SlideShare a Scribd company logo
1 of 22
DBS – A1 Filing Cabinet Project
Presented to
DBS Management
03 April 2012
Alan Kearney
Tom Murphy
Michal Hadjec
“Plan Your Work – Work Your Plan!”
2
“Plan Your Work – Work Your Plan”
Contents
1. Overview
2. Project Feasibility
3. SWOT Analysis
4. Evaluating the Project
5. The Project Plan
6. Project Risks
7. Leadership Issues
8. Communications Challenges
9. Q&A
3
“Plan Your Work – Work Your Plan”
Project Overview
Project Timeline
4
“Plan Your Work – Work Your Plan”
Feasability
€
€
5
“Plan Your Work – Work Your Plan”
SWOT Analysis
External
Focus
Internal
Focus
Strengths
• High Quality Capability
• Automated Manufacturing
• Skilled Staff
Weaknesses
• Medium Capability
• Breadth of Experience
• Location Presence
Opportunities
• Good Reputation
• Strong relationship with A1
• Develop online experience
• Greater revenue streams
Threats
• Damage to A1 relationship if
project fails
• Future Demand greater than
Manufacturing Capability
6
“Plan Your Work – Work Your Plan”
Cost-Benefit Analysis
Preliminary Budget
Indicates not feasible from financial viewpoint
Product Unit Costs = €623
Specified Unit Costs = €100
Unit Costs - one-off Design Costs = €262
Business Benefits
Project Success could generate significant new business
Recommendation
DBS should accept this project.
7
“Plan Your Work – Work Your Plan”
Evaluating the Project
8
“Plan Your Work – Work Your Plan”
Evaluating the Project
Item Measured Metric Measurement Formula Target Acceptable Tolerance
Budget Cost Variance Earned Value less Actual Costs CV=EV-AC 0 +/- 10%
Budget Cost Performance Index
Earned Value divided by Actual
Costs
CPI=EV/AC >1 +/- 10%
Budget Estimate at Completion Total costs at current performance EAC=BAC/CPI =Baseline +/- 10%
Budget Estimate to Complete Estimated remaining Costs ETC=EAC-AC =Baseline +/- 10%
Schedule Schedule Variance Earned Value Less Planned Value SV=EV-PV 0 +/- 10%
Schedule
Schedule Performance
Index
Earned Value divided by Planned
Value
SPI=EV/PV >1 +/- 10%
Scope :
Product Requirements
Variance of Quality
control limits
Qualaity Tolerance Range Mean of tolerance measures
within upper and
lower limits
Anywhere within
control limits
Scope: Project Activities Work Items completed % Work Items Completed
No. of work items completed /
No. of Scheduled work items
1
No Tolerance allowed
Product Quality
Defects per Batch
(manufactured
components)
% defects per manufactured batch
No. of defects /No. of
components sampled
0
No Tolerance allowed
Customer Satisfaction Rating Customer Satisfaction Rating Average of responses Top Box No Tolerance allowed
Employee Satisfaction Rating Employee Satisfaction Rating Average of responses Top Box No Tolerance allowed
• Metrics defined during Planning
• Used during Execution and Control
9
“Plan Your Work – Work Your Plan”
Evaluating Project
10
“Plan Your Work – Work Your Plan”
The Project Plan
11
“Plan Your Work – Work Your Plan”
Milestones against Timeline
12
“Plan Your Work – Work Your Plan”
Network Schedule Diagram
13
“Plan Your Work – Work Your Plan”
Budget – Weekly Breakdown €
14
“Plan Your Work – Work Your Plan”
Scope
ReqID UserRequirement FucntionalRequirement Priority Version Status ForwardsTraceability BackwardsTraceability
DateVerified
(Internal
Validation)
DateAccepted
(Customer
Signoff/Acceptance
R005
Self-Assembly
Capability
Abilityforallcomponentstobeassembled
easilyandquickly(timetobedefined)
1 v.001 Active R010 R001,R002,R003
DBSManaufacturingRequirmentsTraceabilityMatrix-SampleEntry
• High-Quality Project
• Needs Strong Requirements Management Process
15
“Plan Your Work – Work Your Plan”
Scope Management
16
“Plan Your Work – Work Your Plan”
Risk Management
17
“Plan Your Work – Work Your Plan”
Risk Management
• Minimising impact of risk is the important thing
– Rather than the realisation of a risk
• Risk Management is an iterative process
– Not a Once-Off thing
• A1 Filing Cabinets project is a High-Risk Project
18
“Plan Your Work – Work Your Plan”
Major Risks
19
“Plan Your Work – Work Your Plan”
Leadership
20
“Plan Your Work – Work Your Plan”
Communciation
21
“Plan Your Work – Work Your Plan”
RACI Chart
ProjectSponsor
ProjectManager
FunctionalManager-
Manufacturing
ProductionManager
ProductDesigner
Manufacturing
Supervisor-Plastic
Manufacturing
Supervisor-Metal
SafetyEngineer
PlasticEngineer
MetalFabricator
AssemblyOperator
PackagingOperator
LegalCouncil
Strategic Alignment A R c I I
Budget Approval R,A C I I
Project Planning A R I I I I
Project Performance A R C C C C C
Project Reporting C R I I I I I
Risk Management I R,A I I I I I I
Quality Assurance I A R R C C C I
Quality Control I A R R R R R I I I I
Product Design A C C R C C
Product Testing A R R C C C I I I
Manufacturing
Operations
A R C C I I I I I I I
Health & Safety I A C C I C C R I I I I C
Assembly Operations A C C I R R I
Packaging Operations C C C I A A I R
Project Procurements A,R C C I I
Project Dispatching C C C I A A I R
Product Delivery A C R I I I
Customer Liaison I A,R C C I
Legal Services A C R
RACI Chart for a1 Filing Cabinets Project
R Responsible Responsible for Completing the work
A Accountable Accountable for ensuring the work is completed as expected
C Consulted Consulted prior to final decisionor action being taken
I Informed Informed of decisions or actions taken
RACI DESCRIPTION
22
“Plan Your Work – Work Your Plan”
Summary
and
Q&A

More Related Content

What's hot

Project Status Presentation One Pager Presentation Report Infographic Ppt Pdf...
Project Status Presentation One Pager Presentation Report Infographic Ppt Pdf...Project Status Presentation One Pager Presentation Report Infographic Ppt Pdf...
Project Status Presentation One Pager Presentation Report Infographic Ppt Pdf...SlideTeam
 
Vinod cv offshore
Vinod cv offshoreVinod cv offshore
Vinod cv offshorevinod kumar
 
Agile vs Waterfall Project Management Presentation
Agile vs Waterfall Project Management PresentationAgile vs Waterfall Project Management Presentation
Agile vs Waterfall Project Management PresentationPrateek Sharma
 
The Project Status & The Portfolio
The Project Status & The PortfolioThe Project Status & The Portfolio
The Project Status & The PortfolioNed Johnson
 
Project Workforce Management PowerPoint Presentation Slides
Project Workforce Management PowerPoint Presentation SlidesProject Workforce Management PowerPoint Presentation Slides
Project Workforce Management PowerPoint Presentation SlidesSlideTeam
 
Basis of Estimate Processes
Basis of Estimate ProcessesBasis of Estimate Processes
Basis of Estimate ProcessesGlen Alleman
 
Julia Korytko. Fixed Price Projects
Julia Korytko. Fixed Price ProjectsJulia Korytko. Fixed Price Projects
Julia Korytko. Fixed Price ProjectsLviv Startup Club
 
Responsible for overall project management
Responsible for overall project managementResponsible for overall project management
Responsible for overall project managementRajiv Singh
 
Are you forecasting your construction project costs
Are you forecasting your construction project costsAre you forecasting your construction project costs
Are you forecasting your construction project costsEd Williams
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration ManagementSerdar Temiz
 
Project audit and closure
Project audit and closureProject audit and closure
Project audit and closureSanjay Vaij
 
Project Brief PowerPoint Presentation Slides
Project Brief PowerPoint Presentation Slides Project Brief PowerPoint Presentation Slides
Project Brief PowerPoint Presentation Slides SlideTeam
 
Essam lotffy this project is not in line with organizational strategic plans
Essam lotffy   this project is not in line with organizational strategic plansEssam lotffy   this project is not in line with organizational strategic plans
Essam lotffy this project is not in line with organizational strategic plansEssam Lotffy, PMP®, CCP®
 
Project Status Determination (GYR Method)
Project Status Determination (GYR Method)Project Status Determination (GYR Method)
Project Status Determination (GYR Method)Marcello Brivio
 
Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...Harold van Heeringen
 

What's hot (20)

Project Status Presentation One Pager Presentation Report Infographic Ppt Pdf...
Project Status Presentation One Pager Presentation Report Infographic Ppt Pdf...Project Status Presentation One Pager Presentation Report Infographic Ppt Pdf...
Project Status Presentation One Pager Presentation Report Infographic Ppt Pdf...
 
Vinod cv offshore
Vinod cv offshoreVinod cv offshore
Vinod cv offshore
 
Agile vs Waterfall Project Management Presentation
Agile vs Waterfall Project Management PresentationAgile vs Waterfall Project Management Presentation
Agile vs Waterfall Project Management Presentation
 
The Project Status & The Portfolio
The Project Status & The PortfolioThe Project Status & The Portfolio
The Project Status & The Portfolio
 
Dev area wip
Dev area wipDev area wip
Dev area wip
 
Project Workforce Management PowerPoint Presentation Slides
Project Workforce Management PowerPoint Presentation SlidesProject Workforce Management PowerPoint Presentation Slides
Project Workforce Management PowerPoint Presentation Slides
 
Basis of Estimate Processes
Basis of Estimate ProcessesBasis of Estimate Processes
Basis of Estimate Processes
 
Lauren Putthoff Resume
Lauren Putthoff ResumeLauren Putthoff Resume
Lauren Putthoff Resume
 
Julia Korytko. Fixed Price Projects
Julia Korytko. Fixed Price ProjectsJulia Korytko. Fixed Price Projects
Julia Korytko. Fixed Price Projects
 
Cost estimating
Cost estimatingCost estimating
Cost estimating
 
Responsible for overall project management
Responsible for overall project managementResponsible for overall project management
Responsible for overall project management
 
Are you forecasting your construction project costs
Are you forecasting your construction project costsAre you forecasting your construction project costs
Are you forecasting your construction project costs
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
 
Project audit and closure
Project audit and closureProject audit and closure
Project audit and closure
 
Project Brief PowerPoint Presentation Slides
Project Brief PowerPoint Presentation Slides Project Brief PowerPoint Presentation Slides
Project Brief PowerPoint Presentation Slides
 
Essam lotffy this project is not in line with organizational strategic plans
Essam lotffy   this project is not in line with organizational strategic plansEssam lotffy   this project is not in line with organizational strategic plans
Essam lotffy this project is not in line with organizational strategic plans
 
Project Status Determination (GYR Method)
Project Status Determination (GYR Method)Project Status Determination (GYR Method)
Project Status Determination (GYR Method)
 
John Reilly
John ReillyJohn Reilly
John Reilly
 
Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...
 
CV_Ashwini
CV_AshwiniCV_Ashwini
CV_Ashwini
 

Similar to Project presentation - Filing Cabinet Project

Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementBiju Nair
 
Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen...
 Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen... Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen...
Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen...Lviv Startup Club
 
Андрій Мудрий «Risk managemnt: Welcome to Risk World»
Андрій Мудрий «Risk managemnt: Welcome to Risk World»Андрій Мудрий «Risk managemnt: Welcome to Risk World»
Андрій Мудрий «Risk managemnt: Welcome to Risk World»Lviv Startup Club
 
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...Project Controls Expo
 
Managing Projects with Intelligence
Managing Projects with IntelligenceManaging Projects with Intelligence
Managing Projects with IntelligencePaul Gerrard
 
Apple campus 2 Project management
Apple campus 2 Project managementApple campus 2 Project management
Apple campus 2 Project managementKavan Tadhani
 
Creating high performance project teams 2013
Creating high performance project teams   2013Creating high performance project teams   2013
Creating high performance project teams 2013Edward Byers, PMP, SSGB
 
Risk Management ProcessTraining Session Victor Allen.docx
Risk Management ProcessTraining Session Victor Allen.docxRisk Management ProcessTraining Session Victor Allen.docx
Risk Management ProcessTraining Session Victor Allen.docxSUBHI7
 
Project Management Sample
Project Management SampleProject Management Sample
Project Management SampleRavi Nakulan
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure CycleGlen Alleman
 
Project Feasibility [DECEMBER 2006]
Project Feasibility [DECEMBER 2006]Project Feasibility [DECEMBER 2006]
Project Feasibility [DECEMBER 2006]Fahad Mahmud Mirza
 
BioPharma Projects: Essentials in Project Controls
BioPharma Projects: Essentials in Project ControlsBioPharma Projects: Essentials in Project Controls
BioPharma Projects: Essentials in Project ControlsPMA Consultants
 
Quality & the Construction Contractor
Quality & the Construction ContractorQuality & the Construction Contractor
Quality & the Construction ContractorDPSchneider
 
Catalyze Webcast - Surefire Stakeholder Communication Strategy - Carkenord - ...
Catalyze Webcast - Surefire Stakeholder Communication Strategy - Carkenord - ...Catalyze Webcast - Surefire Stakeholder Communication Strategy - Carkenord - ...
Catalyze Webcast - Surefire Stakeholder Communication Strategy - Carkenord - ...Tom Humbarger
 
From Problems to Solutions in Capital Construction
From Problems to Solutions in Capital ConstructionFrom Problems to Solutions in Capital Construction
From Problems to Solutions in Capital ConstructionChris Keyack
 
QA Fest 2017. Ирина Жилинская. Тестирование основанное на рисках в реальности...
QA Fest 2017. Ирина Жилинская. Тестирование основанное на рисках в реальности...QA Fest 2017. Ирина Жилинская. Тестирование основанное на рисках в реальности...
QA Fest 2017. Ирина Жилинская. Тестирование основанное на рисках в реальности...QAFest
 
The project plan
The project planThe project plan
The project planVatsalaPG
 

Similar to Project presentation - Filing Cabinet Project (20)

Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Risk Management
Risk Management Risk Management
Risk Management
 
Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen...
 Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen... Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen...
Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen...
 
Андрій Мудрий «Risk managemnt: Welcome to Risk World»
Андрій Мудрий «Risk managemnt: Welcome to Risk World»Андрій Мудрий «Risk managemnt: Welcome to Risk World»
Андрій Мудрий «Risk managemnt: Welcome to Risk World»
 
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
 
Managing Projects with Intelligence
Managing Projects with IntelligenceManaging Projects with Intelligence
Managing Projects with Intelligence
 
Apple campus 2 Project management
Apple campus 2 Project managementApple campus 2 Project management
Apple campus 2 Project management
 
Creating high performance project teams 2013
Creating high performance project teams   2013Creating high performance project teams   2013
Creating high performance project teams 2013
 
Risk Management ProcessTraining Session Victor Allen.docx
Risk Management ProcessTraining Session Victor Allen.docxRisk Management ProcessTraining Session Victor Allen.docx
Risk Management ProcessTraining Session Victor Allen.docx
 
Project Management Sample
Project Management SampleProject Management Sample
Project Management Sample
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure Cycle
 
Project Feasibility [DECEMBER 2006]
Project Feasibility [DECEMBER 2006]Project Feasibility [DECEMBER 2006]
Project Feasibility [DECEMBER 2006]
 
A Framework for Managing Project Risk
A Framework for Managing Project RiskA Framework for Managing Project Risk
A Framework for Managing Project Risk
 
Managing Project Success
Managing Project SuccessManaging Project Success
Managing Project Success
 
BioPharma Projects: Essentials in Project Controls
BioPharma Projects: Essentials in Project ControlsBioPharma Projects: Essentials in Project Controls
BioPharma Projects: Essentials in Project Controls
 
Quality & the Construction Contractor
Quality & the Construction ContractorQuality & the Construction Contractor
Quality & the Construction Contractor
 
Catalyze Webcast - Surefire Stakeholder Communication Strategy - Carkenord - ...
Catalyze Webcast - Surefire Stakeholder Communication Strategy - Carkenord - ...Catalyze Webcast - Surefire Stakeholder Communication Strategy - Carkenord - ...
Catalyze Webcast - Surefire Stakeholder Communication Strategy - Carkenord - ...
 
From Problems to Solutions in Capital Construction
From Problems to Solutions in Capital ConstructionFrom Problems to Solutions in Capital Construction
From Problems to Solutions in Capital Construction
 
QA Fest 2017. Ирина Жилинская. Тестирование основанное на рисках в реальности...
QA Fest 2017. Ирина Жилинская. Тестирование основанное на рисках в реальности...QA Fest 2017. Ирина Жилинская. Тестирование основанное на рисках в реальности...
QA Fest 2017. Ирина Жилинская. Тестирование основанное на рисках в реальности...
 
The project plan
The project planThe project plan
The project plan
 

More from Michal Harcej

Nano coatings great benefit or great risk - hidden danger behind nano coatings
Nano coatings   great benefit or great risk - hidden danger behind nano coatingsNano coatings   great benefit or great risk - hidden danger behind nano coatings
Nano coatings great benefit or great risk - hidden danger behind nano coatingsMichal Harcej
 
NanoMagic- Managing and Motivation Report
NanoMagic- Managing and Motivation ReportNanoMagic- Managing and Motivation Report
NanoMagic- Managing and Motivation ReportMichal Harcej
 
International Marketing Plan - ETICS
International Marketing Plan - ETICS International Marketing Plan - ETICS
International Marketing Plan - ETICS Michal Harcej
 
Product catalloge self cleanimg coatings
Product catalloge self cleanimg coatingsProduct catalloge self cleanimg coatings
Product catalloge self cleanimg coatingsMichal Harcej
 
ETICS External Thermal Insulation Composite Systems
ETICS External Thermal Insulation Composite SystemsETICS External Thermal Insulation Composite Systems
ETICS External Thermal Insulation Composite SystemsMichal Harcej
 

More from Michal Harcej (6)

Magic IQ Coat
Magic IQ CoatMagic IQ Coat
Magic IQ Coat
 
Nano coatings great benefit or great risk - hidden danger behind nano coatings
Nano coatings   great benefit or great risk - hidden danger behind nano coatingsNano coatings   great benefit or great risk - hidden danger behind nano coatings
Nano coatings great benefit or great risk - hidden danger behind nano coatings
 
NanoMagic- Managing and Motivation Report
NanoMagic- Managing and Motivation ReportNanoMagic- Managing and Motivation Report
NanoMagic- Managing and Motivation Report
 
International Marketing Plan - ETICS
International Marketing Plan - ETICS International Marketing Plan - ETICS
International Marketing Plan - ETICS
 
Product catalloge self cleanimg coatings
Product catalloge self cleanimg coatingsProduct catalloge self cleanimg coatings
Product catalloge self cleanimg coatings
 
ETICS External Thermal Insulation Composite Systems
ETICS External Thermal Insulation Composite SystemsETICS External Thermal Insulation Composite Systems
ETICS External Thermal Insulation Composite Systems
 

Recently uploaded

Using AI to boost productivity for developers
Using AI to boost productivity for developersUsing AI to boost productivity for developers
Using AI to boost productivity for developersTeri Eyenike
 
Call Girls Near The Byke Suraj Plaza Mumbai »¡¡ 07506202331¡¡« R.K. Mumbai
Call Girls Near The Byke Suraj Plaza Mumbai »¡¡ 07506202331¡¡« R.K. MumbaiCall Girls Near The Byke Suraj Plaza Mumbai »¡¡ 07506202331¡¡« R.K. Mumbai
Call Girls Near The Byke Suraj Plaza Mumbai »¡¡ 07506202331¡¡« R.K. MumbaiPriya Reddy
 
Digital collaboration with Microsoft 365 as extension of Drupal
Digital collaboration with Microsoft 365 as extension of DrupalDigital collaboration with Microsoft 365 as extension of Drupal
Digital collaboration with Microsoft 365 as extension of DrupalFabian de Rijk
 
Uncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac FolorunsoUncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac FolorunsoKayode Fayemi
 
Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...
Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...
Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...ZurliaSoop
 
"I hear you": Moving beyond empathy in UXR
"I hear you": Moving beyond empathy in UXR"I hear you": Moving beyond empathy in UXR
"I hear you": Moving beyond empathy in UXRMegan Campos
 
BEAUTIFUL PLACES TO VISIT IN LESOTHO.pptx
BEAUTIFUL PLACES TO VISIT IN LESOTHO.pptxBEAUTIFUL PLACES TO VISIT IN LESOTHO.pptx
BEAUTIFUL PLACES TO VISIT IN LESOTHO.pptxthusosetemere
 
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdf
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdfAWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdf
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdfSkillCertProExams
 
History of Morena Moshoeshoe birth death
History of Morena Moshoeshoe birth deathHistory of Morena Moshoeshoe birth death
History of Morena Moshoeshoe birth deathphntsoaki
 
lONG QUESTION ANSWER PAKISTAN STUDIES10.
lONG QUESTION ANSWER PAKISTAN STUDIES10.lONG QUESTION ANSWER PAKISTAN STUDIES10.
lONG QUESTION ANSWER PAKISTAN STUDIES10.lodhisaajjda
 
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...David Celestin
 
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdf
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdfSOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdf
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdfMahamudul Hasan
 
ECOLOGY OF FISHES.pptx full presentation
ECOLOGY OF FISHES.pptx full presentationECOLOGY OF FISHES.pptx full presentation
ECOLOGY OF FISHES.pptx full presentationFahadFazal7
 
Unlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven Curiosity
Unlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven CuriosityUnlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven Curiosity
Unlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven CuriosityHung Le
 
Introduction to Artificial intelligence.
Introduction to Artificial intelligence.Introduction to Artificial intelligence.
Introduction to Artificial intelligence.thamaeteboho94
 
BIG DEVELOPMENTS IN LESOTHO(DAMS & MINES
BIG DEVELOPMENTS IN LESOTHO(DAMS & MINESBIG DEVELOPMENTS IN LESOTHO(DAMS & MINES
BIG DEVELOPMENTS IN LESOTHO(DAMS & MINESfuthumetsaneliswa
 
Ready Set Go Children Sermon about Mark 16:15-20
Ready Set Go Children Sermon about Mark 16:15-20Ready Set Go Children Sermon about Mark 16:15-20
Ready Set Go Children Sermon about Mark 16:15-20rejz122017
 

Recently uploaded (20)

Using AI to boost productivity for developers
Using AI to boost productivity for developersUsing AI to boost productivity for developers
Using AI to boost productivity for developers
 
Call Girls Near The Byke Suraj Plaza Mumbai »¡¡ 07506202331¡¡« R.K. Mumbai
Call Girls Near The Byke Suraj Plaza Mumbai »¡¡ 07506202331¡¡« R.K. MumbaiCall Girls Near The Byke Suraj Plaza Mumbai »¡¡ 07506202331¡¡« R.K. Mumbai
Call Girls Near The Byke Suraj Plaza Mumbai »¡¡ 07506202331¡¡« R.K. Mumbai
 
ICT role in 21st century education and it's challenges.pdf
ICT role in 21st century education and it's challenges.pdfICT role in 21st century education and it's challenges.pdf
ICT role in 21st century education and it's challenges.pdf
 
Digital collaboration with Microsoft 365 as extension of Drupal
Digital collaboration with Microsoft 365 as extension of DrupalDigital collaboration with Microsoft 365 as extension of Drupal
Digital collaboration with Microsoft 365 as extension of Drupal
 
Uncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac FolorunsoUncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac Folorunso
 
Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...
Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...
Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...
 
"I hear you": Moving beyond empathy in UXR
"I hear you": Moving beyond empathy in UXR"I hear you": Moving beyond empathy in UXR
"I hear you": Moving beyond empathy in UXR
 
BEAUTIFUL PLACES TO VISIT IN LESOTHO.pptx
BEAUTIFUL PLACES TO VISIT IN LESOTHO.pptxBEAUTIFUL PLACES TO VISIT IN LESOTHO.pptx
BEAUTIFUL PLACES TO VISIT IN LESOTHO.pptx
 
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdf
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdfAWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdf
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdf
 
History of Morena Moshoeshoe birth death
History of Morena Moshoeshoe birth deathHistory of Morena Moshoeshoe birth death
History of Morena Moshoeshoe birth death
 
lONG QUESTION ANSWER PAKISTAN STUDIES10.
lONG QUESTION ANSWER PAKISTAN STUDIES10.lONG QUESTION ANSWER PAKISTAN STUDIES10.
lONG QUESTION ANSWER PAKISTAN STUDIES10.
 
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
 
Abortion Pills Fahaheel ௹+918133066128💬@ Safe and Effective Mifepristion and ...
Abortion Pills Fahaheel ௹+918133066128💬@ Safe and Effective Mifepristion and ...Abortion Pills Fahaheel ௹+918133066128💬@ Safe and Effective Mifepristion and ...
Abortion Pills Fahaheel ௹+918133066128💬@ Safe and Effective Mifepristion and ...
 
in kuwait௹+918133066128....) @abortion pills for sale in Kuwait City
in kuwait௹+918133066128....) @abortion pills for sale in Kuwait Cityin kuwait௹+918133066128....) @abortion pills for sale in Kuwait City
in kuwait௹+918133066128....) @abortion pills for sale in Kuwait City
 
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdf
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdfSOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdf
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdf
 
ECOLOGY OF FISHES.pptx full presentation
ECOLOGY OF FISHES.pptx full presentationECOLOGY OF FISHES.pptx full presentation
ECOLOGY OF FISHES.pptx full presentation
 
Unlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven Curiosity
Unlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven CuriosityUnlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven Curiosity
Unlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven Curiosity
 
Introduction to Artificial intelligence.
Introduction to Artificial intelligence.Introduction to Artificial intelligence.
Introduction to Artificial intelligence.
 
BIG DEVELOPMENTS IN LESOTHO(DAMS & MINES
BIG DEVELOPMENTS IN LESOTHO(DAMS & MINESBIG DEVELOPMENTS IN LESOTHO(DAMS & MINES
BIG DEVELOPMENTS IN LESOTHO(DAMS & MINES
 
Ready Set Go Children Sermon about Mark 16:15-20
Ready Set Go Children Sermon about Mark 16:15-20Ready Set Go Children Sermon about Mark 16:15-20
Ready Set Go Children Sermon about Mark 16:15-20
 

Project presentation - Filing Cabinet Project

  • 1. DBS – A1 Filing Cabinet Project Presented to DBS Management 03 April 2012 Alan Kearney Tom Murphy Michal Hadjec “Plan Your Work – Work Your Plan!”
  • 2. 2 “Plan Your Work – Work Your Plan” Contents 1. Overview 2. Project Feasibility 3. SWOT Analysis 4. Evaluating the Project 5. The Project Plan 6. Project Risks 7. Leadership Issues 8. Communications Challenges 9. Q&A
  • 3. 3 “Plan Your Work – Work Your Plan” Project Overview Project Timeline
  • 4. 4 “Plan Your Work – Work Your Plan” Feasability € €
  • 5. 5 “Plan Your Work – Work Your Plan” SWOT Analysis External Focus Internal Focus Strengths • High Quality Capability • Automated Manufacturing • Skilled Staff Weaknesses • Medium Capability • Breadth of Experience • Location Presence Opportunities • Good Reputation • Strong relationship with A1 • Develop online experience • Greater revenue streams Threats • Damage to A1 relationship if project fails • Future Demand greater than Manufacturing Capability
  • 6. 6 “Plan Your Work – Work Your Plan” Cost-Benefit Analysis Preliminary Budget Indicates not feasible from financial viewpoint Product Unit Costs = €623 Specified Unit Costs = €100 Unit Costs - one-off Design Costs = €262 Business Benefits Project Success could generate significant new business Recommendation DBS should accept this project.
  • 7. 7 “Plan Your Work – Work Your Plan” Evaluating the Project
  • 8. 8 “Plan Your Work – Work Your Plan” Evaluating the Project Item Measured Metric Measurement Formula Target Acceptable Tolerance Budget Cost Variance Earned Value less Actual Costs CV=EV-AC 0 +/- 10% Budget Cost Performance Index Earned Value divided by Actual Costs CPI=EV/AC >1 +/- 10% Budget Estimate at Completion Total costs at current performance EAC=BAC/CPI =Baseline +/- 10% Budget Estimate to Complete Estimated remaining Costs ETC=EAC-AC =Baseline +/- 10% Schedule Schedule Variance Earned Value Less Planned Value SV=EV-PV 0 +/- 10% Schedule Schedule Performance Index Earned Value divided by Planned Value SPI=EV/PV >1 +/- 10% Scope : Product Requirements Variance of Quality control limits Qualaity Tolerance Range Mean of tolerance measures within upper and lower limits Anywhere within control limits Scope: Project Activities Work Items completed % Work Items Completed No. of work items completed / No. of Scheduled work items 1 No Tolerance allowed Product Quality Defects per Batch (manufactured components) % defects per manufactured batch No. of defects /No. of components sampled 0 No Tolerance allowed Customer Satisfaction Rating Customer Satisfaction Rating Average of responses Top Box No Tolerance allowed Employee Satisfaction Rating Employee Satisfaction Rating Average of responses Top Box No Tolerance allowed • Metrics defined during Planning • Used during Execution and Control
  • 9. 9 “Plan Your Work – Work Your Plan” Evaluating Project
  • 10. 10 “Plan Your Work – Work Your Plan” The Project Plan
  • 11. 11 “Plan Your Work – Work Your Plan” Milestones against Timeline
  • 12. 12 “Plan Your Work – Work Your Plan” Network Schedule Diagram
  • 13. 13 “Plan Your Work – Work Your Plan” Budget – Weekly Breakdown €
  • 14. 14 “Plan Your Work – Work Your Plan” Scope ReqID UserRequirement FucntionalRequirement Priority Version Status ForwardsTraceability BackwardsTraceability DateVerified (Internal Validation) DateAccepted (Customer Signoff/Acceptance R005 Self-Assembly Capability Abilityforallcomponentstobeassembled easilyandquickly(timetobedefined) 1 v.001 Active R010 R001,R002,R003 DBSManaufacturingRequirmentsTraceabilityMatrix-SampleEntry • High-Quality Project • Needs Strong Requirements Management Process
  • 15. 15 “Plan Your Work – Work Your Plan” Scope Management
  • 16. 16 “Plan Your Work – Work Your Plan” Risk Management
  • 17. 17 “Plan Your Work – Work Your Plan” Risk Management • Minimising impact of risk is the important thing – Rather than the realisation of a risk • Risk Management is an iterative process – Not a Once-Off thing • A1 Filing Cabinets project is a High-Risk Project
  • 18. 18 “Plan Your Work – Work Your Plan” Major Risks
  • 19. 19 “Plan Your Work – Work Your Plan” Leadership
  • 20. 20 “Plan Your Work – Work Your Plan” Communciation
  • 21. 21 “Plan Your Work – Work Your Plan” RACI Chart ProjectSponsor ProjectManager FunctionalManager- Manufacturing ProductionManager ProductDesigner Manufacturing Supervisor-Plastic Manufacturing Supervisor-Metal SafetyEngineer PlasticEngineer MetalFabricator AssemblyOperator PackagingOperator LegalCouncil Strategic Alignment A R c I I Budget Approval R,A C I I Project Planning A R I I I I Project Performance A R C C C C C Project Reporting C R I I I I I Risk Management I R,A I I I I I I Quality Assurance I A R R C C C I Quality Control I A R R R R R I I I I Product Design A C C R C C Product Testing A R R C C C I I I Manufacturing Operations A R C C I I I I I I I Health & Safety I A C C I C C R I I I I C Assembly Operations A C C I R R I Packaging Operations C C C I A A I R Project Procurements A,R C C I I Project Dispatching C C C I A A I R Product Delivery A C R I I I Customer Liaison I A,R C C I Legal Services A C R RACI Chart for a1 Filing Cabinets Project R Responsible Responsible for Completing the work A Accountable Accountable for ensuring the work is completed as expected C Consulted Consulted prior to final decisionor action being taken I Informed Informed of decisions or actions taken RACI DESCRIPTION
  • 22. 22 “Plan Your Work – Work Your Plan” Summary and Q&A