SlideShare a Scribd company logo
1 of 17
Sedimentation
BY
R M BHADARAKA
Sedimentation
• It is physical process
• In this process heavier organic and inorganic particles settle down at
bottom of the sedimentation tank.
• For achieve the removal of suspended settleble particles of desired size
the wastewater is retained in sedimentation tank for a fixed time which
is called detention period.
• The upper clear water is collected from the tank.
• The bottom of the tank formation of sludge because of settled
particles.
• The sludge is drawn out from the bottom through the pipe called
sludge pipe.
Type of sedimentation
• Plain Sedimentation
• Sediment with coagulation
The settlement of the particle largely depends upon their specific gravity and
their type.
Stoke’s Law
𝑣 =
𝑔
18
(𝑠 − 1)𝑑2
𝜗
Where v = settling velocity mm/sec
d = Diameter of particle, mm
μ = Dynamic viscosity of wastewater centistoke
ν =
𝜇
𝜌
= 𝑘𝑖𝑛𝑒𝑚𝑎𝑡𝑖𝑐 𝑣𝑖𝑠𝑐𝑜𝑠𝑖𝑡𝑦 𝑜𝑓 𝑤𝑎𝑠𝑡𝑒𝑤𝑎𝑡𝑒𝑟, 𝑐𝑒𝑛𝑡𝑖𝑠𝑡𝑜𝑘𝑒
g = acceleration due to gravity 9810 mm/𝑠𝑒𝑐2
If taking g = 981 cm/𝑠𝑒𝑐2
and 𝑣= 1 centistoke at 20 C the Factor
𝑔
18𝑣
= 545
At 20 C V = 545 (s - 1) 𝒅 𝟐
At Other temp V =418 (s - 1) 𝒅 𝟐 𝟑𝒕+𝟕𝟎
𝟏𝟎𝟎
Newton’s Law
V = 𝟑. 𝟑𝟑𝒈𝒅(𝒔 − 𝟏)
Where v = settling velocity mm/sec
d = Diameter of particle, mm
g = acceleration due to gravity 9810 mm/𝑠𝑒𝑐2
Hazen’s Equation
V =418 (s-1)
𝟑𝒕+𝟕𝟎
𝟏𝟎𝟎
Where v = settling velocity mm/sec
d = Diameter of particle, mm
t = temperature
 Stoke’s law is valid for particles < 0.2mm and Newton’s equation is valid for
particles > 1mm.
 The grit particles of wastewater are having size between 0.1 to 1 mm.
Hazen’s Equation
V =60.6 (s-1)d
𝟑𝒕+𝟕𝟎
𝟏𝟎𝟎
Where v = settling velocity mm/sec
d = Diameter of particle, mm
t = temperature
 This equation is applicable for discrete spherical grit particle.
Type of settling tanks
 Based on nature of working
 Fill and Empty type
 Continuous flow type
 Based on location in treatment plant
 Preliminary settling tank
 Primary Settling tank
 Secondary Settling tank
 Based on shape of the tank in plant
 Rectangular settling tank
 Circular tanks
Fill and Empty type
This type of tank first of all wastewater is filled and allowed to
remains in still condition for about one hour.
The supernatant is drawn out and settled sludge is cleared.
The cleaning takes another 4 to 6 hours
There is wastage of time and labour
Generally not provided in wastewater treatment plant.
Continuous flow type
This type of tanks wastewater is continuously supplied at one point
called inlet and same after treatment leaves continuously from the
other point called outlet.
The wastewater entering the tank is called influent and leaving the
tank is called effluent.
Surface Overflow Rate
It is expressed in
𝑚3
𝑚2 /𝑑𝑎𝑦.
Sr No Type of sedimentation SOR Depth
Average flow Peak Flow
1 Primary settling only 25-30 50-60 3 to 3.5
2 Primary settling followed by
secondary treatment
35-50 80-125 3 to 3.5
3 Primary settling with activated
sludge returns
25 -35 50-60 3.5 to 4.5
4 Secondary settling with trickling
filter
10-25 40-50 3 to 3.5
5 Secondary settling with activated
sludge
15-35 40-50 3.5 to 4.5
6 Secondary settling with extended
aeration
8-15 35 3.5 to 4.5
Detention Period
It is theoretical time for which wastewater remains inside the tank.
It is calculated by dividing the volume of tank with the discharge.
It is normally kept as 1 to 1.5 hours for wastewater treatment.
The detention time in PST is not increase because of the
development of septic condition.
Velocity of flow
Velocity of flow in case of rectangular primary sedimentation tanks
can be taken between 15 to 30 cm/min.
Weir loading rate
Weir loading rates have some effect on removal efficiency of settling
tanks.
PST are generally designed for loading less than 370
𝑚3
𝑚
/𝑑
Dimension for PST
Clarifier Classification Range Typical
Rectangular
Length, m 10 to 100 25 to 60
Length to width ratio 1 to 7.5 4
Length to depth ratio 4.0 to 25.0 7 to 18
Width 3 – 24 6 to 10
Side water depth, m 2.5 to 3.0 3.5
Circular
Diameter, m 3 to 60 10 – 40
Side water depth, m 3 to 6 4
Example
Design a primarily settling tank of rectangular shape for a town having
population of 40000 with water supply of 135 l/c/d
 Assume 80% of water supply to the town is converted in to wastewater
waste water formed daily = 40000 * 135 * 0.8 litre
= 40 * 135 * 0.8 m3
= 4320 m3/d
Assume detention period of 2 hours.
capacity of tank = flow for 2 hour = 4320 * 2 / 24
= 360 m3
Again let us assume SOR of 30 m3/m2 day
surface area = water flow / SOR
= 4320 / 30
= 144 m2
Effective depth = volume / Surface area = 360/144 = 2.5 m
Example
Design a primarily settling tank of rectangular shape for a town having
population of 40000 with water supply of 135 l/c/d
 Take L/B = 4
L = 4B
L * B = 144
4B * B = 144
B = 6
L = 4B = 4 * 6 = 24 m
Provide 4 m additional for inlet and outlet arrangment
L = 24 + 4 = 28 m
Effective depth = 2.5 m
Provide 1 m for sludge accumulation and 0.5 m for free board
Total depth = 2.5 + 1 + 0.5 = 4.0 m
Hence dimension of tank will be 6 * 28 * 4 m.

More Related Content

What's hot

What's hot (20)

Waster water treatment
Waster water treatmentWaster water treatment
Waster water treatment
 
ULTRA FILTRATION & NANO FILTRATION WITH APPLICATIONS
ULTRA FILTRATION & NANO FILTRATION WITH APPLICATIONSULTRA FILTRATION & NANO FILTRATION WITH APPLICATIONS
ULTRA FILTRATION & NANO FILTRATION WITH APPLICATIONS
 
3. grit chamber
3. grit chamber3. grit chamber
3. grit chamber
 
cross flow filtration
cross flow filtrationcross flow filtration
cross flow filtration
 
L 11 screen chamber
L 11 screen chamberL 11 screen chamber
L 11 screen chamber
 
Nanofiltration
Nanofiltration Nanofiltration
Nanofiltration
 
Waste water treatment processes
Waste water treatment processesWaste water treatment processes
Waste water treatment processes
 
Activated Sludge Process
Activated Sludge ProcessActivated Sludge Process
Activated Sludge Process
 
Sludge thickening and stabilization processes
Sludge thickening and stabilization processes  Sludge thickening and stabilization processes
Sludge thickening and stabilization processes
 
water treatment slides
water treatment slideswater treatment slides
water treatment slides
 
Sedimentation
SedimentationSedimentation
Sedimentation
 
Reverse osmosis
Reverse osmosisReverse osmosis
Reverse osmosis
 
Wastewater treatment
Wastewater treatmentWastewater treatment
Wastewater treatment
 
Filtration
FiltrationFiltration
Filtration
 
Flocculation & Sedimentation
Flocculation & SedimentationFlocculation & Sedimentation
Flocculation & Sedimentation
 
Primary sedimentation
Primary sedimentationPrimary sedimentation
Primary sedimentation
 
L 18 trickling filter
L 18 trickling filterL 18 trickling filter
L 18 trickling filter
 
L 4 wastewater flow rates
L 4 wastewater flow ratesL 4 wastewater flow rates
L 4 wastewater flow rates
 
L 24 filtration
L 24 filtrationL 24 filtration
L 24 filtration
 
Waste water treatment
Waste water treatmentWaste water treatment
Waste water treatment
 

Similar to Sedimentation

Sedimentation tank.pptx
Sedimentation tank.pptxSedimentation tank.pptx
Sedimentation tank.pptxvibja
 
UNIT -II Treatment of water- aeration and sedimentation.ppt
UNIT -II  Treatment of water- aeration and sedimentation.pptUNIT -II  Treatment of water- aeration and sedimentation.ppt
UNIT -II Treatment of water- aeration and sedimentation.pptmadhukarjadhav10
 
Coagulation and flocculation
 Coagulation and flocculation Coagulation and flocculation
Coagulation and flocculationHarshada Vispute
 
Chapter_3.pptx on waste water treatment course
Chapter_3.pptx on waste water treatment courseChapter_3.pptx on waste water treatment course
Chapter_3.pptx on waste water treatment courseManamnoBeza1
 
Physical Unit Operation- Screening, Grit Removal, Equalization
Physical Unit Operation-Screening, Grit Removal,EqualizationPhysical Unit Operation-Screening, Grit Removal,Equalization
Physical Unit Operation- Screening, Grit Removal, EqualizationYash Patel
 
Design of Waste Water Treatment Plant for treating the Effluent generated fro...
Design of Waste Water Treatment Plant for treating the Effluent generated fro...Design of Waste Water Treatment Plant for treating the Effluent generated fro...
Design of Waste Water Treatment Plant for treating the Effluent generated fro...Rita EL Khoury
 
Design criteria for Primary Clarifier.pptx
Design criteria for Primary Clarifier.pptxDesign criteria for Primary Clarifier.pptx
Design criteria for Primary Clarifier.pptxfitamadahlia2021
 
Waste water treatment plant
Waste water treatment plantWaste water treatment plant
Waste water treatment plantAldrin Thambi R
 
14 stokes law and grit separators
14 stokes law and grit separators14 stokes law and grit separators
14 stokes law and grit separatorsAkepati S. Reddy
 
Wastewater engineering info
Wastewater engineering infoWastewater engineering info
Wastewater engineering infoTadviDevarshi
 
Circular clarifiers
Circular clarifiersCircular clarifiers
Circular clarifiersmurtazag46
 
Design of reverse osmosis process plant
Design of reverse osmosis process plantDesign of reverse osmosis process plant
Design of reverse osmosis process plantsandeep atukuri
 

Similar to Sedimentation (20)

Sedimentation tank.pptx
Sedimentation tank.pptxSedimentation tank.pptx
Sedimentation tank.pptx
 
UNIT -II Treatment of water- aeration and sedimentation.ppt
UNIT -II  Treatment of water- aeration and sedimentation.pptUNIT -II  Treatment of water- aeration and sedimentation.ppt
UNIT -II Treatment of water- aeration and sedimentation.ppt
 
Unit 4
Unit  4Unit  4
Unit 4
 
Coagulation and flocculation
 Coagulation and flocculation Coagulation and flocculation
Coagulation and flocculation
 
Chapter_3.pptx on waste water treatment course
Chapter_3.pptx on waste water treatment courseChapter_3.pptx on waste water treatment course
Chapter_3.pptx on waste water treatment course
 
Physical Unit Operation- Screening, Grit Removal, Equalization
Physical Unit Operation-Screening, Grit Removal,EqualizationPhysical Unit Operation-Screening, Grit Removal,Equalization
Physical Unit Operation- Screening, Grit Removal, Equalization
 
Wwwe
WwweWwwe
Wwwe
 
Design of Waste Water Treatment Plant for treating the Effluent generated fro...
Design of Waste Water Treatment Plant for treating the Effluent generated fro...Design of Waste Water Treatment Plant for treating the Effluent generated fro...
Design of Waste Water Treatment Plant for treating the Effluent generated fro...
 
Plain sedimentation
Plain sedimentationPlain sedimentation
Plain sedimentation
 
Design criteria for Primary Clarifier.pptx
Design criteria for Primary Clarifier.pptxDesign criteria for Primary Clarifier.pptx
Design criteria for Primary Clarifier.pptx
 
sedimentation
sedimentationsedimentation
sedimentation
 
Waste water treatment plant
Waste water treatment plantWaste water treatment plant
Waste water treatment plant
 
Low Cost Sanitation Systems
Low Cost Sanitation SystemsLow Cost Sanitation Systems
Low Cost Sanitation Systems
 
Water treatment
Water treatmentWater treatment
Water treatment
 
Lec_7.pptx
Lec_7.pptxLec_7.pptx
Lec_7.pptx
 
Physical Unit Operations
Physical Unit OperationsPhysical Unit Operations
Physical Unit Operations
 
14 stokes law and grit separators
14 stokes law and grit separators14 stokes law and grit separators
14 stokes law and grit separators
 
Wastewater engineering info
Wastewater engineering infoWastewater engineering info
Wastewater engineering info
 
Circular clarifiers
Circular clarifiersCircular clarifiers
Circular clarifiers
 
Design of reverse osmosis process plant
Design of reverse osmosis process plantDesign of reverse osmosis process plant
Design of reverse osmosis process plant
 

Recently uploaded

CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 

Recently uploaded (20)

CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 

Sedimentation

  • 2. Sedimentation • It is physical process • In this process heavier organic and inorganic particles settle down at bottom of the sedimentation tank. • For achieve the removal of suspended settleble particles of desired size the wastewater is retained in sedimentation tank for a fixed time which is called detention period. • The upper clear water is collected from the tank. • The bottom of the tank formation of sludge because of settled particles. • The sludge is drawn out from the bottom through the pipe called sludge pipe.
  • 3. Type of sedimentation • Plain Sedimentation • Sediment with coagulation The settlement of the particle largely depends upon their specific gravity and their type.
  • 4. Stoke’s Law 𝑣 = 𝑔 18 (𝑠 − 1)𝑑2 𝜗 Where v = settling velocity mm/sec d = Diameter of particle, mm μ = Dynamic viscosity of wastewater centistoke ν = 𝜇 𝜌 = 𝑘𝑖𝑛𝑒𝑚𝑎𝑡𝑖𝑐 𝑣𝑖𝑠𝑐𝑜𝑠𝑖𝑡𝑦 𝑜𝑓 𝑤𝑎𝑠𝑡𝑒𝑤𝑎𝑡𝑒𝑟, 𝑐𝑒𝑛𝑡𝑖𝑠𝑡𝑜𝑘𝑒 g = acceleration due to gravity 9810 mm/𝑠𝑒𝑐2 If taking g = 981 cm/𝑠𝑒𝑐2 and 𝑣= 1 centistoke at 20 C the Factor 𝑔 18𝑣 = 545 At 20 C V = 545 (s - 1) 𝒅 𝟐 At Other temp V =418 (s - 1) 𝒅 𝟐 𝟑𝒕+𝟕𝟎 𝟏𝟎𝟎
  • 5. Newton’s Law V = 𝟑. 𝟑𝟑𝒈𝒅(𝒔 − 𝟏) Where v = settling velocity mm/sec d = Diameter of particle, mm g = acceleration due to gravity 9810 mm/𝑠𝑒𝑐2
  • 6. Hazen’s Equation V =418 (s-1) 𝟑𝒕+𝟕𝟎 𝟏𝟎𝟎 Where v = settling velocity mm/sec d = Diameter of particle, mm t = temperature  Stoke’s law is valid for particles < 0.2mm and Newton’s equation is valid for particles > 1mm.  The grit particles of wastewater are having size between 0.1 to 1 mm.
  • 7. Hazen’s Equation V =60.6 (s-1)d 𝟑𝒕+𝟕𝟎 𝟏𝟎𝟎 Where v = settling velocity mm/sec d = Diameter of particle, mm t = temperature  This equation is applicable for discrete spherical grit particle.
  • 8. Type of settling tanks  Based on nature of working  Fill and Empty type  Continuous flow type  Based on location in treatment plant  Preliminary settling tank  Primary Settling tank  Secondary Settling tank  Based on shape of the tank in plant  Rectangular settling tank  Circular tanks
  • 9. Fill and Empty type This type of tank first of all wastewater is filled and allowed to remains in still condition for about one hour. The supernatant is drawn out and settled sludge is cleared. The cleaning takes another 4 to 6 hours There is wastage of time and labour Generally not provided in wastewater treatment plant.
  • 10. Continuous flow type This type of tanks wastewater is continuously supplied at one point called inlet and same after treatment leaves continuously from the other point called outlet. The wastewater entering the tank is called influent and leaving the tank is called effluent.
  • 11. Surface Overflow Rate It is expressed in 𝑚3 𝑚2 /𝑑𝑎𝑦. Sr No Type of sedimentation SOR Depth Average flow Peak Flow 1 Primary settling only 25-30 50-60 3 to 3.5 2 Primary settling followed by secondary treatment 35-50 80-125 3 to 3.5 3 Primary settling with activated sludge returns 25 -35 50-60 3.5 to 4.5 4 Secondary settling with trickling filter 10-25 40-50 3 to 3.5 5 Secondary settling with activated sludge 15-35 40-50 3.5 to 4.5 6 Secondary settling with extended aeration 8-15 35 3.5 to 4.5
  • 12. Detention Period It is theoretical time for which wastewater remains inside the tank. It is calculated by dividing the volume of tank with the discharge. It is normally kept as 1 to 1.5 hours for wastewater treatment. The detention time in PST is not increase because of the development of septic condition.
  • 13. Velocity of flow Velocity of flow in case of rectangular primary sedimentation tanks can be taken between 15 to 30 cm/min.
  • 14. Weir loading rate Weir loading rates have some effect on removal efficiency of settling tanks. PST are generally designed for loading less than 370 𝑚3 𝑚 /𝑑
  • 15. Dimension for PST Clarifier Classification Range Typical Rectangular Length, m 10 to 100 25 to 60 Length to width ratio 1 to 7.5 4 Length to depth ratio 4.0 to 25.0 7 to 18 Width 3 – 24 6 to 10 Side water depth, m 2.5 to 3.0 3.5 Circular Diameter, m 3 to 60 10 – 40 Side water depth, m 3 to 6 4
  • 16. Example Design a primarily settling tank of rectangular shape for a town having population of 40000 with water supply of 135 l/c/d  Assume 80% of water supply to the town is converted in to wastewater waste water formed daily = 40000 * 135 * 0.8 litre = 40 * 135 * 0.8 m3 = 4320 m3/d Assume detention period of 2 hours. capacity of tank = flow for 2 hour = 4320 * 2 / 24 = 360 m3 Again let us assume SOR of 30 m3/m2 day surface area = water flow / SOR = 4320 / 30 = 144 m2 Effective depth = volume / Surface area = 360/144 = 2.5 m
  • 17. Example Design a primarily settling tank of rectangular shape for a town having population of 40000 with water supply of 135 l/c/d  Take L/B = 4 L = 4B L * B = 144 4B * B = 144 B = 6 L = 4B = 4 * 6 = 24 m Provide 4 m additional for inlet and outlet arrangment L = 24 + 4 = 28 m Effective depth = 2.5 m Provide 1 m for sludge accumulation and 0.5 m for free board Total depth = 2.5 + 1 + 0.5 = 4.0 m Hence dimension of tank will be 6 * 28 * 4 m.