Marine Corps Installations East
                NCMBC Federal Construction and
                    Infrastructure Summit
                                   11 OCT 2012
Tony Sholar, P.E.
Facilities Manager
(GF) Installations & Environment
Marine Corps Installations East                    1
MCIEAST Installations


                  MCIEAST
                 Camp Lejeune


                MCAF Quantico
                MCAS Cherry Point
                MCAS New River
                MCB Camp Lejeune
                MCAS Beaufort
                MCLB Albany
                MCSF Blount Island
                                     2
Construction Opportunities

• Traditional construction projects
    Military Construction
       New construction and development
           ‣ These projects are multi-million dollar contracts
           ‣ Each project approved by Congress
    Renovation, maintenance and repair
       Projects can range from a few thousand to several million
        dollars
           ‣ Includes complete building renovations and utility plant and
             infrastructure repairs
           ‣ Funding managed within the Marine Corps
           ‣ History of consistent funding levels to sustain facilities
• Architectural and Engineering Services
    Design drawings (DB and DBB)
    Wide range of consulting services
                                                                            3
Camp Lejeune, New River and
                      Cherry Point MILCON History

                                              Record
                                               Year
Millions of Dollars




                                Fiscal Year

                                                       4
MCIEAST North Carolina
              Military Construction Funding

• FY11 ~ Largest MILCON year
for Camp Lejeune, New River, and
Cherry Point.

• FY12 shows a significant decline
in MILCON.

•FY13 pre-award packages are
nearing completion .
                                                                       *       **
•FY14 have been authorized for
design and continue through the
budget approval process.
                                     * Waiting for PRESBUD to be passed.
                                     ** Submitted in budget process to Congress.


       Future projections return to “normal” funding levels.
                                                                                    5
P1382B BER                P1378/1330 Wounded


MCB Camp Lejeune
                                                            Ramps & Bridge            Warrior H&C and HQ
                                                            Cost: $10.5M              Cost: $15.3M
                                                            CCD: Feb 13               CCD: Jun 12
                                                                                                                                         P1331/1857 Hospital Addition & Renovation
              P1268 SOI East Facilities                                                                                                  Cost: $57.5M, CCD: Jan 15
              Cost: $22.2M, CCD: Apr 13

     P1268B Camp Geiger Access
     Cost: $8.3M CCD: Jan 14
                                               P1382 New Base Entry Point
                                               & Road, PH 1
                                               Cost: $43.9M, CCD: Jan 13

                                                                                                                                         P1304 MP Working Dog Kennel
                                                                      FY 09 BEQ (11 Buildings)                                           Cost: $4.7M, CCD: Jun 12
         P1269 TECOM (SOI) Devil Dog                                  Cost: $199.5M, CCD: Sep 12
         Cost: $9.5M, CCD: Dec 12
                                                                                                                                    Wallace Creek Ph II
                                                                                                                                    Cost: $142.1M, CCD: Oct 12

                                                                                                                                         P1160 Physical Fitness Center
                                   P1269B Verona Loop &                                                                                  Cost: $19.6M, CCD: Jun 12
                                   K-Range Water Line
                                   Cost: $6.2M                                                                                              P1310 Pre-Trial Detainee Fac.
                                   CCD: May 13                                                                                              Cost: $13.6M, CCD: Jun 12
                                                                                                   P1311 Infotech/Telecom Complex
                                                                                                   Cost: $30.9M, CCD: Jul 14

                                          P1136 Mod. K Range Ph. II
                                          Cost: $12.4M, CCD: Apr 12
    P032 Infantry Plt
    Battle Course                                                                                                              P1357 ARRA CDC
    Cost: $15.3M                                                                                                               Cost: $7.5M, CCD: Feb 12
    CCD: Mar 13


                                    P1187B Stone Bay                                                                                                             P031 Multi-Purpose
                                    Exchange                                                                                                                     Machine Gun Range
                                    Cost: $1.6M                                                                                                                  Cost: $15.4M
                                    CCD: Dec 12                                                                                                                  CCD: Dec 11

                                                       P1266 Utilities Upgrades CHB
FY07-10 MILCON PROJECTS                                Cost: $16.6M, CCD: Jul 13                                       P1266B Steam Plant Modifications
                                                                                                                       Cost: $1.5M, CCD: Mar 12
          Under Construction

          Funded Awaiting Award



6
MCB Camp Lejeune
                                                           P1319 Camp Johnson BEQ
                                                           Cost: $39.9M
                                                           CCD: Sep 13



                          P004 SOI Motor
                          Trans./Com Maint.
                          Cost: $10.9M                                                                                                     FY-12 P1383
                          CCD: Dec 12                               P1400 Energy Initiative – PV
                                                                    Cost: $7.5M                                                            New Entry Road, PH 2
                                                                    CCD: Dec 12                                                            Cost: $80.3M
              MILCON Program                                                                            P1249/1322/1323 Wallace
                                                                                                        Creek North BEQs & Armory
                                                                   P1240/1034 Anglico/Intel
FY-13                                                                                                   Cost: $78.5M
                                                                   Maint/Ops Complex
                                                                                                        CCD: Dec 13
P-003 Staff NCO Academy Facilities $30M                            Cost: $92.6M
P-1218 SOF MSOB-Company/Team Fac. $53M                             CCD: Mar 14
P-1384 New Base Entry Road, PH 3 $44M
P-1393 SOF SERE Training Facilities $5M                             FY-12 P138
P-1425 Overhead Range Baffle System $3M                             Wallace Creek, BEQ                                               P1264/1265 HP & FC Utility Expansion
                                                                    Cost: $23.9M                                                     Cost: $65.8M, CCD: Oct 13
FY-14                                                                                                                                     P1246 EOD Addition
P-1346 Simulator Center and Range Dev. $50M                           P1267 French Creek
                                                                      Mess Hall                                                           Cost: $5.2M, CCD: Aug 12
P-1349 Special Ops Training Complex $23M                              Cost: $14.8M
P-1353 Landfill, Phase IV $24M                                                                                                             FY-11 P1264B
                                                                      CCD: Feb 13
                                                                                                                                           Elevated Water Storage Tanks
P-1445 Steam Decentralization – Camp Johnson $2.6M                                                                                         Cost: $18.8M
P-1447 Steam Decentralization – Hadnot Point $13.4M                             P1317 French Creek BEQ
                                                                                Cost: $31.6M
P-1448 Steam Decentralization – BEQ Nodes $18.7M                                                                                        FY-11 P1265B
                                                                                CCD: Aug 13                                             French Creek WWTP Upgrades
P-1362 SOF Perf Resiliency Center $11M
                                                                                                                                        Cost: $17.4M
P-1391 SOF Sustainment Training Complex $28.6M
                                                                                              P1256 Mess Hall Addition
                                                                                              Cost: $1.2M
                                                                                                                                                        FY-12 P030
                                                                                              CCD: Nov 12
                                                                                                                                                        Squad Battle Course
                                                                                                                                                        Cost: $14.0M
                              FY-11 PQ419
                              Battalion Aid Station                                                                      FY-12 P1253
                              Expansion                                                                                  2D Combat Eng. Maint/OPS
                              Cost: $1.6M                                                                                Cost: $66.8M


               P1286 Stone Bay BEQ &                  FY-12 P1285
                                                      SOF Armory Expansion             P1251/1254 BEQ
               Connector Rd.
               Cost: $49.1M                           Cost: $6.6M                      Cost: $67.7M                                   FY11-12 MILCON PROJECTS
                                                      CCD” Sept 13                     CCD: Oct 13
               CCD: Sep 13
                                                                                                                                                    Under Construction

                                                                                                                                                    Funded Awaiting Award
 7
MCAS New River

               FY-12 P025
               Replace Delalio Elementary School
               Cost: $20.4M
                                                                                        P652 VMMT-204 Hangar,
                                                                                        Phase III
                                                                                        Cost: $24.9M
                                                                                        CCD: Sep 13
            P714 Physical
            Fitness Center
            Cost: $11.7M
            CCD: Aug 12




                                      FY-12 P705
                                      Maint Hangar & Apron
                                      Cost: $57.6M

        MILCON Program
                                              FY-12 P710 Ordnance
FY-13
                                              Loading Area Addition
P-711 Personnel Admin Center $34.0M
                                              Cost: $8.2M
FY14
P-674 Corrosion Control Hangar $16M
P-676 CH-53K Maint. Train Fac. $14M                                    P311/683/687/688 V-22 Hangars,
P-726 Regional Comm. Station $22M                                      Parallel Taxiway & Apron Expansion
                                                                       Cost: $138.8M
                                                                       CCD: May 14

                                               Under Construction

                                               Funded awaiting award
8
MILCON Program
FY-13
P-163 Marine Air Support Squadron Compound $34M
                                                                               MCAS Cherry Point
P-601 Armory $14M




                                                      Station Infrastructure
                                                      Upgrades
                                                      Cost: $5.2M
                                                      CCD: Nov 12
                     Ordnance & Missile
                     Magazines
                     Cost: $7.2M
                     CCD: Jul 12 / Dec 12
                                                  BEQ
                                                  Cost: $38.0M
                                                  CCD: Jul 13

                                                                                      Facilities & Facilities
                                                                                      Upgrades (F/A-18 E/F)
                                                                                      Cost: $14.8M
                                                                                      CCD: Feb 12 **
                                                                                      (Suspension of Work I/P)




                                                                                      FY-12 P-991
                                                                                      H-1 Y/Z Gearbox Repair
                                                                                      & Test Facility
      Under Construction                                                              (FRC-E)
                                                                                      Cost: $17.1M
     Funded Awaiting Award

9
FY12 “Maintenance and Repair”
          Construction Program
• MCIEAST North Carolina installations
    Ranges from painting to complete building renovation
    $160 million awarded for more than 500 projects
        Projects range from a few thousand to several million dollars
    Camp Lejeune
        $80 million awarded
    New River
        $24 million awarded
    Cherry Point
        $56 million awarded
• FY13 funding will be similar to last year
    Projects typically approved in November
• Funding projections beyond FY13 remain steady



                                                                         10
Energy Opportunities
• Energy has become a significant focus for the Marine Corps
• Energy Independence and Security Act (EISA) signed December
     2007
       30% reduction in energy intensity
              By end of 2015 based on FY03 baseline
       Expanded use of renewable energy
              25% renewable energy by 2025
• Over $150 million for Marine Corps energy projects in FY13
              Designs
              Audits
              Construction
• Contractor selection criteria will incorporate energy efficiency
     experience as an evaluation factor
       LEED Silver is the standard for FY13 with focus on energy points




10/10/2012                    Marine Corps Installations East              11
Take Aways…

•More than $300 million in construction opportunities in
Eastern NC this year.
    Project size varies widely, from a few thousand dollars to tens of
      millions each.
        FY11 was a “record setting” year
        FY12 was the last “larger than normal” year.
        FY13 and beyond returning to “normal” .
• Energy has become a significant focus for the Marine
Corps
•Still more than $2 billion currently under construction
   In various stages of construction
• Record years behind us but still significant work ahead
   Approximately $300 million each year over next few years




                                                                          12

Marine Corps Installations East

  • 1.
    Marine Corps InstallationsEast NCMBC Federal Construction and Infrastructure Summit 11 OCT 2012 Tony Sholar, P.E. Facilities Manager (GF) Installations & Environment Marine Corps Installations East 1
  • 2.
    MCIEAST Installations MCIEAST Camp Lejeune MCAF Quantico MCAS Cherry Point MCAS New River MCB Camp Lejeune MCAS Beaufort MCLB Albany MCSF Blount Island 2
  • 3.
    Construction Opportunities • Traditionalconstruction projects  Military Construction  New construction and development ‣ These projects are multi-million dollar contracts ‣ Each project approved by Congress  Renovation, maintenance and repair  Projects can range from a few thousand to several million dollars ‣ Includes complete building renovations and utility plant and infrastructure repairs ‣ Funding managed within the Marine Corps ‣ History of consistent funding levels to sustain facilities • Architectural and Engineering Services  Design drawings (DB and DBB)  Wide range of consulting services 3
  • 4.
    Camp Lejeune, NewRiver and Cherry Point MILCON History Record Year Millions of Dollars Fiscal Year 4
  • 5.
    MCIEAST North Carolina Military Construction Funding • FY11 ~ Largest MILCON year for Camp Lejeune, New River, and Cherry Point. • FY12 shows a significant decline in MILCON. •FY13 pre-award packages are nearing completion . * ** •FY14 have been authorized for design and continue through the budget approval process. * Waiting for PRESBUD to be passed. ** Submitted in budget process to Congress. Future projections return to “normal” funding levels. 5
  • 6.
    P1382B BER P1378/1330 Wounded MCB Camp Lejeune Ramps & Bridge Warrior H&C and HQ Cost: $10.5M Cost: $15.3M CCD: Feb 13 CCD: Jun 12 P1331/1857 Hospital Addition & Renovation P1268 SOI East Facilities Cost: $57.5M, CCD: Jan 15 Cost: $22.2M, CCD: Apr 13 P1268B Camp Geiger Access Cost: $8.3M CCD: Jan 14 P1382 New Base Entry Point & Road, PH 1 Cost: $43.9M, CCD: Jan 13 P1304 MP Working Dog Kennel FY 09 BEQ (11 Buildings) Cost: $4.7M, CCD: Jun 12 P1269 TECOM (SOI) Devil Dog Cost: $199.5M, CCD: Sep 12 Cost: $9.5M, CCD: Dec 12 Wallace Creek Ph II Cost: $142.1M, CCD: Oct 12 P1160 Physical Fitness Center P1269B Verona Loop & Cost: $19.6M, CCD: Jun 12 K-Range Water Line Cost: $6.2M P1310 Pre-Trial Detainee Fac. CCD: May 13 Cost: $13.6M, CCD: Jun 12 P1311 Infotech/Telecom Complex Cost: $30.9M, CCD: Jul 14 P1136 Mod. K Range Ph. II Cost: $12.4M, CCD: Apr 12 P032 Infantry Plt Battle Course P1357 ARRA CDC Cost: $15.3M Cost: $7.5M, CCD: Feb 12 CCD: Mar 13 P1187B Stone Bay P031 Multi-Purpose Exchange Machine Gun Range Cost: $1.6M Cost: $15.4M CCD: Dec 12 CCD: Dec 11 P1266 Utilities Upgrades CHB FY07-10 MILCON PROJECTS Cost: $16.6M, CCD: Jul 13 P1266B Steam Plant Modifications Cost: $1.5M, CCD: Mar 12 Under Construction Funded Awaiting Award 6
  • 7.
    MCB Camp Lejeune P1319 Camp Johnson BEQ Cost: $39.9M CCD: Sep 13 P004 SOI Motor Trans./Com Maint. Cost: $10.9M FY-12 P1383 CCD: Dec 12 P1400 Energy Initiative – PV Cost: $7.5M New Entry Road, PH 2 CCD: Dec 12 Cost: $80.3M MILCON Program P1249/1322/1323 Wallace Creek North BEQs & Armory P1240/1034 Anglico/Intel FY-13 Cost: $78.5M Maint/Ops Complex CCD: Dec 13 P-003 Staff NCO Academy Facilities $30M Cost: $92.6M P-1218 SOF MSOB-Company/Team Fac. $53M CCD: Mar 14 P-1384 New Base Entry Road, PH 3 $44M P-1393 SOF SERE Training Facilities $5M FY-12 P138 P-1425 Overhead Range Baffle System $3M Wallace Creek, BEQ P1264/1265 HP & FC Utility Expansion Cost: $23.9M Cost: $65.8M, CCD: Oct 13 FY-14 P1246 EOD Addition P-1346 Simulator Center and Range Dev. $50M P1267 French Creek Mess Hall Cost: $5.2M, CCD: Aug 12 P-1349 Special Ops Training Complex $23M Cost: $14.8M P-1353 Landfill, Phase IV $24M FY-11 P1264B CCD: Feb 13 Elevated Water Storage Tanks P-1445 Steam Decentralization – Camp Johnson $2.6M Cost: $18.8M P-1447 Steam Decentralization – Hadnot Point $13.4M P1317 French Creek BEQ Cost: $31.6M P-1448 Steam Decentralization – BEQ Nodes $18.7M FY-11 P1265B CCD: Aug 13 French Creek WWTP Upgrades P-1362 SOF Perf Resiliency Center $11M Cost: $17.4M P-1391 SOF Sustainment Training Complex $28.6M P1256 Mess Hall Addition Cost: $1.2M FY-12 P030 CCD: Nov 12 Squad Battle Course Cost: $14.0M FY-11 PQ419 Battalion Aid Station FY-12 P1253 Expansion 2D Combat Eng. Maint/OPS Cost: $1.6M Cost: $66.8M P1286 Stone Bay BEQ & FY-12 P1285 SOF Armory Expansion P1251/1254 BEQ Connector Rd. Cost: $49.1M Cost: $6.6M Cost: $67.7M FY11-12 MILCON PROJECTS CCD” Sept 13 CCD: Oct 13 CCD: Sep 13 Under Construction Funded Awaiting Award 7
  • 8.
    MCAS New River FY-12 P025 Replace Delalio Elementary School Cost: $20.4M P652 VMMT-204 Hangar, Phase III Cost: $24.9M CCD: Sep 13 P714 Physical Fitness Center Cost: $11.7M CCD: Aug 12 FY-12 P705 Maint Hangar & Apron Cost: $57.6M MILCON Program FY-12 P710 Ordnance FY-13 Loading Area Addition P-711 Personnel Admin Center $34.0M Cost: $8.2M FY14 P-674 Corrosion Control Hangar $16M P-676 CH-53K Maint. Train Fac. $14M P311/683/687/688 V-22 Hangars, P-726 Regional Comm. Station $22M Parallel Taxiway & Apron Expansion Cost: $138.8M CCD: May 14 Under Construction Funded awaiting award 8
  • 9.
    MILCON Program FY-13 P-163 MarineAir Support Squadron Compound $34M MCAS Cherry Point P-601 Armory $14M Station Infrastructure Upgrades Cost: $5.2M CCD: Nov 12 Ordnance & Missile Magazines Cost: $7.2M CCD: Jul 12 / Dec 12 BEQ Cost: $38.0M CCD: Jul 13 Facilities & Facilities Upgrades (F/A-18 E/F) Cost: $14.8M CCD: Feb 12 ** (Suspension of Work I/P) FY-12 P-991 H-1 Y/Z Gearbox Repair & Test Facility Under Construction (FRC-E) Cost: $17.1M Funded Awaiting Award 9
  • 10.
    FY12 “Maintenance andRepair” Construction Program • MCIEAST North Carolina installations  Ranges from painting to complete building renovation  $160 million awarded for more than 500 projects  Projects range from a few thousand to several million dollars  Camp Lejeune  $80 million awarded  New River  $24 million awarded  Cherry Point  $56 million awarded • FY13 funding will be similar to last year  Projects typically approved in November • Funding projections beyond FY13 remain steady 10
  • 11.
    Energy Opportunities • Energyhas become a significant focus for the Marine Corps • Energy Independence and Security Act (EISA) signed December 2007  30% reduction in energy intensity  By end of 2015 based on FY03 baseline  Expanded use of renewable energy  25% renewable energy by 2025 • Over $150 million for Marine Corps energy projects in FY13  Designs  Audits  Construction • Contractor selection criteria will incorporate energy efficiency experience as an evaluation factor  LEED Silver is the standard for FY13 with focus on energy points 10/10/2012 Marine Corps Installations East 11
  • 12.
    Take Aways… •More than$300 million in construction opportunities in Eastern NC this year.  Project size varies widely, from a few thousand dollars to tens of millions each.  FY11 was a “record setting” year  FY12 was the last “larger than normal” year.  FY13 and beyond returning to “normal” . • Energy has become a significant focus for the Marine Corps •Still more than $2 billion currently under construction In various stages of construction • Record years behind us but still significant work ahead Approximately $300 million each year over next few years 12