In this presentation we share information on how to map / integrated the PMBOK Guide Process Groups with a Project Life Cycle. The project life cycle can be a generic model or per the SUKAD CAM2P™ Model (The Customizable and Adaptable Methodology for Managing Projects™).
We share this topic because it is a common area of confusion among PMPs and those studying the PMBOK Guide.
4. First: there is the project life cycle
• From idea to closure … or
• From which ever point the organization
defines as start and end points
Project Life Cycle
5. Second: the project life cycle is
subdivided into phases (stages)
Idea
Project
Charter Handover
Final
Accept
Intermediate Phases
Pre-Project
Final
Phase 1 Phase 2 Phase N
Project Life Cycle
Study
Start-up
6. This is the project life cycle from the
SUKAD CAM2P™ Model
(the standard model with phases and stages)
11. PMBOK Process Groups, Processes, & Knowledge Areas
Knowledge Areas
Project Management Process Groups
Initiating Process
Group
Planning Process
Group
Executing
Process Group
Monitoring & Controlling
Process Group
Closing Process
Group
Project Integration
Management
• Develop Project Charter • Develop Project Management
Plan
• Direct and Manage Project
Work
• Monitor and Control
Project Work
• Perform Integrated
Change Control
• Close Project
or Phase
Project Scope
Management
• Plan Scope Management
• Collect Requirements
• Define Scope
• Create WBS
• Validate Scope
• Control Scope
Project Time Management
• Plan Schedule Management
• Define Activities
• Sequence Activities
• Estimate Activity Resources
• Estimate Activity Durations
• Develop Schedule
• Control Schedule
Project Cost
Management
• Plan Cost Management
• Estimate Costs
• Determine Budget
• Control Costs
Project Quality
Management
• Plan Quality Management • Perform Quality Assurance • Control Quality
Project Human
Resource Management
• Plan Human Resource
Management
• Acquire Project Team
• Develop Project Team
• Manage Project Team
Project Communications
Management
• Plan Communications
Management
• Manage Communications • Control Communications
Project Risk Management
• Plan Risk Management
• Identify Risks
• Perform Qualitative Risk
Analysis
• Perform Quantitative Risk
Analysis
• Plan Risk Responses
• Control Risks
Project Procurement
Management
• Plan Procurement
Management
• Conduct Procurements • Control Procurements • Close
Procurements
Project Stakeholder
Management
• Identify Stakeholders • Plan Stakeholder Management • Manage Stakeholder
Engagement
• Control Stakeholder
Engagement
12. Initiate Plan Execute
Monitor &
Control
Close
Integration 1 1 1 2 1
Scope 4 2
Time 6 1
Cost 3 1
Quality 1 1 1
Human Resource 1 3
Communication 1 1 1
Risk 5 1
Procurement 1 1 1 1
Stakeholders 1 1 1 1
18. Project Life Cycle
I P E MC C
I
S
T
C
Q
HR
C
R
P
S
Phase 1 Phase 2 Phase 3 Phase N
PMBOK Guide Process Groups Repeating
I P E MC C
I
S
T
C
Q
HR
C
R
P
S
Processes from the knowledge areas repeat as well
PMBOK Guide
Knowledge Areas
and Process
Groups
I P E MC C
I
S
T
C
Q
HR
C
R
P
S
PMBOK Guide
Knowledge Areas
and Process
Groups
PMBOK Guide
Knowledge Areas
and Process
Groups
I P E MC C
I
S
T
C
Q
HR
C
R
P
S
PMBOK Guide
Knowledge Areas
and Process
Groups
Initiate Plan Execute
Monitor &
Control
Close
Integration
Scope
Time
Cost
Quality
Human Resource
Communication
Risk
Procurement
Stakeholders
29. SUKAD business divisions
www.sukad.com | enter the name of the presentation or program 30
http://learning.sukad.com
http://solutions.sukad.com
http://technology.sukad.com
http://multimedia.sukad.com
30. SUKAD knowledge sharing sites
www.sukad.com | enter the name of the presentation or program 31
http://sukadway.sukad.com
http://knowledge.sukad.com
http://blog.sukad.com
http://blog-ar.sukad.com