SlideShare a Scribd company logo
1 of 22
Download to read offline
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
Measurement and its conversion
1 Mile = 1609.75 Meter
1 Meter = 1000 mm
1 Meter = 100 cm
1 Foot = 30 cm
1 Inch = 2.54 cm
1 Foot = 12 inch
1 inch = 25.4 mm
1 foot = 0.0254 m
1 inch = 0.064 m
1 Foot = 300 mm
1 Foot = 1/12 = 0.304 m
1 Meter = 3.281 Feet
1 Meter = 39.37 inch
1 Inch = 0.083 foot
1 Inch = 1/39.37 = 0.025
1 Acre = 2 Jarib
1 Acre = 8 Canal
1 Canal = 20 Marla
1 Marla =272.5 Sq. /ft.
1 inch = 8 sutar
1 ton = 1000 kg
1 ton = 2204 Lbs
1 CFT = 490 Lbs
1 CUM = 7850 kg
1 Lbs = 2.204 kg
1 Meter = 10 Desimeter
1 Dm = 10 cm
1 cm = 10 mm
1 M3
= 35.32 Ft3
1 M2
= 10.76 Ft2
1 Mile = 5280 Ft
1 Mile = 8 Furlong
1 Mile = 1760 Yards
1 Furlong = 220 Yards
1 Yard = 3 Feet
1 inch = 0.083 Ft
2 inch = 0.16 Ft
3 inch = 0.25 Ft
4 inch = 0.33 Ft
5 inch = 0.41Ft
6 inch = 0.50 Ft
7 inch = 0.58 Ft
8 inch = 0.66 Ft
9 inch = 0.75 Ft
10 inch = 0.83 Ft
11 inch = 0.91 Ft
12 inch = 1 Ft
1 Mile = 0.621504 Acre
1 Acre = 0.4047 Hector
1 Canal = 20 Marla
1 Jerab = 4 Canal
1 Muraba = 25 Acre
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
1 cm = 0.3937 inch 1 Decigram = 10 Centigram
1 Decagram = 10 Gram
1 Hectogram = 10 Decigram
1 kg = 10 Hectogram
1 kg = 2.204 Pounds
1 pound = 16 Ounce
1 Ton = 20 Maan
1 Ton = 1000 kg
10 cm = 1 decimeter
1 Maan = 50 kg
10 decimeter = 1 m
10 m = 1 Decameter
10 Decameter = 1 Hectometer
10 mm = 1 cm
10 Milliliter = 1 Centiliter
10 Centiliter = 1 Decalitre
10 Deciliter = 1 Liter
10 liter = 1 Decaliter
10 Decaliter = 1 Hectoleter
10 Hectoliter = 1 Kiloliter
100 Square meter = 1 Acre
1000 Sq.m = 1 He acre
100 kg = 1 Cointal
10 Cointol = 1 Ton
10 Hectometer = 1 Km
1 Yard = 0.914 m
1 m = 1.09 Yard
1 Meter Square = 10.76 Sft
1 meter cube = 35.32 Cft
1 Marla = 9 Sarsai
1 Sarsai = 30.25 Sft
1 Canal = 5445 Sft
1 Pound = 0.453 kg
1 kg = 9.81 Newton
1 Kilo newton = 1000 Newton
1 Liter = 0.93 kg
1 Kips = 0.93 kg
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
RATE ANALYSIS
I. No of bricks in 1 Cft = 13.5 or 14.2
II. No of bricks in 1 cum = 500 bricks
III. Volume of 1 brick in Foot system = 0.0703 Cft
IV. Volume of one brick in meter system = 0.002 Cum
V. Dry mortar used in masonary work = 30 %
VI. Wet mortar convert to dry mortar then multiplying with 1.27
VII. Wet concrete convert to dry multiply with 1.54
VIII. Volume of 1 cement bag = 1.25 Cft
IX. Volume of one cement bag = 0.035 Cum
X. Weight of steel in 1 Cft = 490 Lbs
XI. Weight of steel in 1 Cum = 7850 kg
XII. Volume of block = 0.3075
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
To Find Quantity In A Foot System
Q No 1: Determine The Quantities Of Various Materials Used In 1804 Cft Brick Works In
Cement Mortar Ratio 1:4.
Solution: Quantity Of Bricks = 1805 Cft
Find Bricks Cement And Sand
1: Bricks
Quantity Of Bricks = 1805 Cft
Volume Of One Brick = 0.0703 Cft
No Of Bricks In 1805 Cft = 1805/0.0703 =25675 Bricks
2: Cement
Dry Mortar Used In Masonary = 30 %
Quantity Of Mortar = 1805 x 30/100 = 541.5 Cft
Sum Of Ratio = 1 + 4 = 5
Cement = 1/5 X 541.5 = 108.3 Cft
Convert It To Bags One Bag Volume = 1.25 Cft
No Of Bags In 108.3 Cft = 108.3/1.25 = 86.64 Or 87 Bags
3: Sand
4/5 x 541.5 = 433.2 Cft
Abstract Of Cost
Bricks brick 1 trip = 12’000 Rs
In one dumper 2000 bricks
2000/2000 = 12000/2000 = 6 Rs 1 brick = 6 Rs
No of bricks= 25675 x 6 = 2’14’050 Rs
Cement Cement 1 trip = 80’000
Price of 1 bag = 400 400/400 = 80’000/400 = 200 1 Cft = 200 Rs
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
No of Cement Bags = 87 87 x 200 = 17400 Rs
Qs: Determine the Quantities of various material to prepare 10 Cum concrete
Ratio 1:2:4.
Sol: Quantity of Material = 10 Cum
Quantity of Dry Material = 10 x 1.54 = 15.4
Ratio of concrete = 1:2:4
Sum of ratio: 1 + 2 + 4 = 7
Cement: 1/7 x 15.4 = 2.2 Cum One bag = 0.035 cum
2.2/0.035 = 62.86 Bags Sand: 2/7 x 15.4 = 4.4 Cum
Bajri: 4/7 x 15.4 = 8.8 Cum
 ________________________$_______________________________________*
D.P.C
Qs: Quantity of D.p.c = 97 sqm thichkness of d.p.c = 2.5 cm Ratio: 1:2:4 Find
The Quantity Of Various Materials.
Sol: Qty of D.p.c = 97 sqm Change it to volume
Thickness of D.p.c + 2.5 cm Change it to meter
2.5/100 = 0.025 Cum
Volume = 97 x 0.025 2.42 Cum
Convert It to Dry = 2.42 x 1.54 = 3.73 cum
Mixing Ratio: 1:2:4
Sum of Ratio = 1 + 2 + 4 = 7
Cement: 1/7 x 3.73 = 0.532 Cum
1 bag = 0.035
0.532/0.035 = 15.2 Bags
Sand: 2/7 x 3.73 1.06 Cum
Bajjri: 4/7 x 3.73 = 2.13 Cum
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
Sand: Sand 1 trip = 2000 Rs
Volume Of Tracter Trally = 150 Cft & Volume of dumper = 750 Cft
We Take The Volume of Trally 150/150 = 2000/150 = 13.33 Cft
433.2 x 13.33 = 5774.55 Rs
Meter System
Qs: Determine The Quantities Of Various Materials Used In 81 Cum Brick Work In
Cement Mortar 1:5.
Sol: Quantity Of Brick = 81 Cum Mortar Mixing Ratio = 1:5
No of bricks in one Cum = 500 Volume of one brick = 0.002 Cum
No of bricks = 81/0.002 = 40500 bricks or 500 x 81 = 40500 Bricks
Quantity of Mortar = 81 x 30/100 = 24.3 Cum
Sum of Ratio = 1 + 5 = 6 Cement: 1/6 x 24.3 = 4.05 Cum
Volume of 1 bag = 0.035 No of bags = 4.05/0.035 = 115 bags
Sand: = 5/6 x 24.3 = 20.24 Cum
 _________________________________$_______________________________*
Blocks
Qs: Determine the Quantity of Various materials used in 113 cft block work in
Cement mortar 1:4.
Sol: Quantity of blocks = 113 Cft Mortar Mixing Ratio = 1:4
Blocks: Volume of one block = 0.3075 Cft
N of Blocks in 113 Cft + 113/0.3075 = 368 Blocks
Quantity of Mortar = 113 x 30/100 = 33.9 Cft Sum Of Ratio = 1 + 4 = 5
Cement: 1/5 x 33.9 = 6.78 Cft One bag = 1.25 Cft 6.78/1.25 = 5.24 Bags
Sand: 4/5 x 33.9 = 27.12 Cft
 ______________________$____________________________________*
Concrete Work
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
Qs: Determine The Quantities of Various Materials to Prepare 100 Cft
Concrete Ratio 1:4:8.
Sol: Quantity of Material = 100 x 1.54 = 154 Cft
Sum of Ratio: 1 + 4 + 8 = 13
Cement: 1/13 x 154 = 11.84 Cft
Convert To Bags 1 bag = 1.25 Cft
11.78/1.25 = 9.47 Bags
Sand: 4/13 x 154 = 47.38 Cft
Bajjri: 8/13 x 154 = 94.76 Cft
Floor
Qs: Prepare Analysis of Rates For a Cocrete Floor Consisting Following Structure.
4 inch Base course of brick ballast 2 inch down size
1 inch under layer of cement concrete Ratio 1:3:6
1.5 inch Topping of Cement concrete 1:2:4
Sol: Brick Ballast = 100 x 0.33 = 33.33 Cft
Under Layer = 1:3:6 1 inch = 1/12 = 0.08 ft.
Qty of under layer = 100 x 0.08 = 8 Cft
Dry Qty of concrete = 8 x 1.54 = 12.32 Cft
Sum of Ratio; 1 + 3 + 6 = 10
Cement: 1/10 x 12.32 = 1.232 Cft Convert to Bag
1 Bag = 1.25 Cft 1.232/1.25 = 0.98 Bags
Sand: 3/10 x 12.32 = 3.09 Cft
Bajjri: 6/10 x 12.32 = 7.39 Cft
Topping: P.c.c = 1:2:4 Thickness = 1.5 inch = 1.5/12 = 0.125 Ft
Qty of Topping = 100 x 0.125 = 12.5 Cft
Dry Qty Of P.c.c = 12.5 x 1.54 = 19.25 Cft
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
Sum of Ratio = 1 + 2 + 4 = 7
Cement: 1/7 x 19.25 = 2.75 Cft Convert to Bags
1 bag = 1.25 Cft 2.75/1.25 = 2.2 Bags
Sand: 2/7 x 19.25 = 5.5 Cft
Bajjri: 4/7 x 19.25 = 11 Cft
Adding The Cft Of Topping And Sub Grade
Cement + Cement: 0.98 + 2.2 = 3.18 bags
Sand + Sand: 3.09 + 5.5 = 8.59 Cft
Bajjri + Bajjri: 7.39 + 11 = 18.39 Cft
Slab
Qs: Length of the slab = 10 Ft Width of the Slab = 9 Ft
Thickness of the Slab = 0.5 Ft Steel = 1.5 %
Mixing Ratio: 1:2:4 Determine tne Anaylsis of Follwing Materials.
Sol: First Calculate Its Quantuty: 1 x 10 x 9 x 0.5 = 45 Cft
Qty Of Cement x Dry Mortar Ratio: 45 x 1.54 = 69.3 Cft
Sum Of Ratio: 1 + 2 + 4 = 7
Cement: 1/7 x 45 = 6.42 Cft Convert To Cement
1 Bag = 1.25 Cft 6.42/1.25 = 5.13 Bags
Sand: 2/7 x 45 = 12.85 Cft
Bajjri: 4/7 x 45 = 25.71 Cft
Steel: 45 x 1.5/100 = 0.675 1 Cft = 490 Lbs
0.675 x 490 = 330.75 Lbs
Change it To Kilogram
330.75/2.204 = 150.06 Kg
Plaster
Qs: Prepare Analysis Of Rates For 1 inch Thick Plaster 100 Sft Long
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
Cement Mortar Ratio: 1:3.
Sol: Unit of Rates = 100 Sft
Thickness = 1 inch 1/12 = 0.08 Ft
Wet Volume of Mortar: 100 x 1/12 = 8.33
Dry Volume of Mortar: 8.33 x 1.27 = 10.58 Cft
Sum of Ratio: 1 + 3 = 4
Cement: ¼ x 10.58 = 2.65 Cft Convert To Bags
1 Bag = 1.25 Cft 2.65/1.25 = 2.12 Bags
Sand: ¾ x 10.58 = 7.93 Cft.
Tiles
Qs: Find the Quantity Of Tiles If Length of Roof = 20 Ft & Width = 15 Ft ?
Sol: First Find The Volume Of Tile Volume = L x B x H
Volume Of Tile; L = 1 Ft , B = 6 inch or 0.5 Ft
1 x 0.5 = 0.5
Now Divide The Sum of area of the Roof With the Tile volume.
Total Area of Roof = 20 x 15 = 300 Sft
Volume of one Tile = 0.5 SqFt
300/0.5 = 600 Tiles
Or: 20 x 15 = 300 300 x 2 = 600 Tiles
Because In Every Row One Tile Adjusted So The Number Of Rows Are 2 So We Multiply it with 2.
Bricks
Qs:Toi Find The Brick in a Room L = 20 Ft, B = 15 Ft, Thickness Of Wall = 0.75 Ft
Height = 10 Ft ?
Sol: In Room We Have 2 Long Walls & 2 Short Wall So We Will Cut Of Two Short
Walls Or Two Long Walls Width To find Actual Quantity.
20 + 0.75 + 0.75 = 21.5 Ft
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
Long Wall: No x L x BThickness
x H = Quantity
Long Wall = 2 x 21.5 x 0.75 x 10 = 322.5 Cft
Short Wall = No x L x B Or Thickness x H = Quantity
Short Wall = 2 x 15 x 0.75 x 10 = 225 Cft
Volume of 1 Brick = 0.0703
Now add Long wall & Short Wall
322.5 + 225 = 547.5 547.5/0.0703 = 7788 or 7800 Bricks
Or 547.5 x 14.2 = 7774.5 or 7800 Bricks
Bars
Qs: Suppose the Web of Bar In Which Have 104 Bars & 10 Ft Long
Find Its Weight in Ton ?
Sol: Thickness Of Bar: 6 Sutar
6/4 = 1.5
104 x 10 x 1.5/2040 = 0.76 Ton
1 Ton = 1000 kg 0.76 x 1000 = 760 Kg.
 __________________________$__________________________________*
Qs: Find The Weight of Bars if L = 20 ft. & B = 10 ft.
Width Wise bar: 5 Length Wise Bar: 10
Sol; L x Length Wise Bar = 20 x 5 = 100
W x Width Wise Bar = 10 x 10 = 100
100 + 100/2204 = 200/2204
0.90 Ton 0.90 x 1000 = 90 kg.
 __________________________$____________________________*
Excavation
QS: To Find Out the amount of Excavation Which Length is 100 Ft
Breadth is 3 Ft & Depth is 4 Ft ?
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
Sol: Volume = L x B x H
100 x 4 x 3 = 1200 Cft
Cost of one Cubic Feet = 5 Rupees
Total Cost = 1200 x 5 = 6000 Rs
Earth Work
Qs: Workout the Quantity of Earth Work Required for an Embankment 150 m Long
& 10 m Wide at the top side Slope is 2:1 & depth at each 30 m interval are 0.60, 1.20
1.40, 1.60, 1.40, & 1.60.
Sol: Abstract of Quantity
R.D Depth B.D S.d2
B.d + Sd2
Mean
Area
Length Quantity
Cutting Filling
0 0.60 6 0.72 6.72 ______ ______ ____ ____
30 1.20 12 2.88 14.88 10.98 30 _____ 324 Cft
60 1.40 14 3.92 15.92 15.40 30 ____ 462 Cft
90 1.60 16 5.12 21.12 18.52 30 ____ 556 Cft
120 1.40 14 3.92 17.92 19.52 30 ____ 556 Cft
150 1.60 16 5.12 21.12 19.52 30 ____ 586 Cft
Total ____ ____ _____ _____ _____ _____ _____ 2513 Cft
 _______________________________$_______________________________________*
Types Of Roads
1. Reinforce Cement Concrete Road { R.C.C }
2. Plain Cement Concrete Road { P.C.C }
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
3. Bitumen Road
4. Asphalt Road
5. Tripple Surface Treatment { T.S.T }
6. Double Surface Treatment { D.S.T }
 __________________________$______________________________________*
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
Blocks
Qs: Find The Blocks Used in A Room Which L is = 18 Ft, B = 14 Ft H = 10 Ft
Thickness = 9 inch or 0.75 Ft ?
Sol: Long Wall : 18 + 0.75 + 0.75 = 19.5
Qty For Long Wall = No x L x Thickness x H = Quantity
2 x 19.5 x 0.75 x 10 = 292.5 Cft
Volume of One Block = 0.3075 Cft
292.5/0.3075 = 951 Blocks
Now Quantity for Short Wall = No x B x Thickness x H = Quantity
2 x 14 x 0.75 x 10 = 210 Cft
210/0.3075 = 682 Blocks
Total Blocks = 1633 Blocks
 ________________________$________________________________________*
Circle Or Well
Qs: Find the Quantity Of Well Which is in circle form Depth is 4 m.
Sol: D = 4 so we addd the thickness of wall 0.15
4 + 0.15 + 0.15 = 4.30
Circle = π x D 3.14 x 4.30 = 13,50 m
No x L x B x H = quantity 1 x 13.50 x 0.30 x 4 = 16.21 Cum
Volume of one Brick = 0.002 Cum 16.21/0.002 = 8105 bricks
Mortar: 1:5 Sum of Ratio: 1 + 5 = 6
Cement: 1/6 x 4.863 = 0.8105 Cum 0.8105/0.035 = 23.15 Bags
Sand: 5/6 x 4.863 = 4.0525 Cum.
____________________________$________________________________________*
Bars On Meter System
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
Qs: Find the Weight of Bar Which L = 80 m, Dia of Bar = 2 cm ?
Sol: Formulae: D2
/162.162 x L
Dia Must Be in Milimeter So Convert it to Milimeter
1 cm = 10 mm 2 x 10 = 20 mm L= 80 m
Apply Formulae: (202
)/162.162 x 80 = 197.33 kg
I Convert it to Ton so Divide it on 1000 1 Ton = 1000 kg
197.33/1000 = 0.197 Ton
 _________________________________$______________________________________*
Number of Bars
Qs: Find the Number of Bars in 20 m Long & 10 m Wide beam ?
Sol: Main Bar = 20 cm c/c Dia = 16 mm
Distribution Bar = 10 cm c/c Dia = 12 mm
c/c Means center to center
Main Bar = L of Distribution Bar/Space + 1
Main bar = 20/0.20 + 1 = 101 Bars
Distribution Bar = L of Main Bar/Space + 1
Distribution Bar = 10/0.10 + 1 = 101 Bars
Find Weight = D2
/162.162 x L
Main Bar: Weight = (162
)/162.162 x 20 = 31.57 Kg
Distribution Bar: Weight =(122
)/162.162 x 10 = 8.88 kg
 __________________________________$_______________________________________*
Qs: Find the Weight of Bar When its Length is 150 Ft & Dia is 0.5 inch ?
Sol: 1 inch = 8 sutar so First convert it to sutar
0.5 x 8 = 4 Sutar
Formulae of Weight = D2
/24 x L
Weight = (42
)/24 x 150 = 100
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
1 kg = 2.204 Lbs 100 kg = 100/2.204 = 45.37 kg
 _____________________________________$_______________________________________*
Qs: What is project ?
Ans: Work Complete in A Specific Time is Called A Project.
Qs: What is Meant by Concrete ?
Ans: Concrete Means C.S.C
C: Means Cement
S: Means Sand
C: Means Course Aggregate
Concrete Means That Can be made by these Three Materials.
In 1:2:4 Concrete we Use
1 is A Cement 2 is A Sand 4 is A Bajjri.
In this Cocrete 25-30 Liters Water can used Or 5-6 Gallon use.
 _______________________________$_______________________________*
Qs: What Are the Main Step to Construct Building Or Any
Construction Work ?
Ans: There are Five Main Step For Project Construction,
1. Budget
2. Layout
3. Site Selection
4. Survey
5. Starting Work
If We Have Money the we can easily construct Anything.
First we layout the Building For Better Results.
We can Choose Better Site For Construction .
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
After Site Selection We Survey this place To get Good Result
In last we start the work sothese five are the main steps
To construct any building road Etc.
 ___________________________$__________________________________*
Road Structure
1. Trees: Trees Provide Oxygen And Absorbs Co2
GAS And Protect Human.
2. Drain: In the side We Make Drain To flow Out The road Water.
3. Yellow Line Shows That Don,t Cross me.
4. Center Short Lines Are For Over take when it become long then don,t overtake.
5. Shoulder are created for Maintenance of vehicle When it Switch Down.
Formulae
Formulae For Long Wall = Length of long wall +
{width of short wall - Wall Thickness}
Length of short wall – [width of short wall – Wall thickness]
Quantity of water in Concrete
Concrete Ratio Quantity of Water
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
1:3:6 34 Litre
1:2:4 30 Litre
1:1:2 25 Litre
1:1 ½:3 27 Litre
Cement Quantity = Ratio of Cement/Sum of Ratio x Mortar Ratio
Sand Quantity = Ratio of sand/sum of Ratio x Mortar Ratio
Bricks = Quantity of Wall/volume of brick.
Formulae of striup No in beam = Total length of Beam/Space b/w striuf.
T-Iron No in Roof = Total Length/Space in T-Iron
____________________________$_____________________________________*
Dam
Qs: A Dam Having Breadth 4m and Height 10m ?
Given Data: Breadth of Dam = 4 m
Height of Dam = 10 m
Density of Water = ww = 1000 kg/m3
Density of Masonry = wm = 2000 kg/m3
Required Data: Total Pressure = ?
Resultant Pressure = ?
Position of Resultant Pressure = ?
Sol: P = wh2
/2 putting Values
P = 100 x (10)2
/2 = 50000 kg/m2
R.P = 𝑎2 + 𝑏2
Resultant pressure = 500002 + 4 𝑋 10 𝑋 2000
R.P = 94340 kg/m2
 _____________________________$________________________________*
I. 1 mm = 0.0394 inch
II. 1 cm = 10 mm = 0.3937 inch
III. 1 m = 100 cm = 1.0936 yards
IV. 1 km = 1000 m = 0.6214 mile
V. 1 sq inch = 6.4516 cm2
1 sq ft = 144 sq inches = 0.0929 m2
VI. 1 sq yard = 9 sq feet = 0.8361 m2
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
VII. 1 acre = 4840 sq yards = 446.9 m2
VIII. 1 sq mile = 640 acre = 259 hectares.
 ___________________________$__________________________________*
a. Area of Circle = πR2
π = 3.14 R = Radius
b. Volume of Cylinder = A = πR2
H
c. 1 Gallon Of Water = Weight = 8.35 Lbs. Pound
d. 1 Gallon = 231 Cubic inches
e. 1 Cubic Foot = 7.48 Gallons
f. 1 Cubic foot = 1728 Cube Nene
g. Atmospheric Pressure = 14.7 Psi
h. Head Pressure Of Water = 0.434 Psi Per Ft
i. 1 Psi = 2.30 Feet of Head.
 ________________________$________________________________*
Qs: A Steel bar Having Length = 10 Ft Thickness is = 1 inch
Find The Weight?
Sol: L = 10 , D = 1 inch 1 inch = 8 Sutar so 1 x 8 = 8 Sutar
W = D2
/24 x L W = (8)2
/24 x 10 = 6400/24 = 266.66 Lbs.
Lbs. is the unit of pound so change it to kg 1kg = 2.204 Lbs.
266.66/2.204 = 120.98 kg.
 __________________________$__________________________________*
QS: A Steel Bar Having Length = 80 m Dia = 6 cm Find Weight?
Sol: in Meter System Dia must Be in millimeter.
1 cm = 10 mm 6 x 10 = 60 mm
W = D2
/162.162 x L = (60)2
/162.162 x 80 = 288000/162.162 = 1776 kg
W = 1776 kg Conver it to Ton Divide it on 1000
1776/1000 = 1.776 Ton.
 _________________________$___________________________________*
Concrete Cylinder Dimension
Height = 30.48 cm Dia = 15.24 cm
Area of Cylinder = πd2
/4 3.142[15.24]2
/4
182.43 Volume = area x Height
Volume = 182.43 x 30.48 = 5560.46 cm3
Strength = Load/Area Load = 35000
35000/182.43 = 191.85 Cucm2
.
 ___________________$__________________________________*
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
Quantity of Bridge Pile
Depth of Pile = 24 m Dia of Pile = 0.75 cm
Area = πD2
/4 = 3.14 x [0.75]2
/4 = 0.441 m2
Volume = 0.441 x 24 =10.60 m3
convert to foot
10.60 x 35.32 = 374.5 Wet Qty = 374.5 Cft
Convert it to dry = 374.5 x 1.54 = 576.79
Mixing Ratio = 1:3:6
Sum of Ratio = 1 + 3 + 6 = 10
Cement: 1/10 x576.79 = 57.67 ft3
One bag cement = 1.25 57.67/1.25 = 46.13 Bags
Sand: 3/10 x 576.79 = 173.037 cft
Bajri: 6/10 x 576.79 = 346.074 Cft.
 ________________________$____________________________*
Types of Steel
1. Mild Steel
2. Deformed Steel
3. Tar Steel
Kind of Tar Steel
40 Grade = 40000 Lbs/m2
50 Grade = 50000 Lbs/m2
60 Grade = 60000 Lbs/m2
 _______________________$_____________________________*
Formulaes
Circle = πD2
/2
Triangle = ½[a x b]
Rectangle = a x b
Square = a x b
Trapezoid = a + a2
/2 x b + b2
/2
To Find Percentage of Marks
Obtained marks/100 x total marks = percentage
885/100 x 1100 = 80.45 %
Convert it to Number Again Then opposite the process
80.45 x 1100/100 = 885
 _____________________$_______________________________*
Area and Volume Of Different Shapes
Area of Triangles: Formulae: 1/2 x b x h
Suppose: B = 3 Ft H = 5 Ft
Area = 1/2 x 3 x 5 = 7.5 Sft
Volume of Triangle = ½ x b x h x perpendicular
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
H =2, b = 1, L = 5 Ft
1/2 x 2 x 1 x 5 = 5 Cft
Area and Volume of Circle
Area of Circle = Formulae = π.D2
/4 D = 2 Ft
Putting Values = 3.14 x (2)2
/4 =3.142 Sft
D = 2 Radius πD2
/4 = πr2
π (2r)2
/4 = π 4r2
/4 = πr2
πD2
/4 = πr2
Volume of Circle = πd2
/4 x L
Suppose: D = 2 Ft, L = 10 Ft v = πD2
/4 x L
V = 3.14 x (2)2/4 x 10 = 31.42 Cft.
Area of Rectangle: Formulae = B x L
Suppose: B = 4 Ft, L = 8 Ft
4 x 8 = 32 Sft
Area and volume of Trapezoid:
Formulae = Sum of Two Parallel Side/2 x H
Area = 10 + 8/2 x 5 = 45 Sft
Volume = 8 + 10/2 x 5 x 20 = 900 Cft
 _______________________$______________________________*
Bricks in Cubic Meter
Length of Wall = 12 m
Thickness of Wall = 0.2286 m
Height of Wall = 3 m
Volume of Wall = L x T x H
12 x 0.2286 x 3 = 8.2296
We Know That: 1 cum = 500 Bricks
8.2296 X 500 = 4115 Bricks.
 ______________________$______________________________*
To Find Cement Mortars in CFT.
Quantity of Brick Work = 375 Cft
No of Bricks = 5062.5
Ratio of Cement Mortar = 1:4
Sum of Ratio = 1 + 4 = 5
We Know That 30 Cft Dry Mortar Used in 100 Cft
So: 375 x 30/100 =112.5 Cft
 ______________________$______________________________*
Cement Mortar in Cubic Meter
Quantity of Bricks = 8.2296 Cum
No of Bricks = 4114.8
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
Ratio of Cement = 1:6
Sum of Ratio = 1 + 6 = 7
We know that 0.30 cum dry Mortar Used in 1 Cum
So: Qty of Mortar = 0.30 x 8.2296/1 = 2.4688 cum
Cement: 1/7 x 2.4688 = 0.3526 cum
0.3526/0.035 = 10.07 bags
Sand: 6/7 x 2.4688 = 2.11 cum.
 ___________________________$____________________________*
Quantity of Plaster
Length of Wall = 20 Ft
Height of Wall = 10 Ft
Thickness of Plaster = 1 inch = 1/12 = 0.083 Ft
Wet Volume of Wall = L x H x T
20 x 10 x 0.083 = 16.6 Cft
Dry Volume of Mortar = 16.6 x 1.27 = 21.082 Cft
Ratio of Mortar = 1:3
Sum of Ratio = 1 + 3 = 4
Qty of cement: ¼ x 21.082 = 5.2705 Cft
5.2705/1.25 = 5 Bags
 _____________________$______________________________*
Quantity of Concrete in F.P.S system
Quantity of Wet Material = 150 Cft
Quantity of Dry Material = 150/100 x 154 = 231 Cft
Ratio of Cement: 1:2:4
Sum of Ratio: 1 + 2 + 4 = 7
Cement: 1/7 x 231 = 32.99 Cft 32.99/1.25 = 26.39 Bags
Sand = 2/7 x 231 = 66 Cft
Bajri: 4/7 x 231 = 132 Cft.
 _______________________$_____________________________*
Find Overlap for Steel
Formulae for overlap
Vertical Overlap: Dia of Steel = 40 x D/12 x 8 = 40d/96
Horizontal Overlap: 50 x D/12 x 8 = 50d/96
Suppose: Dia = 4 inch
Vertical: 40d/12 x 8 = 40 x 4/12 x 8 = 160/96 = 1.66 Ft
Vertical Overlap is = 1 Ft & 8 inch
Horizontal: 50d/12 x 8 = 50 x 4/96 = 200/96 = 2.083 Ft
Horizontal Overlap + 1 Ft & 10 inch.
 _________________________$_____________________________*
Stirrup’s (Rings)
Formulae = L x 12/Space
Quantity Notes By Engineer Saqib Imran
Cell No : 0341-7549889
L = 37 Ft Space of Rings c/c = 9 inch
Put Value & Apply Formulae
37 x 12/9 = 49.33 Means 50 Rings.
 _______________________$______________________________*
Length of Rings
Length of Column = 10 Ft
Dia of Column = 1 Ft Concrete cover = 2 inch
No of Bars in Column = 4 Space of Bars = 10 inch
Length of Rings = ?
Formulae: Space of Bar x side of column 3 inch
3 inch are added for hock length
10 x 4 x 3 = 40 + 3 = 43 inch 3 Ft & 7 inches.
 ___________________________$___________________________*
Qs: Core Cutter Was Used to Determined Density for a Road
Site. Weight of the Cutter was 1286 Gram & Total Weight Was
3195 gram. Volume of Core Cutter was 1000 cm3
& Water Content
Was 12%. Determine Bulk Density of This Sample?
Sol: Net of soil in Core Cutter:
W = 3195 – 1286 = 1909 gram
Volume of Core Cutter = V = 1000 c.c
Bulk Density = W/V = 1909/1000 = 1.909 Gm/c.c
M = 12% = 12 x 100 = 0.12
Bulk Density = ϓ/1 + m
Symbol of Bulk Density = ϓ
Bulk Density = 1.909/1 + 0.12 = 1.909/1.12
1.705 gm/c.c.
 ___________________________$_______________________________*
Stair Concrete
Waist & Landing Slab = 6 inch Thick
Tread = 12 inch Riser = 6 inch
Width of Stairs = 4.5 Ft
Formulae: 𝐿2 + 𝐻2
L of Waist Slab = 162 + 82 = 17.89 Ft
Volume of Waist Slab = 17.89 x 0.5 x 4.5 = 40.25 Cft
Volume of Landing = 5 x 4.5 x 0.5 = 11.25 Cft
Volume of Steps = 16 x [1/2 x 1 x 0.5] x 4.5 = 18 Cft
Total Volume = 40.25 + 11.25 + 18 = 69.50 Cft.
 __________________________$__________________________________*

More Related Content

What's hot

Permeability Test of soil Using Constant and Falling Head Method
Permeability Test of soil Using Constant and Falling Head MethodPermeability Test of soil Using Constant and Falling Head Method
Permeability Test of soil Using Constant and Falling Head MethodJameel Academy
 
Compressive Strength of Hydraulic Cement Mortar | Jameel Academy
Compressive Strength of Hydraulic Cement Mortar | Jameel AcademyCompressive Strength of Hydraulic Cement Mortar | Jameel Academy
Compressive Strength of Hydraulic Cement Mortar | Jameel AcademyJameel Academy
 
Cbr aashto t193 plus proctor t180
Cbr aashto t193 plus proctor t180Cbr aashto t193 plus proctor t180
Cbr aashto t193 plus proctor t180Ayaz khan
 
Concrete lab s5 procedure
Concrete lab s5 procedureConcrete lab s5 procedure
Concrete lab s5 procedureSHAMJITH KM
 
Soundness of Hydraulic Cement Paste | Jameel Academy
Soundness of Hydraulic Cement Paste | Jameel AcademySoundness of Hydraulic Cement Paste | Jameel Academy
Soundness of Hydraulic Cement Paste | Jameel AcademyJameel Academy
 
Basic civil engineering part 2
Basic civil engineering part 2Basic civil engineering part 2
Basic civil engineering part 2Akash Pandey
 
Numerical problem on concrete mix design by is 10262(2009) method
Numerical problem on concrete mix design by is 10262(2009) methodNumerical problem on concrete mix design by is 10262(2009) method
Numerical problem on concrete mix design by is 10262(2009) methodDnyaneshwar More
 
Consolidation of Soil Test | Jameel Academy
Consolidation of Soil Test | Jameel AcademyConsolidation of Soil Test | Jameel Academy
Consolidation of Soil Test | Jameel AcademyJameel Academy
 
Mud Dilution, Drilling Engineering Lab.
Mud Dilution, Drilling Engineering Lab.Mud Dilution, Drilling Engineering Lab.
Mud Dilution, Drilling Engineering Lab.Jarjis Mohammed
 
Setting Time of Hydraulic Cement By Vicat Needle | Jameel Academy
Setting Time of Hydraulic Cement By Vicat Needle | Jameel AcademySetting Time of Hydraulic Cement By Vicat Needle | Jameel Academy
Setting Time of Hydraulic Cement By Vicat Needle | Jameel AcademyJameel Academy
 
Standard Compaction Test | Jameel Academy
Standard Compaction Test | Jameel AcademyStandard Compaction Test | Jameel Academy
Standard Compaction Test | Jameel AcademyJameel Academy
 

What's hot (20)

Permeability Test of soil Using Constant and Falling Head Method
Permeability Test of soil Using Constant and Falling Head MethodPermeability Test of soil Using Constant and Falling Head Method
Permeability Test of soil Using Constant and Falling Head Method
 
Compressive Strength of Hydraulic Cement Mortar | Jameel Academy
Compressive Strength of Hydraulic Cement Mortar | Jameel AcademyCompressive Strength of Hydraulic Cement Mortar | Jameel Academy
Compressive Strength of Hydraulic Cement Mortar | Jameel Academy
 
Mud dilution experiment
Mud dilution experimentMud dilution experiment
Mud dilution experiment
 
Penetration test of bitumen
Penetration test of bitumenPenetration test of bitumen
Penetration test of bitumen
 
Cbr aashto t193 plus proctor t180
Cbr aashto t193 plus proctor t180Cbr aashto t193 plus proctor t180
Cbr aashto t193 plus proctor t180
 
Concrete lab s5 procedure
Concrete lab s5 procedureConcrete lab s5 procedure
Concrete lab s5 procedure
 
Concrete lab s5
Concrete lab s5Concrete lab s5
Concrete lab s5
 
Soundness of Hydraulic Cement Paste | Jameel Academy
Soundness of Hydraulic Cement Paste | Jameel AcademySoundness of Hydraulic Cement Paste | Jameel Academy
Soundness of Hydraulic Cement Paste | Jameel Academy
 
Basic civil engineering part 2
Basic civil engineering part 2Basic civil engineering part 2
Basic civil engineering part 2
 
Kamal
KamalKamal
Kamal
 
Numerical problem on concrete mix design by is 10262(2009) method
Numerical problem on concrete mix design by is 10262(2009) methodNumerical problem on concrete mix design by is 10262(2009) method
Numerical problem on concrete mix design by is 10262(2009) method
 
Consolidation of Soil Test | Jameel Academy
Consolidation of Soil Test | Jameel AcademyConsolidation of Soil Test | Jameel Academy
Consolidation of Soil Test | Jameel Academy
 
Mud Dilution, Drilling Engineering Lab.
Mud Dilution, Drilling Engineering Lab.Mud Dilution, Drilling Engineering Lab.
Mud Dilution, Drilling Engineering Lab.
 
Setting Time of Hydraulic Cement By Vicat Needle | Jameel Academy
Setting Time of Hydraulic Cement By Vicat Needle | Jameel AcademySetting Time of Hydraulic Cement By Vicat Needle | Jameel Academy
Setting Time of Hydraulic Cement By Vicat Needle | Jameel Academy
 
Mud density
Mud densityMud density
Mud density
 
Summer training ppt
Summer training pptSummer training ppt
Summer training ppt
 
Standard Compaction Test | Jameel Academy
Standard Compaction Test | Jameel AcademyStandard Compaction Test | Jameel Academy
Standard Compaction Test | Jameel Academy
 
Pressurized mud-balance2
Pressurized mud-balance2Pressurized mud-balance2
Pressurized mud-balance2
 
Mud weighting
 Mud weighting  Mud weighting
Mud weighting
 
Direct Shear Test
Direct Shear TestDirect Shear Test
Direct Shear Test
 

Similar to Quantity notes by engineer saqib imran

Estimation and costing pdf
Estimation and costing pdfEstimation and costing pdf
Estimation and costing pdfSaqib Imran
 
Ratesanalysis for Material and Labor
Ratesanalysis for Material and LaborRatesanalysis for Material and Labor
Ratesanalysis for Material and LaborNagoorkani Majeed
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works ALI HYDER GADHI
 
QUANTITY SURVEYING PORTFOLIO.pptx
QUANTITY SURVEYING PORTFOLIO.pptxQUANTITY SURVEYING PORTFOLIO.pptx
QUANTITY SURVEYING PORTFOLIO.pptxRajnishKumar916873
 
CONCRETE Design mix
CONCRETE Design mixCONCRETE Design mix
CONCRETE Design mixMD AMANULLAH
 
ANALYSIS_OF_RATES.ppt
ANALYSIS_OF_RATES.pptANALYSIS_OF_RATES.ppt
ANALYSIS_OF_RATES.pptRijuDasgupta
 
Basic of civil engineering
Basic of civil engineeringBasic of civil engineering
Basic of civil engineeringVignesh Kumar
 
Material required for different items of civil building works
Material required for different items of civil  building worksMaterial required for different items of civil  building works
Material required for different items of civil building worksALI HYDER GADHI
 
Civil standard notes
Civil standard notesCivil standard notes
Civil standard notesmanu287448
 
civil datas for estimate
civil datas for estimatecivil datas for estimate
civil datas for estimatealwin prabakar
 
IRJET- Partial Replacement of Cement in Concrete by Silica Fume
IRJET- Partial Replacement of Cement in Concrete by Silica FumeIRJET- Partial Replacement of Cement in Concrete by Silica Fume
IRJET- Partial Replacement of Cement in Concrete by Silica FumeIRJET Journal
 
Class 7 PHYSICAL QUANTITY & MEASUREMENT
Class 7 PHYSICAL QUANTITY & MEASUREMENTClass 7 PHYSICAL QUANTITY & MEASUREMENT
Class 7 PHYSICAL QUANTITY & MEASUREMENTSouvikChatterjee53
 

Similar to Quantity notes by engineer saqib imran (20)

Estimation and costing pdf
Estimation and costing pdfEstimation and costing pdf
Estimation and costing pdf
 
Ratesanalysis for Material and Labor
Ratesanalysis for Material and LaborRatesanalysis for Material and Labor
Ratesanalysis for Material and Labor
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
QUANTITY SURVEYING PORTFOLIO.pptx
QUANTITY SURVEYING PORTFOLIO.pptxQUANTITY SURVEYING PORTFOLIO.pptx
QUANTITY SURVEYING PORTFOLIO.pptx
 
CONCRETE Design mix
CONCRETE Design mixCONCRETE Design mix
CONCRETE Design mix
 
ANALYSIS_OF_RATES.ppt
ANALYSIS_OF_RATES.pptANALYSIS_OF_RATES.ppt
ANALYSIS_OF_RATES.ppt
 
Basic of civil engineering
Basic of civil engineeringBasic of civil engineering
Basic of civil engineering
 
Material required for different items of civil building works
Material required for different items of civil  building worksMaterial required for different items of civil  building works
Material required for different items of civil building works
 
Civil standard notes
Civil standard notesCivil standard notes
Civil standard notes
 
Civil book
Civil bookCivil book
Civil book
 
Civil guide
Civil guideCivil guide
Civil guide
 
civil datas for estimate
civil datas for estimatecivil datas for estimate
civil datas for estimate
 
IRJET- Partial Replacement of Cement in Concrete by Silica Fume
IRJET- Partial Replacement of Cement in Concrete by Silica FumeIRJET- Partial Replacement of Cement in Concrete by Silica Fume
IRJET- Partial Replacement of Cement in Concrete by Silica Fume
 
Class 7 PHYSICAL QUANTITY & MEASUREMENT
Class 7 PHYSICAL QUANTITY & MEASUREMENTClass 7 PHYSICAL QUANTITY & MEASUREMENT
Class 7 PHYSICAL QUANTITY & MEASUREMENT
 
Mix design
Mix designMix design
Mix design
 
Konversi satuan
Konversi satuanKonversi satuan
Konversi satuan
 
Numericals.pptx
Numericals.pptxNumericals.pptx
Numericals.pptx
 
Estimation
Estimation    Estimation
Estimation
 
Construction detail
Construction detailConstruction detail
Construction detail
 

More from Saqib Imran

Engineering basic notes
Engineering basic notesEngineering basic notes
Engineering basic notesSaqib Imran
 
Misaali mard مثالی مرد
Misaali mard مثالی مردMisaali mard مثالی مرد
Misaali mard مثالی مردSaqib Imran
 
Khatm e nubuwwat lesson no 2
Khatm e nubuwwat lesson no 2Khatm e nubuwwat lesson no 2
Khatm e nubuwwat lesson no 2Saqib Imran
 
Khatm e nubuwwat lesson no 1
Khatm e nubuwwat lesson no 1Khatm e nubuwwat lesson no 1
Khatm e nubuwwat lesson no 1Saqib Imran
 
Khatm e nabuwat 4
Khatm e nabuwat 4Khatm e nabuwat 4
Khatm e nabuwat 4Saqib Imran
 
Khatm e nabuwat 3
Khatm e nabuwat 3Khatm e nabuwat 3
Khatm e nabuwat 3Saqib Imran
 
Khatm e nabuwat 2
Khatm e nabuwat 2Khatm e nabuwat 2
Khatm e nabuwat 2Saqib Imran
 
Khatm e nabuwat 1
Khatm e nabuwat 1Khatm e nabuwat 1
Khatm e nabuwat 1Saqib Imran
 
Khatm e nubuwwat lesson no 7
Khatm e nubuwwat lesson no 7Khatm e nubuwwat lesson no 7
Khatm e nubuwwat lesson no 7Saqib Imran
 
Khatm e nubuwwat lesson no 6
Khatm e nubuwwat lesson no 6Khatm e nubuwwat lesson no 6
Khatm e nubuwwat lesson no 6Saqib Imran
 
Khatm e nubuwwat lesson no 5
Khatm e nubuwwat lesson no 5Khatm e nubuwwat lesson no 5
Khatm e nubuwwat lesson no 5Saqib Imran
 
Khatm e nubuwwat lesson no 4
Khatm e nubuwwat lesson no 4Khatm e nubuwwat lesson no 4
Khatm e nubuwwat lesson no 4Saqib Imran
 
Khatm e nubuwwat lesson no 3
Khatm e nubuwwat lesson no 3Khatm e nubuwwat lesson no 3
Khatm e nubuwwat lesson no 3Saqib Imran
 
Khatm e nubuwwat 40 hadees
Khatm e nubuwwat 40 hadeesKhatm e nubuwwat 40 hadees
Khatm e nubuwwat 40 hadeesSaqib Imran
 
40 hadees in urdu
40 hadees in urdu40 hadees in urdu
40 hadees in urduSaqib Imran
 
40 hadees in urdu & english
40 hadees in urdu & english40 hadees in urdu & english
40 hadees in urdu & englishSaqib Imran
 
Engineering basic notes
Engineering basic notesEngineering basic notes
Engineering basic notesSaqib Imran
 
Pre stressed & pre-cast concrete technology - ce462
Pre stressed & pre-cast concrete technology - ce462Pre stressed & pre-cast concrete technology - ce462
Pre stressed & pre-cast concrete technology - ce462Saqib Imran
 
Foundations and pavements ce367
Foundations and pavements   ce367Foundations and pavements   ce367
Foundations and pavements ce367Saqib Imran
 
Design of hydraulic structures ce 413
Design of hydraulic structures ce 413Design of hydraulic structures ce 413
Design of hydraulic structures ce 413Saqib Imran
 

More from Saqib Imran (20)

Engineering basic notes
Engineering basic notesEngineering basic notes
Engineering basic notes
 
Misaali mard مثالی مرد
Misaali mard مثالی مردMisaali mard مثالی مرد
Misaali mard مثالی مرد
 
Khatm e nubuwwat lesson no 2
Khatm e nubuwwat lesson no 2Khatm e nubuwwat lesson no 2
Khatm e nubuwwat lesson no 2
 
Khatm e nubuwwat lesson no 1
Khatm e nubuwwat lesson no 1Khatm e nubuwwat lesson no 1
Khatm e nubuwwat lesson no 1
 
Khatm e nabuwat 4
Khatm e nabuwat 4Khatm e nabuwat 4
Khatm e nabuwat 4
 
Khatm e nabuwat 3
Khatm e nabuwat 3Khatm e nabuwat 3
Khatm e nabuwat 3
 
Khatm e nabuwat 2
Khatm e nabuwat 2Khatm e nabuwat 2
Khatm e nabuwat 2
 
Khatm e nabuwat 1
Khatm e nabuwat 1Khatm e nabuwat 1
Khatm e nabuwat 1
 
Khatm e nubuwwat lesson no 7
Khatm e nubuwwat lesson no 7Khatm e nubuwwat lesson no 7
Khatm e nubuwwat lesson no 7
 
Khatm e nubuwwat lesson no 6
Khatm e nubuwwat lesson no 6Khatm e nubuwwat lesson no 6
Khatm e nubuwwat lesson no 6
 
Khatm e nubuwwat lesson no 5
Khatm e nubuwwat lesson no 5Khatm e nubuwwat lesson no 5
Khatm e nubuwwat lesson no 5
 
Khatm e nubuwwat lesson no 4
Khatm e nubuwwat lesson no 4Khatm e nubuwwat lesson no 4
Khatm e nubuwwat lesson no 4
 
Khatm e nubuwwat lesson no 3
Khatm e nubuwwat lesson no 3Khatm e nubuwwat lesson no 3
Khatm e nubuwwat lesson no 3
 
Khatm e nubuwwat 40 hadees
Khatm e nubuwwat 40 hadeesKhatm e nubuwwat 40 hadees
Khatm e nubuwwat 40 hadees
 
40 hadees in urdu
40 hadees in urdu40 hadees in urdu
40 hadees in urdu
 
40 hadees in urdu & english
40 hadees in urdu & english40 hadees in urdu & english
40 hadees in urdu & english
 
Engineering basic notes
Engineering basic notesEngineering basic notes
Engineering basic notes
 
Pre stressed & pre-cast concrete technology - ce462
Pre stressed & pre-cast concrete technology - ce462Pre stressed & pre-cast concrete technology - ce462
Pre stressed & pre-cast concrete technology - ce462
 
Foundations and pavements ce367
Foundations and pavements   ce367Foundations and pavements   ce367
Foundations and pavements ce367
 
Design of hydraulic structures ce 413
Design of hydraulic structures ce 413Design of hydraulic structures ce 413
Design of hydraulic structures ce 413
 

Recently uploaded

Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 

Recently uploaded (20)

Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 

Quantity notes by engineer saqib imran

  • 1. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 Measurement and its conversion 1 Mile = 1609.75 Meter 1 Meter = 1000 mm 1 Meter = 100 cm 1 Foot = 30 cm 1 Inch = 2.54 cm 1 Foot = 12 inch 1 inch = 25.4 mm 1 foot = 0.0254 m 1 inch = 0.064 m 1 Foot = 300 mm 1 Foot = 1/12 = 0.304 m 1 Meter = 3.281 Feet 1 Meter = 39.37 inch 1 Inch = 0.083 foot 1 Inch = 1/39.37 = 0.025 1 Acre = 2 Jarib 1 Acre = 8 Canal 1 Canal = 20 Marla 1 Marla =272.5 Sq. /ft. 1 inch = 8 sutar 1 ton = 1000 kg 1 ton = 2204 Lbs 1 CFT = 490 Lbs 1 CUM = 7850 kg 1 Lbs = 2.204 kg 1 Meter = 10 Desimeter 1 Dm = 10 cm 1 cm = 10 mm 1 M3 = 35.32 Ft3 1 M2 = 10.76 Ft2 1 Mile = 5280 Ft 1 Mile = 8 Furlong 1 Mile = 1760 Yards 1 Furlong = 220 Yards 1 Yard = 3 Feet 1 inch = 0.083 Ft 2 inch = 0.16 Ft 3 inch = 0.25 Ft 4 inch = 0.33 Ft 5 inch = 0.41Ft 6 inch = 0.50 Ft 7 inch = 0.58 Ft 8 inch = 0.66 Ft 9 inch = 0.75 Ft 10 inch = 0.83 Ft 11 inch = 0.91 Ft 12 inch = 1 Ft 1 Mile = 0.621504 Acre 1 Acre = 0.4047 Hector 1 Canal = 20 Marla 1 Jerab = 4 Canal 1 Muraba = 25 Acre
  • 2. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 1 cm = 0.3937 inch 1 Decigram = 10 Centigram 1 Decagram = 10 Gram 1 Hectogram = 10 Decigram 1 kg = 10 Hectogram 1 kg = 2.204 Pounds 1 pound = 16 Ounce 1 Ton = 20 Maan 1 Ton = 1000 kg 10 cm = 1 decimeter 1 Maan = 50 kg 10 decimeter = 1 m 10 m = 1 Decameter 10 Decameter = 1 Hectometer 10 mm = 1 cm 10 Milliliter = 1 Centiliter 10 Centiliter = 1 Decalitre 10 Deciliter = 1 Liter 10 liter = 1 Decaliter 10 Decaliter = 1 Hectoleter 10 Hectoliter = 1 Kiloliter 100 Square meter = 1 Acre 1000 Sq.m = 1 He acre 100 kg = 1 Cointal 10 Cointol = 1 Ton 10 Hectometer = 1 Km 1 Yard = 0.914 m 1 m = 1.09 Yard 1 Meter Square = 10.76 Sft 1 meter cube = 35.32 Cft 1 Marla = 9 Sarsai 1 Sarsai = 30.25 Sft 1 Canal = 5445 Sft 1 Pound = 0.453 kg 1 kg = 9.81 Newton 1 Kilo newton = 1000 Newton 1 Liter = 0.93 kg 1 Kips = 0.93 kg
  • 3. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 RATE ANALYSIS I. No of bricks in 1 Cft = 13.5 or 14.2 II. No of bricks in 1 cum = 500 bricks III. Volume of 1 brick in Foot system = 0.0703 Cft IV. Volume of one brick in meter system = 0.002 Cum V. Dry mortar used in masonary work = 30 % VI. Wet mortar convert to dry mortar then multiplying with 1.27 VII. Wet concrete convert to dry multiply with 1.54 VIII. Volume of 1 cement bag = 1.25 Cft IX. Volume of one cement bag = 0.035 Cum X. Weight of steel in 1 Cft = 490 Lbs XI. Weight of steel in 1 Cum = 7850 kg XII. Volume of block = 0.3075
  • 4. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 To Find Quantity In A Foot System Q No 1: Determine The Quantities Of Various Materials Used In 1804 Cft Brick Works In Cement Mortar Ratio 1:4. Solution: Quantity Of Bricks = 1805 Cft Find Bricks Cement And Sand 1: Bricks Quantity Of Bricks = 1805 Cft Volume Of One Brick = 0.0703 Cft No Of Bricks In 1805 Cft = 1805/0.0703 =25675 Bricks 2: Cement Dry Mortar Used In Masonary = 30 % Quantity Of Mortar = 1805 x 30/100 = 541.5 Cft Sum Of Ratio = 1 + 4 = 5 Cement = 1/5 X 541.5 = 108.3 Cft Convert It To Bags One Bag Volume = 1.25 Cft No Of Bags In 108.3 Cft = 108.3/1.25 = 86.64 Or 87 Bags 3: Sand 4/5 x 541.5 = 433.2 Cft Abstract Of Cost Bricks brick 1 trip = 12’000 Rs In one dumper 2000 bricks 2000/2000 = 12000/2000 = 6 Rs 1 brick = 6 Rs No of bricks= 25675 x 6 = 2’14’050 Rs Cement Cement 1 trip = 80’000 Price of 1 bag = 400 400/400 = 80’000/400 = 200 1 Cft = 200 Rs
  • 5. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 No of Cement Bags = 87 87 x 200 = 17400 Rs Qs: Determine the Quantities of various material to prepare 10 Cum concrete Ratio 1:2:4. Sol: Quantity of Material = 10 Cum Quantity of Dry Material = 10 x 1.54 = 15.4 Ratio of concrete = 1:2:4 Sum of ratio: 1 + 2 + 4 = 7 Cement: 1/7 x 15.4 = 2.2 Cum One bag = 0.035 cum 2.2/0.035 = 62.86 Bags Sand: 2/7 x 15.4 = 4.4 Cum Bajri: 4/7 x 15.4 = 8.8 Cum  ________________________$_______________________________________* D.P.C Qs: Quantity of D.p.c = 97 sqm thichkness of d.p.c = 2.5 cm Ratio: 1:2:4 Find The Quantity Of Various Materials. Sol: Qty of D.p.c = 97 sqm Change it to volume Thickness of D.p.c + 2.5 cm Change it to meter 2.5/100 = 0.025 Cum Volume = 97 x 0.025 2.42 Cum Convert It to Dry = 2.42 x 1.54 = 3.73 cum Mixing Ratio: 1:2:4 Sum of Ratio = 1 + 2 + 4 = 7 Cement: 1/7 x 3.73 = 0.532 Cum 1 bag = 0.035 0.532/0.035 = 15.2 Bags Sand: 2/7 x 3.73 1.06 Cum Bajjri: 4/7 x 3.73 = 2.13 Cum
  • 6. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 Sand: Sand 1 trip = 2000 Rs Volume Of Tracter Trally = 150 Cft & Volume of dumper = 750 Cft We Take The Volume of Trally 150/150 = 2000/150 = 13.33 Cft 433.2 x 13.33 = 5774.55 Rs Meter System Qs: Determine The Quantities Of Various Materials Used In 81 Cum Brick Work In Cement Mortar 1:5. Sol: Quantity Of Brick = 81 Cum Mortar Mixing Ratio = 1:5 No of bricks in one Cum = 500 Volume of one brick = 0.002 Cum No of bricks = 81/0.002 = 40500 bricks or 500 x 81 = 40500 Bricks Quantity of Mortar = 81 x 30/100 = 24.3 Cum Sum of Ratio = 1 + 5 = 6 Cement: 1/6 x 24.3 = 4.05 Cum Volume of 1 bag = 0.035 No of bags = 4.05/0.035 = 115 bags Sand: = 5/6 x 24.3 = 20.24 Cum  _________________________________$_______________________________* Blocks Qs: Determine the Quantity of Various materials used in 113 cft block work in Cement mortar 1:4. Sol: Quantity of blocks = 113 Cft Mortar Mixing Ratio = 1:4 Blocks: Volume of one block = 0.3075 Cft N of Blocks in 113 Cft + 113/0.3075 = 368 Blocks Quantity of Mortar = 113 x 30/100 = 33.9 Cft Sum Of Ratio = 1 + 4 = 5 Cement: 1/5 x 33.9 = 6.78 Cft One bag = 1.25 Cft 6.78/1.25 = 5.24 Bags Sand: 4/5 x 33.9 = 27.12 Cft  ______________________$____________________________________* Concrete Work
  • 7. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 Qs: Determine The Quantities of Various Materials to Prepare 100 Cft Concrete Ratio 1:4:8. Sol: Quantity of Material = 100 x 1.54 = 154 Cft Sum of Ratio: 1 + 4 + 8 = 13 Cement: 1/13 x 154 = 11.84 Cft Convert To Bags 1 bag = 1.25 Cft 11.78/1.25 = 9.47 Bags Sand: 4/13 x 154 = 47.38 Cft Bajjri: 8/13 x 154 = 94.76 Cft Floor Qs: Prepare Analysis of Rates For a Cocrete Floor Consisting Following Structure. 4 inch Base course of brick ballast 2 inch down size 1 inch under layer of cement concrete Ratio 1:3:6 1.5 inch Topping of Cement concrete 1:2:4 Sol: Brick Ballast = 100 x 0.33 = 33.33 Cft Under Layer = 1:3:6 1 inch = 1/12 = 0.08 ft. Qty of under layer = 100 x 0.08 = 8 Cft Dry Qty of concrete = 8 x 1.54 = 12.32 Cft Sum of Ratio; 1 + 3 + 6 = 10 Cement: 1/10 x 12.32 = 1.232 Cft Convert to Bag 1 Bag = 1.25 Cft 1.232/1.25 = 0.98 Bags Sand: 3/10 x 12.32 = 3.09 Cft Bajjri: 6/10 x 12.32 = 7.39 Cft Topping: P.c.c = 1:2:4 Thickness = 1.5 inch = 1.5/12 = 0.125 Ft Qty of Topping = 100 x 0.125 = 12.5 Cft Dry Qty Of P.c.c = 12.5 x 1.54 = 19.25 Cft
  • 8. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 Sum of Ratio = 1 + 2 + 4 = 7 Cement: 1/7 x 19.25 = 2.75 Cft Convert to Bags 1 bag = 1.25 Cft 2.75/1.25 = 2.2 Bags Sand: 2/7 x 19.25 = 5.5 Cft Bajjri: 4/7 x 19.25 = 11 Cft Adding The Cft Of Topping And Sub Grade Cement + Cement: 0.98 + 2.2 = 3.18 bags Sand + Sand: 3.09 + 5.5 = 8.59 Cft Bajjri + Bajjri: 7.39 + 11 = 18.39 Cft Slab Qs: Length of the slab = 10 Ft Width of the Slab = 9 Ft Thickness of the Slab = 0.5 Ft Steel = 1.5 % Mixing Ratio: 1:2:4 Determine tne Anaylsis of Follwing Materials. Sol: First Calculate Its Quantuty: 1 x 10 x 9 x 0.5 = 45 Cft Qty Of Cement x Dry Mortar Ratio: 45 x 1.54 = 69.3 Cft Sum Of Ratio: 1 + 2 + 4 = 7 Cement: 1/7 x 45 = 6.42 Cft Convert To Cement 1 Bag = 1.25 Cft 6.42/1.25 = 5.13 Bags Sand: 2/7 x 45 = 12.85 Cft Bajjri: 4/7 x 45 = 25.71 Cft Steel: 45 x 1.5/100 = 0.675 1 Cft = 490 Lbs 0.675 x 490 = 330.75 Lbs Change it To Kilogram 330.75/2.204 = 150.06 Kg Plaster Qs: Prepare Analysis Of Rates For 1 inch Thick Plaster 100 Sft Long
  • 9. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 Cement Mortar Ratio: 1:3. Sol: Unit of Rates = 100 Sft Thickness = 1 inch 1/12 = 0.08 Ft Wet Volume of Mortar: 100 x 1/12 = 8.33 Dry Volume of Mortar: 8.33 x 1.27 = 10.58 Cft Sum of Ratio: 1 + 3 = 4 Cement: ¼ x 10.58 = 2.65 Cft Convert To Bags 1 Bag = 1.25 Cft 2.65/1.25 = 2.12 Bags Sand: ¾ x 10.58 = 7.93 Cft. Tiles Qs: Find the Quantity Of Tiles If Length of Roof = 20 Ft & Width = 15 Ft ? Sol: First Find The Volume Of Tile Volume = L x B x H Volume Of Tile; L = 1 Ft , B = 6 inch or 0.5 Ft 1 x 0.5 = 0.5 Now Divide The Sum of area of the Roof With the Tile volume. Total Area of Roof = 20 x 15 = 300 Sft Volume of one Tile = 0.5 SqFt 300/0.5 = 600 Tiles Or: 20 x 15 = 300 300 x 2 = 600 Tiles Because In Every Row One Tile Adjusted So The Number Of Rows Are 2 So We Multiply it with 2. Bricks Qs:Toi Find The Brick in a Room L = 20 Ft, B = 15 Ft, Thickness Of Wall = 0.75 Ft Height = 10 Ft ? Sol: In Room We Have 2 Long Walls & 2 Short Wall So We Will Cut Of Two Short Walls Or Two Long Walls Width To find Actual Quantity. 20 + 0.75 + 0.75 = 21.5 Ft
  • 10. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 Long Wall: No x L x BThickness x H = Quantity Long Wall = 2 x 21.5 x 0.75 x 10 = 322.5 Cft Short Wall = No x L x B Or Thickness x H = Quantity Short Wall = 2 x 15 x 0.75 x 10 = 225 Cft Volume of 1 Brick = 0.0703 Now add Long wall & Short Wall 322.5 + 225 = 547.5 547.5/0.0703 = 7788 or 7800 Bricks Or 547.5 x 14.2 = 7774.5 or 7800 Bricks Bars Qs: Suppose the Web of Bar In Which Have 104 Bars & 10 Ft Long Find Its Weight in Ton ? Sol: Thickness Of Bar: 6 Sutar 6/4 = 1.5 104 x 10 x 1.5/2040 = 0.76 Ton 1 Ton = 1000 kg 0.76 x 1000 = 760 Kg.  __________________________$__________________________________* Qs: Find The Weight of Bars if L = 20 ft. & B = 10 ft. Width Wise bar: 5 Length Wise Bar: 10 Sol; L x Length Wise Bar = 20 x 5 = 100 W x Width Wise Bar = 10 x 10 = 100 100 + 100/2204 = 200/2204 0.90 Ton 0.90 x 1000 = 90 kg.  __________________________$____________________________* Excavation QS: To Find Out the amount of Excavation Which Length is 100 Ft Breadth is 3 Ft & Depth is 4 Ft ?
  • 11. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 Sol: Volume = L x B x H 100 x 4 x 3 = 1200 Cft Cost of one Cubic Feet = 5 Rupees Total Cost = 1200 x 5 = 6000 Rs Earth Work Qs: Workout the Quantity of Earth Work Required for an Embankment 150 m Long & 10 m Wide at the top side Slope is 2:1 & depth at each 30 m interval are 0.60, 1.20 1.40, 1.60, 1.40, & 1.60. Sol: Abstract of Quantity R.D Depth B.D S.d2 B.d + Sd2 Mean Area Length Quantity Cutting Filling 0 0.60 6 0.72 6.72 ______ ______ ____ ____ 30 1.20 12 2.88 14.88 10.98 30 _____ 324 Cft 60 1.40 14 3.92 15.92 15.40 30 ____ 462 Cft 90 1.60 16 5.12 21.12 18.52 30 ____ 556 Cft 120 1.40 14 3.92 17.92 19.52 30 ____ 556 Cft 150 1.60 16 5.12 21.12 19.52 30 ____ 586 Cft Total ____ ____ _____ _____ _____ _____ _____ 2513 Cft  _______________________________$_______________________________________* Types Of Roads 1. Reinforce Cement Concrete Road { R.C.C } 2. Plain Cement Concrete Road { P.C.C }
  • 12. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 3. Bitumen Road 4. Asphalt Road 5. Tripple Surface Treatment { T.S.T } 6. Double Surface Treatment { D.S.T }  __________________________$______________________________________*
  • 13. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 Blocks Qs: Find The Blocks Used in A Room Which L is = 18 Ft, B = 14 Ft H = 10 Ft Thickness = 9 inch or 0.75 Ft ? Sol: Long Wall : 18 + 0.75 + 0.75 = 19.5 Qty For Long Wall = No x L x Thickness x H = Quantity 2 x 19.5 x 0.75 x 10 = 292.5 Cft Volume of One Block = 0.3075 Cft 292.5/0.3075 = 951 Blocks Now Quantity for Short Wall = No x B x Thickness x H = Quantity 2 x 14 x 0.75 x 10 = 210 Cft 210/0.3075 = 682 Blocks Total Blocks = 1633 Blocks  ________________________$________________________________________* Circle Or Well Qs: Find the Quantity Of Well Which is in circle form Depth is 4 m. Sol: D = 4 so we addd the thickness of wall 0.15 4 + 0.15 + 0.15 = 4.30 Circle = π x D 3.14 x 4.30 = 13,50 m No x L x B x H = quantity 1 x 13.50 x 0.30 x 4 = 16.21 Cum Volume of one Brick = 0.002 Cum 16.21/0.002 = 8105 bricks Mortar: 1:5 Sum of Ratio: 1 + 5 = 6 Cement: 1/6 x 4.863 = 0.8105 Cum 0.8105/0.035 = 23.15 Bags Sand: 5/6 x 4.863 = 4.0525 Cum. ____________________________$________________________________________* Bars On Meter System
  • 14. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 Qs: Find the Weight of Bar Which L = 80 m, Dia of Bar = 2 cm ? Sol: Formulae: D2 /162.162 x L Dia Must Be in Milimeter So Convert it to Milimeter 1 cm = 10 mm 2 x 10 = 20 mm L= 80 m Apply Formulae: (202 )/162.162 x 80 = 197.33 kg I Convert it to Ton so Divide it on 1000 1 Ton = 1000 kg 197.33/1000 = 0.197 Ton  _________________________________$______________________________________* Number of Bars Qs: Find the Number of Bars in 20 m Long & 10 m Wide beam ? Sol: Main Bar = 20 cm c/c Dia = 16 mm Distribution Bar = 10 cm c/c Dia = 12 mm c/c Means center to center Main Bar = L of Distribution Bar/Space + 1 Main bar = 20/0.20 + 1 = 101 Bars Distribution Bar = L of Main Bar/Space + 1 Distribution Bar = 10/0.10 + 1 = 101 Bars Find Weight = D2 /162.162 x L Main Bar: Weight = (162 )/162.162 x 20 = 31.57 Kg Distribution Bar: Weight =(122 )/162.162 x 10 = 8.88 kg  __________________________________$_______________________________________* Qs: Find the Weight of Bar When its Length is 150 Ft & Dia is 0.5 inch ? Sol: 1 inch = 8 sutar so First convert it to sutar 0.5 x 8 = 4 Sutar Formulae of Weight = D2 /24 x L Weight = (42 )/24 x 150 = 100
  • 15. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 1 kg = 2.204 Lbs 100 kg = 100/2.204 = 45.37 kg  _____________________________________$_______________________________________* Qs: What is project ? Ans: Work Complete in A Specific Time is Called A Project. Qs: What is Meant by Concrete ? Ans: Concrete Means C.S.C C: Means Cement S: Means Sand C: Means Course Aggregate Concrete Means That Can be made by these Three Materials. In 1:2:4 Concrete we Use 1 is A Cement 2 is A Sand 4 is A Bajjri. In this Cocrete 25-30 Liters Water can used Or 5-6 Gallon use.  _______________________________$_______________________________* Qs: What Are the Main Step to Construct Building Or Any Construction Work ? Ans: There are Five Main Step For Project Construction, 1. Budget 2. Layout 3. Site Selection 4. Survey 5. Starting Work If We Have Money the we can easily construct Anything. First we layout the Building For Better Results. We can Choose Better Site For Construction .
  • 16. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 After Site Selection We Survey this place To get Good Result In last we start the work sothese five are the main steps To construct any building road Etc.  ___________________________$__________________________________* Road Structure 1. Trees: Trees Provide Oxygen And Absorbs Co2 GAS And Protect Human. 2. Drain: In the side We Make Drain To flow Out The road Water. 3. Yellow Line Shows That Don,t Cross me. 4. Center Short Lines Are For Over take when it become long then don,t overtake. 5. Shoulder are created for Maintenance of vehicle When it Switch Down. Formulae Formulae For Long Wall = Length of long wall + {width of short wall - Wall Thickness} Length of short wall – [width of short wall – Wall thickness] Quantity of water in Concrete Concrete Ratio Quantity of Water
  • 17. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 1:3:6 34 Litre 1:2:4 30 Litre 1:1:2 25 Litre 1:1 ½:3 27 Litre Cement Quantity = Ratio of Cement/Sum of Ratio x Mortar Ratio Sand Quantity = Ratio of sand/sum of Ratio x Mortar Ratio Bricks = Quantity of Wall/volume of brick. Formulae of striup No in beam = Total length of Beam/Space b/w striuf. T-Iron No in Roof = Total Length/Space in T-Iron ____________________________$_____________________________________* Dam Qs: A Dam Having Breadth 4m and Height 10m ? Given Data: Breadth of Dam = 4 m Height of Dam = 10 m Density of Water = ww = 1000 kg/m3 Density of Masonry = wm = 2000 kg/m3 Required Data: Total Pressure = ? Resultant Pressure = ? Position of Resultant Pressure = ? Sol: P = wh2 /2 putting Values P = 100 x (10)2 /2 = 50000 kg/m2 R.P = 𝑎2 + 𝑏2 Resultant pressure = 500002 + 4 𝑋 10 𝑋 2000 R.P = 94340 kg/m2  _____________________________$________________________________* I. 1 mm = 0.0394 inch II. 1 cm = 10 mm = 0.3937 inch III. 1 m = 100 cm = 1.0936 yards IV. 1 km = 1000 m = 0.6214 mile V. 1 sq inch = 6.4516 cm2 1 sq ft = 144 sq inches = 0.0929 m2 VI. 1 sq yard = 9 sq feet = 0.8361 m2
  • 18. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 VII. 1 acre = 4840 sq yards = 446.9 m2 VIII. 1 sq mile = 640 acre = 259 hectares.  ___________________________$__________________________________* a. Area of Circle = πR2 π = 3.14 R = Radius b. Volume of Cylinder = A = πR2 H c. 1 Gallon Of Water = Weight = 8.35 Lbs. Pound d. 1 Gallon = 231 Cubic inches e. 1 Cubic Foot = 7.48 Gallons f. 1 Cubic foot = 1728 Cube Nene g. Atmospheric Pressure = 14.7 Psi h. Head Pressure Of Water = 0.434 Psi Per Ft i. 1 Psi = 2.30 Feet of Head.  ________________________$________________________________* Qs: A Steel bar Having Length = 10 Ft Thickness is = 1 inch Find The Weight? Sol: L = 10 , D = 1 inch 1 inch = 8 Sutar so 1 x 8 = 8 Sutar W = D2 /24 x L W = (8)2 /24 x 10 = 6400/24 = 266.66 Lbs. Lbs. is the unit of pound so change it to kg 1kg = 2.204 Lbs. 266.66/2.204 = 120.98 kg.  __________________________$__________________________________* QS: A Steel Bar Having Length = 80 m Dia = 6 cm Find Weight? Sol: in Meter System Dia must Be in millimeter. 1 cm = 10 mm 6 x 10 = 60 mm W = D2 /162.162 x L = (60)2 /162.162 x 80 = 288000/162.162 = 1776 kg W = 1776 kg Conver it to Ton Divide it on 1000 1776/1000 = 1.776 Ton.  _________________________$___________________________________* Concrete Cylinder Dimension Height = 30.48 cm Dia = 15.24 cm Area of Cylinder = πd2 /4 3.142[15.24]2 /4 182.43 Volume = area x Height Volume = 182.43 x 30.48 = 5560.46 cm3 Strength = Load/Area Load = 35000 35000/182.43 = 191.85 Cucm2 .  ___________________$__________________________________*
  • 19. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 Quantity of Bridge Pile Depth of Pile = 24 m Dia of Pile = 0.75 cm Area = πD2 /4 = 3.14 x [0.75]2 /4 = 0.441 m2 Volume = 0.441 x 24 =10.60 m3 convert to foot 10.60 x 35.32 = 374.5 Wet Qty = 374.5 Cft Convert it to dry = 374.5 x 1.54 = 576.79 Mixing Ratio = 1:3:6 Sum of Ratio = 1 + 3 + 6 = 10 Cement: 1/10 x576.79 = 57.67 ft3 One bag cement = 1.25 57.67/1.25 = 46.13 Bags Sand: 3/10 x 576.79 = 173.037 cft Bajri: 6/10 x 576.79 = 346.074 Cft.  ________________________$____________________________* Types of Steel 1. Mild Steel 2. Deformed Steel 3. Tar Steel Kind of Tar Steel 40 Grade = 40000 Lbs/m2 50 Grade = 50000 Lbs/m2 60 Grade = 60000 Lbs/m2  _______________________$_____________________________* Formulaes Circle = πD2 /2 Triangle = ½[a x b] Rectangle = a x b Square = a x b Trapezoid = a + a2 /2 x b + b2 /2 To Find Percentage of Marks Obtained marks/100 x total marks = percentage 885/100 x 1100 = 80.45 % Convert it to Number Again Then opposite the process 80.45 x 1100/100 = 885  _____________________$_______________________________* Area and Volume Of Different Shapes Area of Triangles: Formulae: 1/2 x b x h Suppose: B = 3 Ft H = 5 Ft Area = 1/2 x 3 x 5 = 7.5 Sft Volume of Triangle = ½ x b x h x perpendicular
  • 20. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 H =2, b = 1, L = 5 Ft 1/2 x 2 x 1 x 5 = 5 Cft Area and Volume of Circle Area of Circle = Formulae = π.D2 /4 D = 2 Ft Putting Values = 3.14 x (2)2 /4 =3.142 Sft D = 2 Radius πD2 /4 = πr2 π (2r)2 /4 = π 4r2 /4 = πr2 πD2 /4 = πr2 Volume of Circle = πd2 /4 x L Suppose: D = 2 Ft, L = 10 Ft v = πD2 /4 x L V = 3.14 x (2)2/4 x 10 = 31.42 Cft. Area of Rectangle: Formulae = B x L Suppose: B = 4 Ft, L = 8 Ft 4 x 8 = 32 Sft Area and volume of Trapezoid: Formulae = Sum of Two Parallel Side/2 x H Area = 10 + 8/2 x 5 = 45 Sft Volume = 8 + 10/2 x 5 x 20 = 900 Cft  _______________________$______________________________* Bricks in Cubic Meter Length of Wall = 12 m Thickness of Wall = 0.2286 m Height of Wall = 3 m Volume of Wall = L x T x H 12 x 0.2286 x 3 = 8.2296 We Know That: 1 cum = 500 Bricks 8.2296 X 500 = 4115 Bricks.  ______________________$______________________________* To Find Cement Mortars in CFT. Quantity of Brick Work = 375 Cft No of Bricks = 5062.5 Ratio of Cement Mortar = 1:4 Sum of Ratio = 1 + 4 = 5 We Know That 30 Cft Dry Mortar Used in 100 Cft So: 375 x 30/100 =112.5 Cft  ______________________$______________________________* Cement Mortar in Cubic Meter Quantity of Bricks = 8.2296 Cum No of Bricks = 4114.8
  • 21. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 Ratio of Cement = 1:6 Sum of Ratio = 1 + 6 = 7 We know that 0.30 cum dry Mortar Used in 1 Cum So: Qty of Mortar = 0.30 x 8.2296/1 = 2.4688 cum Cement: 1/7 x 2.4688 = 0.3526 cum 0.3526/0.035 = 10.07 bags Sand: 6/7 x 2.4688 = 2.11 cum.  ___________________________$____________________________* Quantity of Plaster Length of Wall = 20 Ft Height of Wall = 10 Ft Thickness of Plaster = 1 inch = 1/12 = 0.083 Ft Wet Volume of Wall = L x H x T 20 x 10 x 0.083 = 16.6 Cft Dry Volume of Mortar = 16.6 x 1.27 = 21.082 Cft Ratio of Mortar = 1:3 Sum of Ratio = 1 + 3 = 4 Qty of cement: ¼ x 21.082 = 5.2705 Cft 5.2705/1.25 = 5 Bags  _____________________$______________________________* Quantity of Concrete in F.P.S system Quantity of Wet Material = 150 Cft Quantity of Dry Material = 150/100 x 154 = 231 Cft Ratio of Cement: 1:2:4 Sum of Ratio: 1 + 2 + 4 = 7 Cement: 1/7 x 231 = 32.99 Cft 32.99/1.25 = 26.39 Bags Sand = 2/7 x 231 = 66 Cft Bajri: 4/7 x 231 = 132 Cft.  _______________________$_____________________________* Find Overlap for Steel Formulae for overlap Vertical Overlap: Dia of Steel = 40 x D/12 x 8 = 40d/96 Horizontal Overlap: 50 x D/12 x 8 = 50d/96 Suppose: Dia = 4 inch Vertical: 40d/12 x 8 = 40 x 4/12 x 8 = 160/96 = 1.66 Ft Vertical Overlap is = 1 Ft & 8 inch Horizontal: 50d/12 x 8 = 50 x 4/96 = 200/96 = 2.083 Ft Horizontal Overlap + 1 Ft & 10 inch.  _________________________$_____________________________* Stirrup’s (Rings) Formulae = L x 12/Space
  • 22. Quantity Notes By Engineer Saqib Imran Cell No : 0341-7549889 L = 37 Ft Space of Rings c/c = 9 inch Put Value & Apply Formulae 37 x 12/9 = 49.33 Means 50 Rings.  _______________________$______________________________* Length of Rings Length of Column = 10 Ft Dia of Column = 1 Ft Concrete cover = 2 inch No of Bars in Column = 4 Space of Bars = 10 inch Length of Rings = ? Formulae: Space of Bar x side of column 3 inch 3 inch are added for hock length 10 x 4 x 3 = 40 + 3 = 43 inch 3 Ft & 7 inches.  ___________________________$___________________________* Qs: Core Cutter Was Used to Determined Density for a Road Site. Weight of the Cutter was 1286 Gram & Total Weight Was 3195 gram. Volume of Core Cutter was 1000 cm3 & Water Content Was 12%. Determine Bulk Density of This Sample? Sol: Net of soil in Core Cutter: W = 3195 – 1286 = 1909 gram Volume of Core Cutter = V = 1000 c.c Bulk Density = W/V = 1909/1000 = 1.909 Gm/c.c M = 12% = 12 x 100 = 0.12 Bulk Density = ϓ/1 + m Symbol of Bulk Density = ϓ Bulk Density = 1.909/1 + 0.12 = 1.909/1.12 1.705 gm/c.c.  ___________________________$_______________________________* Stair Concrete Waist & Landing Slab = 6 inch Thick Tread = 12 inch Riser = 6 inch Width of Stairs = 4.5 Ft Formulae: 𝐿2 + 𝐻2 L of Waist Slab = 162 + 82 = 17.89 Ft Volume of Waist Slab = 17.89 x 0.5 x 4.5 = 40.25 Cft Volume of Landing = 5 x 4.5 x 0.5 = 11.25 Cft Volume of Steps = 16 x [1/2 x 1 x 0.5] x 4.5 = 18 Cft Total Volume = 40.25 + 11.25 + 18 = 69.50 Cft.  __________________________$__________________________________*