations, and adjustments to bring systems
up to full acceptance levels.
• Solicit cooperation from equipment vendors for the purpose of
training of Operations Staff.
• Provide accurate and complete Operation and Maintenance (O&M)
Manuals, Preventive Maintenance Manuals, and Training Manual
Civil and Structural
Drawing
( C&S Drawing )
What is
Civil AND STRUCRURAL
engineer drawing?
• Engineering drawing is a language in which
the idea of engineer are expressed in an
manner that is clearly understood by
technician or people concern with the job.
Tender Drawing
• First evidence if the project scheme regarding type and quality
of the work involved which is prepared by engineer with
clarity and understanding
• It was prepared into various scales using convention and
concepts of engineers for production , manufacture and
construction etc…
Contract Drawing
• Consists of the detailed design when the tender drawings is over
• If the tender drawings don’t have any new changes or any other
alternative proposals, then the contract and the tender drawings will
be the same
• Contract drawings are printed on good quality papers
• The are provided with cloth backing, to withstand handling and the
purpose for long storage.
Working Drawing
• Fill the gaps in constructional details not reflected in tender
drawings
• Working drawings are used for working , manufacturing
,constructing or building purposes to represent the engineers ‘ final
decisions and design details
• Detail working drawings will be prepared by the drawing office ,in
case lack of finer design/construction details ,notes and instructions
are incorporated on the drawings to facilitate construction and avoid
delays
Final Drawing
• Record or As-built drawings are the same name use to refer to completion
drawings.
• There are bound to be certain variations, additions or alternations are
recorded on a set of drawings called completion , record or As-built
drawings.
• Record drawings should be prepared simultaneously as the work proceeds.
PROCESS
DESIGN
STAGE
PRE-
TENDER
STAGE
TENDER
STAGE
CONSTRUCTION
STAGE
FINAL
STAGE
Difference Between
STRUCTURAL DRAWING &
ARCHITECTURE DRAWING
STRUCTURAL DRAWING
ARCHITECTURE DRAWING

More Related Content

What's hot

Professional practices (lec 04) by k.iqbal
Professional practices (lec 04) by k.iqbalProfessional practices (lec 04) by k.iqbal
Professional practices (lec 04) by k.iqbalZakee Kazmee
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyorLY97
 
Professional practices (lec 03) by k.iqbal
Professional practices (lec 03) by k.iqbalProfessional practices (lec 03) by k.iqbal
Professional practices (lec 03) by k.iqbalZakee Kazmee
 
Interviewing contractors
Interviewing contractorsInterviewing contractors
Interviewing contractorsJahh Lavz
 
Flow of construction project , stakeholders , WBS (work breakdown structure)
Flow of construction project , stakeholders , WBS (work breakdown structure)Flow of construction project , stakeholders , WBS (work breakdown structure)
Flow of construction project , stakeholders , WBS (work breakdown structure)SHREYASKUMAR PATEL
 
Who's who in the Building Zoo? Diagram
Who's who in the Building Zoo? DiagramWho's who in the Building Zoo? Diagram
Who's who in the Building Zoo? DiagramStephen Ransley
 
Time & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionTime & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionGalala University
 
Mechanized construction
Mechanized constructionMechanized construction
Mechanized constructionsrinivas2036
 
Professional practices (lec 05) by k.iqbal
Professional practices (lec 05) by k.iqbalProfessional practices (lec 05) by k.iqbal
Professional practices (lec 05) by k.iqbalZakee Kazmee
 
CV Jochen Krick 2015_1
CV Jochen Krick 2015_1CV Jochen Krick 2015_1
CV Jochen Krick 2015_1Jochen Krick
 

What's hot (14)

Professional practices (lec 04) by k.iqbal
Professional practices (lec 04) by k.iqbalProfessional practices (lec 04) by k.iqbal
Professional practices (lec 04) by k.iqbal
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 
Professional practices (lec 03) by k.iqbal
Professional practices (lec 03) by k.iqbalProfessional practices (lec 03) by k.iqbal
Professional practices (lec 03) by k.iqbal
 
Interviewing contractors
Interviewing contractorsInterviewing contractors
Interviewing contractors
 
Flow of construction project , stakeholders , WBS (work breakdown structure)
Flow of construction project , stakeholders , WBS (work breakdown structure)Flow of construction project , stakeholders , WBS (work breakdown structure)
Flow of construction project , stakeholders , WBS (work breakdown structure)
 
mtb resume
mtb resumemtb resume
mtb resume
 
Flowchart maintenance
Flowchart maintenanceFlowchart maintenance
Flowchart maintenance
 
@resume
@resume@resume
@resume
 
Who's who in the Building Zoo? Diagram
Who's who in the Building Zoo? DiagramWho's who in the Building Zoo? Diagram
Who's who in the Building Zoo? Diagram
 
Time & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionTime & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and Inspection
 
Mechanized construction
Mechanized constructionMechanized construction
Mechanized construction
 
Professional practices (lec 05) by k.iqbal
Professional practices (lec 05) by k.iqbalProfessional practices (lec 05) by k.iqbal
Professional practices (lec 05) by k.iqbal
 
AT PLACEMENT -CV
AT PLACEMENT -CVAT PLACEMENT -CV
AT PLACEMENT -CV
 
CV Jochen Krick 2015_1
CV Jochen Krick 2015_1CV Jochen Krick 2015_1
CV Jochen Krick 2015_1
 

Similar to Ici and itd prensentation new

Ici&itd presentation project 1
Ici&itd presentation project 1Ici&itd presentation project 1
Ici&itd presentation project 1IRFAANYADUN
 
FNBE AUGUST'14 ICI&ITD Presentation Project 1
FNBE AUGUST'14 ICI&ITD Presentation Project 1FNBE AUGUST'14 ICI&ITD Presentation Project 1
FNBE AUGUST'14 ICI&ITD Presentation Project 1yangkanglim
 
Ici&itd presentation project 1
Ici&itd presentation project 1Ici&itd presentation project 1
Ici&itd presentation project 1Json96
 
Ici&itd presentation project 1(1) copy
Ici&itd presentation project 1(1)   copyIci&itd presentation project 1(1)   copy
Ici&itd presentation project 1(1) copyIRFAANYADUN
 
10741175 10201912453652001 2034964853_n
10741175 10201912453652001 2034964853_n10741175 10201912453652001 2034964853_n
10741175 10201912453652001 2034964853_nJson96
 
Structure engineer slide share
Structure engineer slide shareStructure engineer slide share
Structure engineer slide shareChia Ting
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Felix Vong
 
building economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTbuilding economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTRiyaVerma238431
 
iosh-temporary-works.pdf
iosh-temporary-works.pdfiosh-temporary-works.pdf
iosh-temporary-works.pdfXiMdhk
 
Guc arct 702 legislations lecture 4 - project delivery process and business...
Guc arct 702 legislations   lecture 4 - project delivery process and business...Guc arct 702 legislations   lecture 4 - project delivery process and business...
Guc arct 702 legislations lecture 4 - project delivery process and business...Galala University
 
Project management
Project managementProject management
Project managementBenjamin Tan
 
Mohamed Mostafa Kamal Mohamed Elsahn 2016
Mohamed Mostafa Kamal Mohamed Elsahn 2016Mohamed Mostafa Kamal Mohamed Elsahn 2016
Mohamed Mostafa Kamal Mohamed Elsahn 2016Mohamed Elsahen
 
FNBE 0814 Introduction To Construction Industry Project 1
FNBE 0814 Introduction To Construction Industry Project 1FNBE 0814 Introduction To Construction Industry Project 1
FNBE 0814 Introduction To Construction Industry Project 1kaiwenyeo
 
ICI & ITD Slideshow
ICI & ITD SlideshowICI & ITD Slideshow
ICI & ITD SlideshowShze Hwa Lee
 
Project Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectProject Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectNekumi Kida
 

Similar to Ici and itd prensentation new (20)

Ici&itd presentation project 1
Ici&itd presentation project 1Ici&itd presentation project 1
Ici&itd presentation project 1
 
FNBE AUGUST'14 ICI&ITD Presentation Project 1
FNBE AUGUST'14 ICI&ITD Presentation Project 1FNBE AUGUST'14 ICI&ITD Presentation Project 1
FNBE AUGUST'14 ICI&ITD Presentation Project 1
 
Ici&itd presentation project 1
Ici&itd presentation project 1Ici&itd presentation project 1
Ici&itd presentation project 1
 
Ici&itd presentation project 1(1) copy
Ici&itd presentation project 1(1)   copyIci&itd presentation project 1(1)   copy
Ici&itd presentation project 1(1) copy
 
10741175 10201912453652001 2034964853_n
10741175 10201912453652001 2034964853_n10741175 10201912453652001 2034964853_n
10741175 10201912453652001 2034964853_n
 
Ici & itd
Ici & itdIci & itd
Ici & itd
 
Structure engineer slide share
Structure engineer slide shareStructure engineer slide share
Structure engineer slide share
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014
 
building economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTbuilding economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENT
 
iosh-temporary-works.pdf
iosh-temporary-works.pdfiosh-temporary-works.pdf
iosh-temporary-works.pdf
 
Guc arct 702 legislations lecture 4 - project delivery process and business...
Guc arct 702 legislations   lecture 4 - project delivery process and business...Guc arct 702 legislations   lecture 4 - project delivery process and business...
Guc arct 702 legislations lecture 4 - project delivery process and business...
 
Ayman curriculum vitae2
Ayman curriculum vitae2Ayman curriculum vitae2
Ayman curriculum vitae2
 
Ayman curriculum vitae
Ayman curriculum vitaeAyman curriculum vitae
Ayman curriculum vitae
 
Ayman curriculum vitae
Ayman curriculum vitaeAyman curriculum vitae
Ayman curriculum vitae
 
Project management
Project managementProject management
Project management
 
ICI & ITD
ICI & ITD ICI & ITD
ICI & ITD
 
Mohamed Mostafa Kamal Mohamed Elsahn 2016
Mohamed Mostafa Kamal Mohamed Elsahn 2016Mohamed Mostafa Kamal Mohamed Elsahn 2016
Mohamed Mostafa Kamal Mohamed Elsahn 2016
 
FNBE 0814 Introduction To Construction Industry Project 1
FNBE 0814 Introduction To Construction Industry Project 1FNBE 0814 Introduction To Construction Industry Project 1
FNBE 0814 Introduction To Construction Industry Project 1
 
ICI & ITD Slideshow
ICI & ITD SlideshowICI & ITD Slideshow
ICI & ITD Slideshow
 
Project Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectProject Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A Project
 

More from WadeLim

final biz plan (1).pptx
final biz plan (1).pptxfinal biz plan (1).pptx
final biz plan (1).pptxWadeLim
 
final biz plan (1).pptx
final biz plan (1).pptxfinal biz plan (1).pptx
final biz plan (1).pptxWadeLim
 
Psychology jornal.docx
Psychology jornal.docxPsychology jornal.docx
Psychology jornal.docxWadeLim
 
Psychology jornal.docx
Psychology jornal.docxPsychology jornal.docx
Psychology jornal.docxWadeLim
 
VideoReport.docx
VideoReport.docxVideoReport.docx
VideoReport.docxWadeLim
 
VideoReport.docx
VideoReport.docxVideoReport.docx
VideoReport.docxWadeLim
 
Psycho-presentation-with-pics-video (1).pptx
Psycho-presentation-with-pics-video (1).pptxPsycho-presentation-with-pics-video (1).pptx
Psycho-presentation-with-pics-video (1).pptxWadeLim
 
PSYCHO-2 (2).pdf
PSYCHO-2 (2).pdfPSYCHO-2 (2).pdf
PSYCHO-2 (2).pdfWadeLim
 
English Report.docx
English Report.docxEnglish Report.docx
English Report.docxWadeLim
 
EPC.pptx
EPC.pptxEPC.pptx
EPC.pptxWadeLim
 
EPC (1).pdf
EPC (1).pdfEPC (1).pdf
EPC (1).pdfWadeLim
 
Cl (final project) briefing
Cl (final project) briefingCl (final project) briefing
Cl (final project) briefingWadeLim
 
Project02 briefing
Project02 briefingProject02 briefing
Project02 briefingWadeLim
 
Project 1 experiential landscape
Project 1 experiential landscapeProject 1 experiential landscape
Project 1 experiential landscapeWadeLim
 
State park (1)
State park (1)State park (1)
State park (1)WadeLim
 
Final report
Final reportFinal report
Final reportWadeLim
 
Ici project2 (1)
Ici project2  (1)Ici project2  (1)
Ici project2 (1)WadeLim
 
Iciprojectbrief1b 141129213936-conversion-gate01
Iciprojectbrief1b 141129213936-conversion-gate01Iciprojectbrief1b 141129213936-conversion-gate01
Iciprojectbrief1b 141129213936-conversion-gate01WadeLim
 
Drawingproject1august brief-updated-141129024845-conversion-gate02
Drawingproject1august brief-updated-141129024845-conversion-gate02Drawingproject1august brief-updated-141129024845-conversion-gate02
Drawingproject1august brief-updated-141129024845-conversion-gate02WadeLim
 
Iciprojectbrief1b 141129213936-conversion-gate01
Iciprojectbrief1b 141129213936-conversion-gate01Iciprojectbrief1b 141129213936-conversion-gate01
Iciprojectbrief1b 141129213936-conversion-gate01WadeLim
 

More from WadeLim (20)

final biz plan (1).pptx
final biz plan (1).pptxfinal biz plan (1).pptx
final biz plan (1).pptx
 
final biz plan (1).pptx
final biz plan (1).pptxfinal biz plan (1).pptx
final biz plan (1).pptx
 
Psychology jornal.docx
Psychology jornal.docxPsychology jornal.docx
Psychology jornal.docx
 
Psychology jornal.docx
Psychology jornal.docxPsychology jornal.docx
Psychology jornal.docx
 
VideoReport.docx
VideoReport.docxVideoReport.docx
VideoReport.docx
 
VideoReport.docx
VideoReport.docxVideoReport.docx
VideoReport.docx
 
Psycho-presentation-with-pics-video (1).pptx
Psycho-presentation-with-pics-video (1).pptxPsycho-presentation-with-pics-video (1).pptx
Psycho-presentation-with-pics-video (1).pptx
 
PSYCHO-2 (2).pdf
PSYCHO-2 (2).pdfPSYCHO-2 (2).pdf
PSYCHO-2 (2).pdf
 
English Report.docx
English Report.docxEnglish Report.docx
English Report.docx
 
EPC.pptx
EPC.pptxEPC.pptx
EPC.pptx
 
EPC (1).pdf
EPC (1).pdfEPC (1).pdf
EPC (1).pdf
 
Cl (final project) briefing
Cl (final project) briefingCl (final project) briefing
Cl (final project) briefing
 
Project02 briefing
Project02 briefingProject02 briefing
Project02 briefing
 
Project 1 experiential landscape
Project 1 experiential landscapeProject 1 experiential landscape
Project 1 experiential landscape
 
State park (1)
State park (1)State park (1)
State park (1)
 
Final report
Final reportFinal report
Final report
 
Ici project2 (1)
Ici project2  (1)Ici project2  (1)
Ici project2 (1)
 
Iciprojectbrief1b 141129213936-conversion-gate01
Iciprojectbrief1b 141129213936-conversion-gate01Iciprojectbrief1b 141129213936-conversion-gate01
Iciprojectbrief1b 141129213936-conversion-gate01
 
Drawingproject1august brief-updated-141129024845-conversion-gate02
Drawingproject1august brief-updated-141129024845-conversion-gate02Drawingproject1august brief-updated-141129024845-conversion-gate02
Drawingproject1august brief-updated-141129024845-conversion-gate02
 
Iciprojectbrief1b 141129213936-conversion-gate01
Iciprojectbrief1b 141129213936-conversion-gate01Iciprojectbrief1b 141129213936-conversion-gate01
Iciprojectbrief1b 141129213936-conversion-gate01
 

Ici and itd prensentation new

  • 1. The 4+1+1Introduction to the Construction Industry & Introduction to Drawing ( Engineering) PROJECT 1 Lim Wei Heng 0320148 Lim Jey Sheng 0319796 Lim Yang Kang 0320538 MarcoLeong Wong Ka Henn 0320026 Muhammad Irfaan Yadun 0319353 Ahmed Ali Karama Senan
  • 2. Civil engineer Introduction to the Construction Industry & Introduction to Drawing
  • 3. What is Civil Engineer? • Civil engineers create, improve and protect the environment in which we live. • They plan, design and oversee construction and maintenance of building structures and facilities, such as roads, power plants, water, sewerage systems and etc… • They also design and build buildings and large structures that they can last for hundreds of years and withstand all weather conditions.
  • 4. Roles - To maintain and stable and secure buildings so that the buildings will not deflect or collapse.
  • 5. Responsibilities • To plan, design and oversee buildings. • Design the foundation structures so that the building can withstand pressure imposed through environmental conditions and human use • To advice on projects and design or contracting engineers to suggest their plans into reality and maintain the structure once they built • To investigate the building structures and facilities.
  • 6. Pre-Construction • Obtaining site surveys and soil-engineering services, which include test borings or pits, soil-bearing values to determine the conditions of the soil and rock as they may impact the foundation design, percolation tests, ground-water levels and also could recommend quality geotechnical firms in the area. • Secure any required technical tests during construction, such as concrete strength tests. • Find an on-site project representative and obtain the necessary legal, auditing, and insurance counseling services needed to fulfill these responsibilities, as outlined in AIA documents B141 and A201.
  • 7. During Construction • Ensuring that a project runs smoothly and that the structure is completed on time and within budget • Adopting all relevant requirements around issues such as building permits, environmental regulations, sanitary design, good manufacturing practices and safety on all work assignments • Attending public meetings to discuss projects, especially in a senior role • Scheduling material and equipment purchases and delivery • Reviewing and approving project drawings • Managing change, as the client may change their mind about the design, and ensuring relevant parties are notified of changes in the project • Thinking both creatively and logically to resolve design and development problems
  • 8. Post Construction • Our relationship with the client does not end when the construction is complete. We continue to serve the client post construction. • Execution of inspections, testing, and functional performance procedures performed during commissioning process. • Provide all equipment, tools, materials, and qualified Commissioning Team personnel required to complete functional performance tests. • Make needed repairs, calibrations, and adjustments to bring systems up to full acceptance levels. • Solicit cooperation from equipment vendors for the purpose of training of Operations Staff. • Provide accurate and complete Operation and Maintenance (O&M) Manuals, Preventive Maintenance Manuals, and Training Manual
  • 10. What is Civil AND STRUCRURAL engineer drawing? • Engineering drawing is a language in which the idea of engineer are expressed in an manner that is clearly understood by technician or people concern with the job.
  • 11. Tender Drawing • First evidence if the project scheme regarding type and quality of the work involved which is prepared by engineer with clarity and understanding • It was prepared into various scales using convention and concepts of engineers for production , manufacture and construction etc…
  • 12. Contract Drawing • Consists of the detailed design when the tender drawings is over • If the tender drawings don’t have any new changes or any other alternative proposals, then the contract and the tender drawings will be the same • Contract drawings are printed on good quality papers • The are provided with cloth backing, to withstand handling and the purpose for long storage.
  • 13. Working Drawing • Fill the gaps in constructional details not reflected in tender drawings • Working drawings are used for working , manufacturing ,constructing or building purposes to represent the engineers ‘ final decisions and design details • Detail working drawings will be prepared by the drawing office ,in case lack of finer design/construction details ,notes and instructions are incorporated on the drawings to facilitate construction and avoid delays
  • 14. Final Drawing • Record or As-built drawings are the same name use to refer to completion drawings. • There are bound to be certain variations, additions or alternations are recorded on a set of drawings called completion , record or As-built drawings. • Record drawings should be prepared simultaneously as the work proceeds.
  • 16. Difference Between STRUCTURAL DRAWING & ARCHITECTURE DRAWING