1. The construction of the highway
over the Dnipro River in
Zaporizhia
Chief administrator of state budget funds: The State Agency of Ukrainian
Automobile Roads “Ukravtodor”
Responsible executor: The Agency of roads in Zaporizhia region
The State Agency of Ukrainian
Automobile Roads “Ukravtodor”
2. Short project descriptionShort project description
Goal: the building of a highway over the Dnipro River in Zaporizhzhia, a total length of 9.1 km.
Project contains 6 traffic junctions and 26 engineering structures:
•1 cable-stayed bridge over the Dnipro River with the length of 660 m;
•1-frame girder bridge with a total length of 340 meters;
•17 reinforced concrete and steel and concrete platforms;
•7 overpasses.
.The highway is planned to be constructed in two stages.
The first stage of construction involves construction of 4 (four) starting complexes.
The first starting complex is already implemented (the installation is completed and the construction of outdoor lighting of
road junction №1) and is put into operation.
The second starting complex is already implemented, the period of putting into operation is 3 months.
The third starting complex is already implemented, the period of putting into operation is 6 months.
It is planned within the project to build the 4th starting complex of the first stage of construction.
The 5th starting complex of the first construction stage and the second stage of construction of the highway over the Dnipro
River ( the completion of construction in general) are not included in the project.
The term of the project: 2017 - 2020 years.
The total estimated construction cost of phase I and II after conversion is 7,585 191.18 thousand UAH.
The total cost of the project ( the construction of the 4th
starting complex of the I stage of construction): 4 991 318.994
thousand. UAH. (Funds provided from the state budget), including:
Work with the adjustment of project documentation etc.: 62 908.000 thousand. UAH .;
work of construction: 4928 410.994 thousand. UAH.
3. The scheme of a highway in Zaporizhzhya over the DniproThe scheme of a highway in Zaporizhzhya over the Dnipro
RiverRiver
Construction readiness of object
under construction (I phase of
construction): 65%
4. Scheme of a highway in. Zaporizhzhia over the Dnipro RiverScheme of a highway in. Zaporizhzhia over the Dnipro River
5. 5
Construction № 1Construction № 1
Implementation of work of the I construction stageImplementation of work of the I construction stage
23. The current situation and problemsThe current situation and problems
The problem of transport communication between the territories of the city of Zaporizhzhia is
associated with a particular geographical location, due to its division by the Dnipro River into two
parts: the Left Bank and Right Bank and location of the island Khortytsya (almost in the middle
between the two parts of the city).
Nowadays the traffic between the left and right banks of the Dnipro River in Zaporizhya is provided by
two road-rail Preobrazhenskyi bridges, constructed in 1953, with one lane in each direction, as well as
on the roadway of the dam of the Dnipro HYES.
The current technical condition of Preobrazhensky bridges is in terrible situation. To this day they have
never been capitally repaired, affecting the reduction of bearing capacity of bridges and in future it may
cause industrial disaster.
24. The results expected from the projectThe results expected from the project
The project is designed to solve the transport problems of the city of
Zaporizhzhia, namely the lack of reliable transport communication between
left-bank and right-bank parts of the city and the right bank and left bank of
south-eastern parts of Ukraine and solve engineering and communication
problems of National Reserve "Khortytsya" considering its status, values and
concepts of the island Khortytsya as a reserve.
Proposed for implementation in 2017 construction and repair works on 5
constructions will open traffic direction to the Reserve "Khortytsya" and solve
the above-mentioned problem with transport communication.
25. Plan the projectPlan the project
Planned arrangements
Total funded
01/01/2016
Plan
for 2017
(ths. UAH)
Plan
for 2018
(ths. UAH)
Plan
for 2019
(ths. UAH)
Adjustment of construction
documents
Execution of construction
work
The diversion of land and
compensation for losses to land
users
Other activities within the
development phase
(supervision, maintenance of
customer service, scientific
support of design work and
construction, etc.)
Total funded:
Total (in years):
TOTAL (demand from the State budget):
TOTAL (the cost of the whole project):
26. The plan of the project in 2017The plan of the project in 2017
Activities
Provided indicators under the state investments project
Planned deadlines Cost (thousand. UAH).
Land allocation, land surveying work January-December 2017 70,00
Design and survey work
adjustment of the "Project“ phase
development of working documentation
January-December 2017 13 879,60
січень-жовтень 2017 12 879,60
January-December 2017 1 800,00
Examination of the adjusted Project phase
листопад-грудень 2017 999,60
Construction works
construction of engineering structures: January-December 2017 89 030,00
Construction number 1 (highway and railroad overpass - exit from
Radyanskyi ave, total length of 135 m) January-December 2017 4000,00
Construction number 2 (railroad overpass, total length of 45.2 m) January-December 2017 500,00
The construction number 3 (overpass to the construction №4, total
length of 289.3 m) January-December 2017 33 010,00
Construction number 4 (girder bridge over the river Old Dnipro,
total length of 340.6 m) January-December 2017 28 220,00
The construction number 5 (346.6 m length overpass to the island
Khortytsya on contiguity to Construction №4) January-December 2017 23 300,00
Supervision
January-December 2017 120,00
Maintenance of customer service January-December 2017 1 266,36
Scientific support of project work and construction January-December 2017 200,00
Total 105 565,56
27. THANK YOU FOR THETHANK YOU FOR THE
ATTENTION!ATTENTION!
Kyiv, 2016
The State Agency of Ukraine roads