SlideShare a Scribd company logo
1 of 4
Download to read offline
For Overpressure Protec on in SRU’s,
Lots of Things are Changing...
Dus n Smith, P.E. & John Burgess, P.E.
7600 W. Tidwell Rd., Ste. 600 | Houston, TX 770400
(713) 802-2647 | SmithBurgess.com
Smith & Burgess LLC Consulting
www.smithburgess.com
For overpressure protection in SRU’s lots of things are changing…
Old school overpressure protection was provided by the exclusion block valves and an open path to the
atmosphere via an incinerator or blowing through the liquid seals into the sulfur pit. A typical Claus
Plant with a Scot Tail Gas treater is shown in the diagram below.
Acid Gas
Combustion Air
Sulfur Condenser
Reactor
Sulfur Trap
To Sulfur Pit
Acid Gas
Burner
Claus
Reactor
Boiler Feed Water (BFW)
Steam
BFW
Steam
BFW
Steam
Inline
Heater
Boiler Feed Water
Hydrogenation
Reactor
To Sulfur Pit
Combustion Air
Hydrogen
Tail Gas
Steam
Sour Water
Incinerator
Amine Contactor
Claus trocess
TGTU
Recycle gas
Waste heat
boiler
Figure 1: Simplified Claus Process with Scot Tail Gas Treater
The EPA has now intervened with consent decrees with most major refiners and the normal discharge of
the exhaust gas from the process to the atmosphere via the incinerator is no longer viable (they now go
through a tail gas treating unit which can “block” the outlet with block valves or liquid head). There are
rumors that certain facilities are going to be required to install traps in the sulfur seals that do not allow
gases to pass through them (similar to a steam trap, but for sulfur). These two steps eliminate the
overpressure protection for “old” SRUs. Note that wherever the emergency vent gas goes, the gas is
extremely toxic, can, and has killed people. For that reason, venting via the sulfur pit is probably a bad
idea as sulfur pits tends to be a buried low pressure tank with a low allowable pressure.
Here is a relatively detailed list of how Smith & Burgess LLC evaluates overpressure protection for these
systems.
Problems Related to Relief Devices
1. Installation of a relief device upstream of the Primary Reaction Furnace (Claus Reactor) may be
acceptable only if the maximum discharge pressure of the combustion air blower is less than the
set pressure of the relief device. If the blower can put up more pressure than the set pressure
(and you have to check on a cold day) the possibility exists that the air will flow backwards
through the burner into the inlet line and melt everything (best case) or result in an internal
explosion (worse case). This has happened!
2. Pressure Relief Valves downstream of the first condenser are generally not recommended (or
useful) due to the complexity associated with ensuring that they do not plug (solid sulfur or
NH4HS deposition). Experts agree that plugged relief devices are close to worthless. One could
steam trace and purge the relief device inlet lines; however, this complexity definitely lowers
Smith & Burgess LLC Consulting
www.smithburgess.com
Page | 2
the availability of the system (not to mention the corrosion concerns associated with H2S / NH4
below about 250 °F). Normal block valves do not stand a chance in this service so why would a
relief device.
3. Putting anything downstream of the first condenser causes a problem because many times the
blocked outlet has been caused by collapsed reactor beds or plugged sulfur condensers. Again
this happens.
4. PSVs also have another challenge. Say the systems normally operates between 10 and 12 psig
(operating pressure is directly related to the capacity so this pressure is creeping up) with a
safety shutdown system at about 12.5 psig. On older systems, the equipment is designed for
about 15 psig (generally 14.8/9 so they don’t have to comply with Section VIII) and the sulfur
seals blow in the 14-15 psig range. ASME Section VIII M-11 (c) recommends a minimum of 5 psi
difference between the set pressure and the operating pressure for relief devices. That aside,
relief devices require 10% on the inlet so they don’t leak, have a +/- 3% for the set pressure
tolerance, and require about ~8% to open. Either way, relief devices in general will not operate
well between the constraints of the operating pressure and blowing vapor through the sulfur
seals.
5. Rupture disks have been installed in low pressure services in the past, but tended to fail at
pressures of 5 psig when set at 15 psig. This results in operational concerns and increased
downtime for the unit and is generally not a viable solution.
Smith & Burgess LLC is working with a rupture pin manufacturer to see if rupture pin technology can
meet the service requirements for installation just after the first sulfur condenser venting directly
into the incinerator. They can be specified with a piston that is flush to the pipe wall and sized in
such a way that the maximum pressure is the set pressure. Current tolerances are +/- 0.5 psi on the
set pressure, so it may work. I am hoping that these devices will work like an HIPS system (without
all of the pain and the ASME Section VIII endorsement for PRDs). I know that block valves are being
replaced with flush pistons and virtually eliminating deposition and corrosion concerns (no dead
space).
Once the means of overpressure protection has been decided, the next question is the ASME VII
requirement for venting the relieved vapors to a safe location. The disposition of the relieved
vapors can raise almost as many questions as the determination of overpressure protection method.
Venting disposition – The following discussion is for a rupture pin or ESD that opens after the first
condenser and lets the flow out to somewhere. Upstream generally of this location presents a problem
(hot air into the flare or other location) and downstream of the first condenser is much more likely to
encounter blockage.
1. Venting the stream from the first condenser to an incinerator is generally a problem as it defeats
the safety instrumented protection against flameout then re-ignition. This is primarily a problem
if the stream is flammable (and they usually are until the very end). Should the venting event
snuff the flame, then the possibility exists that the flammable stream will ignite somewhere in
the piping between the burner and the incinerator outlet (internal explosion).
2. Venting the stream to the flare is also not advisable as the system will frequently have shut-
down logic which could isolated the acid gas but not the blower and blow air into the flare
header. After passing through the inlet furnace, reactor, waste heat boiler and 1st
sulfur
condenser, the air will still be above 600°F and injecting even small quantities of high
temperature air into a flare header is not a good idea. (see above).
Smith & Burgess LLC Consulting
www.smithburgess.com
Page | 3
3. Similarly, venting through the sulfur pits has the problem of over-pressuring the sulfur pit
and/or poor dispersion. Not to mention that if the facility is forced to isolate the sulfur pit with
the SulTraps, this option is gone!
4. Seemingly the best option is a dedicated vent stack that is high enough to prevent unacceptable
concentrations of H2S at grade or nearby elevated structures.
General Concerns
1. The location of the relief protection must account for all the aforementioned problems.
2. SIL-III systems are generally extremely costly to install and maintain due to the number of feeds
to the system (may be over 10 that can overpressure a single SRU train).
3. Relief protection, should it be provided, will have to act above the existing shutdown system but
below the MAWP or sulfur seal pressure.
4. Back flowing acid gas through the inlet of the blower is very bad and has actually killed workers
in the past in Europe. Any system should not stop the blower but isolate the air inlet from the
process and all the anti-surge control system to divert the discharge to atmosphere. We should
also check the blower and ensure that there is some means to stop the backflow of acid gas.

More Related Content

What's hot

Rupture Disks for Process Engineers
Rupture Disks for Process EngineersRupture Disks for Process Engineers
Rupture Disks for Process EngineersSyed Waqas Haider
 
Pressure relief system_design
Pressure relief system_designPressure relief system_design
Pressure relief system_designRahul Tewari
 
Eng handbook crosby pressure relief valve engineering handbook
Eng handbook crosby pressure relief valve engineering handbookEng handbook crosby pressure relief valve engineering handbook
Eng handbook crosby pressure relief valve engineering handbookAli Meshaikhis
 
Ai Ch E Overpressure Protection Training
Ai Ch E Overpressure Protection TrainingAi Ch E Overpressure Protection Training
Ai Ch E Overpressure Protection Trainingernestvictor
 
Anderson Greenwood Pilot Operated Pressure Relief Valves
Anderson Greenwood Pilot Operated Pressure Relief ValvesAnderson Greenwood Pilot Operated Pressure Relief Valves
Anderson Greenwood Pilot Operated Pressure Relief ValvesMiller Energy, Inc.
 
Relief and blowdown in
Relief and blowdown           inRelief and blowdown           in
Relief and blowdown inAkshay Kotkar
 
Accumulation and Over-pressure: difference between accumulation and overpressure
Accumulation and Over-pressure: difference between accumulation and overpressureAccumulation and Over-pressure: difference between accumulation and overpressure
Accumulation and Over-pressure: difference between accumulation and overpressureVarun Patel
 
GE Consolidated Pressure Relief and Safety Valves
GE Consolidated Pressure Relief and Safety ValvesGE Consolidated Pressure Relief and Safety Valves
GE Consolidated Pressure Relief and Safety ValvesClassic Controls, Inc.
 
Emerson Rosemount™ 708 Wireless Acoustic Transmitter, the most reliable, effe...
Emerson Rosemount™ 708 Wireless Acoustic Transmitter, the most reliable, effe...Emerson Rosemount™ 708 Wireless Acoustic Transmitter, the most reliable, effe...
Emerson Rosemount™ 708 Wireless Acoustic Transmitter, the most reliable, effe...Fritz Valencia
 
Workshop On Risk Assesment by Palash Ch Das
Workshop On Risk Assesment by Palash Ch DasWorkshop On Risk Assesment by Palash Ch Das
Workshop On Risk Assesment by Palash Ch DasPalash Das
 
Case Study: Refinery Relief and Flare Study
Case Study: Refinery Relief and Flare StudyCase Study: Refinery Relief and Flare Study
Case Study: Refinery Relief and Flare StudyFlex Process
 
Compressed Air Dryer Products for Industrial Applications
Compressed Air Dryer Products for Industrial ApplicationsCompressed Air Dryer Products for Industrial Applications
Compressed Air Dryer Products for Industrial ApplicationsMiller Energy, Inc.
 
Safety features in_anaesthesia_machine-1
Safety features in_anaesthesia_machine-1Safety features in_anaesthesia_machine-1
Safety features in_anaesthesia_machine-1simegnewyismaw
 
912pressurerelief abb
912pressurerelief abb912pressurerelief abb
912pressurerelief abbHamdan Yusoff
 

What's hot (20)

Rupture Disks for Process Engineers
Rupture Disks for Process EngineersRupture Disks for Process Engineers
Rupture Disks for Process Engineers
 
Pressure relief system_design
Pressure relief system_designPressure relief system_design
Pressure relief system_design
 
Flexible Ducts
Flexible DuctsFlexible Ducts
Flexible Ducts
 
Eng handbook crosby pressure relief valve engineering handbook
Eng handbook crosby pressure relief valve engineering handbookEng handbook crosby pressure relief valve engineering handbook
Eng handbook crosby pressure relief valve engineering handbook
 
Ai Ch E Overpressure Protection Training
Ai Ch E Overpressure Protection TrainingAi Ch E Overpressure Protection Training
Ai Ch E Overpressure Protection Training
 
Anderson Greenwood Pilot Operated Pressure Relief Valves
Anderson Greenwood Pilot Operated Pressure Relief ValvesAnderson Greenwood Pilot Operated Pressure Relief Valves
Anderson Greenwood Pilot Operated Pressure Relief Valves
 
HAZOP Basics
HAZOP BasicsHAZOP Basics
HAZOP Basics
 
API STD 521
API STD 521API STD 521
API STD 521
 
Api 2000 5th vs 6th final
Api 2000 5th vs 6th finalApi 2000 5th vs 6th final
Api 2000 5th vs 6th final
 
Relief and blowdown in
Relief and blowdown           inRelief and blowdown           in
Relief and blowdown in
 
Accumulation and Over-pressure: difference between accumulation and overpressure
Accumulation and Over-pressure: difference between accumulation and overpressureAccumulation and Over-pressure: difference between accumulation and overpressure
Accumulation and Over-pressure: difference between accumulation and overpressure
 
GE Consolidated Pressure Relief and Safety Valves
GE Consolidated Pressure Relief and Safety ValvesGE Consolidated Pressure Relief and Safety Valves
GE Consolidated Pressure Relief and Safety Valves
 
Emerson Rosemount™ 708 Wireless Acoustic Transmitter, the most reliable, effe...
Emerson Rosemount™ 708 Wireless Acoustic Transmitter, the most reliable, effe...Emerson Rosemount™ 708 Wireless Acoustic Transmitter, the most reliable, effe...
Emerson Rosemount™ 708 Wireless Acoustic Transmitter, the most reliable, effe...
 
Workshop On Risk Assesment by Palash Ch Das
Workshop On Risk Assesment by Palash Ch DasWorkshop On Risk Assesment by Palash Ch Das
Workshop On Risk Assesment by Palash Ch Das
 
Case Study: Refinery Relief and Flare Study
Case Study: Refinery Relief and Flare StudyCase Study: Refinery Relief and Flare Study
Case Study: Refinery Relief and Flare Study
 
Compressed Air Dryer Products for Industrial Applications
Compressed Air Dryer Products for Industrial ApplicationsCompressed Air Dryer Products for Industrial Applications
Compressed Air Dryer Products for Industrial Applications
 
Valve sizing
Valve sizingValve sizing
Valve sizing
 
Safety features in_anaesthesia_machine-1
Safety features in_anaesthesia_machine-1Safety features in_anaesthesia_machine-1
Safety features in_anaesthesia_machine-1
 
Line sizing
Line sizingLine sizing
Line sizing
 
912pressurerelief abb
912pressurerelief abb912pressurerelief abb
912pressurerelief abb
 

Similar to For Overpressure Protection in SRU’s, Lots of Things are Changing...

Flare and vent disposal systems molcularseal -
Flare and vent disposal systems molcularseal -Flare and vent disposal systems molcularseal -
Flare and vent disposal systems molcularseal -siavash2010
 
Understanding & Solving Heat Transfer Equipment Stall
Understanding & Solving Heat Transfer Equipment StallUnderstanding & Solving Heat Transfer Equipment Stall
Understanding & Solving Heat Transfer Equipment StallMead O'Brien, Inc.
 
Guidelines for Engineering Design for Process Safety (Process Safety Guidelin...
Guidelines for Engineering Design for Process Safety (Process Safety Guidelin...Guidelines for Engineering Design for Process Safety (Process Safety Guidelin...
Guidelines for Engineering Design for Process Safety (Process Safety Guidelin...gurkanarifyalcinkaya
 
Cng operation safety feature
Cng operation safety featureCng operation safety feature
Cng operation safety featureDanu Jaya Wiguna
 
pressure relief devices scott ostrowski.ppt
pressure relief devices scott ostrowski.pptpressure relief devices scott ostrowski.ppt
pressure relief devices scott ostrowski.pptdavidcorm
 
Pressure Safety Valve Type and application
Pressure Safety Valve Type and applicationPressure Safety Valve Type and application
Pressure Safety Valve Type and applicationharshadbpande07
 
Fundamentals of Pressure Relief Devices.ppt
Fundamentals of Pressure Relief Devices.pptFundamentals of Pressure Relief Devices.ppt
Fundamentals of Pressure Relief Devices.pptLudiDLunar
 
Pressure Reliveing Devices1
Pressure Reliveing Devices1Pressure Reliveing Devices1
Pressure Reliveing Devices1Om Pratap Singh
 
Smoke and environmental ventilation of multi-storey buildings using shafts we...
Smoke and environmental ventilation of multi-storey buildings using shafts we...Smoke and environmental ventilation of multi-storey buildings using shafts we...
Smoke and environmental ventilation of multi-storey buildings using shafts we...Colt UK
 
Review paper on study and implementation of steam traps
Review paper on study and implementation of steam trapsReview paper on study and implementation of steam traps
Review paper on study and implementation of steam trapsIRJET Journal
 
Powder & Bulk Solids Magazine
 Powder & Bulk Solids Magazine Powder & Bulk Solids Magazine
Powder & Bulk Solids MagazineBenjamin Kyalo
 
Pressure Vacuum Relief Valve.pptx
Pressure Vacuum Relief Valve.pptxPressure Vacuum Relief Valve.pptx
Pressure Vacuum Relief Valve.pptxSwamiVidya
 
As schneider-customer-magazine-offshore-2017-en
As schneider-customer-magazine-offshore-2017-enAs schneider-customer-magazine-offshore-2017-en
As schneider-customer-magazine-offshore-2017-enZulfan Syahputra
 
Gas Flare Stack Process
Gas Flare Stack ProcessGas Flare Stack Process
Gas Flare Stack ProcessShad Ibrahim
 
Steam distribution system by Varun Pratap Singh
Steam distribution system by Varun Pratap SinghSteam distribution system by Varun Pratap Singh
Steam distribution system by Varun Pratap SinghVarun Pratap Singh
 
Reducing Shipping Vibration of Compressors in Roof Top Air-conditioning Units...
Reducing Shipping Vibration of Compressors in Roof Top Air-conditioning Units...Reducing Shipping Vibration of Compressors in Roof Top Air-conditioning Units...
Reducing Shipping Vibration of Compressors in Roof Top Air-conditioning Units...HCL Technologies
 

Similar to For Overpressure Protection in SRU’s, Lots of Things are Changing... (20)

Flare and vent disposal systems molcularseal -
Flare and vent disposal systems molcularseal -Flare and vent disposal systems molcularseal -
Flare and vent disposal systems molcularseal -
 
Understanding & Solving Heat Transfer Equipment Stall
Understanding & Solving Heat Transfer Equipment StallUnderstanding & Solving Heat Transfer Equipment Stall
Understanding & Solving Heat Transfer Equipment Stall
 
Guidelines for Engineering Design for Process Safety (Process Safety Guidelin...
Guidelines for Engineering Design for Process Safety (Process Safety Guidelin...Guidelines for Engineering Design for Process Safety (Process Safety Guidelin...
Guidelines for Engineering Design for Process Safety (Process Safety Guidelin...
 
Cng operation safety feature
Cng operation safety featureCng operation safety feature
Cng operation safety feature
 
Silo safety
Silo safety Silo safety
Silo safety
 
pressure relief devices scott ostrowski.ppt
pressure relief devices scott ostrowski.pptpressure relief devices scott ostrowski.ppt
pressure relief devices scott ostrowski.ppt
 
Pressure Safety Valve Type and application
Pressure Safety Valve Type and applicationPressure Safety Valve Type and application
Pressure Safety Valve Type and application
 
Fundamentals of Pressure Relief Devices.ppt
Fundamentals of Pressure Relief Devices.pptFundamentals of Pressure Relief Devices.ppt
Fundamentals of Pressure Relief Devices.ppt
 
Pressure Reliveing Devices1
Pressure Reliveing Devices1Pressure Reliveing Devices1
Pressure Reliveing Devices1
 
Smoke and environmental ventilation of multi-storey buildings using shafts we...
Smoke and environmental ventilation of multi-storey buildings using shafts we...Smoke and environmental ventilation of multi-storey buildings using shafts we...
Smoke and environmental ventilation of multi-storey buildings using shafts we...
 
Review paper on study and implementation of steam traps
Review paper on study and implementation of steam trapsReview paper on study and implementation of steam traps
Review paper on study and implementation of steam traps
 
Giuseppe_Tommasone.pdf
Giuseppe_Tommasone.pdfGiuseppe_Tommasone.pdf
Giuseppe_Tommasone.pdf
 
Powder & Bulk Solids Magazine
 Powder & Bulk Solids Magazine Powder & Bulk Solids Magazine
Powder & Bulk Solids Magazine
 
Pressure Vacuum Relief Valve.pptx
Pressure Vacuum Relief Valve.pptxPressure Vacuum Relief Valve.pptx
Pressure Vacuum Relief Valve.pptx
 
Lessons learned solving pilot valve instability issues on LNG storage tanks
Lessons learned solving pilot valve instability issues on LNG storage tanksLessons learned solving pilot valve instability issues on LNG storage tanks
Lessons learned solving pilot valve instability issues on LNG storage tanks
 
As schneider-customer-magazine-offshore-2017-en
As schneider-customer-magazine-offshore-2017-enAs schneider-customer-magazine-offshore-2017-en
As schneider-customer-magazine-offshore-2017-en
 
Gas Flare Stack Process
Gas Flare Stack ProcessGas Flare Stack Process
Gas Flare Stack Process
 
Steam distribution system by Varun Pratap Singh
Steam distribution system by Varun Pratap SinghSteam distribution system by Varun Pratap Singh
Steam distribution system by Varun Pratap Singh
 
Reducing Shipping Vibration of Compressors in Roof Top Air-conditioning Units...
Reducing Shipping Vibration of Compressors in Roof Top Air-conditioning Units...Reducing Shipping Vibration of Compressors in Roof Top Air-conditioning Units...
Reducing Shipping Vibration of Compressors in Roof Top Air-conditioning Units...
 
Pressure Relief Devices
Pressure Relief DevicesPressure Relief Devices
Pressure Relief Devices
 

Recently uploaded

Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxNANDHAKUMARA10
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...vershagrag
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...jabtakhaidam7
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Servicemeghakumariji156
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxkalpana413121
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementDr. Deepak Mudgal
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...gragchanchal546
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptAfnanAhmad53
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...ronahami
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfsumitt6_25730773
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 

Recently uploaded (20)

Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptx
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 

For Overpressure Protection in SRU’s, Lots of Things are Changing...

  • 1. For Overpressure Protec on in SRU’s, Lots of Things are Changing... Dus n Smith, P.E. & John Burgess, P.E. 7600 W. Tidwell Rd., Ste. 600 | Houston, TX 770400 (713) 802-2647 | SmithBurgess.com
  • 2. Smith & Burgess LLC Consulting www.smithburgess.com For overpressure protection in SRU’s lots of things are changing… Old school overpressure protection was provided by the exclusion block valves and an open path to the atmosphere via an incinerator or blowing through the liquid seals into the sulfur pit. A typical Claus Plant with a Scot Tail Gas treater is shown in the diagram below. Acid Gas Combustion Air Sulfur Condenser Reactor Sulfur Trap To Sulfur Pit Acid Gas Burner Claus Reactor Boiler Feed Water (BFW) Steam BFW Steam BFW Steam Inline Heater Boiler Feed Water Hydrogenation Reactor To Sulfur Pit Combustion Air Hydrogen Tail Gas Steam Sour Water Incinerator Amine Contactor Claus trocess TGTU Recycle gas Waste heat boiler Figure 1: Simplified Claus Process with Scot Tail Gas Treater The EPA has now intervened with consent decrees with most major refiners and the normal discharge of the exhaust gas from the process to the atmosphere via the incinerator is no longer viable (they now go through a tail gas treating unit which can “block” the outlet with block valves or liquid head). There are rumors that certain facilities are going to be required to install traps in the sulfur seals that do not allow gases to pass through them (similar to a steam trap, but for sulfur). These two steps eliminate the overpressure protection for “old” SRUs. Note that wherever the emergency vent gas goes, the gas is extremely toxic, can, and has killed people. For that reason, venting via the sulfur pit is probably a bad idea as sulfur pits tends to be a buried low pressure tank with a low allowable pressure. Here is a relatively detailed list of how Smith & Burgess LLC evaluates overpressure protection for these systems. Problems Related to Relief Devices 1. Installation of a relief device upstream of the Primary Reaction Furnace (Claus Reactor) may be acceptable only if the maximum discharge pressure of the combustion air blower is less than the set pressure of the relief device. If the blower can put up more pressure than the set pressure (and you have to check on a cold day) the possibility exists that the air will flow backwards through the burner into the inlet line and melt everything (best case) or result in an internal explosion (worse case). This has happened! 2. Pressure Relief Valves downstream of the first condenser are generally not recommended (or useful) due to the complexity associated with ensuring that they do not plug (solid sulfur or NH4HS deposition). Experts agree that plugged relief devices are close to worthless. One could steam trace and purge the relief device inlet lines; however, this complexity definitely lowers
  • 3. Smith & Burgess LLC Consulting www.smithburgess.com Page | 2 the availability of the system (not to mention the corrosion concerns associated with H2S / NH4 below about 250 °F). Normal block valves do not stand a chance in this service so why would a relief device. 3. Putting anything downstream of the first condenser causes a problem because many times the blocked outlet has been caused by collapsed reactor beds or plugged sulfur condensers. Again this happens. 4. PSVs also have another challenge. Say the systems normally operates between 10 and 12 psig (operating pressure is directly related to the capacity so this pressure is creeping up) with a safety shutdown system at about 12.5 psig. On older systems, the equipment is designed for about 15 psig (generally 14.8/9 so they don’t have to comply with Section VIII) and the sulfur seals blow in the 14-15 psig range. ASME Section VIII M-11 (c) recommends a minimum of 5 psi difference between the set pressure and the operating pressure for relief devices. That aside, relief devices require 10% on the inlet so they don’t leak, have a +/- 3% for the set pressure tolerance, and require about ~8% to open. Either way, relief devices in general will not operate well between the constraints of the operating pressure and blowing vapor through the sulfur seals. 5. Rupture disks have been installed in low pressure services in the past, but tended to fail at pressures of 5 psig when set at 15 psig. This results in operational concerns and increased downtime for the unit and is generally not a viable solution. Smith & Burgess LLC is working with a rupture pin manufacturer to see if rupture pin technology can meet the service requirements for installation just after the first sulfur condenser venting directly into the incinerator. They can be specified with a piston that is flush to the pipe wall and sized in such a way that the maximum pressure is the set pressure. Current tolerances are +/- 0.5 psi on the set pressure, so it may work. I am hoping that these devices will work like an HIPS system (without all of the pain and the ASME Section VIII endorsement for PRDs). I know that block valves are being replaced with flush pistons and virtually eliminating deposition and corrosion concerns (no dead space). Once the means of overpressure protection has been decided, the next question is the ASME VII requirement for venting the relieved vapors to a safe location. The disposition of the relieved vapors can raise almost as many questions as the determination of overpressure protection method. Venting disposition – The following discussion is for a rupture pin or ESD that opens after the first condenser and lets the flow out to somewhere. Upstream generally of this location presents a problem (hot air into the flare or other location) and downstream of the first condenser is much more likely to encounter blockage. 1. Venting the stream from the first condenser to an incinerator is generally a problem as it defeats the safety instrumented protection against flameout then re-ignition. This is primarily a problem if the stream is flammable (and they usually are until the very end). Should the venting event snuff the flame, then the possibility exists that the flammable stream will ignite somewhere in the piping between the burner and the incinerator outlet (internal explosion). 2. Venting the stream to the flare is also not advisable as the system will frequently have shut- down logic which could isolated the acid gas but not the blower and blow air into the flare header. After passing through the inlet furnace, reactor, waste heat boiler and 1st sulfur condenser, the air will still be above 600°F and injecting even small quantities of high temperature air into a flare header is not a good idea. (see above).
  • 4. Smith & Burgess LLC Consulting www.smithburgess.com Page | 3 3. Similarly, venting through the sulfur pits has the problem of over-pressuring the sulfur pit and/or poor dispersion. Not to mention that if the facility is forced to isolate the sulfur pit with the SulTraps, this option is gone! 4. Seemingly the best option is a dedicated vent stack that is high enough to prevent unacceptable concentrations of H2S at grade or nearby elevated structures. General Concerns 1. The location of the relief protection must account for all the aforementioned problems. 2. SIL-III systems are generally extremely costly to install and maintain due to the number of feeds to the system (may be over 10 that can overpressure a single SRU train). 3. Relief protection, should it be provided, will have to act above the existing shutdown system but below the MAWP or sulfur seal pressure. 4. Back flowing acid gas through the inlet of the blower is very bad and has actually killed workers in the past in Europe. Any system should not stop the blower but isolate the air inlet from the process and all the anti-surge control system to divert the discharge to atmosphere. We should also check the blower and ensure that there is some means to stop the backflow of acid gas.