SlideShare a Scribd company logo
1 of 83
PROTECTIVE RELAYING
INTRODUCTION
Protective Relaying - Introduction
Requires knowledge of :
Equipments to be protected
Behavior of equipment
Faults in an equipment
Protection philosophies
Terminologies used
Protective Relaying - Introduction
Requires knowledge of :
IEEE notations
Protection schemes
Single line diagram
Symmetrical components
Electronics
Communication methods
Power System - Objective
• To generate and supply electrical energy to
the consumers - reliably and economically
• Better reliability can be achieved by
improved system design, allowing for
sufficient spare capacity, considering future
additions and/or expansions
Power Systems Protection -Introduction
Power System Components
1. Generators
2. Transformers
3. Transmission Lines
4. Feeders
5. Motors
6. Capacitor Banks
7. Bus Bars
Protection
WHY?
Why Protection?
• Personnel injury protection
– Guarding
– Equipment accessibility
– Safety procedures
• Equipment & system damage control
• System co-ordination & selectivity
Protection philosophy
EQUIPMENT SPECIFIC
RELATED TO AGE / SIZE OF EQPT
SPLIT INTO MULTIPLE ZONES
PRIMARY PROTECTION
BACK UP PROTECTION
UTILITY MANDATE
CO-ORDINATION
Objectives of protection
Prevent deterioration by disconnecting
circuits & equipments subjected to :
• Overload
• Over-temperature
• Under-over voltages
• Unbalanced currents
• Under – over frequency
Objectives of protection
• Loss of field
• Loss of synchronization
• Anti-motoring
• Reverse power
• Reverse current
• Phase reversal &
• Open phase
Objectives of protection
Limit damage by disconnecting circuits
& equipments subjected to :
• Short circuits
• Earth faults
Power Systems Protection -Introduction
Protection – Purpose
• To detect abnormalities (faults)
• To eliminate such abnormality
- by isolating the smallest portion of the system
in the shortest period of time
• To prevent injury to personnel
• To prevent damage to equipment
Power Systems Protection -Introduction
Protective Relay – What should it do ?
• Monitor system parameters continuously
(V, I, P, F)
• Operate quickly when necessary
(Dependability)
• Should not operate wrongly
(stability, discrimination)
Protective Relaying
Design of Protective Schemes
• General Philosophy
• Reliability (Dependability and Security)
• Sensitivity
• Speed of operation
• Economics
• Simplicity
Protection Relaying
fundamental requirements
• Selectivity
• Stability
• Speed
• Sensitivity
The 4 ‘S’ of a Protection Scheme
• Selectivity: When a fault occurs, the
protection system is required to select and
trip only the nearest circuit breakers. This
property of selective tripping is also called
discrimination. This can either be a current
based discrimination or a time based
discrimination or a combination of both.
The 4 ‘S’ of a Protection Scheme
• Stability: This is the ability of the protection
system to remain inert to all load conditions
and faults external to the relevant zone of
the protection scheme. This is of particular
importance in Unit Protection Schemes
(e.g.) Differential Protection, REF
Protection, etc.
The 4 ‘S’ of a Protection Scheme
• Speed: The primary function of a
protection scheme is to detect and isolate
faults from a power system in a very short
time than which could be achieved
manually. This is to safeguard continuity of
supply to healthier portions, by removing
each disturbance , before it leads to wide
spread loss and/or plant shut downs.
The 4 ‘S’ of a Protection Scheme
• Sensitivity: This refers to the minimum
operating quantity requirements of a
complete protection system. A protection
system is said to be sensitive, if the
operating quantity is low. But, with respect
to individual relays, it is not the current or
voltage, but the VA consumption of the
relay at the minimum operating quantity.
Device Function Numbers (ANSI/IEEE Codes)
The devices in the switching equipment are denoted
by numbers, with appropriate suffix letters when
necessary, according to the functions they perform.
These numbers are based on a system adopted as
standard for automatic switchgear by IEEE and are
incorporated in American Standard (ANSI) C37.2-
1970.
This system is used in connection diagrams, in
instruction booklets and in specifications to designate
the relays and other devices to save text and space.
Power Systems Protection -Introduction
Protection – ANSI Codes
Code numbers
Used to denote
Protections
On a SLD
Power Systems Protection -Introduction
Zone of protection
The zone of protection of relay or
circuit breaker trip device is that
segment of the power system in
which the occurrence of assigned
abnormal conditions should cause the
protective device to operate
Protective Relaying
Design of Protective Schemes
Zones of Protection
Protective Relaying
Design of Protective Schemes
Zones of Protection
Protective Relaying
Design of Protective Schemes
Zones of Protection
Protective Relaying
Design of Protective Schemes
Zones of Protection
Protective Relaying
Design of Protective Schemes
Zones of Protection
Zones of Protection
Protective Relaying
Design of Protective Schemes
Protective Relaying
Design of Protective Schemes
Zones of Protection
Zones of protection
ZONE 1
ZONE 4
ZONE 3
ZONE 2 ZONE 5
Protection
Primary Protection
First line of defence
Is responsible to protect the power system
elements from all types of faults
(e.g.- High speed differential relay,Instantaneous overcurrent relay)
Back-up Protection
Operates only if primary protection fails
(e.g.phase time overcurrent relay)
Power Systems Protection -Introduction
Protective Relay Scheme – What is it ?
• A protective relay
• CT / PT
• Auxiliary Power supply (24 V to 240 V AC/ DC)
• Switching device ( Breaker/ Contactor)
• Trip Coil
• Alarm / Trip contact
• Control Wiring
Protective relaying
basic structure
INPUT MEASURING
ELEMENT
COMPARING
ELEMENT
CONTOL
ELEMENT
Power system
quantities
Tripping
Inputs to Protective relays
OVER CURRENT RELAYS CURRENT
UNDER / OVER VOLTAGE RELAYS VOLTAGE
SYNCHRONISING RELAYS
FREQUENCY RELAYS
DISTANCE RELAYS CURRENT &
DIRECTIONAL RELAYS VOLTAGE
REVERSE POWER RELAYS POWER
SUDDEN PRESSURE RELAY PRESSURE
OVER TEMPERATURE RELAY TEMPERATURE
Measuring element
Current Transformer
Voltage Transformer
Inductive coupling
Electrical isolation
Reduced power quantities (magnitude)
Comparing element or
Comparator
Comparison is made on the basis of
amplitude, relative phase or
combination of amplitude & relative
phase.
• Single input – Electromagnetic
• Multi input – Static
• Output – Mechanical torque /
Electrical signal
Control element
Operated in one direction or other by
the output of comparator and it
controls tripping of circuit breaker.
Trip element
Trip coil associated with circuit
breaker.
Protective relays - Terminology
SETTINGS
PICK UP
LOW SET
HIGH SET
TMS
STEPS
TIME DELAYS
INSTANTANEOUS
INVERSE TIME
DEFINITE TIME
RATINGS
CT
PT
AUX. POWER
BURDEN
CT INPUT
PT INPUT
DIRECT SEQUENCE
NEGATIVE SEQUENCE
ZERO SEQUENCE
VECTORS
CURRENT
VOLTAGE
IMPEDANCE
MACHINE RELATED
PERCENT. IMPEDANCE
FULL LOAD RATING
TIME CONSTANT
OVER LOAD CHAR.
SYSTEM
GROUNDED
UNGROUNDED
RESISTANCE GROUNDED
OPERATIONAL
MASTER TRIP
LOCK OUT
RESTRAINTS
INTER TRIP
BLOCKING
FLAG
SELF RESET
HAND RESET
MANUAL RESET
RELAY TEST
ANALYSIS
TRIP DATA
W/F CAPTURE
DIAGNOSTICS
CONNECTIONS
RESIDUAL
OPEN DELTA
CBCT
Power System - Faults
Current
Over Load
Over Current
Earth Fault
Current Unbalance
Dir. Over Current
Dir. Earth Fault
Voltage
Over Voltage
Under Voltage
Voltage Unbalance
Neutral shift
Frequency
Over Frequency
Under Frequency
dF/dT
Power
Active power
Reactive power
Over power
Under power
Reverse power
Computed
Over fluxing
Loss of field
Differential O/C
Restricted E/F
Under Impedance
Control/Management
Synchronizing
Islanding
Load shedding
Power Systems Protection -Introduction
Power System – Fault Handling
Trip & Isolate
Breaker is tripped on fault
Faulty section is isolated
Control & Regulate
Breaker is not tripped
Corrective actions
Generated on line
Power Systems Protection -Introduction
Power Systems Protection -Introduction
Relay operation when a fault occurs
• Each relay should protect a
specific zone in the system
• If fault is inside its zone,
relay should operate and isolate the zone
• If fault is outside zone,
Relay should not operate –
Some other relay should operate and isolate
Power Systems Protection -Introduction
What happens when a fault occurs
• Fault current flows through number of relays
• Some of these relays will start to operate
• Only one relay should trip and
interrupt fault current
• Remaining relays will reset after above
Protection Relays – Inputs / Out puts
Inputs
Current CTs
Voltage PTs
Frequency PTs
Power CTs + PTs
Outputs
Trip Contact
Power Systems Protection -Introduction
Protection Relays – Settings
Pick up setting Low set
Highset
Time delay setting Definite time
Inverse time
% of CT
Rating
TMS
Setting
Power Systems Protection -Introduction
Power System – Trip time characteristics
I/Is
t
10
1.3 or
3.0 sec
1.4
LS
Power Systems Protection -Introduction
Power System – Trip time characteristics
I/Is
t
10
1.3 or
3.0 sec
50 msec
6
HS
1.4
LS
Power Systems Protection -Introduction
TMS=1
I/Is=2 I/Is=4 I/Is=6 Is=8 I/Is=10 I/Is=15 I/Is=20
Normal Inv 3 sec 10.13 5.03 3.87 3.33 3 2.54 2.29
Normal Inv 1.3 sec 4.39 2.18 1.68 1.44 1.3 1.1 .99
Very Inverse 13.5 4.5 2.7 1.93 1.5 .96 .71
Extremely Inverse 26.66 5.33 2.28 1.27 0.81 0.36 0.20
Typical Inverse time delays
Power Systems Protection -Introduction
[ A]
t(I) = ---------------- * TMS
[(I/Is)a – 1]
Where,
t(I) = Trip Time in Seconds
I = Fault Current
Is = Set Current
TMS = Time Multiplier Setting
Power System – Trip time characteristics
Inverse time delays – General Algorithm
As per BS 142 & IEC 60255-4
Power Systems Protection -Introduction
Curve Name A a
Normal Inverse 1.3 Sec. 0.0613 0.02
Normal Inverse 3.0 Sec. 0.1414 0.02
Very Inverse 13.5 1
Extremely Inverse 80 2
Power System – Trip time characteristics
Inverse time delays – General Algorithm
Power Systems Protection -Introduction
User’s Expectations
Sense a fault &
Initiate trip contact CONVENTIONAL
Parameter display
Event record
Fault data record
Wave form record
Communication
Control logic
PRESENT DAY
NEEDS
Basic types of Relays
• Magnitude relay
• Directional relay
• Ratio relay
• Differential relay
• Pilot relay
Protective relays - Types
PRIMARY RELAYS O/C + E/F RELAYS
MONITORING RELAYS TRIP CKT / PT FUSE / BF
RECLOSING RELAYS AUTO RECLOSE
REGULATING RELAYS POWER / FREQ / PF.
AUXILIARY RELAYS TEMP / SPEED / LEVEL
SYNCHRONISING RELAYS AUTO / CHECK
Protective relays - Evolution
ELECTRO-MECHANICAL
1900 ONWARDS
SOLID STATE
(LATE 70s)
NUMERICAL
(EARLY 90s)
Electromechanical relays -Structure
Electromechanical relays
ADVANTAGES LIMITATIONS
WELL PROVEN(?) LARGE SIZE
LOW COST INACCURACY
SELF POWERED HIGH BURDEN
LARGE VARIETY
LIMITED PROTECTIONS
DIFFICULT TO CO-ORDINATE
NEED FOR EXTRA HARDWARE
INTROVERT IN NATURE
Solidstate relays - Structure
Solid state relays
ADVANTAGES LIMITATIONS
SMALL SIZE NO COST ADVANTAGE
LOW BURDEN HIGHLY NOISE PRONE
EASY TO MANUF DRIFT IN SETTINGS
INACCURACY
LARGE VARIETY
LIMITED PROTECTIONS
DIFFICULT TO CO-ORDINATE
NEED FOR EXTRA HARDWARE
LOW RELIABILITY
INTROVERT IN NATURE
Increase in system capacities
New problems to be handled
New utility conditions
Low factor of safety on equipments
Trip information / analysis
Co-ordination problems
Self diagnostic feature
Concept of “UNMANNED S/S”
Need for new technology
MICROPROCESSORS
FOR
PROTECTIVE RELAYS
MICROPROCESSOR BASED RELAYS - BACKGROUND WORK
1960s
A FEW CONCEPTS WERE PROPOSED
HARDWARE WAS VERY EXPENSIVE
BENEFITS OF MICROPROCESSORS FOR
RELAYS WERE NOT CLEAR
IEEE ARTICLE “FAULT PROTECTION WITH A
DIGITAL COMPUTER” OUTLINED THE FEASIBILITY &
PROBLEMS ASSOCIATED IN S/S PROTECTION WHEN A
DIGITAL COMPUTER IS USED
MICROPROCESSOR BASED RELAYS - BACKGROUND WORK
1970s
TWO PAPERS WERE PUBLISHED
“DIGITAL CALCULATION OF IMPEDANCE FOR TRANSMISSION LINE PROTECTION”
“ 3 PH TRANSMISSION LINE PROTECTION WITH A DIGITAL COMPUTER”
PROMINENT MANUFACTURERS LIKE WESTINGHOUSE, IBM
STARTED INVESTIGATING S/S COMPUTER SYSTEMS
PHILADELPHIA ELECTRIC & GE INITIATED PROJECTS ON
DIGITAL TECHNIQUES FOR PROTECTION
VARIOUS ALGORITHMS WERE DERIVED FOR
DIGITAL CALCULATION OF PROTECTION PARAMETRS
EXPERIMENTAL SYSTEMS WERE BUILT BY GE & WESTINGHOUSE
TO CHECK ALGORITHMS
FIRST GENERATION OF MICROPROCESSOR BASED RELAYS BUILT
MICROPROCESSOR BASED RELAYS - BACKGROUND WORK
1980s
MAJOR MANUFACTURERS LIKE GE, ABB, GEC , TOSHIBA,
SIEMENS START DESIGN & SALES OF BROAD RANGE OF
PRODUCTS FOR POWER SYSTEM PROTECTION
MICROPROCESSOR IMPROVES PERFORMANCE SPECS
FOR OPERATION IN INDUSTRIAL ENVIRONMENT
MANY PLC BASED SYSTEMS ARE COMMISSIONED IN INDIA BY
L&T, SIEMENS, ECIL ETC.
MANY ELECTRICITY BOARDS & PROCESS PLANTS IN INDIA
START USING MICROPROCESSOR BASED INSTRUMENTS
THE WORD SCADA GETS POPULAR IN INDIA
P[GCIL GOES IN FOR MICROPROCESSOR BASED
DISTANCE RELAYS IN INDIA
MICROPROCESSOR BASED RELAYS - BACKGROUND WORK
1990s
ABB & GEC ALSTOM INTRODUCE RANGE OF
MICROPROCESSOR BASED RELAYS FOR
ALLALL UNIT PROTECTIONS
MAJOR MANUFACTURERS LIKE GE, ABB, GEC , TOSHIBA
START DESIGN & SALES OF BROAD RANGE OF PRODUCTS
FOR POWER SYSTEM PROTECTION
MANY ELECTRICITY BOARDS & PROCESS PLANTS IN INDIA
START USING MICROPROCESSOR BASED INSTRUMENTS
PGCIL GOES IN FOR MICROPROCESSOR BASED
DISTANCE RELAYS IN INDIA
MICROCONTROLLERS / DSPs ARE INTRODUCED IN LATE 90s BY
HARDWARE MANUFACTURERS WHICH HAVE IMPROVED THE
SPEED OF OPERATION.
MICROPROCESSOR BASED RELAYS - BACKGROUND WORK
1995
L&T COMES OUT WITH RANGE OF
MICROPROCESSOR BASED RELAYS
IN ASSOCIATION WITH
MICROELETTRICA SCIENTIFICA OF ITALY
ABB COINS THE WORD “NUMERIC RELAYS”
FOR ALL RELAYS WITH MICRO CONTROLLER
Micro-processor based relays
Offer best solution for present day relaying
due to following:
• Intelligent devices
• Can implement complex algorithms
• Oscillographic information
• Networking
• Multi – functions
• Self diagnostics
• User friendly
Numeric relays
- It is an improvement over relays with
Microprocessor
- Heart of the system is a micro-
controller
- Entire operation is based on handling
a set of 8 - bit numbers
Protective relays – Comparison
ELECTRO SOLID-STATE NUMERICAL
MECHANICAL
INPUT PEAK S/H CIRCUITS
SENSING COIL DETECTOR A/D CONVERTERS
SETTINGS TAPS ANALOG REF DIGTAL NUMBER
COMPARISON TORQUE ANALOG DIGITAL NUMBER
VOLTAGE
ALGORITHM/ RLC GAIN ADJ. ARITHMATIC
PARAMETER SCALAR SCALAR VECTORIAL
IDENTITY
OUT PUT PHYSICAL DRIVERS LOGIC ARRAY
PARAMETER NUMERIC CONVENTIONAL
ACCURACY 1% 5% / 7.5%
BURDEN < 0.5 VA > 5 VA
SETTING RANGES WIDE LIMITED
MULTI FUNCTIONALITY YES NO
SIZE SMALL LARGE
FIELD PROGRAMMABILITY YES NO
PARAMETER DISPLAY YES NO
SYSTEM FLEXILBILITY YES NO
CO-ORDINATION TOOLS MANY TWO
COMMUNICATION YES NO
REMOTE CONTROL YES NO
SPECIALALGORITHMS MANY LIMITED
SPECIAL PROTECTIONS YES NO
SELF DIAGNOSTICS YES NO
ADVANTAGES OF NUMERIC RELAYS
Numeric relays
ADVANTAGES OVER
ELECTROMECHANICAL RELAYS
1. FIELD PROGRAMMABILITY
2. PARAMETER DISPLAY
3. SYSTEM FLEXIBILITY
4. CO-ORDINATION
5. COMMUNICATION
6. REMOTE CONTROL
7. SPECIAL ALGORITHMS
8. SUPERIOR PROTECTION
Numeric relays
BENIFITS TO OWNER
1. ADVANCED PERFORMANCE
2. REDUCED EQUIPMENT SIZE
3. STANDARDIZED HARDWARE
4. EASY MAINTENANCE
5. REDUCED BURDEN ON CT/PT
6. OVERALL ECONOMY
Numeric relays
UNIT PROTECTION
FEEDERS
TRANSFORMERS
GENERATORS
MOTORS
CAPACITOR BANKS
BUS BARS
CONTROLS
SYNCHRONISING
ISLANDING
LOAD SHARING
LOAD SHEDDING
DISTANCE
PROTECTION
TRANSMISSION LINES
OTHERS
I/O MODULES
INTERFACES
SOFTWARE
INTEGRATED
SOLUTION FOR
PROTECTION &
CONTROL
C&R PANELS
DIS-ADVANTAGES OF NUMERIC RELAYS
SOFTWARE INTENSIVE
OBSOLESENCE RATE
EMI / EMC PROBLEMS
FUNCTIONAL BLOCKS OF A NUMERIC RELAY
ANALOG
INPUT
SUB-SYSTEM
DIGITAL
INPUT
SUB-SYSTEM
POWER SUPPLY
MICRO
PROCESSOR
COMMUNICATION
INTERFACE
RAM
ROM
EPROM
FLASH
DIGITAL
OUTPUT
SUB-SYSTEM
D
S
P
ANALOG INPUT SUB SYSTEM
CT
PT
SURGE
SUPPRESSION
SURGE
SUPPRESSION
ANALOG
FILTER
ANALOG
FILTER
MUX A / D
CONVERTER
MICRO
PROCESSOR
DIGITAL SIGNAL PROCESSORS
Designed for repetitive measurements
Digital filtering
Highly suitable where microprocessor has to do
measurements, logic, communication and other functions
Designed to handle one instructions per clock cycle
(microprocessors need many clocks per instruction)
Improves speed of operation
DSP Types :
- Analog Devices 21XX family
- Texas Instruments TMS3XX family
- Motorola 56XXX family
MICROPROCESSORS Vs MICRO CONTROLERS
C
O
N
T
R
O
L
C
O
N
T
R
O
L
Accumulator
Arithmatic Logic
Unit
Data Register
Address Register
Data Register
Arithmetic Logic
Unit
Address Register
Accumulator
I/O
ROM
RAM
EPROM
Timers
Counters
UART
Microprocessor Micro controller
TYPES OF MEMORY NUMERIC RELAYS
RAM Read / Write Memory. Used for temporary storage
of variables - like sampled data / oscillographic data
EEPROM / Electrically Erasable Programmable Read Only Memory
NOVRAM Non Volatile RAM
Used for storage of data that remains when power off
(CT/PT/machine ratings, trip settings etc.)
ROM Read Only Memory. Masked version used for high volume
production units. Used for storage of specific programmes.
EPROM Electrically Programmable ROM . Used as above.
Easy to programme and reprogram. Adaptable to changes.
FLASH New type of EPROM that can be programmed repeatedly.
EPROM Allows program updates in the field without changing chips.
SELF DIAGNOSTICS - TECHNIQUES USED
RAM Checked by computing a checksum of memory contents and
comparing it against a stored factory value.
RAM Checked by periodically writing a specific data and
reading back the memory contents
A / D Checked by inputting a known value of + / - voltage.
Any off set at a given time, is software corrected.
SETTINGS Checked by checksums or CRC values can be stored and
compared. Often, 2 or 3 copies of settings are stored and
compared.
POWER Checked by monitoring power supply voltage values
SUPPLY from A / D converter.
FILTERS IN NUMERIC RELAYS
NEED FORE FILTERS
PROTECTIVE RELAYS MUST FILTER UNWANTED SIGNALS
AND HANDLE ONLY THOSE NEEDED FOR TRIP CALCULATIONS
Should be able identify and ignore :
- Switch yard noises
- Harmonics
- Exponentially decaying DC offsets
- CCVT Transients
- Reflections from travelling waves
- Capacitive series compensation
TYPES OF SIGNALS REQUIRED
FOR PROPER PROTECTION
Current, Voltage and Distance Relays :
Require fundamental frequency component signals.
All other signals will interfere with protection process.
Harmonic Restraint Relays :
Require both the fundamental & the Harmonic components ,
each value separately, for decision making process.
STANDARDS FOR RELAYS
• IS 3231 – 1986 Specification for electrical
relays for power system protection .
• IS 1885 – 1966 Electro-technical
PART IX Vocabulary, Electrical relays .
• BS 142 - 1966 Specification for electrical
protective relays.
• BS 3950 – 1965 Specification for electrical
protective system for a.c.plant .
• IS 8686 – 1977 Specification for static protective
relay.
• IS 9124 – 1979 Guide for maintenance and field
testing of relays .
STANDARDS FOR RELAYS
• IS 9124 – 1979 Guide for maintenance and
field testing of relays .
• IS 2705 Part I to IV Specification for
current transformers.
• IS 3156 Part I& II Specification for voltage
transformers .
• BS 3978 – 1973 Specification for current
transformers.
• IS 3842 1972 Application guide for elect.
relays

More Related Content

Similar to PROTECTIVE RELAYING INTRODUCTION

Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1Md Irshad Ahmad
 
Relay Generation and history
Relay Generation and historyRelay Generation and history
Relay Generation and historyDr.Amber Gad
 
Power System Protection
Power System ProtectionPower System Protection
Power System ProtectionRahul Mehra
 
Power System Protection (Primary & Backup)
Power System Protection (Primary & Backup)Power System Protection (Primary & Backup)
Power System Protection (Primary & Backup)Kamran Gillani
 
protectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.pptprotectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.pptThien Phan Bản
 
protectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.pptprotectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.pptThien Phan Bản
 
Power system Protection Services in India
Power system Protection Services in IndiaPower system Protection Services in India
Power system Protection Services in IndiaSystem Protection
 
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptxMuhd Hafizi Idris
 
Measurement and Relay Indications.pptx
Measurement and Relay Indications.pptxMeasurement and Relay Indications.pptx
Measurement and Relay Indications.pptxEngrSyedGhulamMustaf
 
Powerprotection 1421105031
Powerprotection 1421105031Powerprotection 1421105031
Powerprotection 1421105031Chandana Mallik
 
2_Intro Protection + Protection CT.pdf
2_Intro Protection + Protection CT.pdf2_Intro Protection + Protection CT.pdf
2_Intro Protection + Protection CT.pdfLiewChiaPing
 
Switch gear and protection
Switch gear and protectionSwitch gear and protection
Switch gear and protectionDinesh Sharma
 
Switchgear and Protection Engineering Lecture 01.pptx
Switchgear and Protection Engineering Lecture 01.pptxSwitchgear and Protection Engineering Lecture 01.pptx
Switchgear and Protection Engineering Lecture 01.pptxLoitaFredy
 
FUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONFUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONPower System Operation
 
Power System Protection course - Part I
Power System Protection course - Part IPower System Protection course - Part I
Power System Protection course - Part ISlides Hub
 
Power system protection seminar report
Power system protection seminar reportPower system protection seminar report
Power system protection seminar reportRahul Aman
 
Switchgear and Protection ...........................
Switchgear and Protection ...........................Switchgear and Protection ...........................
Switchgear and Protection ...........................MANOJ KHARADE
 
Switchgear and Protection.................
Switchgear and Protection.................Switchgear and Protection.................
Switchgear and Protection.................MANOJ KHARADE
 
Power_System_Protection Lecture-1.pdf
Power_System_Protection Lecture-1.pdfPower_System_Protection Lecture-1.pdf
Power_System_Protection Lecture-1.pdfYogeshGairola2
 

Similar to PROTECTIVE RELAYING INTRODUCTION (20)

Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1
 
Relay Generation and history
Relay Generation and historyRelay Generation and history
Relay Generation and history
 
Power System Protection
Power System ProtectionPower System Protection
Power System Protection
 
Power System Protection (Primary & Backup)
Power System Protection (Primary & Backup)Power System Protection (Primary & Backup)
Power System Protection (Primary & Backup)
 
protectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.pptprotectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.ppt
 
protectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.pptprotectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.ppt
 
Power system Protection Services in India
Power system Protection Services in IndiaPower system Protection Services in India
Power system Protection Services in India
 
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
 
Measurement and Relay Indications.pptx
Measurement and Relay Indications.pptxMeasurement and Relay Indications.pptx
Measurement and Relay Indications.pptx
 
Powerprotection 1421105031
Powerprotection 1421105031Powerprotection 1421105031
Powerprotection 1421105031
 
2_Intro Protection + Protection CT.pdf
2_Intro Protection + Protection CT.pdf2_Intro Protection + Protection CT.pdf
2_Intro Protection + Protection CT.pdf
 
PSG UNIT I.pdf
PSG UNIT I.pdfPSG UNIT I.pdf
PSG UNIT I.pdf
 
Switch gear and protection
Switch gear and protectionSwitch gear and protection
Switch gear and protection
 
Switchgear and Protection Engineering Lecture 01.pptx
Switchgear and Protection Engineering Lecture 01.pptxSwitchgear and Protection Engineering Lecture 01.pptx
Switchgear and Protection Engineering Lecture 01.pptx
 
FUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONFUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTION
 
Power System Protection course - Part I
Power System Protection course - Part IPower System Protection course - Part I
Power System Protection course - Part I
 
Power system protection seminar report
Power system protection seminar reportPower system protection seminar report
Power system protection seminar report
 
Switchgear and Protection ...........................
Switchgear and Protection ...........................Switchgear and Protection ...........................
Switchgear and Protection ...........................
 
Switchgear and Protection.................
Switchgear and Protection.................Switchgear and Protection.................
Switchgear and Protection.................
 
Power_System_Protection Lecture-1.pdf
Power_System_Protection Lecture-1.pdfPower_System_Protection Lecture-1.pdf
Power_System_Protection Lecture-1.pdf
 

More from Satish Pydimarla

Testing_of_transformers_adjusted.ppt
Testing_of_transformers_adjusted.pptTesting_of_transformers_adjusted.ppt
Testing_of_transformers_adjusted.pptSatish Pydimarla
 
Zaragoza Factory_Our product_ EN.ppt
Zaragoza Factory_Our product_ EN.pptZaragoza Factory_Our product_ EN.ppt
Zaragoza Factory_Our product_ EN.pptSatish Pydimarla
 
transformerprotection-180102061059.pdf
transformerprotection-180102061059.pdftransformerprotection-180102061059.pdf
transformerprotection-180102061059.pdfSatish Pydimarla
 
3-Phase-Transformer (1).pptx
3-Phase-Transformer (1).pptx3-Phase-Transformer (1).pptx
3-Phase-Transformer (1).pptxSatish Pydimarla
 
Presentation-Kalinga Stadium.pptx
Presentation-Kalinga Stadium.pptxPresentation-Kalinga Stadium.pptx
Presentation-Kalinga Stadium.pptxSatish Pydimarla
 
understandingtransformervectorgroup-180629014651.pptx
understandingtransformervectorgroup-180629014651.pptxunderstandingtransformervectorgroup-180629014651.pptx
understandingtransformervectorgroup-180629014651.pptxSatish Pydimarla
 
transformeronno-load-200825063948.pptx
transformeronno-load-200825063948.pptxtransformeronno-load-200825063948.pptx
transformeronno-load-200825063948.pptxSatish Pydimarla
 
332038674-Vector-Group-of-Transformers.ppt
332038674-Vector-Group-of-Transformers.ppt332038674-Vector-Group-of-Transformers.ppt
332038674-Vector-Group-of-Transformers.pptSatish Pydimarla
 
Parall Operation Transformers
Parall Operation TransformersParall Operation Transformers
Parall Operation TransformersSatish Pydimarla
 
Understanding_lightning_protection.pptx
Understanding_lightning_protection.pptxUnderstanding_lightning_protection.pptx
Understanding_lightning_protection.pptxSatish Pydimarla
 
Construction of HV Transmission Lines etc.pptx
Construction of HV Transmission Lines etc.pptxConstruction of HV Transmission Lines etc.pptx
Construction of HV Transmission Lines etc.pptxSatish Pydimarla
 

More from Satish Pydimarla (20)

9310091.ppt
9310091.ppt9310091.ppt
9310091.ppt
 
control room.pptx
control room.pptxcontrol room.pptx
control room.pptx
 
Thermovision Test.ppt
Thermovision Test.pptThermovision Test.ppt
Thermovision Test.ppt
 
4143813.ppt
4143813.ppt4143813.ppt
4143813.ppt
 
Transformer_theory.pptx
Transformer_theory.pptxTransformer_theory.pptx
Transformer_theory.pptx
 
Testing_of_transformers_adjusted.ppt
Testing_of_transformers_adjusted.pptTesting_of_transformers_adjusted.ppt
Testing_of_transformers_adjusted.ppt
 
Zaragoza Factory_Our product_ EN.ppt
Zaragoza Factory_Our product_ EN.pptZaragoza Factory_Our product_ EN.ppt
Zaragoza Factory_Our product_ EN.ppt
 
transformerprotection-180102061059.pdf
transformerprotection-180102061059.pdftransformerprotection-180102061059.pdf
transformerprotection-180102061059.pdf
 
3-Phase-Transformer (1).pptx
3-Phase-Transformer (1).pptx3-Phase-Transformer (1).pptx
3-Phase-Transformer (1).pptx
 
Electrical_Engg_Basic.PPT
Electrical_Engg_Basic.PPTElectrical_Engg_Basic.PPT
Electrical_Engg_Basic.PPT
 
Presentation-Kalinga Stadium.pptx
Presentation-Kalinga Stadium.pptxPresentation-Kalinga Stadium.pptx
Presentation-Kalinga Stadium.pptx
 
understandingtransformervectorgroup-180629014651.pptx
understandingtransformervectorgroup-180629014651.pptxunderstandingtransformervectorgroup-180629014651.pptx
understandingtransformervectorgroup-180629014651.pptx
 
transformeronno-load-200825063948.pptx
transformeronno-load-200825063948.pptxtransformeronno-load-200825063948.pptx
transformeronno-load-200825063948.pptx
 
332038674-Vector-Group-of-Transformers.ppt
332038674-Vector-Group-of-Transformers.ppt332038674-Vector-Group-of-Transformers.ppt
332038674-Vector-Group-of-Transformers.ppt
 
tcee-161003100321.pptx
tcee-161003100321.pptxtcee-161003100321.pptx
tcee-161003100321.pptx
 
Parall Operation Transformers
Parall Operation TransformersParall Operation Transformers
Parall Operation Transformers
 
Understanding_lightning_protection.pptx
Understanding_lightning_protection.pptxUnderstanding_lightning_protection.pptx
Understanding_lightning_protection.pptx
 
Understanding VCB.pptx
Understanding VCB.pptxUnderstanding VCB.pptx
Understanding VCB.pptx
 
CT & PT.pptx
CT & PT.pptxCT & PT.pptx
CT & PT.pptx
 
Construction of HV Transmission Lines etc.pptx
Construction of HV Transmission Lines etc.pptxConstruction of HV Transmission Lines etc.pptx
Construction of HV Transmission Lines etc.pptx
 

Recently uploaded

SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 

Recently uploaded (20)

SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 

PROTECTIVE RELAYING INTRODUCTION

  • 2. Protective Relaying - Introduction Requires knowledge of : Equipments to be protected Behavior of equipment Faults in an equipment Protection philosophies Terminologies used
  • 3. Protective Relaying - Introduction Requires knowledge of : IEEE notations Protection schemes Single line diagram Symmetrical components Electronics Communication methods
  • 4. Power System - Objective • To generate and supply electrical energy to the consumers - reliably and economically • Better reliability can be achieved by improved system design, allowing for sufficient spare capacity, considering future additions and/or expansions
  • 5. Power Systems Protection -Introduction Power System Components 1. Generators 2. Transformers 3. Transmission Lines 4. Feeders 5. Motors 6. Capacitor Banks 7. Bus Bars
  • 7. Why Protection? • Personnel injury protection – Guarding – Equipment accessibility – Safety procedures • Equipment & system damage control • System co-ordination & selectivity
  • 8. Protection philosophy EQUIPMENT SPECIFIC RELATED TO AGE / SIZE OF EQPT SPLIT INTO MULTIPLE ZONES PRIMARY PROTECTION BACK UP PROTECTION UTILITY MANDATE CO-ORDINATION
  • 9. Objectives of protection Prevent deterioration by disconnecting circuits & equipments subjected to : • Overload • Over-temperature • Under-over voltages • Unbalanced currents • Under – over frequency
  • 10. Objectives of protection • Loss of field • Loss of synchronization • Anti-motoring • Reverse power • Reverse current • Phase reversal & • Open phase
  • 11. Objectives of protection Limit damage by disconnecting circuits & equipments subjected to : • Short circuits • Earth faults
  • 12. Power Systems Protection -Introduction Protection – Purpose • To detect abnormalities (faults) • To eliminate such abnormality - by isolating the smallest portion of the system in the shortest period of time • To prevent injury to personnel • To prevent damage to equipment
  • 13. Power Systems Protection -Introduction Protective Relay – What should it do ? • Monitor system parameters continuously (V, I, P, F) • Operate quickly when necessary (Dependability) • Should not operate wrongly (stability, discrimination)
  • 14. Protective Relaying Design of Protective Schemes • General Philosophy • Reliability (Dependability and Security) • Sensitivity • Speed of operation • Economics • Simplicity
  • 15. Protection Relaying fundamental requirements • Selectivity • Stability • Speed • Sensitivity
  • 16. The 4 ‘S’ of a Protection Scheme • Selectivity: When a fault occurs, the protection system is required to select and trip only the nearest circuit breakers. This property of selective tripping is also called discrimination. This can either be a current based discrimination or a time based discrimination or a combination of both.
  • 17. The 4 ‘S’ of a Protection Scheme • Stability: This is the ability of the protection system to remain inert to all load conditions and faults external to the relevant zone of the protection scheme. This is of particular importance in Unit Protection Schemes (e.g.) Differential Protection, REF Protection, etc.
  • 18. The 4 ‘S’ of a Protection Scheme • Speed: The primary function of a protection scheme is to detect and isolate faults from a power system in a very short time than which could be achieved manually. This is to safeguard continuity of supply to healthier portions, by removing each disturbance , before it leads to wide spread loss and/or plant shut downs.
  • 19. The 4 ‘S’ of a Protection Scheme • Sensitivity: This refers to the minimum operating quantity requirements of a complete protection system. A protection system is said to be sensitive, if the operating quantity is low. But, with respect to individual relays, it is not the current or voltage, but the VA consumption of the relay at the minimum operating quantity.
  • 20. Device Function Numbers (ANSI/IEEE Codes) The devices in the switching equipment are denoted by numbers, with appropriate suffix letters when necessary, according to the functions they perform. These numbers are based on a system adopted as standard for automatic switchgear by IEEE and are incorporated in American Standard (ANSI) C37.2- 1970. This system is used in connection diagrams, in instruction booklets and in specifications to designate the relays and other devices to save text and space. Power Systems Protection -Introduction
  • 21. Protection – ANSI Codes Code numbers Used to denote Protections On a SLD Power Systems Protection -Introduction
  • 22. Zone of protection The zone of protection of relay or circuit breaker trip device is that segment of the power system in which the occurrence of assigned abnormal conditions should cause the protective device to operate
  • 23. Protective Relaying Design of Protective Schemes Zones of Protection
  • 24. Protective Relaying Design of Protective Schemes Zones of Protection
  • 25. Protective Relaying Design of Protective Schemes Zones of Protection
  • 26. Protective Relaying Design of Protective Schemes Zones of Protection
  • 27. Protective Relaying Design of Protective Schemes Zones of Protection
  • 28. Zones of Protection Protective Relaying Design of Protective Schemes
  • 29. Protective Relaying Design of Protective Schemes Zones of Protection
  • 30. Zones of protection ZONE 1 ZONE 4 ZONE 3 ZONE 2 ZONE 5
  • 31. Protection Primary Protection First line of defence Is responsible to protect the power system elements from all types of faults (e.g.- High speed differential relay,Instantaneous overcurrent relay) Back-up Protection Operates only if primary protection fails (e.g.phase time overcurrent relay)
  • 32. Power Systems Protection -Introduction Protective Relay Scheme – What is it ? • A protective relay • CT / PT • Auxiliary Power supply (24 V to 240 V AC/ DC) • Switching device ( Breaker/ Contactor) • Trip Coil • Alarm / Trip contact • Control Wiring
  • 33. Protective relaying basic structure INPUT MEASURING ELEMENT COMPARING ELEMENT CONTOL ELEMENT Power system quantities Tripping
  • 34. Inputs to Protective relays OVER CURRENT RELAYS CURRENT UNDER / OVER VOLTAGE RELAYS VOLTAGE SYNCHRONISING RELAYS FREQUENCY RELAYS DISTANCE RELAYS CURRENT & DIRECTIONAL RELAYS VOLTAGE REVERSE POWER RELAYS POWER SUDDEN PRESSURE RELAY PRESSURE OVER TEMPERATURE RELAY TEMPERATURE
  • 35. Measuring element Current Transformer Voltage Transformer Inductive coupling Electrical isolation Reduced power quantities (magnitude)
  • 36. Comparing element or Comparator Comparison is made on the basis of amplitude, relative phase or combination of amplitude & relative phase. • Single input – Electromagnetic • Multi input – Static • Output – Mechanical torque / Electrical signal
  • 37. Control element Operated in one direction or other by the output of comparator and it controls tripping of circuit breaker.
  • 38. Trip element Trip coil associated with circuit breaker.
  • 39. Protective relays - Terminology SETTINGS PICK UP LOW SET HIGH SET TMS STEPS TIME DELAYS INSTANTANEOUS INVERSE TIME DEFINITE TIME RATINGS CT PT AUX. POWER BURDEN CT INPUT PT INPUT DIRECT SEQUENCE NEGATIVE SEQUENCE ZERO SEQUENCE VECTORS CURRENT VOLTAGE IMPEDANCE MACHINE RELATED PERCENT. IMPEDANCE FULL LOAD RATING TIME CONSTANT OVER LOAD CHAR. SYSTEM GROUNDED UNGROUNDED RESISTANCE GROUNDED OPERATIONAL MASTER TRIP LOCK OUT RESTRAINTS INTER TRIP BLOCKING FLAG SELF RESET HAND RESET MANUAL RESET RELAY TEST ANALYSIS TRIP DATA W/F CAPTURE DIAGNOSTICS CONNECTIONS RESIDUAL OPEN DELTA CBCT
  • 40. Power System - Faults Current Over Load Over Current Earth Fault Current Unbalance Dir. Over Current Dir. Earth Fault Voltage Over Voltage Under Voltage Voltage Unbalance Neutral shift Frequency Over Frequency Under Frequency dF/dT Power Active power Reactive power Over power Under power Reverse power Computed Over fluxing Loss of field Differential O/C Restricted E/F Under Impedance Control/Management Synchronizing Islanding Load shedding Power Systems Protection -Introduction
  • 41. Power System – Fault Handling Trip & Isolate Breaker is tripped on fault Faulty section is isolated Control & Regulate Breaker is not tripped Corrective actions Generated on line Power Systems Protection -Introduction
  • 42. Power Systems Protection -Introduction Relay operation when a fault occurs • Each relay should protect a specific zone in the system • If fault is inside its zone, relay should operate and isolate the zone • If fault is outside zone, Relay should not operate – Some other relay should operate and isolate
  • 43. Power Systems Protection -Introduction What happens when a fault occurs • Fault current flows through number of relays • Some of these relays will start to operate • Only one relay should trip and interrupt fault current • Remaining relays will reset after above
  • 44. Protection Relays – Inputs / Out puts Inputs Current CTs Voltage PTs Frequency PTs Power CTs + PTs Outputs Trip Contact Power Systems Protection -Introduction
  • 45. Protection Relays – Settings Pick up setting Low set Highset Time delay setting Definite time Inverse time % of CT Rating TMS Setting Power Systems Protection -Introduction
  • 46. Power System – Trip time characteristics I/Is t 10 1.3 or 3.0 sec 1.4 LS Power Systems Protection -Introduction
  • 47. Power System – Trip time characteristics I/Is t 10 1.3 or 3.0 sec 50 msec 6 HS 1.4 LS Power Systems Protection -Introduction
  • 48. TMS=1 I/Is=2 I/Is=4 I/Is=6 Is=8 I/Is=10 I/Is=15 I/Is=20 Normal Inv 3 sec 10.13 5.03 3.87 3.33 3 2.54 2.29 Normal Inv 1.3 sec 4.39 2.18 1.68 1.44 1.3 1.1 .99 Very Inverse 13.5 4.5 2.7 1.93 1.5 .96 .71 Extremely Inverse 26.66 5.33 2.28 1.27 0.81 0.36 0.20 Typical Inverse time delays Power Systems Protection -Introduction
  • 49. [ A] t(I) = ---------------- * TMS [(I/Is)a – 1] Where, t(I) = Trip Time in Seconds I = Fault Current Is = Set Current TMS = Time Multiplier Setting Power System – Trip time characteristics Inverse time delays – General Algorithm As per BS 142 & IEC 60255-4 Power Systems Protection -Introduction
  • 50. Curve Name A a Normal Inverse 1.3 Sec. 0.0613 0.02 Normal Inverse 3.0 Sec. 0.1414 0.02 Very Inverse 13.5 1 Extremely Inverse 80 2 Power System – Trip time characteristics Inverse time delays – General Algorithm Power Systems Protection -Introduction
  • 51. User’s Expectations Sense a fault & Initiate trip contact CONVENTIONAL Parameter display Event record Fault data record Wave form record Communication Control logic PRESENT DAY NEEDS
  • 52. Basic types of Relays • Magnitude relay • Directional relay • Ratio relay • Differential relay • Pilot relay
  • 53. Protective relays - Types PRIMARY RELAYS O/C + E/F RELAYS MONITORING RELAYS TRIP CKT / PT FUSE / BF RECLOSING RELAYS AUTO RECLOSE REGULATING RELAYS POWER / FREQ / PF. AUXILIARY RELAYS TEMP / SPEED / LEVEL SYNCHRONISING RELAYS AUTO / CHECK
  • 54. Protective relays - Evolution ELECTRO-MECHANICAL 1900 ONWARDS SOLID STATE (LATE 70s) NUMERICAL (EARLY 90s)
  • 56. Electromechanical relays ADVANTAGES LIMITATIONS WELL PROVEN(?) LARGE SIZE LOW COST INACCURACY SELF POWERED HIGH BURDEN LARGE VARIETY LIMITED PROTECTIONS DIFFICULT TO CO-ORDINATE NEED FOR EXTRA HARDWARE INTROVERT IN NATURE
  • 57. Solidstate relays - Structure
  • 58. Solid state relays ADVANTAGES LIMITATIONS SMALL SIZE NO COST ADVANTAGE LOW BURDEN HIGHLY NOISE PRONE EASY TO MANUF DRIFT IN SETTINGS INACCURACY LARGE VARIETY LIMITED PROTECTIONS DIFFICULT TO CO-ORDINATE NEED FOR EXTRA HARDWARE LOW RELIABILITY INTROVERT IN NATURE
  • 59. Increase in system capacities New problems to be handled New utility conditions Low factor of safety on equipments Trip information / analysis Co-ordination problems Self diagnostic feature Concept of “UNMANNED S/S” Need for new technology
  • 61. MICROPROCESSOR BASED RELAYS - BACKGROUND WORK 1960s A FEW CONCEPTS WERE PROPOSED HARDWARE WAS VERY EXPENSIVE BENEFITS OF MICROPROCESSORS FOR RELAYS WERE NOT CLEAR IEEE ARTICLE “FAULT PROTECTION WITH A DIGITAL COMPUTER” OUTLINED THE FEASIBILITY & PROBLEMS ASSOCIATED IN S/S PROTECTION WHEN A DIGITAL COMPUTER IS USED
  • 62. MICROPROCESSOR BASED RELAYS - BACKGROUND WORK 1970s TWO PAPERS WERE PUBLISHED “DIGITAL CALCULATION OF IMPEDANCE FOR TRANSMISSION LINE PROTECTION” “ 3 PH TRANSMISSION LINE PROTECTION WITH A DIGITAL COMPUTER” PROMINENT MANUFACTURERS LIKE WESTINGHOUSE, IBM STARTED INVESTIGATING S/S COMPUTER SYSTEMS PHILADELPHIA ELECTRIC & GE INITIATED PROJECTS ON DIGITAL TECHNIQUES FOR PROTECTION VARIOUS ALGORITHMS WERE DERIVED FOR DIGITAL CALCULATION OF PROTECTION PARAMETRS EXPERIMENTAL SYSTEMS WERE BUILT BY GE & WESTINGHOUSE TO CHECK ALGORITHMS FIRST GENERATION OF MICROPROCESSOR BASED RELAYS BUILT
  • 63. MICROPROCESSOR BASED RELAYS - BACKGROUND WORK 1980s MAJOR MANUFACTURERS LIKE GE, ABB, GEC , TOSHIBA, SIEMENS START DESIGN & SALES OF BROAD RANGE OF PRODUCTS FOR POWER SYSTEM PROTECTION MICROPROCESSOR IMPROVES PERFORMANCE SPECS FOR OPERATION IN INDUSTRIAL ENVIRONMENT MANY PLC BASED SYSTEMS ARE COMMISSIONED IN INDIA BY L&T, SIEMENS, ECIL ETC. MANY ELECTRICITY BOARDS & PROCESS PLANTS IN INDIA START USING MICROPROCESSOR BASED INSTRUMENTS THE WORD SCADA GETS POPULAR IN INDIA P[GCIL GOES IN FOR MICROPROCESSOR BASED DISTANCE RELAYS IN INDIA
  • 64. MICROPROCESSOR BASED RELAYS - BACKGROUND WORK 1990s ABB & GEC ALSTOM INTRODUCE RANGE OF MICROPROCESSOR BASED RELAYS FOR ALLALL UNIT PROTECTIONS MAJOR MANUFACTURERS LIKE GE, ABB, GEC , TOSHIBA START DESIGN & SALES OF BROAD RANGE OF PRODUCTS FOR POWER SYSTEM PROTECTION MANY ELECTRICITY BOARDS & PROCESS PLANTS IN INDIA START USING MICROPROCESSOR BASED INSTRUMENTS PGCIL GOES IN FOR MICROPROCESSOR BASED DISTANCE RELAYS IN INDIA MICROCONTROLLERS / DSPs ARE INTRODUCED IN LATE 90s BY HARDWARE MANUFACTURERS WHICH HAVE IMPROVED THE SPEED OF OPERATION.
  • 65. MICROPROCESSOR BASED RELAYS - BACKGROUND WORK 1995 L&T COMES OUT WITH RANGE OF MICROPROCESSOR BASED RELAYS IN ASSOCIATION WITH MICROELETTRICA SCIENTIFICA OF ITALY ABB COINS THE WORD “NUMERIC RELAYS” FOR ALL RELAYS WITH MICRO CONTROLLER
  • 66. Micro-processor based relays Offer best solution for present day relaying due to following: • Intelligent devices • Can implement complex algorithms • Oscillographic information • Networking • Multi – functions • Self diagnostics • User friendly
  • 67. Numeric relays - It is an improvement over relays with Microprocessor - Heart of the system is a micro- controller - Entire operation is based on handling a set of 8 - bit numbers
  • 68. Protective relays – Comparison ELECTRO SOLID-STATE NUMERICAL MECHANICAL INPUT PEAK S/H CIRCUITS SENSING COIL DETECTOR A/D CONVERTERS SETTINGS TAPS ANALOG REF DIGTAL NUMBER COMPARISON TORQUE ANALOG DIGITAL NUMBER VOLTAGE ALGORITHM/ RLC GAIN ADJ. ARITHMATIC PARAMETER SCALAR SCALAR VECTORIAL IDENTITY OUT PUT PHYSICAL DRIVERS LOGIC ARRAY
  • 69. PARAMETER NUMERIC CONVENTIONAL ACCURACY 1% 5% / 7.5% BURDEN < 0.5 VA > 5 VA SETTING RANGES WIDE LIMITED MULTI FUNCTIONALITY YES NO SIZE SMALL LARGE FIELD PROGRAMMABILITY YES NO PARAMETER DISPLAY YES NO SYSTEM FLEXILBILITY YES NO CO-ORDINATION TOOLS MANY TWO COMMUNICATION YES NO REMOTE CONTROL YES NO SPECIALALGORITHMS MANY LIMITED SPECIAL PROTECTIONS YES NO SELF DIAGNOSTICS YES NO ADVANTAGES OF NUMERIC RELAYS
  • 70. Numeric relays ADVANTAGES OVER ELECTROMECHANICAL RELAYS 1. FIELD PROGRAMMABILITY 2. PARAMETER DISPLAY 3. SYSTEM FLEXIBILITY 4. CO-ORDINATION 5. COMMUNICATION 6. REMOTE CONTROL 7. SPECIAL ALGORITHMS 8. SUPERIOR PROTECTION
  • 71. Numeric relays BENIFITS TO OWNER 1. ADVANCED PERFORMANCE 2. REDUCED EQUIPMENT SIZE 3. STANDARDIZED HARDWARE 4. EASY MAINTENANCE 5. REDUCED BURDEN ON CT/PT 6. OVERALL ECONOMY
  • 72. Numeric relays UNIT PROTECTION FEEDERS TRANSFORMERS GENERATORS MOTORS CAPACITOR BANKS BUS BARS CONTROLS SYNCHRONISING ISLANDING LOAD SHARING LOAD SHEDDING DISTANCE PROTECTION TRANSMISSION LINES OTHERS I/O MODULES INTERFACES SOFTWARE INTEGRATED SOLUTION FOR PROTECTION & CONTROL C&R PANELS
  • 73. DIS-ADVANTAGES OF NUMERIC RELAYS SOFTWARE INTENSIVE OBSOLESENCE RATE EMI / EMC PROBLEMS
  • 74. FUNCTIONAL BLOCKS OF A NUMERIC RELAY ANALOG INPUT SUB-SYSTEM DIGITAL INPUT SUB-SYSTEM POWER SUPPLY MICRO PROCESSOR COMMUNICATION INTERFACE RAM ROM EPROM FLASH DIGITAL OUTPUT SUB-SYSTEM D S P
  • 75. ANALOG INPUT SUB SYSTEM CT PT SURGE SUPPRESSION SURGE SUPPRESSION ANALOG FILTER ANALOG FILTER MUX A / D CONVERTER MICRO PROCESSOR
  • 76. DIGITAL SIGNAL PROCESSORS Designed for repetitive measurements Digital filtering Highly suitable where microprocessor has to do measurements, logic, communication and other functions Designed to handle one instructions per clock cycle (microprocessors need many clocks per instruction) Improves speed of operation DSP Types : - Analog Devices 21XX family - Texas Instruments TMS3XX family - Motorola 56XXX family
  • 77. MICROPROCESSORS Vs MICRO CONTROLERS C O N T R O L C O N T R O L Accumulator Arithmatic Logic Unit Data Register Address Register Data Register Arithmetic Logic Unit Address Register Accumulator I/O ROM RAM EPROM Timers Counters UART Microprocessor Micro controller
  • 78. TYPES OF MEMORY NUMERIC RELAYS RAM Read / Write Memory. Used for temporary storage of variables - like sampled data / oscillographic data EEPROM / Electrically Erasable Programmable Read Only Memory NOVRAM Non Volatile RAM Used for storage of data that remains when power off (CT/PT/machine ratings, trip settings etc.) ROM Read Only Memory. Masked version used for high volume production units. Used for storage of specific programmes. EPROM Electrically Programmable ROM . Used as above. Easy to programme and reprogram. Adaptable to changes. FLASH New type of EPROM that can be programmed repeatedly. EPROM Allows program updates in the field without changing chips.
  • 79. SELF DIAGNOSTICS - TECHNIQUES USED RAM Checked by computing a checksum of memory contents and comparing it against a stored factory value. RAM Checked by periodically writing a specific data and reading back the memory contents A / D Checked by inputting a known value of + / - voltage. Any off set at a given time, is software corrected. SETTINGS Checked by checksums or CRC values can be stored and compared. Often, 2 or 3 copies of settings are stored and compared. POWER Checked by monitoring power supply voltage values SUPPLY from A / D converter.
  • 80. FILTERS IN NUMERIC RELAYS NEED FORE FILTERS PROTECTIVE RELAYS MUST FILTER UNWANTED SIGNALS AND HANDLE ONLY THOSE NEEDED FOR TRIP CALCULATIONS Should be able identify and ignore : - Switch yard noises - Harmonics - Exponentially decaying DC offsets - CCVT Transients - Reflections from travelling waves - Capacitive series compensation
  • 81. TYPES OF SIGNALS REQUIRED FOR PROPER PROTECTION Current, Voltage and Distance Relays : Require fundamental frequency component signals. All other signals will interfere with protection process. Harmonic Restraint Relays : Require both the fundamental & the Harmonic components , each value separately, for decision making process.
  • 82. STANDARDS FOR RELAYS • IS 3231 – 1986 Specification for electrical relays for power system protection . • IS 1885 – 1966 Electro-technical PART IX Vocabulary, Electrical relays . • BS 142 - 1966 Specification for electrical protective relays. • BS 3950 – 1965 Specification for electrical protective system for a.c.plant . • IS 8686 – 1977 Specification for static protective relay. • IS 9124 – 1979 Guide for maintenance and field testing of relays .
  • 83. STANDARDS FOR RELAYS • IS 9124 – 1979 Guide for maintenance and field testing of relays . • IS 2705 Part I to IV Specification for current transformers. • IS 3156 Part I& II Specification for voltage transformers . • BS 3978 – 1973 Specification for current transformers. • IS 3842 1972 Application guide for elect. relays