SlideShare a Scribd company logo
1 of 13
Download to read offline
Cost Appraisal of Chhabra Thermal Power Station ( 250 MW)
Cost Appraisal of Chhabra Thermal
Power Station (250 MW)
Deepak Kumar Khandelwal
Prof. (Dr.) M.C. Sharma
Abstract
The Central Electricity Regulatory Commission (CERC) has the power of
deciding the tariff for electricity generated by various power stations.
Tariff is calculated on the basis of capacity charge (fixed cost) and energy
charge (variable cost). The various components of capacity charge on
which the tariff depends are return on equity, interest on capital loan,
depreciation, interest on working capital, operation & maintenance cost,
cost of secondary oil. The components of energy charge are primary fuel
costs, secondary fuel oil consumption and auxiliary energy consumption.
Tariffs are classified into nominal, discount and levelized tariff. Tariff
calculations for 250 MW thermal power plants have been discussed in this
paper.
Keywords: Electricity Act, Electricity tariff, Plant load factor, Fixed and
variable cost.
Objective
his paper aims to present the cost appraisal of thermal power
station at Chhabra of 250 MW. Cost appraisal is done with the
help of costing tools (fixed and variable costs) and Regulatory
Norms for power plants given by Central Electricity Regulatory
Commission (CERC).

Research Scholar, University of Rajasthan, Jaipur

Head, Department of ABST, University of Rajasthan, Jaipur
T
Professional Panorama: An International Journal of Management & Technology
Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 21
Introduction
Chhabra Thermal Power Plant is one of Rajasthan's coal fired power
plants. It is situated at Chowki Motipura (Village) of tehsil
Chhabra in Rajasthan's Baran district. Planned capacity of power plant is
2650MW at the end of 12th Five year plan. The first and 2nd unit at
Chhabra super thermal power plant having capacity of 250 MW each was
set up at a cost of Rs. 2350 crs. by Lodha Construction Company Manak
Chowk (Chandramohan Lodha Civil Engineer). Chhabra is set to become
a power generation hub in the state as in the second phase two more
units with a capacity of 250 MW each will be installed. Table 1 shows the
commissioning and status of various units of this Plant.
Table:-1 Status of Chhabra Thermal Power Station
Stage Unit
no.
Installed
Capacity
(MW)
Date of
commissioning
Status
STAGE-I 1 250 October 2005 Running
STAGE-I 2 250 May 2010 Running
STAGE-II 3 250 December 2013 Running
STAGE-II 4 250 July 2014 Running
STAGE-III 1 660 2016 EPC by L&T MHI
STAGE-IV 2 660 2016 EPC by L&T MHI
The Electricity Act (Supply) 1948 has been replaced by Electricity Act
2003 by Government of India. According to this act, the rights of
determination of tariffs, for the power generated by central, state and
private power generating stations, based on specific terms and
conditions has been given to the CERC. Section 61 of the Act empowers
the Commission to specify and regulate the terms and conditions for
determination of tariff in accordance with the provisions of the said
section along with the National Electricity Policy and Tariff Policy. As per
the Electricity Act 2003, the CERC in March 2004 and January 19, 2009,
had put forth tariff regulations for the FY 2004-09 and FY 2009-14
respectively and on expiry of this, CERC had notified new tariff
Professional Panorama: An International Journal of Management & Technology
Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 22
regulations in the month of January 2014 for the next regulatory period
FY 2014-19. The new regulations were applicable to all power generating
stations (excluding stations based on non-conventional energy sources)
and transmission licensees, except those entities which are determined
through bidding process in accordance with the guidelines issued by the
Central Government.
Review of Literature
Many studies have been conducted in India and abroad related to
working and costing aspects of Thermal Power Plants. Sharma and
Tewari (2015) investigates the impact of various factors affecting coal-
fired power plant economics of 210 MW subcritical unit situated in north
India for electricity generation. Cost analysis of the plant was carried out
on the basis of total capital investment, operating cost and revenue.
Hosseini and Hasanpour (2011) analyses the performance of the Iranian
thermal power plant by working out the technical efficiency using the
mathematical model of data envelopment analysis (DEA). The purpose of
this study was to estimate efficiency and productivity changes in the 48
thermal power plants in Iran during the period 2002-2008.
Regulatory Norms for calculations of Power Tariff
Tariff for power generated by various power stations is decided on the
basis of:
(a) Fixed Cost i.e. capacity charge
(b) Variable Cost i.e. Energy charge
 Components of Capacity Charges/ Fixed Charge
Table: 2 Components of Capacity Charges (Fixed Cost)
for FY 2014-19
S. No. Component of Capacity Charges FY 2014-19
a. Return on Equity 15.50%
b. Interest on Capital Loan As per actual
c. Depreciation 5.28%
Professional Panorama: An International Journal of Management & Technology
Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 23
d. Interest on Working Capital Based on normative
parameters
e. Operation & Maintenance Cost Based on normative
parameters
f. Cost of Secondary Fuel Oil Based on normative
parameters
(a)Return on Equity (ROE)
CERC has specified a Pre-Tax ROE of 15.5% for the tariff period FY 2014-
19. Further, it has allowed an additional ROE of 0.5% for projects
commissioned after April 2014 within specific timelines. The additional
ROE allowed by CERC is acting as an incentive for a project developer to
achieve time-bound milestones. On the other hand, the Tariff Regulations
does not allow utilities to recover tax on income such as unscheduled
interchange (UI) and incentive income from beneficiaries.
(b) Interest on Capital Loan
The CERC has specified a debt-equity ratio of 70:30 as the funding mix
for the capital cost of a project. The interest on debt funds is recoverable
as part of the tariff. Tariff Regulations allows retention of 1/3rd of the
benefits, if any, arising out of re-financing of loans; earlier such benefits
were required to be passed on entirely to the beneficiaries.
(c) Depreciation
In the Regulations for the earlier tariff periods, the CERC followed the
concept of Advance against Depreciation (AAD) in case where the normal
depreciation rates (notified by the regulator) were not sufficient to meet
the debt repayment obligation of the utility. Tariff regulations for the
period FY 2009-14 the CERC has removed the concept of AAD and at the
same time increased the depreciation rates applicable for projects as
against the earlier deprecation rate of 3.6% for thermal power projects
(based on a 25-year project life and 90% of the capital cost), the CERC
has increased the depreciation rate to 5.28% for most components of the
project.
Professional Panorama: An International Journal of Management & Technology
Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 24
(d) Interest on Working Capital
The working capital for a thermal power station is given in table.
Table:-3 Working Capital for Thermal Power Station
S. No. Components FY 2014-19
1. Coal Stock 1½ Months for Pit Head
2 Months for Non-Pit Head
2. Secondary Fuel Oil Stock 2 Month
3. Maintenance Spares 20% of O&M Costs– Coal Based
30% of O&M Costs– Gas Based
4. Sales Receivables 2 Month
5. O&M expenses 1 Month
(e) Operations & Maintenance Costs (O&M)
The CERC has specified O&M Costs for thermal power stations on the
normative parameters (Rs.’ Lacs/MW), depending on the type of
machine installed by the power station. The normative O&M expenses
allowed are given in table:
Table: 4 Operations & Maintenance Costs for Different Capacity
Power Plants
(In Rs.’ Lacs/MW)
(f) Cost of Secondary Fuel Oil
As per Tariff regulations for the period FY 2014-19, the CERC has
included the cost of SFO as part of Auxiliary Fuel Consumption (AFC).
Financial
Year
200/210/250
MW Sets
300/330/350
MW Sets
500 MW
Sets
600MW
Sets and
above
2014-15 23.90 19.95 16.00 14.40
2015-16 25.40 21.21 17.01 15.31
2016-17 27.00 22.54 18.08 16.27
2017-18 28.70 23.96 19.22 17.30
2018-19 30.51 25.47 20.43 18.38
Professional Panorama: An International Journal of Management & Technology
Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 25
Projects are able to recover the cost of SFO on the basis of normative
consumption norms specified by the regulator and the plant availability
factor during the year.
General Concepts & Definitions in Reference to Tariff calculation
(a) Auxiliary Energy Consumption
Quantum of energy consumed by auxiliary equipment of the generating
station, and transformer losses within the generating station, expressed
as a percentage of the sum of gross energy generated at the generator
terminals of all the units of the generating station.
(b) Date of Commercial Operation’ or ‘COD’
The date declared by the generating company after demonstrating the
maximum continuous rating (MCR) or the installed capacity (IC) through
a successful trial run after notice to the beneficiaries, from 0000 hour of
which scheduling process as per the Indian Electricity Grid Code (IEGC)
is fully implemented, and in relation to the generating station as a whole,
the date of commercial operation of last unit or block of the generating
station.
(c) Declared Capacity
The capability to deliver ex-bus electricity in MW declared by such
generating station in relation to any time-block of the day or whole the
day, duly taking into account the availability of fuel or water, and subject
to further qualification in relevant regulation.
(d) Gross Calorific Value
The heat produced in kcal by complete combustion of one kilogram of
solid fuel or one litre of liquid fuel or one standard cubic meter of
gaseous fuel, as the case may be.
Professional Panorama: An International Journal of Management & Technology
Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 26
(e) Gross Station Heat Rate
The heat energy input in kcal required to generate one kWh of electrical
energy at generator terminals of a thermal generating station.
(f) Infirm Power
Electricity injected into the grid prior to the commercial operation of a
unit or block of the generating station.
(g) Installed Capacity
Summation of name plate capacities of all the units of generating station
or capacity of generating station (reckoned at the generator terminals)
approved by the Commission from time to time.
(h) Operation and Maintenance Expenses
Expenditure incurred on operation and maintenance of the project, or
part thereof, and includes the expenditure on manpower, repairs, spares,
consumables, insurance and overheads.
(i) Plant Availability Factor (PAF)
Average of the daily declared capacities (DCs) for all the days during that
period expressed as a percentage of the installed capacity in MW reduced
by the normative auxiliary energy consumption.
(j) Conversion of MW into Million Units (MUs)
1MUs=
1MW x 365days x 24hours xPLFx 1000
10,00,000
(k)Tariffs
 Nominal Tariff
 Discount Tariff
 Levelized Tariff
Nominal Tariff
The tariff calculated at for each year (fixed cost + variable cost)
Professional Panorama: An International Journal of Management & Technology
Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 27
Discount Tariff
The tariff calculated at present value of the future tariffs. This is done by
discounting future tariffs by discount rate (given by CERC)
Discount tariff = Nominal tariff x Discount factor
Levelized Tariff
The tariff calculated for all years. This is a simple tariff representing the
tariffs throughout the plant life. In concept, this is “Weighted Mean” of all
tariffs with weights as discounting factors.
Levelized tariff=
Nominal Tariff i x Discount Rate i
Discount Rate
Where, i varies from 1 to n and n is the life of plant in years.
1. The nominal tariff for the next year may be calculated by individually
calculating for each year taking into consideration of future value of
oil, coal etc.
2. Otherwise, we can escalate the nominal tariff for 1st year taking
appropriate escalation factors. Tariff calculations for a 250 MW
Thermal Power Plants are given in table 5.
Table:- 5 Normative Parameters of 250 MW Thermal Power Station
S. No. Particulars Normative
parameter
1 Plant Capacity 250MW
2 Capital cost Rs.6 Cr/MW
3 Debt equity ratio 70:30
4 Return on equity 15.50%
5 Interest on loan 10%
6 Working capital(10% of capital cost) Rs.150Cr
7 Interest on Working capital 10%
8 Rate of Depreciation 5.28%
Professional Panorama: An International Journal of Management & Technology
Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 28
9 O&M cost Rs.23.90 Lacs/MW
10 Plant Load Factor 85%
11 Plant Availability Factor 85%
12 Specific Oil Consumption 0.86 ml/kwh
13 Price of Oil Rs. 35000/kl
14 Gross Calorific Value of Oil 10000kcal/l
15 Station Heat Rate 2425kcal/kg
16 Cost of Coal Rs. 2000/tones
17 Auxiliary Power Consumption 6.5%
18 Plant Life 25 yrs
19 Gross Calorific value of Coal 3800kcal/kg
20. Plant Load Factor in FY 2014-15 65.37%
*Data as per CERC Tariff Regulations for FY 2014-19
Calculations
Fixed Cost component calculations:
(1) Return on equity
Capital cost = 250MW x 6 Cr/MW = Rs. 1500 Cr.
Debt/Equity ratio = 70:30 Hence Equity = 1500x 0.30 = Rs. 450 Cr.
Debt = 1500 x 0.70 = Rs. 1050 Cr.
Return on Equity (ROE) =
15.50 X450
100
= Rs.69.75 Cr
(2) Interest on loan:
10% of debt = 0.1x1050 = Rs. 105 Cr
(3) Interest on working capital:
10% of WC = 0.1x150 (10% of total cost) = Rs. 15 Cr
Professional Panorama: An International Journal of Management & Technology
Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 29
(4) Depreciation:
5.28% of capital cost =
5.28 X 1500
100
=Rs. 79.20 Cr
(5) O&M cost:
O&M cost for 250 MW = 23.90x250 = Rs. 59.75Cr
(6) Total fixed cost
= S. No.( 1 + 2+ 3+ 4+ 5)
= 69.75 + 105 +15 +79.20 +59.75 = Rs. 328.70 Cr
(a) Fixed cost per unit at actual PLF 65.37%
Total Power Generation =
250 X 365 X 24 X65.37 X 1000
10,00,000x100
= 1431.60 M Units
Hence, fixed cost per unit =
328.70 Cr
1431.60 MUs
= Rs. 2.29603/ Unit
(b) Fixed cost per unit at Normative PLF 85.00%
Total Power Generation =
250 X 365 X 24 X85 X 1000
10,00,000x100
= 1861.50 M Units
Hence fixed cost per unit =
328.70 Cr
1861.50 MUs
= Rs. 1.76578/ Unit
Variable Cost Component calculations:
(1) Specific oil consumption = 0.86ml/ kwh
(2) Cost of oil consumption
= Specific oil consumption x Cost of oil/litre
= (0.86ml/KWh X 35000)/(1000x1000) = Rs. 0.0301/ kwh
(3) Heat contribution of oil
= Gross calorific value of oil x Specific oil consumption
= 10,000 x 0.86ml/KWh = 8.6 kcal/ kwh
Professional Panorama: An International Journal of Management & Technology
Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 30
(4) Station Heat Rate
= Heat contribution of oil + Heat contribution of coal
Therefore, Heat contribution of Coal = Station Heat Rate – Heat
contribution of oil
= 2425-8.6 = 2416.40 kcal/ kwh
(5) Specific coal consumption =
Heat contribution of coal
Gross contribution of coal
= 2416.40/3800 =
0.636 kg/ kwh
(6) Cost of Specific Coal consumption
= Specification Coal consumption x Cost of Coal
=
0.636 X 2000
KWh X Tones
=
0.636 X 2000
KWh X 1000 kg
= 1.272 / kwh
Hence, Total Variable cost per unit:
= Cost of Specific oil consumption + Cost of Specific Coal
consumption
= Rs. (0.0301 + 1.272) / kwh = Rs. 1.3021 / kwh
(a) Variable cost calculated above is the variable cost of generation.
(b) 6.5% of the power generated is consumed in Auxiliary. So, in
calculating power available Ex-bus we have to subtract 6.5% of
available power.
(c) Variable cost per unit at bus bar
=
Variable cost per unit
1−% Auxiliary Consumption
=
1.3021
1−0.065
=Rs 1.39262/ kwh
Nominal Tariff calculation:
Nominal Tariff = [{Total Fixed Cost / Unit} + {Total variable cost (Ex-
bus)/Unit}]
Professional Panorama: An International Journal of Management & Technology
Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 31
= Rs (2.29603+1.39262)/Unit = Rs.3.68865/Unit
Conclusion
The fixed cost per unit and the variable cost per unit of the power
generated by CTPS of 250 MW were found to be Rs 2.29603 and
Rs. 1.39262 respectively. Hence, the total generation cost would be
Rs. 3.68865/unit at 65.37% plant load factor (PLF). If plant achieves the
normative load factor i.e. 85% then fixed cost per unit will be reduced to
Rs 1.76578 per unit and variable cost per unit will remain same. The
total generation cost will be reduced to Rs 3.15840 and overall saving of
Rs 0.53025 will be achieved to operate a plant on normative plant load
factor (PLF). So, it is advised to management of thermal plant to chess
the normative plant load factor in this manner they not only control and
reduce the costing as well as they will also reduce their losses
substantially.
References
1. Kumar, Sharma and Tewari (2015), Cost Analysis of a Coal-fired
Power Plant Using the NPV Method, J Ind Eng Int, 11, 495–504, DOI
10.1007/s40092-015-0116-8
2. Hosseini and Hasanpour (2011), Evaluating the Efficiency Changes of
the Thermal Power Plants in Iran and Examining Its Relation with
Reform using DEA Model & Malmquist Index, IPEDR, Vol.12, IACSIT
Press, Singapore
3. Recommendations on Operation Norms for Thermal Power Stations
Tariff Period 2014-19, Government of India, Ministry of Power
Central Electricity Authority, New Delhi January – 2014
4. Central Electricity Regulatory Commission, New Delhi, Notification
21, February, 2014
5. Cen PEEP, Volume 2009
6. NTPC PMI Noida Volume 5
7. National Productivity Council Volume on Energy Management
Professional Panorama: An International Journal of Management & Technology
Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 32
8. Rajput (2006), Power Plant Engineering, 122-132, 3rd Edition, Laxmi
Publications, Delhi
9. P.K.Nag (2007), Heat Power Engineering, 57-67, 5th Edition, Pearson
Publication, New Delhi
10. Annual Report, CTPS 2014-15

More Related Content

What's hot

IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...IEA DSM Implementing Agreement (IA)
 
Ongoing Macro-Stand Alone and CGE modelling approaches at UCL Energy Institute
Ongoing Macro-Stand Alone and CGE modelling approaches at UCL Energy InstituteOngoing Macro-Stand Alone and CGE modelling approaches at UCL Energy Institute
Ongoing Macro-Stand Alone and CGE modelling approaches at UCL Energy InstituteIEA-ETSAP
 
Project update on Enhancing Flexibility in TIMES: Introducing Ancillary Servi...
Project update on Enhancing Flexibility in TIMES: Introducing Ancillary Servi...Project update on Enhancing Flexibility in TIMES: Introducing Ancillary Servi...
Project update on Enhancing Flexibility in TIMES: Introducing Ancillary Servi...IEA-ETSAP
 
Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India sanjeev jain
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Gensol Engineering Limited
 
Renewable Energy Certificate
Renewable Energy CertificateRenewable Energy Certificate
Renewable Energy CertificateJaspal Bhatia
 
Webinar: Post-combusion carbon capture - Thermodynamic modelling
Webinar: Post-combusion carbon capture - Thermodynamic modellingWebinar: Post-combusion carbon capture - Thermodynamic modelling
Webinar: Post-combusion carbon capture - Thermodynamic modellingGlobal CCS Institute
 
Technical minimum schedule for ppt f
Technical minimum schedule for  ppt fTechnical minimum schedule for  ppt f
Technical minimum schedule for ppt fvickylko11
 
Introduction to the Renewable Energy Certificate (REC) Mechanism
Introduction to the Renewable Energy Certificate (REC) MechanismIntroduction to the Renewable Energy Certificate (REC) Mechanism
Introduction to the Renewable Energy Certificate (REC) MechanismSpark Network
 
Addressing demand uncertainty in long-term planning models
Addressing demand uncertainty in long-term planning modelsAddressing demand uncertainty in long-term planning models
Addressing demand uncertainty in long-term planning modelsIEA-ETSAP
 
Effcacious pitch angle control of variable-speed wind turbine using fuzzy bas...
Effcacious pitch angle control of variable-speed wind turbine using fuzzy bas...Effcacious pitch angle control of variable-speed wind turbine using fuzzy bas...
Effcacious pitch angle control of variable-speed wind turbine using fuzzy bas...Kashif Mehmood
 
NASPI_BPA_EPG_LSE_SDVCA_031816-F
NASPI_BPA_EPG_LSE_SDVCA_031816-FNASPI_BPA_EPG_LSE_SDVCA_031816-F
NASPI_BPA_EPG_LSE_SDVCA_031816-FLin Zhang, PhD
 
KK Wind Solutions presentation on Control System Retrofit
KK Wind Solutions presentation on Control System RetrofitKK Wind Solutions presentation on Control System Retrofit
KK Wind Solutions presentation on Control System RetrofitRené Balle
 
How do changes to future technology and fuel developments affect the optimal ...
How do changes to future technology and fuel developments affect the optimal ...How do changes to future technology and fuel developments affect the optimal ...
How do changes to future technology and fuel developments affect the optimal ...IEA-ETSAP
 
Msedcl aar 2018-19
Msedcl aar 2018-19Msedcl aar 2018-19
Msedcl aar 2018-19ZahidManiyar
 

What's hot (18)

Abt meter
Abt meterAbt meter
Abt meter
 
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
 
Levellised generic tariff
Levellised generic tariffLevellised generic tariff
Levellised generic tariff
 
Ongoing Macro-Stand Alone and CGE modelling approaches at UCL Energy Institute
Ongoing Macro-Stand Alone and CGE modelling approaches at UCL Energy InstituteOngoing Macro-Stand Alone and CGE modelling approaches at UCL Energy Institute
Ongoing Macro-Stand Alone and CGE modelling approaches at UCL Energy Institute
 
Project update on Enhancing Flexibility in TIMES: Introducing Ancillary Servi...
Project update on Enhancing Flexibility in TIMES: Introducing Ancillary Servi...Project update on Enhancing Flexibility in TIMES: Introducing Ancillary Servi...
Project update on Enhancing Flexibility in TIMES: Introducing Ancillary Servi...
 
Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
 
Renewable Energy Certificate
Renewable Energy CertificateRenewable Energy Certificate
Renewable Energy Certificate
 
Energy audit tata power solar
Energy audit   tata power solarEnergy audit   tata power solar
Energy audit tata power solar
 
Webinar: Post-combusion carbon capture - Thermodynamic modelling
Webinar: Post-combusion carbon capture - Thermodynamic modellingWebinar: Post-combusion carbon capture - Thermodynamic modelling
Webinar: Post-combusion carbon capture - Thermodynamic modelling
 
Technical minimum schedule for ppt f
Technical minimum schedule for  ppt fTechnical minimum schedule for  ppt f
Technical minimum schedule for ppt f
 
Introduction to the Renewable Energy Certificate (REC) Mechanism
Introduction to the Renewable Energy Certificate (REC) MechanismIntroduction to the Renewable Energy Certificate (REC) Mechanism
Introduction to the Renewable Energy Certificate (REC) Mechanism
 
Addressing demand uncertainty in long-term planning models
Addressing demand uncertainty in long-term planning modelsAddressing demand uncertainty in long-term planning models
Addressing demand uncertainty in long-term planning models
 
Effcacious pitch angle control of variable-speed wind turbine using fuzzy bas...
Effcacious pitch angle control of variable-speed wind turbine using fuzzy bas...Effcacious pitch angle control of variable-speed wind turbine using fuzzy bas...
Effcacious pitch angle control of variable-speed wind turbine using fuzzy bas...
 
NASPI_BPA_EPG_LSE_SDVCA_031816-F
NASPI_BPA_EPG_LSE_SDVCA_031816-FNASPI_BPA_EPG_LSE_SDVCA_031816-F
NASPI_BPA_EPG_LSE_SDVCA_031816-F
 
KK Wind Solutions presentation on Control System Retrofit
KK Wind Solutions presentation on Control System RetrofitKK Wind Solutions presentation on Control System Retrofit
KK Wind Solutions presentation on Control System Retrofit
 
How do changes to future technology and fuel developments affect the optimal ...
How do changes to future technology and fuel developments affect the optimal ...How do changes to future technology and fuel developments affect the optimal ...
How do changes to future technology and fuel developments affect the optimal ...
 
Msedcl aar 2018-19
Msedcl aar 2018-19Msedcl aar 2018-19
Msedcl aar 2018-19
 

Viewers also liked

Housing finance in india challenges and issues
Housing finance in india challenges and issuesHousing finance in india challenges and issues
Housing finance in india challenges and issuesTapasya123
 
Marketing strategies in apparel exports an insight
Marketing strategies in apparel exports an insightMarketing strategies in apparel exports an insight
Marketing strategies in apparel exports an insightTapasya123
 
A study on celebrity endorsement in advertisement
A study on celebrity endorsement in advertisementA study on celebrity endorsement in advertisement
A study on celebrity endorsement in advertisementTapasya123
 
Working capital management through
Working capital management throughWorking capital management through
Working capital management throughTapasya123
 
Significance of market timing and stock selection ability of mutual fund mana...
Significance of market timing and stock selection ability of mutual fund mana...Significance of market timing and stock selection ability of mutual fund mana...
Significance of market timing and stock selection ability of mutual fund mana...Tapasya123
 
Make in india campaign a role and impact of human resource valuation
Make in india campaign a role and impact of human resource valuationMake in india campaign a role and impact of human resource valuation
Make in india campaign a role and impact of human resource valuationTapasya123
 
Higher education in rajasthan
Higher education in rajasthanHigher education in rajasthan
Higher education in rajasthanTapasya123
 
Impact of media on youngsters of jaipur
Impact of media on youngsters of jaipurImpact of media on youngsters of jaipur
Impact of media on youngsters of jaipurTapasya123
 
Comparing stress levels in female doctors of selected public and private sect...
Comparing stress levels in female doctors of selected public and private sect...Comparing stress levels in female doctors of selected public and private sect...
Comparing stress levels in female doctors of selected public and private sect...Tapasya123
 
Impression of mid day meal scheme on enrolment & daily attendance of scho...
Impression of mid day meal scheme on enrolment & daily attendance of scho...Impression of mid day meal scheme on enrolment & daily attendance of scho...
Impression of mid day meal scheme on enrolment & daily attendance of scho...Tapasya123
 
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...SlideShare
 
How to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksHow to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksSlideShare
 
Getting Started With SlideShare
Getting Started With SlideShareGetting Started With SlideShare
Getting Started With SlideShareSlideShare
 

Viewers also liked (13)

Housing finance in india challenges and issues
Housing finance in india challenges and issuesHousing finance in india challenges and issues
Housing finance in india challenges and issues
 
Marketing strategies in apparel exports an insight
Marketing strategies in apparel exports an insightMarketing strategies in apparel exports an insight
Marketing strategies in apparel exports an insight
 
A study on celebrity endorsement in advertisement
A study on celebrity endorsement in advertisementA study on celebrity endorsement in advertisement
A study on celebrity endorsement in advertisement
 
Working capital management through
Working capital management throughWorking capital management through
Working capital management through
 
Significance of market timing and stock selection ability of mutual fund mana...
Significance of market timing and stock selection ability of mutual fund mana...Significance of market timing and stock selection ability of mutual fund mana...
Significance of market timing and stock selection ability of mutual fund mana...
 
Make in india campaign a role and impact of human resource valuation
Make in india campaign a role and impact of human resource valuationMake in india campaign a role and impact of human resource valuation
Make in india campaign a role and impact of human resource valuation
 
Higher education in rajasthan
Higher education in rajasthanHigher education in rajasthan
Higher education in rajasthan
 
Impact of media on youngsters of jaipur
Impact of media on youngsters of jaipurImpact of media on youngsters of jaipur
Impact of media on youngsters of jaipur
 
Comparing stress levels in female doctors of selected public and private sect...
Comparing stress levels in female doctors of selected public and private sect...Comparing stress levels in female doctors of selected public and private sect...
Comparing stress levels in female doctors of selected public and private sect...
 
Impression of mid day meal scheme on enrolment & daily attendance of scho...
Impression of mid day meal scheme on enrolment & daily attendance of scho...Impression of mid day meal scheme on enrolment & daily attendance of scho...
Impression of mid day meal scheme on enrolment & daily attendance of scho...
 
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...
 
How to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksHow to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & Tricks
 
Getting Started With SlideShare
Getting Started With SlideShareGetting Started With SlideShare
Getting Started With SlideShare
 

Similar to Cost appraisal of chhabra thermal

Summer training project on DVC power plant
Summer training project on DVC power plantSummer training project on DVC power plant
Summer training project on DVC power plantAnkita Shrestha
 
Renewable energy and grid integration energy transition
Renewable energy and grid integration   energy transitionRenewable energy and grid integration   energy transition
Renewable energy and grid integration energy transitionNarinporn Malasri
 
Net energy metering manual for three schemes
Net energy metering manual for three schemesNet energy metering manual for three schemes
Net energy metering manual for three schemesPrivate Consultants
 
IRJET-Detailed Energy Audit in a Captive Cogeneration Plant
IRJET-Detailed Energy Audit in a Captive Cogeneration PlantIRJET-Detailed Energy Audit in a Captive Cogeneration Plant
IRJET-Detailed Energy Audit in a Captive Cogeneration PlantIRJET Journal
 
Consideration of reactive energy in the tariff structure
Consideration of reactive energy in the tariff structureConsideration of reactive energy in the tariff structure
Consideration of reactive energy in the tariff structureIAEME Publication
 
“Optimization of battery Cooling system for electric vehicle using Simulation”
“Optimization of battery Cooling system for electric vehicle using Simulation”“Optimization of battery Cooling system for electric vehicle using Simulation”
“Optimization of battery Cooling system for electric vehicle using Simulation”IRJET Journal
 
ABT a complete report and a case study
ABT a complete report and a case studyABT a complete report and a case study
ABT a complete report and a case studyWaseem Hashmat
 
Final Report For Summer Training - Naif AlJuhani
Final Report For Summer Training - Naif AlJuhaniFinal Report For Summer Training - Naif AlJuhani
Final Report For Summer Training - Naif AlJuhaniNaif AlJuhani, PMP®
 
WinD Force Newsletter October Edition
WinD Force Newsletter   October EditionWinD Force Newsletter   October Edition
WinD Force Newsletter October Editionrupeshsingh_1
 
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...electricitygovernance
 
Expert group constituted by CERC proposes draft IEGC 2020
Expert group constituted by CERC proposes draft IEGC 2020Expert group constituted by CERC proposes draft IEGC 2020
Expert group constituted by CERC proposes draft IEGC 2020Amitava Nag
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projectssmsksolar
 
Session 13 national policy & regulatory framework & available incentives
Session 13   national policy & regulatory framework & available incentivesSession 13   national policy & regulatory framework & available incentives
Session 13 national policy & regulatory framework & available incentivesChirag Jain
 
Mixed Energy(NEPRA- State of industry Report 2020-2021)- Presentation
Mixed Energy(NEPRA- State of industry Report 2020-2021)- PresentationMixed Energy(NEPRA- State of industry Report 2020-2021)- Presentation
Mixed Energy(NEPRA- State of industry Report 2020-2021)- PresentationNAUMAN NAEEM
 

Similar to Cost appraisal of chhabra thermal (20)

Discussion paper 16.11.2015
Discussion paper 16.11.2015Discussion paper 16.11.2015
Discussion paper 16.11.2015
 
Summer training project on DVC power plant
Summer training project on DVC power plantSummer training project on DVC power plant
Summer training project on DVC power plant
 
Renewable energy and grid integration energy transition
Renewable energy and grid integration   energy transitionRenewable energy and grid integration   energy transition
Renewable energy and grid integration energy transition
 
DSM.pptx
DSM.pptxDSM.pptx
DSM.pptx
 
Net energy metering manual for three schemes
Net energy metering manual for three schemesNet energy metering manual for three schemes
Net energy metering manual for three schemes
 
IRJET-Detailed Energy Audit in a Captive Cogeneration Plant
IRJET-Detailed Energy Audit in a Captive Cogeneration PlantIRJET-Detailed Energy Audit in a Captive Cogeneration Plant
IRJET-Detailed Energy Audit in a Captive Cogeneration Plant
 
Consideration of reactive energy in the tariff structure
Consideration of reactive energy in the tariff structureConsideration of reactive energy in the tariff structure
Consideration of reactive energy in the tariff structure
 
“Optimization of battery Cooling system for electric vehicle using Simulation”
“Optimization of battery Cooling system for electric vehicle using Simulation”“Optimization of battery Cooling system for electric vehicle using Simulation”
“Optimization of battery Cooling system for electric vehicle using Simulation”
 
Economic_Dispatch_in_power_systems.pdf
Economic_Dispatch_in_power_systems.pdfEconomic_Dispatch_in_power_systems.pdf
Economic_Dispatch_in_power_systems.pdf
 
ABT a complete report and a case study
ABT a complete report and a case studyABT a complete report and a case study
ABT a complete report and a case study
 
ACRITI~1.PDF
ACRITI~1.PDFACRITI~1.PDF
ACRITI~1.PDF
 
Final Report For Summer Training - Naif AlJuhani
Final Report For Summer Training - Naif AlJuhaniFinal Report For Summer Training - Naif AlJuhani
Final Report For Summer Training - Naif AlJuhani
 
Small Power Generation Plant
Small Power Generation PlantSmall Power Generation Plant
Small Power Generation Plant
 
WinD Force Newsletter October Edition
WinD Force Newsletter   October EditionWinD Force Newsletter   October Edition
WinD Force Newsletter October Edition
 
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
 
PSP & Guidelines MOP.pptx
PSP & Guidelines MOP.pptxPSP & Guidelines MOP.pptx
PSP & Guidelines MOP.pptx
 
Expert group constituted by CERC proposes draft IEGC 2020
Expert group constituted by CERC proposes draft IEGC 2020Expert group constituted by CERC proposes draft IEGC 2020
Expert group constituted by CERC proposes draft IEGC 2020
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Session 13 national policy & regulatory framework & available incentives
Session 13   national policy & regulatory framework & available incentivesSession 13   national policy & regulatory framework & available incentives
Session 13 national policy & regulatory framework & available incentives
 
Mixed Energy(NEPRA- State of industry Report 2020-2021)- Presentation
Mixed Energy(NEPRA- State of industry Report 2020-2021)- PresentationMixed Energy(NEPRA- State of industry Report 2020-2021)- Presentation
Mixed Energy(NEPRA- State of industry Report 2020-2021)- Presentation
 

Recently uploaded

dusjagr & nano talk on open tools for agriculture research and learning
dusjagr & nano talk on open tools for agriculture research and learningdusjagr & nano talk on open tools for agriculture research and learning
dusjagr & nano talk on open tools for agriculture research and learningMarc Dusseiller Dusjagr
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Pooja Bhuva
 
Economic Importance Of Fungi In Food Additives
Economic Importance Of Fungi In Food AdditivesEconomic Importance Of Fungi In Food Additives
Economic Importance Of Fungi In Food AdditivesSHIVANANDaRV
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxDr. Ravikiran H M Gowda
 
Introduction to TechSoup’s Digital Marketing Services and Use Cases
Introduction to TechSoup’s Digital Marketing  Services and Use CasesIntroduction to TechSoup’s Digital Marketing  Services and Use Cases
Introduction to TechSoup’s Digital Marketing Services and Use CasesTechSoup
 
How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17Celine George
 
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSAnaAcapella
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Jisc
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - Englishneillewis46
 
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...EADTU
 
PANDITA RAMABAI- Indian political thought GENDER.pptx
PANDITA RAMABAI- Indian political thought GENDER.pptxPANDITA RAMABAI- Indian political thought GENDER.pptx
PANDITA RAMABAI- Indian political thought GENDER.pptxakanksha16arora
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxheathfieldcps1
 
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdfFICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdfPondicherry University
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Pooja Bhuva
 
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxPooja Bhuva
 
How to Add a Tool Tip to a Field in Odoo 17
How to Add a Tool Tip to a Field in Odoo 17How to Add a Tool Tip to a Field in Odoo 17
How to Add a Tool Tip to a Field in Odoo 17Celine George
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17Celine George
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxPooja Bhuva
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxJisc
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxEsquimalt MFRC
 

Recently uploaded (20)

dusjagr & nano talk on open tools for agriculture research and learning
dusjagr & nano talk on open tools for agriculture research and learningdusjagr & nano talk on open tools for agriculture research and learning
dusjagr & nano talk on open tools for agriculture research and learning
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
 
Economic Importance Of Fungi In Food Additives
Economic Importance Of Fungi In Food AdditivesEconomic Importance Of Fungi In Food Additives
Economic Importance Of Fungi In Food Additives
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 
Introduction to TechSoup’s Digital Marketing Services and Use Cases
Introduction to TechSoup’s Digital Marketing  Services and Use CasesIntroduction to TechSoup’s Digital Marketing  Services and Use Cases
Introduction to TechSoup’s Digital Marketing Services and Use Cases
 
How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17
 
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
 
PANDITA RAMABAI- Indian political thought GENDER.pptx
PANDITA RAMABAI- Indian political thought GENDER.pptxPANDITA RAMABAI- Indian political thought GENDER.pptx
PANDITA RAMABAI- Indian political thought GENDER.pptx
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdfFICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
 
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
 
How to Add a Tool Tip to a Field in Odoo 17
How to Add a Tool Tip to a Field in Odoo 17How to Add a Tool Tip to a Field in Odoo 17
How to Add a Tool Tip to a Field in Odoo 17
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 

Cost appraisal of chhabra thermal

  • 1. Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) Cost Appraisal of Chhabra Thermal Power Station (250 MW) Deepak Kumar Khandelwal Prof. (Dr.) M.C. Sharma Abstract The Central Electricity Regulatory Commission (CERC) has the power of deciding the tariff for electricity generated by various power stations. Tariff is calculated on the basis of capacity charge (fixed cost) and energy charge (variable cost). The various components of capacity charge on which the tariff depends are return on equity, interest on capital loan, depreciation, interest on working capital, operation & maintenance cost, cost of secondary oil. The components of energy charge are primary fuel costs, secondary fuel oil consumption and auxiliary energy consumption. Tariffs are classified into nominal, discount and levelized tariff. Tariff calculations for 250 MW thermal power plants have been discussed in this paper. Keywords: Electricity Act, Electricity tariff, Plant load factor, Fixed and variable cost. Objective his paper aims to present the cost appraisal of thermal power station at Chhabra of 250 MW. Cost appraisal is done with the help of costing tools (fixed and variable costs) and Regulatory Norms for power plants given by Central Electricity Regulatory Commission (CERC).  Research Scholar, University of Rajasthan, Jaipur  Head, Department of ABST, University of Rajasthan, Jaipur T
  • 2. Professional Panorama: An International Journal of Management & Technology Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 21 Introduction Chhabra Thermal Power Plant is one of Rajasthan's coal fired power plants. It is situated at Chowki Motipura (Village) of tehsil Chhabra in Rajasthan's Baran district. Planned capacity of power plant is 2650MW at the end of 12th Five year plan. The first and 2nd unit at Chhabra super thermal power plant having capacity of 250 MW each was set up at a cost of Rs. 2350 crs. by Lodha Construction Company Manak Chowk (Chandramohan Lodha Civil Engineer). Chhabra is set to become a power generation hub in the state as in the second phase two more units with a capacity of 250 MW each will be installed. Table 1 shows the commissioning and status of various units of this Plant. Table:-1 Status of Chhabra Thermal Power Station Stage Unit no. Installed Capacity (MW) Date of commissioning Status STAGE-I 1 250 October 2005 Running STAGE-I 2 250 May 2010 Running STAGE-II 3 250 December 2013 Running STAGE-II 4 250 July 2014 Running STAGE-III 1 660 2016 EPC by L&T MHI STAGE-IV 2 660 2016 EPC by L&T MHI The Electricity Act (Supply) 1948 has been replaced by Electricity Act 2003 by Government of India. According to this act, the rights of determination of tariffs, for the power generated by central, state and private power generating stations, based on specific terms and conditions has been given to the CERC. Section 61 of the Act empowers the Commission to specify and regulate the terms and conditions for determination of tariff in accordance with the provisions of the said section along with the National Electricity Policy and Tariff Policy. As per the Electricity Act 2003, the CERC in March 2004 and January 19, 2009, had put forth tariff regulations for the FY 2004-09 and FY 2009-14 respectively and on expiry of this, CERC had notified new tariff
  • 3. Professional Panorama: An International Journal of Management & Technology Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 22 regulations in the month of January 2014 for the next regulatory period FY 2014-19. The new regulations were applicable to all power generating stations (excluding stations based on non-conventional energy sources) and transmission licensees, except those entities which are determined through bidding process in accordance with the guidelines issued by the Central Government. Review of Literature Many studies have been conducted in India and abroad related to working and costing aspects of Thermal Power Plants. Sharma and Tewari (2015) investigates the impact of various factors affecting coal- fired power plant economics of 210 MW subcritical unit situated in north India for electricity generation. Cost analysis of the plant was carried out on the basis of total capital investment, operating cost and revenue. Hosseini and Hasanpour (2011) analyses the performance of the Iranian thermal power plant by working out the technical efficiency using the mathematical model of data envelopment analysis (DEA). The purpose of this study was to estimate efficiency and productivity changes in the 48 thermal power plants in Iran during the period 2002-2008. Regulatory Norms for calculations of Power Tariff Tariff for power generated by various power stations is decided on the basis of: (a) Fixed Cost i.e. capacity charge (b) Variable Cost i.e. Energy charge  Components of Capacity Charges/ Fixed Charge Table: 2 Components of Capacity Charges (Fixed Cost) for FY 2014-19 S. No. Component of Capacity Charges FY 2014-19 a. Return on Equity 15.50% b. Interest on Capital Loan As per actual c. Depreciation 5.28%
  • 4. Professional Panorama: An International Journal of Management & Technology Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 23 d. Interest on Working Capital Based on normative parameters e. Operation & Maintenance Cost Based on normative parameters f. Cost of Secondary Fuel Oil Based on normative parameters (a)Return on Equity (ROE) CERC has specified a Pre-Tax ROE of 15.5% for the tariff period FY 2014- 19. Further, it has allowed an additional ROE of 0.5% for projects commissioned after April 2014 within specific timelines. The additional ROE allowed by CERC is acting as an incentive for a project developer to achieve time-bound milestones. On the other hand, the Tariff Regulations does not allow utilities to recover tax on income such as unscheduled interchange (UI) and incentive income from beneficiaries. (b) Interest on Capital Loan The CERC has specified a debt-equity ratio of 70:30 as the funding mix for the capital cost of a project. The interest on debt funds is recoverable as part of the tariff. Tariff Regulations allows retention of 1/3rd of the benefits, if any, arising out of re-financing of loans; earlier such benefits were required to be passed on entirely to the beneficiaries. (c) Depreciation In the Regulations for the earlier tariff periods, the CERC followed the concept of Advance against Depreciation (AAD) in case where the normal depreciation rates (notified by the regulator) were not sufficient to meet the debt repayment obligation of the utility. Tariff regulations for the period FY 2009-14 the CERC has removed the concept of AAD and at the same time increased the depreciation rates applicable for projects as against the earlier deprecation rate of 3.6% for thermal power projects (based on a 25-year project life and 90% of the capital cost), the CERC has increased the depreciation rate to 5.28% for most components of the project.
  • 5. Professional Panorama: An International Journal of Management & Technology Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 24 (d) Interest on Working Capital The working capital for a thermal power station is given in table. Table:-3 Working Capital for Thermal Power Station S. No. Components FY 2014-19 1. Coal Stock 1½ Months for Pit Head 2 Months for Non-Pit Head 2. Secondary Fuel Oil Stock 2 Month 3. Maintenance Spares 20% of O&M Costs– Coal Based 30% of O&M Costs– Gas Based 4. Sales Receivables 2 Month 5. O&M expenses 1 Month (e) Operations & Maintenance Costs (O&M) The CERC has specified O&M Costs for thermal power stations on the normative parameters (Rs.’ Lacs/MW), depending on the type of machine installed by the power station. The normative O&M expenses allowed are given in table: Table: 4 Operations & Maintenance Costs for Different Capacity Power Plants (In Rs.’ Lacs/MW) (f) Cost of Secondary Fuel Oil As per Tariff regulations for the period FY 2014-19, the CERC has included the cost of SFO as part of Auxiliary Fuel Consumption (AFC). Financial Year 200/210/250 MW Sets 300/330/350 MW Sets 500 MW Sets 600MW Sets and above 2014-15 23.90 19.95 16.00 14.40 2015-16 25.40 21.21 17.01 15.31 2016-17 27.00 22.54 18.08 16.27 2017-18 28.70 23.96 19.22 17.30 2018-19 30.51 25.47 20.43 18.38
  • 6. Professional Panorama: An International Journal of Management & Technology Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 25 Projects are able to recover the cost of SFO on the basis of normative consumption norms specified by the regulator and the plant availability factor during the year. General Concepts & Definitions in Reference to Tariff calculation (a) Auxiliary Energy Consumption Quantum of energy consumed by auxiliary equipment of the generating station, and transformer losses within the generating station, expressed as a percentage of the sum of gross energy generated at the generator terminals of all the units of the generating station. (b) Date of Commercial Operation’ or ‘COD’ The date declared by the generating company after demonstrating the maximum continuous rating (MCR) or the installed capacity (IC) through a successful trial run after notice to the beneficiaries, from 0000 hour of which scheduling process as per the Indian Electricity Grid Code (IEGC) is fully implemented, and in relation to the generating station as a whole, the date of commercial operation of last unit or block of the generating station. (c) Declared Capacity The capability to deliver ex-bus electricity in MW declared by such generating station in relation to any time-block of the day or whole the day, duly taking into account the availability of fuel or water, and subject to further qualification in relevant regulation. (d) Gross Calorific Value The heat produced in kcal by complete combustion of one kilogram of solid fuel or one litre of liquid fuel or one standard cubic meter of gaseous fuel, as the case may be.
  • 7. Professional Panorama: An International Journal of Management & Technology Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 26 (e) Gross Station Heat Rate The heat energy input in kcal required to generate one kWh of electrical energy at generator terminals of a thermal generating station. (f) Infirm Power Electricity injected into the grid prior to the commercial operation of a unit or block of the generating station. (g) Installed Capacity Summation of name plate capacities of all the units of generating station or capacity of generating station (reckoned at the generator terminals) approved by the Commission from time to time. (h) Operation and Maintenance Expenses Expenditure incurred on operation and maintenance of the project, or part thereof, and includes the expenditure on manpower, repairs, spares, consumables, insurance and overheads. (i) Plant Availability Factor (PAF) Average of the daily declared capacities (DCs) for all the days during that period expressed as a percentage of the installed capacity in MW reduced by the normative auxiliary energy consumption. (j) Conversion of MW into Million Units (MUs) 1MUs= 1MW x 365days x 24hours xPLFx 1000 10,00,000 (k)Tariffs  Nominal Tariff  Discount Tariff  Levelized Tariff Nominal Tariff The tariff calculated at for each year (fixed cost + variable cost)
  • 8. Professional Panorama: An International Journal of Management & Technology Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 27 Discount Tariff The tariff calculated at present value of the future tariffs. This is done by discounting future tariffs by discount rate (given by CERC) Discount tariff = Nominal tariff x Discount factor Levelized Tariff The tariff calculated for all years. This is a simple tariff representing the tariffs throughout the plant life. In concept, this is “Weighted Mean” of all tariffs with weights as discounting factors. Levelized tariff= Nominal Tariff i x Discount Rate i Discount Rate Where, i varies from 1 to n and n is the life of plant in years. 1. The nominal tariff for the next year may be calculated by individually calculating for each year taking into consideration of future value of oil, coal etc. 2. Otherwise, we can escalate the nominal tariff for 1st year taking appropriate escalation factors. Tariff calculations for a 250 MW Thermal Power Plants are given in table 5. Table:- 5 Normative Parameters of 250 MW Thermal Power Station S. No. Particulars Normative parameter 1 Plant Capacity 250MW 2 Capital cost Rs.6 Cr/MW 3 Debt equity ratio 70:30 4 Return on equity 15.50% 5 Interest on loan 10% 6 Working capital(10% of capital cost) Rs.150Cr 7 Interest on Working capital 10% 8 Rate of Depreciation 5.28%
  • 9. Professional Panorama: An International Journal of Management & Technology Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 28 9 O&M cost Rs.23.90 Lacs/MW 10 Plant Load Factor 85% 11 Plant Availability Factor 85% 12 Specific Oil Consumption 0.86 ml/kwh 13 Price of Oil Rs. 35000/kl 14 Gross Calorific Value of Oil 10000kcal/l 15 Station Heat Rate 2425kcal/kg 16 Cost of Coal Rs. 2000/tones 17 Auxiliary Power Consumption 6.5% 18 Plant Life 25 yrs 19 Gross Calorific value of Coal 3800kcal/kg 20. Plant Load Factor in FY 2014-15 65.37% *Data as per CERC Tariff Regulations for FY 2014-19 Calculations Fixed Cost component calculations: (1) Return on equity Capital cost = 250MW x 6 Cr/MW = Rs. 1500 Cr. Debt/Equity ratio = 70:30 Hence Equity = 1500x 0.30 = Rs. 450 Cr. Debt = 1500 x 0.70 = Rs. 1050 Cr. Return on Equity (ROE) = 15.50 X450 100 = Rs.69.75 Cr (2) Interest on loan: 10% of debt = 0.1x1050 = Rs. 105 Cr (3) Interest on working capital: 10% of WC = 0.1x150 (10% of total cost) = Rs. 15 Cr
  • 10. Professional Panorama: An International Journal of Management & Technology Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 29 (4) Depreciation: 5.28% of capital cost = 5.28 X 1500 100 =Rs. 79.20 Cr (5) O&M cost: O&M cost for 250 MW = 23.90x250 = Rs. 59.75Cr (6) Total fixed cost = S. No.( 1 + 2+ 3+ 4+ 5) = 69.75 + 105 +15 +79.20 +59.75 = Rs. 328.70 Cr (a) Fixed cost per unit at actual PLF 65.37% Total Power Generation = 250 X 365 X 24 X65.37 X 1000 10,00,000x100 = 1431.60 M Units Hence, fixed cost per unit = 328.70 Cr 1431.60 MUs = Rs. 2.29603/ Unit (b) Fixed cost per unit at Normative PLF 85.00% Total Power Generation = 250 X 365 X 24 X85 X 1000 10,00,000x100 = 1861.50 M Units Hence fixed cost per unit = 328.70 Cr 1861.50 MUs = Rs. 1.76578/ Unit Variable Cost Component calculations: (1) Specific oil consumption = 0.86ml/ kwh (2) Cost of oil consumption = Specific oil consumption x Cost of oil/litre = (0.86ml/KWh X 35000)/(1000x1000) = Rs. 0.0301/ kwh (3) Heat contribution of oil = Gross calorific value of oil x Specific oil consumption = 10,000 x 0.86ml/KWh = 8.6 kcal/ kwh
  • 11. Professional Panorama: An International Journal of Management & Technology Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 30 (4) Station Heat Rate = Heat contribution of oil + Heat contribution of coal Therefore, Heat contribution of Coal = Station Heat Rate – Heat contribution of oil = 2425-8.6 = 2416.40 kcal/ kwh (5) Specific coal consumption = Heat contribution of coal Gross contribution of coal = 2416.40/3800 = 0.636 kg/ kwh (6) Cost of Specific Coal consumption = Specification Coal consumption x Cost of Coal = 0.636 X 2000 KWh X Tones = 0.636 X 2000 KWh X 1000 kg = 1.272 / kwh Hence, Total Variable cost per unit: = Cost of Specific oil consumption + Cost of Specific Coal consumption = Rs. (0.0301 + 1.272) / kwh = Rs. 1.3021 / kwh (a) Variable cost calculated above is the variable cost of generation. (b) 6.5% of the power generated is consumed in Auxiliary. So, in calculating power available Ex-bus we have to subtract 6.5% of available power. (c) Variable cost per unit at bus bar = Variable cost per unit 1−% Auxiliary Consumption = 1.3021 1−0.065 =Rs 1.39262/ kwh Nominal Tariff calculation: Nominal Tariff = [{Total Fixed Cost / Unit} + {Total variable cost (Ex- bus)/Unit}]
  • 12. Professional Panorama: An International Journal of Management & Technology Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 31 = Rs (2.29603+1.39262)/Unit = Rs.3.68865/Unit Conclusion The fixed cost per unit and the variable cost per unit of the power generated by CTPS of 250 MW were found to be Rs 2.29603 and Rs. 1.39262 respectively. Hence, the total generation cost would be Rs. 3.68865/unit at 65.37% plant load factor (PLF). If plant achieves the normative load factor i.e. 85% then fixed cost per unit will be reduced to Rs 1.76578 per unit and variable cost per unit will remain same. The total generation cost will be reduced to Rs 3.15840 and overall saving of Rs 0.53025 will be achieved to operate a plant on normative plant load factor (PLF). So, it is advised to management of thermal plant to chess the normative plant load factor in this manner they not only control and reduce the costing as well as they will also reduce their losses substantially. References 1. Kumar, Sharma and Tewari (2015), Cost Analysis of a Coal-fired Power Plant Using the NPV Method, J Ind Eng Int, 11, 495–504, DOI 10.1007/s40092-015-0116-8 2. Hosseini and Hasanpour (2011), Evaluating the Efficiency Changes of the Thermal Power Plants in Iran and Examining Its Relation with Reform using DEA Model & Malmquist Index, IPEDR, Vol.12, IACSIT Press, Singapore 3. Recommendations on Operation Norms for Thermal Power Stations Tariff Period 2014-19, Government of India, Ministry of Power Central Electricity Authority, New Delhi January – 2014 4. Central Electricity Regulatory Commission, New Delhi, Notification 21, February, 2014 5. Cen PEEP, Volume 2009 6. NTPC PMI Noida Volume 5 7. National Productivity Council Volume on Energy Management
  • 13. Professional Panorama: An International Journal of Management & Technology Cost Appraisal of Chhabra Thermal Power Station ( 250 MW) 32 8. Rajput (2006), Power Plant Engineering, 122-132, 3rd Edition, Laxmi Publications, Delhi 9. P.K.Nag (2007), Heat Power Engineering, 57-67, 5th Edition, Pearson Publication, New Delhi 10. Annual Report, CTPS 2014-15