Tarbela Dam is one of the world’s largest earth and rock filled Dam and greatest water resources development project which was completed in 1976 as a component of Indus Basin Project.
It is also the second largest dam in the world in terms of reservoir capacity, which is 11.62 million acre-feet (14.3 billion cubic meters).
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Tarbela Hydro Power Plant
1.
2.
3.
4. Introduction
Location
History
Purpose
Construction
Power plant Description
Power Generation
Transmission Lines
Projects Benefits
5.
6. Tarbela Dam is one of the world’s largest
earth and rock filled Dam and greatest
water resources development project
which was completed in 1976 as a
component of Indus Basin Project.
It is also the second largest dam in the
world in terms of reservoir capacity,
which is 11.62 million acre-feet (14.3
billion cubic meters).
7. The Dam is located
on the river Indus
known as the
“Abbasin” or the
father of the river
at a distance of
130 KM (80 Miles) to
the North West of
Islamabad, in Topi,
Distt Sawabi, KPK.
8. Pakistan was entirely dependent on
unregulated flows of the Indus River and her
tributaries even after 20 years of
independence.
The main reason behind this problem was
the seasonal variations in the river flow.
Additionally, there were no storage
reservoirs to conserve surplus flows.
Tarbela Dam was constructed as part of the
Indus Basin Project after signing of the
1960 Indus Waters Treaty between India
and Pakistan.
9.
10. The primary purpose of the Tarbela Dam
Project was to regulate the flows of the
Indus River for irrigation use.
Other objectives were to achieve
substantial generation of hydroelectric
power and flood control by conserving
snow melt and monsoon flows of the
Indus River.
11.
12. Construction on the primary elements of
the project was started in 1968 and
completed in 1976. The initial operations
of the dam started in 1978. The project
was fully completed in 1984, at a cost of
$1.49bn.
Construction of Tarbela Dam was carried
out in three stages to meet the diversion
requirements of the river.
13.
14. The Tarbela hydro power plant is constructed on the right side of
the main embankment. Five large tunnels were constructed as
part of Tarbela Dam's outlet works. Hydroelectricity is generated
from turbines in tunnel 1 through 3, while tunnels 4 and 5 were
designed for irrigation use. Both tunnels are to be converted to
hydropower tunnels to increase Tarbela's electricity-generating
capacity. These tunnels were originally used to divert the Indus
River while the dam was being constructed.
It is installed with 14 power generating units and the water is fed
from outlet tunnels one, two and three. The plant has a total
installed capacity of 3,478MW.
Four generators of 175MW each on tunnel one were put into
production in 1977. There are six 175MW generators on tunnel
two, four of which were commissioned in 1982 and the
remaining two in 1985. Four generators of 432MW each were
installed in tunnel three in 1992, , for a total generating capacity
of 3,478 MW.
15.
16. No of Units 14
Installed
Capacity
3478 MW
UNITS 1-10 175 MW EACH (Total 1750 MW)
UNITS 11-14 432 MW EACH (Total 1728 MW)
TUNNEL-1 4 UNITS OF 175 MW EACH
(COMPLETED 1977)
TUNNEL-2 6 UNITS OF 175 MW EACH
(COMPLETED 1985)
TUNNEL-3 4 UNITS OF 432 MW EACH
(COMPLETED 1993)
18. It is the biggest hydro power station in
Pakistan having a capacity of generating
3,478 MW of electricity. It provides nearly 30
percent of all the irrigation water available
in dry season, 2100 MW of hydropower was
to be initially generated as a by-product. By
the year 1992, the generating capacity was
raised to 3428 MW, with the 3rd extension
comprising four more units of 432 MW
capacity each.
19.
20. No of turbines/Units 14
Output (BPH) 1-10 23900
Output (BPH) 11-14 586000
Generator 1-10 11-14
Output (P.f) 0.85 0.85
Output (MW) 175 432
Rated voltage (KV) 13.8 13.8
Transformer 1-4 5-14
Capability
(MVA/Phase)
79 71
Voltage ratio 13.8/220 13.8/500
23. In addition to fulfilling the primary purpose
of the dam, i.e., supplying water for
irrigation, Tarbela Power Station has
generated 341.139 billion kWh of
cheap hydro-electric energy since
commissioning. A record annual generation
of 16.463 billion kWh was recorded during
1998–99. Annual generation during 2007–08
was 14.959 billion kWh while the station
shared peak load of 3702 MW during the
year, which was 23.057% of total WAPDA
system peak.
24.
25. In September 2013, Pakistan's Water and Power
Development Authority signed a Rs. 26.053 billion
contract with Chinese firm Sinohydro and
Germany's Voith Hydro for executing civil works on
the 1,410 MW Tarbela-IV Extension Project.
The project is being constructed at tunnel 4 which
was originally intended for irrigation but was later
taken up for power generation as country’s electricity
demand increased.
On an annual basis, over 70% of water passing
through Tarbela is discharged over spillways, while
only a portion of the remaining 30% is used for
hydropower generation.
26. The fifth phase extension will use the second
irrigation tunnel. The project will require
installation of three turbines with a capacity
of 470 MW each in Tarbela's fifth tunnel
which was previously dedicated to
agricultural use. Upon completion, the total
power generating capacity of Tarbela Dam
will be increased to 6,298 MW.
The hydro power project of tunnel 5 has two
major components: power generation
facilities and power evacuation facilities.