SlideShare a Scribd company logo
1 of 29
Download to read offline
Conceptual Design Optimism,
Cost and Schedule Growth Effects
                 Presented at the
  2010 NASA Program Management Challenge
         9-10 February 2010, Houston, Texas




Claude Freaner, Bob Bitten, Debra Emmons
                  Used with permission
                           1
Agenda

• Background/Overview

• Database Description

• Resource Growth
  – Mass, Power, Cost & Schedule Trends


• Findings
  – Progression from milestones
  – Comparison of mission types
  – Payload vs. Spacecraft comparisons


• Potential Considerations


                               2
Background

• Results from a recent study* of 10 NASA missions over the past decade
  indicated that the average cost and schedule growth of these missions, over
  and above programmatic reserves, was 76% and 26%, respectively,
  measured from beginning of Phase B
• One potential causative factor postulated was the inherent optimism in initial
  concept designs due to competitive pressures
• Inherent optimism can translate to the underestimation of the technical
  specifications such as mass, power, data rate, and the complexity of a system
• Underestimation of these resources can lead to the underestimation of the
  final cost of the mission since most cost models use some form of system
  resources as a predictor of mission cost
• To compound problems, the desire to launch a system as early as possible, in
  order to obtain science quickly, can lead to a success oriented schedule that
  may be shorter than historical comparisons would indicate
• This combination of underestimated resources providing an optimistic cost
  estimate basis combined with a success oriented schedule can contribute to
  the observed history of cost and schedule growth
      * “An Assessment of the Inherent Optimism in Early Conceptual Designs and its Effect on Cost and
      Schedule Growth”, Freaner C., Bitten R., Bearden D., and Emmons D., May 2008
                                                                 3
Study Approach

• For a set of 20 missions in the study, the mass, power, cost,
  schedule and other parameters were identified at the beginning of
  the Preliminary Design phase (NASA Phase B) of a mission*
• These values were then compared to values presented at the
  Preliminary Design Review (PDR), Critical Design Review (CDR)
  and at the time of launch to understand the growth over time of each
  of these resources
• The resource growth is then compared to industry guidelines to
  understand if these guidelines would have adequately predicted the
  growth for the mission data set studied
• In addition, resource growth of different mission types and
  correlation of cost growth in relation to different parameters is also
  shown

 * All parametric and programmatic data were obtained from NASA CADRe data"




                                                                 4
Agenda

• Background/Overview

• Database Description

• Resource Growth
  – Mass, Power, Cost & Schedule Trends


• Findings
  – Progression from milestones
  – Comparison of mission types
  – Payload vs. Spacecraft comparisons


• Potential Considerations


                               5
Database Description:
       20 Missions Represent a Wide Range of Recent NASA Missions
                                                                                          Key         Launch Acquisition Number of
                                        Planetary?    Program       Science Type        Center(s)      Year     Type     Instruments                  Comments
                                                                                                                                       Advanced land imaging technology
                          EO-1                       NMP         Earth Science            GSFC         2000   Competed       5
                                                                                                                                       demonstrator
                                                                                                                                       Collect samples of solar wind particles at
                          GENESIS           X        Discovery   Planetary Science          JPL        2001   Competed       4
                                                                                                                                       L1 point and return them to Earth
• 5 Directed vs.          GRACE                      ESSP        Earth Science              JPL        2002   Competed       6         Earth Gravity Measurement

  15 Competed             Spitzer
                                                     Physics of
                                                     the Cosmos
                                                                Astrophysics                JPL        2003    Directed      4
                                                                                                                                       IR space telescope, the last of the Great
                                                                                                                                       Observatories
  missions                GALEX                      Explorers   Astrophysics           JPL/CalTech    2003   Competed       1         UV space telescope

                          SWIFT                      Explorers   Astrophysics             GSFC         2004   Competed       4         Gamma Ray burst detector

                          MESSENGER         X        Discovery   Planetary Science         APL         2004   Competed       7         Investigate Mercury
• 7 Planetary missions    MRO               X        MEP         Planetary Science          JPL        2005    Directed      7         Investigate history of water on Mars

  vs. 13 Earth or near-   Deep Impact       X        Discovery   Planetary Science          JPL        2005   Competed       3         Comet impactor

  Earth Orbiters          Cloudsat                   ESSP        Earth Science              JPL        2006   Competed       1         Radar observation of clouds
                                                                                                                                       2 spacecraft looking at solar dynamics -
                          STEREO                     STP         Heliospheric Science   GSFC/APL       2006    Directed      4
                                                                                                                                       Earth leading and trailing orbits
                          CALIPSO                    ESSP        Earth Science             LARC        2006   Competed       3         Aerosols
• 7 Planetary Science     New
                                            X
                                                     New
                                                                 Planetary Science         APL         2006   Competed       7         Investigate Pluto
                          Horizons                   Frontiers
  vs. 5 Astrophysics      DAWN              X        Discovery   Planetary Science          JPL        2007   Competed       2         Investigate Ceres and Vesta protoplanets

  vs. 5 Earth Science     AIM                        Explorers   Heliospheric Science      LASP        2007   Competed       3         Aeronomy of Ice in Mesosphere

  vs. 3 Heliophysics      Fermi
                          (GLAST)
                                                     Physics of
                                                     the Cosmos
                                                                Astrophysics              GSFC         2008    Directed      2         Gamma Ray Telescope
                                                                                                                                       Interaction between solar wind and
  missions                IBEX                       Explorers   Heliospheric Science     GSFC         2008   Competed       2
                                                                                                                                       interstellar medium
                          Kepler                     Discovery   Astrophysics               JPL        2009   Competed       1         Search for Earth-sized exoplanets
                                                     Robotic     ESMD/Planetary
                          LRO               X                                             GSFC         2009    Directed      7         Origin of the Moon
                                                     Lunar       Science
                                                                                                                                       Carbon Dioxide Investigation. Mission
                          OCO                        ESSP        Earth Science              JPL        2009   Competed       1
                                                                                                                                       failed due to launch vehicle failure




                                                                                6
Updated 20 Mission Results Are
                                  Similar to Initial 10 Mission Paper* Results
                         80%                                                                      76%
                                             10 Mission Study
                         70%
                                             20 Mission Study
                                                                                                          56%
Average Percent Growth




                         60%

                         50%             43%                          42% 41%
                         40%                     37%                                                                          36% 38%

                         30%

                         20%

                         10%

                          0%
                                             Mass                       Power 1                       Cost                    Schedule
                                                      1                                                       2                          2
Note:
1)                       As measured from Current Best Estimate, not including reserves
2)                       As measured from baseline estimate, including reserves

                           * “An Assessment of the Inherent Optimism in Early Conceptual Designs and its Effect on Cost and
                           Schedule Growth”, Freaner C., Bitten R., Bearden D., and Emmons D., May 2008
                                                                                      7
Agenda

• Background/Overview

• Database Description

• Resource Growth
  – Mass, Power, Cost & Schedule Trends


• Findings
  – Progression from milestones
  – Comparison of mission types
  – Payload vs. Spacecraft comparisons


• Potential Considerations


                               8
Satellite Mass Growth Relative to CBE (%)
                                                                          M
                                                                           is




                                                                                          0%
                                                                                                 10%
                                                                                                       20%
                                                                                                             30%
                                                                                                                   40%
                                                                                                                          50%
                                                                                                                                60%
                                                                                                                                      70%
                                                                                                                                                     80%
                                                                                                                                                                90%
                                                                              si
                                                                                 on
                                                                          M         #1
                                                                           is
                                                                              si
                                                                                 on
                                                                          M         #2
                                                                           is
                                                                              si
                                                                                 on
                                                                          M         #3
                                                                           is
                                                                              si
                                                                                 on
                                                                          M         #4
                                                                           is
                                                                              si
                                                                                 on
                                                                          M         #5
                                                                           is
                                                                              si
                                                                                 on
                                                                          M         #6
                                                                           is
                                                                              si
                                                                                 on
                                                                          M         #7
                                                                           is
                                                                              si
                                                                                 on
                                                                          M         #8
                                                                           is
                                                                              si
                                                                                 on
                                                                         M          #9
                                                                          is
                                                                            si
                                                                               on
                                                                         M         #1
                                                                          is          0
                                                                            si
                                                                               on




9
                                                                         M         #1
                                                                          is          1
                                                                            si
                                                                                                                                      Average




                                                                               on
                                                                         M         #1
                                                                          is          2
                                                                            si
                                                                               on
                                                                         M         #1
                                                                          is          3
                                                                            si
                                                                                                                                      Planetary Missions




                                                                               on
                                                                         M         #1
                                                                          is          4
                                                                                                                                      Earth Orbiting Missions




                                                                            si
                                                                               on
                                                                         M         #1
                                                                          is          5
                                                                            si
                                                                               on
                  Mass Growth Exceeds Typical Guidance:



                                                                         M         #1
                                                                          is          6
                                                                            si
                                                                               on
                                                                         M         #1
                                                                          is          7
                                                                            si
                                                                               on
                                                                         M         #1
                                                                          is          8
                                                                            si
                                                                               on
                                                                         M         #1
                                                                                                                                                                      Summary of Mass Growth from Start of Phase B




                                                                          is          9
                                                                            si
                                                                               on
    13 out of 20 Missions Exceed 30% Growth from Current Best Estimate




                                                                                   #2
                                                                                      0
                                                                             A
                                                                               ve
                                                                                  ra
                                                                                    ge
                                                                                                                    37%
Summary of Satellite Mass Growth Over Time

                                     90%
                                            Mission #1
                                            Mission #2
                                     80%    Mission #3
                                            Mission #4
                                     70%    Mission #5
                                            Mission #6
Satellite Mass Growth over CBE (%)




                                            Mission #7
                                     60%    Mission #8
                                            Mission #9
                                            Mission #10
                                     50%
                                            Mission #11
                                            Mission #12
                                     40%    Mission #13
                                            Mission #14                                                           37%
                                            Mission #15
                                     30%
                                            Mission #16
                                            Mission #17
                                                                                               28%
                                     20%    Mission #18
                                            Mission #19                     19%
                                            Mission #20
                                     10%    Average


                                      0%
                                                       0%
                                                     ATP                  PDR                CDR              Launch
                                     -10%




                                                          Majority of Mass Growth Occurs Primarily Prior to PDR


                                                                                    10
Satellite Power Growth Relative to CBE (%)

                                                                          M
                                                                           is




                                                                                          -20%
                                                                                                    0%
                                                                                                         20%
                                                                                                               40%
                                                                                                                           60%
                                                                                                                                 80%
                                                                                                                                       100%
                                                                                                                                                       120%
                                                                                                                                                                        140%
                                                                              si
                                                                                 on
                                                                          M         #1
                                                                           is
                                                                              si
                                                                                 on
                                                                          M         #2
                                                                           is
                                                                              si
                                                                                 on
                                                                          M         #3
                                                                           is
                                                                              si
                                                                                 on
                                                                          M         #4
                                                                           is
                                                                              si
                                                                                 on
                                                                          M         #5
                                                                           is
                                                                              si
                                                                                 on
                                                                          M         #6
                                                                           is
                                                                              si
                                                                                 on
                                                                          M         #7
                                                                           is
                                                                              si
                                                                                 on
                                                                          M         #8
                                                                           is
                                                                              si
                                                                                 on
                                                                         M          #9
                                                                          is
                                                                             si
                                                                                on
                                                                         M         #1
                                                                          is          0
                                                                             si
                                                                                on
                                                                         M         #1




11
                                                                          is          1
                                                                             si
                                                                                on
                                                                                                                                              Average




                                                                         M         #1
                                                                          is          2
                                                                             si
                                                                                on
                                                                         M         #1
                                                                          is          3
                                                                             si
                                                                                on
                                                                                                                                              Planetary Missions




                                                                         M         #1
                                                                          is          4
                                                                             si
                                                                                on
                                                                                                                                              Earth Orbiting Missions




                                                                         M         #1
                                                                          is          5
                                                                             si
                                                                                on
                                                                         M         #1
                                                                          is          6
                   Power Growth Exceeds Typical Guidance:



                                                                             si
                                                                                on
                                                                         M         #1
                                                                          is          7
                                                                             si
                                                                                on
                                                                         M         #1
                                                                          is          8
                                                                             si
                                                                                on
                                                                         M         #1
                                                                          is          9
                                                                             si
                                                                                                                                                                               Summary of Power Growth from Start of Phase B




                                                                                on
     8 out of 19 Missions Exceed 30% Growth from Current Best Estimate




                                                                                   #2
                                                                                      0
                                                                             A
                                                                                ve
                                                                                  ra
                                                                                    ge
                                                                                                                     41%
Summary of Power Growth Over Time

                                      140%
                                             Mission #1
                                             Mission #2
                                             Mission #3
                                      120%
                                             Mission #4
                                             Mission #5
                                             Mission #6
Satellite Power Growth over CBE (%)




                                      100%
                                             Mission #7
                                             Mission #8
                                             Mission #9
                                      80%    Mission #10
                                             Mission #11
                                             Mission #12
                                      60%    Mission #13
                                             Mission #14
                                             Mission #15
                                                                                                                    41%
                                                                                              36%
                                      40%    Mission #16
                                             Mission #17
                                             Mission #18                    19%
                                      20%    Mission #19
                                             Mission #20
                                             Average       0%
                                       0%

                                                       ATP                  PDR               CDR               Launch
                                      -20%




                                                           Majority of Power Growth Occurs Primarily Prior to CDR


                                                                                      12
Development Cost Growth over Baseline (%)

                                                           M
                                                            is




                                                                           0%
                                                                                 20%
                                                                                             40%
                                                                                                          60%
                                                                                                                  80%
                                                                                                                           100%
                                                                                                                                         120%
                                                                                                                                                       140%
                                                                                                                                                                160%
                                                               si
                                                                  on
                                                           M         #1
                                                            is
                                                               si
                                                                  on
                                                           M         #2
                                                            is
                                                               si
                                                                  on
                                                           M         #3
                                                            is
                                                               si
                                                                  on
                                                           M         #4
                                                            is
                                                               si
                                                                  on
                                                           M         #5
                                                            is
                                                               si
                                                                  on
                                                           M         #6
                                                            is
                                                               si
                                                                  on
                                                           M         #7
                                                            is
                                                               si
                                                                  on
                                                           M         #8
                                                            is
                                                               si
                                                                  on
                                                          M          #9
                                                           is
                                                              si
                                                                 on
                                                          M         #1
                                                           is
                                                              si       0
                                                                 on
                                                          M         #1
                                                           is
                                                              si       1
                                                                 on
                                                          M




13
                                                                    #1
                                                           is
                                                              si       2
                                                                 on
                                                                                                                                    Average




                                                          M         #1
                                                           is
                                                              si       3
                                                                 on
                                                          M         #1
                                                           is
                                                              si       4
                                                                 on
                                                          M         #1
                                                                                                                                    Planetary Missions




                                                           is
                                                              si       5
                                                                 on
                                                          M         #1
                                                                                                                                    Absolute Growth in $M
                                                                                                                                    Earth Orbiting Missions




                                                           is
                                                              si       6
                                                                 on
                                                          M         #1
                                                           is
                                                              si       7
           Development Cost Growth is Significant:



                                                                 on
                                                          M         #1
                                                           is
                                                              si       8
                                                                 on
                                                          M         #1
                                                           is
                                                              si       9
                                                                 on
     Average Cost Growth, Over & Above Reserves, is 56%




                                                                    #2
                                                                       0
                                                              A
                                                                 ve
                                                                   ra
                                                                                                                                                                       Summary of Cost Growth from Start of Phase B




                                                                     ge
                                                                                                           56%




                                                                           $-
                                                                                $40
                                                                                       $80
                                                                                                   $120
                                                                                                           $160
                                                                                                                  $200
                                                                                                                         $240
                                                                                                                                  $280
                                                                                                                                                $320
                                                                                                                                                         $360
                                                                                                                                                                $400




                                                                           Development Cost Growth over Baseline ($M)
Summary of Cost Growth Over Time

                                                                  150%
Mission Development Cost Growth over Baseline with Reserves (%)




                                                                         Mission #1
                                                                         Mission #2
                                                                         Mission #3
                                                                  125%
                                                                         Mission #4
                                                                         Mission #5
                                                                         Mission #6
                                                                  100%   Mission #7
                                                                         Mission #8
                                                                         Mission #9
                                                                         Mission #10
                                                                  75%    Mission #11
                                                                         Mission #12
                                                                         Mission #13
                                                                         Mission #14
                                                                                                                                        56%
                                                                  50%
                                                                         Mission #15
                                                                         Mission #16
                                                                         Mission #17
                                                                  25%    Mission #18
                                                                         Mission #19              14%              21%
                                                                         Mission #20
                                                                         Average
                                                                   0%
                                                                                   0%
                                                                                 ATP             PDR             CDR              Launch
                                                                  -25%


                                                                                   Cost Growth Occurs Primarily After PDR:
                                                                          More than Half of Growth (14% to 56%) is Realized After PDR


                                                                                                        14
Development Schedule Growth over Baseline
                                                                                                (%)

                                                             M
                                                              is




                                                                             0%
                                                                                  10%
                                                                                        20%
                                                                                              30%
                                                                                                    40%
                                                                                                           50%
                                                                                                                 60%
                                                                                                                       70%
                                                                                                                                80%
                                                                                                                                           90%
                                                                                                                                                    100%
                                                                 si
                                                                    on
                                                             M         #1
                                                              is
                                                                 si
                                                                    on
                                                             M         #2
                                                              is
                                                                 si
                                                                    on
                                                             M         #3
                                                              is
                                                                 si
                                                                    on
                                                             M         #4
                                                              is
                                                                 si
                                                                    on
                                                             M         #5
                                                              is
                                                                 si
                                                                    on
                                                             M         #6
                                                              is
                                                                 si
                                                                                                                        Average




                                                                    on
                                                             M         #7
                                                              is
                                                                 si
                                                                    on
                                                             M         #8
                                                              is
                                                                 si
                                                                    on
                                                            M
                                                                                                                        Planetary Missions




                                                             is        #9
                                                                si
                                                                   on
                                                            M
                                                                                                                        Earth Orbiting Missions




                                                                      #1
                                                             is          0
                                                                si
                                                                   on
                                                            M
                                                                                                                        Absolute Growth in Months




                                                                      #1
                                                             is          1
                                                                si
                                                                   on




15
                                                            M         #1
                                                             is          2
                                                                si
                                                                   on
                                                            M         #1
                                                             is          3
                                                                si
                                                                   on
                                                            M         #1
                                                             is          4
                                                                si
                                                                   on
                                                            M         #1
                                                             is          5
                                                                si
                                                                   on
                                                            M         #1
                                                             is          6
               Schedule Growth is Significant:

                                                                si
                                                                   on
                                                            M         #1
                                                             is          7
                                                                si
                                                                   on
                                                            M         #1
                                                             is          8
                                                                si
                                                                   on
                                                            M         #1
                                                             is          9
                                                                si
                                                                   on
     Average Schedule Growth is on the order of 18 Months




                                                                      #2
                                                                A        0
                                                                   ve
                                                                     ra
                                                                       ge
                                                                                                     38%
                                                                                                                                                           Summary of Schedule Growth from Start of Phase B




                                                                             0
                                                                                  5
                                                                                        10
                                                                                              15
                                                                                                    20
                                                                                                           25
                                                                                                                 30
                                                                                                                       35
                                                                                                                                40
                                                                                                                                           45
                                                                                                                                                    50




                                                                              Development Schedule Growth over Baseline
                                                                                             (Months)
Summary of Schedule Growth Over Time
                                                    100%
                                                           Mission #1
                                                           Mission #2
                                                           Mission #3
Mission Development Schedule Growth over Plan (%)




                                                           Mission #4
                                                    80%
                                                           Mission #5
                                                           Mission #6
                                                           Mission #7
                                                           Mission #8
                                                    60%    Mission #9
                                                           Mission #10                                               18 months
                                                           Mission #11             5 months        8 months
                                                           Mission #12
                                                    40%    Mission #13
                                                           Mission #14
                                                                                                                          38%
                                                           Mission #15
                                                           Mission #16
                                                           Mission #17
                                                    20%
                                                           Mission #18                                 17%
                                                           Mission #19
                                                           Mission #20                10%
                                                           Average
                                                     0%

                                                                    ATP             PDR              CDR              Launch

                                                    -20%



                                                                      Schedule Growth Occurs Primarily After PDR:
                                                             More than Half of Growth (13 of 18 Months) is Realized After PDR


                                                                                              16
Agenda

• Background/Overview

• Database Description

• Resource Growth
  – Mass, Power, Cost & Schedule Trends


• Findings
  – Progression from milestones
  – Comparison of mission types
  – Payload vs. Spacecraft comparisons


• Potential Considerations


                               17
Cost & Schedule Still Show Significant Growth from
                               Baseline Established at PDR
                         60%
                                                                                                  56%
                                            From Phase B Start
                         50%                From PDR
Average Percent Growth




                                                                      41%
                         40%              37%                                                           37%   38%


                         30%                                                                                        27%

                                                                              19%
                         20%                      15%

                         10%

                           0%
                                                                                                         2
                                       Mass             Power          Cost           Schedule
                                                      1                            1                                      2


                                 Over Half of Uncertainty for Mass & Power is Retired by PDR
                                      while 2/3 of Cost & Schedule Uncertainty Remain
                         Note:
                         1)      As measured from Current Best Estimate, not including reserves
                         2)      As measured from baseline estimate, including reserves
                                                                                       18
Data Shows that Programmatic Baseline Maturity
                                 Lags Technical Design Maturity

                                                    Programmatic Realization
                         60%                            Not Until Launch
                                         Mass
                         50%             Power       Technical Design
Average Percent Growth




                                                      Mature by CDR
                                         Cost
                         40%             Schedule

                         30%

                         20%

                         10%

                         0%
                               Phase B Start        PDR           CDR          Launch


                                                          19
Comparison of Competed vs. Directed Missions:
                                                      No Significant Difference in Results
                                            70%
Average Percent Growth from Phase B Start


                                                              Directed (5)
                                            60%                                                                      58%
                                                              Competed (15)
                                                                                                               51%
                                            50%
                                                                                             42%                                 40%
                                                        40%
                                            40%                 36%
                                                                                     29%                                   31%
                                            30%

                                            20%

                                            10%

                                            0%
                                                            Mass                       Power 1                  Cost       Schedule
                                                                     1                                                 2               2



      Growth in All Resources are Similar Between Competed & Directed Missions
                                  Note:
                                  1)          As measured from Current Best Estimate, not including reserves
                                  2)          As measured from baseline estimate, including reserves
                                                                                                      20
Planetary vs. Earth Orbiting Missions:
                                                      Resource Growth is Similar for Mass & Power
                                            80%                                                                       73%
Average Percent Growth from Phase B Start


                                                            Planetary (7)
                                            70%
                                                            Earth Orbiting (13)
                                            60%

                                            50%                                                                                   47%
                                                         40%                                  40%
                                            40%                  35%                 37%

                                            30%                                                                 25%
                                                                                                                            22%
                                            20%

                                            10%

                                            0%
                                                            Mass                        Power 1                  Cost       Schedule 2
                                                                     1                                                  2



                                             Cost & Schedule Growth for Planetary Missions is Significantly Less
                                    Note:
                                    1)         As measured from Current Best Estimate, not including reserves
                                    2)         As measured from baseline estimate, including reserves 21
Correlation Between Cost and Schedule Growth Indicates that
   Schedule Growth Has Strong Influence on Cost Growth
                                              140%
 Development Cost Growth from Phase B Start




                                              120%


                                                      % Cost Growth = 1.4775 * % Schedule Growth
                                              100%
                                                                     R2 = 0.6166


                                              80%



                                              60%



                                              40%



                                              20%



                                               0%
                                                     0%    10%     20%    30%     40%     50%      60%    70%   80%   90%   100%
                                                                           Schedule Growth from Phase B Start



                                                                                         22
Payload Mass and Cost Growth Significantly Greater than
                                                        Spacecraft Mass & Cost Growth

                                            120%
Average Percent Growth from Phase B Start



                                                                      Payload                                        101%
                                            100%                      Spacecraft

                                             80%
                                                                        60%
                                             60%
                                                                                                                                   44%
                                             40%                                        33%

                                             20%

                                               0%
                                                                               Mass                                         Cost
                                                                                        1                                          1



                     Data Indicated Payload Resource has Greater Uncertainty than Spacecraft
                                            Note:
                                            1)      As measured from Current Best Estimate, not including reserves
                                                                                                         23
Cumulative Cost Distribution Shows Wide Distribution of
   Payload Cost Growth vs. Spacecraft Cost Growth
                                                 100%


                                                 90%
   Cumulative Distribution for All Data Points




                                                 80%


                                                 70%
                                                                                                             Payload Cost Growth has
                                                 60%                                                           Much Greater Variance
                                                                                                              than Spacecraft Growth
                                                 50%

                                                                                                         Spacecraft Cost Growth
                                                 40%
                                                                                                         Payload Cost Growth

                                                 30%


                                                 20%


                                                 10%


                                                  0%
                                                    -25%    0%     25%     50%    75%    100%     125%   150%    175%   200%      225%   250%
                                                           Cost Growth from Phase B Start over Initial Estimate without Cost Reserve



                                                                                             24
Instrument Payload Mass/Cost Growth Data Over Time Also
                                              Indicates Payload Cost Lags Payload Maturity

                                       120%
Percent Growth over CBE w/o reserves




                                       100%          Payload Mass                                       101%
                                                     Payload Cost
                                       80%
                                                                                                  60%
                                       60%
                                                                                  43%
                                       40%                          31%              37%

                                       20%                            18%
                                                   0%
                                        0%           0%
                                              Phase B Start         PDR           CDR            Launch
                                              Payload Cost Significantly Lags Payload Design Maturity


                                                                            25
Range of Mass Growth at Instrument & Subsystem Level
        Can Provide Guidance for Initial KDP-B Cost Estimates
   Typical Mass Reserve
                                                                                                                      Instruments
   Design Guidance 30%

                                                                                                                      Propulsion
                                                                                          Below Mean
                                                                                          Above Mean                  ADCS


                                                                                                                      Thermal


                                                              Subsystem           Min      Mean     Max      Median
                                                                                                                      Comm
                                                              Instrument            11%      60%     202%       51%
                                                              Propulsion           -73%      10%      69%       18%
                                                              ADCS                 -21%      29%     108%       24%
                                                              Thermal              -36%      77%     269%       58%   C&DH
                                                              Comm                 -55%       5%      76%        7%
                                                              C&DH                 -37%      16%     104%        6%
                                                              Power                -37%      45%     103%       40%   Power
                                                              Structure & Mech     -19%      57%     142%       60%


                                                                                                                      Struct & Mech


-75%   -50%   -25%        0%   25%   50%      75%     100%     125%       150%   175%     200%     225%     250%   275%
                                           Range for Mass Distributions



          Range of Mass Growth is Large and Exceeds Typical Industry Guidance


                                                                26
Agenda

• Background/Overview

• Database Description

• Resource Growth
  – Mass, Power, Cost & Schedule Trends


• Findings
  – Progression from milestones
  – Comparison of mission types
  – Payload vs. Spacecraft comparisons


• Potential Considerations


                               27
Potential Considerations
• For Project Managers
  – Mass and power reserve guidelines for spacecraft and payload
    could be increased to be more consistent with historical
    averages
  – Schedule growth seems to be a key factor in controlling cost
    growth
  – More emphasis could be placed on early payload designs as
    there is much greater uncertainty in the payload development
    than the spacecraft


• For Cost Analysts
  – Wider ranges of input parameters could be used to provide more
    robust initial cost estimates which can address uncertainty in
    early design

                                 28
References
1)   Freaner C., Bitten R., Bearden D., and Emmons D., “An Assessment of the Inherent Optimism
     in Early Conceptual Designs and its Effect on Cost and Schedule Growth”, 2008
     SSCAG/SCAF/EACE Joint International Conference, Noordwijk, The Netherlands, 15-16 May
     2008.
2)   Bitten R., Emmons D., Freaner C., “Using Historical NASA Cost and Schedule Growth to Set
     Future Program and Project Reserve Guidelines”, IEEE Aerospace Conference, Big Sky,
     Montana, March 3-10, 2007.
3)   Bitten R.E., “Determining When A Mission Is "Outside The Box": Guidelines For A Cost-
     Constrained Environment”, 6th IAA International Low Cost Planetary Conference, October 11-
     13, 2005.
4)   Bitten R.E., Bearden D.A., Lao N.Y. and Park, T.H., “The Effect of Schedule Constraints on the
     Success of Planetary Missions”, 5th IAA International Conference on Low-Cost Planetary
     Missions, 24 September 2003
5)   Emmons D., “A Quantitative Approach to Independent Schedule Estimates of Planetary &
     Earth-orbiting Missions”, 2008 ISPA-SCEA Joint International Conference, Netherlands, 12-14
     May 2008




                                                  29

More Related Content

What's hot

WE1.L10 - USE OF NASA DATA IN THE JOINT CENTER FOR SATELLITE DATA ASSIMILATION
WE1.L10 - USE OF NASA DATA IN THE JOINT CENTER FOR SATELLITE DATA ASSIMILATIONWE1.L10 - USE OF NASA DATA IN THE JOINT CENTER FOR SATELLITE DATA ASSIMILATION
WE1.L10 - USE OF NASA DATA IN THE JOINT CENTER FOR SATELLITE DATA ASSIMILATIONgrssieee
 
The use of geoinformatics in mineral exploration and exploitation
The use of geoinformatics in mineral exploration and exploitationThe use of geoinformatics in mineral exploration and exploitation
The use of geoinformatics in mineral exploration and exploitationMarguerite Walsh
 
The search for_extraterrestrial_civilizations_with_large_energy_supplies
The search for_extraterrestrial_civilizations_with_large_energy_suppliesThe search for_extraterrestrial_civilizations_with_large_energy_supplies
The search for_extraterrestrial_civilizations_with_large_energy_suppliesSérgio Sacani
 
20131107 damasso great
20131107 damasso great20131107 damasso great
20131107 damasso greatOAVdA_APACHE
 
Fundamentals remote sensing land used
Fundamentals remote sensing land usedFundamentals remote sensing land used
Fundamentals remote sensing land usedHidraulica Tymanzo
 
The 2013 NRC Decadal Survey in Solar and Space Physics (Heliophysics)
The 2013 NRC Decadal Survey in Solar and Space Physics (Heliophysics)The 2013 NRC Decadal Survey in Solar and Space Physics (Heliophysics)
The 2013 NRC Decadal Survey in Solar and Space Physics (Heliophysics)Art Charo
 
20110728_IGARSS_GDPS(ryu)fin1.pptx
20110728_IGARSS_GDPS(ryu)fin1.pptx20110728_IGARSS_GDPS(ryu)fin1.pptx
20110728_IGARSS_GDPS(ryu)fin1.pptxgrssieee
 
A terrestrial planet_candidate_in_a_temperate_orbit_around_proxima_centauri
A terrestrial planet_candidate_in_a_temperate_orbit_around_proxima_centauriA terrestrial planet_candidate_in_a_temperate_orbit_around_proxima_centauri
A terrestrial planet_candidate_in_a_temperate_orbit_around_proxima_centauriSérgio Sacani
 
Rs satellites catelogue 2012
Rs satellites catelogue 2012Rs satellites catelogue 2012
Rs satellites catelogue 2012Atiqa Khan
 
The 19 Feb. 2016 Outburst of Comet 67P/CG: An ESA Rosetta Multi-Instrument Study
The 19 Feb. 2016 Outburst of Comet 67P/CG: An ESA Rosetta Multi-Instrument StudyThe 19 Feb. 2016 Outburst of Comet 67P/CG: An ESA Rosetta Multi-Instrument Study
The 19 Feb. 2016 Outburst of Comet 67P/CG: An ESA Rosetta Multi-Instrument StudySérgio Sacani
 
WE4.L10.1: OPERATIONAL ENVIRONMENTAL DATA IN 2010: CONNECTING GLOBAL AND LOCA...
WE4.L10.1: OPERATIONAL ENVIRONMENTAL DATA IN 2010: CONNECTING GLOBAL AND LOCA...WE4.L10.1: OPERATIONAL ENVIRONMENTAL DATA IN 2010: CONNECTING GLOBAL AND LOCA...
WE4.L10.1: OPERATIONAL ENVIRONMENTAL DATA IN 2010: CONNECTING GLOBAL AND LOCA...grssieee
 
TU2.T10.1.pptx
TU2.T10.1.pptxTU2.T10.1.pptx
TU2.T10.1.pptxgrssieee
 
Cold Molecular Gas in Merger Remnants. I. Formation of Molecular Gas Discs
Cold Molecular Gas in Merger Remnants. I. Formation of Molecular Gas DiscsCold Molecular Gas in Merger Remnants. I. Formation of Molecular Gas Discs
Cold Molecular Gas in Merger Remnants. I. Formation of Molecular Gas DiscsGOASA
 
Earth Observation for Climate - Julian Wilson, Joint Research Centre, institu...
Earth Observation for Climate - Julian Wilson, Joint Research Centre, institu...Earth Observation for Climate - Julian Wilson, Joint Research Centre, institu...
Earth Observation for Climate - Julian Wilson, Joint Research Centre, institu...Environmental Protection Agency, Ireland
 

What's hot (20)

WE1.L10 - USE OF NASA DATA IN THE JOINT CENTER FOR SATELLITE DATA ASSIMILATION
WE1.L10 - USE OF NASA DATA IN THE JOINT CENTER FOR SATELLITE DATA ASSIMILATIONWE1.L10 - USE OF NASA DATA IN THE JOINT CENTER FOR SATELLITE DATA ASSIMILATION
WE1.L10 - USE OF NASA DATA IN THE JOINT CENTER FOR SATELLITE DATA ASSIMILATION
 
The use of geoinformatics in mineral exploration and exploitation
The use of geoinformatics in mineral exploration and exploitationThe use of geoinformatics in mineral exploration and exploitation
The use of geoinformatics in mineral exploration and exploitation
 
The search for_extraterrestrial_civilizations_with_large_energy_supplies
The search for_extraterrestrial_civilizations_with_large_energy_suppliesThe search for_extraterrestrial_civilizations_with_large_energy_supplies
The search for_extraterrestrial_civilizations_with_large_energy_supplies
 
20131107 damasso great
20131107 damasso great20131107 damasso great
20131107 damasso great
 
Fundamentals remote sensing land used
Fundamentals remote sensing land usedFundamentals remote sensing land used
Fundamentals remote sensing land used
 
The 2013 NRC Decadal Survey in Solar and Space Physics (Heliophysics)
The 2013 NRC Decadal Survey in Solar and Space Physics (Heliophysics)The 2013 NRC Decadal Survey in Solar and Space Physics (Heliophysics)
The 2013 NRC Decadal Survey in Solar and Space Physics (Heliophysics)
 
Scientific platforms
Scientific platformsScientific platforms
Scientific platforms
 
20110728_IGARSS_GDPS(ryu)fin1.pptx
20110728_IGARSS_GDPS(ryu)fin1.pptx20110728_IGARSS_GDPS(ryu)fin1.pptx
20110728_IGARSS_GDPS(ryu)fin1.pptx
 
AJ_Article
AJ_ArticleAJ_Article
AJ_Article
 
A terrestrial planet_candidate_in_a_temperate_orbit_around_proxima_centauri
A terrestrial planet_candidate_in_a_temperate_orbit_around_proxima_centauriA terrestrial planet_candidate_in_a_temperate_orbit_around_proxima_centauri
A terrestrial planet_candidate_in_a_temperate_orbit_around_proxima_centauri
 
Cosmology Research in China
Cosmology Research in ChinaCosmology Research in China
Cosmology Research in China
 
Rs satellites catelogue 2012
Rs satellites catelogue 2012Rs satellites catelogue 2012
Rs satellites catelogue 2012
 
Manuscript7
Manuscript7Manuscript7
Manuscript7
 
Mercator Ocean newsletter 47
Mercator Ocean newsletter 47Mercator Ocean newsletter 47
Mercator Ocean newsletter 47
 
The 19 Feb. 2016 Outburst of Comet 67P/CG: An ESA Rosetta Multi-Instrument Study
The 19 Feb. 2016 Outburst of Comet 67P/CG: An ESA Rosetta Multi-Instrument StudyThe 19 Feb. 2016 Outburst of Comet 67P/CG: An ESA Rosetta Multi-Instrument Study
The 19 Feb. 2016 Outburst of Comet 67P/CG: An ESA Rosetta Multi-Instrument Study
 
WE4.L10.1: OPERATIONAL ENVIRONMENTAL DATA IN 2010: CONNECTING GLOBAL AND LOCA...
WE4.L10.1: OPERATIONAL ENVIRONMENTAL DATA IN 2010: CONNECTING GLOBAL AND LOCA...WE4.L10.1: OPERATIONAL ENVIRONMENTAL DATA IN 2010: CONNECTING GLOBAL AND LOCA...
WE4.L10.1: OPERATIONAL ENVIRONMENTAL DATA IN 2010: CONNECTING GLOBAL AND LOCA...
 
TU2.T10.1.pptx
TU2.T10.1.pptxTU2.T10.1.pptx
TU2.T10.1.pptx
 
Cold Molecular Gas in Merger Remnants. I. Formation of Molecular Gas Discs
Cold Molecular Gas in Merger Remnants. I. Formation of Molecular Gas DiscsCold Molecular Gas in Merger Remnants. I. Formation of Molecular Gas Discs
Cold Molecular Gas in Merger Remnants. I. Formation of Molecular Gas Discs
 
Earth Observation for Climate - Julian Wilson, Joint Research Centre, institu...
Earth Observation for Climate - Julian Wilson, Joint Research Centre, institu...Earth Observation for Climate - Julian Wilson, Joint Research Centre, institu...
Earth Observation for Climate - Julian Wilson, Joint Research Centre, institu...
 
PellegrinoHonorsThesis
PellegrinoHonorsThesisPellegrinoHonorsThesis
PellegrinoHonorsThesis
 

Viewers also liked

Duncan.william
Duncan.williamDuncan.william
Duncan.williamNASAPMC
 
Lisa.ditullio
Lisa.ditullioLisa.ditullio
Lisa.ditullioNASAPMC
 
Unger massey
Unger masseyUnger massey
Unger masseyNASAPMC
 
Mitchell.davis
Mitchell.davisMitchell.davis
Mitchell.davisNASAPMC
 
Manthos jeff
Manthos jeffManthos jeff
Manthos jeffNASAPMC
 
Calloway amer v2
Calloway amer v2Calloway amer v2
Calloway amer v2NASAPMC
 
Albert sierra
Albert sierraAlbert sierra
Albert sierraNASAPMC
 

Viewers also liked (7)

Duncan.william
Duncan.williamDuncan.william
Duncan.william
 
Lisa.ditullio
Lisa.ditullioLisa.ditullio
Lisa.ditullio
 
Unger massey
Unger masseyUnger massey
Unger massey
 
Mitchell.davis
Mitchell.davisMitchell.davis
Mitchell.davis
 
Manthos jeff
Manthos jeffManthos jeff
Manthos jeff
 
Calloway amer v2
Calloway amer v2Calloway amer v2
Calloway amer v2
 
Albert sierra
Albert sierraAlbert sierra
Albert sierra
 

Similar to Bitten

Freaner.claude
Freaner.claudeFreaner.claude
Freaner.claudeNASAPMC
 
Salute.joan
Salute.joanSalute.joan
Salute.joanNASAPMC
 
Data Science Education: Needs & Opportunities in Astronomy
Data Science Education: Needs & Opportunities in AstronomyData Science Education: Needs & Opportunities in Astronomy
Data Science Education: Needs & Opportunities in AstronomyJoshua Bloom
 
Bitten mahr phasee
Bitten mahr phaseeBitten mahr phasee
Bitten mahr phaseeNASAPMC
 
Dennon.clardy
Dennon.clardyDennon.clardy
Dennon.clardyNASAPMC
 
Dennon.clardy
Dennon.clardyDennon.clardy
Dennon.clardyNASAPMC
 
Patterson.donna
Patterson.donnaPatterson.donna
Patterson.donnaNASAPMC
 
Canberra Nanosatellitre Keynote-jw hines
Canberra Nanosatellitre Keynote-jw hinesCanberra Nanosatellitre Keynote-jw hines
Canberra Nanosatellitre Keynote-jw hinesJohn Hines
 
The Transit Method for Exoplanet Detection
The Transit Method for Exoplanet DetectionThe Transit Method for Exoplanet Detection
The Transit Method for Exoplanet DetectionKennedy Jnr Izuagbe
 
The messenger mission_to_mercury
The messenger mission_to_mercuryThe messenger mission_to_mercury
The messenger mission_to_mercurySérgio Sacani
 
Science with small telescopes - exoplanets
Science with small telescopes - exoplanetsScience with small telescopes - exoplanets
Science with small telescopes - exoplanetsguest8aa6ebb
 
Kepler’s last planet discoveries: two new planets and one single-transit cand...
Kepler’s last planet discoveries: two new planets and one single-transit cand...Kepler’s last planet discoveries: two new planets and one single-transit cand...
Kepler’s last planet discoveries: two new planets and one single-transit cand...Sérgio Sacani
 
Silicon Happy Valley 2016
Silicon Happy Valley 2016Silicon Happy Valley 2016
Silicon Happy Valley 2016Corey Cochrane
 

Similar to Bitten (20)

Freaner.claude
Freaner.claudeFreaner.claude
Freaner.claude
 
Salute.joan
Salute.joanSalute.joan
Salute.joan
 
The Future of Solar System Exploration
The Future of Solar System ExplorationThe Future of Solar System Exploration
The Future of Solar System Exploration
 
AAS National Conference 2008: Jon Morse
AAS National Conference 2008: Jon MorseAAS National Conference 2008: Jon Morse
AAS National Conference 2008: Jon Morse
 
Bicay_Post
Bicay_PostBicay_Post
Bicay_Post
 
Data Science Education: Needs & Opportunities in Astronomy
Data Science Education: Needs & Opportunities in AstronomyData Science Education: Needs & Opportunities in Astronomy
Data Science Education: Needs & Opportunities in Astronomy
 
Bitten mahr phasee
Bitten mahr phaseeBitten mahr phasee
Bitten mahr phasee
 
Dennon.clardy
Dennon.clardyDennon.clardy
Dennon.clardy
 
Dennon.clardy
Dennon.clardyDennon.clardy
Dennon.clardy
 
Patterson.donna
Patterson.donnaPatterson.donna
Patterson.donna
 
Canberra Nanosatellitre Keynote-jw hines
Canberra Nanosatellitre Keynote-jw hinesCanberra Nanosatellitre Keynote-jw hines
Canberra Nanosatellitre Keynote-jw hines
 
Goddard 2015: John Mather, NASA
Goddard 2015: John Mather, NASAGoddard 2015: John Mather, NASA
Goddard 2015: John Mather, NASA
 
AAS National Conference 2008: Diana Blaney
AAS National Conference 2008: Diana BlaneyAAS National Conference 2008: Diana Blaney
AAS National Conference 2008: Diana Blaney
 
VO Course 11: Spatial indexing
VO Course 11: Spatial indexingVO Course 11: Spatial indexing
VO Course 11: Spatial indexing
 
Path tolifefinder
Path tolifefinderPath tolifefinder
Path tolifefinder
 
The Transit Method for Exoplanet Detection
The Transit Method for Exoplanet DetectionThe Transit Method for Exoplanet Detection
The Transit Method for Exoplanet Detection
 
The messenger mission_to_mercury
The messenger mission_to_mercuryThe messenger mission_to_mercury
The messenger mission_to_mercury
 
Science with small telescopes - exoplanets
Science with small telescopes - exoplanetsScience with small telescopes - exoplanets
Science with small telescopes - exoplanets
 
Kepler’s last planet discoveries: two new planets and one single-transit cand...
Kepler’s last planet discoveries: two new planets and one single-transit cand...Kepler’s last planet discoveries: two new planets and one single-transit cand...
Kepler’s last planet discoveries: two new planets and one single-transit cand...
 
Silicon Happy Valley 2016
Silicon Happy Valley 2016Silicon Happy Valley 2016
Silicon Happy Valley 2016
 

More from NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 

More from NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

Recently uploaded

Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024BookNet Canada
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhisoniya singh
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Scott Keck-Warren
 
Build your next Gen AI Breakthrough - April 2024
Build your next Gen AI Breakthrough - April 2024Build your next Gen AI Breakthrough - April 2024
Build your next Gen AI Breakthrough - April 2024Neo4j
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...Fwdays
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxMaking_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxnull - The Open Security Community
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 

Recently uploaded (20)

E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
 
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
 
Vulnerability_Management_GRC_by Sohang Sengupta.pptx
Vulnerability_Management_GRC_by Sohang Sengupta.pptxVulnerability_Management_GRC_by Sohang Sengupta.pptx
Vulnerability_Management_GRC_by Sohang Sengupta.pptx
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024
 
Build your next Gen AI Breakthrough - April 2024
Build your next Gen AI Breakthrough - April 2024Build your next Gen AI Breakthrough - April 2024
Build your next Gen AI Breakthrough - April 2024
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxMaking_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food Manufacturing
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 

Bitten

  • 1. Conceptual Design Optimism, Cost and Schedule Growth Effects Presented at the 2010 NASA Program Management Challenge 9-10 February 2010, Houston, Texas Claude Freaner, Bob Bitten, Debra Emmons Used with permission 1
  • 2. Agenda • Background/Overview • Database Description • Resource Growth – Mass, Power, Cost & Schedule Trends • Findings – Progression from milestones – Comparison of mission types – Payload vs. Spacecraft comparisons • Potential Considerations 2
  • 3. Background • Results from a recent study* of 10 NASA missions over the past decade indicated that the average cost and schedule growth of these missions, over and above programmatic reserves, was 76% and 26%, respectively, measured from beginning of Phase B • One potential causative factor postulated was the inherent optimism in initial concept designs due to competitive pressures • Inherent optimism can translate to the underestimation of the technical specifications such as mass, power, data rate, and the complexity of a system • Underestimation of these resources can lead to the underestimation of the final cost of the mission since most cost models use some form of system resources as a predictor of mission cost • To compound problems, the desire to launch a system as early as possible, in order to obtain science quickly, can lead to a success oriented schedule that may be shorter than historical comparisons would indicate • This combination of underestimated resources providing an optimistic cost estimate basis combined with a success oriented schedule can contribute to the observed history of cost and schedule growth * “An Assessment of the Inherent Optimism in Early Conceptual Designs and its Effect on Cost and Schedule Growth”, Freaner C., Bitten R., Bearden D., and Emmons D., May 2008 3
  • 4. Study Approach • For a set of 20 missions in the study, the mass, power, cost, schedule and other parameters were identified at the beginning of the Preliminary Design phase (NASA Phase B) of a mission* • These values were then compared to values presented at the Preliminary Design Review (PDR), Critical Design Review (CDR) and at the time of launch to understand the growth over time of each of these resources • The resource growth is then compared to industry guidelines to understand if these guidelines would have adequately predicted the growth for the mission data set studied • In addition, resource growth of different mission types and correlation of cost growth in relation to different parameters is also shown * All parametric and programmatic data were obtained from NASA CADRe data" 4
  • 5. Agenda • Background/Overview • Database Description • Resource Growth – Mass, Power, Cost & Schedule Trends • Findings – Progression from milestones – Comparison of mission types – Payload vs. Spacecraft comparisons • Potential Considerations 5
  • 6. Database Description: 20 Missions Represent a Wide Range of Recent NASA Missions Key Launch Acquisition Number of Planetary? Program Science Type Center(s) Year Type Instruments Comments Advanced land imaging technology EO-1 NMP Earth Science GSFC 2000 Competed 5 demonstrator Collect samples of solar wind particles at GENESIS X Discovery Planetary Science JPL 2001 Competed 4 L1 point and return them to Earth • 5 Directed vs. GRACE ESSP Earth Science JPL 2002 Competed 6 Earth Gravity Measurement 15 Competed Spitzer Physics of the Cosmos Astrophysics JPL 2003 Directed 4 IR space telescope, the last of the Great Observatories missions GALEX Explorers Astrophysics JPL/CalTech 2003 Competed 1 UV space telescope SWIFT Explorers Astrophysics GSFC 2004 Competed 4 Gamma Ray burst detector MESSENGER X Discovery Planetary Science APL 2004 Competed 7 Investigate Mercury • 7 Planetary missions MRO X MEP Planetary Science JPL 2005 Directed 7 Investigate history of water on Mars vs. 13 Earth or near- Deep Impact X Discovery Planetary Science JPL 2005 Competed 3 Comet impactor Earth Orbiters Cloudsat ESSP Earth Science JPL 2006 Competed 1 Radar observation of clouds 2 spacecraft looking at solar dynamics - STEREO STP Heliospheric Science GSFC/APL 2006 Directed 4 Earth leading and trailing orbits CALIPSO ESSP Earth Science LARC 2006 Competed 3 Aerosols • 7 Planetary Science New X New Planetary Science APL 2006 Competed 7 Investigate Pluto Horizons Frontiers vs. 5 Astrophysics DAWN X Discovery Planetary Science JPL 2007 Competed 2 Investigate Ceres and Vesta protoplanets vs. 5 Earth Science AIM Explorers Heliospheric Science LASP 2007 Competed 3 Aeronomy of Ice in Mesosphere vs. 3 Heliophysics Fermi (GLAST) Physics of the Cosmos Astrophysics GSFC 2008 Directed 2 Gamma Ray Telescope Interaction between solar wind and missions IBEX Explorers Heliospheric Science GSFC 2008 Competed 2 interstellar medium Kepler Discovery Astrophysics JPL 2009 Competed 1 Search for Earth-sized exoplanets Robotic ESMD/Planetary LRO X GSFC 2009 Directed 7 Origin of the Moon Lunar Science Carbon Dioxide Investigation. Mission OCO ESSP Earth Science JPL 2009 Competed 1 failed due to launch vehicle failure 6
  • 7. Updated 20 Mission Results Are Similar to Initial 10 Mission Paper* Results 80% 76% 10 Mission Study 70% 20 Mission Study 56% Average Percent Growth 60% 50% 43% 42% 41% 40% 37% 36% 38% 30% 20% 10% 0% Mass Power 1 Cost Schedule 1 2 2 Note: 1) As measured from Current Best Estimate, not including reserves 2) As measured from baseline estimate, including reserves * “An Assessment of the Inherent Optimism in Early Conceptual Designs and its Effect on Cost and Schedule Growth”, Freaner C., Bitten R., Bearden D., and Emmons D., May 2008 7
  • 8. Agenda • Background/Overview • Database Description • Resource Growth – Mass, Power, Cost & Schedule Trends • Findings – Progression from milestones – Comparison of mission types – Payload vs. Spacecraft comparisons • Potential Considerations 8
  • 9. Satellite Mass Growth Relative to CBE (%) M is 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% si on M #1 is si on M #2 is si on M #3 is si on M #4 is si on M #5 is si on M #6 is si on M #7 is si on M #8 is si on M #9 is si on M #1 is 0 si on 9 M #1 is 1 si Average on M #1 is 2 si on M #1 is 3 si Planetary Missions on M #1 is 4 Earth Orbiting Missions si on M #1 is 5 si on Mass Growth Exceeds Typical Guidance: M #1 is 6 si on M #1 is 7 si on M #1 is 8 si on M #1 Summary of Mass Growth from Start of Phase B is 9 si on 13 out of 20 Missions Exceed 30% Growth from Current Best Estimate #2 0 A ve ra ge 37%
  • 10. Summary of Satellite Mass Growth Over Time 90% Mission #1 Mission #2 80% Mission #3 Mission #4 70% Mission #5 Mission #6 Satellite Mass Growth over CBE (%) Mission #7 60% Mission #8 Mission #9 Mission #10 50% Mission #11 Mission #12 40% Mission #13 Mission #14 37% Mission #15 30% Mission #16 Mission #17 28% 20% Mission #18 Mission #19 19% Mission #20 10% Average 0% 0% ATP PDR CDR Launch -10% Majority of Mass Growth Occurs Primarily Prior to PDR 10
  • 11. Satellite Power Growth Relative to CBE (%) M is -20% 0% 20% 40% 60% 80% 100% 120% 140% si on M #1 is si on M #2 is si on M #3 is si on M #4 is si on M #5 is si on M #6 is si on M #7 is si on M #8 is si on M #9 is si on M #1 is 0 si on M #1 11 is 1 si on Average M #1 is 2 si on M #1 is 3 si on Planetary Missions M #1 is 4 si on Earth Orbiting Missions M #1 is 5 si on M #1 is 6 Power Growth Exceeds Typical Guidance: si on M #1 is 7 si on M #1 is 8 si on M #1 is 9 si Summary of Power Growth from Start of Phase B on 8 out of 19 Missions Exceed 30% Growth from Current Best Estimate #2 0 A ve ra ge 41%
  • 12. Summary of Power Growth Over Time 140% Mission #1 Mission #2 Mission #3 120% Mission #4 Mission #5 Mission #6 Satellite Power Growth over CBE (%) 100% Mission #7 Mission #8 Mission #9 80% Mission #10 Mission #11 Mission #12 60% Mission #13 Mission #14 Mission #15 41% 36% 40% Mission #16 Mission #17 Mission #18 19% 20% Mission #19 Mission #20 Average 0% 0% ATP PDR CDR Launch -20% Majority of Power Growth Occurs Primarily Prior to CDR 12
  • 13. Development Cost Growth over Baseline (%) M is 0% 20% 40% 60% 80% 100% 120% 140% 160% si on M #1 is si on M #2 is si on M #3 is si on M #4 is si on M #5 is si on M #6 is si on M #7 is si on M #8 is si on M #9 is si on M #1 is si 0 on M #1 is si 1 on M 13 #1 is si 2 on Average M #1 is si 3 on M #1 is si 4 on M #1 Planetary Missions is si 5 on M #1 Absolute Growth in $M Earth Orbiting Missions is si 6 on M #1 is si 7 Development Cost Growth is Significant: on M #1 is si 8 on M #1 is si 9 on Average Cost Growth, Over & Above Reserves, is 56% #2 0 A ve ra Summary of Cost Growth from Start of Phase B ge 56% $- $40 $80 $120 $160 $200 $240 $280 $320 $360 $400 Development Cost Growth over Baseline ($M)
  • 14. Summary of Cost Growth Over Time 150% Mission Development Cost Growth over Baseline with Reserves (%) Mission #1 Mission #2 Mission #3 125% Mission #4 Mission #5 Mission #6 100% Mission #7 Mission #8 Mission #9 Mission #10 75% Mission #11 Mission #12 Mission #13 Mission #14 56% 50% Mission #15 Mission #16 Mission #17 25% Mission #18 Mission #19 14% 21% Mission #20 Average 0% 0% ATP PDR CDR Launch -25% Cost Growth Occurs Primarily After PDR: More than Half of Growth (14% to 56%) is Realized After PDR 14
  • 15. Development Schedule Growth over Baseline (%) M is 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% si on M #1 is si on M #2 is si on M #3 is si on M #4 is si on M #5 is si on M #6 is si Average on M #7 is si on M #8 is si on M Planetary Missions is #9 si on M Earth Orbiting Missions #1 is 0 si on M Absolute Growth in Months #1 is 1 si on 15 M #1 is 2 si on M #1 is 3 si on M #1 is 4 si on M #1 is 5 si on M #1 is 6 Schedule Growth is Significant: si on M #1 is 7 si on M #1 is 8 si on M #1 is 9 si on Average Schedule Growth is on the order of 18 Months #2 A 0 ve ra ge 38% Summary of Schedule Growth from Start of Phase B 0 5 10 15 20 25 30 35 40 45 50 Development Schedule Growth over Baseline (Months)
  • 16. Summary of Schedule Growth Over Time 100% Mission #1 Mission #2 Mission #3 Mission Development Schedule Growth over Plan (%) Mission #4 80% Mission #5 Mission #6 Mission #7 Mission #8 60% Mission #9 Mission #10 18 months Mission #11 5 months 8 months Mission #12 40% Mission #13 Mission #14 38% Mission #15 Mission #16 Mission #17 20% Mission #18 17% Mission #19 Mission #20 10% Average 0% ATP PDR CDR Launch -20% Schedule Growth Occurs Primarily After PDR: More than Half of Growth (13 of 18 Months) is Realized After PDR 16
  • 17. Agenda • Background/Overview • Database Description • Resource Growth – Mass, Power, Cost & Schedule Trends • Findings – Progression from milestones – Comparison of mission types – Payload vs. Spacecraft comparisons • Potential Considerations 17
  • 18. Cost & Schedule Still Show Significant Growth from Baseline Established at PDR 60% 56% From Phase B Start 50% From PDR Average Percent Growth 41% 40% 37% 37% 38% 30% 27% 19% 20% 15% 10% 0% 2 Mass Power Cost Schedule 1 1 2 Over Half of Uncertainty for Mass & Power is Retired by PDR while 2/3 of Cost & Schedule Uncertainty Remain Note: 1) As measured from Current Best Estimate, not including reserves 2) As measured from baseline estimate, including reserves 18
  • 19. Data Shows that Programmatic Baseline Maturity Lags Technical Design Maturity Programmatic Realization 60% Not Until Launch Mass 50% Power Technical Design Average Percent Growth Mature by CDR Cost 40% Schedule 30% 20% 10% 0% Phase B Start PDR CDR Launch 19
  • 20. Comparison of Competed vs. Directed Missions: No Significant Difference in Results 70% Average Percent Growth from Phase B Start Directed (5) 60% 58% Competed (15) 51% 50% 42% 40% 40% 40% 36% 29% 31% 30% 20% 10% 0% Mass Power 1 Cost Schedule 1 2 2 Growth in All Resources are Similar Between Competed & Directed Missions Note: 1) As measured from Current Best Estimate, not including reserves 2) As measured from baseline estimate, including reserves 20
  • 21. Planetary vs. Earth Orbiting Missions: Resource Growth is Similar for Mass & Power 80% 73% Average Percent Growth from Phase B Start Planetary (7) 70% Earth Orbiting (13) 60% 50% 47% 40% 40% 40% 35% 37% 30% 25% 22% 20% 10% 0% Mass Power 1 Cost Schedule 2 1 2 Cost & Schedule Growth for Planetary Missions is Significantly Less Note: 1) As measured from Current Best Estimate, not including reserves 2) As measured from baseline estimate, including reserves 21
  • 22. Correlation Between Cost and Schedule Growth Indicates that Schedule Growth Has Strong Influence on Cost Growth 140% Development Cost Growth from Phase B Start 120% % Cost Growth = 1.4775 * % Schedule Growth 100% R2 = 0.6166 80% 60% 40% 20% 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Schedule Growth from Phase B Start 22
  • 23. Payload Mass and Cost Growth Significantly Greater than Spacecraft Mass & Cost Growth 120% Average Percent Growth from Phase B Start Payload 101% 100% Spacecraft 80% 60% 60% 44% 40% 33% 20% 0% Mass Cost 1 1 Data Indicated Payload Resource has Greater Uncertainty than Spacecraft Note: 1) As measured from Current Best Estimate, not including reserves 23
  • 24. Cumulative Cost Distribution Shows Wide Distribution of Payload Cost Growth vs. Spacecraft Cost Growth 100% 90% Cumulative Distribution for All Data Points 80% 70% Payload Cost Growth has 60% Much Greater Variance than Spacecraft Growth 50% Spacecraft Cost Growth 40% Payload Cost Growth 30% 20% 10% 0% -25% 0% 25% 50% 75% 100% 125% 150% 175% 200% 225% 250% Cost Growth from Phase B Start over Initial Estimate without Cost Reserve 24
  • 25. Instrument Payload Mass/Cost Growth Data Over Time Also Indicates Payload Cost Lags Payload Maturity 120% Percent Growth over CBE w/o reserves 100% Payload Mass 101% Payload Cost 80% 60% 60% 43% 40% 31% 37% 20% 18% 0% 0% 0% Phase B Start PDR CDR Launch Payload Cost Significantly Lags Payload Design Maturity 25
  • 26. Range of Mass Growth at Instrument & Subsystem Level Can Provide Guidance for Initial KDP-B Cost Estimates Typical Mass Reserve Instruments Design Guidance 30% Propulsion Below Mean Above Mean ADCS Thermal Subsystem Min Mean Max Median Comm Instrument 11% 60% 202% 51% Propulsion -73% 10% 69% 18% ADCS -21% 29% 108% 24% Thermal -36% 77% 269% 58% C&DH Comm -55% 5% 76% 7% C&DH -37% 16% 104% 6% Power -37% 45% 103% 40% Power Structure & Mech -19% 57% 142% 60% Struct & Mech -75% -50% -25% 0% 25% 50% 75% 100% 125% 150% 175% 200% 225% 250% 275% Range for Mass Distributions Range of Mass Growth is Large and Exceeds Typical Industry Guidance 26
  • 27. Agenda • Background/Overview • Database Description • Resource Growth – Mass, Power, Cost & Schedule Trends • Findings – Progression from milestones – Comparison of mission types – Payload vs. Spacecraft comparisons • Potential Considerations 27
  • 28. Potential Considerations • For Project Managers – Mass and power reserve guidelines for spacecraft and payload could be increased to be more consistent with historical averages – Schedule growth seems to be a key factor in controlling cost growth – More emphasis could be placed on early payload designs as there is much greater uncertainty in the payload development than the spacecraft • For Cost Analysts – Wider ranges of input parameters could be used to provide more robust initial cost estimates which can address uncertainty in early design 28
  • 29. References 1) Freaner C., Bitten R., Bearden D., and Emmons D., “An Assessment of the Inherent Optimism in Early Conceptual Designs and its Effect on Cost and Schedule Growth”, 2008 SSCAG/SCAF/EACE Joint International Conference, Noordwijk, The Netherlands, 15-16 May 2008. 2) Bitten R., Emmons D., Freaner C., “Using Historical NASA Cost and Schedule Growth to Set Future Program and Project Reserve Guidelines”, IEEE Aerospace Conference, Big Sky, Montana, March 3-10, 2007. 3) Bitten R.E., “Determining When A Mission Is "Outside The Box": Guidelines For A Cost- Constrained Environment”, 6th IAA International Low Cost Planetary Conference, October 11- 13, 2005. 4) Bitten R.E., Bearden D.A., Lao N.Y. and Park, T.H., “The Effect of Schedule Constraints on the Success of Planetary Missions”, 5th IAA International Conference on Low-Cost Planetary Missions, 24 September 2003 5) Emmons D., “A Quantitative Approach to Independent Schedule Estimates of Planetary & Earth-orbiting Missions”, 2008 ISPA-SCEA Joint International Conference, Netherlands, 12-14 May 2008 29