SlideShare a Scribd company logo
1 of 2
Download to read offline
Janelia Facts and Features - Landscape Building – July 2006
Procurement
• Design: Charette Competition with World class
signature architects
• Contractor selection: Negotiated, experienced-based
qualifications with depth of staff and proven ability to
manage large complex fast-track projects within budget
and schedule
• Contract type: Design-build Guaranteed Maximum
Price based on schematic design drawings and
specifications
Comparable Footprints
• Landscape Building 500,000 sf (1000’ x 200’) including
garage
• Dulles Airport Main Terminal 240,000 sf (1200’ x 200’)
• Flight deck of JFK Aircraft Carrier 265,000 sf (1052’ x
252’)
• Stood on end the building would equal the height of an
85 story building and would exceed the height of the
Eiffel Tower (986’)
• Length is equal to three football fields
Total Project Construction Man-hours
• 3,000,000 hours
Design Hours
• 175,000 Architect
• 135,000 Design Consultants
• 310,000 Total
Schedule
• Land Acquisition Dec 2000
• Assemble Design, Management, and Construction
teams 2001
• Project Definition, Site design for Rough Grading
permit, and budgeting 2002
• GMP Contract Nov 2002
• Groundbreaking Nov 2002
• Substantial Completion of Construction Documents
June 2004
• Concrete start June 2003
• Concrete Complete September 2004
• Enclosure Start September 2004
• Substantially weather-tight August 2005
• Phased Occupancy May – August 2006
Concrete
• 66,000 cubic yards of Concrete, more concrete than in
one tower of the Petronas Towers
• 4700 tons of Reinforcing steel
• 4 tower cranes and two on site batch plants utilized at
height of concrete placement
Stone Flooring
• First floor stone: Italian Basaltina
• Same material as used in the Vatican
• Stone treads for Feature Stairs black granite from India
Site
• 681 acres, wooded and meadows
• 60 acres developed
• Stone excavation 200,000 cys
• Stone crushed for backfill and road beds
• Total Excavated material 400,00 cys
• Total stone crushed on site 110,000 cys
• 2 acre wetland migration area
• Public road improvements: Dual lane Riverside
Parkway, Intersection improvements at Route 7
• Preservation of 17 acre home lot and National Historic
Register Manor House and associated historic vista
• Excess excavated earth and stone used on site to create
naturalized meadows
Structure
• Hybrid steel frame and reinforced concrete both mild
steel and post-tension reinforcement to allow for clear
span requirements and necessary low floor vibration
characteristics for labs
Steel
• 90’ Clear span girder fro column free labs
• Girder 54” deep, 30” wide, Clear Span for Column-free
Labs
• Cross Section comparable to highway bridge sections
• 3200 Total tons
Mechanical
• Central plant (100,000 sf on two levels) with in
building footprint
• 3- gas fired Steam Boilers (2- 1500 hp, 1- 900 hp)
• 5- Cooling towers at 1200 tons each
• 15- Air handling units at 45,000 cfm
Glass
• One of largest structurally glazed system in US
(147,000 sf)
• The largest as far as uniqueness and at the outer limits
of production capabilities of glass
• Installation time: 85,000 man hours
• Glass Manufactured in Belgium
• Assembled Albany, New York, and New Brunswick,
Canada
• 60 custom dyes for aluminum extrusions
• Glass Doors from Singapore, assembled California
• Systems underwent one year of independent testing of
performance and design validation
Janelia Facts and Features - Landscape Building – July 2006
Electrical
• 3- 35 kvA substations
• Emergency power: 3- 2000 kw gensets with catalytic
converters powers all critical equipment and telecom
switches, lab lighting, and lab convenience outlets
• Street lighting: Custom Designed LEDs Manufactured
in Krakow Poland
Millwork/Wood Flooring
• Hand selected Maple veneers from Michigan trees
• Veneers laid up in Indiana, assembled into finished
work Providence, RI
• End grain Hornbeam flooring from France; also
mesquite from Texas
Site Trees 100% Recycled
• Stumps and softwoods ground into mulch
• Small trees and limbs chipped for waste-to-energy plant
• 35,000 Board feet of Hardwoods milled into random
width plank flooring for Project hotel and townhouses
Landscape
• Low impact drought resistant plant materials and low
impact design strategy
• 180,000 sf Green roof with cell gardens (second largest
green roof in US)
• Two manmade lakes fed by roof drainage, ground run-
off, spring and deep well, used for irrigation and
wildlife habitat; preservation of third farm pond as
amenity along new public roadway
Scientific Equipment Areas
• 30’ clear height by 13,00 sf for large equipment, with
isolated slab construction
• Additional 30,000 sf of non-programmed space for
electron microscopy, and other TBD scientific uses
Labs
• 16 each 9,600 sf Lab pods
• Custom design, flexible and interchangeable lab bench
system, UL listed
• All areas quickly converted from bench system to
computer labs or robotic uses
• Open design concept to facilitate interaction and
collaboration between researchers
• All labs have unobstructed view of cell gardens and
north facing glass walls for natural light
• Column free 90’ clear span open plan
• Finished ceiling heights 12 feet
Data Center
• 10,000 sf (5,000 sf initial fitup)
• 142 tons AC
• 100 watts/sf electric basis of design
Public Areas/Conference Center
• Full conference facilities including library, 250 seat
auditorium, 125 seat seminar room
• Full commercial kitchen
• Dining facility ability to seat 200
• 2 monumental structural glass and stainless steel
staircases to enhance circulation between lower Public
floor and conference facilities and two upper floors of
labs
Vivarium
• 8,000 sf
• Swedish manufactured Robotic cagewash system
Communications
• Two independent access points to offsite facilities for
redundancy
• Hardwired and wireless systems in building for
tele/data/network
• Voice-over IP technology for telephone system
• One million LF of cabling both fiber and copper
Administration
• 2850 Total Drawings
• 7100 Pages of Specifications
• 2300 Total Submittals
• 5000 Total RFI’s Projected
• 1350 Total PCO’s Projected
Countries Represented
• Sweden – Robotics
• India – Stone Stair Treads @ Feature Stair
• Italy – Basaltina Stone Flooring on First Floor of the
Landscape Building, Stone Countertops & Seat Fabric
In the Auditorium & Seminar Room
• Belgium – Auditorium Curtain & Glass Fabrication
• Canada – Feature Stair Glass & Stainless Steel
Handrails (Ornamental Metals)
• Poland – Custom Light Fixtures
• England – Project Screens
• Argentina – Roof Railing, Stainless Steel Security
Bollards, Exterior & Interior Benches & Misc. Stainless
Steel Ornamental Metals
• Denmark – Day Care Playground Equipment
• Austria – Glass
• Finland – Glass
• China – Granite Tops
• France – Hornbeam Wood Flooring Processed in
France, Trees Grown in Germany
• Germany – Plumbing Fixtures, Blasi Doors @ Main
Entrance of Landscape Building, Green Roof Grass
Seed & Roof Cell Drains
• Dubai - Furniture

More Related Content

What's hot

NJFuture Redevelopment Forum 2015 Hanini
NJFuture Redevelopment Forum 2015 HaniniNJFuture Redevelopment Forum 2015 Hanini
NJFuture Redevelopment Forum 2015 HaniniNew Jersey Future
 
Commercial complex at parel south mumbai
Commercial complex   at parel south mumbaiCommercial complex   at parel south mumbai
Commercial complex at parel south mumbaiRAAJESH SHETH
 
one angel square Manchester
 one angel square Manchester one angel square Manchester
one angel square ManchesterYuktashah
 
LEED 2009 applied to a mixed - use building
LEED 2009 applied to a mixed - use buildingLEED 2009 applied to a mixed - use building
LEED 2009 applied to a mixed - use buildingWaleed Liaqat
 
GROUP HOUSING-Case study-CLEO COUNTY
GROUP HOUSING-Case study-CLEO COUNTYGROUP HOUSING-Case study-CLEO COUNTY
GROUP HOUSING-Case study-CLEO COUNTYShivamSuman
 
Designer Bungalow for Sale
Designer Bungalow for SaleDesigner Bungalow for Sale
Designer Bungalow for SaleSaif Yousuf
 
New Brick Homes in Country Club Neighborhood South Carolina
New Brick Homes in Country Club Neighborhood South CarolinaNew Brick Homes in Country Club Neighborhood South Carolina
New Brick Homes in Country Club Neighborhood South CarolinaExecutive Construction Homes
 
150316 case studies
150316 case studies150316 case studies
150316 case studiesTieng Wei
 
DTH coaxial vacuum tube solar collector
DTH coaxial vacuum tube solar collectorDTH coaxial vacuum tube solar collector
DTH coaxial vacuum tube solar collectorStefano Bertolini
 
The capital nomination 31-08-2013
The capital nomination   31-08-2013The capital nomination   31-08-2013
The capital nomination 31-08-2013engineeringwatch
 
Sherman Associates Park/Washington Block Development
Sherman Associates Park/Washington Block DevelopmentSherman Associates Park/Washington Block Development
Sherman Associates Park/Washington Block DevelopmentLindsay Bales
 
4 eu best practices a141428
4 eu best practices a1414284 eu best practices a141428
4 eu best practices a141428Azman Samer
 
Principles of planning and bye laws pns
Principles of planning and bye laws pnsPrinciples of planning and bye laws pns
Principles of planning and bye laws pnsPratap Shinde
 
Case study on Leadenhall Building KUET BECM 2k15
Case study on Leadenhall Building KUET BECM 2k15Case study on Leadenhall Building KUET BECM 2k15
Case study on Leadenhall Building KUET BECM 2k15Arafat Akash
 
Hot Climate Double Facades: A Focus on Solar Avoidance
Hot Climate Double Facades: A Focus on Solar AvoidanceHot Climate Double Facades: A Focus on Solar Avoidance
Hot Climate Double Facades: A Focus on Solar AvoidanceTerri Meyer Boake
 

What's hot (20)

From Sieve to Silver
From Sieve to SilverFrom Sieve to Silver
From Sieve to Silver
 
NJFuture Redevelopment Forum 2015 Hanini
NJFuture Redevelopment Forum 2015 HaniniNJFuture Redevelopment Forum 2015 Hanini
NJFuture Redevelopment Forum 2015 Hanini
 
Commercial complex at parel south mumbai
Commercial complex   at parel south mumbaiCommercial complex   at parel south mumbai
Commercial complex at parel south mumbai
 
one angel square Manchester
 one angel square Manchester one angel square Manchester
one angel square Manchester
 
LEED 2009 applied to a mixed - use building
LEED 2009 applied to a mixed - use buildingLEED 2009 applied to a mixed - use building
LEED 2009 applied to a mixed - use building
 
GROUP HOUSING-Case study-CLEO COUNTY
GROUP HOUSING-Case study-CLEO COUNTYGROUP HOUSING-Case study-CLEO COUNTY
GROUP HOUSING-Case study-CLEO COUNTY
 
AIA Chicago Presentation
AIA Chicago PresentationAIA Chicago Presentation
AIA Chicago Presentation
 
Designer Bungalow for Sale
Designer Bungalow for SaleDesigner Bungalow for Sale
Designer Bungalow for Sale
 
New Brick Homes in Country Club Neighborhood South Carolina
New Brick Homes in Country Club Neighborhood South CarolinaNew Brick Homes in Country Club Neighborhood South Carolina
New Brick Homes in Country Club Neighborhood South Carolina
 
150316 case studies
150316 case studies150316 case studies
150316 case studies
 
30 st.mary axe
30 st.mary axe30 st.mary axe
30 st.mary axe
 
DTH coaxial vacuum tube solar collector
DTH coaxial vacuum tube solar collectorDTH coaxial vacuum tube solar collector
DTH coaxial vacuum tube solar collector
 
The capital nomination 31-08-2013
The capital nomination   31-08-2013The capital nomination   31-08-2013
The capital nomination 31-08-2013
 
Sherman Associates Park/Washington Block Development
Sherman Associates Park/Washington Block DevelopmentSherman Associates Park/Washington Block Development
Sherman Associates Park/Washington Block Development
 
4 eu best practices a141428
4 eu best practices a1414284 eu best practices a141428
4 eu best practices a141428
 
Ulx June09
Ulx June09Ulx June09
Ulx June09
 
Principles of planning and bye laws pns
Principles of planning and bye laws pnsPrinciples of planning and bye laws pns
Principles of planning and bye laws pns
 
Case study on Leadenhall Building KUET BECM 2k15
Case study on Leadenhall Building KUET BECM 2k15Case study on Leadenhall Building KUET BECM 2k15
Case study on Leadenhall Building KUET BECM 2k15
 
Mrr ppt aug2011
Mrr ppt aug2011Mrr ppt aug2011
Mrr ppt aug2011
 
Hot Climate Double Facades: A Focus on Solar Avoidance
Hot Climate Double Facades: A Focus on Solar AvoidanceHot Climate Double Facades: A Focus on Solar Avoidance
Hot Climate Double Facades: A Focus on Solar Avoidance
 

Similar to Janelia Facts and Features

Oldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand HotelOldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand HotelBlake Johnson
 
Instacon tower mohali
Instacon tower mohaliInstacon tower mohali
Instacon tower mohalivibha goyal
 
Webinar 630 lofts
Webinar   630 loftsWebinar   630 lofts
Webinar 630 loftsdouglasco
 
High rise building case study
High rise building case study High rise building case study
High rise building case study VISHAKA BOTHRA
 
A presentation on high rise
A presentation on high riseA presentation on high rise
A presentation on high riseAnamikaAntora
 
Seminar on capital gate building
Seminar on capital gate buildingSeminar on capital gate building
Seminar on capital gate buildingNayan Rao
 
Industrial Ventilation and Air Pollution Control
Industrial Ventilation and Air Pollution ControlIndustrial Ventilation and Air Pollution Control
Industrial Ventilation and Air Pollution ControlJohn Kleinfelter
 
70 Acres of Net-Zero Energy
70 Acres of Net-Zero Energy70 Acres of Net-Zero Energy
70 Acres of Net-Zero EnergyDerek Satnik
 
Aldar Headquarters Dubai
Aldar Headquarters DubaiAldar Headquarters Dubai
Aldar Headquarters DubaiNeha Rampuria
 
Mixing Roofing Materials at Waldegrave School - Steve Scottorn, SIG Design & ...
Mixing Roofing Materials at Waldegrave School - Steve Scottorn, SIG Design & ...Mixing Roofing Materials at Waldegrave School - Steve Scottorn, SIG Design & ...
Mixing Roofing Materials at Waldegrave School - Steve Scottorn, SIG Design & ...SIG Design and Technology
 
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
ALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTIONALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTION
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTIONRajesh Kolli
 
Hilton at High Point
Hilton at High PointHilton at High Point
Hilton at High PointDavid Schultz
 
HOA ASSGINMENT.pptx
HOA ASSGINMENT.pptxHOA ASSGINMENT.pptx
HOA ASSGINMENT.pptxArpita K
 

Similar to Janelia Facts and Features (20)

Vcc canada
Vcc canadaVcc canada
Vcc canada
 
Oldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand HotelOldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
 
One world trade centre
One world trade centreOne world trade centre
One world trade centre
 
high tech building
high tech buildinghigh tech building
high tech building
 
Instacon tower mohali
Instacon tower mohaliInstacon tower mohali
Instacon tower mohali
 
IFC
IFCIFC
IFC
 
Webinar 630 lofts
Webinar   630 loftsWebinar   630 lofts
Webinar 630 lofts
 
High rise building case study
High rise building case study High rise building case study
High rise building case study
 
A presentation on high rise
A presentation on high riseA presentation on high rise
A presentation on high rise
 
Seminar on capital gate building
Seminar on capital gate buildingSeminar on capital gate building
Seminar on capital gate building
 
Norman foster
Norman foster Norman foster
Norman foster
 
Norman foster
Norman foster Norman foster
Norman foster
 
Industrial Ventilation and Air Pollution Control
Industrial Ventilation and Air Pollution ControlIndustrial Ventilation and Air Pollution Control
Industrial Ventilation and Air Pollution Control
 
70 Acres of Net-Zero Energy
70 Acres of Net-Zero Energy70 Acres of Net-Zero Energy
70 Acres of Net-Zero Energy
 
Aldar Headquarters Dubai
Aldar Headquarters DubaiAldar Headquarters Dubai
Aldar Headquarters Dubai
 
Mixing Roofing Materials at Waldegrave School - Steve Scottorn, SIG Design & ...
Mixing Roofing Materials at Waldegrave School - Steve Scottorn, SIG Design & ...Mixing Roofing Materials at Waldegrave School - Steve Scottorn, SIG Design & ...
Mixing Roofing Materials at Waldegrave School - Steve Scottorn, SIG Design & ...
 
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
ALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTIONALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTION
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
 
Hilton at High Point
Hilton at High PointHilton at High Point
Hilton at High Point
 
HOA ASSGINMENT.pptx
HOA ASSGINMENT.pptxHOA ASSGINMENT.pptx
HOA ASSGINMENT.pptx
 
RiverArch Investor Summary - Sponsor.pdf
RiverArch Investor Summary - Sponsor.pdfRiverArch Investor Summary - Sponsor.pdf
RiverArch Investor Summary - Sponsor.pdf
 

More from Rodrigo Uribe CSI, LEED AP BD+C (10)

Massing
MassingMassing
Massing
 
HDRAWN3
HDRAWN3HDRAWN3
HDRAWN3
 
DivingTwr
DivingTwrDivingTwr
DivingTwr
 
A-311
A-311A-311
A-311
 
HHMI AERIAL_NIGHT
HHMI AERIAL_NIGHTHHMI AERIAL_NIGHT
HHMI AERIAL_NIGHT
 
11x17 A4 A5 A6 FIRST
11x17 A4 A5 A6 FIRST11x17 A4 A5 A6 FIRST
11x17 A4 A5 A6 FIRST
 
WMT WS
WMT WSWMT WS
WMT WS
 
Bldg Section 2
Bldg Section 2Bldg Section 2
Bldg Section 2
 
Solar Res 2
Solar Res 2Solar Res 2
Solar Res 2
 
Rodrigo Uribe LEED AP BD+C 2017
Rodrigo Uribe LEED AP BD+C 2017Rodrigo Uribe LEED AP BD+C 2017
Rodrigo Uribe LEED AP BD+C 2017
 

Janelia Facts and Features

  • 1. Janelia Facts and Features - Landscape Building – July 2006 Procurement • Design: Charette Competition with World class signature architects • Contractor selection: Negotiated, experienced-based qualifications with depth of staff and proven ability to manage large complex fast-track projects within budget and schedule • Contract type: Design-build Guaranteed Maximum Price based on schematic design drawings and specifications Comparable Footprints • Landscape Building 500,000 sf (1000’ x 200’) including garage • Dulles Airport Main Terminal 240,000 sf (1200’ x 200’) • Flight deck of JFK Aircraft Carrier 265,000 sf (1052’ x 252’) • Stood on end the building would equal the height of an 85 story building and would exceed the height of the Eiffel Tower (986’) • Length is equal to three football fields Total Project Construction Man-hours • 3,000,000 hours Design Hours • 175,000 Architect • 135,000 Design Consultants • 310,000 Total Schedule • Land Acquisition Dec 2000 • Assemble Design, Management, and Construction teams 2001 • Project Definition, Site design for Rough Grading permit, and budgeting 2002 • GMP Contract Nov 2002 • Groundbreaking Nov 2002 • Substantial Completion of Construction Documents June 2004 • Concrete start June 2003 • Concrete Complete September 2004 • Enclosure Start September 2004 • Substantially weather-tight August 2005 • Phased Occupancy May – August 2006 Concrete • 66,000 cubic yards of Concrete, more concrete than in one tower of the Petronas Towers • 4700 tons of Reinforcing steel • 4 tower cranes and two on site batch plants utilized at height of concrete placement Stone Flooring • First floor stone: Italian Basaltina • Same material as used in the Vatican • Stone treads for Feature Stairs black granite from India Site • 681 acres, wooded and meadows • 60 acres developed • Stone excavation 200,000 cys • Stone crushed for backfill and road beds • Total Excavated material 400,00 cys • Total stone crushed on site 110,000 cys • 2 acre wetland migration area • Public road improvements: Dual lane Riverside Parkway, Intersection improvements at Route 7 • Preservation of 17 acre home lot and National Historic Register Manor House and associated historic vista • Excess excavated earth and stone used on site to create naturalized meadows Structure • Hybrid steel frame and reinforced concrete both mild steel and post-tension reinforcement to allow for clear span requirements and necessary low floor vibration characteristics for labs Steel • 90’ Clear span girder fro column free labs • Girder 54” deep, 30” wide, Clear Span for Column-free Labs • Cross Section comparable to highway bridge sections • 3200 Total tons Mechanical • Central plant (100,000 sf on two levels) with in building footprint • 3- gas fired Steam Boilers (2- 1500 hp, 1- 900 hp) • 5- Cooling towers at 1200 tons each • 15- Air handling units at 45,000 cfm Glass • One of largest structurally glazed system in US (147,000 sf) • The largest as far as uniqueness and at the outer limits of production capabilities of glass • Installation time: 85,000 man hours • Glass Manufactured in Belgium • Assembled Albany, New York, and New Brunswick, Canada • 60 custom dyes for aluminum extrusions • Glass Doors from Singapore, assembled California • Systems underwent one year of independent testing of performance and design validation
  • 2. Janelia Facts and Features - Landscape Building – July 2006 Electrical • 3- 35 kvA substations • Emergency power: 3- 2000 kw gensets with catalytic converters powers all critical equipment and telecom switches, lab lighting, and lab convenience outlets • Street lighting: Custom Designed LEDs Manufactured in Krakow Poland Millwork/Wood Flooring • Hand selected Maple veneers from Michigan trees • Veneers laid up in Indiana, assembled into finished work Providence, RI • End grain Hornbeam flooring from France; also mesquite from Texas Site Trees 100% Recycled • Stumps and softwoods ground into mulch • Small trees and limbs chipped for waste-to-energy plant • 35,000 Board feet of Hardwoods milled into random width plank flooring for Project hotel and townhouses Landscape • Low impact drought resistant plant materials and low impact design strategy • 180,000 sf Green roof with cell gardens (second largest green roof in US) • Two manmade lakes fed by roof drainage, ground run- off, spring and deep well, used for irrigation and wildlife habitat; preservation of third farm pond as amenity along new public roadway Scientific Equipment Areas • 30’ clear height by 13,00 sf for large equipment, with isolated slab construction • Additional 30,000 sf of non-programmed space for electron microscopy, and other TBD scientific uses Labs • 16 each 9,600 sf Lab pods • Custom design, flexible and interchangeable lab bench system, UL listed • All areas quickly converted from bench system to computer labs or robotic uses • Open design concept to facilitate interaction and collaboration between researchers • All labs have unobstructed view of cell gardens and north facing glass walls for natural light • Column free 90’ clear span open plan • Finished ceiling heights 12 feet Data Center • 10,000 sf (5,000 sf initial fitup) • 142 tons AC • 100 watts/sf electric basis of design Public Areas/Conference Center • Full conference facilities including library, 250 seat auditorium, 125 seat seminar room • Full commercial kitchen • Dining facility ability to seat 200 • 2 monumental structural glass and stainless steel staircases to enhance circulation between lower Public floor and conference facilities and two upper floors of labs Vivarium • 8,000 sf • Swedish manufactured Robotic cagewash system Communications • Two independent access points to offsite facilities for redundancy • Hardwired and wireless systems in building for tele/data/network • Voice-over IP technology for telephone system • One million LF of cabling both fiber and copper Administration • 2850 Total Drawings • 7100 Pages of Specifications • 2300 Total Submittals • 5000 Total RFI’s Projected • 1350 Total PCO’s Projected Countries Represented • Sweden – Robotics • India – Stone Stair Treads @ Feature Stair • Italy – Basaltina Stone Flooring on First Floor of the Landscape Building, Stone Countertops & Seat Fabric In the Auditorium & Seminar Room • Belgium – Auditorium Curtain & Glass Fabrication • Canada – Feature Stair Glass & Stainless Steel Handrails (Ornamental Metals) • Poland – Custom Light Fixtures • England – Project Screens • Argentina – Roof Railing, Stainless Steel Security Bollards, Exterior & Interior Benches & Misc. Stainless Steel Ornamental Metals • Denmark – Day Care Playground Equipment • Austria – Glass • Finland – Glass • China – Granite Tops • France – Hornbeam Wood Flooring Processed in France, Trees Grown in Germany • Germany – Plumbing Fixtures, Blasi Doors @ Main Entrance of Landscape Building, Green Roof Grass Seed & Roof Cell Drains • Dubai - Furniture