SlideShare a Scribd company logo
1 of 37
Network Planning Workshop 16 September
Workshop Summary 
The workshop held on 16 September 2014 brought together a range of organisations and experts to explore 
network planning as a possible initiative to form part of the solution for the Powering Sydney’s Future 
Project. 
Approximately 50 representatives and experts gathered to hear about the TransGrid network planning 
process and how it has been applied to the Powering Sydney’s Future project to develop and assess 
possible network infrastructure solutions. 
Workshop participants included representatives from consumer advocacy groups, academics, government 
representatives, regulators, large energy users, solution providers and other electricity networks. 
Participants were involved in interactive sessions to provide feedback on the topics discussed.
Agenda 
- Introduction 
- TransGrid’s network planning process 
- Options review process 
- Breakout discussions 
- Wrap up
Introduction 
Stephen Clark, Executive General Manager 
Network Planning & Performance
TransGrid’s role in electricity supply
Inner Sydney network
Powering Sydney’s 
Future Project 
 Maximise utilisation of assets 
 Deferral of capital expenditure 
 Just in time delivery 
 Keeping options open 
 Joint planning with Ausgrid 
 Keeping customers and 
consumers informed
Five key initiatives 
Supply 
Demand 
Population 
growth
Network planning process 
Gordon Burbidge, Consultations Manager
Joint planning process 
Ausgrid TransGrid 
Project 
implementation 
Project 
implementation 
Joint Planning Committee 
Least community cost solution
The “Planning Cycle” 
 Review of need drivers to inform decisions 
 Typically when updated forecast become available 
 Less frequently other factors such as changes to 
 Generation 
 Capability and performance of the existing network
Planning “stages” 
We are here
demand range 
A range of futures 
2500 
2000 
1500 
1000 
500 
0 
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 
MW 
existing
Option Evaluation 
 Regulatory consultation: 
 Three part process (two 
opportunities for inputs) 
 Seeking all credible options to 
maximise net market benefit 
 Selecting the “best” option
Questions
Network Planning for the Inner 
Sydney area 
Bruce Howard, Connections Planning Manager
demand range 
2500 
2000 
1500 
1000 
500 
0 
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 
MW 
existing 
The situation
Joint planning process 
Strategy 
development 
Options review 
Load sensitivity 
analysis 
TransGrid Ausgrid 
Joint planning strategy
Supply to inner Sydney
Supply to inner Sydney 
 >40 supply options 
 Sydney West BSP 
(Rookwood Rd) most 
suitable 
 Further investigation to 
optimise options
Route cost comparison 
Route options 
 Rookwood (R) 
 Sydney South (S) 
 Sydney East (E) 
 Sydney North (N)
Joint planning process 
Strategy 
development 
Options review 
Load sensitivity 
analysis 
TransGrid 
Options feasibility 
(330kv) 
Route selection (330kv) 
Ausgrid 
Retirement strategy 
132kv Replacement 
Joint planning strategy
Joint planning outcomes 
 Credible network strategies developed for supply 
to inner Sydney 
 a full 330 kV solution (Strategy ‘A’) 
 a mix of 330 kV and 132 kV solutions (strategies ‘B’ & 
‘C’) 
 a full 132 kV solution (Strategy ‘D’) 
 Strategies have 20-30 yr outlook 
 Strategies tested against different demand 
scenarios to understand cost-effectiveness of 
each
Route selection study
Strategies
Strategy evaluation 
Strategy NPV 
($m) 
NPV 
Low growth 
($m) 
Cable routes 
(km) 
Comments 
A (Full 
330kV) 
432 294 34 (34) Minimal cable routes 
Highest capability 
B (Hybrid 
1) 
417 266 42 (34) Lowest cost 
C (Hybrid 
2) 
463 266 52 (34) Higher cost 
Community disruption 
D (Full 
132kV) 
466 286 79 (60) Highest cost 
Community disruption 
Lower capability
Current preferred 
€
Questions
Single large cable 
Multiple replacements
Single large cable
Breakout discussions
Activity 1 – Evaluation 
 Facilitator 1 : What key advantages do you see 
about the infrastructure option 
 Facilitator 2 : What concerns you most about 
the infrastructure option 
 Facilitator 3 : Factors that TransGrid should 
consider in evaluating an infrastructure option
Activity 2 – Priorities 
First (Red) 
Second (Yellow) 
Third (Green)
Wrap up and closing
Next steps
Thank you 
Stay informed and 
involved through the 
project web page 
www.yoursaytransgrid 
.com.au/psf

More Related Content

What's hot

Cross border procurement of e-infrastructure services
Cross border procurement of e-infrastructure services Cross border procurement of e-infrastructure services
Cross border procurement of e-infrastructure services Helix Nebula The Science Cloud
 
Linlithgow Natural Grid_Initial Report
Linlithgow Natural Grid_Initial ReportLinlithgow Natural Grid_Initial Report
Linlithgow Natural Grid_Initial ReportChrisJCook
 
Finance & Sustainability Aggregators forum 2014
Finance & Sustainability Aggregators forum 2014Finance & Sustainability Aggregators forum 2014
Finance & Sustainability Aggregators forum 2014Europeana
 
Lars Coenen, forsker, Circle/Universitetet i Lund
Lars Coenen, forsker, Circle/Universitetet i LundLars Coenen, forsker, Circle/Universitetet i Lund
Lars Coenen, forsker, Circle/Universitetet i Lundinsam
 
Inter-modal Transport Data Sharing in Hong Kong: Use Case Development Workshop
Inter-modal Transport Data Sharing in Hong Kong: Use Case Development WorkshopInter-modal Transport Data Sharing in Hong Kong: Use Case Development Workshop
Inter-modal Transport Data Sharing in Hong Kong: Use Case Development WorkshopTRPC Pte Ltd
 
resilience.io - Cities Alliance Africa Strategy Workshop - Sept 2016
resilience.io - Cities Alliance Africa Strategy Workshop - Sept 2016resilience.io - Cities Alliance Africa Strategy Workshop - Sept 2016
resilience.io - Cities Alliance Africa Strategy Workshop - Sept 2016Ecological Sequestration Trust
 
Rachel Dunk | The ICARB Sector Workshop Programme
Rachel Dunk | The ICARB Sector Workshop ProgrammeRachel Dunk | The ICARB Sector Workshop Programme
Rachel Dunk | The ICARB Sector Workshop Programmeicarb
 
Infrastructure Seminar | The Infrastructure Systems competition scope | Harsh...
Infrastructure Seminar | The Infrastructure Systems competition scope | Harsh...Infrastructure Seminar | The Infrastructure Systems competition scope | Harsh...
Infrastructure Seminar | The Infrastructure Systems competition scope | Harsh...Invest Northern Ireland
 
BDE_SC4_WS3_4_Victor Corral - AutoMat Project
BDE_SC4_WS3_4_Victor Corral - AutoMat ProjectBDE_SC4_WS3_4_Victor Corral - AutoMat Project
BDE_SC4_WS3_4_Victor Corral - AutoMat ProjectBigData_Europe
 
Madcom offers a Broadband Feasibility Study Toolkit for Municipalities and Ec...
Madcom offers a Broadband Feasibility Study Toolkit for Municipalities and Ec...Madcom offers a Broadband Feasibility Study Toolkit for Municipalities and Ec...
Madcom offers a Broadband Feasibility Study Toolkit for Municipalities and Ec...Rich Frank
 
Green ICT in London HEIs
Green ICT in London HEIsGreen ICT in London HEIs
Green ICT in London HEIsJISC Netskills
 
Flex coop iea-meeting_berlin_okt18
Flex coop iea-meeting_berlin_okt18Flex coop iea-meeting_berlin_okt18
Flex coop iea-meeting_berlin_okt18WolfArmin
 
Mark Hudson Total Transport Pilot Fund
Mark Hudson Total Transport Pilot FundMark Hudson Total Transport Pilot Fund
Mark Hudson Total Transport Pilot FundTrapezeGroupUK
 
Qrowd transport session-bdv-forum-2018
Qrowd transport session-bdv-forum-2018Qrowd transport session-bdv-forum-2018
Qrowd transport session-bdv-forum-2018Luis Daniel Ibáñez
 
RV 2014: Space Exploration: Innovative Tools + Strategies by Mark Gander
RV 2014: Space Exploration: Innovative Tools + Strategies by Mark GanderRV 2014: Space Exploration: Innovative Tools + Strategies by Mark Gander
RV 2014: Space Exploration: Innovative Tools + Strategies by Mark GanderRail~Volution
 

What's hot (16)

Cross border procurement of e-infrastructure services
Cross border procurement of e-infrastructure services Cross border procurement of e-infrastructure services
Cross border procurement of e-infrastructure services
 
Linlithgow Natural Grid_Initial Report
Linlithgow Natural Grid_Initial ReportLinlithgow Natural Grid_Initial Report
Linlithgow Natural Grid_Initial Report
 
Finance & Sustainability Aggregators forum 2014
Finance & Sustainability Aggregators forum 2014Finance & Sustainability Aggregators forum 2014
Finance & Sustainability Aggregators forum 2014
 
Lars Coenen, forsker, Circle/Universitetet i Lund
Lars Coenen, forsker, Circle/Universitetet i LundLars Coenen, forsker, Circle/Universitetet i Lund
Lars Coenen, forsker, Circle/Universitetet i Lund
 
Inter-modal Transport Data Sharing in Hong Kong: Use Case Development Workshop
Inter-modal Transport Data Sharing in Hong Kong: Use Case Development WorkshopInter-modal Transport Data Sharing in Hong Kong: Use Case Development Workshop
Inter-modal Transport Data Sharing in Hong Kong: Use Case Development Workshop
 
resilience.io - Cities Alliance Africa Strategy Workshop - Sept 2016
resilience.io - Cities Alliance Africa Strategy Workshop - Sept 2016resilience.io - Cities Alliance Africa Strategy Workshop - Sept 2016
resilience.io - Cities Alliance Africa Strategy Workshop - Sept 2016
 
Rachel Dunk | The ICARB Sector Workshop Programme
Rachel Dunk | The ICARB Sector Workshop ProgrammeRachel Dunk | The ICARB Sector Workshop Programme
Rachel Dunk | The ICARB Sector Workshop Programme
 
Infrastructure Seminar | The Infrastructure Systems competition scope | Harsh...
Infrastructure Seminar | The Infrastructure Systems competition scope | Harsh...Infrastructure Seminar | The Infrastructure Systems competition scope | Harsh...
Infrastructure Seminar | The Infrastructure Systems competition scope | Harsh...
 
BDE_SC4_WS3_4_Victor Corral - AutoMat Project
BDE_SC4_WS3_4_Victor Corral - AutoMat ProjectBDE_SC4_WS3_4_Victor Corral - AutoMat Project
BDE_SC4_WS3_4_Victor Corral - AutoMat Project
 
Madcom offers a Broadband Feasibility Study Toolkit for Municipalities and Ec...
Madcom offers a Broadband Feasibility Study Toolkit for Municipalities and Ec...Madcom offers a Broadband Feasibility Study Toolkit for Municipalities and Ec...
Madcom offers a Broadband Feasibility Study Toolkit for Municipalities and Ec...
 
Green ICT in London HEIs
Green ICT in London HEIsGreen ICT in London HEIs
Green ICT in London HEIs
 
Thesis presentation
Thesis presentationThesis presentation
Thesis presentation
 
Flex coop iea-meeting_berlin_okt18
Flex coop iea-meeting_berlin_okt18Flex coop iea-meeting_berlin_okt18
Flex coop iea-meeting_berlin_okt18
 
Mark Hudson Total Transport Pilot Fund
Mark Hudson Total Transport Pilot FundMark Hudson Total Transport Pilot Fund
Mark Hudson Total Transport Pilot Fund
 
Qrowd transport session-bdv-forum-2018
Qrowd transport session-bdv-forum-2018Qrowd transport session-bdv-forum-2018
Qrowd transport session-bdv-forum-2018
 
RV 2014: Space Exploration: Innovative Tools + Strategies by Mark Gander
RV 2014: Space Exploration: Innovative Tools + Strategies by Mark GanderRV 2014: Space Exploration: Innovative Tools + Strategies by Mark Gander
RV 2014: Space Exploration: Innovative Tools + Strategies by Mark Gander
 

Viewers also liked

5.1 Design exercise presentation
5.1 Design exercise presentation5.1 Design exercise presentation
5.1 Design exercise presentationUtttam Kumar
 
ILRI-BMZ Project on Improving the Livelihoods of Poor Livestock-keepers in Af...
ILRI-BMZ Project on Improving the Livelihoods of Poor Livestock-keepers in Af...ILRI-BMZ Project on Improving the Livelihoods of Poor Livestock-keepers in Af...
ILRI-BMZ Project on Improving the Livelihoods of Poor Livestock-keepers in Af...ILRI
 
2013 extension inhouse review program
2013 extension inhouse review program2013 extension inhouse review program
2013 extension inhouse review programLetecia Ladera
 
Presentation for Annual Review and Planning Workshop of ndbmp - 2012
Presentation for Annual Review and Planning Workshop of  ndbmp - 2012Presentation for Annual Review and Planning Workshop of  ndbmp - 2012
Presentation for Annual Review and Planning Workshop of ndbmp - 2012Nazmul Faisal
 
Review and forward planning workshop 2012
Review and forward planning workshop 2012Review and forward planning workshop 2012
Review and forward planning workshop 2012David Carr
 
Extension (capacity development, knowledge management and linkages) research ...
Extension (capacity development, knowledge management and linkages) research ...Extension (capacity development, knowledge management and linkages) research ...
Extension (capacity development, knowledge management and linkages) research ...ILRI
 
Promoting Agri-based Entrepreneurship through PCAARRD Extension Modalities
Promoting Agri-based Entrepreneurship through PCAARRD Extension ModalitiesPromoting Agri-based Entrepreneurship through PCAARRD Extension Modalities
Promoting Agri-based Entrepreneurship through PCAARRD Extension ModalitiesAgricultural Training Institute
 
Effective Strategic Planning Workshop
Effective Strategic Planning WorkshopEffective Strategic Planning Workshop
Effective Strategic Planning WorkshopCyber Sari-Sari
 

Viewers also liked (10)

5.1 Design exercise presentation
5.1 Design exercise presentation5.1 Design exercise presentation
5.1 Design exercise presentation
 
ILRI-BMZ Project on Improving the Livelihoods of Poor Livestock-keepers in Af...
ILRI-BMZ Project on Improving the Livelihoods of Poor Livestock-keepers in Af...ILRI-BMZ Project on Improving the Livelihoods of Poor Livestock-keepers in Af...
ILRI-BMZ Project on Improving the Livelihoods of Poor Livestock-keepers in Af...
 
2013 extension inhouse review program
2013 extension inhouse review program2013 extension inhouse review program
2013 extension inhouse review program
 
Presentation for Annual Review and Planning Workshop of ndbmp - 2012
Presentation for Annual Review and Planning Workshop of  ndbmp - 2012Presentation for Annual Review and Planning Workshop of  ndbmp - 2012
Presentation for Annual Review and Planning Workshop of ndbmp - 2012
 
Review and forward planning workshop 2012
Review and forward planning workshop 2012Review and forward planning workshop 2012
Review and forward planning workshop 2012
 
Extension (capacity development, knowledge management and linkages) research ...
Extension (capacity development, knowledge management and linkages) research ...Extension (capacity development, knowledge management and linkages) research ...
Extension (capacity development, knowledge management and linkages) research ...
 
Promoting Agri-based Entrepreneurship through PCAARRD Extension Modalities
Promoting Agri-based Entrepreneurship through PCAARRD Extension ModalitiesPromoting Agri-based Entrepreneurship through PCAARRD Extension Modalities
Promoting Agri-based Entrepreneurship through PCAARRD Extension Modalities
 
Farm Tourism in Organic Agriculture
Farm Tourism in Organic AgricultureFarm Tourism in Organic Agriculture
Farm Tourism in Organic Agriculture
 
Strategic Planning Workshop
Strategic Planning WorkshopStrategic Planning Workshop
Strategic Planning Workshop
 
Effective Strategic Planning Workshop
Effective Strategic Planning WorkshopEffective Strategic Planning Workshop
Effective Strategic Planning Workshop
 

Similar to Network Planning Workshop - Powering Sydney

Powering sydneys future workshop
Powering sydneys future workshopPowering sydneys future workshop
Powering sydneys future workshopTransGrid AU
 
Efficiency Based Comparison of Project Delivery Methods
Efficiency Based Comparison of Project Delivery MethodsEfficiency Based Comparison of Project Delivery Methods
Efficiency Based Comparison of Project Delivery MethodsRajnish Lekhi M.S, LEED GA
 
Powering Sydney's Future Forum June 2014 - Network Planning - Bruce Howard
Powering Sydney's Future Forum June 2014 - Network Planning - Bruce HowardPowering Sydney's Future Forum June 2014 - Network Planning - Bruce Howard
Powering Sydney's Future Forum June 2014 - Network Planning - Bruce HowardTransGrid AU
 
TransGrid deliberative forums
TransGrid deliberative forumsTransGrid deliberative forums
TransGrid deliberative forumsTransGrid AU
 
B-IoT based Green Technology Solutions to Control Pollution by Tracing Carbon...
B-IoT based Green Technology Solutions to Control Pollution by Tracing Carbon...B-IoT based Green Technology Solutions to Control Pollution by Tracing Carbon...
B-IoT based Green Technology Solutions to Control Pollution by Tracing Carbon...Darniss
 
Demand Response workshop - Powering Sydney
Demand Response workshop - Powering SydneyDemand Response workshop - Powering Sydney
Demand Response workshop - Powering SydneyTransGrid AU
 
20131127 Presentation - TransGrid Deliberative Forums
20131127   Presentation - TransGrid Deliberative Forums20131127   Presentation - TransGrid Deliberative Forums
20131127 Presentation - TransGrid Deliberative ForumsTransGrid AU
 
Lessons Learned from Global Megaprojects including Sydney Light Rail, Crossra...
Lessons Learned from Global Megaprojects including Sydney Light Rail, Crossra...Lessons Learned from Global Megaprojects including Sydney Light Rail, Crossra...
Lessons Learned from Global Megaprojects including Sydney Light Rail, Crossra...LogiKal Projects
 
2022 GATF Annual Meeting - Item 7.5 - Sustainable Infrastructure Programme in...
2022 GATF Annual Meeting - Item 7.5 - Sustainable Infrastructure Programme in...2022 GATF Annual Meeting - Item 7.5 - Sustainable Infrastructure Programme in...
2022 GATF Annual Meeting - Item 7.5 - Sustainable Infrastructure Programme in...OECD Environment
 
Sense of Place - National Grid Guidance.pdf
Sense of Place - National Grid Guidance.pdfSense of Place - National Grid Guidance.pdf
Sense of Place - National Grid Guidance.pdfSAID MASHATE
 
Presentation - Consumer Engagement - 30 September 2013
Presentation - Consumer Engagement - 30 September 2013Presentation - Consumer Engagement - 30 September 2013
Presentation - Consumer Engagement - 30 September 2013TransGrid AU
 
Flexibility needs at system level and how RD&I projects are leveraging these ...
Flexibility needs at system level and how RD&I projects are leveraging these ...Flexibility needs at system level and how RD&I projects are leveraging these ...
Flexibility needs at system level and how RD&I projects are leveraging these ...Leonardo ENERGY
 
Final_year_presentation_1.pptx
Final_year_presentation_1.pptxFinal_year_presentation_1.pptx
Final_year_presentation_1.pptxBuddyGeneral
 
TransGrid consumer advisory panel
TransGrid consumer advisory panelTransGrid consumer advisory panel
TransGrid consumer advisory panelTransGrid AU
 
Optimizing Your Supply Chain with the Neo4j Graph
Optimizing Your Supply Chain with the Neo4j GraphOptimizing Your Supply Chain with the Neo4j Graph
Optimizing Your Supply Chain with the Neo4j GraphNeo4j
 
Managing Smart Grids, Power System Networks with Analytics
Managing Smart Grids, Power System Networks with Analytics Managing Smart Grids, Power System Networks with Analytics
Managing Smart Grids, Power System Networks with Analytics HIMADRI BANERJI
 

Similar to Network Planning Workshop - Powering Sydney (20)

Powering sydneys future workshop
Powering sydneys future workshopPowering sydneys future workshop
Powering sydneys future workshop
 
Efficiency Based Comparison of Project Delivery Methods
Efficiency Based Comparison of Project Delivery MethodsEfficiency Based Comparison of Project Delivery Methods
Efficiency Based Comparison of Project Delivery Methods
 
Powering Sydney's Future Forum June 2014 - Network Planning - Bruce Howard
Powering Sydney's Future Forum June 2014 - Network Planning - Bruce HowardPowering Sydney's Future Forum June 2014 - Network Planning - Bruce Howard
Powering Sydney's Future Forum June 2014 - Network Planning - Bruce Howard
 
TransGrid deliberative forums
TransGrid deliberative forumsTransGrid deliberative forums
TransGrid deliberative forums
 
B-IoT based Green Technology Solutions to Control Pollution by Tracing Carbon...
B-IoT based Green Technology Solutions to Control Pollution by Tracing Carbon...B-IoT based Green Technology Solutions to Control Pollution by Tracing Carbon...
B-IoT based Green Technology Solutions to Control Pollution by Tracing Carbon...
 
Demand Response workshop - Powering Sydney
Demand Response workshop - Powering SydneyDemand Response workshop - Powering Sydney
Demand Response workshop - Powering Sydney
 
20131127 Presentation - TransGrid Deliberative Forums
20131127   Presentation - TransGrid Deliberative Forums20131127   Presentation - TransGrid Deliberative Forums
20131127 Presentation - TransGrid Deliberative Forums
 
Lessons Learned from Global Megaprojects including Sydney Light Rail, Crossra...
Lessons Learned from Global Megaprojects including Sydney Light Rail, Crossra...Lessons Learned from Global Megaprojects including Sydney Light Rail, Crossra...
Lessons Learned from Global Megaprojects including Sydney Light Rail, Crossra...
 
2022 GATF Annual Meeting - Item 7.5 - Sustainable Infrastructure Programme in...
2022 GATF Annual Meeting - Item 7.5 - Sustainable Infrastructure Programme in...2022 GATF Annual Meeting - Item 7.5 - Sustainable Infrastructure Programme in...
2022 GATF Annual Meeting - Item 7.5 - Sustainable Infrastructure Programme in...
 
Sense of Place - National Grid Guidance.pdf
Sense of Place - National Grid Guidance.pdfSense of Place - National Grid Guidance.pdf
Sense of Place - National Grid Guidance.pdf
 
Presentation - Consumer Engagement - 30 September 2013
Presentation - Consumer Engagement - 30 September 2013Presentation - Consumer Engagement - 30 September 2013
Presentation - Consumer Engagement - 30 September 2013
 
SGIP August 15, 2013 eMeeting - State of the Union
SGIP August 15, 2013 eMeeting - State of the UnionSGIP August 15, 2013 eMeeting - State of the Union
SGIP August 15, 2013 eMeeting - State of the Union
 
Griha
GrihaGriha
Griha
 
Flexibility needs at system level and how RD&I projects are leveraging these ...
Flexibility needs at system level and how RD&I projects are leveraging these ...Flexibility needs at system level and how RD&I projects are leveraging these ...
Flexibility needs at system level and how RD&I projects are leveraging these ...
 
Final_year_presentation_1.pptx
Final_year_presentation_1.pptxFinal_year_presentation_1.pptx
Final_year_presentation_1.pptx
 
TransGrid consumer advisory panel
TransGrid consumer advisory panelTransGrid consumer advisory panel
TransGrid consumer advisory panel
 
AURA: Asset Management & Decision Support Systems
AURA: Asset Management & Decision Support SystemsAURA: Asset Management & Decision Support Systems
AURA: Asset Management & Decision Support Systems
 
Optimizing Your Supply Chain with the Neo4j Graph
Optimizing Your Supply Chain with the Neo4j GraphOptimizing Your Supply Chain with the Neo4j Graph
Optimizing Your Supply Chain with the Neo4j Graph
 
GreenTree_Capacity Statement-2016-17
GreenTree_Capacity Statement-2016-17GreenTree_Capacity Statement-2016-17
GreenTree_Capacity Statement-2016-17
 
Managing Smart Grids, Power System Networks with Analytics
Managing Smart Grids, Power System Networks with Analytics Managing Smart Grids, Power System Networks with Analytics
Managing Smart Grids, Power System Networks with Analytics
 

More from TransGrid AU

Unlocking Australia's Renewable Energy Future
Unlocking Australia's Renewable Energy Future Unlocking Australia's Renewable Energy Future
Unlocking Australia's Renewable Energy Future TransGrid AU
 
All Energy 2017_TransGrid
All Energy 2017_TransGridAll Energy 2017_TransGrid
All Energy 2017_TransGridTransGrid AU
 
Power Safety System Rules: Revisions effective in version 5.3
Power Safety System Rules: Revisions effective in  version 5.3Power Safety System Rules: Revisions effective in  version 5.3
Power Safety System Rules: Revisions effective in version 5.3TransGrid AU
 
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...TransGrid AU
 
New regulation for a new energy system: Australian Clean Energy Summit 2017
New regulation for a new energy system: Australian Clean Energy Summit 2017New regulation for a new energy system: Australian Clean Energy Summit 2017
New regulation for a new energy system: Australian Clean Energy Summit 2017TransGrid AU
 
Local Energy & Microgrids Conference 2016
Local Energy & Microgrids Conference  2016 Local Energy & Microgrids Conference  2016
Local Energy & Microgrids Conference 2016 TransGrid AU
 
CommsDay 2016 Sydney Summit
CommsDay 2016 Sydney SummitCommsDay 2016 Sydney Summit
CommsDay 2016 Sydney SummitTransGrid AU
 
TransGrid's Renewable Energy Hub
TransGrid's Renewable Energy Hub TransGrid's Renewable Energy Hub
TransGrid's Renewable Energy Hub TransGrid AU
 
Electricity Storage Forum 2016
Electricity Storage Forum 2016Electricity Storage Forum 2016
Electricity Storage Forum 2016TransGrid AU
 
150819 Reliability Webinar presentation
150819 Reliability Webinar presentation150819 Reliability Webinar presentation
150819 Reliability Webinar presentationTransGrid AU
 
TransGrid Energy Storage Australia 2015
TransGrid Energy Storage Australia 2015TransGrid Energy Storage Australia 2015
TransGrid Energy Storage Australia 2015TransGrid AU
 
2015 TAPR Forum Presentation
2015 TAPR Forum Presentation2015 TAPR Forum Presentation
2015 TAPR Forum PresentationTransGrid AU
 
Webinar - December Revenue Proposal Update
Webinar - December Revenue Proposal UpdateWebinar - December Revenue Proposal Update
Webinar - December Revenue Proposal UpdateTransGrid AU
 
Powering Sydney's Future - end of year briefing
Powering Sydney's Future - end of year briefing Powering Sydney's Future - end of year briefing
Powering Sydney's Future - end of year briefing TransGrid AU
 
TransGrid's December 2014 Engagement Workshop
TransGrid's December 2014 Engagement WorkshopTransGrid's December 2014 Engagement Workshop
TransGrid's December 2014 Engagement WorkshopTransGrid AU
 
141208 AER Public Forum - TransGrid Revenue Proposal
141208 AER Public Forum - TransGrid Revenue Proposal141208 AER Public Forum - TransGrid Revenue Proposal
141208 AER Public Forum - TransGrid Revenue ProposalTransGrid AU
 
Local Generation Workshop - Powering Sydney
Local Generation Workshop - Powering SydneyLocal Generation Workshop - Powering Sydney
Local Generation Workshop - Powering SydneyTransGrid AU
 
Energy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering SydneyEnergy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering SydneyTransGrid AU
 
Technology Trialing - TransGrid's 2014 Demand Management Innovation Forum
Technology Trialing - TransGrid's 2014 Demand Management Innovation ForumTechnology Trialing - TransGrid's 2014 Demand Management Innovation Forum
Technology Trialing - TransGrid's 2014 Demand Management Innovation ForumTransGrid AU
 
Market Development and Understanding - 2014 Demand Management Innovation Forum
Market Development and Understanding - 2014 Demand Management Innovation ForumMarket Development and Understanding - 2014 Demand Management Innovation Forum
Market Development and Understanding - 2014 Demand Management Innovation ForumTransGrid AU
 

More from TransGrid AU (20)

Unlocking Australia's Renewable Energy Future
Unlocking Australia's Renewable Energy Future Unlocking Australia's Renewable Energy Future
Unlocking Australia's Renewable Energy Future
 
All Energy 2017_TransGrid
All Energy 2017_TransGridAll Energy 2017_TransGrid
All Energy 2017_TransGrid
 
Power Safety System Rules: Revisions effective in version 5.3
Power Safety System Rules: Revisions effective in  version 5.3Power Safety System Rules: Revisions effective in  version 5.3
Power Safety System Rules: Revisions effective in version 5.3
 
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...
 
New regulation for a new energy system: Australian Clean Energy Summit 2017
New regulation for a new energy system: Australian Clean Energy Summit 2017New regulation for a new energy system: Australian Clean Energy Summit 2017
New regulation for a new energy system: Australian Clean Energy Summit 2017
 
Local Energy & Microgrids Conference 2016
Local Energy & Microgrids Conference  2016 Local Energy & Microgrids Conference  2016
Local Energy & Microgrids Conference 2016
 
CommsDay 2016 Sydney Summit
CommsDay 2016 Sydney SummitCommsDay 2016 Sydney Summit
CommsDay 2016 Sydney Summit
 
TransGrid's Renewable Energy Hub
TransGrid's Renewable Energy Hub TransGrid's Renewable Energy Hub
TransGrid's Renewable Energy Hub
 
Electricity Storage Forum 2016
Electricity Storage Forum 2016Electricity Storage Forum 2016
Electricity Storage Forum 2016
 
150819 Reliability Webinar presentation
150819 Reliability Webinar presentation150819 Reliability Webinar presentation
150819 Reliability Webinar presentation
 
TransGrid Energy Storage Australia 2015
TransGrid Energy Storage Australia 2015TransGrid Energy Storage Australia 2015
TransGrid Energy Storage Australia 2015
 
2015 TAPR Forum Presentation
2015 TAPR Forum Presentation2015 TAPR Forum Presentation
2015 TAPR Forum Presentation
 
Webinar - December Revenue Proposal Update
Webinar - December Revenue Proposal UpdateWebinar - December Revenue Proposal Update
Webinar - December Revenue Proposal Update
 
Powering Sydney's Future - end of year briefing
Powering Sydney's Future - end of year briefing Powering Sydney's Future - end of year briefing
Powering Sydney's Future - end of year briefing
 
TransGrid's December 2014 Engagement Workshop
TransGrid's December 2014 Engagement WorkshopTransGrid's December 2014 Engagement Workshop
TransGrid's December 2014 Engagement Workshop
 
141208 AER Public Forum - TransGrid Revenue Proposal
141208 AER Public Forum - TransGrid Revenue Proposal141208 AER Public Forum - TransGrid Revenue Proposal
141208 AER Public Forum - TransGrid Revenue Proposal
 
Local Generation Workshop - Powering Sydney
Local Generation Workshop - Powering SydneyLocal Generation Workshop - Powering Sydney
Local Generation Workshop - Powering Sydney
 
Energy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering SydneyEnergy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering Sydney
 
Technology Trialing - TransGrid's 2014 Demand Management Innovation Forum
Technology Trialing - TransGrid's 2014 Demand Management Innovation ForumTechnology Trialing - TransGrid's 2014 Demand Management Innovation Forum
Technology Trialing - TransGrid's 2014 Demand Management Innovation Forum
 
Market Development and Understanding - 2014 Demand Management Innovation Forum
Market Development and Understanding - 2014 Demand Management Innovation ForumMarket Development and Understanding - 2014 Demand Management Innovation Forum
Market Development and Understanding - 2014 Demand Management Innovation Forum
 

Recently uploaded

High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service MumbaiHigh Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbaisonalikaur4
 
WORLD CREATIVITY AND INNOVATION DAY 2024.
WORLD CREATIVITY AND INNOVATION DAY 2024.WORLD CREATIVITY AND INNOVATION DAY 2024.
WORLD CREATIVITY AND INNOVATION DAY 2024.Christina Parmionova
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27JSchaus & Associates
 
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfYHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfyalehistoricalreview
 
Club of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationClub of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationEnergy for One World
 
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up NumberMs Riya
 
productionpost-productiondiary-240320114322-5004daf6.pptx
productionpost-productiondiary-240320114322-5004daf6.pptxproductionpost-productiondiary-240320114322-5004daf6.pptx
productionpost-productiondiary-240320114322-5004daf6.pptxHenryBriggs2
 
Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Christina Parmionova
 
Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Christina Parmionova
 
Start Donating your Old Clothes to Poor People kurnool
Start Donating your Old Clothes to Poor People kurnoolStart Donating your Old Clothes to Poor People kurnool
Start Donating your Old Clothes to Poor People kurnoolSERUDS INDIA
 
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…nishakur201
 
Call Girls Rohini Delhi reach out to us at ☎ 9711199012
Call Girls Rohini Delhi reach out to us at ☎ 9711199012Call Girls Rohini Delhi reach out to us at ☎ 9711199012
Call Girls Rohini Delhi reach out to us at ☎ 9711199012rehmti665
 
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service BangaloreCall Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalorenarwatsonia7
 
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...ResolutionFoundation
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28JSchaus & Associates
 
Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Christina Parmionova
 
2024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 262024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 26JSchaus & Associates
 
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...ankitnayak356677
 

Recently uploaded (20)

The Federal Budget and Health Care Policy
The Federal Budget and Health Care PolicyThe Federal Budget and Health Care Policy
The Federal Budget and Health Care Policy
 
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service MumbaiHigh Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
 
WORLD CREATIVITY AND INNOVATION DAY 2024.
WORLD CREATIVITY AND INNOVATION DAY 2024.WORLD CREATIVITY AND INNOVATION DAY 2024.
WORLD CREATIVITY AND INNOVATION DAY 2024.
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27
 
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfYHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
 
Club of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationClub of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological Civilization
 
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
 
productionpost-productiondiary-240320114322-5004daf6.pptx
productionpost-productiondiary-240320114322-5004daf6.pptxproductionpost-productiondiary-240320114322-5004daf6.pptx
productionpost-productiondiary-240320114322-5004daf6.pptx
 
Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...
 
Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.
 
Start Donating your Old Clothes to Poor People kurnool
Start Donating your Old Clothes to Poor People kurnoolStart Donating your Old Clothes to Poor People kurnool
Start Donating your Old Clothes to Poor People kurnool
 
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
 
Call Girls Rohini Delhi reach out to us at ☎ 9711199012
Call Girls Rohini Delhi reach out to us at ☎ 9711199012Call Girls Rohini Delhi reach out to us at ☎ 9711199012
Call Girls Rohini Delhi reach out to us at ☎ 9711199012
 
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service BangaloreCall Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
 
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28
 
Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.
 
2024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 262024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 26
 
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
 
Model Town (Delhi) 9953330565 Escorts, Call Girls Services
Model Town (Delhi)  9953330565 Escorts, Call Girls ServicesModel Town (Delhi)  9953330565 Escorts, Call Girls Services
Model Town (Delhi) 9953330565 Escorts, Call Girls Services
 

Network Planning Workshop - Powering Sydney

  • 2. Workshop Summary The workshop held on 16 September 2014 brought together a range of organisations and experts to explore network planning as a possible initiative to form part of the solution for the Powering Sydney’s Future Project. Approximately 50 representatives and experts gathered to hear about the TransGrid network planning process and how it has been applied to the Powering Sydney’s Future project to develop and assess possible network infrastructure solutions. Workshop participants included representatives from consumer advocacy groups, academics, government representatives, regulators, large energy users, solution providers and other electricity networks. Participants were involved in interactive sessions to provide feedback on the topics discussed.
  • 3. Agenda - Introduction - TransGrid’s network planning process - Options review process - Breakout discussions - Wrap up
  • 4. Introduction Stephen Clark, Executive General Manager Network Planning & Performance
  • 5. TransGrid’s role in electricity supply
  • 7. Powering Sydney’s Future Project  Maximise utilisation of assets  Deferral of capital expenditure  Just in time delivery  Keeping options open  Joint planning with Ausgrid  Keeping customers and consumers informed
  • 8. Five key initiatives Supply Demand Population growth
  • 9. Network planning process Gordon Burbidge, Consultations Manager
  • 10. Joint planning process Ausgrid TransGrid Project implementation Project implementation Joint Planning Committee Least community cost solution
  • 11. The “Planning Cycle”  Review of need drivers to inform decisions  Typically when updated forecast become available  Less frequently other factors such as changes to  Generation  Capability and performance of the existing network
  • 13. demand range A range of futures 2500 2000 1500 1000 500 0 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 MW existing
  • 14. Option Evaluation  Regulatory consultation:  Three part process (two opportunities for inputs)  Seeking all credible options to maximise net market benefit  Selecting the “best” option
  • 16. Network Planning for the Inner Sydney area Bruce Howard, Connections Planning Manager
  • 17. demand range 2500 2000 1500 1000 500 0 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 MW existing The situation
  • 18. Joint planning process Strategy development Options review Load sensitivity analysis TransGrid Ausgrid Joint planning strategy
  • 19. Supply to inner Sydney
  • 20. Supply to inner Sydney  >40 supply options  Sydney West BSP (Rookwood Rd) most suitable  Further investigation to optimise options
  • 21. Route cost comparison Route options  Rookwood (R)  Sydney South (S)  Sydney East (E)  Sydney North (N)
  • 22. Joint planning process Strategy development Options review Load sensitivity analysis TransGrid Options feasibility (330kv) Route selection (330kv) Ausgrid Retirement strategy 132kv Replacement Joint planning strategy
  • 23. Joint planning outcomes  Credible network strategies developed for supply to inner Sydney  a full 330 kV solution (Strategy ‘A’)  a mix of 330 kV and 132 kV solutions (strategies ‘B’ & ‘C’)  a full 132 kV solution (Strategy ‘D’)  Strategies have 20-30 yr outlook  Strategies tested against different demand scenarios to understand cost-effectiveness of each
  • 26. Strategy evaluation Strategy NPV ($m) NPV Low growth ($m) Cable routes (km) Comments A (Full 330kV) 432 294 34 (34) Minimal cable routes Highest capability B (Hybrid 1) 417 266 42 (34) Lowest cost C (Hybrid 2) 463 266 52 (34) Higher cost Community disruption D (Full 132kV) 466 286 79 (60) Highest cost Community disruption Lower capability
  • 29.
  • 30. Single large cable Multiple replacements
  • 33. Activity 1 – Evaluation  Facilitator 1 : What key advantages do you see about the infrastructure option  Facilitator 2 : What concerns you most about the infrastructure option  Facilitator 3 : Factors that TransGrid should consider in evaluating an infrastructure option
  • 34. Activity 2 – Priorities First (Red) Second (Yellow) Third (Green)
  • 35. Wrap up and closing
  • 37. Thank you Stay informed and involved through the project web page www.yoursaytransgrid .com.au/psf

Editor's Notes

  1. TransGrid’s overall network and focus on the significance of the inner Sydney network
  2. Sydney is an area of critical economic importance. The map is an excerpt from a PWC report on the location of economic activity in Australia. Sydney CBD generated $64 b of Gross Product in 2012/13 and just 1 square metre of land in Sydney’s CBD generates $15k of economic output. - The seven LGAs that are in the inner Sydney area for the Powering Sydney’s Future project consist of approximately 650k residents and generate aprox  770k jobs and $125b of economic activity or 27.4% of NSW’s Gross State Product. The provision of a reliable supply to Inner Sydney is perhaps TransGrid and Ausgrid’s most critical responsibility. Any interruption will affect: Gas. Water, Telecommunications, Road and Traffic control and Fuel Supply Hospitals, the ASX, Sydney Airport, Port Botany, major road tunnels, Sydney railways -Any interruption to the supply to this heavily populated area will result in enormous inconvenience and any prolonged interruption in just not acceptable.
  3. Parts of the existing network supplying the inner Sydney area are approaching the end of their service life and we need to start planning now for the future. Much of the infrastructure was built in the 50s and 60s when the network was established Planning inner Sydney’s future electricity network provides an opportunity to consider a range of initiatives. Project concurrently investigating multiple initiatives to develop a progressive and cost-effective solution.
  4. Explain why we are looking at these different initiatives. Explain benefits of deferring large investments. Touch on each initiative and explain that no specific decision on a solution has been made. Builder of last resort: ongoing testing/review of underlying assumptions and solutions allows more responsiveness to changing environment.
  5. Network planning is really only applied common sense. 1. Identify a need (generally an expected inability to meet NSW reliability obligations) 2. Develop and evaluate options 3. Select the best option Then move to “Implementation” Underpinned by “prudent” practices. Use the most up to date information when making decisions Don’t make a commitment until necessary (keep your options open) Review things as circumstances change (typically forecasts, but can be other things such as generation retirements and/or new generation) Consider uncertainty (consider different possible futures) Balance of the presentation touches on these aspects
  6. Well established and longstanding process Decisions not affected by “artificial” boundaries Helps understand holistic aspects/impacts The representatives from both Ausgrid and TransGrid work as a Joint Planning Committee to identify requirements and develop options for ensuring a reliable supply to the Ausgrid supply area – especially the Inner Sydney area. The JPC looks for solutions with the Least Community Cost in terms of cost, environmental impact and inconvenience to the community during construction. Decisions are not influenced by considerations of which organisation will be responsible for implementing the recommendations.
  7. Triggers of reviews can be changes anywhere in the electricity supply chain (generation – network – loads). Reviews typically occur when updated forecasts become available (the “load” end of the supply chain). Typically forecasts are updated annually, leading to an annual planning cycle. Reviews can also be prompted by other things such as changes to network capability or generation (the other two supply chain components). “As required” basis.
  8. The four steps, although the titles are slightly different. We are presently at the second stage (option identification). In addition of the above planning process, annual planning cycles and revised forecast data is analysed to review the need of each project.
  9. “Existing” should be “network capability”. The objective is not to “get the forecast right”. Rather it is to test how robust the “ranking” of the options being considered is to changes in “needs date”. Upper is Ausgrid forecast (need in the near term) Lower is “no nett growth” (need in the longer term). The assumption was that factors which decrease demand on the network (energy efficiency, PV generation) are balanced by factors which increase demand (primarily population growth).
  10. Before handing over to Bruce, I would like to touch on the next stage of the process, Option Selection. This includes a regulatory consultation process which includes applying the AER’s RIT-T. It is a public process to demonstrate: There is a need to do something A reasonable range of options have been considered The “best” option has been selected The RIT-T is an economic (cost/benefit) analysis. The preferred option under the RIT-T is the credible option that maximises the net market benefit taking into account the direct cost of the option and the market benefits arising from that option. Effectively “least community cost”.
  11. A high level desktop assessment was completed in 2012 to assess feasible options for a third 330kV electricity supply into the Sydney Metropolitan CBD originating from each of the four Bulk Supply Points (BSP’s) surrounding the greater Sydney Metropolitan area.
  12. The assessment considered, but was not limited to, the cost, timing of activities, environmental and social issues, key risks and the practicality of being able to carry out the works. Over fourty potential supply options (including a range of overhead, overhead/trench, trench, overhead/trench/tunnel, tunnel and trench/tunnel combinations) into the Sydney Metropolitan CBD from the four BSPs were identified. These potential supply options were then individually assessed and if not considered feasible were rejected. All remaining 25 feasible supply options were then put through a Multi-Criteria Analysis (MCA) to evaluate and compare the range of viable supply options from each BSP. The assessment identified that the third point of supply for the Sydney Metropolitan CBD area should be sourced from the Sydney West (Rookwood Rd) BSP to the as all of the supply options out this BSP have either the highest Relative Benefit Index score or are the least cost. Only the full tunnel supply options from the North and East BSP’s share this ranking but are at significantly higher cost. Further investigations were therefore focused on the next level of detail to determine the optimum route and construction mode combinations out of Sydney West (Rookwood Rd) BSP.
  13. The assessment considered, but was not limited to, the cost, timing of activities, environmental and social issues, key risks and the practicality of being able to carry out the works. Over fourty potential supply options (including a range of overhead, overhead/trench, trench, overhead/trench/tunnel, tunnel and trench/tunnel combinations) into the Sydney Metropolitan CBD from the four BSPs were identified. These potential supply options were then individually assessed and if not considered feasible were rejected. All remaining 25 feasible supply options were then put through a Multi-Criteria Analysis (MCA) to evaluate and compare the range of viable supply options from each BSP. The assessment identified that the third point of supply for the Sydney Metropolitan CBD area should be sourced from the Sydney West (Rookwood Rd) BSP to the as all of the supply options out this BSP have either the highest Relative Benefit Index score or are the least cost. Only the full tunnel supply options from the North and East BSP’s share this ranking but are at significantly higher cost. Further investigations were therefore focused on the next level of detail to determine the optimum route and construction mode combinations out of Sydney West (Rookwood Rd) BSP.
  14. Strategies developed through joint planning with Ausgrid over the past 5-7 years. All strategies have been developed to provide adequate supply to the study area. Many different options considered within each strategy and these continue to evolve and be optimised as new relevant data becomes available.
  15. A Route Selection Report was prepared to investigate route and mode options (ie. provision of a transmission network connection using trenched, tunnel or overhead infrastructure) for a potential future transmission supply between the Sydney West (Rookwood Rd) Substation and the Beaconsfield West Substation (in the inner Sydney area). An initial screening was conducted to identify a preliminary list of potential route options. The initial screening applied a series of guiding principles consistent with those in the earlier options feasibility study and was also supported by a series of constraints maps developed from publicly-available information. Based on the initial screening the following options were identified for further evaluation: - fourteen trenched route options; - ten hybrid route options (involving a combination of any or all of trenched, tunnel or overhead modes);   These options were comparatively evaluated and narrowed down to a short-list of options using a risk analysis approach that considered: - engineering implications; - cost implications; - environmental and land use implications; potential community and stakeholder response; and program implications. TransGrid has not yet made a financial commitment to developing a new transmission supply between the Sydney West (Rookwood Rd) Substation and the Beaconsfield West Substation and is currently also investigating several alternative non-network initiatives (e.g. demand response) that could defer or avoid the need to build a new underground cable. It is anticipated that the planning for a new transmission supply between the Sydney West (Rookwood Rd) Substation and the Beaconsfield West Substation will continue to progress to ensure a network solution can be delivered in time if needed. The preferred route will undergo detailed design and be refined through consultation with the community, local government and other interested parties.
  16. Provide info about other strategies and approximate number of options considered within each. Can use some of the previous graphs from introductory forum (see slides below) Provide context on long-term strategy objectives associated with 330KV supply from Rookwood to Beaconsfield (applicable to all strategies) TransGrid will continue to monitor drivers on electricity demand in the region, and continue to adjust demand forecasts and network planning decisions accordingly. Non-network support Importantly, for each network strategy, the procurement of economic network support could be used as a non-network alternative to defer the need for network investment (e.g. demand response and demand management initiatives). These non-network support initiatives will be the focus of separate workshops and will not be delved further in today’s workshop.
  17. NPV costs are for the ultimate development to 2030’s 10% discount rate has been assumed (under lower discount rate, 330kV options fare even more favourably) The first 3 strategies all share the same initial development (ie. 330kV cable from Rookwood to Beaconsfield) Each 330kV easement gives approximately 2 x 680 = 1360MW capability. Each 132kV easement gives approximately 2 x 225 = 250MW capability. Easement lengths would be reduced under low growth scenario (figures in parenthesis)
  18. -Early engagement: already commenced (local councils, this forum, other key stakeholders); reaching out to community next -Options Review: ongoing investigations on all initiatives, with a RIT-T process commencing this year. - The next stages are dependent on revised forecast data that is expected in the next two months -Network Support Market Development: to develop market interest; RFPs -Environmental Assessment for cable option: critical to ensure a new cable (network infrastructure) remains an option. Will involve finalising cable route and submitting Preliminary Environmental Assessment (timing- after RIT-T has commenced this year) NO INVESTMENT DECISION MADE
  19. Many thanks for your feedback today. Webpage will be regularly updated. Today’s presentations will be available on the website in the next few days. Welcome feedback and will tailor engagement approach to address specific needs.