SlideShare a Scribd company logo
1 of 77
Recovery of Gladstone Gate
1 Description
2 Initial Concept
3 Solution
4 Refining Solution
5 Design Method
6 Fabrication
7 Lift
8 Lessons Learned
9 Questions & Answers
Introduction
Recovery of Gladstone Gate
• The gate was subsequently recovered & put in temporary
storage
• Temporary measures to bring port back into operation
• The gate was damaged & required repairing
• Removal from the dock was required
• Solution for gate removal from the dock to be developed
In January 2004 operations at the Port of Liverpool were
brought to a halt, when, during a storm one of the lock
gates at Gladstone dock was ripped from its hinges.
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Height 17 600 mm
Breadth 21 952 mm
Depth 2 400 mm
Weight 393 tonnes
Details of Gate`
Recovery of Gladstone Gate
Gladstone Dock Gate
London Bus
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Initial Concept
Initial feasibility undertaken by MDHC
Options considered
•Conventional repair using dry dock
•Conventional lift of gate using crane
•Tipping cradle
Recovery of Gladstone Gate
Conventional repair using dry dock
• Condition of gate below water line unknown
• Availability of dry dock
Recovery of Gladstone Gate
Conventional lift using cranes
• Weight & size of gate would require a tandem
lift using two 1000 tonne cranes
• Availability of space to accommodate the
footprint
Recovery of Gladstone Gate
Tipping Cradle
Recovery of Gladstone Gate
Tipping Cradle
• Distinct advantages to MDHC
• Mersey Mammoth floating crane could be used
(250 t capacity)
• Wholly owned by MDHC
• Another 5 gates require refurbishment
• cradle could be reused
Recovery of Gladstone Gate
400t
250 t
184 t
BuoyancyTotal Lift
400-184=216 t max
Recovery of Gladstone Gate
Initial Option
Use of Mersey Mammoth to rotate gate and pull it onto quay
side
230 tonne of kentledge required
Requirement to rotate gate from bottom
Recovery of Gladstone Gate
What to do when gate is horizontal
Two options considered
• Slide gate onto quay side
• Provide vertical support at end of cradle
• Enter the Camel
Recovery of Gladstone Gate
What is “The Camel”
• Floating barge Used to salvage vessels
• Built circa 1958
• Length 104’ (42.67m)
• Beam 35’ (10.67 m)
• Owned by MDHC
• Laid-Up for 3-4 years
• Therefore no cost on project & ideal for use
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Problems With Using Camel
• Floating vessel
• Age – Unknown condition
• No access to inside for condition survey
• Fuel on board – No possibility of welding to deck
Recovery of Gladstone Gate
Problems With Using Camel
• Floating vessel
Design calculations
• Age – Unknown condition
Lloyds survey
• No access to inside for condition survey
Lloyds survey
• Fuel on board – No possibility of welding to deck
Clamped connection to bollards
Recovery of Gladstone Gate
Details of Camel Bollard Clamp
Recovery of Gladstone Gate
Preferred solution
• Use tipping cradle to recover gate
• Mersey Mammoth used to lift cradle
• Camel used to support gate during repairs
Recovery of Gladstone Gate
Tipping Cradle
Recovery of Gladstone Gate
Design Method
• Very good drawings of gate available
• Strength an condition of dock wall uncertain
• Good Guide to gate weights & CoG’s
• Uncertainty on gate condition
Amount of leakage
Amount of entrained silt
• Trial lift required
Recovery of Gladstone Gate
Trial Lift
• Trial lift undertaken May 2005
• Results inconclusive –
Gate appears heavier than drawing weight
• Further investigation revealed gate was not
emptied of all water for trial.
• Gate reported as being clear of silt
• 2nd
trial lift not possible during design
• Uncertainty as to reason for excess weight
Recovery of Gladstone Gate
Design Brief
• To cater for uncertainty of gate weight 50 tonne allowance
• 60% / 40% split in load to cater for
1.Uneven distribution in load
2. Incorrect position of gate in cradle
• Upper & lower bound load cases defined
• Upper bound – Used for member design & lifting loads
• Lower bound – Used for lifting loads
• Stability and strength of dock wall by assessment
• Lateral load resisted by shear key in foundations
Recovery of Gladstone Gate
Gate Prior to Rotation Gate in Final Position
Recovery of Gladstone Gate
Recovery of Gladstone Gate
171 te
83 te
72 te 75 te
100 te
74 te
329 te
201 te
230 te
195 te
168 te
142 te
0 te
50 te
100 te
150 te
200 te
250 te
300 te
350 te
400 te
450 te
0 10 20 30 40 50 60 70 80 90 100
Angle of Rotation
MammothLoad
Upper Bound Vertical Mammoth Load
Lower Bound Vertical Mammoth Load
High Predicted load on Mammoth not including
Buoyancy
Low Predicted load on Mammoth including
Buoyancy
Recovery of Gladstone Gate
Design Brief
• 250 tonne capacity of Mammoth not sufficient to rotate
gate from vertical
• Additional lifting capacity required
• Additional capacity should provide horizontal pull
• Use of tugs to start lift
• Mammoth to complete lift
• Foundations provided remote from quay edge to take
lateral loads
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Method of Analysis
Simple 2D STAAD Pro models for various configurations
Vertical, 10°,22.5°, 33.75°, 45°, 67.5, 90°
Various configurations
•Gate against wall
•Gate supported on Mammoth
•Gate supported on tug
•Gate supported on Camel (final condition)
Recovery of Gladstone Gate
Testing Requirements
• Two types of testing
• NDT of welds
• Load testing of critical items
Recovery of Gladstone Gate
Testing Requirements
NDT of welds
• Many full penetration weld in highly loaded areas
• No redundant load path in these areas
• All full pen welds 100% MPI & 100% UT
Recovery of Gladstone Gate
Main Pin Detail
No positive
connection to coping
Recovery of Gladstone Gate
Main Pin Detail
Recovery of Gladstone Gate
Testing Requirements
LOLER Requirements
REGULATION 9 -THOROUGH EXAMINATION AND
INSPECTION
Load testing to confirm the build quality and structural load
bearing capability of the lifting equipment
Functional and operational envelope tests to verify the
satisfactory working range of the lifting equipment.
Testing of lifting equipment should be undertaken at the
discretion of the competent person
.
Recovery of Gladstone Gate
Testing Requirements
Load test of critical items
Discussions with HSE
• Main pin assembly
• Tug lifting eye
• Mammoth lifting eye
Recovery of Gladstone Gate
Testing Requirements
Load test of critical items
Programme & cost implications
•Test main pin assemblies only
•Full NDT of all components of Lifting Eyes
•Measures taken to ensure no person under the shadow
of the lift
•For design of lift items FoS = 2.0
•For load test proof load = 1.5
Recovery of Gladstone Gate
Testing Frame for Main Pin
Recovery of Gladstone Gate
Testing Frame for Main Pin
Recovery of Gladstone Gate
Testing Frame for Main Pin
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Lifting of Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Recovery of Gladstone Gate
Lessons Learned
Recovery of Gladstone Gate
Test requirements and impact
Tightening of clamp assemblies
Use of Camel
Lessons Learned
Recovery of Gladstone Gate
Questions & Answers

More Related Content

What's hot

Foiling Week™ 2015. July 2nd - Presentation by Larry Knauer: "The Rave V Wind...
Foiling Week™ 2015. July 2nd - Presentation by Larry Knauer: "The Rave V Wind...Foiling Week™ 2015. July 2nd - Presentation by Larry Knauer: "The Rave V Wind...
Foiling Week™ 2015. July 2nd - Presentation by Larry Knauer: "The Rave V Wind...Foiling Week™
 
Access Engineering PLC - Training Presentation
Access Engineering PLC - Training PresentationAccess Engineering PLC - Training Presentation
Access Engineering PLC - Training PresentationGihan Anuradha Bombuwala
 
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...Nick Bentley
 
Intro to offshore drilling
Intro to offshore drilling Intro to offshore drilling
Intro to offshore drilling amrhaggag
 
Presentation (Pagkratios Chitas)
Presentation (Pagkratios Chitas)Presentation (Pagkratios Chitas)
Presentation (Pagkratios Chitas)Pagkratios Chitas
 
July 8th 2014 - Key note speech by Martin Fischer: "The main recent areas of ...
July 8th 2014 - Key note speech by Martin Fischer: "The main recent areas of ...July 8th 2014 - Key note speech by Martin Fischer: "The main recent areas of ...
July 8th 2014 - Key note speech by Martin Fischer: "The main recent areas of ...Foiling Week™
 
Lecture01 140412064456-phpapp02 - copy
Lecture01 140412064456-phpapp02 - copyLecture01 140412064456-phpapp02 - copy
Lecture01 140412064456-phpapp02 - copytaye2020
 
Massarsch uevos desarrollos en pilotes de fundación
Massarsch    uevos desarrollos en pilotes de fundaciónMassarsch    uevos desarrollos en pilotes de fundación
Massarsch uevos desarrollos en pilotes de fundacióncfpbolivia
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavementsHARITSEHRAWAT
 
offshore support vessel design
offshore support vessel designoffshore support vessel design
offshore support vessel designAhmed Taha
 
Benkelman beam deflection studies
Benkelman beam deflection studiesBenkelman beam deflection studies
Benkelman beam deflection studiesvikasravekar
 
Hpht lessons maersk oil uk 1st
Hpht lessons maersk oil uk 1stHpht lessons maersk oil uk 1st
Hpht lessons maersk oil uk 1stPritish Mukherjee
 
Designing of Offshore DNV Container
Designing of Offshore DNV ContainerDesigning of Offshore DNV Container
Designing of Offshore DNV ContainerIDES Editor
 
Fundamentals of Petroleum Engineering Module 4
Fundamentals of Petroleum Engineering Module 4Fundamentals of Petroleum Engineering Module 4
Fundamentals of Petroleum Engineering Module 4Aijaz Ali Mooro
 
Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)Pagkratios Chitas
 
Offshore Support Vessels Design
Offshore Support Vessels DesignOffshore Support Vessels Design
Offshore Support Vessels DesignAhmed Taha
 
Offshore pile design according to international practice
Offshore pile design according to international practiceOffshore pile design according to international practice
Offshore pile design according to international practiceWeb2Present
 

What's hot (20)

Casting yard
Casting yardCasting yard
Casting yard
 
Foiling Week™ 2015. July 2nd - Presentation by Larry Knauer: "The Rave V Wind...
Foiling Week™ 2015. July 2nd - Presentation by Larry Knauer: "The Rave V Wind...Foiling Week™ 2015. July 2nd - Presentation by Larry Knauer: "The Rave V Wind...
Foiling Week™ 2015. July 2nd - Presentation by Larry Knauer: "The Rave V Wind...
 
Access Engineering PLC - Training Presentation
Access Engineering PLC - Training PresentationAccess Engineering PLC - Training Presentation
Access Engineering PLC - Training Presentation
 
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
 
Intro to offshore drilling
Intro to offshore drilling Intro to offshore drilling
Intro to offshore drilling
 
Dariush.resume
Dariush.resumeDariush.resume
Dariush.resume
 
Presentation (Pagkratios Chitas)
Presentation (Pagkratios Chitas)Presentation (Pagkratios Chitas)
Presentation (Pagkratios Chitas)
 
July 8th 2014 - Key note speech by Martin Fischer: "The main recent areas of ...
July 8th 2014 - Key note speech by Martin Fischer: "The main recent areas of ...July 8th 2014 - Key note speech by Martin Fischer: "The main recent areas of ...
July 8th 2014 - Key note speech by Martin Fischer: "The main recent areas of ...
 
Lecture01 140412064456-phpapp02 - copy
Lecture01 140412064456-phpapp02 - copyLecture01 140412064456-phpapp02 - copy
Lecture01 140412064456-phpapp02 - copy
 
Massarsch uevos desarrollos en pilotes de fundación
Massarsch    uevos desarrollos en pilotes de fundaciónMassarsch    uevos desarrollos en pilotes de fundación
Massarsch uevos desarrollos en pilotes de fundación
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavements
 
offshore support vessel design
offshore support vessel designoffshore support vessel design
offshore support vessel design
 
Benkelman beam deflection studies
Benkelman beam deflection studiesBenkelman beam deflection studies
Benkelman beam deflection studies
 
Hpht lessons maersk oil uk 1st
Hpht lessons maersk oil uk 1stHpht lessons maersk oil uk 1st
Hpht lessons maersk oil uk 1st
 
Rig inspection, Sigve Hamilton Aspelund
Rig inspection, Sigve Hamilton AspelundRig inspection, Sigve Hamilton Aspelund
Rig inspection, Sigve Hamilton Aspelund
 
Designing of Offshore DNV Container
Designing of Offshore DNV ContainerDesigning of Offshore DNV Container
Designing of Offshore DNV Container
 
Fundamentals of Petroleum Engineering Module 4
Fundamentals of Petroleum Engineering Module 4Fundamentals of Petroleum Engineering Module 4
Fundamentals of Petroleum Engineering Module 4
 
Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
 
Offshore Support Vessels Design
Offshore Support Vessels DesignOffshore Support Vessels Design
Offshore Support Vessels Design
 
Offshore pile design according to international practice
Offshore pile design according to international practiceOffshore pile design according to international practice
Offshore pile design according to international practice
 

Similar to Recovery of Damaged Lock Gate

Water customer presentation
Water customer presentationWater customer presentation
Water customer presentationSuj Kang
 
July 8th 2014 - Presentation by Doug Schicler and Davide Tagliapietra
July 8th 2014 - Presentation by Doug Schicler and Davide TagliapietraJuly 8th 2014 - Presentation by Doug Schicler and Davide Tagliapietra
July 8th 2014 - Presentation by Doug Schicler and Davide TagliapietraFoiling Week™
 
D-wall Presentation - Rebar Cage.pdf
D-wall Presentation - Rebar Cage.pdfD-wall Presentation - Rebar Cage.pdf
D-wall Presentation - Rebar Cage.pdfAnonymousTxhyGf
 
1. completion sequance
1. completion sequance1. completion sequance
1. completion sequanceElsayed Amer
 
Innovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngInnovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngSafdar Ali
 
Subsea pipelines the remotely welded retrofit tee for hot tap applications ...
Subsea pipelines the remotely welded retrofit tee for hot tap applications   ...Subsea pipelines the remotely welded retrofit tee for hot tap applications   ...
Subsea pipelines the remotely welded retrofit tee for hot tap applications ...Neil Woodward
 
facilities at Dock
facilities at Dockfacilities at Dock
facilities at Dockamrutaware2
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover projectKriShna Sharma
 
InterMoor Installation of Subsea Pile and Manifold at AC24
InterMoor Installation of Subsea Pile and Manifold at AC24InterMoor Installation of Subsea Pile and Manifold at AC24
InterMoor Installation of Subsea Pile and Manifold at AC24jonathonmiller2008
 
Patrick Hudd Me Mo October 2010 Raise Boring Presentation Rev 1
Patrick Hudd Me Mo October 2010 Raise Boring Presentation Rev 1Patrick Hudd Me Mo October 2010 Raise Boring Presentation Rev 1
Patrick Hudd Me Mo October 2010 Raise Boring Presentation Rev 1patrickhudd
 
Marine-Shipbuilding-and-Onboard-Systems.ppt
Marine-Shipbuilding-and-Onboard-Systems.pptMarine-Shipbuilding-and-Onboard-Systems.ppt
Marine-Shipbuilding-and-Onboard-Systems.pptdevmarineacademy
 
RUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCHRUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCHApoorv Dhawan
 
DATA2015-12-06 Ashghal Presentation 2
DATA2015-12-06 Ashghal Presentation 2DATA2015-12-06 Ashghal Presentation 2
DATA2015-12-06 Ashghal Presentation 2Ian Kelly
 
DATA2015-12-06 Ashghal Presentation 2
DATA2015-12-06 Ashghal Presentation 2DATA2015-12-06 Ashghal Presentation 2
DATA2015-12-06 Ashghal Presentation 2Ian Kelly
 
MOQ Platform installation_Lesson learnt_Rev B
MOQ Platform installation_Lesson learnt_Rev BMOQ Platform installation_Lesson learnt_Rev B
MOQ Platform installation_Lesson learnt_Rev BVishak Gopi
 
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design EngineerPortfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design EngineerTheodoros Dragonas
 

Similar to Recovery of Damaged Lock Gate (20)

Water customer presentation
Water customer presentationWater customer presentation
Water customer presentation
 
July 8th 2014 - Presentation by Doug Schicler and Davide Tagliapietra
July 8th 2014 - Presentation by Doug Schicler and Davide TagliapietraJuly 8th 2014 - Presentation by Doug Schicler and Davide Tagliapietra
July 8th 2014 - Presentation by Doug Schicler and Davide Tagliapietra
 
D-wall Presentation - Rebar Cage.pdf
D-wall Presentation - Rebar Cage.pdfD-wall Presentation - Rebar Cage.pdf
D-wall Presentation - Rebar Cage.pdf
 
1. completion sequance
1. completion sequance1. completion sequance
1. completion sequance
 
Innovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngInnovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellng
 
Subsea pipelines the remotely welded retrofit tee for hot tap applications ...
Subsea pipelines the remotely welded retrofit tee for hot tap applications   ...Subsea pipelines the remotely welded retrofit tee for hot tap applications   ...
Subsea pipelines the remotely welded retrofit tee for hot tap applications ...
 
facilities at Dock
facilities at Dockfacilities at Dock
facilities at Dock
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
 
InterMoor Installation of Subsea Pile and Manifold at AC24
InterMoor Installation of Subsea Pile and Manifold at AC24InterMoor Installation of Subsea Pile and Manifold at AC24
InterMoor Installation of Subsea Pile and Manifold at AC24
 
Patrick Hudd Me Mo October 2010 Raise Boring Presentation Rev 1
Patrick Hudd Me Mo October 2010 Raise Boring Presentation Rev 1Patrick Hudd Me Mo October 2010 Raise Boring Presentation Rev 1
Patrick Hudd Me Mo October 2010 Raise Boring Presentation Rev 1
 
Offshore platforms
Offshore platformsOffshore platforms
Offshore platforms
 
Storage head works
Storage head worksStorage head works
Storage head works
 
Marine-Shipbuilding-and-Onboard-Systems.ppt
Marine-Shipbuilding-and-Onboard-Systems.pptMarine-Shipbuilding-and-Onboard-Systems.ppt
Marine-Shipbuilding-and-Onboard-Systems.ppt
 
RUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCHRUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCH
 
Aggregate testing .pptx
Aggregate testing .pptxAggregate testing .pptx
Aggregate testing .pptx
 
DATA2015-12-06 Ashghal Presentation 2
DATA2015-12-06 Ashghal Presentation 2DATA2015-12-06 Ashghal Presentation 2
DATA2015-12-06 Ashghal Presentation 2
 
DATA2015-12-06 Ashghal Presentation 2
DATA2015-12-06 Ashghal Presentation 2DATA2015-12-06 Ashghal Presentation 2
DATA2015-12-06 Ashghal Presentation 2
 
PFS.pptx
PFS.pptxPFS.pptx
PFS.pptx
 
MOQ Platform installation_Lesson learnt_Rev B
MOQ Platform installation_Lesson learnt_Rev BMOQ Platform installation_Lesson learnt_Rev B
MOQ Platform installation_Lesson learnt_Rev B
 
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design EngineerPortfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
 

Recovery of Damaged Lock Gate