SlideShare a Scribd company logo
1 of 46
Download to read offline
12-Apr-18
By Tsegaye Arega
M Tech student in Construction
Engineering and Management
IIT Delhi
April 2018
DEMOLISHING OF CONCRETE
STRUCTURES
INTRODUCTION
īą Demolition is the dÄąsmantlÄąng, razÄąng,
destroyÄąng or wreckÄąng any building or structure
or any part of building by pre-planned and
controlled methods.
īą Demolition is bringing down the building and
other structures safely
īą Demolition is one of the most dangerous
activities in the construction sector
īą Demolition Can be total or partial
īą Total demolition is aimed at the recovery of the
area for subsequent re-use, while partial
demolition is aimed at the recovery of the
building for refurbishing or rebuilding.
.
12-Apr-18
īą The structures which have already passed their
design life need to be reconstructed, for safety and
operational requirements.
īą The old structures need to be demolished for
replacement by new structures
īą Small structures can be demolished by manual
methods but machinery and
advanced techniques are required for demolition of
bigger structures
īą Advanced techniques are also required for faster
demolition and demolition in confined areas.
12-Apr-18
WHY DEMOLISHING?
ī‚ĸ Demolition work is to be performed safely and
with number of different steps involved before
and during the execution of a demolition
process.
12-Apr-18
STEPS BEFORE DEMOLITION
īą For demolition of a building ,detailed survey
and assessment of a building is necessary.
It includes
A. Building survey
īą Drawing records
īą Material survey
īą Hazardous materials
īą Photographs of a building to be demolished
īą Surrounding buildings
īą Building height, distance from nearby buildings
īą Type of building
12-Apr-18
1. SURVEY FOR DEMOLITION
B. Structural survey
īą Drawing records
īą Special structure
īą Behavior of structure
īą Structural support system
īą Degree of deterioration
12-Apr-18
1. SURVEY FOR DEMOLITION
a. Asbestos Containing Material
In the case when asbestos
containing material are
discovered, specialist contractor
shall be employed to remove such
asbestos containing material. The
asbestos waste should be handled,
stored and disposed of as chemical
waste in accordance with the
Waste Disposal Regulation
12-Apr-18
2. REMOVAL OF HAZARDOUS MATERIALS
Asbestos Material
In the case when possible soil
contamination material is
present, specialist shall be
employed to prepare soil
contamination test proposal and
submit such proposal to the
Environmental Protection
Department for comment.
12-Apr-18
2. REMOVAL OF HAZARDOUS MATERIALS
b. Soil Contamination Material
Soil contamination
12-Apr-18
3. PREPARATION OF PLAN
ī‚ĸ Based on demolition surveys, a demolition plan is
prepared This plan is produced with the application for
approval to the local authority. This plan includes
ī‚ĸ Plan showing the location of a building to be
demolished.
īļ Building height, structural system
īļ Extent of damage to the building
īļ Existing structures and facilities in the vicinity
īļ Layout plan
īļ Proposed method of demolition
īļ Safety measures
īļ Proposed sequence of demolition steps
īļ Details of equipment's used.
īļ plan for handling and disposal of debris
īļ Proposed arrangements for site supervision
12-Apr-18
4. SAFETY MEASURES
ī‚§ Training and Communication:
Demolition workers, including
plant or equipment operators,
shall go through proper job safety
training and be informed of the
potential hazards by attending
training sessions as well as on-the-
job training
ī‚§ Equipment Maintenance:
All equipment shall be tested and
examined before use. They shall be
properly stored and maintained.
The equipment shall be inspected
daily and results of the inspection
shall be recorded accordingly.
12-Apr-18
4. SAFETY MEASURES
A properly connected power source from a local electric utility
supplier or a mobile electricity generator shall be utilized in
demolition sites
All flammable goods shall be removed from site unless they
are necessary for the works involved. Any remaining
flammable goods shall be stored in proper storage facilities.
All furniture, timber, doors, etc. shall be removed before any
welding work is performed. Fire fighting appliances shall be
provided and maintained in working conditions.
Electrical Safety
Fire
12-Apr-18
DEMOLISHING SEQUENCE
Demolition sequence shall be determined based on Actual site
conditions, Restraints, The building layout, The Structural
layout and its construction. In general, the following sequence
shall apply:
īą Utilities disconnection. Electricity, plumbing water lines,
drainage connections etc..
īą All cantilevered structures, canopies, verandahs and
features attached to the external walls shall first be
demolished prior to demolition of main building and its
internal structures on each floor
12-Apr-18
DEMOLISHING SEQUENCE
īą When demolishing the roof structure, all lift machine rooms
and water tanks at high level shall be demolished in “top
down” sequence to the main roof level
īą Demolition of the floor slabs shall begin at mid span and
work towards the supporting beams.
īą Floor beams shall be demolished in the order of
cantilevered beams, secondary beams and then main beams.
īą Non-load bearing walls shall be removed prior to
demolition of load bearing walls.
12-Apr-18
DEMOLISHING SEQUENCE
If site conditions permit, the first floor slab directly above the
ground floor may be demolished by machine standing on
ground.
12-Apr-18
FACTORS AFFECTING DEMOLISHING METHODS
īą According to Kasai et al/1988/ are demolition methods
classified into principles and mechanisms of breaking.
īą The selection of a specific process should be based on the
experience learned from the conventional demolition
industry, and applicable experience from actual
decommissioning programs.
īą Some of the factors to affecting selection of
demolishing methods are;
a) Type of structure
Different types of structure like load bearing masonry
structure , RCC framed structure, steel structure , etc.
12-Apr-18
FACTORS AFFECTING DEMOLISHING METHODS
b. Size of structure
If the size of structure is small, hand demolition can be
sufficient. for large structures and multi storied buildings
special like wrecking ball method, deliberate collapse,
implosion technique etc are necessary.
c. Available time period
d. Location of structure
e. Limitation of noise, dust and vibrations
f. Skill of workers
g. Safety
h. Availability of equipment
i. Adjacent structures
12-Apr-18
FACTORS AFFECTING DEMOLISHING METHODS
Demolishing
Techniques
Engineering
Demolishing
Mechanical
method
Implosion
Method
Deconstruction
Method
Non
Engineering
demolishing
Manual
demolition
12-Apr-18
CONTINUEDâ€Ļ
Manual Methods
īą This is demolishing by human operatives/hand held
operations.
īą Suitable for use in smaller site with congested space where
larger machine cannot be employed.
īą using simple electrically or pneumatically powered tools such
as picks, hammers, wire cutters or hand driven hydraulic
jacks etc. to carry out the demolition of individual elements.
īą Tools required for manual demolition;
â€ĸ Hammers
â€ĸ Picks
â€ĸ Wire cutters
â€ĸ Welding cutters
â€ĸ Hand driven hydraulic jacks etc.
12-Apr-18
Mechanical Methods
īą Wrecking method
īą Pusher arm technique
īą Thermic lance technique
īą Non explosive demolition
īą Concrete sawing method
īą Deliberate collapse method
īą Pressure jetting method
īą bursting
Implosion Methods
īą demolition of structure with the help of explosives is called
as implosion
CONTINUEDâ€Ļ
12-Apr-18
ī‚ĸ Manual methods are carried out top down,
proceeding, in general, from the roof to ground. The sequence
of demolition may vary, depending on
ī‚— Site conditions and
ī‚— Structural element to be demolished
1. MANUAL METHODS
12-Apr-18
1. Hand held hammering; Repeated hammering is often
used to fracture and break concrete mainly due to occurring
tensile and shear stress.
1. MANUAL METHODS
i. Rotary-hammer ;boring holes by
Rotary hammering; in concrete. They
are versatile and also work well in the
hammer-only mode.
ii. Chipping hammer; Lightweight and
hand-held, chipping hammers are
perfect for breaking
vertical and overhead concrete surfaces.
12-Apr-18
2. Hydraulic concrete crusher
Hydraulic concrete crushers are
used to reduce concrete into
smaller, more manageable pieces.
They also separate steel
reinforcement from concrete.
1. MANUAL METHODS
iii. Demolition hammer;
Demolition hammers deliver hammering action
only, unlike rotary hammers, which are used to
bore holes.
12-Apr-18
3. Pavement breaker
Pavement breakers are used in
heavy concrete demolition projects
because they can demolish
pavements, roads, and extremely
thick concrete
3. Hydraulic splitter
Hydraulic splitters use lateral
forces against the insides of
concrete holes to break up the
concrete without creating
lots of noise and debris.
1. MANUAL METHODS
12-Apr-18
īą The sequence of demolition by machine is typically the
same as the top down manual method, except that
most of the demolition is done by mechanical plant
2. MECHANICAL METHODS
1. Excavator and attachments
12-Apr-18
2. MECHANICAL METHODS
1.1 Excavator mounted with hydraulic
crasher
â€ĸ The crusher attachment breaks the
concrete and the reinforcement by the
hydraulic thrust through the long
boom arm system
â€ĸ The hydraulic crusher can be
operated from
the ground outside the building. This
method is also suitable for dangerous
buildings, silos and other industrial
facilities.
â€ĸ The excavator shall operate on firm
ground that can support the machine
during the crusher operation.
â€ĸ Each section of the structure shall be
demolished in a top down sequence
12-Apr-18
1.2. Excavator mounted with A
hydraulic jackhammer;
ī‚ĸ Typically much larger than
portable ones, may be fitted to
mechanical excavators or backhoes
and is widely used for roadwork,
quarrying and general demolition
or construction groundwork.
ī‚ĸ Pneumatic breakers are simpler
tools with fewer moving parts,
requiring less maintenance.
2. MECHANICAL METHODS
12-Apr-18
īą The demolition begins with the lifting of the
mechanical plant on to the building top floor.
īą Adequate propping shall be installed at floor levels
below the working floor to safely support the operation of
the mechanical plant.
īą The movement of the mechanical plant shall only be
within the propped area. The propped areas shall be
suitably marked.
īą The mechanical plant shall be lifted onto the roof of the
building by the use of mobile crane or other appropriate
means as approved.
īą The machine shall descend down to the next floor by
means of a ramp. The ramp may be a temporary structure
or other appropriate design.
2. MECHANICAL METHODS
12-Apr-18
2. MECHANICAL METHODS
12-Apr-18
2. MECHANICAL METHODS
2. Ball and crane
ī‚§ This is one of the oldest and most
commonly used methods for
demolition.
ī‚§ The wrecking ball application
consists of a crane equipped with a
steel ball.
ī‚§ A crane uses a wrecking ball,
weighing up to 6120kg, which is
either dropped onto or swung into
the element to be demolished.
ī‚§ Concrete members can be broken
into small pieces, but secondary
cutting of reinforcing may be
necessary.
12-Apr-18
2. MECHANICAL METHODS
ī‚§ The destruction of the building is by the impact energy
of the steel ball suspended from the crawler crane. The
wrecking ball operates outside the building.
ī‚§ However, the operation requires substantial clear
space. The application also demands high level skill
operators and well maintained equipment
12-Apr-18
2. MECHANICAL METHODS
īą Recommended techniques for the wrecking ball
operations include (1) Vertical Drop -free falling of
the wrecking ball onto the structure and (2) Swing
in line - swinging of the ball in-line with the jib.
īą A second dragline will normally connect to the ball
horizontally to control the ball motion
īą The operation shall not be performed adjacent to
overhead power lines. The site shall be entirely
fenced off to forbid public access.
īą One of the disadvantage of this method is he
breakup process can cause considerable dust,
vibration and noise which may be objectionable.
12-Apr-18
2. MECHANICAL METHODS
3. Dismantling
ī‚§ Selective or complete demolition of
concrete structures is possible by cutting
elements and then removing them with a
crane.
ī‚§ The cutting process may be by
sawing, water jetting or thermal
lance.
ī‚§ Because the surface of the cut
concrete is smooth and relatively regular,
these methods have particular
application when the objective is partial
demolition, for instance in the creation of
openings in walls and slabs.
Dismantling a beam
12-Apr-18
2. MECHANICAL METHODS
Continuedâ€Ļ
ī‚§ Hydro demolition uses a high pressure
supersonic water jet, that penetrates
the pores and cracks of the concrete
and builds up an internal pressure.
When this pressure exceeds the tensile
strength of the concrete, the concrete
breaks.
ī‚§ The water jet can be used not only for
cutting straight lines but also contours,
a useful feature for cutting access
manholes.
ī‚§ A thermal lance is created by packing a
seamless mild steel tube with low
carbon rods and passing oxygen
through the tube.
Water jet cutting
12-Apr-18
2. MECHANICAL METHODS
Continuedâ€Ļ
ī‚§ While this method eliminates vibration
and dust problems, it creates other
hazards associated with smoke and fire
danger.
ī‚§ Whether sawing, jetting or lancing is
used to dismantle the structure or its
components, each element must be safely
lowered to the ground.
ī‚§ The amount of time and cost of labor are
the main drawbacks.
ī‚§ Toxic waste such as asbestos sheets and
lead paint have no resale value so they
are discarded.
12-Apr-18
2. MECHANICAL METHODS
4. Pressure bursting
o can be used in cases where relatively
quiet, dust-free, controlled demolition is
preferred The cutting process may be by
sawing, water jetting or thermal lance.
o Both mechanical and chemical pressure
bursting split the concrete, either with a
splitting machine operating on hydraulic
pressure provided by a motor in the case
of mechanical bursting, or through the
insertion of an expansive slurry into a
pre-determined pattern of boreholes in
the case of chemical bursting
ī‚§ Both methods work by applying lateral forces against
the inside of holes drilled into the concrete.
12-Apr-18
5. EXPLOSIVES
īą Implosion is the strategic placing of explosive material and
timing of its detonation so that a structure collapses on itself in
a matter of seconds, minimizing the physical damage to its
immediate surroundings
īą The technique weakens or removes critical supports so that
the building can no longer withstand the force of gravity and
falls under its own weight.
īą Numerous small explosives, strategically placed within the
structure, are used to catalyze the collapse. Nitroglycerine,
dynamite, or other explosives are used to shatter reinforced
concrete supports.
īą For the demolition of concrete structures it is usual to drill holes
at a pre determined angle into the concrete to be removed
12-Apr-18
īą The holes are then charged with an explosive which is
electrically detonated
īą Despite its terminology, building implosion also includes the
controlled demolition of other structures, such as bridges,
smokestacks, towers, and tunnels
īą Empirical judgment based on the skill and experience of the
operator is the basis for blasting design.
īą A simpler but far less effective method of blasting is to lay
the explosive charge on the element to be demolished and
cover it with sand bags.
īą Precautions should be taken to stop flying debris and in all
circumstances strict site control must be maintained to
ensure the safety of workers and the general public.
5. EXPLOSIVES
12-Apr-18
Pre blast considerations
īą The design may include pre-weakening of the structure, the
strategy in placement of the explosives and time delay so
that the building will collapse in a safe manner.
īą Pre-weakening of the structure may include cutting out a
portion of the shear walls and other structural elements
īą A test blast may be conducted to verify the strength of the
structural member and to fine tune the explosive design.
īą Protection of the adjacent properties and habitats is also an
important consideration.
Concrete columns fully
loaded with explosives
CONTINUEDâ€Ļ
12-Apr-18
Test blast
īą Before carrying out the actual blasting, a test blast, in
ordered
to ascertain the efficiency of explosive & detonators.
īą The wrapping of holes can be done to ensure debris does not
fly in air due to explosion of charges.
Before After
CONTINUEDâ€Ļ
12-Apr-18
5. Explosives
General things
ī‚§ High Risk Factor
ī‚§ Time Taken
ī‚§ Produce Distortion
ī‚§ Expensive
ī‚§ Chances of error
ī‚§ Need of experts
ī‚§ Error may leads to
ī‚§ No demolition
ī‚§ Loss of life's
CONTINUEDâ€Ļ
12-Apr-18
īą Demolishing pre stressed concrete structures can be
more difficult than demolishing reinforced concrete
because of the energy stored in the pre stressing
tendons.
īą Pre stressing tendons are likes stretched rubber bands,
with energy stored in the stretching process.
īą The release of the stored energy in a rubber band
causes it to sail through the air.
īą The total demolition of a pre stressed pre-tensioned
structure is no more difficult than the demolition of a
cast-in-place reinforce concrete structure.
DEMOLITION OF PRESTRESSED CONCRETE
12-Apr-18
īą Pre stressed pre-tensioned members are usually designed to
resist applied loading in only one direction.
īą Because of this, the members will fail rather easily if a force
can be applied in an opposite or lateral direction
īą The partial demolition of pre tensioned pre stressed structure
requires more care than similar operations on a cast in place
structure.
DEMOLITION OF PRESTRESSED CONCRETE
īą Pre-tensioned slabs and beams, or
smaller dismantled portions, may be
lifted and lowered to the ground as
complete units (As shown in the photo).
Generally, any necessary shoring and
subsequent lifting should be from
points near the ends of the units
12-Apr-18
īą Sa f e, uneventful demolition of relatively low structures
using a crane and a ball has been accomplished where there is
adequate surrounding work space.
īą Disassembly or from - the - top -down demolition requires a
large amount of shoring which must be installed along the
entire length of the members, unless intermediate tendon
anchors we re installed d u ring construction.
īą Once shore d , the slab and beams can be de tensioned—in re
verse order in which they we re tensioned. Then the slabs and
beams can be demolished using those methods previously
described, with the exception of the ball-and-crane method.
īą The partial demolition of an un bonded post-tensioned
structure can be very complicated and hazardous. If “as -
built” drawings are not available, this operation can be even
more complex.
DEMOLITION OF PRESTRESSED CONCRETE
12-Apr-18
DEMOLITION OF PRESTRESSED CONCRETE
īą After the shoring is in place, the tendon and reinforcing bars
a re located using magnetic detection devices.
īą Once this is done, careful drilling,
chipping or sawing may be used to
expose the pre stressing tendons
(Photo B).
īą The concrete can then be bro k e n
with either hand-held or machine
mounted breakers, or once completely
severed, reduced to a size which may
be lifted and lowered .
īą Careful planning by competent
persons experienced in post tensioning
is essential before attempting partial
demolition of post-tensioned structures
12-Apr-18
TOPIC REFERENCES
1. Christer Molin,1996 , Demolition techniques, IABSE congress
report, Stockholm Sweden
2. Hal T. Hudgins, Demolition of Concrete Structures ,
demolition specialists Atlanta, Georgia
3. Ravi Patel , Demolition Method & Techniques, International
Journal of Advanced Research in Engineering, Science and
Management (IJARESM), Umrakh, Gujarat, India
4. Thomas S. LaGuardia, P.E., Concrete Decontamination And
Demolition Methods, Nuclear Energy Services, Inc. Danbury,
Connecticut.
5. Prof. Ankit Pate, Demolition of Structures, BITS Edu
Campus
6. Martin Johansson, 2002, Handbook on Demolition with
Brokk , Managing director of Brokk AB, Skellefta.
12-Apr-18

More Related Content

What's hot

Top down construction
Top down constructionTop down construction
Top down constructionAglaia Connect
 
Case studies for strengthening of existing structures
Case studies for strengthening of existing structuresCase studies for strengthening of existing structures
Case studies for strengthening of existing structuresParamaAthmeka
 
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)Shanmugasundaram N
 
Different types of damages that have been observed in masonry buildings durin...
Different types of damages that have been observed in masonry buildings durin...Different types of damages that have been observed in masonry buildings durin...
Different types of damages that have been observed in masonry buildings durin...Nitin Kumar
 
Repair and Rehabilitation
Repair and RehabilitationRepair and Rehabilitation
Repair and RehabilitationGAURAV. H .TANDON
 
Precast elements
Precast elementsPrecast elements
Precast elementsShrividhyah
 
Prestressed concrete continuous beam
Prestressed concrete continuous beamPrestressed concrete continuous beam
Prestressed concrete continuous beamPraveenKumar Shanmugam
 
075 Modern Methods of Construction
075 Modern Methods of Construction075 Modern Methods of Construction
075 Modern Methods of ConstructionDr Fereidoun Dejahang
 
Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequenceRanjith Kumar
 
Slipform construction
Slipform constructionSlipform construction
Slipform constructiontivar rose
 
Ch 5 demolition of structures
Ch 5 demolition of structuresCh 5 demolition of structures
Ch 5 demolition of structuresAnkit Patel
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing TechniqueSeminar Links
 
Repair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRSRepair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRSShanmugasundaram N
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of buildingvikas mishra
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.NAVNEET KUMAR JHA
 
Safety precautions during demolition
Safety precautions during demolitionSafety precautions during demolition
Safety precautions during demolitionManthan Vaghasiya
 
Building information modelling report
Building information modelling reportBuilding information modelling report
Building information modelling reportKiran Birdi
 

What's hot (20)

Top down construction
Top down constructionTop down construction
Top down construction
 
Case studies for strengthening of existing structures
Case studies for strengthening of existing structuresCase studies for strengthening of existing structures
Case studies for strengthening of existing structures
 
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
 
Different types of damages that have been observed in masonry buildings durin...
Different types of damages that have been observed in masonry buildings durin...Different types of damages that have been observed in masonry buildings durin...
Different types of damages that have been observed in masonry buildings durin...
 
Maintenance of concrete structures
Maintenance of concrete structuresMaintenance of concrete structures
Maintenance of concrete structures
 
Repair and Rehabilitation
Repair and RehabilitationRepair and Rehabilitation
Repair and Rehabilitation
 
Precast elements
Precast elementsPrecast elements
Precast elements
 
Prestressed concrete continuous beam
Prestressed concrete continuous beamPrestressed concrete continuous beam
Prestressed concrete continuous beam
 
075 Modern Methods of Construction
075 Modern Methods of Construction075 Modern Methods of Construction
075 Modern Methods of Construction
 
Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequence
 
Building maintenance
Building maintenanceBuilding maintenance
Building maintenance
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
Ch 5 demolition of structures
Ch 5 demolition of structuresCh 5 demolition of structures
Ch 5 demolition of structures
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 
Repair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRSRepair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRS
 
Demolition of building
Demolition of building Demolition of building
Demolition of building
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of building
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
 
Safety precautions during demolition
Safety precautions during demolitionSafety precautions during demolition
Safety precautions during demolition
 
Building information modelling report
Building information modelling reportBuilding information modelling report
Building information modelling report
 

Similar to Demolishing of concrete structures

Demolishing of concrete structures
Demolishing of concrete structuresDemolishing of concrete structures
Demolishing of concrete structuresTsegaye Arega
 
DEMOLITION OF BUILDING
DEMOLITION OF BUILDINGDEMOLITION OF BUILDING
DEMOLITION OF BUILDINGshubhajitdua
 
DEMOLITION OF STRUCTURE BY ABHINAV RAWAT
DEMOLITION OF STRUCTURE BY ABHINAV RAWATDEMOLITION OF STRUCTURE BY ABHINAV RAWAT
DEMOLITION OF STRUCTURE BY ABHINAV RAWATAbhinav Rawat
 
Study of Safety in Demolition of Buildings
Study of Safety in Demolition of BuildingsStudy of Safety in Demolition of Buildings
Study of Safety in Demolition of BuildingsIRJET Journal
 
Demolition of Structures.
Demolition of Structures.Demolition of Structures.
Demolition of Structures.Chintan Varia
 
Building Service Chapter 4
Building Service Chapter 4Building Service Chapter 4
Building Service Chapter 4Izam Lukman
 
Rehabilitation of structures,Method of Demolition of Structures
Rehabilitation of  structures,Method of Demolition of  StructuresRehabilitation of  structures,Method of Demolition of  Structures
Rehabilitation of structures,Method of Demolition of StructuresPRAJWAL SHRIRAO
 
Engineering Failure(Case Study of Rana Plaza Collapse-An Example of Engineeri...
Engineering Failure(Case Study of Rana Plaza Collapse-An Example of Engineeri...Engineering Failure(Case Study of Rana Plaza Collapse-An Example of Engineeri...
Engineering Failure(Case Study of Rana Plaza Collapse-An Example of Engineeri...Ariful Islam
 
Demolition Techniques.pptx
Demolition Techniques.pptxDemolition Techniques.pptx
Demolition Techniques.pptxAnanthakumar75
 
DEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUESDEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUESNirant Patel
 
Building Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing ConstructionBuilding Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing Constructionjisunfoo
 
Demolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS codeDemolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS codejaimin1702
 
Techniques for Demolition of Structure
Techniques for Demolition of StructureTechniques for Demolition of Structure
Techniques for Demolition of StructureDinaker Dixit
 
Increase reliability of restoration sewer asset
Increase reliability of restoration sewer assetIncrease reliability of restoration sewer asset
Increase reliability of restoration sewer assetPeerless Industrial Systems
 
Report 150720083151-lva1-app6892
Report 150720083151-lva1-app6892Report 150720083151-lva1-app6892
Report 150720083151-lva1-app6892Sumit Modi
 

Similar to Demolishing of concrete structures (20)

Demolishing of concrete structures
Demolishing of concrete structuresDemolishing of concrete structures
Demolishing of concrete structures
 
DEMOLITION OF BUILDING
DEMOLITION OF BUILDINGDEMOLITION OF BUILDING
DEMOLITION OF BUILDING
 
DEMOLITION OF STRUCTURE BY ABHINAV RAWAT
DEMOLITION OF STRUCTURE BY ABHINAV RAWATDEMOLITION OF STRUCTURE BY ABHINAV RAWAT
DEMOLITION OF STRUCTURE BY ABHINAV RAWAT
 
Techniques behind demolition of structures
Techniques behind demolition of structuresTechniques behind demolition of structures
Techniques behind demolition of structures
 
BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)
 
Study of Safety in Demolition of Buildings
Study of Safety in Demolition of BuildingsStudy of Safety in Demolition of Buildings
Study of Safety in Demolition of Buildings
 
Bs bab 4
Bs bab 4Bs bab 4
Bs bab 4
 
Demolition of Structures.
Demolition of Structures.Demolition of Structures.
Demolition of Structures.
 
BCT Mod 4 demolition of structure
BCT Mod 4 demolition of structureBCT Mod 4 demolition of structure
BCT Mod 4 demolition of structure
 
Building Service Chapter 4
Building Service Chapter 4Building Service Chapter 4
Building Service Chapter 4
 
Demolition pptx
Demolition pptxDemolition pptx
Demolition pptx
 
Rehabilitation of structures,Method of Demolition of Structures
Rehabilitation of  structures,Method of Demolition of  StructuresRehabilitation of  structures,Method of Demolition of  Structures
Rehabilitation of structures,Method of Demolition of Structures
 
Engineering Failure(Case Study of Rana Plaza Collapse-An Example of Engineeri...
Engineering Failure(Case Study of Rana Plaza Collapse-An Example of Engineeri...Engineering Failure(Case Study of Rana Plaza Collapse-An Example of Engineeri...
Engineering Failure(Case Study of Rana Plaza Collapse-An Example of Engineeri...
 
Demolition Techniques.pptx
Demolition Techniques.pptxDemolition Techniques.pptx
Demolition Techniques.pptx
 
DEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUESDEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUES
 
Building Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing ConstructionBuilding Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing Construction
 
Demolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS codeDemolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS code
 
Techniques for Demolition of Structure
Techniques for Demolition of StructureTechniques for Demolition of Structure
Techniques for Demolition of Structure
 
Increase reliability of restoration sewer asset
Increase reliability of restoration sewer assetIncrease reliability of restoration sewer asset
Increase reliability of restoration sewer asset
 
Report 150720083151-lva1-app6892
Report 150720083151-lva1-app6892Report 150720083151-lva1-app6892
Report 150720083151-lva1-app6892
 

Recently uploaded

power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoÃŖo Esperancinha
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

Demolishing of concrete structures

  • 1. 12-Apr-18 By Tsegaye Arega M Tech student in Construction Engineering and Management IIT Delhi April 2018 DEMOLISHING OF CONCRETE STRUCTURES
  • 2. INTRODUCTION īą Demolition is the dÄąsmantlÄąng, razÄąng, destroyÄąng or wreckÄąng any building or structure or any part of building by pre-planned and controlled methods. īą Demolition is bringing down the building and other structures safely īą Demolition is one of the most dangerous activities in the construction sector īą Demolition Can be total or partial īą Total demolition is aimed at the recovery of the area for subsequent re-use, while partial demolition is aimed at the recovery of the building for refurbishing or rebuilding. . 12-Apr-18
  • 3. īą The structures which have already passed their design life need to be reconstructed, for safety and operational requirements. īą The old structures need to be demolished for replacement by new structures īą Small structures can be demolished by manual methods but machinery and advanced techniques are required for demolition of bigger structures īą Advanced techniques are also required for faster demolition and demolition in confined areas. 12-Apr-18 WHY DEMOLISHING?
  • 4. ī‚ĸ Demolition work is to be performed safely and with number of different steps involved before and during the execution of a demolition process. 12-Apr-18 STEPS BEFORE DEMOLITION
  • 5. īą For demolition of a building ,detailed survey and assessment of a building is necessary. It includes A. Building survey īą Drawing records īą Material survey īą Hazardous materials īą Photographs of a building to be demolished īą Surrounding buildings īą Building height, distance from nearby buildings īą Type of building 12-Apr-18 1. SURVEY FOR DEMOLITION
  • 6. B. Structural survey īą Drawing records īą Special structure īą Behavior of structure īą Structural support system īą Degree of deterioration 12-Apr-18 1. SURVEY FOR DEMOLITION
  • 7. a. Asbestos Containing Material In the case when asbestos containing material are discovered, specialist contractor shall be employed to remove such asbestos containing material. The asbestos waste should be handled, stored and disposed of as chemical waste in accordance with the Waste Disposal Regulation 12-Apr-18 2. REMOVAL OF HAZARDOUS MATERIALS Asbestos Material
  • 8. In the case when possible soil contamination material is present, specialist shall be employed to prepare soil contamination test proposal and submit such proposal to the Environmental Protection Department for comment. 12-Apr-18 2. REMOVAL OF HAZARDOUS MATERIALS b. Soil Contamination Material Soil contamination
  • 9. 12-Apr-18 3. PREPARATION OF PLAN ī‚ĸ Based on demolition surveys, a demolition plan is prepared This plan is produced with the application for approval to the local authority. This plan includes ī‚ĸ Plan showing the location of a building to be demolished. īļ Building height, structural system īļ Extent of damage to the building īļ Existing structures and facilities in the vicinity īļ Layout plan īļ Proposed method of demolition īļ Safety measures īļ Proposed sequence of demolition steps īļ Details of equipment's used. īļ plan for handling and disposal of debris īļ Proposed arrangements for site supervision
  • 10. 12-Apr-18 4. SAFETY MEASURES ī‚§ Training and Communication: Demolition workers, including plant or equipment operators, shall go through proper job safety training and be informed of the potential hazards by attending training sessions as well as on-the- job training ī‚§ Equipment Maintenance: All equipment shall be tested and examined before use. They shall be properly stored and maintained. The equipment shall be inspected daily and results of the inspection shall be recorded accordingly.
  • 11. 12-Apr-18 4. SAFETY MEASURES A properly connected power source from a local electric utility supplier or a mobile electricity generator shall be utilized in demolition sites All flammable goods shall be removed from site unless they are necessary for the works involved. Any remaining flammable goods shall be stored in proper storage facilities. All furniture, timber, doors, etc. shall be removed before any welding work is performed. Fire fighting appliances shall be provided and maintained in working conditions. Electrical Safety Fire
  • 12. 12-Apr-18 DEMOLISHING SEQUENCE Demolition sequence shall be determined based on Actual site conditions, Restraints, The building layout, The Structural layout and its construction. In general, the following sequence shall apply: īą Utilities disconnection. Electricity, plumbing water lines, drainage connections etc.. īą All cantilevered structures, canopies, verandahs and features attached to the external walls shall first be demolished prior to demolition of main building and its internal structures on each floor
  • 13. 12-Apr-18 DEMOLISHING SEQUENCE īą When demolishing the roof structure, all lift machine rooms and water tanks at high level shall be demolished in “top down” sequence to the main roof level īą Demolition of the floor slabs shall begin at mid span and work towards the supporting beams. īą Floor beams shall be demolished in the order of cantilevered beams, secondary beams and then main beams. īą Non-load bearing walls shall be removed prior to demolition of load bearing walls.
  • 14. 12-Apr-18 DEMOLISHING SEQUENCE If site conditions permit, the first floor slab directly above the ground floor may be demolished by machine standing on ground.
  • 15. 12-Apr-18 FACTORS AFFECTING DEMOLISHING METHODS īą According to Kasai et al/1988/ are demolition methods classified into principles and mechanisms of breaking. īą The selection of a specific process should be based on the experience learned from the conventional demolition industry, and applicable experience from actual decommissioning programs. īą Some of the factors to affecting selection of demolishing methods are; a) Type of structure Different types of structure like load bearing masonry structure , RCC framed structure, steel structure , etc.
  • 16. 12-Apr-18 FACTORS AFFECTING DEMOLISHING METHODS b. Size of structure If the size of structure is small, hand demolition can be sufficient. for large structures and multi storied buildings special like wrecking ball method, deliberate collapse, implosion technique etc are necessary. c. Available time period d. Location of structure e. Limitation of noise, dust and vibrations f. Skill of workers g. Safety h. Availability of equipment i. Adjacent structures
  • 17. 12-Apr-18 FACTORS AFFECTING DEMOLISHING METHODS Demolishing Techniques Engineering Demolishing Mechanical method Implosion Method Deconstruction Method Non Engineering demolishing Manual demolition
  • 18. 12-Apr-18 CONTINUEDâ€Ļ Manual Methods īą This is demolishing by human operatives/hand held operations. īą Suitable for use in smaller site with congested space where larger machine cannot be employed. īą using simple electrically or pneumatically powered tools such as picks, hammers, wire cutters or hand driven hydraulic jacks etc. to carry out the demolition of individual elements. īą Tools required for manual demolition; â€ĸ Hammers â€ĸ Picks â€ĸ Wire cutters â€ĸ Welding cutters â€ĸ Hand driven hydraulic jacks etc.
  • 19. 12-Apr-18 Mechanical Methods īą Wrecking method īą Pusher arm technique īą Thermic lance technique īą Non explosive demolition īą Concrete sawing method īą Deliberate collapse method īą Pressure jetting method īą bursting Implosion Methods īą demolition of structure with the help of explosives is called as implosion CONTINUEDâ€Ļ
  • 20. 12-Apr-18 ī‚ĸ Manual methods are carried out top down, proceeding, in general, from the roof to ground. The sequence of demolition may vary, depending on ī‚— Site conditions and ī‚— Structural element to be demolished 1. MANUAL METHODS
  • 21. 12-Apr-18 1. Hand held hammering; Repeated hammering is often used to fracture and break concrete mainly due to occurring tensile and shear stress. 1. MANUAL METHODS i. Rotary-hammer ;boring holes by Rotary hammering; in concrete. They are versatile and also work well in the hammer-only mode. ii. Chipping hammer; Lightweight and hand-held, chipping hammers are perfect for breaking vertical and overhead concrete surfaces.
  • 22. 12-Apr-18 2. Hydraulic concrete crusher Hydraulic concrete crushers are used to reduce concrete into smaller, more manageable pieces. They also separate steel reinforcement from concrete. 1. MANUAL METHODS iii. Demolition hammer; Demolition hammers deliver hammering action only, unlike rotary hammers, which are used to bore holes.
  • 23. 12-Apr-18 3. Pavement breaker Pavement breakers are used in heavy concrete demolition projects because they can demolish pavements, roads, and extremely thick concrete 3. Hydraulic splitter Hydraulic splitters use lateral forces against the insides of concrete holes to break up the concrete without creating lots of noise and debris. 1. MANUAL METHODS
  • 24. 12-Apr-18 īą The sequence of demolition by machine is typically the same as the top down manual method, except that most of the demolition is done by mechanical plant 2. MECHANICAL METHODS 1. Excavator and attachments
  • 25. 12-Apr-18 2. MECHANICAL METHODS 1.1 Excavator mounted with hydraulic crasher â€ĸ The crusher attachment breaks the concrete and the reinforcement by the hydraulic thrust through the long boom arm system â€ĸ The hydraulic crusher can be operated from the ground outside the building. This method is also suitable for dangerous buildings, silos and other industrial facilities. â€ĸ The excavator shall operate on firm ground that can support the machine during the crusher operation. â€ĸ Each section of the structure shall be demolished in a top down sequence
  • 26. 12-Apr-18 1.2. Excavator mounted with A hydraulic jackhammer; ī‚ĸ Typically much larger than portable ones, may be fitted to mechanical excavators or backhoes and is widely used for roadwork, quarrying and general demolition or construction groundwork. ī‚ĸ Pneumatic breakers are simpler tools with fewer moving parts, requiring less maintenance. 2. MECHANICAL METHODS
  • 27. 12-Apr-18 īą The demolition begins with the lifting of the mechanical plant on to the building top floor. īą Adequate propping shall be installed at floor levels below the working floor to safely support the operation of the mechanical plant. īą The movement of the mechanical plant shall only be within the propped area. The propped areas shall be suitably marked. īą The mechanical plant shall be lifted onto the roof of the building by the use of mobile crane or other appropriate means as approved. īą The machine shall descend down to the next floor by means of a ramp. The ramp may be a temporary structure or other appropriate design. 2. MECHANICAL METHODS
  • 29. 12-Apr-18 2. MECHANICAL METHODS 2. Ball and crane ī‚§ This is one of the oldest and most commonly used methods for demolition. ī‚§ The wrecking ball application consists of a crane equipped with a steel ball. ī‚§ A crane uses a wrecking ball, weighing up to 6120kg, which is either dropped onto or swung into the element to be demolished. ī‚§ Concrete members can be broken into small pieces, but secondary cutting of reinforcing may be necessary.
  • 30. 12-Apr-18 2. MECHANICAL METHODS ī‚§ The destruction of the building is by the impact energy of the steel ball suspended from the crawler crane. The wrecking ball operates outside the building. ī‚§ However, the operation requires substantial clear space. The application also demands high level skill operators and well maintained equipment
  • 31. 12-Apr-18 2. MECHANICAL METHODS īą Recommended techniques for the wrecking ball operations include (1) Vertical Drop -free falling of the wrecking ball onto the structure and (2) Swing in line - swinging of the ball in-line with the jib. īą A second dragline will normally connect to the ball horizontally to control the ball motion īą The operation shall not be performed adjacent to overhead power lines. The site shall be entirely fenced off to forbid public access. īą One of the disadvantage of this method is he breakup process can cause considerable dust, vibration and noise which may be objectionable.
  • 32. 12-Apr-18 2. MECHANICAL METHODS 3. Dismantling ī‚§ Selective or complete demolition of concrete structures is possible by cutting elements and then removing them with a crane. ī‚§ The cutting process may be by sawing, water jetting or thermal lance. ī‚§ Because the surface of the cut concrete is smooth and relatively regular, these methods have particular application when the objective is partial demolition, for instance in the creation of openings in walls and slabs. Dismantling a beam
  • 33. 12-Apr-18 2. MECHANICAL METHODS Continuedâ€Ļ ī‚§ Hydro demolition uses a high pressure supersonic water jet, that penetrates the pores and cracks of the concrete and builds up an internal pressure. When this pressure exceeds the tensile strength of the concrete, the concrete breaks. ī‚§ The water jet can be used not only for cutting straight lines but also contours, a useful feature for cutting access manholes. ī‚§ A thermal lance is created by packing a seamless mild steel tube with low carbon rods and passing oxygen through the tube. Water jet cutting
  • 34. 12-Apr-18 2. MECHANICAL METHODS Continuedâ€Ļ ī‚§ While this method eliminates vibration and dust problems, it creates other hazards associated with smoke and fire danger. ī‚§ Whether sawing, jetting or lancing is used to dismantle the structure or its components, each element must be safely lowered to the ground. ī‚§ The amount of time and cost of labor are the main drawbacks. ī‚§ Toxic waste such as asbestos sheets and lead paint have no resale value so they are discarded.
  • 35. 12-Apr-18 2. MECHANICAL METHODS 4. Pressure bursting o can be used in cases where relatively quiet, dust-free, controlled demolition is preferred The cutting process may be by sawing, water jetting or thermal lance. o Both mechanical and chemical pressure bursting split the concrete, either with a splitting machine operating on hydraulic pressure provided by a motor in the case of mechanical bursting, or through the insertion of an expansive slurry into a pre-determined pattern of boreholes in the case of chemical bursting ī‚§ Both methods work by applying lateral forces against the inside of holes drilled into the concrete.
  • 36. 12-Apr-18 5. EXPLOSIVES īą Implosion is the strategic placing of explosive material and timing of its detonation so that a structure collapses on itself in a matter of seconds, minimizing the physical damage to its immediate surroundings īą The technique weakens or removes critical supports so that the building can no longer withstand the force of gravity and falls under its own weight. īą Numerous small explosives, strategically placed within the structure, are used to catalyze the collapse. Nitroglycerine, dynamite, or other explosives are used to shatter reinforced concrete supports. īą For the demolition of concrete structures it is usual to drill holes at a pre determined angle into the concrete to be removed
  • 37. 12-Apr-18 īą The holes are then charged with an explosive which is electrically detonated īą Despite its terminology, building implosion also includes the controlled demolition of other structures, such as bridges, smokestacks, towers, and tunnels īą Empirical judgment based on the skill and experience of the operator is the basis for blasting design. īą A simpler but far less effective method of blasting is to lay the explosive charge on the element to be demolished and cover it with sand bags. īą Precautions should be taken to stop flying debris and in all circumstances strict site control must be maintained to ensure the safety of workers and the general public. 5. EXPLOSIVES
  • 38. 12-Apr-18 Pre blast considerations īą The design may include pre-weakening of the structure, the strategy in placement of the explosives and time delay so that the building will collapse in a safe manner. īą Pre-weakening of the structure may include cutting out a portion of the shear walls and other structural elements īą A test blast may be conducted to verify the strength of the structural member and to fine tune the explosive design. īą Protection of the adjacent properties and habitats is also an important consideration. Concrete columns fully loaded with explosives CONTINUEDâ€Ļ
  • 39. 12-Apr-18 Test blast īą Before carrying out the actual blasting, a test blast, in ordered to ascertain the efficiency of explosive & detonators. īą The wrapping of holes can be done to ensure debris does not fly in air due to explosion of charges. Before After CONTINUEDâ€Ļ
  • 40. 12-Apr-18 5. Explosives General things ī‚§ High Risk Factor ī‚§ Time Taken ī‚§ Produce Distortion ī‚§ Expensive ī‚§ Chances of error ī‚§ Need of experts ī‚§ Error may leads to ī‚§ No demolition ī‚§ Loss of life's CONTINUEDâ€Ļ
  • 41. 12-Apr-18 īą Demolishing pre stressed concrete structures can be more difficult than demolishing reinforced concrete because of the energy stored in the pre stressing tendons. īą Pre stressing tendons are likes stretched rubber bands, with energy stored in the stretching process. īą The release of the stored energy in a rubber band causes it to sail through the air. īą The total demolition of a pre stressed pre-tensioned structure is no more difficult than the demolition of a cast-in-place reinforce concrete structure. DEMOLITION OF PRESTRESSED CONCRETE
  • 42. 12-Apr-18 īą Pre stressed pre-tensioned members are usually designed to resist applied loading in only one direction. īą Because of this, the members will fail rather easily if a force can be applied in an opposite or lateral direction īą The partial demolition of pre tensioned pre stressed structure requires more care than similar operations on a cast in place structure. DEMOLITION OF PRESTRESSED CONCRETE īą Pre-tensioned slabs and beams, or smaller dismantled portions, may be lifted and lowered to the ground as complete units (As shown in the photo). Generally, any necessary shoring and subsequent lifting should be from points near the ends of the units
  • 43. 12-Apr-18 īą Sa f e, uneventful demolition of relatively low structures using a crane and a ball has been accomplished where there is adequate surrounding work space. īą Disassembly or from - the - top -down demolition requires a large amount of shoring which must be installed along the entire length of the members, unless intermediate tendon anchors we re installed d u ring construction. īą Once shore d , the slab and beams can be de tensioned—in re verse order in which they we re tensioned. Then the slabs and beams can be demolished using those methods previously described, with the exception of the ball-and-crane method. īą The partial demolition of an un bonded post-tensioned structure can be very complicated and hazardous. If “as - built” drawings are not available, this operation can be even more complex. DEMOLITION OF PRESTRESSED CONCRETE
  • 44. 12-Apr-18 DEMOLITION OF PRESTRESSED CONCRETE īą After the shoring is in place, the tendon and reinforcing bars a re located using magnetic detection devices. īą Once this is done, careful drilling, chipping or sawing may be used to expose the pre stressing tendons (Photo B). īą The concrete can then be bro k e n with either hand-held or machine mounted breakers, or once completely severed, reduced to a size which may be lifted and lowered . īą Careful planning by competent persons experienced in post tensioning is essential before attempting partial demolition of post-tensioned structures
  • 45. 12-Apr-18 TOPIC REFERENCES 1. Christer Molin,1996 , Demolition techniques, IABSE congress report, Stockholm Sweden 2. Hal T. Hudgins, Demolition of Concrete Structures , demolition specialists Atlanta, Georgia 3. Ravi Patel , Demolition Method & Techniques, International Journal of Advanced Research in Engineering, Science and Management (IJARESM), Umrakh, Gujarat, India 4. Thomas S. LaGuardia, P.E., Concrete Decontamination And Demolition Methods, Nuclear Energy Services, Inc. Danbury, Connecticut. 5. Prof. Ankit Pate, Demolition of Structures, BITS Edu Campus 6. Martin Johansson, 2002, Handbook on Demolition with Brokk , Managing director of Brokk AB, Skellefta.