SlideShare a Scribd company logo
1 of 62
Download to read offline
Mumbai Metro Line 4&
4A& 4A
Presentation on Track Work
Riyadh Metro – Slab Track
Mumbai Metro Line 4 & 4A Track Structure.
a) Ballastless Track:
 Track elements comprising of running rails, rail-fastening,
embedded in concrete at-grade slab, a concrete viaduct deck,
or a concrete underground invert.
 Track slab will be Cast in situ/ plinth, The track slab shall be
designed as plinth beam or slab type ballastless track with
derailment gaurds.
Track Structure
MumbMumbai Metro – Plinth Track
-Plinth Track
Ballast-less Track
Components:
• Rail (Hardened Rail UIC
60E1)
• Track fastening system
• Track Plinth
Sl. No. CRITERIA DIMENSION
1 Gauge 1435 mm Standard Gauge,
2 Max.train speed a) Maximum
(Design)
b) Maximum (Operating)
90 Kmph (in straight) and 80 kmph (in curves upto Radius
300m)
80 Kmph (To be confirmed by Employer at later stage)
3 Max. axle load, loaded condition 17 tonnes Standard Gauge,
4 Max. desirable gradient running track
Absolute max. gradient running track
3%
4%
5 Minimum vertical curve radius
Minimum horizontal curve radius
1500 m
120 m
6 Electric power 25KV AC overhead traction
7 Inclination of Rail 1 in 20
8 Wheel profile IRS type to be interfaced with Rolling Stock Supplier.
9 Rail profile UIC 60E1
10 Design Rail Temperature 8 Deg C to 54 Deg C
Technical Criteria and Operation Standards
a) Rail Section:
b. Fastening:
Having record of minimum three years in service in regular revenue
for a length of at least 5km with speed potential of 80 kmph & design
axle load 16T.
Track Components – Plinth TrackComponents:
c) Concrete:
 The concrete shall be of minimum M45 grade as per the
Indian Standard IS-456 – 2000
d) Steel Reinforcement:
 Reinforcement & shear connector shall be IS 1786 in
accordance with relevant IS codes.
PlinthTrack Components – Plinth Trackmponents:
Trac Alignment – Specificationponents
tructure ParameterDescription Standard Gauge Corridor
Rail type main line UIC 60E1, IRS-T-12-2009 with all correction
slips, 1080 grade head hardened (HH)
Tentative Base Plate Spacing (Shall be
reviewed by Contractor as per detailed
design, following approval from Engineer
for varying curvature)
650 mm ( Main line (on elevated viaducts
and stations in straight) and curves with
radius >300M
600 mm in case of curves with radius ≤ 300
M
Standard Rail Length Main line 18m
Maximum cant permissible 110mm
Maximum cant deficiency Permissible 85 mm
Maximum cant gradient Permissible
Maximum cant gradient Desirable
1 in 440
1 in 720
Rate of change of cant/cant deficiency
Standard Gauge maximum Permissible
Standard Gauge maximum Desirable
40mm/sec
25mm/sec
Type of turnouts – Standard Gauge 1 in 9 :300m radius
Type of Scissor Crossover 1 in 9: 300 m radius Diamond Crossing
Track Gauge
Picture: Taking over of Finished over Grade / Vaiduct Section
Track Installation
Track Installation
Fig : Total Station Survey Capturing of Finished Levels
Track Installation
(5) Step 5 – Welding Pulling of Rail Panels
Fig : Flash Butt Welding of Rail
Track Installation
(4) Step 4 – Rail Drop into position – Track Site
Fig: Unloading of Rails over Deck slab
Track Installation
(5) Step 5 – Welding Pulling of Rail Panels
Fig : Marking of alignment center
Fig : Lifting and Rails with GSF Supports over the alignment center
Track Installation
Track Installation
(5) Step 5 – Welding Pulling of Rail Panels
Fig : Fixing of Dummy Plates with Vossloh Fastenings
Track Installation
(5) Step 5 – Welding Pulling of Rail Panels
Fig : Vossloh Fastenings FE 336 used in Riyadh Metro
Fig : Reinforcement of Track Slab
Track Installation
Fig : From Work for Track Slab including Derailment Guard
Track Installation
Fig : Third Rail Dowel Provision Works
Track Installation
Fig : Final Inspection Works
Track Inspection
Inspection of vertical & horizontal
alignment with Track Master
Inspection of vertical alignment
Fig : Adjustment of Errors
Track Inspection
Ignment
Track Installation
Dimensional Tolerances Ballastless Track
Gauge maximum variation +/- 2 mm
Mean Gauge per 200 m -1 mm
Max difference of any point in relation to the designed
layout ( Vertical )
-4 mm/+4 mm
Max difference of any point in relation to the designed
layout ( horizontal)
-4 mm/+4 mm
On curve, deviation of measured versine 20 m chord:
(half overlapping)
+/- 2 mm
Maximum deviation of measured versine (vertical) over
its designed value on a 10 m chord (half overlapping)
+/- 2 mm
Baseplate to base plate (ballastless) Variation of cant/x-
level
 1 mm
Twist: (over & above designed value) straight and circular
portion of curve
On transition portion of curve
1 mm/m
0.5 mm/m
Fig : Track Slab Concrete
Track Installation
Fig : Surface finishing Track Slab Concrete
Track Installation
Fig : Rear Works of Finished Track Slab
Track Installation
Fig : Fixing of Fastenings
Track Installation
Fig : Destressing Works at Temp 37°C to 43°C
Track Installation
N
Fig : Final Track installation and Recording Data
Track Installation
a) Track Structure in Depot :
 Ballasted Track for Main Lines.
 Pedestal Track for inspection lines.
 Embedded track inside the Workshop.
 Plinth type for Washing Plant line.
Depot Track Works
Track elements running rails, rail-fastening rail pads,, concrete
sleeper blocks, stone ballast installed upon a well compacted
subgrade.
Ballasted Track In Depots
Ballasted Track Standard
Description Standard Gauge Corridor
Rail type UIC 60E1, IRS-T-12-2009 with all
correction slips, 880 grade and 1080
grade head hardened (HH)
Tentative Base Plate Spacing (Shall be
reviewed by Contractor as per detailed
design, following approval from
Engineer for varying curvature)
700 mm +/- 25 mm
600 mm +/- 25 mm (curve radius ≤ 300
m)
Standard Rail Length 18 m
Minimum ballast cushion depth 200 mm
Formation cross fall 1 in 20
Type of turnouts – Standard Gauge 1 in 7 :190m radius
Type of Scissor Crossover 1 in 7: 190 m radius
Diamond Crossing (to be adequately
designed by Contractor)
b. Components of Ballasted track :
 Rails: UIC 60E1, IRS-T-12-2009 with all correction slips, 880
grade and 1080 grade head hardened (HH)
 Sleepers :The PSC sleepers shall be used in accordance with
RDSO drawing no.T-2496 and specification IRS-T-39 (revised
from time to time)
 Fastenings : compatible fastening system with minimum toe
load of 1045kg and approved by Indian Railway shall be
used.
Ballasted Track Structure
c. Rail Fixtures of Ballasted track :
 The various types of rail fixtures and fastenings commonly
used in a permanent way are the following:
1. Fish plates 8. Check rails
2. Bolts 9. M.C.I. Insert
3. Spikes 10. Rubber pads
4. Chairs
5. Keys, cotters and tie bars
6. Bearing plates
7. Guard rails
Ballasted Track Structure
d. Pictures of Rail fixtures in Ballasted track :
Dog Spike Chairs with Tie plates
Ballasted Track Structure
e. Specificaitons:
 Basic Quality:
Ballast should be hard durable and as far as possible
angular edges/corners, free, organic Impurities
and inorganic residues.
 Shape:
Ballast should be cubical in shape as far as possible.
Track ballast
f. Physical Properties of Ballast:
 Ballast sample should satisfy the following physical properties
in accordance with IS: 2386 Pt. IV-1963 when tested as per
RDSO detailed specifications.
 Aggregate Abrasion Value: 30% Max.
 Aggregate Impact Value: 20% Max.
 The “Water Absorption” tested as per IS2386 Pt.-III 1963
following the procedure given in in RDSO detailed
specifications should not be more than 1%.
Specification of Track ballast
g. Size and Gradation of Ballast:
 Ballast should satisfy the following size and gradation:
 Retained on 65 mm sq. Mesh sieve 5% Maximum.
 Retained on 40 mm sq. Mesh sieve 40% -60% for machine
crushed ballast.
 Retained on 20 mm sq. Mesh sieve not less than 98% for
machine crushed. Not less than 95% for hand broken.
Specification of Track ballast
Gradation of Ballast
(5) Step 5 – Welding Pulling of Rail Panels
Fig : Ballast Sieve Analysis
Earth Works of Ballasted Track
(5) Step 5 – Welding Pulling of Rail Panels
Fig : Earth Works of Ballasted Track
a. Blanket layers :
This layer is placed between the prepared subgrade and ballast
layers and may consist of one or several layers:,
It has the following functions:
 improving the bearing capacity by a better distribution of
transmitted loads,
 protecting against erosion and frost,
 acting as a filter between subgrade and ballast,
 shedding surface water.
Earth Works of Ballasted Track
b. Formation/Subgrade :
 Prepared subgrade (also named as “Form layer”): this layer
must have bearing capacity to support the ballast and
blanket layers and to avoid water infiltration in the
embankment.
c. Embankment or Cutting:
 If the design level of the rails is above the current surface
ground, it will be necessary to build an embankment; in the
opposite case, a cutting of the natural ground will have to be
performed.
Earth Works of Ballasted Track
For efficient execution of track work the following tools and
machinery are proposed to be deployed. This list is not
exhaustive and is subject to change as per site requirement.
 Mobile Flash butt Welding machine
 New Track layer self propelled with sleeper Gantry Crane
 Tractor/Dozer / Loader for pulling Rail Panel
 Clip applicator mounter on Track
 Sleeper Loading Gantry Crane
 Fixed rail Gantry Crane 21 X 2T
 Rail Profile Grinder
Plant and Equipment
 Flat Wagons for Rail & Sleeper transport
 Hopper Wagons for Ballast training out
 Wheel Loader
 Grader
 Vibratory Roller 8T
 Hydra Crane
 Mobile Crane 25 Tonne Capacity
 Loco / UTV
 Unimat Tamping machine for plain track and turnout
 Dumoatic Tamping Machine for plain track
 DGS 62 N dynamic Track Stabilizer.
Plant and Equipment
 Abrasive Rail Saw
 Rail drilling Machine
 Rail head Grinding machine
 Rail Web Grinding Machine
 Rail tensor
 Motor Trolley,
 Motorized dip lorries
 Push trolley
 Welding Tool: Gas cutter, Single Phase Welding M/C,
Industrial Tool Kit set. Rail Gripper and allied tools etc
Plant and Equipment
Track Installation
(5) Step 5 – Welding Pulling of Rail Panels
Fig : Sub Grade Soil Cutting and Filling
Track Installation
(5) Step 5 – Welding Pulling of Rail Panels
Fig : Compaction of Subgrade and Blanket Materials not
exceeding 250 mm to 103% relative compaction
Track Installation
Fig : Survey Capturing of Finished Levels and Marking of Track
Centers
Track Installation
Fig : Laying of Ballast over the Formation
Track Installation
Fig : Compaction of Ballast
Track Installation
Fig : Rail Panels Pulled Over Ballast
Track Installation
Fig : Laying of Sleeper With Track Construction Machine
Track Installation
Fig : Laying of Sleepers and Laying of Rails Over the Sleeper by
New Track Construction Machine
Track Installation
Fig : Track Laid with New Track Construction Machine
Track Installation
Fig : Track Ready for Ballast Works
Track Installation
Fig : Completed Ballasted Track
DRAFT
Overview
Depot Tracks
Fig : Pedestal Tack
• The Pedestal Track structure consists of a
support base and a reinforced concrete
slab in where the steel pillars are fixed.
• Used in workshop building.
Depot Tracks
Fig : Embedded Block System (EBS)
• Used to reduce
dynamic loads and
vibrations.
• Used also to reduce
ground-borne noises
and provide electrical
insulation especially
around the depot
areas.
Depot Tracks
Fig : Turn Table
• Device for turning
maintenance
trains so that they
can be moved in
different
directions within
the depot
maintenance
facilities.
Query

More Related Content

What's hot

Delhi metro internship Report (05.05.2018 04.06.2018)
Delhi metro internship Report (05.05.2018 04.06.2018)Delhi metro internship Report (05.05.2018 04.06.2018)
Delhi metro internship Report (05.05.2018 04.06.2018)Shubham Bhargava Slideshares
 
Railway Bridges History & Construction
Railway Bridges History & ConstructionRailway Bridges History & Construction
Railway Bridges History & ConstructionZakaria Yahya
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)RAMPRASAD KUMAWAT
 
Point and crossing of railway
Point and crossing of railwayPoint and crossing of railway
Point and crossing of railwayRAMPRASAD KUMAWAT
 
Bridges and its Types & Components by Chetan Bisht
Bridges and its Types & Components by  Chetan BishtBridges and its Types & Components by  Chetan Bisht
Bridges and its Types & Components by Chetan BishtChetanBisht16
 
Unit ii railways
Unit ii railwaysUnit ii railways
Unit ii railwaysVipul Naidu
 
62617938 launching-girder
62617938 launching-girder62617938 launching-girder
62617938 launching-girderlotuseye
 
railway ppt for civil engg.
 railway ppt for civil engg. railway ppt for civil engg.
railway ppt for civil engg.ashrafdgrt
 
Metro ppt-180628112005
Metro ppt-180628112005Metro ppt-180628112005
Metro ppt-180628112005PRATAP MISHRA
 
Presentation on railway construction and maintenance
Presentation on railway construction and maintenancePresentation on railway construction and maintenance
Presentation on railway construction and maintenanceMohd Bakhsh
 
Railway station and YARD
Railway station and YARD Railway station and YARD
Railway station and YARD Dhruv Makadia
 
Alignment of railway tracks
Alignment of railway tracksAlignment of railway tracks
Alignment of railway tracksGowtham G
 
Depots presentation
Depots presentationDepots presentation
Depots presentationKumar M.
 

What's hot (20)

Delhi metro internship Report (05.05.2018 04.06.2018)
Delhi metro internship Report (05.05.2018 04.06.2018)Delhi metro internship Report (05.05.2018 04.06.2018)
Delhi metro internship Report (05.05.2018 04.06.2018)
 
Metro ppt - copy
Metro ppt - copyMetro ppt - copy
Metro ppt - copy
 
Railway Bridges History & Construction
Railway Bridges History & ConstructionRailway Bridges History & Construction
Railway Bridges History & Construction
 
Chenab bridge ppt
Chenab bridge pptChenab bridge ppt
Chenab bridge ppt
 
CHENAB BRIDGE
CHENAB BRIDGECHENAB BRIDGE
CHENAB BRIDGE
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
 
Point and crossing of railway
Point and crossing of railwayPoint and crossing of railway
Point and crossing of railway
 
Bridges and its Types & Components by Chetan Bisht
Bridges and its Types & Components by  Chetan BishtBridges and its Types & Components by  Chetan Bisht
Bridges and its Types & Components by Chetan Bisht
 
Unit ii railways
Unit ii railwaysUnit ii railways
Unit ii railways
 
62617938 launching-girder
62617938 launching-girder62617938 launching-girder
62617938 launching-girder
 
Chenab Bridge
Chenab BridgeChenab Bridge
Chenab Bridge
 
railway ppt for civil engg.
 railway ppt for civil engg. railway ppt for civil engg.
railway ppt for civil engg.
 
Rapid transit system
Rapid transit systemRapid transit system
Rapid transit system
 
Metro ppt-180628112005
Metro ppt-180628112005Metro ppt-180628112005
Metro ppt-180628112005
 
report
reportreport
report
 
Presentation on railway construction and maintenance
Presentation on railway construction and maintenancePresentation on railway construction and maintenance
Presentation on railway construction and maintenance
 
presentation
presentationpresentation
presentation
 
Railway station and YARD
Railway station and YARD Railway station and YARD
Railway station and YARD
 
Alignment of railway tracks
Alignment of railway tracksAlignment of railway tracks
Alignment of railway tracks
 
Depots presentation
Depots presentationDepots presentation
Depots presentation
 

Similar to Presentation on track works

viewNitPdf_3777461.pdf
viewNitPdf_3777461.pdfviewNitPdf_3777461.pdf
viewNitPdf_3777461.pdfDivyanshTotla
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019David H Moloney
 
458531017-Slipform-technology-ppt.ppt
458531017-Slipform-technology-ppt.ppt458531017-Slipform-technology-ppt.ppt
458531017-Slipform-technology-ppt.pptJerryMah1
 
SCHEDULE OF DIMENSIONS.ppt
SCHEDULE OF DIMENSIONS.pptSCHEDULE OF DIMENSIONS.ppt
SCHEDULE OF DIMENSIONS.pptzubersana
 
BALLAST SPEC
BALLAST SPECBALLAST SPEC
BALLAST SPECtywaoy
 
BALLAST-spec-Nov 2014.ppt
BALLAST-spec-Nov 2014.pptBALLAST-spec-Nov 2014.ppt
BALLAST-spec-Nov 2014.pptPrakashbudhani
 
Rail, sleepers fittings.ppt
Rail, sleepers  fittings.pptRail, sleepers  fittings.ppt
Rail, sleepers fittings.pptAdityaDubewar2
 
Coiled Tubing Introduction and Basics.pdf
Coiled Tubing Introduction and Basics.pdfCoiled Tubing Introduction and Basics.pdf
Coiled Tubing Introduction and Basics.pdfsalem123gmaal
 
IRJET- Finite Element Analysis of Slabs, Cross Girders and Main Girders in RC...
IRJET- Finite Element Analysis of Slabs, Cross Girders and Main Girders in RC...IRJET- Finite Element Analysis of Slabs, Cross Girders and Main Girders in RC...
IRJET- Finite Element Analysis of Slabs, Cross Girders and Main Girders in RC...IRJET Journal
 
Iai ct4 cj0194 2-a-ust-1-1213
Iai ct4 cj0194 2-a-ust-1-1213Iai ct4 cj0194 2-a-ust-1-1213
Iai ct4 cj0194 2-a-ust-1-1213Electromate
 
Road making machines in mines
Road making machines in minesRoad making machines in mines
Road making machines in minesVijayant Singh
 
Iai rcs3 ct8 c-cj0210-1a-ust-1-0114
Iai rcs3 ct8 c-cj0210-1a-ust-1-0114Iai rcs3 ct8 c-cj0210-1a-ust-1-0114
Iai rcs3 ct8 c-cj0210-1a-ust-1-0114Electromate
 
Alternative Approach to Permanent way Alignment Design
Alternative Approach to Permanent way Alignment DesignAlternative Approach to Permanent way Alignment Design
Alternative Approach to Permanent way Alignment DesignConstantin Ciobanu
 
Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Malyar Talash
 
Part 1 T-Track - Introduction
Part 1 T-Track - IntroductionPart 1 T-Track - Introduction
Part 1 T-Track - IntroductionSean Wilson
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanDavid H Moloney
 
Electric Wire Rope Hoist Manufacturers in Ahmedabad
Electric Wire Rope Hoist Manufacturers in AhmedabadElectric Wire Rope Hoist Manufacturers in Ahmedabad
Electric Wire Rope Hoist Manufacturers in AhmedabadTechno Industries
 
Tsurumi Submersible Pump for Wastewater - B series Non clog impeller
Tsurumi Submersible Pump for Wastewater - B series Non clog impellerTsurumi Submersible Pump for Wastewater - B series Non clog impeller
Tsurumi Submersible Pump for Wastewater - B series Non clog impellerMuliawan Wawan
 

Similar to Presentation on track works (20)

viewNitPdf_3777461.pdf
viewNitPdf_3777461.pdfviewNitPdf_3777461.pdf
viewNitPdf_3777461.pdf
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019
 
458531017-Slipform-technology-ppt.ppt
458531017-Slipform-technology-ppt.ppt458531017-Slipform-technology-ppt.ppt
458531017-Slipform-technology-ppt.ppt
 
SCHEDULE OF DIMENSIONS.ppt
SCHEDULE OF DIMENSIONS.pptSCHEDULE OF DIMENSIONS.ppt
SCHEDULE OF DIMENSIONS.ppt
 
BALLAST SPEC
BALLAST SPECBALLAST SPEC
BALLAST SPEC
 
BALLAST-spec-Nov 2014.ppt
BALLAST-spec-Nov 2014.pptBALLAST-spec-Nov 2014.ppt
BALLAST-spec-Nov 2014.ppt
 
Rail, sleepers fittings.ppt
Rail, sleepers  fittings.pptRail, sleepers  fittings.ppt
Rail, sleepers fittings.ppt
 
Coiled Tubing Introduction and Basics.pdf
Coiled Tubing Introduction and Basics.pdfCoiled Tubing Introduction and Basics.pdf
Coiled Tubing Introduction and Basics.pdf
 
IRJET- Finite Element Analysis of Slabs, Cross Girders and Main Girders in RC...
IRJET- Finite Element Analysis of Slabs, Cross Girders and Main Girders in RC...IRJET- Finite Element Analysis of Slabs, Cross Girders and Main Girders in RC...
IRJET- Finite Element Analysis of Slabs, Cross Girders and Main Girders in RC...
 
Iai ct4 cj0194 2-a-ust-1-1213
Iai ct4 cj0194 2-a-ust-1-1213Iai ct4 cj0194 2-a-ust-1-1213
Iai ct4 cj0194 2-a-ust-1-1213
 
Road making machines in mines
Road making machines in minesRoad making machines in mines
Road making machines in mines
 
Iai rcs3 ct8 c-cj0210-1a-ust-1-0114
Iai rcs3 ct8 c-cj0210-1a-ust-1-0114Iai rcs3 ct8 c-cj0210-1a-ust-1-0114
Iai rcs3 ct8 c-cj0210-1a-ust-1-0114
 
Alternative Approach to Permanent way Alignment Design
Alternative Approach to Permanent way Alignment DesignAlternative Approach to Permanent way Alignment Design
Alternative Approach to Permanent way Alignment Design
 
Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)
 
Part 1 T-Track - Introduction
Part 1 T-Track - IntroductionPart 1 T-Track - Introduction
Part 1 T-Track - Introduction
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, Oman
 
Closure Report
Closure ReportClosure Report
Closure Report
 
Electric Wire Rope Hoist Manufacturers in Ahmedabad
Electric Wire Rope Hoist Manufacturers in AhmedabadElectric Wire Rope Hoist Manufacturers in Ahmedabad
Electric Wire Rope Hoist Manufacturers in Ahmedabad
 
Rail track geometry
Rail track geometryRail track geometry
Rail track geometry
 
Tsurumi Submersible Pump for Wastewater - B series Non clog impeller
Tsurumi Submersible Pump for Wastewater - B series Non clog impellerTsurumi Submersible Pump for Wastewater - B series Non clog impeller
Tsurumi Submersible Pump for Wastewater - B series Non clog impeller
 

Recently uploaded

Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 

Recently uploaded (20)

Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 

Presentation on track works

  • 1. Mumbai Metro Line 4& 4A& 4A Presentation on Track Work
  • 2. Riyadh Metro – Slab Track
  • 3. Mumbai Metro Line 4 & 4A Track Structure. a) Ballastless Track:  Track elements comprising of running rails, rail-fastening, embedded in concrete at-grade slab, a concrete viaduct deck, or a concrete underground invert.  Track slab will be Cast in situ/ plinth, The track slab shall be designed as plinth beam or slab type ballastless track with derailment gaurds. Track Structure
  • 4. MumbMumbai Metro – Plinth Track -Plinth Track Ballast-less Track Components: • Rail (Hardened Rail UIC 60E1) • Track fastening system • Track Plinth
  • 5. Sl. No. CRITERIA DIMENSION 1 Gauge 1435 mm Standard Gauge, 2 Max.train speed a) Maximum (Design) b) Maximum (Operating) 90 Kmph (in straight) and 80 kmph (in curves upto Radius 300m) 80 Kmph (To be confirmed by Employer at later stage) 3 Max. axle load, loaded condition 17 tonnes Standard Gauge, 4 Max. desirable gradient running track Absolute max. gradient running track 3% 4% 5 Minimum vertical curve radius Minimum horizontal curve radius 1500 m 120 m 6 Electric power 25KV AC overhead traction 7 Inclination of Rail 1 in 20 8 Wheel profile IRS type to be interfaced with Rolling Stock Supplier. 9 Rail profile UIC 60E1 10 Design Rail Temperature 8 Deg C to 54 Deg C Technical Criteria and Operation Standards
  • 6. a) Rail Section: b. Fastening: Having record of minimum three years in service in regular revenue for a length of at least 5km with speed potential of 80 kmph & design axle load 16T. Track Components – Plinth TrackComponents:
  • 7. c) Concrete:  The concrete shall be of minimum M45 grade as per the Indian Standard IS-456 – 2000 d) Steel Reinforcement:  Reinforcement & shear connector shall be IS 1786 in accordance with relevant IS codes. PlinthTrack Components – Plinth Trackmponents:
  • 8. Trac Alignment – Specificationponents tructure ParameterDescription Standard Gauge Corridor Rail type main line UIC 60E1, IRS-T-12-2009 with all correction slips, 1080 grade head hardened (HH) Tentative Base Plate Spacing (Shall be reviewed by Contractor as per detailed design, following approval from Engineer for varying curvature) 650 mm ( Main line (on elevated viaducts and stations in straight) and curves with radius >300M 600 mm in case of curves with radius ≤ 300 M Standard Rail Length Main line 18m Maximum cant permissible 110mm Maximum cant deficiency Permissible 85 mm Maximum cant gradient Permissible Maximum cant gradient Desirable 1 in 440 1 in 720 Rate of change of cant/cant deficiency Standard Gauge maximum Permissible Standard Gauge maximum Desirable 40mm/sec 25mm/sec Type of turnouts – Standard Gauge 1 in 9 :300m radius Type of Scissor Crossover 1 in 9: 300 m radius Diamond Crossing
  • 10.
  • 11. Picture: Taking over of Finished over Grade / Vaiduct Section Track Installation
  • 12. Track Installation Fig : Total Station Survey Capturing of Finished Levels
  • 13. Track Installation (5) Step 5 – Welding Pulling of Rail Panels Fig : Flash Butt Welding of Rail
  • 14. Track Installation (4) Step 4 – Rail Drop into position – Track Site Fig: Unloading of Rails over Deck slab
  • 15. Track Installation (5) Step 5 – Welding Pulling of Rail Panels Fig : Marking of alignment center
  • 16. Fig : Lifting and Rails with GSF Supports over the alignment center Track Installation
  • 17. Track Installation (5) Step 5 – Welding Pulling of Rail Panels Fig : Fixing of Dummy Plates with Vossloh Fastenings
  • 18. Track Installation (5) Step 5 – Welding Pulling of Rail Panels Fig : Vossloh Fastenings FE 336 used in Riyadh Metro
  • 19. Fig : Reinforcement of Track Slab Track Installation
  • 20. Fig : From Work for Track Slab including Derailment Guard Track Installation
  • 21. Fig : Third Rail Dowel Provision Works Track Installation
  • 22. Fig : Final Inspection Works Track Inspection Inspection of vertical & horizontal alignment with Track Master Inspection of vertical alignment
  • 23. Fig : Adjustment of Errors Track Inspection Ignment
  • 24. Track Installation Dimensional Tolerances Ballastless Track Gauge maximum variation +/- 2 mm Mean Gauge per 200 m -1 mm Max difference of any point in relation to the designed layout ( Vertical ) -4 mm/+4 mm Max difference of any point in relation to the designed layout ( horizontal) -4 mm/+4 mm On curve, deviation of measured versine 20 m chord: (half overlapping) +/- 2 mm Maximum deviation of measured versine (vertical) over its designed value on a 10 m chord (half overlapping) +/- 2 mm Baseplate to base plate (ballastless) Variation of cant/x- level  1 mm Twist: (over & above designed value) straight and circular portion of curve On transition portion of curve 1 mm/m 0.5 mm/m
  • 25. Fig : Track Slab Concrete Track Installation
  • 26. Fig : Surface finishing Track Slab Concrete Track Installation
  • 27. Fig : Rear Works of Finished Track Slab Track Installation
  • 28. Fig : Fixing of Fastenings Track Installation
  • 29. Fig : Destressing Works at Temp 37°C to 43°C Track Installation N
  • 30. Fig : Final Track installation and Recording Data Track Installation
  • 31. a) Track Structure in Depot :  Ballasted Track for Main Lines.  Pedestal Track for inspection lines.  Embedded track inside the Workshop.  Plinth type for Washing Plant line. Depot Track Works
  • 32. Track elements running rails, rail-fastening rail pads,, concrete sleeper blocks, stone ballast installed upon a well compacted subgrade. Ballasted Track In Depots
  • 33. Ballasted Track Standard Description Standard Gauge Corridor Rail type UIC 60E1, IRS-T-12-2009 with all correction slips, 880 grade and 1080 grade head hardened (HH) Tentative Base Plate Spacing (Shall be reviewed by Contractor as per detailed design, following approval from Engineer for varying curvature) 700 mm +/- 25 mm 600 mm +/- 25 mm (curve radius ≤ 300 m) Standard Rail Length 18 m Minimum ballast cushion depth 200 mm Formation cross fall 1 in 20 Type of turnouts – Standard Gauge 1 in 7 :190m radius Type of Scissor Crossover 1 in 7: 190 m radius Diamond Crossing (to be adequately designed by Contractor)
  • 34. b. Components of Ballasted track :  Rails: UIC 60E1, IRS-T-12-2009 with all correction slips, 880 grade and 1080 grade head hardened (HH)  Sleepers :The PSC sleepers shall be used in accordance with RDSO drawing no.T-2496 and specification IRS-T-39 (revised from time to time)  Fastenings : compatible fastening system with minimum toe load of 1045kg and approved by Indian Railway shall be used. Ballasted Track Structure
  • 35. c. Rail Fixtures of Ballasted track :  The various types of rail fixtures and fastenings commonly used in a permanent way are the following: 1. Fish plates 8. Check rails 2. Bolts 9. M.C.I. Insert 3. Spikes 10. Rubber pads 4. Chairs 5. Keys, cotters and tie bars 6. Bearing plates 7. Guard rails Ballasted Track Structure
  • 36. d. Pictures of Rail fixtures in Ballasted track : Dog Spike Chairs with Tie plates Ballasted Track Structure
  • 37. e. Specificaitons:  Basic Quality: Ballast should be hard durable and as far as possible angular edges/corners, free, organic Impurities and inorganic residues.  Shape: Ballast should be cubical in shape as far as possible. Track ballast
  • 38. f. Physical Properties of Ballast:  Ballast sample should satisfy the following physical properties in accordance with IS: 2386 Pt. IV-1963 when tested as per RDSO detailed specifications.  Aggregate Abrasion Value: 30% Max.  Aggregate Impact Value: 20% Max.  The “Water Absorption” tested as per IS2386 Pt.-III 1963 following the procedure given in in RDSO detailed specifications should not be more than 1%. Specification of Track ballast
  • 39. g. Size and Gradation of Ballast:  Ballast should satisfy the following size and gradation:  Retained on 65 mm sq. Mesh sieve 5% Maximum.  Retained on 40 mm sq. Mesh sieve 40% -60% for machine crushed ballast.  Retained on 20 mm sq. Mesh sieve not less than 98% for machine crushed. Not less than 95% for hand broken. Specification of Track ballast
  • 40. Gradation of Ballast (5) Step 5 – Welding Pulling of Rail Panels Fig : Ballast Sieve Analysis
  • 41. Earth Works of Ballasted Track (5) Step 5 – Welding Pulling of Rail Panels Fig : Earth Works of Ballasted Track
  • 42. a. Blanket layers : This layer is placed between the prepared subgrade and ballast layers and may consist of one or several layers:, It has the following functions:  improving the bearing capacity by a better distribution of transmitted loads,  protecting against erosion and frost,  acting as a filter between subgrade and ballast,  shedding surface water. Earth Works of Ballasted Track
  • 43. b. Formation/Subgrade :  Prepared subgrade (also named as “Form layer”): this layer must have bearing capacity to support the ballast and blanket layers and to avoid water infiltration in the embankment. c. Embankment or Cutting:  If the design level of the rails is above the current surface ground, it will be necessary to build an embankment; in the opposite case, a cutting of the natural ground will have to be performed. Earth Works of Ballasted Track
  • 44. For efficient execution of track work the following tools and machinery are proposed to be deployed. This list is not exhaustive and is subject to change as per site requirement.  Mobile Flash butt Welding machine  New Track layer self propelled with sleeper Gantry Crane  Tractor/Dozer / Loader for pulling Rail Panel  Clip applicator mounter on Track  Sleeper Loading Gantry Crane  Fixed rail Gantry Crane 21 X 2T  Rail Profile Grinder Plant and Equipment
  • 45.  Flat Wagons for Rail & Sleeper transport  Hopper Wagons for Ballast training out  Wheel Loader  Grader  Vibratory Roller 8T  Hydra Crane  Mobile Crane 25 Tonne Capacity  Loco / UTV  Unimat Tamping machine for plain track and turnout  Dumoatic Tamping Machine for plain track  DGS 62 N dynamic Track Stabilizer. Plant and Equipment
  • 46.  Abrasive Rail Saw  Rail drilling Machine  Rail head Grinding machine  Rail Web Grinding Machine  Rail tensor  Motor Trolley,  Motorized dip lorries  Push trolley  Welding Tool: Gas cutter, Single Phase Welding M/C, Industrial Tool Kit set. Rail Gripper and allied tools etc Plant and Equipment
  • 47. Track Installation (5) Step 5 – Welding Pulling of Rail Panels Fig : Sub Grade Soil Cutting and Filling
  • 48. Track Installation (5) Step 5 – Welding Pulling of Rail Panels Fig : Compaction of Subgrade and Blanket Materials not exceeding 250 mm to 103% relative compaction
  • 49. Track Installation Fig : Survey Capturing of Finished Levels and Marking of Track Centers
  • 50. Track Installation Fig : Laying of Ballast over the Formation
  • 51. Track Installation Fig : Compaction of Ballast
  • 52. Track Installation Fig : Rail Panels Pulled Over Ballast
  • 53. Track Installation Fig : Laying of Sleeper With Track Construction Machine
  • 54. Track Installation Fig : Laying of Sleepers and Laying of Rails Over the Sleeper by New Track Construction Machine
  • 55. Track Installation Fig : Track Laid with New Track Construction Machine
  • 56. Track Installation Fig : Track Ready for Ballast Works
  • 57. Track Installation Fig : Completed Ballasted Track
  • 59. Depot Tracks Fig : Pedestal Tack • The Pedestal Track structure consists of a support base and a reinforced concrete slab in where the steel pillars are fixed. • Used in workshop building.
  • 60. Depot Tracks Fig : Embedded Block System (EBS) • Used to reduce dynamic loads and vibrations. • Used also to reduce ground-borne noises and provide electrical insulation especially around the depot areas.
  • 61. Depot Tracks Fig : Turn Table • Device for turning maintenance trains so that they can be moved in different directions within the depot maintenance facilities.
  • 62. Query