The document reviews the HVAC system for a Santa Fe store. It finds that the existing 7 air handling units (AHUs) are 9 years old and do not provide adequate heating, cooling or zoning coverage. Two options are proposed: 1) Replace all equipment with new AHUs and pumps that can independently control temperature in each zone. 2) Use only existing equipment, which is not recommended as it cannot maintain the required 10 degree Celsius differential between supply and room air temperatures.
3. 3
Actual
Condition:
BMS system will be independent from the
Santa Fe Plaza.
No current information from Santa Fe
commercial plaza.
Recommendations:
The BMS system will be monitored
independently for the store.
MEPF – REVIEW
System Reviewed: BMS System
4. 4
Actual
Condition:
Currently the Santa Fe has 7
AHU units.
Other areas have minor
equipment such as minisplit
units, not recommended for
reusage.
Equipment brand is TRANE, 9
years of usage.
Key
Findings:
Limited space on roof for extra
equipment.
No heating is incorporated in
the existing equipment.
Skating ring that is in BL causes
low temperature in the
surrounding areas.
Temperature observed in the
food court (currently not in
usage) is of 12°C.
Recommendations:
Implement heating stage for
additional air conditioning units.
Structural loads for additional
AHU shall be analyzed.
MEPF – REVIEW
System Reviewed: HVAC System
5. 5
MEPF – MECHANICAL
EXISTING AIR HANDLING UNITS
UMA-01
AHU, Model CSA A-035 UBC 00, Brand
TRANE
SEARS RFL
460V,3F,
60HZ 469,920 BTU/HR TOTAL (137.7
KW), 17,626 CFM, 72.95 GPM 5,450 KG
UMA-02
AHU, Model CSA A-035 UBC 00, Brand
TRANE
SEARS RFL
460V,3F,
60HZ 469,920 BTU/HR TOTAL (137.7
KW), 17,626 CFM, 72.95 GPM 5,450 KG
UMA-03
AHU, Model CSA A-035 UBC 00, Brand
TRANE
SEARS RFL
460V,3F,
60HZ 469,920 BTU/HR TOTAL (137.7
KW), 17,626 CFM, 72.95 GPM 5,450 KG
UMA-04
AHU, Model CSA A-035 UBC 00, Brand
TRANE
SEARS RFL
460V,3F,
60HZ 469,920 BTU/HR TOTAL (137.7
KW), 17,626 CFM, 72.95 GPM 5,450 KG
UMA-05
AHU, Model CSA A-040 UBC 00, Brand
TRANE
SEARS RFL
460V,3F,
60HZ 480,000 BTU/HR TOTAL (140.68
KW), 28,270 CFM, 125.12 GPM 5,450 KG
UMA-06
AHU, Model CSA A-040 UBC 00, Brand
TRANE
SEARS RFL
460V,3F,
60HZ 480,000 BTU/HR TOTAL (140.68
KW), 28,270 CFM, 125.12 GPM 5,450 KG
UMA-07
AHU, Model CSA A-040 UBC 00, Brand
TRANE
SEARS RFL
460V,3F,
60HZ 480,000 BTU/HR TOTAL (140.68
KW), 28,270 CFM, 125.12 GPM 5,450 KG
System Reviewed: HVAC System / Existing Equipment
6. 6
MEPF – MECHANICAL
System Reviewed: HVAC System / Existing Equipment (Pump)
• Remark:
• Current water flow installed with two water
pumps and one stand by is of 2650 lt/min.
TAG DESCRPTION, MODEL, BRAND ELECTRICAL WATER FLOW, TOTAL DYNAMIC LOAD & VELOCITY WEIGHT
BAH 01 Recirculation Water Pump, Type 342, Mod 4x4x7, Picsa Brand 20 HP,460V,3F,60HZ 1325 lt/min, 38m wc, 3500 rpm 40 KG
BAH 02 Recirculation Water Pump, 4x4x7, Picsa-Aurora Brand 20 HP,460V,3F,60HZ 1325 lt/min, 38m wc, 3500 rpm 40 KG
BAH 03 Recirculation Water Pump, 4x4x7, Picsa-Aurora Brand 20 HP,460V,3F,60HZ 1325 lt/min, 38m wc, 3500 rpm 40 KG
Water flow installed with 2 water pump & 1 stand by 2650 lt/min, 38m wc
7. 7
MEPF – MECHANICAL
System Reviewed: HVAC System / Basement Level
Key
Findings:
This area in BL will be considered
for storage, currently there is no
HVAC units covering this area.
Skating ring that is in BL causes
low temperature in the
surrounding areas.
Temperature observed in the
food court (currently not in
usage) is of 12°C.
8. 8
MEPF – MECHANICAL
System Reviewed: HVAC System / Zoning Existing Equipment GL
Zone per
Equipment
Supplied
Floor Level
Area (m2)
UMA-1 Ground Level 1,429 m2
UMA-2 Ground Level 1,315 m2
UMA-3 First Level 1,694 m2
UMA-4 First Level 1,181 m2
UMA-5 - - m2
UMA-6 Second Level 2,234 m2
UMA-7 Second Level 2,080 m2
9. 9
MEPF – MECHANICAL
System Reviewed: HVAC System / Zoning Existing Equipment 1FL
Zone per
Equipment
Supplied
Floor Level
Area (m2)
UMA-1 Ground Level 1,429 m2
UMA-2 Ground Level 1,315 m2
UMA-3 First Level 1,694 m2
UMA-4 First Level 1,181 m2
UMA-5 - - m2
UMA-6 Second Level 2,234 m2
UMA-7 Second Level 2,080 m2
10. 10
MEPF – MECHANICAL
System Reviewed: HVAC System / Zoning Existing Equipment 2FL
Zone per
Equipment
Supplied
Floor Level
Area (m2)
UMA-1 Ground Level 1,429 m2
UMA-2 Ground Level 1,315 m2
UMA-3 First Level 1,694 m2
UMA-4 First Level 1,181 m2
UMA-5 - - m2
UMA-6 Second Level 2,234 m2
UMA-7 Second Level 2,080 m2
11. 11
MEPF – MECHANICAL
System Reviewed: HVAC System / ∆ Temperature °C in Existing
Equipment
Zone per
Equipment
Floor
Level
Area
(m2)
Air
Volume
(CFM)
Air
Volume
(CMH)
∆ °C
UMA-1 Ground
Level
1,429 m2 17,626 29,947 >10°C
UMA-2 Ground
Level
1,315 m2 17,626 29,947 >10°C
UMA-3 First
Level
1,694 m2 17,626 29,947 >10°C
UMA-4 First
Level
1,181 m2 17,626 29,947 >10°C
UMA-5 - - m2 28,270 29,947 -
UMA-6 Second
Level
2,234 m2 28,270 48,031 >10°C
UMA-7 Second
Level
2,080 m2 28,270 48,031 >10°C
Considerations:
Following IKEA’s Engineering &
Construction Manual, Chapter 5, Section
5.1.3:
The differential temperature between
room air temperature and supply air
cannot exceed 10°C (13.3°C).
12. 12
MEPF – MECHANICAL:
EQUIPMENT REQUIRED
System Reviewed: HVAC System / Required Additional Equipment
REQUIRED EQUIPMENT
No. Q'ty
Cooling Cap (Each) Heating Cap (Each) Model (Each)
W kW W kW m3/h
AHU 1 7 163,300 163.3 114,800 114.8 40,171
AHU-2 6 118,500 118.5 85,900 85.9 41,000
AHU-3 3 108,200 108.2 92,600 92.6 35,567
PAC 5 22,600 22.6 26,500 26.5 7,820
13. 13
MEPF – MECHANICAL
System Reviewed: HVAC System / Existing Equipment
USING ONLY EXISTING EQUIPMENT
Remark:
• Not recommended; it is not in compliance
with IKEA ECM Chapter 5 section 5.1.3,
because the differential temperature of the
supply air is below dew point temperature;
therefore, condensing is to be expected on
diffusers.
• The differential temperature between room
air temperature and supply air cannot
exceed 10°C.
ExistingEquipm
entValue
No, Floor AreaNam
e Area Supply Def
No, Qty CCap HCap AVolum
e WFlow CCap HCap AVolum
e WFlow AirTem
p Tem
p
m
2 kW kW m
3/h L/m
in kW kW m
3/h L/m
in degC. degC.
1 1 Showroom 5080 UM
A3,4 2 118.5 - 29,515 236.98 - 59,030 12.80 13.20
2 1 IKEARestaurant&Café 1480
3 1 OfficeCo-
w
orkerarea 970
4 G M
arketHall 4510 UM
A1,2 2 107.27 - 29946.5 214.54 - 59893 13.20
5 G Entrance 200
6 G Selfservicearea 1170
7 G Checkoutarea 370
8 G Exithall 380
9 G SFM
/Bistro 175
10 G As-
Is 170
11 B1 Custom
erServicearea 550 UM
A5,6 2 180 - 48,031 360 - 96,061 13.60 12.40
12 B1 HighLevelPicking 1150
13 B1 W
arehouse 1180
14 B1 Goodsrecivingarea 250
Equim
ent Total
14. 14
MEPF – MECHANICAL
System Reviewed: HVAC System / Option 1: All New Equipment
REPLACING ALL EQUIPMENT WITH NEW
EQUIPMENT
Remark:
• Recommended; the existing equipment have
been in usage from 9 years ago. Do not cover
all areas and do not meet temperature
compliance for the areas.
• Limited area on roof.
• With new equipment, heating will be
implemented.
O
p
tio
n1
_A
llN
e
wE
q
u
ip
m
e
n
ts_A
H
U
(C
:W
a
te
r,H
:W
a
te
r)
N
o
, F
lo
o
r A
re
aN
a
m
e A
re
a S
u
p
p
ly D
e
f
N
o
, Q
y
t CC
a
p HC
a
p AV
o
lu
m
e W
F
lo
w CC
a
p HC
a
p AV
o
lu
m
e W
F
lo
w A
irT
e
m
p T
e
m
p
m
2 kW kW m
3
/
h L
/
m
in kW kW m
3
/
h L
/
m
in d
e
gC
. d
e
gC
.
1 1 S
h
o
wro
o
m 5
0
8
0 A
H
U
1 7 1
6
3
.3 1
1
4
.8 4
0
,1
7
1 8
1
6
.6 5
7
4
.1 2
8
1
,2
0
0 1
6
.0
0 1
0
.0
0
2 1 IK
E
AR
e
s
ta
u
ra
n
t&C
a
fé 1
4
8
0
3 1 O
ffic
eC
o
-
w
o
rke
ra
re
a 9
7
0 P
A
C 5 2
2
.6 2
6
.5 7
,8
2
0 1
1
2
.8 1
3
2
.5 3
9
,1
0
0
4 G M
a
rke
tH
a
ll 4
5
1
0 A
H
U
2 6 1
1
8
.5 8
5
.9 4
1
,0
0
0 7
1
1
.1 5
1
5
.6 2
4
6
,0
0
0 1
6
.0
0 1
0
.0
0
5 G E
n
tra
n
c
e 2
0
0
6 G S
e
lfs
e
rv
ic
ea
re
a 1
1
7
0
7 G C
h
e
c
ko
u
ta
re
a 3
7
0
8 G E
xith
a
ll 3
8
0
9 G S
F
M
/B
is
tro 1
7
5
1
0 G A
s
-
Is 1
7
0
1
1 B
1 C
u
s
to
m
e
rS
e
rv
ic
ea
re
a 5
5
0 A
H
U
3 3 1
0
8
.2 9
2
.6 3
5
,5
6
7 3
2
4
.7 2
7
7
.9 1
0
6
,7
0
0 1
6
.0
0 1
0
.0
0
1
2 B
1 H
ig
hL
e
v
e
lP
ic
kin
g 1
1
5
0
1
3 B
1 W
a
re
h
o
u
s
e 1
1
8
0
1
4 B
1 G
o
o
d
sre
c
iv
in
ga
re
a 2
5
0
H
e
a
tS
o
u
rc
efo
rA
H
U 1
8
9
8
.6
4 1
,8
9
9 3
,9
0
0
A
irC
o
o
le
dW
a
te
rC
h
ille
r(E
xis
tin
g
)
C
o
o
le
dW
a
te
rP
u
m
p
(E
xis
tin
g
)
H
e
a
tp
u
m
pm
o
d
u
lec
h
ille
r(B
ra
n
db
yM
its
u
b
is
h
i) E
-
0
2 3 6
3
2
.8
8 6
3
3 1
8
9
8
.6
4 1
,8
9
9 N
/
A
C
o
o
l&H
e
a
tW
a
te
rP
u
m
p B
A
H
-
0
3
,0
4 3
+
(3
) 1
,3
0
0 3
,9
0
0
A
irC
o
o
le
dW
a
te
rC
h
ille
r(N
e
w
)
C
o
o
le
dW
a
te
rP
u
m
p
(N
e
w
)
E
le
c
tric
a
lH
e
a
te
rD
u
c
tT
y
p
e
E
le
c
tric
a
lH
e
a
te
rD
u
c
tT
y
p
e
E
le
c
tric
a
lH
e
a
te
rD
u
c
tT
y
p
e
E
le
c
tric
a
lH
e
a
te
rD
u
c
tT
y
p
e
E
q
u
im
e
n
t T
o
ta
l
15. 15
MEPF – MECHANICAL
System Reviewed: HVAC System / Option 2
REUSING EXISTING EQUIPMENT, PLUS
IMPLEMENTING DUCT HEATERS
Remark:
• Limited area under revision.
O
p
tio
n2
_R
e
u
seE
xistin
g
(a
d
dE
,H
e
a
te
r+N
e
wA
irH
a
n
d
lin
gU
n
it(C
:W
a
te
r,H
:E
le
c
tric
a
l)
N
o
, F
lo
o
r A
re
aN
a
m
e A
re
a E
q
u
ip
m
e
n
ts Q
ty S
u
p
p
ly D
e
f
N
o
, CC
a
p HC
a
p AV
o
lu
m
e W
F
lo
w CC
a
p HC
a
p AV
o
lu
m
e W
F
lo
w A
irT
e
m
p T
e
m
p
m
2 kW kW m
3
/
h L
/
m
in kW kW m
3
/
h L
/
m
in d
e
gC
. d
e
gC
.
1 1 S
h
o
wro
o
m 5
0
8
0 U
M
A3
,4 2 8
4
.5 6
4
.2 2
9
,5
1
5 1
6
8
.9
8 1
2
8 5
9
,0
3
0 1
6
.0
0 1
0
.0
0
A
C
-
1 9 8
4
.5 6
4
.2 2
9
,5
1
5 7
6
0
.4
2 5
7
8 2
6
5
,6
3
5 1
6
.0
0 1
0
.0
0
2 1 IK
E
AR
e
sta
u
ra
n
t&C
a
fé 1
4
8
0
3 1 O
ffic
eC
o
-
w
o
rke
ra
re
a 9
7
0 P
A
C 5 2
2
.6 2
6
.5 7
,8
2
0 1
1
2
.8
0 1
3
2
.5 3
9
,1
0
0
4 G M
a
rke
tH
a
ll 4
5
1
0 U
M
A1
,2 2 7
9
.1 5
7
.4 2
9
,9
4
7 1
5
8
.2
2 1
1
4
.8 5
9
,8
9
3 1
6
.0
0 1
0
.0
0
5 G E
n
tra
n
c
e 2
0
0 A
C
-
2 7 7
9
.1 5
7
.4 2
9
,9
4
7 5
5
3
.7
8 4
0
1
.6 2
0
9
,6
2
6 1
6
.0
0 1
0
.0
0
6 G S
e
lfse
rv
ic
ea
re
a 1
1
7
0
7 G C
h
e
c
ko
u
ta
re
a 3
7
0
8 G E
xith
a
ll 3
8
0
9 G S
F
M
/B
istro 1
7
5
1
0 G A
s-
Is 1
7
0
1
1 B
1 C
u
sto
m
e
rS
e
rv
ic
ea
re
a 5
5
0 U
M
A5
,6 2 1
0
8
.2 9
2
.6 4
8
,0
3
1 2
1
6
.4
7 1
8
5 9
6
,0
6
2 1
6
.0
0 1
0
.0
0
A
C
-
3 1 1
0
8
.2 9
2
.6 4
8
,0
3
1 1
0
8
.2
3 9
3 4
8
,0
3
1 1
6
.0
0 1
0
.0
0
1
2 B
1 H
ig
hL
e
v
e
lP
ic
kin
g 1
1
5
0
1
3 B
1 W
a
re
h
o
u
se 1
1
8
0
1
4 B
1 G
o
o
d
sre
c
iv
in
ga
re
a 2
5
0
H
e
a
tS
o
u
rc
efo
rA
H
U 1
7
5
8
.0 1
5
9
3
.5
3
3 5
,2
9
0
A
irC
o
o
le
dW
a
te
rC
h
ille
r(E
xistin
g
) E
-
0
1 2 3
5
1
.6 - N
/
A 7
0
3
.2 - N
/
A N
/
A N
/
A
C
o
o
le
dW
a
te
rP
u
m
p
(E
xistin
g
) B
A
H
-0
1
-
0
3 2
+
(1
) 1
,0
5
8 2
,1
1
6
H
e
a
tp
u
m
pm
o
d
u
lec
h
ille
r(B
ra
n
db
yM
itsu
b
ish
i)
C
o
o
l&H
e
a
tW
a
te
rP
u
m
p
A
irC
o
o
le
dW
a
te
rC
h
ille
r(N
e
w
) E
-
0
3 3 3
5
1
.6 - N
/
A 1
0
5
4
.8 - N
/
A N
/
A N
/
A
C
o
o
le
dW
a
te
rP
u
m
p
(N
e
w
) B
A
H
-0
4
-
0
6 3
+
(1
) 1
,0
5
8 3
,1
7
4
E
le
c
tric
a
lH
e
a
te
rD
u
c
tT
y
p
e E
H
-
0
1 1
1 6
4
.2 2
9
,5
1
5 7
0
6
.6 3
2
4
,6
6
5
E
le
c
tric
a
lH
e
a
te
rD
u
c
tT
y
p
e E
H
-
0
2 9 5
7
.4 2
9
,9
4
7 5
1
6
.4 2
6
9
,5
1
9
E
le
c
tric
a
lH
e
a
te
rD
u
c
tT
y
p
e E
H
-
0
1 4 9
2
.6 4
8
,0
3
1 3
7
0
.5 1
9
2
,1
2
4
E
le
c
tric
a
lH
e
a
te
rD
u
c
tT
y
p
e
T
o
ta
l
E
q
u
im
e
n
t
16. 16
MEPF – MECHANICAL
System Reviewed: HVAC System / Option 3
REUSING EXISTING EQUIPMENT
WITHOUT IMPLEMENTING HEATING IN
THE SYSTEM
Remark:
• Not recommended; there is no heating
implemented, does not meet the required
room conditions.
• It is not in compliance with IKEA ECM
Chapter 5 HVAC 5.1.3.
O
p
tio
n3
_R
e
u
s
eE
xis
tin
g
(N
e
wA
irH
a
n
d
lin
gU
n
it(C
:W
a
te
r)
N
o
, F
lo
o
r A
re
aN
a
m
e A
re
a E
q
u
ip
m
e
n
ts Q
ty S
u
p
p
ly D
e
f
N
o
, CC
a
p HC
a
p AV
o
lu
m
e W
F
lo
w CC
a
p HC
a
p AV
o
lu
m
e W
F
lo
w A
irT
e
m
p T
e
m
p
m
2 kW kW m
3
/
h L
/
m
in kW kW m
3
/
h L
/
m
in d
e
gC
. d
e
gC
.
1 1 S
h
o
wro
o
m 5
0
8
0 U
M
A3
,4 2 8
4
.5 2
9
5
1
5 0 1
6
9
.0 5
9
0
3
0 1
6 1
0
A
C
-
1 9 8
4
.5 2
9
5
1
5 0 7
6
0
.4 2
6
5
6
3
5 1
6 1
0
2 1 IK
E
AR
e
s
ta
u
ra
n
t&C
a
fé 1
4
8
0
3 1 O
ffic
eC
o
-
w
o
rke
ra
re
a 9
7
0 P
A
C 5 2
2
.6 2
6
.5 7
8
2
0 0 1
1
2
.8 1
3
2
.5 3
9
1
0
0
4 G M
a
rke
tH
a
ll 4
5
1
0 U
M
A1
,2 2 7
9
.1 2
9
9
4
6
.5 0 1
5
8
.2 5
9
8
9
3 1
6 1
0
5 G E
n
tra
n
c
e 2
0
0 A
C
-
2 7 7
9
.1 2
9
9
4
6
.5 0 5
5
3
.8 2
0
9
6
2
5
.5 1
6 1
0
6 G S
e
lfs
e
rv
ic
ea
re
a 1
1
7
0
7 G C
h
e
c
ko
u
ta
re
a 3
7
0
8 G E
xith
a
ll 3
8
0
9 G S
F
M
/B
is
tro 1
7
5
1
0 G A
s
-
Is 1
7
0
1
1 B
1 C
u
s
to
m
e
rS
e
rv
ic
ea
re
a 5
5
0 U
M
A5
,6 2 1
0
8
.2 4
8
0
3
1 0 2
1
6
.5 9
6
0
6
2 1
6 1
0
A
C
-
3 1 1
0
8
.2 4
8
0
3
1 0 1
0
8
.2 4
8
0
3
1 1
6 1
0
1
2 B
1 H
ig
hL
e
v
e
lP
ic
kin
g 1
1
5
0
1
3 B
1 W
a
re
h
o
u
s
e 1
1
8
0
1
4 B
1 G
o
o
d
sre
c
iv
in
ga
re
a 2
5
0
H
e
a
tS
o
u
rc
efo
rA
H
U 1
7
5
8
.0 - 5
,2
9
0
A
irC
o
o
le
dW
a
te
rC
h
ille
r(E
xis
tin
g
) E
-
0
1 2 3
5
1
.6 - N
/
A 7
0
3
.2 - N
/
A N
/
A N
/
A
C
o
o
le
dW
a
te
rP
u
m
p
(E
xis
tin
g
) B
A
H
-
0
1
-
0
3 2
+
(1
) 1
,0
5
8 2
,1
1
6
H
e
a
tp
u
m
pm
o
d
u
lec
h
ille
r(B
ra
n
db
yM
its
u
b
is
h
i)
C
o
o
l&H
e
a
tW
a
te
rP
u
m
p
A
irC
o
o
le
dW
a
te
rC
h
ille
r(N
e
w
) E
-
0
3 3 3
5
1
.6 - N
/
A 1
0
5
4
.8 - N
/
A N
/
A N
/
A
C
o
o
le
dW
a
te
rP
u
m
p
(N
e
w
) B
A
H
-
0
4
-
0
6 3
+
(1
) 1
,0
5
8 3
,1
7
4
E
le
c
tric
a
lH
e
a
te
rD
u
c
tT
y
p
e
E
le
c
tric
a
lH
e
a
te
rD
u
c
tT
y
p
e
E
le
c
tric
a
lH
e
a
te
rD
u
c
tT
y
p
e
E
le
c
tric
a
lH
e
a
te
rD
u
c
tT
y
p
e
T
o
ta
l
E
q
u
im
e
n
t
17. 17
Actual
Condition:
Currently the Santa Fe has no
provision connection for smoke
extraction.
Key
Findings:
Front perimeter is not to be
used for extraction.
Recommendations:
Mechanical extraction shall be
implemented for this case.
• Smoke hatches are not to be
considered for this project
due to the opening on roof
and available space.
MEPF – REVIEW
System Reviewed: Smoke Management System
18. 18
System Reviewed: Smoke Management System / Basement Level
MEPF – MECHANICAL
Zone Floor Level Area (m2)
B1-1 Basement Level 550 m2
B1-2 Basement Level 274 m2
B1-3 Basement Level 861 m2
B1-4 Basement Level 386 m2
20. 20
System Reviewed: Smoke Management System / First Floor Level
MEPF – MECHANICAL
Zone Floor Level Area (m2)
1-1 First Floor Level 1129 m2
1-2 First Floor Level 1150 m2
1-3 First Floor Level 1441 m2
1-4 First Floor Level 1588 m2
21. 21
System Reviewed: Smoke Management System / Section Proposal
MEPF – MECHANICAL
SMF-2
SMF-3
SFM-4
SMF-1
SHOW ROOM
MARKET HALL
SHOW ROOM
MARKET HALL SELF SERVE/EXIT
CUSTOMER SERVICE
RECIEVING AREA
22. 22
System Reviewed: Smoke Management System / Calculation
MEPF – MECHANICAL
IKEA CDMX#2 Smoke outlet List ( 20220120) ②Exhaut rates by NFPA t=tg×(Q/1055kW)^1/2 Z=0.91×Zs×(t/tg^2/5×Zs^4/5×(A/Zs^2)^3/5)^-1.45 Zt=0.166Qc^2/5 m=0.032Qc^3/5×Z ρ=Patm/RT V=m/ρ
Z Zt when Z<Zt
FLOOR ZONE AREA CH
heat release rate
*1
(熱発生率)
熱発生率の
エリア判断
*1
convective heat
release rate *2
(対流熱発生率)
height(smo
ke)
(天井高)
growth
time
*a
(成長時間)
time
*b
(有効発火
後時間)
(面積/Zs^2
)3/5
height(origi
n)
(煙層深)
height
*c
(清浄高)
Zt *3
(制限高さ)
tempera
ture *4
(温度)
ambient
density *5
(周囲密度)
Exhaust
rates
(排煙風
量)
Exhaust
rates *7
(排煙風
量)
Exhaust
rates
(Z>Zt)
(排煙風
量)
Exhaust
rates
(Z<Zt)
(排煙風
量)
NFPA
風量
REQUIRED
AIR FLOW
決定風量
(Ⅰ)
FINAL
RESULT
Q'TY GRILL SIZE Q'TY FAN NO. FAN CAP.
A Zs Q
Qc
(Q×0.7)
Zs tg t ― ― ― ― Z0
Z
=Zs-Z0
― Zt ― m T ρ V Q Q Q (Ⅰ) - (Ⅱ)
m2 m kW kW m sec sec tg^2/5 Zs^4/5 Zs^2 (面積/Zs^2)^3/5
m m Qc^2/5 0.166*Qc^2/5 Qc^3/5 kg-sec ℃ kg/m3 m3/sec m3/h m3/h m3/h m3/h m3/h m3/h mm × mm mm × mm m/s m3/h
1 1-1 SHOW ROOM -1 1129.00 6.12 10,000 ③ 7,000 6.12 300.0 923.6 9.8 4.3 37.45 7.7 4.9 1.2 34.52 5.73 202.80 7.84 280 0.968 8 29,160 0 29,160 29,200 29,200 29,200 1 SMD-1-1 900 x 900 1,000 x 1,000 2 5.1
1 1-2 SHOW ROOM -2 1150.00 6.12 10,000 ③ 7,000 6.12 300.0 923.6 9.8 4.3 37.45 7.8 4.9 1.2 34.52 5.73 202.80 7.97 280 0.968 8 29,631 0 29,631 29,700 29,700 29,700 1 SMD-1-2 900 x 900 1,000 x 1,100 1 9.4
G G-1 MARKET HALL -1 974.00 6.37 10,000 ③ 7,000 6.37 300.0 923.6 9.8 4.4 40.51 6.7 5.3 1.1 34.52 5.73 202.80 7.01 280 0.968 7 26,070 0 26,070 26,100 26,100 26,100 1 SMD-G-1 850 x 850 1,000 x 950 1 9.5
G G-2 MARKET HALL -2 929.00 6.37 10,000 ③ 7,000 6.37 300.0 923.6 9.8 4.4 40.51 6.6 5.3 1.0 34.52 5.73 202.80 6.73 280 0.968 7 25,019 0 25,019 25,100 25,100 25,100 1 SMD-G-2 850 x 850 1,000 x 950 1 9.2
1 1-3 SHOW ROOM -3 1441.00 6.12 10,000 ③ 7,000 6.12 300.0 923.6 9.8 4.3 37.45 8.9 4.6 1.5 34.52 5.73 202.80 9.69 280 0.968 10 36,056 0 36,056 36,100 36,100 36,100 1 SMD-1-3 950 x 950 850 x 800 2 9.2
1 1-4 SHOW ROOM -4 1588.00 6.12 10,000 ③ 7,000 6.12 300.0 923.6 9.8 4.3 37.45 9.5 4.5 1.6 34.52 5.73 202.80 10.55 280 0.968 11 39,236 0 39,236 39,300 39,300 39,300 1 SMD-1-4 950 x 950 850 x 800 2 10.0
G G-3 MARKET HALL -3 1341.00 6.37 10,000 ③ 7,000 6.37 300.0 923.6 9.8 4.4 40.51 8.2 4.9 1.4 34.52 5.73 202.80 9.26 280 0.968 10 34,432 0 34,432 34,500 34,500 34,500 1 SMD-G-3 950 x 900 800 x 750 2 10.0
G G-4 MARKET HALL -4 1225.00 6.37 10,000 ③ 7,000 6.37 300.0 923.6 9.8 4.4 40.51 7.7 5.0 1.3 34.52 5.73 202.80 8.56 280 0.968 9 31,826 0 31,826 31,900 31,900 31,900 1 SMD-G-4 950 x 900 800 x 750 2 9.2
G G-5-1 SELF SERVE 623.00 6.37 17,000 ② 11,900 6.37 150.0 602.1 7.4 4.4 40.51 5.2 5.5 0.9 42.68 7.08 278.82 8.13 280 0.968 8 30,227 0 30,227 30,300 37,400 37,400 1 SMD-G-5-1 950 × 950 850 x 750 2 10.2
G G-5-2 SELF SERVE 623.00 6.37 17,000 ② 11,900 6.37 150.0 602.1 7.4 4.4 40.51 5.2 5.5 0.9 42.68 7.08 278.82 8.13 280 0.968 8 30,227 0 30,227 30,300 37,400 37,400 1 SMD-G-5-2 950 × 950 850 x 750 2 10.2
G G-6 AS-IS 170.00 6.37 10,000 ③ 7,000 6.37 300.0 923.6 9.8 4.4 40.51 2.4 6.1 0.2 34.52 5.73 202.80 1.53 280 0.968 2 5,709 0 5,709 5,800 5,800 5,800 1 SMD-G-6 500 x 450 500 x 450 1 9.0
G G-7 CHECK OUTS 370.00 6.37 10,000 ③ 7,000 6.37 300.0 923.6 9.8 4.4 40.51 3.8 5.9 0.5 34.52 5.73 202.80 3.02 280 0.968 3 11,231 0 11,231 11,300 11,300 11,300 1 SMD-G-7 600 x 600 750 x 600 1 8.7
G G-8 ENTRANCE 207.00 6.37 10,000 ③ 7,000 6.37 300.0 923.6 9.8 4.4 40.51 2.7 6.1 0.3 34.52 5.73 202.80 1.82 280 0.968 2 6,776 0 6,776 6,800 6,800 6,800 1 SMD-G-8 500 x 500 550 x 450 1 9.5
G G-9 EXIT/SFM 518.00 6.37 10,000 ③ 7,000 6.37 300.0 923.6 9.8 4.4 40.51 4.6 5.7 0.6 34.52 5.73 202.80 4.05 280 0.968 4 15,051 0 15,051 15,100 15,100 15,100 1 SMD-G-9 700 x 700 850 x 750 1 8.2
B1 B1-1 CUSTOMER SERVICE 550.00 7.00 17,000 ② 11,900 7.00 150.0 602.1 7.4 4.7 49.00 4.3 6.1 0.9 42.68 7.08 278.82 7.59 280 0.968 8 28,226 0 28,226 28,300 28,300 28,300 1 SMD-B1-1 850 x 850 1,000 x 1,000 1 9.8
B1 B1-2 WAREHOUSE 274.00 7.00 17,000 ③ 11,900 7.00 300.0 1204.3 9.8 4.7 49.00 2.8 6.7 0.3 42.68 7.08 278.82 2.26 280 0.968 2 8,423 0 8,423 8,500 8,500 8,500 1 SMD-B1-2 900 x 850 800 x 700 2 2.6
B1 B1-3 HIGH LEVEL PICKING 861.00 7.00 17,000 ③ 11,900 7.00 300.0 1204.3 9.8 4.7 49.00 5.6 6.3 0.7 42.68 7.08 278.82 6.13 280 0.968 6 22,808 0 22,808 22,900 22,900 22,900 1 SMD-B1-3 850 x 850 800 x 700 2 7.1
B1 B1-4 GOODS RECEIVING 386.00 7.00 17,000 ② 11,900 7.00 150.0 602.1 7.4 4.7 49.00 3.5 6.4 0.6 42.68 7.08 278.82 5.58 280 0.968 6 20,743 0 20,743 20,800 20,800 20,800 1 SMD-B1-4 650 x 650 800 x 700 1 12.9
29,700
SMF-1
ROOM NAME SMOKE DAMPER SIZE
28,300
SFM-4
37,400
SFM-3
SMF-2 39,300
23. 23
System Reviewed: Smoke Management System / Calculation
MEPF – MECHANICAL
FLOOR ZONE AREA CH
heat release
rate *1
(熱発生率)
Q'TY GRILL SIZE Q'TY FAN NO. FAN CAP.
A Zs Q
m2 m kW mm × mm mm × mm m/s m3/h
1 1-1 SHOW ROOM -1 1129.00 6.12 10,000 1 SMD-1-1 900 x 900 1,000 x 1,000 2 5.1
1 1-2 SHOW ROOM -2 1150.00 6.12 10,000 1 SMD-1-2 900 x 900 1,000 x 1,100 1 9.4
G G-1 MARKET HALL -1 974.00 6.37 10,000 1 SMD-G-1 850 x 850 1,000 x 950 1 9.5
G G-2 MARKET HALL -2 929.00 6.37 10,000 1 SMD-G-2 850 x 850 1,000 x 950 1 9.2
1 1-3 SHOW ROOM -3 1441.00 6.12 10,000 1 SMD-1-3 950 x 950 850 x 800 2 9.2
1 1-4 SHOW ROOM -4 1588.00 6.12 10,000 1 SMD-1-4 950 x 950 850 x 800 2 10.0
G G-3 MARKET HALL -3 1341.00 6.37 10,000 1 SMD-G-3 950 x 900 800 x 750 2 10.0
G G-4 MARKET HALL -4 1225.00 6.37 10,000 1 SMD-G-4 950 x 900 800 x 750 2 9.2
G G-5-1 SELF SERVE 623.00 6.37 17,000 1 SMD-G-5-1 950 × 950 850 x 750 2 10.2
G G-5-2 SELF SERVE 623.00 6.37 17,000 1 SMD-G-5-2 950 × 950 850 x 750 2 10.2
G G-6 AS-IS 170.00 6.37 10,000 1 SMD-G-6 500 x 450 500 x 450 1 9.0
G G-7 CHECK OUTS 370.00 6.37 10,000 1 SMD-G-7 600 x 600 750 x 600 1 8.7
G G-8 ENTRANCE 207.00 6.37 10,000 1 SMD-G-8 500 x 500 550 x 450 1 9.5
G G-9 EXIT/SFM 518.00 6.37 10,000 1 SMD-G-9 700 x 700 850 x 750 1 8.2
B1 B1-1 CUSTOMER SERVICE 550.00 7.00 17,000 1 SMD-B1-1 850 x 850 1,000 x 1,000 1 9.8
B1 B1-2 WAREHOUSE 274.00 7.00 17,000 1 SMD-B1-2 900 x 850 800 x 700 2 2.6
B1 B1-3 HIGH LEVEL PICKING 861.00 7.00 17,000 1 SMD-B1-3 850 x 850 800 x 700 2 7.1
B1 B1-4 GOODS RECEIVING 386.00 7.00 17,000 1 SMD-B1-4 650 x 650 800 x 700 1 12.9
ROOM NAME SMOKE DAMPER SIZE
SFM-3 37,400
SFM-4 28,300
SMF-1 29,700
SMF-2 39,300
24. 24
MEPF – MECHANICAL
System Reviewed: Smoke Management System / Design Criteria
Performance Based Fire Safety
• Engineering Approach
25. 25
MEPF – MECHANICAL
System Reviewed: Smoke Management System / Design Criteria
Performance Based Fire Safety
• Engineering Approach
26. 26
MEPF – MECHANICAL
System Reviewed: Smoke Management System / Design Criteria
Performance Based Fire Safety
• Engineering Approach
27. 27
MEPF – MECHANICAL
• IKEA ENGINEERING & CONSTRUCTION MANUAL
• CHAPTER 7 7.6.2.2
• The air velocity for make-up air in evacuation routes may not exceed 2m/s.
• Maximum commercial smoke extraction is 39,300 CMH (from Show Room /
Market Hall).
• When air velocity is less than 2m/s, effective opening size is as below.
• 39,300[CMH] / 3,600[s/h] / 2[m/s] = 5.46 m2
• When make-up air from louver, louver size is 13.65 m2 (opening rate 40%)
PROPOSED CONCEPT-1
SUPPLY AIR VOLUME
System Reviewed: Smoke Management System / Design Criteria
29. 29
Actual
Condition:
The main existing equipment
from Sears:
• One 500 KVA transformer.
• One 750 KVA transformer.
• One 250 KW generator.
Key
Findings:
BL1 substation space & Roof.
Recommendations:
Currently under IKEA standards,
one transformer with enough
capacity to hold all loads should
be installed, as well as a standby
equipment with the same
capacity (Ikea’s Engineering and
Construction Manuals, Chapter
8, Section 8.1.2).
• In order to join both
transformers, they are
recommended to have same
capacities and supplier must
guarantee alignment in
impedance.
• In case of reusing
equipment, loads will be
segregated.
MEPF – REVIEW
System Reviewed: Electrical System
30. 30
MEPF – MECHANICAL
System Reviewed: Electrical System / Existing Equipment
Medium Voltage Switchgear
Remark:
• Not recommended to reuse; the existing medium voltage switch gear
does not comply with the IKEA Standard: ES-01-001.
• Current switchgear is air-insulated type.
31. 31
MEPF – MECHANICAL
System Reviewed: Electrical System / Option A
ELECTRICAL EQUIPMENT
Remark:
• All new equipment; complies with Ikea and local norms.
• Power line 2 is subject to CFE’s supply, this is not common
practice in Mexico.
HVS
500 KVA
1500 KVA
1500 KVA
HVS: HIGH VOLTAGE SWITCHGEAR
EMG: EMERGENCY GENERATOR
T1
T2
M G
M
POWER LINE 1 POWER LINE 2
EMG LVS
HVS
500 KVA
1500 KVA
1500 KVA
HVS: HIGH VOLTAGE SWITCHGEAR
EMG: EMERGENCY GENERATOR
LVS: LOW VOLTAGE SWITCHGEAR
M: METERING EQUIPMENT
POWER TRANSFORMER
BREAKERS/SWITCHES
T1
T2
M G
M
POWER LINE 1 POWER LINE 2
EMG LVS
32. 32
MEPF – MECHANICAL
System Reviewed: Electrical System / Option B
ELECTRICAL EQUIPMENT
Remark:
• Reusing both transformers and generator; complies with local norms.
Implications:
• One transformer will not have a back up in case of failure (TR3).
• Low voltage is segregated.
HVS
500 KVA
1500 KVA
1500 KVA
HVS: HIGH VOLTAGE SWITCHGEAR
EMG: EMERGENCY GENERATOR
LVS: LOW VOLTAGE SWITCHGEAR
M: METERING EQUIPMENT
POWER TRANSFORMER
BREAKERS/SWITCHES
T1
T2
M G
M
POWER LINE 1 POWER LINE 2
EMG LVS
BLUE: EXISTING EQUIPMENT
BLACK: NEW EQUIPMENT/UPGRADED
POWER LINE 1
EMG LVS
T1
T2
M G
300 KVA
750 KVA
500 KVA
EMG
M G
250 KVA
T3
300 KVA
HVS
M
33. 33
Actual
Condition:
There is no solar panel
sustainability proposal or
system to be considered as
such.
Key
Findings:
300 m2 area where some
unused gas tanks is available,
awaiting information from the
LL.
Recommendations:
This system is beneficial to the
fiscal annual tax deductions.
MEPF – REVIEW
System Reviewed: Sustainability
35. 35
Actual
Condition:
The plaza Santa Fe has two
current cisterns with a capacity
of 345 m3 total.
• This is not enough space for
the sprinkler system and its
storage requirement
according to NFPA.
Key
Findings:
Additional spacing needs to be
considered for an 1100 m3 tank.
• Considered/proposed location
is in BL.
Recommendations:
Additional space for pumps
needs to be considered.
• Proposed location is BL.
MEPF – REVIEW
System Reviewed: Fire Protection System
36. 36
MEPF – FIRE PROTECTION
FIRE PROTECTION SYSTEM – HAZARD CLASSIFICATION
37. 37
MEPF – FIRE PROTECTION
WATER FLOW RATE-MARKET HALL
Area: Market Hall
Hazard Classification: EH2/Storage
Commodity: Group A Exposed Expanded Plastics / Stable
Water Flow rate
Density : 0.6GPM/Sqft
Coverage Area : 2,500Sqft
Sprinkler flow : 1,500 GPM (0.6gpm/sqft x2500 sqft)
Hose Stream : 500GPM
Duration : 120 min
Total Water Flow rate : 2,000gpm
Total Water Storage : 240,000 gallons (2,000 gpm x 120 min)
1091 m3
Fire Tank 1091 m3
Areas W/The Most Risk
38. 38
MEPF – MECHANICAL
System Reviewed: Fire Protection System / Storage Tank Option 1
CEILING HEIGHT: <4.6 m, GROUP A, EXPOSED, EXPANDED PLASTIC, STABLE
Implications:
• According to IKEA’s Chapter 7, Section 7.3.4: additional sprinklers are needed if:
• Also, according to IKEA’s Chapter 7, Section 7.7.1: additional smoke detectors are required if:
39. 39
MEPF – MECHANICAL
System Reviewed: Fire Protection System / Storage Tank Option 2
EH1
Remark:
• With this option storage tank’s volume is
lowered, impact architectural height limitations
& commodity criteria, all criteria is met
according to NFPA 13 (Classification according
to IKEA’s Chapter 7, Table 7.1 and NFPA 13
Section 21.3.1)
• Storage tank needed is 511 m3.
Implications:
• Commodity classification non complaint to IKEA
Engineering & Construction Manual Chapter 7.
• Smallest tank in compliance with NFPA.
• Reevaluation of goods.
40. 40
MEPF – MECHANICAL
System Reviewed: Fire Protection System / Storage Tank Option 3
EH1 VS EH2
Classification of NFPA 13 2019
4.3.5* Extra Hazard (Group 1) (EH1). The following shall be protected with EH1 occupancy criteria in this standard:
1) Spaces with very high quantity and combustibility of contents.
2) Spaces where dust, lint, or other materials are present, introducing the probability of rapidly developing fires.
4.3.6* Extra Hazard (Group 2) (EH2). The following shall be protected with EH2 occupancy criteria in this standard:
1) Spaces with very high quantity and combustibility of contents.
2) Spaces with substantial amounts of combustible or flammable liquids.
3) Spaces where shielding of combustibles is extensive.
41. 41
MEPF – MECHANICAL
System Reviewed: Fire Protection System / Storage Tank Option 3
Goods Classification / Hazard Classification
Classification is in accordance with Chapter 7, Table 7.1
With the following reference: “Product Classification
Report, Code Consultants, Inc., 2009”
42. 42
MEPF – MECHANICAL
System Reviewed: Fire Protection System / Storage Tank Option 3
Goods Classification / Hazard Classification
The basis for the Product Classification Report, Code
Consultants, Inc., 2009 report is on account of the inventory
and classified material as per NFPA 13. Keeping in mind that
this is a benchmark report between two stores in the US,
from 2009 and with different sizes compared to Santa Fe
CDMX.
Therefore, if a new Goods Classification is to be made, in
order to change the Hazard Classification, reevaluating the
inventory is a must.
44. 44
Actual
Condition:
The plaza Santa Fe has two
current cisterns with a capacity
of 345 m3 total.
Key
Findings:
These two cisterns can be
reused.
• 50% of daily consumption for
storage.
Recommendations:
Additional space for pumps is
required.
MEPF – REVIEW
System Reviewed: Sanitary & Plumbing System
47. 47
DISCIPLINE ITEM
INFORMATION
AVAILABLE
TENANTS COMMENTS RISK IMPACT DESIGN / PROJECT
CALCULATION
REPORTS
X -
MATERIAL
SPECIFICATIONS
O -
EQUIPMENT
SPECIFICATIONS
O SEARS
LOW VOLTAGE SYSTEMS:
IPTV
IT & TELECOMMUNICATIONS
SECURITY & CCTV
CARD ACCESS & INTRUSION ALARM
PUBLIC ADDRESS
PEOPLECOUNTING
CALCULATION
REPORTS
X -
MATERIAL
SPECIFICATIONS
O -
EQUIPMENT
SPECIFICATIONS
O SEARS
CALCULATION
REPORTS
X -
MATERIAL
SPECIFICATIONS
X -
EQUIPMENT
SPECIFICATIONS
X -
CALCULATION
REPORTS
X -
MATERIAL
SPECIFICATIONS
O -
EQUIPMENT
SPECIFICATIONS
O SEARS
CALCULATION
REPORTS
X -
MATERIAL
SPECIFICATIONS
X -
EQUIPMENT
SPECIFICATIONS
X -
CALCULATION
REPORTS
X -
MATERIAL
SPECIFICATIONS
X -
EQUIPMENT
SPECIFICATIONS
X -
CALCULATION
REPORTS
X -
MATERIAL
SPECIFICATIONS
X -
EQUIPMENT
SPECIFICATIONS
O -
CALCULATION
REPORTS
X -
MATERIAL
SPECIFICATIONS
X -
EQUIPMENT
SPECIFICATIONS
X -
CALCULATION
REPORTS
X -
MATERIAL
SPECIFICATIONS
X -
EQUIPMENT
SPECIFICATIONS
X -
CALCULATION
REPORTS
X -
MATERIAL
SPECIFICATIONS
X -
EQUIPMENT
SPECIFICATIONS
X -
MATERIAL CHECK
ELECTRICAL SYSTEM Continue
The information available corresponds to
the commercial plaza.
Proposal can be made independently. Continue
MATERIAL
SPECIFICATIONS
SANITARY & PLUMBING SYSTEM Continue
BUILDING MANAGEMENT SYSTEM No information is available. Proposal can be made independently. Continue
HVAC SYSTEM
Equipment information does not
correspond to the equipment installed.
Reutilizing the equipment is not a
recommendation for warranty purposes.
Continue
SMOKE EXHAUST SYSTEM No information on this system available.
Proposal can be made independently and
coordinated with smoke exhaust system.
Continue
Continue
FIRE ALARM SYSTEM
Connection location and specs should be
supplied by LL.
Compatibility and communication point to
be aligned.
Continue
FIRE PROTECTION SYSTEM
The solution to water storage location
should be decided. Reutilizing the
equipment is not a recommendation for
warranty purposes (pumps).
Delay
RAINWATER SYSTEM
The information available corresponds to
the commercial plaza.
Continue
Electrical equipment information is
provided.
Lightning system information is missing.
Reutilizing the equipment is not a
recommendation for warranty purposes.
Lightning system to be analyzed for
possible upgrade; cost to be impacted.
Architectural consultant will confirm
number of sanitary fixtures to include
according to norm.
Ikea standards do not accept existing pipe
material (PVC).
Cost impact if sanitary installations are not
reused.
Water quality to be analyzed.
Ikea standards do not accept existing pipe
material (PVC).
CALCULATION
REPORTS
X -
GAS SUPLY SYSTEM
Natural gas is to be considered. LL will
share connection point
Proposal can be made independently. Continue
PNEUMATIC HANDLING SYSTEM No information is available.
Ikea standards do not accept existing pipe
material (PVC).
Cost to be impacted if needs to be
upgraded.
X -
EQUIPMENT
SPECIFICATIONS
X -
The water storage is not enough for the
system required as per IKEA standards.
The information on the existing equipment
and corresponding capacities will be
analyzed to store requirements (for pumps).
Proposal can be made independently.
48. 48
CODES REQUIREMENT
DISCIPLINE EXISTING EQUIPMENT / SERVICE AREA IN PLAZA
COMPLIES W/NATIONAL
STANDARD
COMPLIES W/IKEA
STANDARD
ADDITIONAL NOTES
SANITARY & PLUMBING SYSTEM Sanitary System SEARS Yes No
PVC material is not accepted
by IKEA standards (Chapter 6,
Section 6.3.2).
Water Supply System SEARS/BL Yes No
PVC material is not accepted
by IKEA standards (Chapter 6,
Section 6.3.2).
FIRE PROTECTION SYSTEM Fire Protection System BL - No
Storage cistern required is of
1100 m3.
RAINWATER SYSTEM Rainwater System ROOF Yes No
PVC material is not accepted
by IKEA standards and
siphonic rainwater system is
preferred by IKEA Standards
(Chapter 6, Section 6.4.2).
49. 49
DUE DILIGENCE REPORT: MEPF
IMPROVEMENTS SUMMARY
NO. SPECIALTY ITEM PRIORITY IMPROVEMENT REQUIRED SPECS TO
COMPLY
NOTES
1.- Fire Protection System Storage Tank 1 1100 m3 cistern should be
constructed to comply with
NFPA.
IKEA / NFPA Important is location and
foundation reinforcement.
2.- Plumbing System PVC Installations 3 Change material to comply with
IKEA standards.
IKEA Shall be reviewed by IKEA.
3.- Rainwater System PVC Installations 3 Change material to comply with
IKEA standards.
IKEA Shall be reviewed by IKEA.
4.- Electrical System Reusing Transformers (TR-1 &
TR-2)
2 Replace with new equipment. IKEA Shall be reviewed by IKEA.
5.- HVAC System Reusing HVAC Equipment 2 Additional equipment, if enough
space.
IKEA Consider an improvement
in design and system to
avoid condensation.
6.- HVAC System Reusing Chiller Equipment 2 No heating is implemented in
current equipment
IKEA Assist in achieving comfort
temperatures during
winter season.