SlideShare a Scribd company logo
1 of 25
Download to read offline
Tampa Scrap Site Remediation (TSSR)
A Project Management Outlook
Tampa Scrap Processors Site Data
 Previous Uses: Submerged Lands Prior to 1976; Created from dredge
spoils 1976-79; Scrap Metal Recycling Mid- 1980’s to 2000.
 Size: 16 acres.
 BSRA: Executed 5/3/2003
 Contaminants: Petroleum, Organic Solvents, PCB’s, PAH’s, and Metals.
 Future Uses: Cargo Yard for Container Storage.
 Controls: Deed Restrictions, Impervious Cap
 Design Cost: $801,202
 Construction Costs: $2,469,775
 Total Costs (2005-2012): $3,370,977
 VCTC – Total est.@$232,000
 Project Management Knowledge Areas *
 Scope
 Time
 Cost
 Communication
 Risk
 * Knowledge areas as defined by the PMBOK
(PMI – Project Management Book of Knowledge)
Scope – defines what work is needed to complete project
objectives.
• MUST be highly developed
• Design Group (Remediation and Engineering Consultants)
must develop a very detailed Remediation Action Plan and
Construction Plans.
Time – Processes required to ensure timely completion of
the project.
 As a MINIMUM the PM should prepare:
- Activity List
- Dependencies
- Mandatory
- External
 Constraints
 Assumptions
Costs – processes required to ensure that the project is
completed within the approved budget.
 Resource Planning – determine the resources needed and
the quantities of each.
 Cost Estimating – develop an estimate of the cost of the
resources.
 Cost Budgeting - allocating the overall cost estimate.
 Cost Control – controlling changes to the project budget.
Communication – processes required to ensure timely
and appropriate generation, collection and
dissemination of project information.
 Planning – determine the information and
communications needed for ALL of your stakeholders.
 Information Distribution – making the needed
information available to project stakeholders in a timely
manner.
Risk – processes concerned with identifying, analyzing,
and responding to project risks.
 Identification – which risks are likely to affect the project.
 Quantification – evaluate the risks and risk interactions to
assess the range of possible project outcomes.
 Response Development – defining the steps for
opportunities and responses to threats.
 Response Control – responding to changes in risks over the
course of the project.
Phase I
Free Product Remediation
Phase II
Liner/Cap/Stormwater System
Acknowledgements
 Ardaman & Associates
 Stantec
 Batson Cook
 Ripa

More Related Content

Similar to TSSR

2017 Updated CV - Essam Harby
2017 Updated  CV - Essam Harby2017 Updated  CV - Essam Harby
2017 Updated CV - Essam HarbyEssam Harby
 
PROJECT MGT. PRESENTATION
PROJECT MGT. PRESENTATIONPROJECT MGT. PRESENTATION
PROJECT MGT. PRESENTATIONmaheshvkat1972
 
BMH - Detail Resume - August 2016
BMH - Detail Resume - August  2016BMH - Detail Resume - August  2016
BMH - Detail Resume - August 2016Brian Hannigan
 
DHines Planner Scheduler Materials 3-1-17
DHines Planner Scheduler Materials 3-1-17 DHines Planner Scheduler Materials 3-1-17
DHines Planner Scheduler Materials 3-1-17 Deborah Hines
 
Environmental Advances in Mining
Environmental Advances in Mining Environmental Advances in Mining
Environmental Advances in Mining Punita Mehta
 
Scheme for the construction of water channels
Scheme for the construction of water channelsScheme for the construction of water channels
Scheme for the construction of water channelsmirzaqadeer
 
Brian Nicholls resume 2016-08-11
Brian Nicholls resume   2016-08-11Brian Nicholls resume   2016-08-11
Brian Nicholls resume 2016-08-11Brian Nicholls
 
Resume - Suzanne Pearce
Resume - Suzanne PearceResume - Suzanne Pearce
Resume - Suzanne PearceSuzanne Pearce
 
Resume_Sannikov Detailed
Resume_Sannikov DetailedResume_Sannikov Detailed
Resume_Sannikov DetailedAndrei Sannikov
 
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...Nicholas Phelan
 
Senior Planning Engineer -Mohidee Sheik Asan
Senior Planning Engineer -Mohidee Sheik AsanSenior Planning Engineer -Mohidee Sheik Asan
Senior Planning Engineer -Mohidee Sheik AsanMohideen Sheik Asan
 
engineer_Mohamed_Gamal Projects' control_CV-016
engineer_Mohamed_Gamal Projects' control_CV-016engineer_Mohamed_Gamal Projects' control_CV-016
engineer_Mohamed_Gamal Projects' control_CV-016Mohamed Gamal
 
Project PlanGroup 2The Data Center Project PlanProj.docx
Project PlanGroup 2The Data Center Project PlanProj.docxProject PlanGroup 2The Data Center Project PlanProj.docx
Project PlanGroup 2The Data Center Project PlanProj.docxbriancrawford30935
 
Planning and cost analysis of the commercial building
Planning and cost analysis of the commercial buildingPlanning and cost analysis of the commercial building
Planning and cost analysis of the commercial buildingila vamsi krishna
 
Resume R_McCray FEB 2016
Resume R_McCray FEB 2016Resume R_McCray FEB 2016
Resume R_McCray FEB 2016Robert McCray
 
The Rebirth of Cleveland on the Lake Project
The Rebirth of Cleveland on the Lake ProjectThe Rebirth of Cleveland on the Lake Project
The Rebirth of Cleveland on the Lake ProjectTan Dao
 

Similar to TSSR (20)

2017 Updated CV - Essam Harby
2017 Updated  CV - Essam Harby2017 Updated  CV - Essam Harby
2017 Updated CV - Essam Harby
 
PROJECT MGT. PRESENTATION
PROJECT MGT. PRESENTATIONPROJECT MGT. PRESENTATION
PROJECT MGT. PRESENTATION
 
BMH - Detail Resume - August 2016
BMH - Detail Resume - August  2016BMH - Detail Resume - August  2016
BMH - Detail Resume - August 2016
 
DHines Planner Scheduler Materials 3-1-17
DHines Planner Scheduler Materials 3-1-17 DHines Planner Scheduler Materials 3-1-17
DHines Planner Scheduler Materials 3-1-17
 
Antonio MartinezArano B. Ch. E, MBA, PMP, Resume
Antonio MartinezArano B. Ch. E, MBA, PMP, ResumeAntonio MartinezArano B. Ch. E, MBA, PMP, Resume
Antonio MartinezArano B. Ch. E, MBA, PMP, Resume
 
Environmental Advances in Mining
Environmental Advances in Mining Environmental Advances in Mining
Environmental Advances in Mining
 
Scheme for the construction of water channels
Scheme for the construction of water channelsScheme for the construction of water channels
Scheme for the construction of water channels
 
Brian Nicholls resume 2016-08-11
Brian Nicholls resume   2016-08-11Brian Nicholls resume   2016-08-11
Brian Nicholls resume 2016-08-11
 
Resume - Suzanne Pearce
Resume - Suzanne PearceResume - Suzanne Pearce
Resume - Suzanne Pearce
 
Resume_Sannikov Detailed
Resume_Sannikov DetailedResume_Sannikov Detailed
Resume_Sannikov Detailed
 
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...
 
CV
CVCV
CV
 
Senior Planning Engineer -Mohidee Sheik Asan
Senior Planning Engineer -Mohidee Sheik AsanSenior Planning Engineer -Mohidee Sheik Asan
Senior Planning Engineer -Mohidee Sheik Asan
 
engineer_Mohamed_Gamal Projects' control_CV-016
engineer_Mohamed_Gamal Projects' control_CV-016engineer_Mohamed_Gamal Projects' control_CV-016
engineer_Mohamed_Gamal Projects' control_CV-016
 
Project PlanGroup 2The Data Center Project PlanProj.docx
Project PlanGroup 2The Data Center Project PlanProj.docxProject PlanGroup 2The Data Center Project PlanProj.docx
Project PlanGroup 2The Data Center Project PlanProj.docx
 
Roshanak Jalili CV
Roshanak Jalili CVRoshanak Jalili CV
Roshanak Jalili CV
 
Planning and cost analysis of the commercial building
Planning and cost analysis of the commercial buildingPlanning and cost analysis of the commercial building
Planning and cost analysis of the commercial building
 
Resume R_McCray FEB 2016
Resume R_McCray FEB 2016Resume R_McCray FEB 2016
Resume R_McCray FEB 2016
 
Gerry_Garciano_resume
Gerry_Garciano_resumeGerry_Garciano_resume
Gerry_Garciano_resume
 
The Rebirth of Cleveland on the Lake Project
The Rebirth of Cleveland on the Lake ProjectThe Rebirth of Cleveland on the Lake Project
The Rebirth of Cleveland on the Lake Project
 

TSSR

  • 1. Tampa Scrap Site Remediation (TSSR) A Project Management Outlook
  • 2.
  • 3. Tampa Scrap Processors Site Data  Previous Uses: Submerged Lands Prior to 1976; Created from dredge spoils 1976-79; Scrap Metal Recycling Mid- 1980’s to 2000.  Size: 16 acres.  BSRA: Executed 5/3/2003  Contaminants: Petroleum, Organic Solvents, PCB’s, PAH’s, and Metals.  Future Uses: Cargo Yard for Container Storage.  Controls: Deed Restrictions, Impervious Cap  Design Cost: $801,202  Construction Costs: $2,469,775  Total Costs (2005-2012): $3,370,977  VCTC – Total est.@$232,000
  • 4.  Project Management Knowledge Areas *  Scope  Time  Cost  Communication  Risk  * Knowledge areas as defined by the PMBOK (PMI – Project Management Book of Knowledge)
  • 5. Scope – defines what work is needed to complete project objectives. • MUST be highly developed • Design Group (Remediation and Engineering Consultants) must develop a very detailed Remediation Action Plan and Construction Plans.
  • 6. Time – Processes required to ensure timely completion of the project.  As a MINIMUM the PM should prepare: - Activity List - Dependencies - Mandatory - External  Constraints  Assumptions
  • 7. Costs – processes required to ensure that the project is completed within the approved budget.  Resource Planning – determine the resources needed and the quantities of each.  Cost Estimating – develop an estimate of the cost of the resources.  Cost Budgeting - allocating the overall cost estimate.  Cost Control – controlling changes to the project budget.
  • 8. Communication – processes required to ensure timely and appropriate generation, collection and dissemination of project information.  Planning – determine the information and communications needed for ALL of your stakeholders.  Information Distribution – making the needed information available to project stakeholders in a timely manner.
  • 9. Risk – processes concerned with identifying, analyzing, and responding to project risks.  Identification – which risks are likely to affect the project.  Quantification – evaluate the risks and risk interactions to assess the range of possible project outcomes.  Response Development – defining the steps for opportunities and responses to threats.  Response Control – responding to changes in risks over the course of the project.
  • 10. Phase I Free Product Remediation
  • 11.
  • 12.
  • 13.
  • 14.
  • 16.
  • 17.
  • 18.
  • 19.
  • 20.
  • 21.
  • 22.
  • 23.
  • 24.
  • 25. Acknowledgements  Ardaman & Associates  Stantec  Batson Cook  Ripa