SlideShare a Scribd company logo
1 of 10
b= 4.5m
a= 6m
How to determine Design moment for
a slab using StripMethod
Determine the design moment for rectangular slab shown below using strip method
a= 6m b = 4.5m t = 150mm
Use C-25 concrete & S-300 steel , Take variable load ,
Floor finish, 30mm cement screed and 20 mm thick marble
b= 4.5m
a= 6m
2
Q=3kN/m
Step 1 Divide the slab in to rectangular strips
a= 6m
b= 4.5m
b/4
b/4
b- b/2
/ 2
w
/ 2
w
/ 2
w
/ 2
w
w w
w
b/4
Step 2 Determine the design load , Wd
+
Design load 1.3Gk 1.6Qk

Gk
Where = Permanent load
Qk =Variable load
Self weight of slab = . *h
R C


h
= Unit weight
= thickness
3
25 / * 0.15
kN m m

2
3.75 /
kN m

Self weight of Cement screed= *h
c

3
23 / * 0.03
kN m m

2
0.69 /
kN m

Self weight of Marble= *h
M

3
27 / * 0.02
kN m m

2
0.54 /
kN m

Total permanent load = Gk Slab + Gk Cement screed + Gk Marble
2
(3.75 0.69 0.54) /
kN m
  
2
4.98 /
kN m

+
Design load(Wd) 1.3Gk 1.6Qk

2 2
+
1.3*4.98 / 1.6*3 /
kN m kN m

2
11.27 /
kN m

2
Design load(Wd) 11.27 / * 1 =11.27 /
kN m m kN m

a= 6m
b= 4.5m
b/4
b/4
b- b/2
/ 2
w
/ 2
w
/ 2
w
/ 2
w
w w
w 1
1
Step 3 Determine the design moment in each strip
Strip 1-1
11.27 /
w kN m
 11.27 /
w kN m

2
*
4 8 32
= *
x
b b wb
w
m 
2
32
11.27*4.5
7.13 . /
x kN m m
m 

b/4
a= 6m
b= 4.5m
b/4
b/4
b- b/2
/ 2
w
/ 2
w
/ 2
w
/ 2
w
w w
w
2 2
Step 3 Determine the design moment in each strip
Strip 2-2
/ 2 5.64 /
w kN m

2
2 *
2 4 8 64
= *
x
b b wb
w
m 
2
2 64
11.27*4.5
3.56 . /
x
kN m m
m 

b/4
/ 2 5.64 /
w kN m

a= 6m
b= 4.5m
b/4
b/4
b- b/2
/ 2
w
/ 2
w
/ 2
w
/ 2
w
w w
w
3
3
Step 3 Determine the design moment in each strip
Strip 3-3
11.27 /
w kN m

3
2
8
=
y
wb
m
2
3 8
11.27*4.5
28.53 . /
y
kN m m
m 

4.5 m
a= 6m
b= 4.5m
b/4
b/4
b- b/2
/ 2
w / 2
w
/ 2
w / 2
w
w w
w
4
4
Step 3 Determine the design moment in each strip
Strip 4-4
/ 2 5.64 /
w kN m

2
4 *
2 4 8 64
= *
y
b b wb
w
m 
2
4 64
11.27*4.5
3.56 . /
y
kN m m
m 

b/4
/ 2 5.64 /
w kN m

Strip method for slab

More Related Content

What's hot

CE6704_uw.pdf
CE6704_uw.pdfCE6704_uw.pdf
CE6704_uw.pdfhitusp
 
Design of RCC Column footing
Design of RCC Column footingDesign of RCC Column footing
Design of RCC Column footingArun Kurali
 
Worked example extract_flat_slabs
Worked example extract_flat_slabsWorked example extract_flat_slabs
Worked example extract_flat_slabsLuan Truong Van
 
Onewayslab
OnewayslabOnewayslab
OnewayslabP Ramana
 
Lec 3 design problem of flat plate slab
Lec 3 design problem of flat plate slabLec 3 design problem of flat plate slab
Lec 3 design problem of flat plate slabMD.MAHBUB UL ALAM
 
Analysis and design of flat slabs using various codes
Analysis and design of flat slabs using various codesAnalysis and design of flat slabs using various codes
Analysis and design of flat slabs using various codeseSAT Publishing House
 
Guide to the design and construction of reinforced concrete flat slabs (1)
Guide to the design and construction of reinforced concrete flat slabs (1)Guide to the design and construction of reinforced concrete flat slabs (1)
Guide to the design and construction of reinforced concrete flat slabs (1)abbdou001
 
Design of combined footing ppt
Design of combined footing pptDesign of combined footing ppt
Design of combined footing pptBharti Shinde
 
Chapter 5 beams design
Chapter 5  beams designChapter 5  beams design
Chapter 5 beams designSimon Foo
 
Footing design
Footing designFooting design
Footing designShubham .
 
Design and analysis of RC structures with flat slab
Design and analysis of RC structures with flat slabDesign and analysis of RC structures with flat slab
Design and analysis of RC structures with flat slabDeepak Patil
 
base plate in bending and anchor bolts in tension
base plate in bending and anchor bolts in tensionbase plate in bending and anchor bolts in tension
base plate in bending and anchor bolts in tensionabdul latief
 
07-Strength of Bolted Connections (Steel Structural Design & Prof. Shehab Mou...
07-Strength of Bolted Connections (Steel Structural Design & Prof. Shehab Mou...07-Strength of Bolted Connections (Steel Structural Design & Prof. Shehab Mou...
07-Strength of Bolted Connections (Steel Structural Design & Prof. Shehab Mou...Hossam Shafiq II
 

What's hot (20)

Two-Way Floor Slab
Two-Way Floor SlabTwo-Way Floor Slab
Two-Way Floor Slab
 
CE6704_uw.pdf
CE6704_uw.pdfCE6704_uw.pdf
CE6704_uw.pdf
 
Design of RCC Column footing
Design of RCC Column footingDesign of RCC Column footing
Design of RCC Column footing
 
Worked example extract_flat_slabs
Worked example extract_flat_slabsWorked example extract_flat_slabs
Worked example extract_flat_slabs
 
Onewayslab
OnewayslabOnewayslab
Onewayslab
 
Rc detailing-to-ec2
Rc detailing-to-ec2Rc detailing-to-ec2
Rc detailing-to-ec2
 
Lec 3 design problem of flat plate slab
Lec 3 design problem of flat plate slabLec 3 design problem of flat plate slab
Lec 3 design problem of flat plate slab
 
Analysis and design of flat slabs using various codes
Analysis and design of flat slabs using various codesAnalysis and design of flat slabs using various codes
Analysis and design of flat slabs using various codes
 
Slab Design-(BNBC & ACI)
Slab Design-(BNBC & ACI)Slab Design-(BNBC & ACI)
Slab Design-(BNBC & ACI)
 
Flat slab
Flat slabFlat slab
Flat slab
 
Slender columnn and two-way slabs
Slender columnn and two-way slabsSlender columnn and two-way slabs
Slender columnn and two-way slabs
 
Guide to the design and construction of reinforced concrete flat slabs (1)
Guide to the design and construction of reinforced concrete flat slabs (1)Guide to the design and construction of reinforced concrete flat slabs (1)
Guide to the design and construction of reinforced concrete flat slabs (1)
 
Design of combined footing ppt
Design of combined footing pptDesign of combined footing ppt
Design of combined footing ppt
 
Chapter 5 beams design
Chapter 5  beams designChapter 5  beams design
Chapter 5 beams design
 
Footing design
Footing designFooting design
Footing design
 
Design and analysis of RC structures with flat slab
Design and analysis of RC structures with flat slabDesign and analysis of RC structures with flat slab
Design and analysis of RC structures with flat slab
 
Swimming pool new roof
Swimming pool new roofSwimming pool new roof
Swimming pool new roof
 
DESIGN OF FLAT SLABS
DESIGN OF FLAT SLABSDESIGN OF FLAT SLABS
DESIGN OF FLAT SLABS
 
base plate in bending and anchor bolts in tension
base plate in bending and anchor bolts in tensionbase plate in bending and anchor bolts in tension
base plate in bending and anchor bolts in tension
 
07-Strength of Bolted Connections (Steel Structural Design & Prof. Shehab Mou...
07-Strength of Bolted Connections (Steel Structural Design & Prof. Shehab Mou...07-Strength of Bolted Connections (Steel Structural Design & Prof. Shehab Mou...
07-Strength of Bolted Connections (Steel Structural Design & Prof. Shehab Mou...
 

Similar to Strip method for slab

individual part
individual part individual part
individual part KC Wong
 
Building Structures Report (Group and Individual)
Building Structures Report (Group and Individual)Building Structures Report (Group and Individual)
Building Structures Report (Group and Individual)Patch Yuen
 
Building structures final
Building structures finalBuilding structures final
Building structures finalJamie Lee
 
Cantilever Retaining Wall
Cantilever Retaining Wall Cantilever Retaining Wall
Cantilever Retaining Wall Harsh Shani
 
INDUSTRIAL BUILDING GANTRY GIRDER
INDUSTRIAL BUILDING  GANTRY GIRDERINDUSTRIAL BUILDING  GANTRY GIRDER
INDUSTRIAL BUILDING GANTRY GIRDERHarsh Shani
 
Ref F2F Week 4 - Solution_unlocked.pdf
Ref F2F Week 4 - Solution_unlocked.pdfRef F2F Week 4 - Solution_unlocked.pdf
Ref F2F Week 4 - Solution_unlocked.pdfRobin Arthur Flores
 
Design of flyover presented by Vikas GLNAIT, Mathura
Design of flyover presented by Vikas GLNAIT, MathuraDesign of flyover presented by Vikas GLNAIT, Mathura
Design of flyover presented by Vikas GLNAIT, Mathuravikaschaudhary15011991
 
Building Structures Report
Building Structures ReportBuilding Structures Report
Building Structures ReportJoe Onn Lim
 
Building Structure Project 2 (Taylor's lakeside campus)
Building Structure Project 2 (Taylor's lakeside campus)Building Structure Project 2 (Taylor's lakeside campus)
Building Structure Project 2 (Taylor's lakeside campus)Ong Seng Peng Jeff
 
Building Structure : Structural analysis of a bungalow
Building Structure : Structural analysis of a bungalowBuilding Structure : Structural analysis of a bungalow
Building Structure : Structural analysis of a bungalowchiwunloi
 
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problemdhineshkumar002
 
Mechanics of materials
Mechanics of materialsMechanics of materials
Mechanics of materialsAnand Gadge
 
Design of composite steel and concrete structures.pptx
Design of composite steel and concrete structures.pptxDesign of composite steel and concrete structures.pptx
Design of composite steel and concrete structures.pptxSharpEyu
 
Final structure report
Final structure reportFinal structure report
Final structure reportTay Jit Ying
 
B.structure report
B.structure reportB.structure report
B.structure reportjiuaN59
 
Structure report final
Structure report finalStructure report final
Structure report finaltristan yu
 

Similar to Strip method for slab (20)

individual part
individual part individual part
individual part
 
Building Structures Report (Group and Individual)
Building Structures Report (Group and Individual)Building Structures Report (Group and Individual)
Building Structures Report (Group and Individual)
 
Building structures final
Building structures finalBuilding structures final
Building structures final
 
Structures
StructuresStructures
Structures
 
Cantilever Retaining Wall
Cantilever Retaining Wall Cantilever Retaining Wall
Cantilever Retaining Wall
 
INDUSTRIAL BUILDING GANTRY GIRDER
INDUSTRIAL BUILDING  GANTRY GIRDERINDUSTRIAL BUILDING  GANTRY GIRDER
INDUSTRIAL BUILDING GANTRY GIRDER
 
Ref F2F Week 4 - Solution_unlocked.pdf
Ref F2F Week 4 - Solution_unlocked.pdfRef F2F Week 4 - Solution_unlocked.pdf
Ref F2F Week 4 - Solution_unlocked.pdf
 
Design of flyover presented by Vikas GLNAIT, Mathura
Design of flyover presented by Vikas GLNAIT, MathuraDesign of flyover presented by Vikas GLNAIT, Mathura
Design of flyover presented by Vikas GLNAIT, Mathura
 
Building Structures Report
Building Structures ReportBuilding Structures Report
Building Structures Report
 
Building Structure Project 2 (Taylor's lakeside campus)
Building Structure Project 2 (Taylor's lakeside campus)Building Structure Project 2 (Taylor's lakeside campus)
Building Structure Project 2 (Taylor's lakeside campus)
 
1622828460.pdf
1622828460.pdf1622828460.pdf
1622828460.pdf
 
Building Structure : Structural analysis of a bungalow
Building Structure : Structural analysis of a bungalowBuilding Structure : Structural analysis of a bungalow
Building Structure : Structural analysis of a bungalow
 
Qp
QpQp
Qp
 
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problem
 
Mechanics of materials
Mechanics of materialsMechanics of materials
Mechanics of materials
 
Design of composite steel and concrete structures.pptx
Design of composite steel and concrete structures.pptxDesign of composite steel and concrete structures.pptx
Design of composite steel and concrete structures.pptx
 
Final structure report
Final structure reportFinal structure report
Final structure report
 
B.structure report
B.structure reportB.structure report
B.structure report
 
TDS Lec 2a-Dams.pdf
TDS Lec 2a-Dams.pdfTDS Lec 2a-Dams.pdf
TDS Lec 2a-Dams.pdf
 
Structure report final
Structure report finalStructure report final
Structure report final
 

Recently uploaded

An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIkoyaldeepu123
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 

Recently uploaded (20)

An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AI
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 

Strip method for slab

  • 1. b= 4.5m a= 6m How to determine Design moment for a slab using StripMethod
  • 2. Determine the design moment for rectangular slab shown below using strip method a= 6m b = 4.5m t = 150mm Use C-25 concrete & S-300 steel , Take variable load , Floor finish, 30mm cement screed and 20 mm thick marble b= 4.5m a= 6m 2 Q=3kN/m
  • 3. Step 1 Divide the slab in to rectangular strips a= 6m b= 4.5m b/4 b/4 b- b/2 / 2 w / 2 w / 2 w / 2 w w w w b/4
  • 4. Step 2 Determine the design load , Wd + Design load 1.3Gk 1.6Qk  Gk Where = Permanent load Qk =Variable load Self weight of slab = . *h R C   h = Unit weight = thickness 3 25 / * 0.15 kN m m  2 3.75 / kN m  Self weight of Cement screed= *h c  3 23 / * 0.03 kN m m  2 0.69 / kN m  Self weight of Marble= *h M  3 27 / * 0.02 kN m m  2 0.54 / kN m 
  • 5. Total permanent load = Gk Slab + Gk Cement screed + Gk Marble 2 (3.75 0.69 0.54) / kN m    2 4.98 / kN m  + Design load(Wd) 1.3Gk 1.6Qk  2 2 + 1.3*4.98 / 1.6*3 / kN m kN m  2 11.27 / kN m  2 Design load(Wd) 11.27 / * 1 =11.27 / kN m m kN m 
  • 6. a= 6m b= 4.5m b/4 b/4 b- b/2 / 2 w / 2 w / 2 w / 2 w w w w 1 1 Step 3 Determine the design moment in each strip Strip 1-1 11.27 / w kN m  11.27 / w kN m  2 * 4 8 32 = * x b b wb w m  2 32 11.27*4.5 7.13 . / x kN m m m   b/4
  • 7. a= 6m b= 4.5m b/4 b/4 b- b/2 / 2 w / 2 w / 2 w / 2 w w w w 2 2 Step 3 Determine the design moment in each strip Strip 2-2 / 2 5.64 / w kN m  2 2 * 2 4 8 64 = * x b b wb w m  2 2 64 11.27*4.5 3.56 . / x kN m m m   b/4 / 2 5.64 / w kN m 
  • 8. a= 6m b= 4.5m b/4 b/4 b- b/2 / 2 w / 2 w / 2 w / 2 w w w w 3 3 Step 3 Determine the design moment in each strip Strip 3-3 11.27 / w kN m  3 2 8 = y wb m 2 3 8 11.27*4.5 28.53 . / y kN m m m   4.5 m
  • 9. a= 6m b= 4.5m b/4 b/4 b- b/2 / 2 w / 2 w / 2 w / 2 w w w w 4 4 Step 3 Determine the design moment in each strip Strip 4-4 / 2 5.64 / w kN m  2 4 * 2 4 8 64 = * y b b wb w m  2 4 64 11.27*4.5 3.56 . / y kN m m m   b/4 / 2 5.64 / w kN m 