SlideShare a Scribd company logo
1 of 48
Download to read offline
Mitigating the Adverse Impact
                   of
         Technology Maturity
        Project Management Challenge 2007
Fourth Annual NASA Project Management Conference

                  February 6-7, 2007

                      James W. Bilbro
   Assistant Director for Technology/Chief Technologist
         George C. Marshall Space Flight Center
Mitigating the Adverse Impact of Technology Maturity




 • Why do Technology Assessment?




                                                       2
Mitigating the Adverse Impact of Technology Maturity

      Knowledge Building for Development
      of New Products*

                   Technologies        Design            Production can meet
                   match               performs as       cost, schedule, and
                   requirements        expected          quality targets
                                  1              2   3
Commercial
Knowledge Points

                      Program launch
                                                            1
DOD
Knowledge Points                                                  2
                                                                               3


   *GAO
                                                                                   3
Mitigating the Adverse Impact of Technology Maturity

  Timing of Match Between Customer
  Expectations and Developer Resources*


        Customer
       expectations




        Developer
        resources

                        Launch point for    Launch point for
                        successful cases    problematic cases


*GAO
                                                                4
Mitigating the Adverse Impact of Technology Maturity

  Development of the Radio
  Frequency Countermeasures System*
                        F-15 and B-1                   Match
                     requirements added               achieved


       Customer’s
       expectations
                                           Customer   Developer reports
               Developer proposes
                                            says no   197% cost increase
               additional resources
                                                      & 15-month delay
       Developer’s
        resources

                                          Program
                                            start
*GAO
                                                                           5
Mitigating the Adverse Impact of Technology Maturity


                NPR 7120.5d Requirements

            KDP A – Transition from Pre-Phase A to Phase A:
Requires an assessment of potential technology needs versus current
and planned technology readiness levels, as well as potential
opportunities to use commercial, academic, and other government
agency sources of technology. Included as part of the draft integrated
baseline.
              KDP B – Transition from Phase A to Phase B:
Requires a Technology Development plan identifying technologies to
be developed, heritage systems to be modified, alternate paths to be
pursued, fall back positions and corresponding performance de-
scopes, milestones, metrics and key decision points. Incorporated in
the preliminary Project Plan.
             KDP C – Transition from Phase B to Phase C/D:
Technology Readiness Assessment Report (TRAR) demonstrating
that all systems, subsystems and components have achieved a level
of technological maturity with demonstrated evidence of qualification
in a relevant environment.
                                                                         6
Mitigating the Adverse Impact of Technology Maturity




            And besides that –
        It’s the right thing to do!




                                                       7
Mitigating the Adverse Impact of Technology Maturity


    How do you perform a Technology Assessment (TA)?

•    There are many ways to perform Technology Assessments.

•    The ensuing material describes one method that is essentially
     based on fundamental systems engineering principles.




                                                                     8
Mitigating the Adverse Impact of Technology Maturity



What is Technology Assessment (TA)?

•   It is a two-step process that involves:

     – The determination of the Technology Readiness Levels (TRLs) (i.e.
       current level of maturity).

     – The determination of the Advancement Degree of Difficulty (AD2) (i.e.,
       what is required to advance a technology from its current TRL to what is
       required for infusion into the program/project at an acceptable level of
       risk.)




                                                                                  9
Mitigating the Adverse Impact of Technology Maturity



What is a Technology Readiness Level (TRL)?

•   At its most basic, the TRL is a description of the maturity of a given
    technology defined by what has been done, under what conditions
    at a given point in time.

•   However, the TRL is just one part of the equation – and the initial
    assessment establishes the baseline for the program/project.

•   The more fundamental question is what is required (in terms of cost,
    schedule and risk to move the technology from where it is to where it
    needs to be.



                                                                             10
Mitigating the Adverse Impact of Technology Maturity

What is an Advancement Degree of Difficulty (AD2)?

•   AD2 is a method of dealing with the other aspects beyond TRL, it is
    the description of what is required to move a technology from one
    TRL to another.
•   It takes into account:
     – Design Readiness Level
     – Manufacturing Readiness Level (MRL)
     – Integration Readiness Level (IRL)
     – Software Readiness Level (SRL)
     – Operational Readiness Level
     – Human Readiness Levels (HRL) (skills)
     – Capability Readiness Levels (CRL) (people and tools)
     – organizational aspects (ability of an organization to reproduce existing
       technology)
     – Etc.

                                                                                  11
Mitigating the Adverse Impact of Technology Maturity


                    Technology Assessment (TA)

•   It is extremely important that a Technology Assessment process be
    defined at the beginning of the program/project.

•   It is also extremely important that it be performed at the earliest
    possible stage (concept development) and repeated periodically
    throughout the program/project through PDR.

•   Inputs to the process will vary in level of detail according to the
    phase of the program/project in which it is conducted.




                                                                          12
Mitigating the Adverse Impact of Technology Maturity


                     Technology Assessment (TA)

•   Even though there is a lack of detail in pre-phase A, the TA will drive
    out the major critical technological advancements required.

•   Therefore, at the beginning of pre-phase A, the following should be
    provided:
     – Refinement of Technology Readiness Level Definitions
     – Definition of Advancement Degree of Difficulty Process
     – Definition of terms to be used in the assessment process
     – Establishment of meaningful evaluation criteria and metrics that will
       allow for clear identification of gaps and shortfalls in performance.
     – Establishment of the TA team
     – Establishment of an independent TA review team.



                                                                               13
Mitigating the Adverse Impact of Technology Maturity



              Technology Assessment (TA)

• The complete TA should be repeated just prior to
  SRR to:
   – establish the baseline maturity of the design and
   – To provide the material necessary to prepare the
     Technology Development Plan
• A TRL assessment should be completed just prior to
  PDR to provide the material necessary to prepare the
  Technology Readiness Assessment Report



                                                          14
Mitigating the Adverse Impact of Technology Maturity
               Technology Assessment
                     Start with the WBS

                       Crew Launch
                        Crew Launch         136905
                         Vehicle
                          Vehicle
                                     1.3



                          Launch
                           Launch
                          Vehicle
                                                136905.08
                           Vehicle
                                    1.3.8




                       Upper Stage              136905.08.05
                        Upper Stage
                                 1.3.8.2




 136905.08.05.06       136905.08.05.07      136905.08.05.08      136905.08.05.09
   FS RCS                  TVCS               Avionics             Software
    FS RCS                  TVCS               Avionics             Software
         1.3.8.2.6              1.3.8.2.7            1.3.8.2.8            1.3.8.2.9


                                                                                      15
Mitigating the Adverse Impact of Technology Maturity

          The Technology Assessment Process

Identify systems, subsystems        Assign TRL to all          Assign TRL to
and components per the             components based            subsystems based on
hierarchical product                on assessment of           lowest TRL of
breakdown of the WBS                maturity                   components + TRL
                                                               state of integration


                                                               Assign TRL to
                                 Identify all components,      Systems based on
  Baseline Technological        subsystems and systems
  Maturity Assessment                                          lowest TRL of
                                that are at lower TRL’s than   subsystems + TRL
                                required by the program        state of integration



                               Perform AD2 on all identified
                                components, subsystems and
                                systemsthat are below
                                requisite maturity level.



                               Technology Development Plan
                                         Cost Plan
                                     Schedule Plan
                                      Risk Assessment
                                                                                      16
Mitigating the Adverse Impact of Technology Maturity




Architectural Study & Technology Assessment Interaction


Requirements   Concepts     Architecture Studies      System Design



                            TRL/AD2 Assessment


                              Technology Maturation




                                                                      17
Mitigating the Adverse Impact of Technology Maturity
             TRL Descriptions



System Test, Launch           Actual system “flight proven” through successful
& Operations          TRL 9
                              mission operations
                      TRL 8   Actual system completed and “flight qualified” through
System/Subsystem              test and demonstration (Ground or Flight)
Development
                      TRL 7   System prototype demonstration in a space
                              environment
Technology
Demonstration         TRL 6   System/subsystem model or prototype demonstration
                              in a relevant environment (Ground or Space)
                      TRL 5   Component and/or breadboard validation in relevant
Technology                    environment
Development
                      TRL 4   Component and/or breadboard validation in laboratory
                              environment
Research to Prove
Feasibility           TRL 3   Analytical and experimental critical function and/or
                              characteristic proof-of-concept
Basic Technology      TRL 2   Technology concept and/or application formulated
Research

                      TRL 1   Basic principles observed and reported




                                                                                       18
Mitigating the Adverse Impact of Technology Maturity


                                              TRL Descriptions
Technology
 Readiness             Definition             Hardware Description              Software Description                     Exit Criteria
Level - (TRL)
                                                                             Scientific knowledge
                                          Scientific knowledge
                                                                             generated underpinning basic Peer reviewed publication of
                Basic principles observed generated underpinning
     1                                                                       properties of software       research underlying the
                and reported              hardware technology
                                                                             architecture and             proposed concept/application
                                          concepts/applications.
                                                                             mathematical formulation.
                                                                             Invention begins, practical
                                          Invention begins, practical        application is identified but is
                                          application is identified but is   speculative, no experimental       Documented description of
                Technology concept or     speculative, no experimental       proof or detailed analysis is      the application/concept that
     2
                application formulated    proof or detailed analysis is      available to support the           addresses feasibility and
                                          available to support the           conjecture. Underlying             benefit
                                          conjecture.                        Algorithms are clarified and
                                                                             documented.
                                           Analytical studies place the
                                                                             Development of limited
                Analytical and/or          technology in an appropriate                                         Documented
                                                                             functionality to validate critical
                experimental critical      context and laboratory                                               analytical/experimental results
     3                                                                       properties and predictions
                function or characteristic demonstrations, modeling and                                         validating predicitions of key
                                                                             using non-integrated software
                proof-of-concept           simulation validate analytical                                       parameters
                                                                             components
                                           prediction.




                                                                                                                                                  19
Mitigating the Adverse Impact of Technology Maturity

                    TRL Descriptions - continued
                               A low fidelity                     Key, functionally critical,
                               system/component                   software components are
                               breadboard is built and            integrated, and functionally   Documented test performance
    Component or               operated to demonstrate basic      validated, to establish        demonstrating agreement with
4   breadboard validation in   functionality and critical test    interoperability and begin     analytical predictions.
    laboratory                 environments and associated        architecture development.      Documented definition of
                               performance predicitions are       Relevant Evironments           relevant environment.
                               defined relative to the final      defined and performance in
                               operating environment.             this environment predicted.


                               A mid-level fidelity
                                                                  End to End Software
                               system/component
                                                                  elements implemented and
                               brassboard is built and
                                                                  interfaced with existing
                               operated to demonstrate
                                                                  systems conforming to target
                               overall performance in a                                          Documented test performance
                                                                  environment, including the
    Component or               simulated operational                                             demonstrating agreement with
                                                                  target o software
5   breadboard validation in   environment with realistic                                        analytical predictions.
                                                                  environment. End to End
    a relevant environment     support elements that                                             Documented definition of
                                                                  Software System, Tested in
                               demonstrates overall                                              scaling requirements
                                                                  Relevant Environment, Meets
                               performance in critical areas.
                                                                  Predicted Performance.
                               Performance predictions are
                                                                  Operational Environment
                               made for subsequent
                                                                  Performance Predicted.
                               development phases.

                               A high-fidelity
                               system/component prototype
                                                                  Prototype software partially
    System/subsystem           that adequately addresses all
                                                                  integrated with existing       Documented test performance
    model or prototype         critical scaling issues is built
6                                                                 hardware/software sytems       demonstrating agreement with
    demonstration in a         and operated in a relevant
                                                                  and demonstrated on full-      analytical predictions
    relevant environment       environment to demonstrate
                                                                  scale realistic problems.
                               operations under critical
                               environmental conditions.

                                                                                                                                20
Mitigating the Adverse Impact of Technology Maturity

                           TRL Descriptions - continued


                             A high fidelity engineering unit
                             that adequately addresses all
                             critical scaling issues is built   Prototype software is fully
                             and operated in a relevant         integrated with operational    Documented test performance
    System prototype
7                            environment to demonstrate         harware/software sytems        demonstrating agreement with
    demonstration in space
                             performance in the actual          demonstrating operational      analytical predictions
                             operational environment and        feasibility.
                             platform (ground, airborne or
                             space).
                            The final product in its final      The final product in its final
                            configuration is successfully       configuration is successfully
    Actual system completed
                            demonstrated through test and       [demonstrated] through test
    and flight qualified                                                                       Documented test performance
8                           analysis for its intended           and analysis for its intended
    through test and                                                                           verifying analytical predictions
                            operational environment and         operational environment and
    demonstration
                            platform (ground, airborne or       platform (ground, airborne or
                            space).                             space).
    Actual system flight
                             The final product is               The final product is
    proven through                                                                             Documented mission
9                            successfully operated in an        successfully operated in an
    successful mission                                                                         operational results
                             actual mission.                    actual mission.
    operations




                                                                                                                                  21
Mitigating the Adverse Impact of Technology Maturity
                       Definitions
•   Proof of Concept: (TRL 3)
    Analytical and experimental demonstration of hardware/software concepts
    that may or may not be incorporated into subsequent development and/or
    operational units.

•   Breadboard: (TRL 4)
    A low fidelity unit that demonstrates function only, without respect to form or
    fit in the case of hardware, or platform in the case of software. It often uses
    commercial and/or ad hoc components and is not intended to provide
    definitive information regarding operational performance.

•   Developmental Model/ Developmental Test Model: (TRL 4)
    Any of a series of units built to evaluate various aspects of form, fit, function
    or any combination thereof. In general these units may have some high
    fidelity aspects but overall will be in the breadboard category.

•   Brassboard: (TRL 5 – TRL6)
    A mid-fidelity functional unit that typically tries to make use of as much
    operational hardware/software as possible and begins to address scaling
    issues associated with the operational system. It does not have the
    engineering pedigree in all aspects, but is structured to be able to operate in
    simulated operational environments in order to assess performance of
    critical functions.                                                                 22
Mitigating the Adverse Impact of Technology Maturity
                       Definitions - continued

•   Mass Model: (TRL 5)
    Nonfunctional hardware that demonstrates form and/or fit for use in
    interface testing, handling, and modal anchoring.

•   Subscale model: (TRL 5 – TRL7)
    Hardware demonstrated in subscale to reduce cost and address critical
    aspects of the final system. If done at a scale that is adequate to address
    final system performance issue it may become the prototype.

•   Proof Model: (TRL 6)
    Hardware built for functional validation up to the breaking point, usually
    associated with fluid system over pressure, vibration, force loads,
    environmental extremes, and other mechanical stresses.




                                                                                  23
Mitigating the Adverse Impact of Technology Maturity
                   Definitions - continued
•   Proto-type Unit: (TRL 6 – TRL 7)
    The proto-type unit demonstrates form (shape and interfaces), fit (must be at
    a scale to adequately address critical full size issues), and function (full
    performance capability) of the final hardware. It can be considered as the first
    Engineering Model. It does not have the engineering pedigree or data to
    support its use in environments outside of a controlled laboratory environment
    – except for instances where a specific environment is required to enable the
    functional operation including in-space. It is to the maximum extent possible
    identical to flight hardware/software and is built to test the manufacturing and
    testing processes at a scale that is appropriate to address critical full scale
    issues.

•   Engineering Model: (TRL 6 – TRL 8)
    A full scale high-fidelity unit that demonstrates critical aspects of the
    engineering processes involved in the development of the operational unit. It
    demonstrates function, form, fit or any combination thereof at a scale that is
    deemed to be representative of the final product operating in its operational
    environment. Engineering test units are intended to closely resemble the final
    product (hardware/software) to the maximum extent possible and are built
    and tested so as to establish confidence that the design will function in the
    expected environments. In some cases, the engineering unit will become the
    protoflight or final product, assuming proper traceability has been exercised
    over the components and hardware handling.
                                                                                       24
Mitigating the Adverse Impact of Technology Maturity
                   Definitions - continued
•   Flight Qualification Unit: (TRL 8)
    Flight hardware that is tested to the levels that demonstrate the desired
    margins, particularly for exposing fatigue stress., typically 20-30%.
    Sometimes this means testing to failure. This unit is never flown. Key
    overtest levels are usually +6db above maximum expected for 3 minutes in all
    axes for shock, acoustic, and vibration; thermal vacuum 10C beyond
    acceptance for 6 cycles, and 1.25 times static load for unmanned flight.

•   Protoflight Unit: (TRL 8 – TRL 9)
    Hardware built for the flight mission that includes the lessons learned from the
    Engineering Model but where no Qualification model was built to reduce cost.
    It is however tested to enhanced environmental acceptance levels. It
    becomes the mission flight article. A higher risk tolerance is accepted as a
    tradeoff. Key protoflight overtest levels are usually +3db for shock, vibration,
    and acoustic; 5C beyond acceptance levels for thermal vacuum tests.

•   Flight Qualified Unit: (TRL8 – TRL9)
    Actual flight hardware/software that has been through acceptance testing.
    Acceptance test levels are designed to demonstrate flight-worthiness, to
    screen for infant failures without degrading performance. The levels are
    typically less than anticipated levels.

                                                                                       25
Mitigating the Adverse Impact of Technology Maturity
                      Definitions - continued




•   Flight Proven: (TRL 9)
    Hardware/software that is identical to hardware/software that has been
    successfully operated in a space mission and that is being used in an
    identical architecture under identical operational environments.




                                                                             26
Mitigating the Adverse Impact of Technology Maturity
                        Definitions - continued
•   Laboratory Environment:
    An environment that does not address in any manner the environment to be
    encountered by the system, subsystem or component (hardware or software)
    during its intended operation. Tests in a laboratory environment are solely for
    the purpose of demonstrating the underlying principles of technical
    performance (functions) without respect to the impact of environment.

•   Relevant Environment:
    Not all systems, subsystems and/or components need to be operated in the
    operational environment in order to satisfactorily address performance margin
    requirements. Consequently, the relevant environment is the specific subset
    of the operational environment that is required to demonstrate critical “at risk”
    aspects of the final product performance in an operational environment.

•   Operational Environment:
    The environment in which the final product will be operated. In the case of
    spaceflight hardware/software it is space. In the case of ground based or
    airborne systems that are not directed toward space flight it will be the
    environments defined by the scope of operations. For software, the
    environment will be defined by the operational platform and software
    operating system.
                                                                                        27
Mitigating the Adverse Impact of Technology Maturity


               Form Fit & Function Definitions
                                                                 Flight Unit
                           Mass Model                         Proto-flight Unit
          Form           *                               **   Qualification Unit
                                                              Engineering Model


      100%
                                                 *Prototype

                                        *Brassboard


                             Fit
                                         *Subscale
                                         unitSu

 Wind Tunnel
   Model   *      *                 Breadboard                Function
                 Proof of concept            *
                                             100%


                                                                                   28
Mitigating the Adverse Impact of Technology Maturity

              TRL Assessment Thought Process
Has an identical unit been successfully operated/launched in identical                  YES   TRL 9
configuration/environment?
                                        NO

Has an identical unit been successfully operated in space or launch in a different      YES   TRL5
configuration/ system architecture? If so then this initially drops to TRL 5 until
                                                                                              ?
differences are evaluated.
                                        NO


Has an identical unit been flight qualified, but not yet operated in space or launch?   YES   TRL 8

                                         NO


Has a prototype unit (or one similar enough to be considered a prototype) been          YES
successfully operated in space or launch?                                                     TRL 7

                                         NO


Has a prototype unit (or one similar enough to be considered a prototype) been          YES
demonstrated in a relevant environment?                                                       TRL 6

                                         NO
                                                                                                      29
Mitigating the Adverse Impact of Technology Maturity

          TRL Assessment Thought Process


Has a breadboard unit been demonstrated in a relevant environment?     YES   TRL 5
                                       NO

Has a breadboard unit been demonstrated in a laboratory environment?   YES   TRL 4
                                       NO

Has analytical and experimental proof-of-concept been demonstrated?    YES   TRL 3

                                       NO

Has concept or application been formulated?                            YES   TRL 2
                                        NO

Have basic principles been observed and reported?                      YES   TRL 1

                                        NO
      RETHINK YOUR POSITION REGARDING THIS TECHNOLOGY!


                                                                                     30
Mitigating the Adverse Impact of Technology Maturity

                               TRL Assessment Matrix

                                          TRL Assessment
                                                     Demonstration Units                                                                                Environment                                                                           Unit Description
 R   Red = Below TRL 3
 Y   Yellow = TRL 3,4 & 5




                                                                                                                                                                                                                 Space/Launch Operation
                                                                                                                                        Lab ora tory Env iron men t
 G   Green = TRL 6 and above




                                                                                                                                                                      Relevant Environment
 W   White = Unknown




                                                                                                                                                                                             Space Environment
                                                                              Developmental Model
 X   Exists




                                                                                                                                                                                                                                                                          Appropriate Scale
                                                                                                                  Flig ht Qua lifie d




                                                                                                                                                                                                                                                                                              Overall TRL
                                                    Breadboard

                                                                 Brassboard


                                                                                                    Pro toty pe




                                                                                                                                                                                                                                                               Function
                                          Concept




                                                                                                                                                                                                                                              Form
                                                                                                                                                                                                                                                         Fit
     1.0 System
       1.1 Subsystem X
          1.1.1 Mechanical Components
          1.1.2 Mechanical Systems
          1.1.3 Electrical Components                                                                 X                                                                                      X                                                X          X     X
          1.1.4 Electrical Systems
          1.1.5 Control Systems
          1.1.6 Thermal Systems                                                                                                         X                                                                                                 X          X
          1.1.7 Fluid Systems                       X
          1.1.8 Optical Systems
          1.1.9 Electro-optical Systems
          1.1.10 Software Systems
          1.1.11 Mechanisms               X
          1.1.12 Integration
      1.2 Subsystem Y
        1.2.1 Mechanical Components



                                                                                                                                                                                                                                                                                                            31
Mitigating the Adverse Impact of Technology Maturity

                                          TRL Calcualtor

            Main Menu                             TRL Calculator                         Release Notes
                                                                                                                                                  1

          AFRL Hardware and Software Transition Readiness Level Calculator, Version 2.2

     This worksheet summarizes the TRL Calculator results. It displays the TRL, MRL, and PRL computed elsewhere. You may select the technology types
     and TRL categories (elements) you wish to include here or on the Calculator worksheet. Choose Hardware, Software, or Both to fit your program. If
     you omit a category of readiness level, (TRL, MRL, or PRL) that calculation is removed from the summary. The box in front of each readiness level
     element is checked when that category is included in the summary.
     You can enter program identification information here, too.
     TRL documentation including discussions of TRL, MRL, and PRL is available
     from the Main Menu.


                           Include Hardware Only
                           Include Software Only
        X                  Include Hardware and Software


       X            Use

                    Omit
                               Technology Readiness Level


       X            Use

                    Omit
                             Manufacturing Readiness Level


       X            Use

                    Omit
                             Programmatic Readiness Level

                                                         Here you can change the default values the spreadsheet uses to determine which color to award
        Green / Yellow set points:                       at a given level of question completion. System defaults are 100% for Green, and 67%
     for Yellow. You can change these set points to any value above 75% for Green, and any value from 50% to 85% for Yellow; however, the Yellow
     set point will always be at least 15% below the Green set point. Use the spinners to set your desired values. The defaults kick in if you try to set
     a value less than the minimum values of 75% for Green and 50% for Yellow. Start with the "Up" arrow to change defaults.


        Green set point is now at:                            100%                         Yellow set point is now at:                        67%




                                                                                                                                                            32
Mitigating the Adverse Impact of Technology Maturity

                                          TRL Calculator Example



     WS
      B                      Elem N e
                                 ent am                   AssessedArea                   TR Score
                                                                                           L                  M LScore
                                                                                                               R
                                                       a) Prim Structure
                                                               ary                   5      6         7   5
                                                       b) Secondary Structure        5      6         7   5      6
136905.08.05.03   Structure &Thermal
                                                       c) Flight Separation System   5     6, 7       8   5      7
                                                       d) TPS                        5     6, 7       8   6      7
                                                       a) D &Lines
                                                            ucts                     5      6         7   5      6
136905.08.05.04   M Propulsion System
                   ain
                                                       b) Valves &Actuators          5      6         7   5      6
136905.08.05.05   U R
                   S eaction C  ontrol System                                        5     6, 7       8   5      7
136905.08.05.06   1st Stage Reaction C ontrol System                                 5     6, 7       8   5      7
                                                       a) Actuators                  5      6         7   5      6
136905.08.05.07   Thrust Vector Control
                                                       b) H ydraulic Pow System
                                                                        er     s     4     5, 6       7   5      6
136905.08.05.08   Avionics                             a) C H
                                                            &D                       4     5, 6       7   5      6
                                                       b) G CH are
                                                            N ardw                   5      6         7   6
                                                       c) Electrical Power           6      7             6      7
                                                       d) Sensors                    6      7             6      7
136905.08.05.09   Flight Softw System
                              are                                                    4      5         6   4      5
136905.08.05.10   C ponent Integration &Test
                    om                                                                 N Applicable
                                                                                        ot
136905.08.05.11   Logistics Support Infrastructure     GSE                           6      7         8   6      7
136905.08.05.12   M anufacturingandAssem     bly       Tooling                       5     6, 7       8   6      7


                                                                                                                         33
Mitigating the Adverse Impact of Technology Maturity

                         TRL Revised Questions
          1     Critical functions and associated subsystems and components identified?
          2     Relevant environments finalized?
          3     Scaling requirements defined & documented?
          4     Critical subsystems and components breadboards/brassboards identified and designed?
TRL 5




          5     Subsystem/component breadboards/brassboards built?
          6     Facilities, GSE, STE available to support testing in a relevant environment?
          7     M&S performance predictions completed?
          8     System level performance predictions made for subsequent development phases?
          9     Breadboards/brassboards successfully demonstrated in a relevant environment?
         10     Successful demonstration documented along with scaling requirements?

         1      System requirements finalized?
         2      Operating environment definition finalized?
                Subset of relevant environments identified that address key aspects of the final operating
         3      environment?
         4      M&S used to simulate system performance in an operational environment?
                M&S used to simulate system/subsystem engineering model/protype performance in the
         5      relevant environment?
TRL 6




         6      External interfaces baselined?
         7      Scaling requirements finalized?
                Facilities, GSE, STE available to support system/subsystem engineering model/prototype
         8      testing in the relevant environment?
         9      System/subsystem engineering model/prototype that adequately addresses critical scaling
                System/subsystem engineering model/prototype that adequately addresses critical scaling
         10     issues tested in the relevant environment?
         11     Analysis of test results verify performance predictions for relevant environment?
         12     Test performance demonstrating agreement with performance predictions documented?

                                                                                                             34
Mitigating the Adverse Impact of Technology Maturity

    Advancement Degree of Difficulty AD2


    Degree of Difficulty                             Description
                           0% Development Risk - Exists with no or only minor
             9                 modifications being required. A single development
                               approach is adequate.
                           10% Development Risk - Exists but requires major
             8                 modifications. A single development approach is
                               adequate.
                           20% Development Risk - Requires new development well
             7                 within the experience base. A single development
                               approach is adequate.
                           30% Development Risk - Requires new development but
                               similarity to existing experience is sufficient to warrant
             6                 comparison across the board. A single development
                               approach can be taken with a high degree of confidence
                               for success.
                           40% Development Risk - Requires new development but
                               similarity to existing experience is sufficient to warrant
             5                 comparison in all critical areas. Dual development
                               approaches should be pursued to provide a high degree
                               of confidence for success.



                                                                                            35
Mitigating the Adverse Impact of Technology Maturity

Advancement Degree of Difficulty AD2 - continued


                        50% Development Risk - Requires new development but
                        similarity to existing experience is sufficient to warrant
                        comparison in only a subset of critical areas. Dual
         4              development approaches should be pursued in order to
                        achieve a moderate degree of confidence for success.
                        (Desired performance can be achieved in subsequent block
                        upgrades with high degree of confidence.)

                        60% Development Risk - Requires new development but
                        similarity to existing experience is sufficient to warrant
         3
                        comparison in only a subset of critical areas. Multiple
                        development routes must be pursued.

                        80% Development Risk - Requires new development where
                        similarity to existing experience base can be defined only in
         2
                        the broadest sense. Multiple development routes must be
                        pursued.

                        100% Development Risk - Requires new development
                        outside of any existing experience base. No viable
         1              approaches exist that can be pursued with any degree of
                        confidence. Basic research in key areas needed before
                        feasible approaches can be defined.


                                                                                        36
Mitigating the Adverse Impact of Technology Maturity

Design and Analysis

•   Do the necessary data bases exist and if not, what level of development is
    required to produce them?
•   Do the necessary design methods exist and if not, what level of development is
    required to produce them?
•   Do the necessary design tools exist and if not, what level of development is
    required to produce them?
•   Do the necessary analytical methods exist and if not, what level of development
    is required to produce them?
•   Do the necessary analysis tools exist and if not, what level of development is
    required to produce them?
•   Do the appropriate models with sufficient accuracy exist and if not, what level of
    development is required to produce them?
•   Do the available personnel have the appropriate skills and if not, what level of
    development is required to acquire them?
•   Has the design been optimized for manufacturability and if not, what level of
    development is required to optimize it?
•   Has the design been optimized for testability and if not, what level of
    development is required to optimize it?




                                                                                         37
Mitigating the Adverse Impact of Technology Maturity

Manufacturing

•   Do the necessary materials exist and if not, what level of development is
    required to produce them?
•   Do the necessary manufacturing facilities exist and if not, what level of
    development is required to produce them?
•   Do the necessary manufacturing machines exist and if not, what level of
    development is required to produce them?
•   Does the necessary manufacturing tooling exist and if not, what level of
    development is required to produce it?
•   Does the necessary metrology exist and if not, what level of development is
    required to produce it?
•   Does the necessary manufacturing software exist and if not, what level of
    development is required to produce it?
•   Do the available personnel have the appropriate skills and if not, what level of
    development is required to acquire them?
•   Has the design been optimized for manufacturability and if not, what level of
    development is required to optimize it?
•   Has the manufacturing process flow been optimized and if not, what level of
    development is required to optimize it?
•   Has the manufacturing process variability been minimized and if not, what level
    of development is required to optimize it?



                                                                                       38
Mitigating the Adverse Impact of Technology Maturity

Manufacturing – continued

•   Has the design been optimized for reproducibility and if not, what level of
    development is required to optimize it?
•   Has the design been optimized for assembly & alignment and if not, what level
    of development is required to optimize it?
•   Has the design been optimized for integration at the component, subsystem
    and system level and if not, what level of development is required to optimize
    it?
•   Are breadboards required and if so what level of development is required to
    produce them?
•   Are brassboards required and if so what level of development is required to
    produce them?
•   Are subscale models required and if so what level of development is required
    to produce them?
•   Are engineering models required and if so what level of development is
    required to produce them?
•   Are prototypes required and if so what level of development is required to
    produce them?
•   Are breadboards, brassboards, engineering models and prototypes at the
    appropriate scale and fidelity for what they are to demonstrate, and if not what
    level of development is required to modify them accordingly?
•   Are Qualification models required and if so what level of development is
    required to produce them?

                                                                                       39
Mitigating the Adverse Impact of Technology Maturity

Operations

•   Has the design been optimized for maintainability and servicing and if not,
    what level of development is required to optimize it?
•   Has the design been optimized for minimum life cycle cost and if not, what
    level of development is required to optimize it?
•   Has the design been optimized for minimum annual recurring / operational cost
    and if not, what level of development is required to optimize it?
•   Has the design been optimized for reliability and if not, what level of
    development is required to optimize it?
•   Has the design been optimized for availability {ratio of operating time
    (reliability) to downtime (maintainability/ supportability)} and if not, what level
    of development is required to optimize it?
•   Do the necessary ground systems facilities & infrastructure exist and if not,
    what level of development is required to produce them?
•   Does the necessary ground systems equipment exist and if not, what level of
    development is required to produce it?
•   Does the necessary ground systems software exist and if not, what level of
    development is required to produce it?
•   Do the available personnel have the appropriate skills and if not, what level of
    development is required to acquire them?




                                                                                          40
Mitigating the Adverse Impact of Technology Maturity

Test & Evaluation

•   Do the necessary test facilities exist and if not, what level of development is
    required to produce them?
•   Does the necessary test equipment exist and if not, what level of development
    is required to produce them?
•   Does the necessary test tooling exist and if not, what level of development is
    required to produce it?
•   Do the necessary test measurement systems exist and if not, what level of
    development is required to produce them?
•   Does the necessary software exist and if not, what level of development is
    required to produce it?
•   Do the available personnel have the appropriate skills and if not, what level of
    development is required to acquire them?
•   Has the design been optimized for testability and if not, what level of
    development is required to optimize it?
•   Are breadboards required to be tested and if so what level of development is
    required to test them?
•   Are brassboards required to be tested and if so what level of development is
    required to test them?




                                                                                       41
Mitigating the Adverse Impact of Technology Maturity


Test & Evaluation – continued

•   Are subscale models required to be tested and if so what level of development
    is required to test them?
•   Are engineering models required to be tested and if so what level of
    development is required to test them?
•   Are prototypes required to be tested and if so what level of development is
    required to test them?
•   Are Qualification models required to be tested and if so what level of
    development is required to test them?




                                                                                    42
Mitigating the Adverse Impact of Technology Maturity

                                         AD2 Automated Format
                                                                                                                   2/7/07 11:45 AM                                      12/3/2006
Advancement Degree of Difficulty - Questions

                                                                                                                               Title:
                                                                                                                         Evaluator:
WBS Product Hierarchy   Name           WBS#, use multiple decimal points

      System

      Subsystem

      Component



                          Only Answer Those Questions That Apply


                                             Technical Deg
         Schedule              Cost           Of Difficulty            Design and Analysis                                              Comments (42 character limit)
                                                                       Do the necessary data bases exist and if not, what level of
                    4                                                  development is required to produce them?
                                                                       Do the necessary design methods exist and if not, what
                                                                       level of development is required to produce them?
                                                                       Do the necessary design tools exist and if not, what level of
                                                                       development is required to produce them?
                                                                       Do the necessary analytical methods exist and if not, what
                                                                       level of development is required to produce them?
                                                                       Do the necessary analysis tools exist and if not, what level
                                                                       of development is required to produce them?
                                                                       Do the appropriate models with sufficient accuracy exist and
                                                                       if not, what level of development is required to produce
                                                                       them?

                                                                       Do the available personnel have the appropriate skills and if
                                                                       not, what level of development is required to acquire them?

                                                                       Has the design been optimized for manufacturability and if
                                                                       not, what level of development is required to optimize it?
                                                                       Has the design been optimized for testability and if not,
                                                                       what level of development is required to optimize it?




                                                                                                                                                                                    43
Mitigating the Adverse Impact of Technology Maturity


                                                                                                                                                                                  AD2 Example

                    Criteria               TRL                                    Design & Analysis                                                                                                                                                                      Manufacturing                                                                                                                                                                                       Operability                                                                                                             Test & Evaluation                                                                   Demonstration Units




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                          Overall Qualitative Assessment
  R   High Risk =1-4

                                                                                              Analytical Methods & Tools




                                                                                                                                                                                                                                                                                                                                                                                                                    Minimized Life Cycle Costs

                                                                                                                                                                                                                                                                                                                                                                                                                                                 Minimized Operating Costs
  O   Moderate Risk =5-6




                                                                                                                                                                                                                                                                                                                                                                                                                                                                             Maxmized Raintainability
                                                                     Design Methods & Tools




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                Overall Numerical Score
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                          Environmental Facilities
  G   Existing to Low Risk = 7-9




                                                                                                                                                                                                                                                                                                                                 Min. Process Variability



                                                                                                                                                                                                                                                                                                                                                                              Assembly & Allignment




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                Maximized Availability
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                        Maximized Reliability
  W   White = Not Considered                                                                                               Appropriate Models

                                                                                                                                                Manufacturability




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                 Engineering Unit
                                                                                                                                                                                  Personnel Skills




                                                                                                                                                                                                                              Personnel Skills




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                          Personnel Skills




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                     Analytical Tools

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                        Test Equipment
                                                                                                                                                                                                                                                                                                                Mfg. Processes




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                        Personnel Skils
                                                                                                                                                                                                                                                                                                                                                            Reproducibility




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         GSE Required
                                                                                                                                                                                                                                                                                                Mfg. Software
                                                                                                                                                                                                     Components




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                   Scale Model
                                           Current TRL




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         Breadboard

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                      Brassboard
                                                         Databases




                                                                                                                                                                                                                                                                                                                                                                                                      Integration
                                                                                                                                                                    Testability




                                                                                                                                                                                                                                                                                    Metrology
                                                                                                                                                                                                                                                              Machines




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                    Prototype
                                                                                                                                                                                                                  Materials



                                                                                                                                                                                                                                                 Facilities




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                             Facilities
                                                                                                                                                                                                                                                                          Tooling
WBS                   Element
1.0   Turbopump
1.1     Inducer                             4            4           7                        4                              5                     7                              9                               9                                                                                                                                         7                                                                                                                                                                                                                             9                  9                                       9                  9                                          9
1.2     Impeller                            8            8           8                        8                              9                     7                              9                               9                                                                                                                                         8                                                                                                                                                                                                                             9                  9                                       9                  9                                          9
1.3     Pump Housing
1.3.1     Volute                            9            9           9                        7                              8                     8                              9                               9
1.3.2     Diffuser                          9            9           9                        7                              8                     8                              9                               9
1.4     Turbine manifold
1.4.1     Turbine Blades                    5            8           9                        8                              8                     8                              9                               7                                                                                                                                         8                                                       6                                                                                                                                                                     9                  9                                       9                  9                                          9
1.4.2     Turbine Nozzles                   8            9           9                        8                              8                     8                              9                               7                                                                                                                                         8                                                       6                                                                                                                                                                     9                  9                                       9                  9
1.5     Dynamic Seals                       5            6           6                        6                              6                     7                 5            5                               7                                                                                                                                                                                                 6                                                                                                                                                                     9
1.6     Bearings Supports                   7            5           6                        6                              6                     6                 5            6                               7                                                                                                                                         8                                                       6                                                                                                                                                                     8
1.7     Secondary Flow Path                 8            8           8                        8                              8                     7                              9                               9
1.8     Axial Thrust Balance                7            7           7                        7                              7                     7                              7                               8                                                                                                                                         8                    7                                                                                                                                                                                                        8
1.9     Materials                                                                                                                                                                 9                                                                                                                                                                                                                                                                                                                                                                                                       9                  9
1.10     Design Integration and Assembly    9                                                                                                                                     9
2.0   Fabrication                                                                                                                                                                 8
3.0   Validation Testing                                                                                                                                                          9                                                                                                                                                                                                                                                                                                                                                                      9              9                 9                                                                                                                                      8                  8




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           44
Mitigating the Adverse Impact of Technology Maturity
                                     Summary


•   The TRL assessment provides the baseline maturity at the start of a
    program/project and is the basis for the preparation of the
    Technology Readiness Assessment Report.
•   The AD2 assessment provides the basis for the development of the
    Technology Development Plan.
•   It also can provide considerable detail for more accurate
    determination of program cost and schedule.
     – The identification of data bases, tools, processes, facilities tests, scale
       model development and integration issues in particular will assist in
       developing realistic cost plans.
     – The identification of requirements for engineering model development
       and subsequent tests will be of particular benefit in outlining realistic
       schedules.
•   Both processes can significantly contribute to ensuring
    program/project success.


                                                                                     45
Mitigating the Adverse Impact of Technology Maturity


Bibliography:
•   Schinasi, Katherine, V., Sullivan, Michael, “Findings and Recommendations
    on Incorporating New Technology into Acquisition Programs,” Technology
    Readiness and Development Seminar, Space System Engineering and
    Acquisition Excellence Forum, The Aerospace Corporation, April 28, 2005.
•   “Better Management of Technology Development Can Improve Weapon
    System Outcomes,” GAO Report, GAO/NSIAD-99-162, July 1999.
•   “Using a Knowledge-Based Approach to Improve Weapon Acquisition,”
    GAO Report, GAO-04-386SP. January 2004.
•   “Capturing Design and Manufacturing Knowledge Early Improves
    Acquisition Outcomes,” GAO Report, GAO-02-701, July 2002.
•   Wheaton, Marilee, Valerdi, Ricardo, “EIA/ANSI 632 as a Standardized WBS
    for COSYSMO,” 2005 NASA Cost Analysis Symposium, April 13, 2005.




                                                                                46
Mitigating the Adverse Impact of Technology Maturity



Bibliography - continued:
•   Sadin, Stanley T.; Povinelli, Frederick P.; Rosen, Robert, “NASA technology
    push towards future space mission systems,” Space and Humanity
    Conference Bangalore, India, Selected Proceedings of the 39th
    International Astronautical Federation Congress, Acta Astronautica, pp 73-
    77, V 20, 1989
•   Mankins, John C. “Technology Readiness Levels” a White Paper, April 6,
    1995.
•   Nolte, William, “Technology Readiness Level Calculator, “Technology
    Readiness and Development Seminar, Space System Engineering and
    Acquisition Excellence Forum, The Aerospace Corporation, April 28, 2005.
•   TRL Calculator is available at the Defense Acquisition University Website at
    the following URL: https://acc.dau.mil/communitybrowser.aspx?id=25811




                                                                                   47
Mitigating the Adverse Impact of Technology Maturity



Bibliography - continued:
•   Manufacturing Readiness Level description is found at the Defense
    Acquisition University Website at the following URL:
    https://acc.dau.mil/CommunityBrowser.aspx?id=18231
•   Mankins, John C. , “Research & Development Degree of Difficulty (RD3)” A
    White Paper, March 10, 1998.
•   Sauser, Brian J., “Determining system Interoperability using an Integration
    Readiness Level”, Proceedings, NDIA Conference Proceedings.
•   Sauser, Brian, Ramirez-Marquez, Jose, Verma, Dinesh, Gove, Ryan, “
    From TRL to SRL: The Concept of Systems Readiness Levels, Paper #126,
    Conference on Systems Engineering Proceedings.
•   Additional material of interest
•   De Meyer, Arnould, Loch, Christoph H., and Pich Michael T., “Managing
    Project Uncertainty: From Variation to Chaos,” MIT Sloan Management
    Review, pp. 60-67, Winter 2002.



                                                                                  48

More Related Content

What's hot

Jim.free
Jim.freeJim.free
Jim.freeNASAPMC
 
Saltzman.john
Saltzman.johnSaltzman.john
Saltzman.johnNASAPMC
 
Lawrence.jim
Lawrence.jimLawrence.jim
Lawrence.jimNASAPMC
 
Jenks.ken
Jenks.kenJenks.ken
Jenks.kenNASAPMC
 
Armstrong
ArmstrongArmstrong
ArmstrongNASAPMC
 
Sean carter dan_deans
Sean carter dan_deansSean carter dan_deans
Sean carter dan_deansNASAPMC
 
Carol daniele
Carol danieleCarol daniele
Carol danieleNASAPMC
 
Kapruch steve
Kapruch steveKapruch steve
Kapruch steveNASAPMC
 
Odum.t.averbeck.r
Odum.t.averbeck.rOdum.t.averbeck.r
Odum.t.averbeck.rNASAPMC
 
Hughitt brian
Hughitt brianHughitt brian
Hughitt brianNASAPMC
 
Hazen michael
Hazen michaelHazen michael
Hazen michaelNASAPMC
 
Baldwin.kristen
Baldwin.kristenBaldwin.kristen
Baldwin.kristenNASAPMC
 
Vonnie simonsen
Vonnie simonsenVonnie simonsen
Vonnie simonsenNASAPMC
 
Quantitative Risk Analysis - Preventing Project cost escalation
Quantitative Risk Analysis - Preventing Project cost escalationQuantitative Risk Analysis - Preventing Project cost escalation
Quantitative Risk Analysis - Preventing Project cost escalationKarl Davey
 
David.oberhettinger
David.oberhettingerDavid.oberhettinger
David.oberhettingerNASAPMC
 
Poole.eric
Poole.ericPoole.eric
Poole.ericNASAPMC
 

What's hot (20)

Symons
SymonsSymons
Symons
 
Jim.free
Jim.freeJim.free
Jim.free
 
Housch
HouschHousch
Housch
 
Saltzman.john
Saltzman.johnSaltzman.john
Saltzman.john
 
Lawrence.jim
Lawrence.jimLawrence.jim
Lawrence.jim
 
Jenks.ken
Jenks.kenJenks.ken
Jenks.ken
 
Armstrong
ArmstrongArmstrong
Armstrong
 
Sean carter dan_deans
Sean carter dan_deansSean carter dan_deans
Sean carter dan_deans
 
Carol daniele
Carol danieleCarol daniele
Carol daniele
 
D081073[1]
D081073[1]D081073[1]
D081073[1]
 
Kapruch steve
Kapruch steveKapruch steve
Kapruch steve
 
Odum.t.averbeck.r
Odum.t.averbeck.rOdum.t.averbeck.r
Odum.t.averbeck.r
 
Hughitt brian
Hughitt brianHughitt brian
Hughitt brian
 
Hazen michael
Hazen michaelHazen michael
Hazen michael
 
Baldwin.kristen
Baldwin.kristenBaldwin.kristen
Baldwin.kristen
 
5_16_15_Chron_Resume
5_16_15_Chron_Resume5_16_15_Chron_Resume
5_16_15_Chron_Resume
 
Vonnie simonsen
Vonnie simonsenVonnie simonsen
Vonnie simonsen
 
Quantitative Risk Analysis - Preventing Project cost escalation
Quantitative Risk Analysis - Preventing Project cost escalationQuantitative Risk Analysis - Preventing Project cost escalation
Quantitative Risk Analysis - Preventing Project cost escalation
 
David.oberhettinger
David.oberhettingerDavid.oberhettinger
David.oberhettinger
 
Poole.eric
Poole.ericPoole.eric
Poole.eric
 

Viewers also liked

Viewers also liked (9)

Technology Readiness
Technology ReadinessTechnology Readiness
Technology Readiness
 
Steve blank moneyball and evidence-based entreprenuership
Steve blank moneyball and evidence-based entreprenuership Steve blank moneyball and evidence-based entreprenuership
Steve blank moneyball and evidence-based entreprenuership
 
BCN Biosciences I-corps@nih 121014
BCN Biosciences I-corps@nih 121014 BCN Biosciences I-corps@nih 121014
BCN Biosciences I-corps@nih 121014
 
Gammaglobulin I-Corps@NIH 121014
Gammaglobulin I-Corps@NIH 121014Gammaglobulin I-Corps@NIH 121014
Gammaglobulin I-Corps@NIH 121014
 
Clinacuity I-Corps@NIH 121014
Clinacuity I-Corps@NIH 121014Clinacuity I-Corps@NIH 121014
Clinacuity I-Corps@NIH 121014
 
Haro Pharmaceutical I-Corps@NIH 121014
Haro Pharmaceutical I-Corps@NIH 121014Haro Pharmaceutical I-Corps@NIH 121014
Haro Pharmaceutical I-Corps@NIH 121014
 
Affinity I-Corps@NIH 121014
Affinity I-Corps@NIH 121014Affinity I-Corps@NIH 121014
Affinity I-Corps@NIH 121014
 
CardiaX I-Corps@NIH 121014
CardiaX I-Corps@NIH 121014CardiaX I-Corps@NIH 121014
CardiaX I-Corps@NIH 121014
 
Innovation at 50x 031616
Innovation at 50x 031616Innovation at 50x 031616
Innovation at 50x 031616
 

Similar to Bilbro james

A suite of tools for technology assessment
A suite of tools for technology assessmentA suite of tools for technology assessment
A suite of tools for technology assessmentNitish Mahajan
 
Lect2 conventional software management
Lect2 conventional software managementLect2 conventional software management
Lect2 conventional software managementmeena466141
 
5WCSQ - Quality Improvement by the Real-Time Detection of the Problems
5WCSQ - Quality Improvement by the Real-Time Detection of the Problems5WCSQ - Quality Improvement by the Real-Time Detection of the Problems
5WCSQ - Quality Improvement by the Real-Time Detection of the ProblemsTakanori Suzuki
 
Pm soln9416141129710
Pm soln9416141129710Pm soln9416141129710
Pm soln9416141129710Nikhil Todkar
 
Software Requirements Prioritization: What, Why, and How?
Software Requirements Prioritization: What, Why, and How?Software Requirements Prioritization: What, Why, and How?
Software Requirements Prioritization: What, Why, and How?IRJET Journal
 
IRJET- Research Study on Testing Mantle in SDLC
IRJET- Research Study on Testing Mantle in SDLCIRJET- Research Study on Testing Mantle in SDLC
IRJET- Research Study on Testing Mantle in SDLCIRJET Journal
 
Primer on application_performance_testing_v0.2
Primer on application_performance_testing_v0.2Primer on application_performance_testing_v0.2
Primer on application_performance_testing_v0.2Trevor Warren
 
由政府採購體系檢視國內政府與業界有關系統工程之落差
由政府採購體系檢視國內政府與業界有關系統工程之落差由政府採購體系檢視國內政府與業界有關系統工程之落差
由政府採購體系檢視國內政府與業界有關系統工程之落差Alex Yin
 
Building products - A Nifty Approach
Building products - A Nifty ApproachBuilding products - A Nifty Approach
Building products - A Nifty ApproachGuruprasadBhat21
 
Using Doors® And Taug2® To Support A Simplified
Using Doors® And Taug2® To Support A SimplifiedUsing Doors® And Taug2® To Support A Simplified
Using Doors® And Taug2® To Support A Simplifiedcbb010
 
Software Defect Prediction Techniques in the Automotive Domain: Evaluation, S...
Software Defect Prediction Techniques in the Automotive Domain: Evaluation, S...Software Defect Prediction Techniques in the Automotive Domain: Evaluation, S...
Software Defect Prediction Techniques in the Automotive Domain: Evaluation, S...RAKESH RANA
 
Software Reliability CMM-DFSS
Software Reliability CMM-DFSSSoftware Reliability CMM-DFSS
Software Reliability CMM-DFSSGuy Van Hooveld
 
Using The Advancement Degree Of Difficulty (Ad2) As An Input To Risk Management
Using The Advancement Degree Of Difficulty (Ad2) As An Input To Risk ManagementUsing The Advancement Degree Of Difficulty (Ad2) As An Input To Risk Management
Using The Advancement Degree Of Difficulty (Ad2) As An Input To Risk Managementjbci
 
EPC Construction CQA Program
EPC Construction CQA ProgramEPC Construction CQA Program
EPC Construction CQA ProgramDan Stehling
 
SPS IPC Drives 2015 - Itris Automation paper
SPS IPC Drives 2015 - Itris Automation paperSPS IPC Drives 2015 - Itris Automation paper
SPS IPC Drives 2015 - Itris Automation paperItris Automation Square
 
Priority based software development and testing technique
Priority based software development and testing techniquePriority based software development and testing technique
Priority based software development and testing techniqueBTCTechnologies
 
Software/System Development Life Cycle
Software/System Development Life CycleSoftware/System Development Life Cycle
Software/System Development Life CycleHem Pokhrel
 
Cocomo ( cot constrictive model) and capability maturity model
Cocomo ( cot constrictive model) and capability maturity modelCocomo ( cot constrictive model) and capability maturity model
Cocomo ( cot constrictive model) and capability maturity modelPrakash Poudel
 

Similar to Bilbro james (20)

A suite of tools for technology assessment
A suite of tools for technology assessmentA suite of tools for technology assessment
A suite of tools for technology assessment
 
WBS is Paramount
WBS is ParamountWBS is Paramount
WBS is Paramount
 
Lect2 conventional software management
Lect2 conventional software managementLect2 conventional software management
Lect2 conventional software management
 
5WCSQ - Quality Improvement by the Real-Time Detection of the Problems
5WCSQ - Quality Improvement by the Real-Time Detection of the Problems5WCSQ - Quality Improvement by the Real-Time Detection of the Problems
5WCSQ - Quality Improvement by the Real-Time Detection of the Problems
 
Pm soln9416141129710
Pm soln9416141129710Pm soln9416141129710
Pm soln9416141129710
 
Software Requirements Prioritization: What, Why, and How?
Software Requirements Prioritization: What, Why, and How?Software Requirements Prioritization: What, Why, and How?
Software Requirements Prioritization: What, Why, and How?
 
IRJET- Research Study on Testing Mantle in SDLC
IRJET- Research Study on Testing Mantle in SDLCIRJET- Research Study on Testing Mantle in SDLC
IRJET- Research Study on Testing Mantle in SDLC
 
Primer on application_performance_testing_v0.2
Primer on application_performance_testing_v0.2Primer on application_performance_testing_v0.2
Primer on application_performance_testing_v0.2
 
由政府採購體系檢視國內政府與業界有關系統工程之落差
由政府採購體系檢視國內政府與業界有關系統工程之落差由政府採購體系檢視國內政府與業界有關系統工程之落差
由政府採購體系檢視國內政府與業界有關系統工程之落差
 
Building products - A Nifty Approach
Building products - A Nifty ApproachBuilding products - A Nifty Approach
Building products - A Nifty Approach
 
Using Doors® And Taug2® To Support A Simplified
Using Doors® And Taug2® To Support A SimplifiedUsing Doors® And Taug2® To Support A Simplified
Using Doors® And Taug2® To Support A Simplified
 
Software Defect Prediction Techniques in the Automotive Domain: Evaluation, S...
Software Defect Prediction Techniques in the Automotive Domain: Evaluation, S...Software Defect Prediction Techniques in the Automotive Domain: Evaluation, S...
Software Defect Prediction Techniques in the Automotive Domain: Evaluation, S...
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Software Reliability CMM-DFSS
Software Reliability CMM-DFSSSoftware Reliability CMM-DFSS
Software Reliability CMM-DFSS
 
Using The Advancement Degree Of Difficulty (Ad2) As An Input To Risk Management
Using The Advancement Degree Of Difficulty (Ad2) As An Input To Risk ManagementUsing The Advancement Degree Of Difficulty (Ad2) As An Input To Risk Management
Using The Advancement Degree Of Difficulty (Ad2) As An Input To Risk Management
 
EPC Construction CQA Program
EPC Construction CQA ProgramEPC Construction CQA Program
EPC Construction CQA Program
 
SPS IPC Drives 2015 - Itris Automation paper
SPS IPC Drives 2015 - Itris Automation paperSPS IPC Drives 2015 - Itris Automation paper
SPS IPC Drives 2015 - Itris Automation paper
 
Priority based software development and testing technique
Priority based software development and testing techniquePriority based software development and testing technique
Priority based software development and testing technique
 
Software/System Development Life Cycle
Software/System Development Life CycleSoftware/System Development Life Cycle
Software/System Development Life Cycle
 
Cocomo ( cot constrictive model) and capability maturity model
Cocomo ( cot constrictive model) and capability maturity modelCocomo ( cot constrictive model) and capability maturity model
Cocomo ( cot constrictive model) and capability maturity model
 

More from NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 

More from NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

Recently uploaded

Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Wonjun Hwang
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentationphoebematthew05
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024BookNet Canada
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksSoftradix Technologies
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024BookNet Canada
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Scott Keck-Warren
 
Science&tech:THE INFORMATION AGE STS.pdf
Science&tech:THE INFORMATION AGE STS.pdfScience&tech:THE INFORMATION AGE STS.pdf
Science&tech:THE INFORMATION AGE STS.pdfjimielynbastida
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 

Recently uploaded (20)

Hot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort Service
Hot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort ServiceHot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort Service
Hot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort Service
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentation
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other Frameworks
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024
 
Science&tech:THE INFORMATION AGE STS.pdf
Science&tech:THE INFORMATION AGE STS.pdfScience&tech:THE INFORMATION AGE STS.pdf
Science&tech:THE INFORMATION AGE STS.pdf
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 

Bilbro james

  • 1. Mitigating the Adverse Impact of Technology Maturity Project Management Challenge 2007 Fourth Annual NASA Project Management Conference February 6-7, 2007 James W. Bilbro Assistant Director for Technology/Chief Technologist George C. Marshall Space Flight Center
  • 2. Mitigating the Adverse Impact of Technology Maturity • Why do Technology Assessment? 2
  • 3. Mitigating the Adverse Impact of Technology Maturity Knowledge Building for Development of New Products* Technologies Design Production can meet match performs as cost, schedule, and requirements expected quality targets 1 2 3 Commercial Knowledge Points Program launch 1 DOD Knowledge Points 2 3 *GAO 3
  • 4. Mitigating the Adverse Impact of Technology Maturity Timing of Match Between Customer Expectations and Developer Resources* Customer expectations Developer resources Launch point for Launch point for successful cases problematic cases *GAO 4
  • 5. Mitigating the Adverse Impact of Technology Maturity Development of the Radio Frequency Countermeasures System* F-15 and B-1 Match requirements added achieved Customer’s expectations Customer Developer reports Developer proposes says no 197% cost increase additional resources & 15-month delay Developer’s resources Program start *GAO 5
  • 6. Mitigating the Adverse Impact of Technology Maturity NPR 7120.5d Requirements KDP A – Transition from Pre-Phase A to Phase A: Requires an assessment of potential technology needs versus current and planned technology readiness levels, as well as potential opportunities to use commercial, academic, and other government agency sources of technology. Included as part of the draft integrated baseline. KDP B – Transition from Phase A to Phase B: Requires a Technology Development plan identifying technologies to be developed, heritage systems to be modified, alternate paths to be pursued, fall back positions and corresponding performance de- scopes, milestones, metrics and key decision points. Incorporated in the preliminary Project Plan. KDP C – Transition from Phase B to Phase C/D: Technology Readiness Assessment Report (TRAR) demonstrating that all systems, subsystems and components have achieved a level of technological maturity with demonstrated evidence of qualification in a relevant environment. 6
  • 7. Mitigating the Adverse Impact of Technology Maturity And besides that – It’s the right thing to do! 7
  • 8. Mitigating the Adverse Impact of Technology Maturity How do you perform a Technology Assessment (TA)? • There are many ways to perform Technology Assessments. • The ensuing material describes one method that is essentially based on fundamental systems engineering principles. 8
  • 9. Mitigating the Adverse Impact of Technology Maturity What is Technology Assessment (TA)? • It is a two-step process that involves: – The determination of the Technology Readiness Levels (TRLs) (i.e. current level of maturity). – The determination of the Advancement Degree of Difficulty (AD2) (i.e., what is required to advance a technology from its current TRL to what is required for infusion into the program/project at an acceptable level of risk.) 9
  • 10. Mitigating the Adverse Impact of Technology Maturity What is a Technology Readiness Level (TRL)? • At its most basic, the TRL is a description of the maturity of a given technology defined by what has been done, under what conditions at a given point in time. • However, the TRL is just one part of the equation – and the initial assessment establishes the baseline for the program/project. • The more fundamental question is what is required (in terms of cost, schedule and risk to move the technology from where it is to where it needs to be. 10
  • 11. Mitigating the Adverse Impact of Technology Maturity What is an Advancement Degree of Difficulty (AD2)? • AD2 is a method of dealing with the other aspects beyond TRL, it is the description of what is required to move a technology from one TRL to another. • It takes into account: – Design Readiness Level – Manufacturing Readiness Level (MRL) – Integration Readiness Level (IRL) – Software Readiness Level (SRL) – Operational Readiness Level – Human Readiness Levels (HRL) (skills) – Capability Readiness Levels (CRL) (people and tools) – organizational aspects (ability of an organization to reproduce existing technology) – Etc. 11
  • 12. Mitigating the Adverse Impact of Technology Maturity Technology Assessment (TA) • It is extremely important that a Technology Assessment process be defined at the beginning of the program/project. • It is also extremely important that it be performed at the earliest possible stage (concept development) and repeated periodically throughout the program/project through PDR. • Inputs to the process will vary in level of detail according to the phase of the program/project in which it is conducted. 12
  • 13. Mitigating the Adverse Impact of Technology Maturity Technology Assessment (TA) • Even though there is a lack of detail in pre-phase A, the TA will drive out the major critical technological advancements required. • Therefore, at the beginning of pre-phase A, the following should be provided: – Refinement of Technology Readiness Level Definitions – Definition of Advancement Degree of Difficulty Process – Definition of terms to be used in the assessment process – Establishment of meaningful evaluation criteria and metrics that will allow for clear identification of gaps and shortfalls in performance. – Establishment of the TA team – Establishment of an independent TA review team. 13
  • 14. Mitigating the Adverse Impact of Technology Maturity Technology Assessment (TA) • The complete TA should be repeated just prior to SRR to: – establish the baseline maturity of the design and – To provide the material necessary to prepare the Technology Development Plan • A TRL assessment should be completed just prior to PDR to provide the material necessary to prepare the Technology Readiness Assessment Report 14
  • 15. Mitigating the Adverse Impact of Technology Maturity Technology Assessment Start with the WBS Crew Launch Crew Launch 136905 Vehicle Vehicle 1.3 Launch Launch Vehicle 136905.08 Vehicle 1.3.8 Upper Stage 136905.08.05 Upper Stage 1.3.8.2 136905.08.05.06 136905.08.05.07 136905.08.05.08 136905.08.05.09 FS RCS TVCS Avionics Software FS RCS TVCS Avionics Software 1.3.8.2.6 1.3.8.2.7 1.3.8.2.8 1.3.8.2.9 15
  • 16. Mitigating the Adverse Impact of Technology Maturity The Technology Assessment Process Identify systems, subsystems Assign TRL to all Assign TRL to and components per the components based subsystems based on hierarchical product on assessment of lowest TRL of breakdown of the WBS maturity components + TRL state of integration Assign TRL to Identify all components, Systems based on Baseline Technological subsystems and systems Maturity Assessment lowest TRL of that are at lower TRL’s than subsystems + TRL required by the program state of integration Perform AD2 on all identified components, subsystems and systemsthat are below requisite maturity level. Technology Development Plan Cost Plan Schedule Plan Risk Assessment 16
  • 17. Mitigating the Adverse Impact of Technology Maturity Architectural Study & Technology Assessment Interaction Requirements Concepts Architecture Studies System Design TRL/AD2 Assessment Technology Maturation 17
  • 18. Mitigating the Adverse Impact of Technology Maturity TRL Descriptions System Test, Launch Actual system “flight proven” through successful & Operations TRL 9 mission operations TRL 8 Actual system completed and “flight qualified” through System/Subsystem test and demonstration (Ground or Flight) Development TRL 7 System prototype demonstration in a space environment Technology Demonstration TRL 6 System/subsystem model or prototype demonstration in a relevant environment (Ground or Space) TRL 5 Component and/or breadboard validation in relevant Technology environment Development TRL 4 Component and/or breadboard validation in laboratory environment Research to Prove Feasibility TRL 3 Analytical and experimental critical function and/or characteristic proof-of-concept Basic Technology TRL 2 Technology concept and/or application formulated Research TRL 1 Basic principles observed and reported 18
  • 19. Mitigating the Adverse Impact of Technology Maturity TRL Descriptions Technology Readiness Definition Hardware Description Software Description Exit Criteria Level - (TRL) Scientific knowledge Scientific knowledge generated underpinning basic Peer reviewed publication of Basic principles observed generated underpinning 1 properties of software research underlying the and reported hardware technology architecture and proposed concept/application concepts/applications. mathematical formulation. Invention begins, practical Invention begins, practical application is identified but is application is identified but is speculative, no experimental Documented description of Technology concept or speculative, no experimental proof or detailed analysis is the application/concept that 2 application formulated proof or detailed analysis is available to support the addresses feasibility and available to support the conjecture. Underlying benefit conjecture. Algorithms are clarified and documented. Analytical studies place the Development of limited Analytical and/or technology in an appropriate Documented functionality to validate critical experimental critical context and laboratory analytical/experimental results 3 properties and predictions function or characteristic demonstrations, modeling and validating predicitions of key using non-integrated software proof-of-concept simulation validate analytical parameters components prediction. 19
  • 20. Mitigating the Adverse Impact of Technology Maturity TRL Descriptions - continued A low fidelity Key, functionally critical, system/component software components are breadboard is built and integrated, and functionally Documented test performance Component or operated to demonstrate basic validated, to establish demonstrating agreement with 4 breadboard validation in functionality and critical test interoperability and begin analytical predictions. laboratory environments and associated architecture development. Documented definition of performance predicitions are Relevant Evironments relevant environment. defined relative to the final defined and performance in operating environment. this environment predicted. A mid-level fidelity End to End Software system/component elements implemented and brassboard is built and interfaced with existing operated to demonstrate systems conforming to target overall performance in a Documented test performance environment, including the Component or simulated operational demonstrating agreement with target o software 5 breadboard validation in environment with realistic analytical predictions. environment. End to End a relevant environment support elements that Documented definition of Software System, Tested in demonstrates overall scaling requirements Relevant Environment, Meets performance in critical areas. Predicted Performance. Performance predictions are Operational Environment made for subsequent Performance Predicted. development phases. A high-fidelity system/component prototype Prototype software partially System/subsystem that adequately addresses all integrated with existing Documented test performance model or prototype critical scaling issues is built 6 hardware/software sytems demonstrating agreement with demonstration in a and operated in a relevant and demonstrated on full- analytical predictions relevant environment environment to demonstrate scale realistic problems. operations under critical environmental conditions. 20
  • 21. Mitigating the Adverse Impact of Technology Maturity TRL Descriptions - continued A high fidelity engineering unit that adequately addresses all critical scaling issues is built Prototype software is fully and operated in a relevant integrated with operational Documented test performance System prototype 7 environment to demonstrate harware/software sytems demonstrating agreement with demonstration in space performance in the actual demonstrating operational analytical predictions operational environment and feasibility. platform (ground, airborne or space). The final product in its final The final product in its final configuration is successfully configuration is successfully Actual system completed demonstrated through test and [demonstrated] through test and flight qualified Documented test performance 8 analysis for its intended and analysis for its intended through test and verifying analytical predictions operational environment and operational environment and demonstration platform (ground, airborne or platform (ground, airborne or space). space). Actual system flight The final product is The final product is proven through Documented mission 9 successfully operated in an successfully operated in an successful mission operational results actual mission. actual mission. operations 21
  • 22. Mitigating the Adverse Impact of Technology Maturity Definitions • Proof of Concept: (TRL 3) Analytical and experimental demonstration of hardware/software concepts that may or may not be incorporated into subsequent development and/or operational units. • Breadboard: (TRL 4) A low fidelity unit that demonstrates function only, without respect to form or fit in the case of hardware, or platform in the case of software. It often uses commercial and/or ad hoc components and is not intended to provide definitive information regarding operational performance. • Developmental Model/ Developmental Test Model: (TRL 4) Any of a series of units built to evaluate various aspects of form, fit, function or any combination thereof. In general these units may have some high fidelity aspects but overall will be in the breadboard category. • Brassboard: (TRL 5 – TRL6) A mid-fidelity functional unit that typically tries to make use of as much operational hardware/software as possible and begins to address scaling issues associated with the operational system. It does not have the engineering pedigree in all aspects, but is structured to be able to operate in simulated operational environments in order to assess performance of critical functions. 22
  • 23. Mitigating the Adverse Impact of Technology Maturity Definitions - continued • Mass Model: (TRL 5) Nonfunctional hardware that demonstrates form and/or fit for use in interface testing, handling, and modal anchoring. • Subscale model: (TRL 5 – TRL7) Hardware demonstrated in subscale to reduce cost and address critical aspects of the final system. If done at a scale that is adequate to address final system performance issue it may become the prototype. • Proof Model: (TRL 6) Hardware built for functional validation up to the breaking point, usually associated with fluid system over pressure, vibration, force loads, environmental extremes, and other mechanical stresses. 23
  • 24. Mitigating the Adverse Impact of Technology Maturity Definitions - continued • Proto-type Unit: (TRL 6 – TRL 7) The proto-type unit demonstrates form (shape and interfaces), fit (must be at a scale to adequately address critical full size issues), and function (full performance capability) of the final hardware. It can be considered as the first Engineering Model. It does not have the engineering pedigree or data to support its use in environments outside of a controlled laboratory environment – except for instances where a specific environment is required to enable the functional operation including in-space. It is to the maximum extent possible identical to flight hardware/software and is built to test the manufacturing and testing processes at a scale that is appropriate to address critical full scale issues. • Engineering Model: (TRL 6 – TRL 8) A full scale high-fidelity unit that demonstrates critical aspects of the engineering processes involved in the development of the operational unit. It demonstrates function, form, fit or any combination thereof at a scale that is deemed to be representative of the final product operating in its operational environment. Engineering test units are intended to closely resemble the final product (hardware/software) to the maximum extent possible and are built and tested so as to establish confidence that the design will function in the expected environments. In some cases, the engineering unit will become the protoflight or final product, assuming proper traceability has been exercised over the components and hardware handling. 24
  • 25. Mitigating the Adverse Impact of Technology Maturity Definitions - continued • Flight Qualification Unit: (TRL 8) Flight hardware that is tested to the levels that demonstrate the desired margins, particularly for exposing fatigue stress., typically 20-30%. Sometimes this means testing to failure. This unit is never flown. Key overtest levels are usually +6db above maximum expected for 3 minutes in all axes for shock, acoustic, and vibration; thermal vacuum 10C beyond acceptance for 6 cycles, and 1.25 times static load for unmanned flight. • Protoflight Unit: (TRL 8 – TRL 9) Hardware built for the flight mission that includes the lessons learned from the Engineering Model but where no Qualification model was built to reduce cost. It is however tested to enhanced environmental acceptance levels. It becomes the mission flight article. A higher risk tolerance is accepted as a tradeoff. Key protoflight overtest levels are usually +3db for shock, vibration, and acoustic; 5C beyond acceptance levels for thermal vacuum tests. • Flight Qualified Unit: (TRL8 – TRL9) Actual flight hardware/software that has been through acceptance testing. Acceptance test levels are designed to demonstrate flight-worthiness, to screen for infant failures without degrading performance. The levels are typically less than anticipated levels. 25
  • 26. Mitigating the Adverse Impact of Technology Maturity Definitions - continued • Flight Proven: (TRL 9) Hardware/software that is identical to hardware/software that has been successfully operated in a space mission and that is being used in an identical architecture under identical operational environments. 26
  • 27. Mitigating the Adverse Impact of Technology Maturity Definitions - continued • Laboratory Environment: An environment that does not address in any manner the environment to be encountered by the system, subsystem or component (hardware or software) during its intended operation. Tests in a laboratory environment are solely for the purpose of demonstrating the underlying principles of technical performance (functions) without respect to the impact of environment. • Relevant Environment: Not all systems, subsystems and/or components need to be operated in the operational environment in order to satisfactorily address performance margin requirements. Consequently, the relevant environment is the specific subset of the operational environment that is required to demonstrate critical “at risk” aspects of the final product performance in an operational environment. • Operational Environment: The environment in which the final product will be operated. In the case of spaceflight hardware/software it is space. In the case of ground based or airborne systems that are not directed toward space flight it will be the environments defined by the scope of operations. For software, the environment will be defined by the operational platform and software operating system. 27
  • 28. Mitigating the Adverse Impact of Technology Maturity Form Fit & Function Definitions Flight Unit Mass Model Proto-flight Unit Form * ** Qualification Unit Engineering Model 100% *Prototype *Brassboard Fit *Subscale unitSu Wind Tunnel Model * * Breadboard Function Proof of concept * 100% 28
  • 29. Mitigating the Adverse Impact of Technology Maturity TRL Assessment Thought Process Has an identical unit been successfully operated/launched in identical YES TRL 9 configuration/environment? NO Has an identical unit been successfully operated in space or launch in a different YES TRL5 configuration/ system architecture? If so then this initially drops to TRL 5 until ? differences are evaluated. NO Has an identical unit been flight qualified, but not yet operated in space or launch? YES TRL 8 NO Has a prototype unit (or one similar enough to be considered a prototype) been YES successfully operated in space or launch? TRL 7 NO Has a prototype unit (or one similar enough to be considered a prototype) been YES demonstrated in a relevant environment? TRL 6 NO 29
  • 30. Mitigating the Adverse Impact of Technology Maturity TRL Assessment Thought Process Has a breadboard unit been demonstrated in a relevant environment? YES TRL 5 NO Has a breadboard unit been demonstrated in a laboratory environment? YES TRL 4 NO Has analytical and experimental proof-of-concept been demonstrated? YES TRL 3 NO Has concept or application been formulated? YES TRL 2 NO Have basic principles been observed and reported? YES TRL 1 NO RETHINK YOUR POSITION REGARDING THIS TECHNOLOGY! 30
  • 31. Mitigating the Adverse Impact of Technology Maturity TRL Assessment Matrix TRL Assessment Demonstration Units Environment Unit Description R Red = Below TRL 3 Y Yellow = TRL 3,4 & 5 Space/Launch Operation Lab ora tory Env iron men t G Green = TRL 6 and above Relevant Environment W White = Unknown Space Environment Developmental Model X Exists Appropriate Scale Flig ht Qua lifie d Overall TRL Breadboard Brassboard Pro toty pe Function Concept Form Fit 1.0 System 1.1 Subsystem X 1.1.1 Mechanical Components 1.1.2 Mechanical Systems 1.1.3 Electrical Components X X X X X 1.1.4 Electrical Systems 1.1.5 Control Systems 1.1.6 Thermal Systems X X X 1.1.7 Fluid Systems X 1.1.8 Optical Systems 1.1.9 Electro-optical Systems 1.1.10 Software Systems 1.1.11 Mechanisms X 1.1.12 Integration 1.2 Subsystem Y 1.2.1 Mechanical Components 31
  • 32. Mitigating the Adverse Impact of Technology Maturity TRL Calcualtor Main Menu TRL Calculator Release Notes 1 AFRL Hardware and Software Transition Readiness Level Calculator, Version 2.2 This worksheet summarizes the TRL Calculator results. It displays the TRL, MRL, and PRL computed elsewhere. You may select the technology types and TRL categories (elements) you wish to include here or on the Calculator worksheet. Choose Hardware, Software, or Both to fit your program. If you omit a category of readiness level, (TRL, MRL, or PRL) that calculation is removed from the summary. The box in front of each readiness level element is checked when that category is included in the summary. You can enter program identification information here, too. TRL documentation including discussions of TRL, MRL, and PRL is available from the Main Menu. Include Hardware Only Include Software Only X Include Hardware and Software X Use Omit Technology Readiness Level X Use Omit Manufacturing Readiness Level X Use Omit Programmatic Readiness Level Here you can change the default values the spreadsheet uses to determine which color to award Green / Yellow set points: at a given level of question completion. System defaults are 100% for Green, and 67% for Yellow. You can change these set points to any value above 75% for Green, and any value from 50% to 85% for Yellow; however, the Yellow set point will always be at least 15% below the Green set point. Use the spinners to set your desired values. The defaults kick in if you try to set a value less than the minimum values of 75% for Green and 50% for Yellow. Start with the "Up" arrow to change defaults. Green set point is now at: 100% Yellow set point is now at: 67% 32
  • 33. Mitigating the Adverse Impact of Technology Maturity TRL Calculator Example WS B Elem N e ent am AssessedArea TR Score L M LScore R a) Prim Structure ary 5 6 7 5 b) Secondary Structure 5 6 7 5 6 136905.08.05.03 Structure &Thermal c) Flight Separation System 5 6, 7 8 5 7 d) TPS 5 6, 7 8 6 7 a) D &Lines ucts 5 6 7 5 6 136905.08.05.04 M Propulsion System ain b) Valves &Actuators 5 6 7 5 6 136905.08.05.05 U R S eaction C ontrol System 5 6, 7 8 5 7 136905.08.05.06 1st Stage Reaction C ontrol System 5 6, 7 8 5 7 a) Actuators 5 6 7 5 6 136905.08.05.07 Thrust Vector Control b) H ydraulic Pow System er s 4 5, 6 7 5 6 136905.08.05.08 Avionics a) C H &D 4 5, 6 7 5 6 b) G CH are N ardw 5 6 7 6 c) Electrical Power 6 7 6 7 d) Sensors 6 7 6 7 136905.08.05.09 Flight Softw System are 4 5 6 4 5 136905.08.05.10 C ponent Integration &Test om N Applicable ot 136905.08.05.11 Logistics Support Infrastructure GSE 6 7 8 6 7 136905.08.05.12 M anufacturingandAssem bly Tooling 5 6, 7 8 6 7 33
  • 34. Mitigating the Adverse Impact of Technology Maturity TRL Revised Questions 1 Critical functions and associated subsystems and components identified? 2 Relevant environments finalized? 3 Scaling requirements defined & documented? 4 Critical subsystems and components breadboards/brassboards identified and designed? TRL 5 5 Subsystem/component breadboards/brassboards built? 6 Facilities, GSE, STE available to support testing in a relevant environment? 7 M&S performance predictions completed? 8 System level performance predictions made for subsequent development phases? 9 Breadboards/brassboards successfully demonstrated in a relevant environment? 10 Successful demonstration documented along with scaling requirements? 1 System requirements finalized? 2 Operating environment definition finalized? Subset of relevant environments identified that address key aspects of the final operating 3 environment? 4 M&S used to simulate system performance in an operational environment? M&S used to simulate system/subsystem engineering model/protype performance in the 5 relevant environment? TRL 6 6 External interfaces baselined? 7 Scaling requirements finalized? Facilities, GSE, STE available to support system/subsystem engineering model/prototype 8 testing in the relevant environment? 9 System/subsystem engineering model/prototype that adequately addresses critical scaling System/subsystem engineering model/prototype that adequately addresses critical scaling 10 issues tested in the relevant environment? 11 Analysis of test results verify performance predictions for relevant environment? 12 Test performance demonstrating agreement with performance predictions documented? 34
  • 35. Mitigating the Adverse Impact of Technology Maturity Advancement Degree of Difficulty AD2 Degree of Difficulty Description 0% Development Risk - Exists with no or only minor 9 modifications being required. A single development approach is adequate. 10% Development Risk - Exists but requires major 8 modifications. A single development approach is adequate. 20% Development Risk - Requires new development well 7 within the experience base. A single development approach is adequate. 30% Development Risk - Requires new development but similarity to existing experience is sufficient to warrant 6 comparison across the board. A single development approach can be taken with a high degree of confidence for success. 40% Development Risk - Requires new development but similarity to existing experience is sufficient to warrant 5 comparison in all critical areas. Dual development approaches should be pursued to provide a high degree of confidence for success. 35
  • 36. Mitigating the Adverse Impact of Technology Maturity Advancement Degree of Difficulty AD2 - continued 50% Development Risk - Requires new development but similarity to existing experience is sufficient to warrant comparison in only a subset of critical areas. Dual 4 development approaches should be pursued in order to achieve a moderate degree of confidence for success. (Desired performance can be achieved in subsequent block upgrades with high degree of confidence.) 60% Development Risk - Requires new development but similarity to existing experience is sufficient to warrant 3 comparison in only a subset of critical areas. Multiple development routes must be pursued. 80% Development Risk - Requires new development where similarity to existing experience base can be defined only in 2 the broadest sense. Multiple development routes must be pursued. 100% Development Risk - Requires new development outside of any existing experience base. No viable 1 approaches exist that can be pursued with any degree of confidence. Basic research in key areas needed before feasible approaches can be defined. 36
  • 37. Mitigating the Adverse Impact of Technology Maturity Design and Analysis • Do the necessary data bases exist and if not, what level of development is required to produce them? • Do the necessary design methods exist and if not, what level of development is required to produce them? • Do the necessary design tools exist and if not, what level of development is required to produce them? • Do the necessary analytical methods exist and if not, what level of development is required to produce them? • Do the necessary analysis tools exist and if not, what level of development is required to produce them? • Do the appropriate models with sufficient accuracy exist and if not, what level of development is required to produce them? • Do the available personnel have the appropriate skills and if not, what level of development is required to acquire them? • Has the design been optimized for manufacturability and if not, what level of development is required to optimize it? • Has the design been optimized for testability and if not, what level of development is required to optimize it? 37
  • 38. Mitigating the Adverse Impact of Technology Maturity Manufacturing • Do the necessary materials exist and if not, what level of development is required to produce them? • Do the necessary manufacturing facilities exist and if not, what level of development is required to produce them? • Do the necessary manufacturing machines exist and if not, what level of development is required to produce them? • Does the necessary manufacturing tooling exist and if not, what level of development is required to produce it? • Does the necessary metrology exist and if not, what level of development is required to produce it? • Does the necessary manufacturing software exist and if not, what level of development is required to produce it? • Do the available personnel have the appropriate skills and if not, what level of development is required to acquire them? • Has the design been optimized for manufacturability and if not, what level of development is required to optimize it? • Has the manufacturing process flow been optimized and if not, what level of development is required to optimize it? • Has the manufacturing process variability been minimized and if not, what level of development is required to optimize it? 38
  • 39. Mitigating the Adverse Impact of Technology Maturity Manufacturing – continued • Has the design been optimized for reproducibility and if not, what level of development is required to optimize it? • Has the design been optimized for assembly & alignment and if not, what level of development is required to optimize it? • Has the design been optimized for integration at the component, subsystem and system level and if not, what level of development is required to optimize it? • Are breadboards required and if so what level of development is required to produce them? • Are brassboards required and if so what level of development is required to produce them? • Are subscale models required and if so what level of development is required to produce them? • Are engineering models required and if so what level of development is required to produce them? • Are prototypes required and if so what level of development is required to produce them? • Are breadboards, brassboards, engineering models and prototypes at the appropriate scale and fidelity for what they are to demonstrate, and if not what level of development is required to modify them accordingly? • Are Qualification models required and if so what level of development is required to produce them? 39
  • 40. Mitigating the Adverse Impact of Technology Maturity Operations • Has the design been optimized for maintainability and servicing and if not, what level of development is required to optimize it? • Has the design been optimized for minimum life cycle cost and if not, what level of development is required to optimize it? • Has the design been optimized for minimum annual recurring / operational cost and if not, what level of development is required to optimize it? • Has the design been optimized for reliability and if not, what level of development is required to optimize it? • Has the design been optimized for availability {ratio of operating time (reliability) to downtime (maintainability/ supportability)} and if not, what level of development is required to optimize it? • Do the necessary ground systems facilities & infrastructure exist and if not, what level of development is required to produce them? • Does the necessary ground systems equipment exist and if not, what level of development is required to produce it? • Does the necessary ground systems software exist and if not, what level of development is required to produce it? • Do the available personnel have the appropriate skills and if not, what level of development is required to acquire them? 40
  • 41. Mitigating the Adverse Impact of Technology Maturity Test & Evaluation • Do the necessary test facilities exist and if not, what level of development is required to produce them? • Does the necessary test equipment exist and if not, what level of development is required to produce them? • Does the necessary test tooling exist and if not, what level of development is required to produce it? • Do the necessary test measurement systems exist and if not, what level of development is required to produce them? • Does the necessary software exist and if not, what level of development is required to produce it? • Do the available personnel have the appropriate skills and if not, what level of development is required to acquire them? • Has the design been optimized for testability and if not, what level of development is required to optimize it? • Are breadboards required to be tested and if so what level of development is required to test them? • Are brassboards required to be tested and if so what level of development is required to test them? 41
  • 42. Mitigating the Adverse Impact of Technology Maturity Test & Evaluation – continued • Are subscale models required to be tested and if so what level of development is required to test them? • Are engineering models required to be tested and if so what level of development is required to test them? • Are prototypes required to be tested and if so what level of development is required to test them? • Are Qualification models required to be tested and if so what level of development is required to test them? 42
  • 43. Mitigating the Adverse Impact of Technology Maturity AD2 Automated Format 2/7/07 11:45 AM 12/3/2006 Advancement Degree of Difficulty - Questions Title: Evaluator: WBS Product Hierarchy Name WBS#, use multiple decimal points System Subsystem Component Only Answer Those Questions That Apply Technical Deg Schedule Cost Of Difficulty Design and Analysis Comments (42 character limit) Do the necessary data bases exist and if not, what level of 4 development is required to produce them? Do the necessary design methods exist and if not, what level of development is required to produce them? Do the necessary design tools exist and if not, what level of development is required to produce them? Do the necessary analytical methods exist and if not, what level of development is required to produce them? Do the necessary analysis tools exist and if not, what level of development is required to produce them? Do the appropriate models with sufficient accuracy exist and if not, what level of development is required to produce them? Do the available personnel have the appropriate skills and if not, what level of development is required to acquire them? Has the design been optimized for manufacturability and if not, what level of development is required to optimize it? Has the design been optimized for testability and if not, what level of development is required to optimize it? 43
  • 44. Mitigating the Adverse Impact of Technology Maturity AD2 Example Criteria TRL Design & Analysis Manufacturing Operability Test & Evaluation Demonstration Units Overall Qualitative Assessment R High Risk =1-4 Analytical Methods & Tools Minimized Life Cycle Costs Minimized Operating Costs O Moderate Risk =5-6 Maxmized Raintainability Design Methods & Tools Overall Numerical Score Environmental Facilities G Existing to Low Risk = 7-9 Min. Process Variability Assembly & Allignment Maximized Availability Maximized Reliability W White = Not Considered Appropriate Models Manufacturability Engineering Unit Personnel Skills Personnel Skills Personnel Skills Analytical Tools Test Equipment Mfg. Processes Personnel Skils Reproducibility GSE Required Mfg. Software Components Scale Model Current TRL Breadboard Brassboard Databases Integration Testability Metrology Machines Prototype Materials Facilities Facilities Tooling WBS Element 1.0 Turbopump 1.1 Inducer 4 4 7 4 5 7 9 9 7 9 9 9 9 9 1.2 Impeller 8 8 8 8 9 7 9 9 8 9 9 9 9 9 1.3 Pump Housing 1.3.1 Volute 9 9 9 7 8 8 9 9 1.3.2 Diffuser 9 9 9 7 8 8 9 9 1.4 Turbine manifold 1.4.1 Turbine Blades 5 8 9 8 8 8 9 7 8 6 9 9 9 9 9 1.4.2 Turbine Nozzles 8 9 9 8 8 8 9 7 8 6 9 9 9 9 1.5 Dynamic Seals 5 6 6 6 6 7 5 5 7 6 9 1.6 Bearings Supports 7 5 6 6 6 6 5 6 7 8 6 8 1.7 Secondary Flow Path 8 8 8 8 8 7 9 9 1.8 Axial Thrust Balance 7 7 7 7 7 7 7 8 8 7 8 1.9 Materials 9 9 9 1.10 Design Integration and Assembly 9 9 2.0 Fabrication 8 3.0 Validation Testing 9 9 9 9 8 8 44
  • 45. Mitigating the Adverse Impact of Technology Maturity Summary • The TRL assessment provides the baseline maturity at the start of a program/project and is the basis for the preparation of the Technology Readiness Assessment Report. • The AD2 assessment provides the basis for the development of the Technology Development Plan. • It also can provide considerable detail for more accurate determination of program cost and schedule. – The identification of data bases, tools, processes, facilities tests, scale model development and integration issues in particular will assist in developing realistic cost plans. – The identification of requirements for engineering model development and subsequent tests will be of particular benefit in outlining realistic schedules. • Both processes can significantly contribute to ensuring program/project success. 45
  • 46. Mitigating the Adverse Impact of Technology Maturity Bibliography: • Schinasi, Katherine, V., Sullivan, Michael, “Findings and Recommendations on Incorporating New Technology into Acquisition Programs,” Technology Readiness and Development Seminar, Space System Engineering and Acquisition Excellence Forum, The Aerospace Corporation, April 28, 2005. • “Better Management of Technology Development Can Improve Weapon System Outcomes,” GAO Report, GAO/NSIAD-99-162, July 1999. • “Using a Knowledge-Based Approach to Improve Weapon Acquisition,” GAO Report, GAO-04-386SP. January 2004. • “Capturing Design and Manufacturing Knowledge Early Improves Acquisition Outcomes,” GAO Report, GAO-02-701, July 2002. • Wheaton, Marilee, Valerdi, Ricardo, “EIA/ANSI 632 as a Standardized WBS for COSYSMO,” 2005 NASA Cost Analysis Symposium, April 13, 2005. 46
  • 47. Mitigating the Adverse Impact of Technology Maturity Bibliography - continued: • Sadin, Stanley T.; Povinelli, Frederick P.; Rosen, Robert, “NASA technology push towards future space mission systems,” Space and Humanity Conference Bangalore, India, Selected Proceedings of the 39th International Astronautical Federation Congress, Acta Astronautica, pp 73- 77, V 20, 1989 • Mankins, John C. “Technology Readiness Levels” a White Paper, April 6, 1995. • Nolte, William, “Technology Readiness Level Calculator, “Technology Readiness and Development Seminar, Space System Engineering and Acquisition Excellence Forum, The Aerospace Corporation, April 28, 2005. • TRL Calculator is available at the Defense Acquisition University Website at the following URL: https://acc.dau.mil/communitybrowser.aspx?id=25811 47
  • 48. Mitigating the Adverse Impact of Technology Maturity Bibliography - continued: • Manufacturing Readiness Level description is found at the Defense Acquisition University Website at the following URL: https://acc.dau.mil/CommunityBrowser.aspx?id=18231 • Mankins, John C. , “Research & Development Degree of Difficulty (RD3)” A White Paper, March 10, 1998. • Sauser, Brian J., “Determining system Interoperability using an Integration Readiness Level”, Proceedings, NDIA Conference Proceedings. • Sauser, Brian, Ramirez-Marquez, Jose, Verma, Dinesh, Gove, Ryan, “ From TRL to SRL: The Concept of Systems Readiness Levels, Paper #126, Conference on Systems Engineering Proceedings. • Additional material of interest • De Meyer, Arnould, Loch, Christoph H., and Pich Michael T., “Managing Project Uncertainty: From Variation to Chaos,” MIT Sloan Management Review, pp. 60-67, Winter 2002. 48