SlideShare a Scribd company logo
1 of 16
Electrical power engineering
test (2(
Elect.Eng/ Mohamed Safwat
Q1) 1a-What are abbreviations referring to?
1- UPS
2- ONAN
3- BDV
1-UPS: Uninterruptible Power Supply
Is used in very important loads.
2-ONAN: Oil Natural Air Natural
is a type of cooling used in oil transformers up to (30 MVA(.
3-BDV: Break Down Voltage
Break down voltage of any isolation material like [ oil , pvc , ……,etc[
This value the voltage of any system can’t be over it , may be [33 KV or 66 KV[
Q2) What is meant by derating factor = 0.65
This mean that if we have cable withstand 100 A in normal condition so if we take
derating factor 0.65 the maximum withstanding current will be 65 A so we lost
35A
Q3) what is the function of Synchrocheck relay?
Is used in case of parallel connection
between two generators to feed large load
to adapt the synchronization
Q4)What are the conditions of parallel connection
between transformers?
1-The voltage ratio must be the same.
2-The per-unit impedence must be the same.
3-The polarity connection must be the same I order to
avoid circulating current.
Q5) what are the suitable method to start induction motor ,
explain with drawings?
1-Rotor resistance method (only for wound rotor).
2-Stator resistor or reactance.
3-Auto transformer method.
4-Star-Delta Switch.
5-Soft starting method.
The best method is:
1-Soft starting method.
2-Star delta switch.
1-Soft starting method.
2-Star delta switch.
Q6) what are the excitation system types for synchronous
generators , explain with drawings?
1-Dc excitation system using amplidyne
2-Ac excitation system
a- using rectifier
b- using brushless
3-using static excitation method
Q7) draw the schematic drawing for ups system and
identify each component of it
ups
Q8)what are the precaution required to change the CT
burden during energized system?
Never open circuit a current transformer
secondary while the primary is energized
Q9) draw the differential protection circuit install on motor
and identify its parameters and draw C/C curve of it?
Q10)Three pumps working sequentially after delayed for
some time in start one after one with motor rated power
= 55 KW and rated voltage = 400V and rated power
factor = 0.85 lag please draw the power and control
circuit for it and determine all circuit components
parameters that you use it

More Related Content

What's hot

Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performancemichaeljmack
 
Scherbius drive of electrical machines
Scherbius drive of electrical machinesScherbius drive of electrical machines
Scherbius drive of electrical machinesemredurna
 
EEP301: Ac position control
EEP301: Ac position controlEEP301: Ac position control
EEP301: Ac position controlUmang Gupta
 
07 modelling.electric.motors
07 modelling.electric.motors07 modelling.electric.motors
07 modelling.electric.motorsMahmoud Hussein
 
Automatic synch of gen
Automatic synch of genAutomatic synch of gen
Automatic synch of genmichaeljmack
 
EEP301: Dc modular servo motor
EEP301: Dc modular servo motorEEP301: Dc modular servo motor
EEP301: Dc modular servo motorUmang Gupta
 
Generator basic concepts
Generator basic conceptsGenerator basic concepts
Generator basic conceptsmichaeljmack
 
Auto synch considerations methods
Auto synch considerations methodsAuto synch considerations methods
Auto synch considerations methodsmichaeljmack
 
analysis of induction motor drive using slip power recovery scheme
analysis of induction motor drive using slip power recovery schemeanalysis of induction motor drive using slip power recovery scheme
analysis of induction motor drive using slip power recovery schemePrakash_13209
 
Detection of Generator Loss of Excitation (LOE)
Detection of Generator Loss of Excitation (LOE)Detection of Generator Loss of Excitation (LOE)
Detection of Generator Loss of Excitation (LOE)Anmol Dwivedi
 
EEP301: Analog control of DC motor
EEP301: Analog control of DC motorEEP301: Analog control of DC motor
EEP301: Analog control of DC motorUmang Gupta
 
Speed control of dc motor using matlab
Speed control of dc motor using matlabSpeed control of dc motor using matlab
Speed control of dc motor using matlabShridhar kulkarni
 
Motor bus transfer
Motor bus transferMotor bus transfer
Motor bus transfermichaeljmack
 
Design of Highly Reliable and Efficient Next Generation Power Converters(Tran...
Design of Highly Reliable and Efficient Next Generation Power Converters(Tran...Design of Highly Reliable and Efficient Next Generation Power Converters(Tran...
Design of Highly Reliable and Efficient Next Generation Power Converters(Tran...SHAHRUKH ALAM
 

What's hot (20)

Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performance
 
Static kramer system
Static kramer systemStatic kramer system
Static kramer system
 
Scherbius drive of electrical machines
Scherbius drive of electrical machinesScherbius drive of electrical machines
Scherbius drive of electrical machines
 
EEP301: Ac position control
EEP301: Ac position controlEEP301: Ac position control
EEP301: Ac position control
 
07 modelling.electric.motors
07 modelling.electric.motors07 modelling.electric.motors
07 modelling.electric.motors
 
Automatic synch of gen
Automatic synch of genAutomatic synch of gen
Automatic synch of gen
 
EEP301: Dc modular servo motor
EEP301: Dc modular servo motorEEP301: Dc modular servo motor
EEP301: Dc modular servo motor
 
Generator basic concepts
Generator basic conceptsGenerator basic concepts
Generator basic concepts
 
Auto synch considerations methods
Auto synch considerations methodsAuto synch considerations methods
Auto synch considerations methods
 
analysis of induction motor drive using slip power recovery scheme
analysis of induction motor drive using slip power recovery schemeanalysis of induction motor drive using slip power recovery scheme
analysis of induction motor drive using slip power recovery scheme
 
Detection of Generator Loss of Excitation (LOE)
Detection of Generator Loss of Excitation (LOE)Detection of Generator Loss of Excitation (LOE)
Detection of Generator Loss of Excitation (LOE)
 
Electrical machines-lab-i-ee0209
Electrical machines-lab-i-ee0209Electrical machines-lab-i-ee0209
Electrical machines-lab-i-ee0209
 
EEP301: Exp5
EEP301: Exp5EEP301: Exp5
EEP301: Exp5
 
(6) finite
(6) finite(6) finite
(6) finite
 
EEP301: Analog control of DC motor
EEP301: Analog control of DC motorEEP301: Analog control of DC motor
EEP301: Analog control of DC motor
 
Speed control of dc motor using matlab
Speed control of dc motor using matlabSpeed control of dc motor using matlab
Speed control of dc motor using matlab
 
5
55
5
 
Motor bus transfer
Motor bus transferMotor bus transfer
Motor bus transfer
 
Design of Highly Reliable and Efficient Next Generation Power Converters(Tran...
Design of Highly Reliable and Efficient Next Generation Power Converters(Tran...Design of Highly Reliable and Efficient Next Generation Power Converters(Tran...
Design of Highly Reliable and Efficient Next Generation Power Converters(Tran...
 
Chapter 6 edit
Chapter 6 editChapter 6 edit
Chapter 6 edit
 

Similar to Electrical power engineering test (2)

BEF43303 - 201620171 W1 Power System Analysis and Protection.pdf
BEF43303 - 201620171 W1 Power System Analysis and Protection.pdfBEF43303 - 201620171 W1 Power System Analysis and Protection.pdf
BEF43303 - 201620171 W1 Power System Analysis and Protection.pdfLiewChiaPing
 
Electric-Traction-Railways.ppt
Electric-Traction-Railways.pptElectric-Traction-Railways.ppt
Electric-Traction-Railways.pptssuserf805c8
 
Assignment 1 170901 interconnected power system
Assignment 1 170901 interconnected power systemAssignment 1 170901 interconnected power system
Assignment 1 170901 interconnected power systemVara Prasad
 
Assignment 1 170901 interconnected power system
Assignment 1 170901 interconnected power systemAssignment 1 170901 interconnected power system
Assignment 1 170901 interconnected power systemVara Prasad
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)IJERD Editor
 
Electrical Engineering Interview Questions
Electrical Engineering Interview QuestionsElectrical Engineering Interview Questions
Electrical Engineering Interview Questionsashiesh0007
 
Improvement In Pre-Regulation For Power Factor Using CUK Converter
Improvement In Pre-Regulation For Power Factor Using CUK ConverterImprovement In Pre-Regulation For Power Factor Using CUK Converter
Improvement In Pre-Regulation For Power Factor Using CUK ConverterIJRES Journal
 
Design and Development of Power Electronic Controller for Grid-connected PV A...
Design and Development of Power Electronic Controller for Grid-connected PV A...Design and Development of Power Electronic Controller for Grid-connected PV A...
Design and Development of Power Electronic Controller for Grid-connected PV A...IJAPEJOURNAL
 
Bidirectional full bridge dc-dc converter with flyback snubber for photovolta...
Bidirectional full bridge dc-dc converter with flyback snubber for photovolta...Bidirectional full bridge dc-dc converter with flyback snubber for photovolta...
Bidirectional full bridge dc-dc converter with flyback snubber for photovolta...IAEME Publication
 
INDUSTRIAL TRAINING REPORT.pptx
INDUSTRIAL TRAINING REPORT.pptxINDUSTRIAL TRAINING REPORT.pptx
INDUSTRIAL TRAINING REPORT.pptxSanatKumar66
 
Study of the impact on the protection plan of a pv production integrated to t...
Study of the impact on the protection plan of a pv production integrated to t...Study of the impact on the protection plan of a pv production integrated to t...
Study of the impact on the protection plan of a pv production integrated to t...IAEME Publication
 
Optimum Amplitude Venturini ModulationBased Matrix Converter Fed Induction Mo...
Optimum Amplitude Venturini ModulationBased Matrix Converter Fed Induction Mo...Optimum Amplitude Venturini ModulationBased Matrix Converter Fed Induction Mo...
Optimum Amplitude Venturini ModulationBased Matrix Converter Fed Induction Mo...iosrjce
 
ECNG 3015 - PU system and 3Phase Fault calculation
ECNG 3015 - PU system and 3Phase Fault calculation ECNG 3015 - PU system and 3Phase Fault calculation
ECNG 3015 - PU system and 3Phase Fault calculation Chandrabhan Sharma
 
Parameter estimation of three-phase linear induction motor by a DSP-based el...
Parameter estimation of three-phase linear induction motor  by a DSP-based el...Parameter estimation of three-phase linear induction motor  by a DSP-based el...
Parameter estimation of three-phase linear induction motor by a DSP-based el...IJECEIAES
 
SPEED CONTROL OF SEPARATELY EXCITED DC MOTOR USING POWER ELECTRONIC CONVERTER
 SPEED CONTROL OF SEPARATELY EXCITED DC MOTOR USING POWER ELECTRONIC CONVERTER  SPEED CONTROL OF SEPARATELY EXCITED DC MOTOR USING POWER ELECTRONIC CONVERTER
SPEED CONTROL OF SEPARATELY EXCITED DC MOTOR USING POWER ELECTRONIC CONVERTER ijiert bestjournal
 

Similar to Electrical power engineering test (2) (20)

Untitled document.PDF
Untitled document.PDFUntitled document.PDF
Untitled document.PDF
 
BEF43303 - 201620171 W1 Power System Analysis and Protection.pdf
BEF43303 - 201620171 W1 Power System Analysis and Protection.pdfBEF43303 - 201620171 W1 Power System Analysis and Protection.pdf
BEF43303 - 201620171 W1 Power System Analysis and Protection.pdf
 
Two Quadrant chopper
Two Quadrant chopperTwo Quadrant chopper
Two Quadrant chopper
 
Electric-Traction-Railways.ppt
Electric-Traction-Railways.pptElectric-Traction-Railways.ppt
Electric-Traction-Railways.ppt
 
Assignment 1 170901 interconnected power system
Assignment 1 170901 interconnected power systemAssignment 1 170901 interconnected power system
Assignment 1 170901 interconnected power system
 
Assignment 1 170901 interconnected power system
Assignment 1 170901 interconnected power systemAssignment 1 170901 interconnected power system
Assignment 1 170901 interconnected power system
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 
Electrical Engineering Interview Questions
Electrical Engineering Interview QuestionsElectrical Engineering Interview Questions
Electrical Engineering Interview Questions
 
Introduction to PLC
Introduction to PLCIntroduction to PLC
Introduction to PLC
 
Improvement In Pre-Regulation For Power Factor Using CUK Converter
Improvement In Pre-Regulation For Power Factor Using CUK ConverterImprovement In Pre-Regulation For Power Factor Using CUK Converter
Improvement In Pre-Regulation For Power Factor Using CUK Converter
 
Design and Development of Power Electronic Controller for Grid-connected PV A...
Design and Development of Power Electronic Controller for Grid-connected PV A...Design and Development of Power Electronic Controller for Grid-connected PV A...
Design and Development of Power Electronic Controller for Grid-connected PV A...
 
Bidirectional full bridge dc-dc converter with flyback snubber for photovolta...
Bidirectional full bridge dc-dc converter with flyback snubber for photovolta...Bidirectional full bridge dc-dc converter with flyback snubber for photovolta...
Bidirectional full bridge dc-dc converter with flyback snubber for photovolta...
 
INDUSTRIAL TRAINING REPORT.pptx
INDUSTRIAL TRAINING REPORT.pptxINDUSTRIAL TRAINING REPORT.pptx
INDUSTRIAL TRAINING REPORT.pptx
 
Study of the impact on the protection plan of a pv production integrated to t...
Study of the impact on the protection plan of a pv production integrated to t...Study of the impact on the protection plan of a pv production integrated to t...
Study of the impact on the protection plan of a pv production integrated to t...
 
EEE Interview Question
EEE Interview QuestionEEE Interview Question
EEE Interview Question
 
J010627885
J010627885J010627885
J010627885
 
Optimum Amplitude Venturini ModulationBased Matrix Converter Fed Induction Mo...
Optimum Amplitude Venturini ModulationBased Matrix Converter Fed Induction Mo...Optimum Amplitude Venturini ModulationBased Matrix Converter Fed Induction Mo...
Optimum Amplitude Venturini ModulationBased Matrix Converter Fed Induction Mo...
 
ECNG 3015 - PU system and 3Phase Fault calculation
ECNG 3015 - PU system and 3Phase Fault calculation ECNG 3015 - PU system and 3Phase Fault calculation
ECNG 3015 - PU system and 3Phase Fault calculation
 
Parameter estimation of three-phase linear induction motor by a DSP-based el...
Parameter estimation of three-phase linear induction motor  by a DSP-based el...Parameter estimation of three-phase linear induction motor  by a DSP-based el...
Parameter estimation of three-phase linear induction motor by a DSP-based el...
 
SPEED CONTROL OF SEPARATELY EXCITED DC MOTOR USING POWER ELECTRONIC CONVERTER
 SPEED CONTROL OF SEPARATELY EXCITED DC MOTOR USING POWER ELECTRONIC CONVERTER  SPEED CONTROL OF SEPARATELY EXCITED DC MOTOR USING POWER ELECTRONIC CONVERTER
SPEED CONTROL OF SEPARATELY EXCITED DC MOTOR USING POWER ELECTRONIC CONVERTER
 

Recently uploaded

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 

Recently uploaded (20)

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 

Electrical power engineering test (2)

  • 1. Electrical power engineering test (2( Elect.Eng/ Mohamed Safwat
  • 2. Q1) 1a-What are abbreviations referring to? 1- UPS 2- ONAN 3- BDV 1-UPS: Uninterruptible Power Supply Is used in very important loads. 2-ONAN: Oil Natural Air Natural is a type of cooling used in oil transformers up to (30 MVA(. 3-BDV: Break Down Voltage Break down voltage of any isolation material like [ oil , pvc , ……,etc[ This value the voltage of any system can’t be over it , may be [33 KV or 66 KV[
  • 3. Q2) What is meant by derating factor = 0.65 This mean that if we have cable withstand 100 A in normal condition so if we take derating factor 0.65 the maximum withstanding current will be 65 A so we lost 35A
  • 4. Q3) what is the function of Synchrocheck relay? Is used in case of parallel connection between two generators to feed large load to adapt the synchronization
  • 5. Q4)What are the conditions of parallel connection between transformers? 1-The voltage ratio must be the same. 2-The per-unit impedence must be the same. 3-The polarity connection must be the same I order to avoid circulating current.
  • 6. Q5) what are the suitable method to start induction motor , explain with drawings? 1-Rotor resistance method (only for wound rotor). 2-Stator resistor or reactance. 3-Auto transformer method. 4-Star-Delta Switch. 5-Soft starting method. The best method is: 1-Soft starting method. 2-Star delta switch.
  • 9. Q6) what are the excitation system types for synchronous generators , explain with drawings? 1-Dc excitation system using amplidyne
  • 10. 2-Ac excitation system a- using rectifier
  • 13. Q7) draw the schematic drawing for ups system and identify each component of it ups
  • 14. Q8)what are the precaution required to change the CT burden during energized system? Never open circuit a current transformer secondary while the primary is energized
  • 15. Q9) draw the differential protection circuit install on motor and identify its parameters and draw C/C curve of it?
  • 16. Q10)Three pumps working sequentially after delayed for some time in start one after one with motor rated power = 55 KW and rated voltage = 400V and rated power factor = 0.85 lag please draw the power and control circuit for it and determine all circuit components parameters that you use it