The document discusses the materials and labor required to apply a 20mm thick external plaster over an area of 10 square meters. It calculates that 1.5 bags of cement and 0.15 cubic meters of sand will be needed, along with 2 masons, 1 male coolie, 1 female coolie, and 0.5 bhisties. The total material cost is estimated to be Rs. 590 and total labor cost as Rs. 2030, bringing the initial cost to Rs. 2620. Adding 1.5% for water charges and 20% contractor's profit, the final cost is calculated to be Rs. 3200, or Rs. 320 per square meter.
4. Labor required for both coats
• The following labor is required for mixing, applying mortar on the wall,
smoothening, finishing…etc.
AY: 2020-21 Professional Practices and Valuation (2170610) 3
Labor Number Job
Mason 2 Smoothening, finishing
Male coolie 1 Mixing mortar
Female coolie 1 Carrying mortar
Bhistie 0.5 Surface preparation and
applying mortar on wall
5. Calculation Table
Particulars Quantity/Number Rate
Rs.
Per Amount
Rs.
Materials:
Cement
Sand
Sundries
Labor:
Mason
Male coolie
Female coolie
Bhistie
Scaffolding
Sundries
1.5
0.15
2
1
1
0.5
300
800
600
300
300
300
Bag
Meter cube
Day
Day
Day
Day
Lump sum
450
120
20
---------------
590
1200
300
300
150
60
20
----------------
2030
AY: 2020-21 Professional Practices and Valuation (2170610) 4
6. s
Final Calculations:
Material cost 590
Labor cost 2030
-----------
2620
Add 1.5% water charges and 20% contractor’s profit
Final Amnount = 1.015 × 1.2 × 2620 = 3191.16 ≈ 3200
Rate per meter square =
3200
10
= 320