SlideShare a Scribd company logo
1 of 13
Wind Farm
Operators Forum
Workshop:
Cable pooling
Alberto Orejana
Paweł Wołczański
Grzegorz Skarżyński
10 March 2022
Table of content
1
Hybridization potential of an existing wind farm in Poland through cable pooling:
1. Spanish case & legislation.
2. Hybrid installation effect based on Polish example.
3. How to implement the cable pooling
1. Spanish case & legislation (1)
2
1. Spanish case & legislation (2)
3
1. Spanish case & legislation (3)
4
2. Hybrid installation effect (1)
5
Following installations were taken into consideration once calculating hybrid effect of wind + PV:
Wind farm 1:
a) Capacity: ~40 MW
b) Low productivity: ~2050 nh
c) Hourly data: 2018 – 2021 (4 years)
Wind farm 2:
a) Capacity: ~40 MW
b) High productivity : ~3500 nh
c) Hourly data: 2018 – 2021 (4 years)
PV:
a) Capacity: multiple of 5 MW between 0 to 60 MW.
b) Medium productivity: 1225 nh (north Poland)
c) Hourly data: based on data published by PSE for total PV generation in Poland.
1) Source: EU PVGIS Photovoltaic Geographical Information System
2) Icons have been designed using resources from Flaticon.com
PV potential
installation:
Wind farms:
2. Hybrid installation effect (2)
6
As within cable pooling, total generation of hybrid installation (both wind + PV) cannot exceed the
already granted interconnection capacity, then number of hours with active curtailment were calculated.
Results are presented below with the breakdown into individual PV capacity for given year.
For low wind productivity:
1) up to 50% of added PV capacity, the curtailment appears only up to ~90 hours (in other words - up to
2 hours per week),
2) once similar PV installation installed, then curtailment of generation takes places proportionally up
to ~320 hours (in other words – in 1 hour a day).
For high wind productivity:
1) situation changes and hours with curtailment appears already with few additional MW installed
growing linearly.
2. Hybrid installation effect (3)
7
Number of hours when total generation exceeds granted interconnection capacity does not reflect the real
effect of curtailment. Therefore, lost (curtailed) production from added PV installation (with wind generation
kept unchanged) is presented on graphs below.
Productivity in different years varied significantly (between ~P15 and P90).
For low wind productivity:
1) hybrid installations with even 75% of added PV capacity have very limited impact (up to 2%) of PV
generation. With higher capacity of new PV (50% more than installed as possible in Spain) the PV
curtailed generation would be even up to ~17%.
For high wind productivity:
2) curtailed PV generation is low only with small added PV installation (up to 25% with losses of 2%),
whereas the curtailment increases exponentially.
3. How to implement the cable pooling
within the current regulatory framework
8
1. Cable pooling means increasing potential of electricity generation, without increasing the
interconnection capacity (more energy exported to the grid through the existing interconnection
point).
2. Cable pooling does not mean any increase of the interconnection capacity for individual installation,
therefore should not be treated in the same way as the application for the grid connection capacity
for the new projects – this is not the same procedure.
3. It is possible to implement the cable pooling by amending actual interconnection agreement at the
individual investor request – new installation has to be harmonized with the existing one (integrated
communication system, emergency shutdown, new equipment to be install etc.).
4. Similarities to the self generation facilities (companies planning to build its own generating
facilities), prosumers (only notification needed for installation energy generating facilities within the
max capacity granted by interconnection agreement).
5. RES installations operating under the „green certificates” scheme could implement cable pooling
without losing this support (electricity generation is measured on the turbines), while the auction
projects will not be allowed to participate (energy measured at interconnection point).
3. How to implement the cable pooling –
suggested regulatory changes
9
1. In order to streamline the process of acceptance cable pooling by DSOs as well as to avoid potential
disputes between investors and DSOs, it would be advisable to introduce following provisions:
a) DSO obligation to positively accept cable pooling up to the max capacity (similar to the Spanish
regulations), unless it could significantly negatively impact the grid (justified evidence has to
be provided when application was rejected).
b) under paying deposit fee, such acceptance has to be granted for max 4 years to give time for
permitting the additional installation; within this 4 years period investor can sign amended
connection agreement; deposit is returnable after construction of the new installation or
resignation from construction.
2. It could be also recommended to widely allow the proportional measurement at the interconnection
point (currently it is applicable only to hybrid projects) to include the „auction projects” to use in the
cable pooling model (energy generated by the new installation will not be counted for the auction
scheme).
3. How to implement the cable pooling –
final remarks
10
1. Taking into consideration findings from our calculations, application of the cable pooling model for all
wind farms operated under the green certificate scheme with accepted lost of 5% of the new PV
generation, may allow to build up to 87% new PV capacity (6 400 MW in wind – 5 600 MW in PV),
which may increase the electricity generation by max 42% (15 440 GWh in wind – 6 517 GWh in new
PV). In reality it will be lower numbers, as such new PV installation could not be developed for all
wind park locations.
2. If we add also „auction projects” this additional PV capacity may increase further, however less than
for the „old” wind portfolio (the higher wind productivity, the lower new PV capacity).
3. It has to be considered to extend the cable pooling concept by including granting grid capacity for
new installations connected in the new interconnection points under the acceptance of the
obligatory curtailment not compensated by DSO (the max curtailment ratio will be calculated taking
into consideration operating installations located in the neighboring area); it will allow to built new
installations by new investors in the new locations, not necessarily connected to the existing
interconnection points.
11
TundraAdvisory Sp. zo.o.
ul.DoStudzienki 63, lok. 115
80-227 Gdańsk
NIP527-255-24-72
+48 58 580 17 89
tundra@tundraadvisory.com
We make your projects
grow

More Related Content

Similar to Tundra_FOFW2022.pptx

NanoGrids for Home Application in a Power Cloud Framework
NanoGrids for Home Application in a Power Cloud Framework NanoGrids for Home Application in a Power Cloud Framework
NanoGrids for Home Application in a Power Cloud Framework Alessandro Burgio
 
GRID FLEXIBILITY: an antidote to relieve pain in a changing energy system
GRID FLEXIBILITY: an antidote to relieve pain in a changing energy systemGRID FLEXIBILITY: an antidote to relieve pain in a changing energy system
GRID FLEXIBILITY: an antidote to relieve pain in a changing energy systemIRIS Smart Cities
 
POWER ELECTRONIC IN POWER SYSTEM KELAS.pptx
POWER ELECTRONIC IN POWER SYSTEM KELAS.pptxPOWER ELECTRONIC IN POWER SYSTEM KELAS.pptx
POWER ELECTRONIC IN POWER SYSTEM KELAS.pptxmasterunedo
 
Grid Integration: Future for Electricity Transmission
Grid Integration: Future for Electricity TransmissionGrid Integration: Future for Electricity Transmission
Grid Integration: Future for Electricity TransmissionTorben Haagh
 
Energetic payback time of PV: In Germany and Tunisia
Energetic payback time of PV: In Germany and TunisiaEnergetic payback time of PV: In Germany and Tunisia
Energetic payback time of PV: In Germany and TunisiaInsulin Angel
 
Net Metering-NEPRA & DISCOS Rules/Regulations and Procedure
Net Metering-NEPRA & DISCOS Rules/Regulations and ProcedureNet Metering-NEPRA & DISCOS Rules/Regulations and Procedure
Net Metering-NEPRA & DISCOS Rules/Regulations and ProcedureSALMAN SAEED
 
Boo wind power in egypt
Boo wind power in egyptBoo wind power in egypt
Boo wind power in egyptRCREEE
 
Scenario analysis of data centres in the Irish energy system
Scenario analysis of data centres in the Irish energy systemScenario analysis of data centres in the Irish energy system
Scenario analysis of data centres in the Irish energy systemIEA-ETSAP
 
Microgrids and their destructuring eff ects on the electrical industry
Microgrids and their destructuring effects on the electrical industryMicrogrids and their destructuring effects on the electrical industry
Microgrids and their destructuring eff ects on the electrical industryUniversité de Liège (ULg)
 
Micro Generation And Selling Your Power
Micro Generation And Selling Your PowerMicro Generation And Selling Your Power
Micro Generation And Selling Your PowerStephen Rowley
 
Bizando - Minieolico 60KW - November 2013
Bizando - Minieolico 60KW - November 2013Bizando - Minieolico 60KW - November 2013
Bizando - Minieolico 60KW - November 2013Edoardo Verduci
 
Ontario solar pres
Ontario solar presOntario solar pres
Ontario solar presmarzan
 
Modeling, Control, and Performance Evaluation of Grid-Tied Hybrid PV/Wind Pow...
Modeling, Control, and Performance Evaluation of Grid-Tied Hybrid PV/Wind Pow...Modeling, Control, and Performance Evaluation of Grid-Tied Hybrid PV/Wind Pow...
Modeling, Control, and Performance Evaluation of Grid-Tied Hybrid PV/Wind Pow...Asoka Technologies
 

Similar to Tundra_FOFW2022.pptx (20)

Levellised generic tariff
Levellised generic tariffLevellised generic tariff
Levellised generic tariff
 
Energy, Grids and Microgrids
Energy, Grids and MicrogridsEnergy, Grids and Microgrids
Energy, Grids and Microgrids
 
Why Solar rg
Why Solar rgWhy Solar rg
Why Solar rg
 
NanoGrids for Home Application in a Power Cloud Framework
NanoGrids for Home Application in a Power Cloud Framework NanoGrids for Home Application in a Power Cloud Framework
NanoGrids for Home Application in a Power Cloud Framework
 
GRID FLEXIBILITY: an antidote to relieve pain in a changing energy system
GRID FLEXIBILITY: an antidote to relieve pain in a changing energy systemGRID FLEXIBILITY: an antidote to relieve pain in a changing energy system
GRID FLEXIBILITY: an antidote to relieve pain in a changing energy system
 
Draft Feed-In Tariffs
Draft Feed-In TariffsDraft Feed-In Tariffs
Draft Feed-In Tariffs
 
POWER ELECTRONIC IN POWER SYSTEM KELAS.pptx
POWER ELECTRONIC IN POWER SYSTEM KELAS.pptxPOWER ELECTRONIC IN POWER SYSTEM KELAS.pptx
POWER ELECTRONIC IN POWER SYSTEM KELAS.pptx
 
Grid Integration: Future for Electricity Transmission
Grid Integration: Future for Electricity TransmissionGrid Integration: Future for Electricity Transmission
Grid Integration: Future for Electricity Transmission
 
Energetic payback time of PV: In Germany and Tunisia
Energetic payback time of PV: In Germany and TunisiaEnergetic payback time of PV: In Germany and Tunisia
Energetic payback time of PV: In Germany and Tunisia
 
Net Metering-NEPRA & DISCOS Rules/Regulations and Procedure
Net Metering-NEPRA & DISCOS Rules/Regulations and ProcedureNet Metering-NEPRA & DISCOS Rules/Regulations and Procedure
Net Metering-NEPRA & DISCOS Rules/Regulations and Procedure
 
Egeruoh chigoziri
Egeruoh chigoziriEgeruoh chigoziri
Egeruoh chigoziri
 
Boo wind power in egypt
Boo wind power in egyptBoo wind power in egypt
Boo wind power in egypt
 
Scenario analysis of data centres in the Irish energy system
Scenario analysis of data centres in the Irish energy systemScenario analysis of data centres in the Irish energy system
Scenario analysis of data centres in the Irish energy system
 
Microgrids and their destructuring eff ects on the electrical industry
Microgrids and their destructuring effects on the electrical industryMicrogrids and their destructuring effects on the electrical industry
Microgrids and their destructuring eff ects on the electrical industry
 
Micro Generation And Selling Your Power
Micro Generation And Selling Your PowerMicro Generation And Selling Your Power
Micro Generation And Selling Your Power
 
Bizando - Minieolico 60KW - November 2013
Bizando - Minieolico 60KW - November 2013Bizando - Minieolico 60KW - November 2013
Bizando - Minieolico 60KW - November 2013
 
Ontario solar pres
Ontario solar presOntario solar pres
Ontario solar pres
 
Az Zour EPP08
Az Zour EPP08Az Zour EPP08
Az Zour EPP08
 
RWF PR90
RWF PR90RWF PR90
RWF PR90
 
Modeling, Control, and Performance Evaluation of Grid-Tied Hybrid PV/Wind Pow...
Modeling, Control, and Performance Evaluation of Grid-Tied Hybrid PV/Wind Pow...Modeling, Control, and Performance Evaluation of Grid-Tied Hybrid PV/Wind Pow...
Modeling, Control, and Performance Evaluation of Grid-Tied Hybrid PV/Wind Pow...
 

Recently uploaded

The Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism PresentationThe Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism PresentationNathan Young
 
Event 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxEvent 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxaryanv1753
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Krijn Poppe
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...NETWAYS
 
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
SBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation TrackSBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation TrackSebastiano Panichella
 
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Salam Al-Karadaghi
 
James Joyce, Dubliners and Ulysses.ppt !
James Joyce, Dubliners and Ulysses.ppt !James Joyce, Dubliners and Ulysses.ppt !
James Joyce, Dubliners and Ulysses.ppt !risocarla2016
 
miladyskindiseases-200705210221 2.!!pptx
miladyskindiseases-200705210221 2.!!pptxmiladyskindiseases-200705210221 2.!!pptx
miladyskindiseases-200705210221 2.!!pptxCarrieButtitta
 
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...NETWAYS
 
PHYSICS PROJECT BY MSC - NANOTECHNOLOGY
PHYSICS PROJECT BY MSC  - NANOTECHNOLOGYPHYSICS PROJECT BY MSC  - NANOTECHNOLOGY
PHYSICS PROJECT BY MSC - NANOTECHNOLOGYpruthirajnayak525
 
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...NETWAYS
 
Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170Escort Service
 
Mathan flower ppt.pptx slide orchids ✨🌸
Mathan flower ppt.pptx slide orchids ✨🌸Mathan flower ppt.pptx slide orchids ✨🌸
Mathan flower ppt.pptx slide orchids ✨🌸mathanramanathan2005
 
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...NETWAYS
 
The 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringThe 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringSebastiano Panichella
 
call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@vikas rana
 
Anne Frank A Beacon of Hope amidst darkness ppt.pptx
Anne Frank A Beacon of Hope amidst darkness ppt.pptxAnne Frank A Beacon of Hope amidst darkness ppt.pptx
Anne Frank A Beacon of Hope amidst darkness ppt.pptxnoorehahmad
 
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxGenesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxFamilyWorshipCenterD
 
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...NETWAYS
 

Recently uploaded (20)

The Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism PresentationThe Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism Presentation
 
Event 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxEvent 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptx
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
 
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
 
SBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation TrackSBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation Track
 
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
 
James Joyce, Dubliners and Ulysses.ppt !
James Joyce, Dubliners and Ulysses.ppt !James Joyce, Dubliners and Ulysses.ppt !
James Joyce, Dubliners and Ulysses.ppt !
 
miladyskindiseases-200705210221 2.!!pptx
miladyskindiseases-200705210221 2.!!pptxmiladyskindiseases-200705210221 2.!!pptx
miladyskindiseases-200705210221 2.!!pptx
 
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
 
PHYSICS PROJECT BY MSC - NANOTECHNOLOGY
PHYSICS PROJECT BY MSC  - NANOTECHNOLOGYPHYSICS PROJECT BY MSC  - NANOTECHNOLOGY
PHYSICS PROJECT BY MSC - NANOTECHNOLOGY
 
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
 
Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170
 
Mathan flower ppt.pptx slide orchids ✨🌸
Mathan flower ppt.pptx slide orchids ✨🌸Mathan flower ppt.pptx slide orchids ✨🌸
Mathan flower ppt.pptx slide orchids ✨🌸
 
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
 
The 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringThe 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software Engineering
 
call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@
 
Anne Frank A Beacon of Hope amidst darkness ppt.pptx
Anne Frank A Beacon of Hope amidst darkness ppt.pptxAnne Frank A Beacon of Hope amidst darkness ppt.pptx
Anne Frank A Beacon of Hope amidst darkness ppt.pptx
 
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxGenesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
 
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
 

Tundra_FOFW2022.pptx

  • 1. Wind Farm Operators Forum Workshop: Cable pooling Alberto Orejana Paweł Wołczański Grzegorz Skarżyński 10 March 2022
  • 2. Table of content 1 Hybridization potential of an existing wind farm in Poland through cable pooling: 1. Spanish case & legislation. 2. Hybrid installation effect based on Polish example. 3. How to implement the cable pooling
  • 3. 1. Spanish case & legislation (1) 2
  • 4. 1. Spanish case & legislation (2) 3
  • 5. 1. Spanish case & legislation (3) 4
  • 6. 2. Hybrid installation effect (1) 5 Following installations were taken into consideration once calculating hybrid effect of wind + PV: Wind farm 1: a) Capacity: ~40 MW b) Low productivity: ~2050 nh c) Hourly data: 2018 – 2021 (4 years) Wind farm 2: a) Capacity: ~40 MW b) High productivity : ~3500 nh c) Hourly data: 2018 – 2021 (4 years) PV: a) Capacity: multiple of 5 MW between 0 to 60 MW. b) Medium productivity: 1225 nh (north Poland) c) Hourly data: based on data published by PSE for total PV generation in Poland. 1) Source: EU PVGIS Photovoltaic Geographical Information System 2) Icons have been designed using resources from Flaticon.com PV potential installation: Wind farms:
  • 7. 2. Hybrid installation effect (2) 6 As within cable pooling, total generation of hybrid installation (both wind + PV) cannot exceed the already granted interconnection capacity, then number of hours with active curtailment were calculated. Results are presented below with the breakdown into individual PV capacity for given year. For low wind productivity: 1) up to 50% of added PV capacity, the curtailment appears only up to ~90 hours (in other words - up to 2 hours per week), 2) once similar PV installation installed, then curtailment of generation takes places proportionally up to ~320 hours (in other words – in 1 hour a day). For high wind productivity: 1) situation changes and hours with curtailment appears already with few additional MW installed growing linearly.
  • 8. 2. Hybrid installation effect (3) 7 Number of hours when total generation exceeds granted interconnection capacity does not reflect the real effect of curtailment. Therefore, lost (curtailed) production from added PV installation (with wind generation kept unchanged) is presented on graphs below. Productivity in different years varied significantly (between ~P15 and P90). For low wind productivity: 1) hybrid installations with even 75% of added PV capacity have very limited impact (up to 2%) of PV generation. With higher capacity of new PV (50% more than installed as possible in Spain) the PV curtailed generation would be even up to ~17%. For high wind productivity: 2) curtailed PV generation is low only with small added PV installation (up to 25% with losses of 2%), whereas the curtailment increases exponentially.
  • 9. 3. How to implement the cable pooling within the current regulatory framework 8 1. Cable pooling means increasing potential of electricity generation, without increasing the interconnection capacity (more energy exported to the grid through the existing interconnection point). 2. Cable pooling does not mean any increase of the interconnection capacity for individual installation, therefore should not be treated in the same way as the application for the grid connection capacity for the new projects – this is not the same procedure. 3. It is possible to implement the cable pooling by amending actual interconnection agreement at the individual investor request – new installation has to be harmonized with the existing one (integrated communication system, emergency shutdown, new equipment to be install etc.). 4. Similarities to the self generation facilities (companies planning to build its own generating facilities), prosumers (only notification needed for installation energy generating facilities within the max capacity granted by interconnection agreement). 5. RES installations operating under the „green certificates” scheme could implement cable pooling without losing this support (electricity generation is measured on the turbines), while the auction projects will not be allowed to participate (energy measured at interconnection point).
  • 10. 3. How to implement the cable pooling – suggested regulatory changes 9 1. In order to streamline the process of acceptance cable pooling by DSOs as well as to avoid potential disputes between investors and DSOs, it would be advisable to introduce following provisions: a) DSO obligation to positively accept cable pooling up to the max capacity (similar to the Spanish regulations), unless it could significantly negatively impact the grid (justified evidence has to be provided when application was rejected). b) under paying deposit fee, such acceptance has to be granted for max 4 years to give time for permitting the additional installation; within this 4 years period investor can sign amended connection agreement; deposit is returnable after construction of the new installation or resignation from construction. 2. It could be also recommended to widely allow the proportional measurement at the interconnection point (currently it is applicable only to hybrid projects) to include the „auction projects” to use in the cable pooling model (energy generated by the new installation will not be counted for the auction scheme).
  • 11. 3. How to implement the cable pooling – final remarks 10 1. Taking into consideration findings from our calculations, application of the cable pooling model for all wind farms operated under the green certificate scheme with accepted lost of 5% of the new PV generation, may allow to build up to 87% new PV capacity (6 400 MW in wind – 5 600 MW in PV), which may increase the electricity generation by max 42% (15 440 GWh in wind – 6 517 GWh in new PV). In reality it will be lower numbers, as such new PV installation could not be developed for all wind park locations. 2. If we add also „auction projects” this additional PV capacity may increase further, however less than for the „old” wind portfolio (the higher wind productivity, the lower new PV capacity). 3. It has to be considered to extend the cable pooling concept by including granting grid capacity for new installations connected in the new interconnection points under the acceptance of the obligatory curtailment not compensated by DSO (the max curtailment ratio will be calculated taking into consideration operating installations located in the neighboring area); it will allow to built new installations by new investors in the new locations, not necessarily connected to the existing interconnection points.
  • 12. 11
  • 13. TundraAdvisory Sp. zo.o. ul.DoStudzienki 63, lok. 115 80-227 Gdańsk NIP527-255-24-72 +48 58 580 17 89 tundra@tundraadvisory.com We make your projects grow