SlideShare a Scribd company logo
1 of 13
WORK METHODE OF
DEMOLISH OCR-001
Present by
This Construction Method Statement covers all activities associated with Demolition work in area 53 with building code 341-
OCR-001 OSBL specifically the balcony area including extended ancillary areas and provides a problem statement or
description of the work.
SCOPE OF WORK
The scope of demolition works
includes the following:
 Site Preparation
 Install Scaffolding
 Demolition of Ramp
 Demolition of Ceilling
 Demolition of Balcony 1st Floor
 Demolition of Stair
 Dismantling the Scaffold and
propping structure.
 Disposal
WORK SQUENCE
Site Preparation
 Identify the site location, neighborhood conditions, adjoining buildings, land slope and retaining walls.
 Identify special site restrictions such as designated planned areas, special restrictions on operating times, noise and
vibration restrictions and others.
 Verification of building dimensions, such as overall building height, inter-storey height and building footprint.
 Identify the building/structure to be demolished. make several segments to know which one is prioritized for demolition,
with the order of segment 1 being demolished first followed by segment 2.
METHODE OF EXECUTION
Site Preparation
• Verify all underground and overhead utilities.
• Temporary utility arrangements for project activities, such as supply of water supplies to minimize dust, etc.
• Moving Air-condtional to safe place
METHODE OF EXECUTION
Site Preparation
 Identify factors that may affect the Demolition schedule, such as operational restrictions imposed by regulations and
anticipated weather conditions.
METHODE OF EXECUTION
DISCRIPTION
DATE
17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 1-May 2-May 3-May 1-May 2-May 3-May 4-May 5-May 6-May 7-May 8-May 9-May 10-May 11-May 12-May 13-May
Segemnt 1
Cleaning
Moving AC
Install Protection
Demolish Ramp
Install Scaffolding
Demolish Balcony
Demolish Scaffold
Segment 2
Install Scaffolding
Demolish Balcony
Demolish Scaffold
Disposal
Site Preparation
 Requirements for walkway covers
and demolition catch platforms for
pedestrian protection.
 Requirements for scaffolding, asiba,
and double-layered work platforms
to hold demolition debris,
depending on the method used and
environmental conditions.
Temporary support and cross
structure (bracing) for each
structure.
 Make temporary acces door for
people's access in and out.
 The number and size of debris
wrappers depends on the volume
level of the debris, and the disposal
route.
 Planning for window and door
covers to prevent dust and debris
from entering the room.
METHODE OF EXECUTION
Site Preparation
 Submit scaffolding layout drawings and details to be approved by authorities / consultant.
 Ensure that the scaffolding to be used is fit for purpose. Inspect the scaffolding for damage. Any items deemed to be
damages shall not be used.
 Do not start the erection of scaffolding / form-work until approval to proceed has been received from the appropriate
authorities.
 Install asiba right below the area that will be demolished which is useful for holding the former demolition that falls down
can be accommodated in the asiba area.
 Review the project specification to ensure that the back propping has been undertaken correctly.
METHODE OF EXECUTION
STEP #1 DEMOLOTION OF RAMP
Before installing scaffolding in the front area, the ramp slope must be demolished first, to support the surface to be flat when
installing scaffolding.
For concrete demolish work other than slabs, namely ramp. using a jack hammer tool. In accordance with its function this
tool is often used in various construction projects which are generally used for the destruction and demolition of foundation
structures. And also often used in excavation and mining. Using a jack hammer machine will save more time and be more
efficient.
METHODE OF EXECUTION
STEP #2 DEMOLOTION OF CEILING
 After the ramp has been
dismantled, the next step is to
install scaffolding on the leveled
area.
 The ceiling can be removed
with a hammer, a pry bar and
one's hands. One must watch
out for any plumbing, heating
or electrical lines.
 Check whether there is an
electrical installation or not, if
there is first turn off the power
source, then dismantle the
electrical installation and store
it in a safe place.
 If the area is free from electrical
installations, then the next step
can be continued by
dismantling the roof from the
front to the back and so on.
make a demolition parimeter
per 1 m2. repeat the next step.
METHODE OF EXECUTION
STEP #3 DEMOLOTION OF BALCONY 1st FLOOR
Reinforced concrete balcony shall be demolished by gradually breaking away the concrete. The reinforcement shall remain
and be cut off after the concrete is broken away. Demolition by cutting is suitable for work that requires accuracy and
tolerance of noise and vibration. Concrete or other building parts are divided into segments to facilitate demolition.
METHODE OF EXECUTION
Segmen 1 Demolih with concrete cutter
Unlike crushing tools such as hammers and jack hammers,
this cutting tool will make concrete that is not cut will be
maintained and not damaged. This cutting tool itself is now
equipped with a water tank, this serves to reduce dust
flying during the cutting process as well as a medium for
cooling the engine. and also for more precise cutting and
avoiding concrete that will not be cut.
Segmen 2 Demolish with jack hammer
For concrete demolish work other than slabs, namely
columns and beams. using a jack hammer tool. In
accordance with its function this tool is often used in
various construction projects which are generally used for
the destruction and demolition of foundation structures.
And also often used in excavation and mining. Using a jack
hammer machine will save more time and be more efficient.
STEP #4 DEMOLOTION OF STAIR
 In general, the concrete demolition process can be done using concrete hammers and jack hammers, although some use
concrete saws to cut the reinforcing bars that are still embedded.
 Try not to make the demolition work field too large. For example, when you have successfully demolished a 1 m2 concrete
field, you can move to the next field with the same area. Its function, in addition to making the work process easier, the
risk of harm caused can also be minimized.
 Then, the edges of the concrete structure that are in direct contact with the neighboring structure must be done at the
final stage. This is the stage that must be done carefully.
 Preceded by lowering the u-head at the center of the span or the area of greatest moment towards the edge, to avoid a
sudden drop.
 Followed by dismantling the scaffolding frame.
 Next, remove the join pin and cross brace
METHODE OF EXECUTION
STEP #5 DISMANTLING THE SCAFFOLDING
STEP #6 DISPOSAL
 First, prepare transport vehicles such as pick-up or dump truck as a means of transporting demolition materials.
 After the debris material is collected, immediately move it into a pick-up truck or dump truck.
 Once all the debris has been loaded into the hauler and it has been confirmed that there are no hazardous objects on site,
the material is ready to be sent to the disposal site. repeat the above steps if the material being transported is large.
THANK YOU FOR
ATTENTION

More Related Content

Similar to PPT DEMOLISH.pptx

advanced constructiion technologies
advanced constructiion technologiesadvanced constructiion technologies
advanced constructiion technologiesMOHANAHARIHARAN R
 
Maintenanceandrepairofbuildings Amit Payal
Maintenanceandrepairofbuildings Amit PayalMaintenanceandrepairofbuildings Amit Payal
Maintenanceandrepairofbuildings Amit PayalAMIT PAYAL
 
final report last.pdf
final report last.pdffinal report last.pdf
final report last.pdfwzhen77
 
Final slides
Final slidesFinal slides
Final slideshongbinng
 
Building Contruction 1 Project 1: Experience Construction
Building Contruction 1 Project 1: Experience ConstructionBuilding Contruction 1 Project 1: Experience Construction
Building Contruction 1 Project 1: Experience ConstructionYung Kai
 
Building Construction Details
Building Construction DetailsBuilding Construction Details
Building Construction Detailscocongkening
 
Demolition of building and blasting equipment
Demolition of building and blasting equipmentDemolition of building and blasting equipment
Demolition of building and blasting equipmentChetan Karwa
 
Demolition of Structures.
Demolition of Structures.Demolition of Structures.
Demolition of Structures.Chintan Varia
 
Experiencing Construction
Experiencing ConstructionExperiencing Construction
Experiencing ConstructionSNLim125
 
Summer training report
Summer training reportSummer training report
Summer training reportaki8872233
 
Construction site
Construction siteConstruction site
Construction siteTimun Loh
 
Building Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing ConstructionBuilding Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing Constructionjisunfoo
 
Lecture_all.pdf
Lecture_all.pdfLecture_all.pdf
Lecture_all.pdfRanadita
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of buildingAnimesh1714013
 
Rehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structuresRehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structuresShahrukh Niaz
 
Techniques for Demolition of Structure
Techniques for Demolition of StructureTechniques for Demolition of Structure
Techniques for Demolition of StructureDinaker Dixit
 
GOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptxGOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptxHirenThakkar31
 

Similar to PPT DEMOLISH.pptx (20)

advanced constructiion technologies
advanced constructiion technologiesadvanced constructiion technologies
advanced constructiion technologies
 
Maintenanceandrepairofbuildings Amit Payal
Maintenanceandrepairofbuildings Amit PayalMaintenanceandrepairofbuildings Amit Payal
Maintenanceandrepairofbuildings Amit Payal
 
Demolition pptx
Demolition pptxDemolition pptx
Demolition pptx
 
final report last.pdf
final report last.pdffinal report last.pdf
final report last.pdf
 
Final slides
Final slidesFinal slides
Final slides
 
Final slides
Final slidesFinal slides
Final slides
 
Building Contruction 1 Project 1: Experience Construction
Building Contruction 1 Project 1: Experience ConstructionBuilding Contruction 1 Project 1: Experience Construction
Building Contruction 1 Project 1: Experience Construction
 
Building Construction Details
Building Construction DetailsBuilding Construction Details
Building Construction Details
 
Demolition of building and blasting equipment
Demolition of building and blasting equipmentDemolition of building and blasting equipment
Demolition of building and blasting equipment
 
Demolition of Structures.
Demolition of Structures.Demolition of Structures.
Demolition of Structures.
 
Experiencing Construction
Experiencing ConstructionExperiencing Construction
Experiencing Construction
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Construction site
Construction siteConstruction site
Construction site
 
Building Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing ConstructionBuilding Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing Construction
 
Lecture_all.pdf
Lecture_all.pdfLecture_all.pdf
Lecture_all.pdf
 
Demolition.pptx
Demolition.pptxDemolition.pptx
Demolition.pptx
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of building
 
Rehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structuresRehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structures
 
Techniques for Demolition of Structure
Techniques for Demolition of StructureTechniques for Demolition of Structure
Techniques for Demolition of Structure
 
GOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptxGOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptx
 

More from RizqiNoviant

LEMARI DEP.DALITAS.pdf
LEMARI DEP.DALITAS.pdfLEMARI DEP.DALITAS.pdf
LEMARI DEP.DALITAS.pdfRizqiNoviant
 
DENAH TITIK PENERANGAN KANOPI LOADING-UNLOADING.pdf
DENAH TITIK PENERANGAN KANOPI LOADING-UNLOADING.pdfDENAH TITIK PENERANGAN KANOPI LOADING-UNLOADING.pdf
DENAH TITIK PENERANGAN KANOPI LOADING-UNLOADING.pdfRizqiNoviant
 
Layout Dominos Solo.pdf
Layout Dominos Solo.pdfLayout Dominos Solo.pdf
Layout Dominos Solo.pdfRizqiNoviant
 
ANALISA STRUKTUR I kuliah 1.ppt
ANALISA STRUKTUR I kuliah 1.pptANALISA STRUKTUR I kuliah 1.ppt
ANALISA STRUKTUR I kuliah 1.pptRizqiNoviant
 
ANSTRUK 2 2015 (6).pptx
ANSTRUK 2 2015 (6).pptxANSTRUK 2 2015 (6).pptx
ANSTRUK 2 2015 (6).pptxRizqiNoviant
 
HBK Seturan - PPT Approval - 03 Mar 22.pdf
HBK Seturan - PPT Approval - 03 Mar 22.pdfHBK Seturan - PPT Approval - 03 Mar 22.pdf
HBK Seturan - PPT Approval - 03 Mar 22.pdfRizqiNoviant
 
Approval-Des ME HBK Solo Baru-22.02.22.pdf
Approval-Des ME HBK Solo Baru-22.02.22.pdfApproval-Des ME HBK Solo Baru-22.02.22.pdf
Approval-Des ME HBK Solo Baru-22.02.22.pdfRizqiNoviant
 
METODE KERJA RENOVASI RUMAH JABATAN DEWAN GUBERNUR BANK INDONESIA.pptx
METODE KERJA RENOVASI RUMAH JABATAN DEWAN GUBERNUR BANK INDONESIA.pptxMETODE KERJA RENOVASI RUMAH JABATAN DEWAN GUBERNUR BANK INDONESIA.pptx
METODE KERJA RENOVASI RUMAH JABATAN DEWAN GUBERNUR BANK INDONESIA.pptxRizqiNoviant
 

More from RizqiNoviant (9)

LEMARI DEP.DALITAS.pdf
LEMARI DEP.DALITAS.pdfLEMARI DEP.DALITAS.pdf
LEMARI DEP.DALITAS.pdf
 
DENAH TITIK PENERANGAN KANOPI LOADING-UNLOADING.pdf
DENAH TITIK PENERANGAN KANOPI LOADING-UNLOADING.pdfDENAH TITIK PENERANGAN KANOPI LOADING-UNLOADING.pdf
DENAH TITIK PENERANGAN KANOPI LOADING-UNLOADING.pdf
 
PPT Brawijaya.ppt
PPT Brawijaya.pptPPT Brawijaya.ppt
PPT Brawijaya.ppt
 
Layout Dominos Solo.pdf
Layout Dominos Solo.pdfLayout Dominos Solo.pdf
Layout Dominos Solo.pdf
 
ANALISA STRUKTUR I kuliah 1.ppt
ANALISA STRUKTUR I kuliah 1.pptANALISA STRUKTUR I kuliah 1.ppt
ANALISA STRUKTUR I kuliah 1.ppt
 
ANSTRUK 2 2015 (6).pptx
ANSTRUK 2 2015 (6).pptxANSTRUK 2 2015 (6).pptx
ANSTRUK 2 2015 (6).pptx
 
HBK Seturan - PPT Approval - 03 Mar 22.pdf
HBK Seturan - PPT Approval - 03 Mar 22.pdfHBK Seturan - PPT Approval - 03 Mar 22.pdf
HBK Seturan - PPT Approval - 03 Mar 22.pdf
 
Approval-Des ME HBK Solo Baru-22.02.22.pdf
Approval-Des ME HBK Solo Baru-22.02.22.pdfApproval-Des ME HBK Solo Baru-22.02.22.pdf
Approval-Des ME HBK Solo Baru-22.02.22.pdf
 
METODE KERJA RENOVASI RUMAH JABATAN DEWAN GUBERNUR BANK INDONESIA.pptx
METODE KERJA RENOVASI RUMAH JABATAN DEWAN GUBERNUR BANK INDONESIA.pptxMETODE KERJA RENOVASI RUMAH JABATAN DEWAN GUBERNUR BANK INDONESIA.pptx
METODE KERJA RENOVASI RUMAH JABATAN DEWAN GUBERNUR BANK INDONESIA.pptx
 

Recently uploaded

IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 

Recently uploaded (20)

IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 

PPT DEMOLISH.pptx

  • 1. WORK METHODE OF DEMOLISH OCR-001 Present by
  • 2. This Construction Method Statement covers all activities associated with Demolition work in area 53 with building code 341- OCR-001 OSBL specifically the balcony area including extended ancillary areas and provides a problem statement or description of the work. SCOPE OF WORK The scope of demolition works includes the following:  Site Preparation  Install Scaffolding  Demolition of Ramp  Demolition of Ceilling  Demolition of Balcony 1st Floor  Demolition of Stair  Dismantling the Scaffold and propping structure.  Disposal
  • 4. Site Preparation  Identify the site location, neighborhood conditions, adjoining buildings, land slope and retaining walls.  Identify special site restrictions such as designated planned areas, special restrictions on operating times, noise and vibration restrictions and others.  Verification of building dimensions, such as overall building height, inter-storey height and building footprint.  Identify the building/structure to be demolished. make several segments to know which one is prioritized for demolition, with the order of segment 1 being demolished first followed by segment 2. METHODE OF EXECUTION
  • 5. Site Preparation • Verify all underground and overhead utilities. • Temporary utility arrangements for project activities, such as supply of water supplies to minimize dust, etc. • Moving Air-condtional to safe place METHODE OF EXECUTION
  • 6. Site Preparation  Identify factors that may affect the Demolition schedule, such as operational restrictions imposed by regulations and anticipated weather conditions. METHODE OF EXECUTION DISCRIPTION DATE 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 1-May 2-May 3-May 1-May 2-May 3-May 4-May 5-May 6-May 7-May 8-May 9-May 10-May 11-May 12-May 13-May Segemnt 1 Cleaning Moving AC Install Protection Demolish Ramp Install Scaffolding Demolish Balcony Demolish Scaffold Segment 2 Install Scaffolding Demolish Balcony Demolish Scaffold Disposal
  • 7. Site Preparation  Requirements for walkway covers and demolition catch platforms for pedestrian protection.  Requirements for scaffolding, asiba, and double-layered work platforms to hold demolition debris, depending on the method used and environmental conditions. Temporary support and cross structure (bracing) for each structure.  Make temporary acces door for people's access in and out.  The number and size of debris wrappers depends on the volume level of the debris, and the disposal route.  Planning for window and door covers to prevent dust and debris from entering the room. METHODE OF EXECUTION
  • 8. Site Preparation  Submit scaffolding layout drawings and details to be approved by authorities / consultant.  Ensure that the scaffolding to be used is fit for purpose. Inspect the scaffolding for damage. Any items deemed to be damages shall not be used.  Do not start the erection of scaffolding / form-work until approval to proceed has been received from the appropriate authorities.  Install asiba right below the area that will be demolished which is useful for holding the former demolition that falls down can be accommodated in the asiba area.  Review the project specification to ensure that the back propping has been undertaken correctly. METHODE OF EXECUTION
  • 9. STEP #1 DEMOLOTION OF RAMP Before installing scaffolding in the front area, the ramp slope must be demolished first, to support the surface to be flat when installing scaffolding. For concrete demolish work other than slabs, namely ramp. using a jack hammer tool. In accordance with its function this tool is often used in various construction projects which are generally used for the destruction and demolition of foundation structures. And also often used in excavation and mining. Using a jack hammer machine will save more time and be more efficient. METHODE OF EXECUTION
  • 10. STEP #2 DEMOLOTION OF CEILING  After the ramp has been dismantled, the next step is to install scaffolding on the leveled area.  The ceiling can be removed with a hammer, a pry bar and one's hands. One must watch out for any plumbing, heating or electrical lines.  Check whether there is an electrical installation or not, if there is first turn off the power source, then dismantle the electrical installation and store it in a safe place.  If the area is free from electrical installations, then the next step can be continued by dismantling the roof from the front to the back and so on. make a demolition parimeter per 1 m2. repeat the next step. METHODE OF EXECUTION
  • 11. STEP #3 DEMOLOTION OF BALCONY 1st FLOOR Reinforced concrete balcony shall be demolished by gradually breaking away the concrete. The reinforcement shall remain and be cut off after the concrete is broken away. Demolition by cutting is suitable for work that requires accuracy and tolerance of noise and vibration. Concrete or other building parts are divided into segments to facilitate demolition. METHODE OF EXECUTION Segmen 1 Demolih with concrete cutter Unlike crushing tools such as hammers and jack hammers, this cutting tool will make concrete that is not cut will be maintained and not damaged. This cutting tool itself is now equipped with a water tank, this serves to reduce dust flying during the cutting process as well as a medium for cooling the engine. and also for more precise cutting and avoiding concrete that will not be cut. Segmen 2 Demolish with jack hammer For concrete demolish work other than slabs, namely columns and beams. using a jack hammer tool. In accordance with its function this tool is often used in various construction projects which are generally used for the destruction and demolition of foundation structures. And also often used in excavation and mining. Using a jack hammer machine will save more time and be more efficient.
  • 12. STEP #4 DEMOLOTION OF STAIR  In general, the concrete demolition process can be done using concrete hammers and jack hammers, although some use concrete saws to cut the reinforcing bars that are still embedded.  Try not to make the demolition work field too large. For example, when you have successfully demolished a 1 m2 concrete field, you can move to the next field with the same area. Its function, in addition to making the work process easier, the risk of harm caused can also be minimized.  Then, the edges of the concrete structure that are in direct contact with the neighboring structure must be done at the final stage. This is the stage that must be done carefully.  Preceded by lowering the u-head at the center of the span or the area of greatest moment towards the edge, to avoid a sudden drop.  Followed by dismantling the scaffolding frame.  Next, remove the join pin and cross brace METHODE OF EXECUTION STEP #5 DISMANTLING THE SCAFFOLDING STEP #6 DISPOSAL  First, prepare transport vehicles such as pick-up or dump truck as a means of transporting demolition materials.  After the debris material is collected, immediately move it into a pick-up truck or dump truck.  Once all the debris has been loaded into the hauler and it has been confirmed that there are no hazardous objects on site, the material is ready to be sent to the disposal site. repeat the above steps if the material being transported is large.