SlideShare a Scribd company logo
1 of 6
Download to read offline
Comparative Evaluation of Alternative Methods for the
Construction of Underground Car Parks
Meliti Pappa1
, Andreas Benardos2
1
Civil Engineeer, MSc, Greece
2
Mining Engineer, PhD, Lab. of Mining & Environmental Technology – NTUA, Greece
ABSTRACT
The present paper focuses on the comparison between the alternative methods of constructing
underground parking spaces. It analyses and compares the “cut-and-cover” method, a most common
method for the construction of underground parking stations, with the “room-and-pillar” method
originating from the mining sector which also exhibits equally satisfactory results. This evaluation
takes into account the applicability of each method in relation to the ground conditions, their ease of
use, as well as their performance in terms of financial efficiency during construction. The assessment
is made using reference projects as input. More specifically, the construction costs of three
underground car-stations, constructed with the “cut-and-cover” method are compared with the
construction costs of three other underground car-stations which were designed following the “room-
and-pillar” method principles. Their key elements are recognized and major cost components are
evaluated in a head to head analysis.
1. IMPORTANCE OF PARKING SPACES – UNDERGROUND CAR PARKS
Car plays an important role to modern societies as it is a comfortable and fast mean of transport.
However, its usefulness and service degree depends particularly on the sufficiency of suitable parking
spaces. The importance of “parking” is evident from the space that is provided and the time that a car
is found parked in relation to the time of its movement. Thus, a passenger car requires a parking area
of approximately 25 m2
, including the essential areas for gaining access and manoeuvres, while the
time it remains parked is more than 90% of the total.
However, the lack of parking spaces is one of the most significant problems that large urban centres
face today. This fact has lead to particularly negative consequences in the life and style of the cities
because of the traffic jams and long delays, as well as the environmental pollution.
The utilisation of the subsurface with the establishment of underground car parks has been proposed as
a measure to alleviate the lack of parking space in urban areas and today, along with the underground
transit systems (metros, etc.), can be characterised as the most typical form of underground
development (Kaliampakos D., 2003). The advantages that such facilities offer are significant and
their use is widespread. In particular, they contribute to the environmental protection, as valuable
surface space can be preserved and the visual annoyance is minimal, assisting in the improvement of
the quality of the city life, and at the same time they can provide a safe environment with high
availability since their construction could take place almost anywhere (Tareau, J.P., 1995).
Nevertheless, underground car parks have to deal with a high construction and service cost, in relation
to aboveground solutions, because of the increased need for support, lightning and ventilation. That
issue puts forth the necessity to further investigate solutions capable of offering lower costs without on
the same time affecting the efficiency of underground car parks.
2. UNDERGROUND CAR PARKS - “CUT-AND-COVER” METHOD
2.1. General outline – Cases examined
This method, which is commonly used for the construction of underground parking areas, is quite
flexible and it requires simple mechanical equipment. For the support of the cutting perimetric walls,
steel strands or reinforced concrete, or tensile anchors are used. Cut and cover is easily adapted on the
loose soil of top layers while in exceptional cases also in hard soil.
In recent years a booming in the development of underground car parks following this method was
experienced in Greece and in Athens in particular. In Table 1 the characteristics of three underground
garages are presented, (J.&P., 2002) namely the stations of Paidon Hospital square (Fig. 1a), Rizari
street, and finally Kanigos Square (Fig 1b). These car parks are located under public squares, having a
total capacity ranging from 500 to 650 parking places, covering a surface of about 17,000 m2
allocated
in 4-5 floors.
Parking Station Surface (m2
) Volume (m3
) Floors Capacity (cars)
Paidon Hospital Square 17,433 54,764 5 576
Rizari Street 18,997 56,339 4 664
Kaniggos Square 15,401 49,283 4 491
Table 1. Characteristics of underground car parks constructed following the cut-and-cover method.
Fig. 1. Underground car stations in Athens. (a) Vehicle entry point of the Paidon Hospital Square car
park; (b) Ground plan of the car station developed under the Kanjgos Square.
2.2. Cost Analysis – Key issues
The cost analysis of the underground car parks are based on the as-build cost data and concern the
cost of individual construction phases of the Paidon Hospital Square and Rizari Street stations, as well
as the total construction cost of the three stations. Therefore the comparison is aiming not only at
providing general cost assumptions but also at identifying key factors which affect the construction
process and differentiate the project’s cost.
Parking Station Total Cost (x103
€) Cost/parking place (€) Cost/m2
(€)
Paidon Hospital Square 5,283 9,170 303
Rizari Street 4,830 7,275 254
Kaniggos Square 9,856 20,075 640
Table 2. Cost data of the cut-and-cover underground car stations in Athens.
Even though there are differentiations between the examined “cut-and-cover” projects, and each car
park has unique design features, the expenditure allocation of the construction costs are distributed
roughly at the same cost components. Thus, the cost of the concrete works is the most important one,
reaching almost to the 30% of the total cost, followed by the electrical and mechanical works (20%).
Also, the required support amounts approximately to 10%, whereas the excavation and waterproofing
is almost 9% and 5% of the total cost, respectively. In Fig. 2 the major cost components of the
examined projects are presented.
0
5
10
15
20
25
30
35
40
D
esign
Studies
Support
Excavation
C
oncrete
W
aterproofing
Pavem
ents
C
oatings
Landscaping/decoration
Electrical&
M
echanical
ParallelworksG
eneralexpences
As-buildCost(%)
Paidon Square station
Rizari street station
Fig. 2. Analysis of the major cost components in the construction of cut-and-cover parking
facilities.
Based on the examined data, the factors that play an important role to the total cost are:
 local conditions in the construction area
 geological background and
 excavation depth
The siting of an underground car parking facility has a great effect not only to its utilisation but is also
of major importance to its construction cost. As the cut-and-cover method requires the excavation to
start from the top and gradually reach to the target depth, in the early stages, it is possible to have
reprecautions to the city life. Thus, the proximity of the construction site to other buildings, nodal
points in the city, etc. mandate the establishment of additional measures to alleviate possible
consequences. On the other hand, after the construction period a series of parallel work are required to
redevelop the original forms or even improve the prevailing conditions.
In the examined cases, the most characteristic examples are the car parks constructed under Kaniggos
Square and the Paidon Hospital Square. In the first case, the construction took place in the heart of
Athens centre, under both the homonymous square and Akadimias avenue. Thus, a number of parallel
works, rerouting of the traffic, pedestrian passages, rearrangement of utility networks, etc. were
required along with a complete renovation and landscaping after the construction period. Moreover, in
order to minimise the impacts it was decided to divide the construction in many phases, element that
affected both the project’s budget and its construction period.
Another important factor is the need for additional support measures so as to ensure that the safety of
the surrounding buildings and ensure that ground deformations will be kept at a minimum level. Thus,
the design of the support system (piles, diaphragm walls, cable support, etc.) should include the
additional loadings, while the installation of steel braces and other support types at the topmost level
should be made parallel or before the actual start of the excavation. This was the case in the Paidon
Hospital Square car park and is reflected to the extra cost spending in support and concrete works,
compared to the case of the Rizari street garage where the structure was built under a public garden.
The geological structure is also of importance, as it affects the excavation and support cost. If the rock
has increased strength, more recourses should be allocated in the excavation stage, while the support
can be simpler and more economical. The geological background of the Paidon Hospital square is
constituted by hard red clay, loose soil, conglomerate and gravel, rocks, of low to medium strength
and cohesiveness while in the Rizari Street car park, the Athenian Schist prevails as it is characterized
by higher strength and cohesiveness, and consists a rocky formation.
Hence, the underground parking area of the Paidon Hospital square presents lower excavation cost in
relation to the Rizari Street’s case. This happens not only because of the smaller volume of the first
but also because of the fact that the subsoil is constituted by loose soil, low stiffness and cohesion,
contrary to the rocky formation of the second region, that is extracted more difficultly. As with
support, the opposite stands. The support required for the Rizari Street car park is lighter and of lower
cost, whereas in the Paidon square’s case, more material, personnel and labour hours are required.
Finally, the excavation depth is in proportion to the support and the excavation costs. As it increases
more difficulties are to be encountered as the mucking of the materials becomes an important cost
centre and the support used should be capable of overcoming increased lateral pressures. This has been
also the case for the Paidon Square Hospital car park as increased expenses were required to the
support system.
3. UNDERGROUND CAR PARKS – “ROOM AND PILLAR” METHOD
3.1. General outline – Cases examined
The room-and-pillar is a typical “open stope” mining method, where only part of the ore/rock is
extracted while the rest remains in place in the form of pillars so as to provide natural support of the
overburden. The method can be used in horizontal or slightly inclined formations, located in low to
medium depth and are characterised of high to medium strength. The approach of this method for the
creation of void space is different than mining. More specifically, instead of designing the exploitation
scheme with a view to extract as much rock as possible and achieve the highest recovery ratio, the
project’s design aims at providing adequate space to serve the needs of a typical parking facility,
without compromising the safety of the site.
The data provided regarding the construction cost of the underground parking places is relied on three
specific cases (Table 3), the construction of which is proposed to take place by using the principles of
the room-and-pillar method (Kaliampakos et al, 2003)..
Parking Station Surface (m2
) Volume (m3
) Floors Capacity (cars)
Agia Paraskevi 13,248 66,240 1 360
Tourkovounia 11,319 45,276 1 346
Katehaki Bus depot 59,917 479,336 1 284 (buses)
Table 3. Characteristics of underground car parking stations designed with the room and pillar method.
The first two car parks have a capacity of around 360 parking places, while the third is designed to
host the depot of the public bus company of Athens, with a capacity of 284 busses. All of those
facilities are designed within limestone formations of good to medium strength and the rock will be
extracted using blasting agents. Moreover, the facilities are developed in a single floor space.
3.2. Cost Analysis
In the cost analysis of the selected projects, two major cost components can be discerned; the
excavation cost and the development cost. The first incorporates all the necessary operations for the
creation of the void space (excavation, mucking, support, etc.), while the second includes all the
required works to develop and transform the site into a fully working underground car parking facility
(mechanical installations, waterproofing, pavements, etc.). The cost data is presented in Table 4.
Parking Station Total Cost (x103
€) Cost/parking place (€) Cost/m2
(€)
Agia Paraskevi 1,353 3,760 102
Tourkovounia 3,067 8,865 297
Katehaki Bus depot 3,667 12,910 61
Table 2. Cost data of the room-and-pillar underground car stations in Athens.
It should also be noted that the excavation cost takes into account the income gained from the sale of
the extracted raw materials which could be used as aggregates. The impact of such decision is of
extreme importance, as for example, with a no sale option, the cost for the Agia Paraskevi case would
be approximately at 170 €/m2
.
To understand the differentiation in the cost figures, the case of the Agia Paraskevi car park will be
used as a base example. This garage is constructed in a hilly environment allowing for the
minimisation of the access tunnels. The Tourkovounia car park has almost the same characteristics,
nevertheless its siting requires a number of parallel works to be completed so as to become attractive
to the end users. Thus, a series of access tunnels is required, along with the construction of an inclined
shaft, in which a shuttle funicular lift will allow easy passage to the city’s centre. Nevertheless, the
total cost of these works is extremely high, estimated at approximately 2 million €, increasing the total
cost per parking place from 2,900 € to 8,865 €.
Another issue that plays an important role is the size of the garage itself and more specifically the
height. This can be shown by examining the Katehaki bus depot case, the main difference of which
lies on its preferred dimensions. As it should facilitate buses, its dimensions are increased allowing for
the creation of economies of scale. Furthermore, it allows for the development of a bench type
operation where the excavation of the lower part could be made using vertical blastholes, and thus
achieving higher productivity rates, which are reflected to the decrease of the construction cost.
4. DISCUSSION – CONCLUSIONS
The development of car parks underground is an efficient method of overcoming surface space
constrains and provide at the same time an efficient way to facilitate the parking needs in modern
cities. Each one of the construction method that was examined in this paper has its own unique
features and characteristics. The cut-and-cover method is most efficient in soils or soft ground
conditions and when multi level structures are to be constructed, whereas the room and pillar method
presents significant advantages in cases of rock formations and suitable geomorphologic setting.
The cost analysis however indicates that the room and pillar method offers a considerable reduction in
the total cost (Fig. 3).
Agia Paraskevi
102
Τourkovounia
297
Paidon Hospital
Square
303 Rizari Street
254
Kaniggos Square
640
Katehaki
Bus Depot
61
0
150
300
450
600
750
Totalcost(€/m2)
Hospital Paidon Square
Rizari Street
Kaniggos Square
Agia Paraskevi
Thermal Bus Company
Τourkovounia
Figure 3. Comparison of total construction cost (€/m2
) of underground car parks constructed with the
“cut-and- cover” and “room-and-pillar” methods.
The cost per square meter is at least 3 times lower in the room and pillar cases than of the cut-and-
cover ones. This differentiation in the total cost is due to two main reasons; the revenues from the
aggregate sales and the absence of major support systems and concrete works in the very form of the
room and pillar facility, as the pillars themselves constitute the structural elements that offer the
natural support. Consequently, the selection of the room-and-pillar construction scheme can be proved
most efficient in terms of financial results and can become the standard construction method,
particularly in cases of special projects and where the feasibility of creating an underground car park is
marginal or questioned.
REFERENCES
Christopoulos, C., 2003. Construction of underground car parking station with the room-and
pillar-method in Agia Paraskevi, Diploma thesis Lab of Mining & Environmental
Technology-NTUA, Greece.
J&P ,2002. As built cost report for Paidon Hospital Square underground car parking station .
J&P, 2002. As built cost report for Rizari Street underground car parking station .
J&P, 2002. As built cost report for Kaniggos Square underground car parking station .
Dimitroukas, A, Tolis T., 2003. Construction of underground car parking station with the room-and
pillar-method in Tourkovounia, Diploma thesis, Lab of Mining & Environmental Technology-
NTUA, Greece.
ITA Working Group No.13, 1995. Direct and Indirect Advantages of Underground Structures,
Tunnelling and Underground Space Technology, vol.10, no 3, pp.321-341.
Kaliampakos, D., Mavrikos, A., 2003. Underground Development in Greece: History, Current
Situation and Trends”, Proceedings of the 1st International Conference Sustainable
Development and Management of the Subsurface, 5-7 November, Utrecht.
Kaliampakos, D., Manaras, S. Orfanos, C., Mavrikos, A., 2005. Underground bus depot in Athens: A
novel design approach. 10th ACUUS International Conference Underground Space: Economy
and Environment, pp. 94-98, 24-28 January, Moscow.
Kaliampakos, D., 2003. Notes for the course “Underground works”, Lab of Mining & Environmental
Technology-NTUA, Greece.
Sterling, R., 1997. Underground Technologies for Livable Cities, Tunnelling and Underground Space
Technology, vol.12, no 4, pp. 479-490.
Sterling, R., Godard, J-P., 2001. Geoengineering considerations in the optimum use of underground
space, ITA-AITES Position Papers, 2001.
Tareau, J.P., 1995. Underground Car Parks", Tunneling and Underground Space Technology, vol.10,
no 3, pp.299-309.

More Related Content

What's hot

presentation on Proposal for road survey & construction
presentation on Proposal for road survey & constructionpresentation on Proposal for road survey & construction
presentation on Proposal for road survey & constructionDipendra Bhattarai
 
Final Presentation (Transportation Planning & Design)
Final Presentation (Transportation Planning & Design)Final Presentation (Transportation Planning & Design)
Final Presentation (Transportation Planning & Design)Josia Tannos, EIT
 
Highway design raport(final) (group 2)
Highway design raport(final) (group 2)Highway design raport(final) (group 2)
Highway design raport(final) (group 2)haayaav
 
Proposed cable car project, Uttarakhnad, India.
Proposed cable car project, Uttarakhnad, India.Proposed cable car project, Uttarakhnad, India.
Proposed cable car project, Uttarakhnad, India.Sameer Mohan
 
Civil Engineering by Engr. Shahzaib Farooq
Civil Engineering by Engr. Shahzaib FarooqCivil Engineering by Engr. Shahzaib Farooq
Civil Engineering by Engr. Shahzaib FarooqShahzaibfarooq111
 
IRJET- Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET-  	  Design and Analysis of Flexible Pavement in Amaravati Governemnt C...IRJET-  	  Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET- Design and Analysis of Flexible Pavement in Amaravati Governemnt C...IRJET Journal
 
Paper European Conference Athens 2011
Paper European Conference Athens 2011Paper European Conference Athens 2011
Paper European Conference Athens 2011ILIAS MICHALIS
 
State of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignState of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignDr Mazin Alhamrany
 
L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3 L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3 Sachin PatiL
 
Chapter 3 geometric design
Chapter 3 geometric  designChapter 3 geometric  design
Chapter 3 geometric designBashaFayissa1
 
Chapter 2 highway route surveys and locationaa
Chapter 2 highway route surveys and locationaaChapter 2 highway route surveys and locationaa
Chapter 2 highway route surveys and locationaaBashaFayissa1
 
Beckom Aerial Mapping
Beckom Aerial MappingBeckom Aerial Mapping
Beckom Aerial Mappingbrian.beckom
 
Highway route location
Highway route locationHighway route location
Highway route locationwrya hade
 

What's hot (19)

elements of civil engineering Chapter 1
elements of civil engineering Chapter 1elements of civil engineering Chapter 1
elements of civil engineering Chapter 1
 
presentation on Proposal for road survey & construction
presentation on Proposal for road survey & constructionpresentation on Proposal for road survey & construction
presentation on Proposal for road survey & construction
 
Final Presentation (Transportation Planning & Design)
Final Presentation (Transportation Planning & Design)Final Presentation (Transportation Planning & Design)
Final Presentation (Transportation Planning & Design)
 
20320140503005
2032014050300520320140503005
20320140503005
 
Geometric design
Geometric designGeometric design
Geometric design
 
IPTC_12_2015
IPTC_12_2015IPTC_12_2015
IPTC_12_2015
 
Highway design raport(final) (group 2)
Highway design raport(final) (group 2)Highway design raport(final) (group 2)
Highway design raport(final) (group 2)
 
Proposed cable car project, Uttarakhnad, India.
Proposed cable car project, Uttarakhnad, India.Proposed cable car project, Uttarakhnad, India.
Proposed cable car project, Uttarakhnad, India.
 
Civil Engineering by Engr. Shahzaib Farooq
Civil Engineering by Engr. Shahzaib FarooqCivil Engineering by Engr. Shahzaib Farooq
Civil Engineering by Engr. Shahzaib Farooq
 
IRJET- Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET-  	  Design and Analysis of Flexible Pavement in Amaravati Governemnt C...IRJET-  	  Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET- Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
 
Geological investigations for highways
Geological investigations for highwaysGeological investigations for highways
Geological investigations for highways
 
PORTFOLIO_AntonioPeriago_2015
PORTFOLIO_AntonioPeriago_2015PORTFOLIO_AntonioPeriago_2015
PORTFOLIO_AntonioPeriago_2015
 
Paper European Conference Athens 2011
Paper European Conference Athens 2011Paper European Conference Athens 2011
Paper European Conference Athens 2011
 
State of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignState of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical Design
 
L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3 L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3
 
Chapter 3 geometric design
Chapter 3 geometric  designChapter 3 geometric  design
Chapter 3 geometric design
 
Chapter 2 highway route surveys and locationaa
Chapter 2 highway route surveys and locationaaChapter 2 highway route surveys and locationaa
Chapter 2 highway route surveys and locationaa
 
Beckom Aerial Mapping
Beckom Aerial MappingBeckom Aerial Mapping
Beckom Aerial Mapping
 
Highway route location
Highway route locationHighway route location
Highway route location
 

Viewers also liked

Slide Executive Coaching
Slide Executive CoachingSlide Executive Coaching
Slide Executive Coachingmotivazione1988
 
Portfolio of fakier jacobs
Portfolio of fakier jacobsPortfolio of fakier jacobs
Portfolio of fakier jacobsFakier Jacobs
 
The problem with problems
The problem with problemsThe problem with problems
The problem with problemsAndrey Gargul
 
K 2 Reading Institute RSU5
K 2 Reading Institute RSU5K 2 Reading Institute RSU5
K 2 Reading Institute RSU5Susan Dee
 
GAP Adventure Tourism
GAP Adventure TourismGAP Adventure Tourism
GAP Adventure TourismShaheer Naeem
 
Examen final
Examen finalExamen final
Examen finalclauu1213
 
Transmision de datos part3 diana giraldo
Transmision de datos part3 diana giraldoTransmision de datos part3 diana giraldo
Transmision de datos part3 diana giraldoDiana Giraldo
 
Plano de red (maria alejandra pimiento)
Plano de red (maria alejandra pimiento)Plano de red (maria alejandra pimiento)
Plano de red (maria alejandra pimiento)Aleja Angarita
 
Preguntas de investigacion
Preguntas de investigacionPreguntas de investigacion
Preguntas de investigacionsergio-1998
 
Presentación de Uso de la Tecnología en la Investigación por estudiantes de B...
Presentación de Uso de la Tecnología en la Investigación por estudiantes de B...Presentación de Uso de la Tecnología en la Investigación por estudiantes de B...
Presentación de Uso de la Tecnología en la Investigación por estudiantes de B...Loyda Navas
 
Esta navidad todos sean felices
Esta navidad todos sean felicesEsta navidad todos sean felices
Esta navidad todos sean felicesdiego_futbol10
 
Academy Manageriale 2011 - Presentazione
Academy Manageriale 2011 - PresentazioneAcademy Manageriale 2011 - Presentazione
Academy Manageriale 2011 - PresentazioneClaudio Fasola
 
Il nuovo ruolo del distributore gas
Il nuovo ruolo del distributore gasIl nuovo ruolo del distributore gas
Il nuovo ruolo del distributore gasServizi a rete
 
Il catasto elettronico delle infrastrutture del sottosuolo
Il catasto elettronico delle infrastrutture del sottosuoloIl catasto elettronico delle infrastrutture del sottosuolo
Il catasto elettronico delle infrastrutture del sottosuoloServizi a rete
 
Charmed discussion carmen
Charmed discussion   carmenCharmed discussion   carmen
Charmed discussion carmenKimberly McKee
 

Viewers also liked (20)

Slide Executive Coaching
Slide Executive CoachingSlide Executive Coaching
Slide Executive Coaching
 
Portfolio of fakier jacobs
Portfolio of fakier jacobsPortfolio of fakier jacobs
Portfolio of fakier jacobs
 
The problem with problems
The problem with problemsThe problem with problems
The problem with problems
 
K 2 Reading Institute RSU5
K 2 Reading Institute RSU5K 2 Reading Institute RSU5
K 2 Reading Institute RSU5
 
New Doc 41
New Doc 41New Doc 41
New Doc 41
 
New Doc 27
New Doc 27New Doc 27
New Doc 27
 
GAP Adventure Tourism
GAP Adventure TourismGAP Adventure Tourism
GAP Adventure Tourism
 
Examen final
Examen finalExamen final
Examen final
 
La familia
La familiaLa familia
La familia
 
Transmision de datos part3 diana giraldo
Transmision de datos part3 diana giraldoTransmision de datos part3 diana giraldo
Transmision de datos part3 diana giraldo
 
Plano de red (maria alejandra pimiento)
Plano de red (maria alejandra pimiento)Plano de red (maria alejandra pimiento)
Plano de red (maria alejandra pimiento)
 
Preguntas de investigacion
Preguntas de investigacionPreguntas de investigacion
Preguntas de investigacion
 
Presentación de Uso de la Tecnología en la Investigación por estudiantes de B...
Presentación de Uso de la Tecnología en la Investigación por estudiantes de B...Presentación de Uso de la Tecnología en la Investigación por estudiantes de B...
Presentación de Uso de la Tecnología en la Investigación por estudiantes de B...
 
Esta navidad todos sean felices
Esta navidad todos sean felicesEsta navidad todos sean felices
Esta navidad todos sean felices
 
Academy Manageriale 2011 - Presentazione
Academy Manageriale 2011 - PresentazioneAcademy Manageriale 2011 - Presentazione
Academy Manageriale 2011 - Presentazione
 
Il nuovo ruolo del distributore gas
Il nuovo ruolo del distributore gasIl nuovo ruolo del distributore gas
Il nuovo ruolo del distributore gas
 
Il catasto elettronico delle infrastrutture del sottosuolo
Il catasto elettronico delle infrastrutture del sottosuoloIl catasto elettronico delle infrastrutture del sottosuolo
Il catasto elettronico delle infrastrutture del sottosuolo
 
Vendere idee
Vendere ideeVendere idee
Vendere idee
 
Charmed discussion carmen
Charmed discussion   carmenCharmed discussion   carmen
Charmed discussion carmen
 
Virtual dj 8 user guide
Virtual dj 8   user guideVirtual dj 8   user guide
Virtual dj 8 user guide
 

Similar to Paper-11th ACUUS International Conference

Evaluation and strengthening of reconstructed roads excavated for utilities u...
Evaluation and strengthening of reconstructed roads excavated for utilities u...Evaluation and strengthening of reconstructed roads excavated for utilities u...
Evaluation and strengthening of reconstructed roads excavated for utilities u...IAEME Publication
 
EVALUATION AND STRENGTHENING OF RECONSTRUCTED ROADS EXCAVATED FOR UTILITIES U...
EVALUATION AND STRENGTHENING OF RECONSTRUCTED ROADS EXCAVATED FOR UTILITIES U...EVALUATION AND STRENGTHENING OF RECONSTRUCTED ROADS EXCAVATED FOR UTILITIES U...
EVALUATION AND STRENGTHENING OF RECONSTRUCTED ROADS EXCAVATED FOR UTILITIES U...IAEME Publication
 
Evaluation of Flexible Pavement Failures-A Case Study on Izki Road
Evaluation of Flexible Pavement Failures-A Case Study on Izki RoadEvaluation of Flexible Pavement Failures-A Case Study on Izki Road
Evaluation of Flexible Pavement Failures-A Case Study on Izki RoadIJAEMSJORNAL
 
IRJET- Exprimental Analysis of Permeable Concrete and its Application over Co...
IRJET- Exprimental Analysis of Permeable Concrete and its Application over Co...IRJET- Exprimental Analysis of Permeable Concrete and its Application over Co...
IRJET- Exprimental Analysis of Permeable Concrete and its Application over Co...IRJET Journal
 
A new soil tunnelling machine with waterjet technology
A new soil tunnelling machine with waterjet technologyA new soil tunnelling machine with waterjet technology
A new soil tunnelling machine with waterjet technologyPatricia Faria
 
Resume Transportasi.docx
Resume Transportasi.docxResume Transportasi.docx
Resume Transportasi.docxSeptianAnsori
 
White paper - Encapsulated Post Tensioned Concrete
White paper -  Encapsulated Post Tensioned ConcreteWhite paper -  Encapsulated Post Tensioned Concrete
White paper - Encapsulated Post Tensioned ConcreteAMSYSCO Inc.
 
"The Disadvantages of Designing to a Blanket Factor of Safety"
"The Disadvantages of Designing to a Blanket Factor of Safety""The Disadvantages of Designing to a Blanket Factor of Safety"
"The Disadvantages of Designing to a Blanket Factor of Safety"Remedy Geotechnics Ltd
 
SHATEC Engineering Consultants - Graniterock dba FMG CIR Whitepaper
SHATEC Engineering Consultants - Graniterock dba FMG CIR WhitepaperSHATEC Engineering Consultants - Graniterock dba FMG CIR Whitepaper
SHATEC Engineering Consultants - Graniterock dba FMG CIR WhitepaperDennis McElroy
 
Construction of multi storied machanised (semi-automatic) car
Construction of multi storied machanised (semi-automatic) carConstruction of multi storied machanised (semi-automatic) car
Construction of multi storied machanised (semi-automatic) carDar Hilal
 
IRJET- Study on Design of Polymer based Flexible Pavements for Low Volume Roads
IRJET- Study on Design of Polymer based Flexible Pavements for Low Volume RoadsIRJET- Study on Design of Polymer based Flexible Pavements for Low Volume Roads
IRJET- Study on Design of Polymer based Flexible Pavements for Low Volume RoadsIRJET Journal
 
IRJET- Optimization of Process Parameters of Submerged ARC Welding
IRJET- Optimization of Process Parameters of Submerged ARC WeldingIRJET- Optimization of Process Parameters of Submerged ARC Welding
IRJET- Optimization of Process Parameters of Submerged ARC WeldingIRJET Journal
 
IRJET- A Review Paper on Study on Strengthening and Drainage of Flexible Pave...
IRJET- A Review Paper on Study on Strengthening and Drainage of Flexible Pave...IRJET- A Review Paper on Study on Strengthening and Drainage of Flexible Pave...
IRJET- A Review Paper on Study on Strengthening and Drainage of Flexible Pave...IRJET Journal
 
IRJET- A Study of Cement Treated Base and Sub Base in Flexible Pavement
IRJET-  	  A Study of Cement Treated Base and Sub Base in Flexible PavementIRJET-  	  A Study of Cement Treated Base and Sub Base in Flexible Pavement
IRJET- A Study of Cement Treated Base and Sub Base in Flexible PavementIRJET Journal
 
ACCESS RESEARCH ARTICLE OPEN ACCES Wastewater Pipeline Design in Accordance w...
ACCESS RESEARCH ARTICLE OPEN ACCES Wastewater Pipeline Design in Accordance w...ACCESS RESEARCH ARTICLE OPEN ACCES Wastewater Pipeline Design in Accordance w...
ACCESS RESEARCH ARTICLE OPEN ACCES Wastewater Pipeline Design in Accordance w...IJERA Editor
 
NSL General HdW.update nov09
NSL General HdW.update nov09NSL General HdW.update nov09
NSL General HdW.update nov09Hans De Wit
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work reportAbdul rahman kureshi
 

Similar to Paper-11th ACUUS International Conference (20)

Evaluation and strengthening of reconstructed roads excavated for utilities u...
Evaluation and strengthening of reconstructed roads excavated for utilities u...Evaluation and strengthening of reconstructed roads excavated for utilities u...
Evaluation and strengthening of reconstructed roads excavated for utilities u...
 
EVALUATION AND STRENGTHENING OF RECONSTRUCTED ROADS EXCAVATED FOR UTILITIES U...
EVALUATION AND STRENGTHENING OF RECONSTRUCTED ROADS EXCAVATED FOR UTILITIES U...EVALUATION AND STRENGTHENING OF RECONSTRUCTED ROADS EXCAVATED FOR UTILITIES U...
EVALUATION AND STRENGTHENING OF RECONSTRUCTED ROADS EXCAVATED FOR UTILITIES U...
 
Evaluation of Flexible Pavement Failures-A Case Study on Izki Road
Evaluation of Flexible Pavement Failures-A Case Study on Izki RoadEvaluation of Flexible Pavement Failures-A Case Study on Izki Road
Evaluation of Flexible Pavement Failures-A Case Study on Izki Road
 
IRJET- Exprimental Analysis of Permeable Concrete and its Application over Co...
IRJET- Exprimental Analysis of Permeable Concrete and its Application over Co...IRJET- Exprimental Analysis of Permeable Concrete and its Application over Co...
IRJET- Exprimental Analysis of Permeable Concrete and its Application over Co...
 
A new soil tunnelling machine with waterjet technology
A new soil tunnelling machine with waterjet technologyA new soil tunnelling machine with waterjet technology
A new soil tunnelling machine with waterjet technology
 
Resume Transportasi.docx
Resume Transportasi.docxResume Transportasi.docx
Resume Transportasi.docx
 
White paper - Encapsulated Post Tensioned Concrete
White paper -  Encapsulated Post Tensioned ConcreteWhite paper -  Encapsulated Post Tensioned Concrete
White paper - Encapsulated Post Tensioned Concrete
 
"The Disadvantages of Designing to a Blanket Factor of Safety"
"The Disadvantages of Designing to a Blanket Factor of Safety""The Disadvantages of Designing to a Blanket Factor of Safety"
"The Disadvantages of Designing to a Blanket Factor of Safety"
 
SHATEC Engineering Consultants - Graniterock dba FMG CIR Whitepaper
SHATEC Engineering Consultants - Graniterock dba FMG CIR WhitepaperSHATEC Engineering Consultants - Graniterock dba FMG CIR Whitepaper
SHATEC Engineering Consultants - Graniterock dba FMG CIR Whitepaper
 
20320130406022 2
20320130406022 220320130406022 2
20320130406022 2
 
20320130406022 2
20320130406022 220320130406022 2
20320130406022 2
 
Construction of multi storied machanised (semi-automatic) car
Construction of multi storied machanised (semi-automatic) carConstruction of multi storied machanised (semi-automatic) car
Construction of multi storied machanised (semi-automatic) car
 
IRJET- Study on Design of Polymer based Flexible Pavements for Low Volume Roads
IRJET- Study on Design of Polymer based Flexible Pavements for Low Volume RoadsIRJET- Study on Design of Polymer based Flexible Pavements for Low Volume Roads
IRJET- Study on Design of Polymer based Flexible Pavements for Low Volume Roads
 
Bituminous Road
 Bituminous Road Bituminous Road
Bituminous Road
 
IRJET- Optimization of Process Parameters of Submerged ARC Welding
IRJET- Optimization of Process Parameters of Submerged ARC WeldingIRJET- Optimization of Process Parameters of Submerged ARC Welding
IRJET- Optimization of Process Parameters of Submerged ARC Welding
 
IRJET- A Review Paper on Study on Strengthening and Drainage of Flexible Pave...
IRJET- A Review Paper on Study on Strengthening and Drainage of Flexible Pave...IRJET- A Review Paper on Study on Strengthening and Drainage of Flexible Pave...
IRJET- A Review Paper on Study on Strengthening and Drainage of Flexible Pave...
 
IRJET- A Study of Cement Treated Base and Sub Base in Flexible Pavement
IRJET-  	  A Study of Cement Treated Base and Sub Base in Flexible PavementIRJET-  	  A Study of Cement Treated Base and Sub Base in Flexible Pavement
IRJET- A Study of Cement Treated Base and Sub Base in Flexible Pavement
 
ACCESS RESEARCH ARTICLE OPEN ACCES Wastewater Pipeline Design in Accordance w...
ACCESS RESEARCH ARTICLE OPEN ACCES Wastewater Pipeline Design in Accordance w...ACCESS RESEARCH ARTICLE OPEN ACCES Wastewater Pipeline Design in Accordance w...
ACCESS RESEARCH ARTICLE OPEN ACCES Wastewater Pipeline Design in Accordance w...
 
NSL General HdW.update nov09
NSL General HdW.update nov09NSL General HdW.update nov09
NSL General HdW.update nov09
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work report
 

Paper-11th ACUUS International Conference

  • 1. Comparative Evaluation of Alternative Methods for the Construction of Underground Car Parks Meliti Pappa1 , Andreas Benardos2 1 Civil Engineeer, MSc, Greece 2 Mining Engineer, PhD, Lab. of Mining & Environmental Technology – NTUA, Greece ABSTRACT The present paper focuses on the comparison between the alternative methods of constructing underground parking spaces. It analyses and compares the “cut-and-cover” method, a most common method for the construction of underground parking stations, with the “room-and-pillar” method originating from the mining sector which also exhibits equally satisfactory results. This evaluation takes into account the applicability of each method in relation to the ground conditions, their ease of use, as well as their performance in terms of financial efficiency during construction. The assessment is made using reference projects as input. More specifically, the construction costs of three underground car-stations, constructed with the “cut-and-cover” method are compared with the construction costs of three other underground car-stations which were designed following the “room- and-pillar” method principles. Their key elements are recognized and major cost components are evaluated in a head to head analysis. 1. IMPORTANCE OF PARKING SPACES – UNDERGROUND CAR PARKS Car plays an important role to modern societies as it is a comfortable and fast mean of transport. However, its usefulness and service degree depends particularly on the sufficiency of suitable parking spaces. The importance of “parking” is evident from the space that is provided and the time that a car is found parked in relation to the time of its movement. Thus, a passenger car requires a parking area of approximately 25 m2 , including the essential areas for gaining access and manoeuvres, while the time it remains parked is more than 90% of the total. However, the lack of parking spaces is one of the most significant problems that large urban centres face today. This fact has lead to particularly negative consequences in the life and style of the cities because of the traffic jams and long delays, as well as the environmental pollution. The utilisation of the subsurface with the establishment of underground car parks has been proposed as a measure to alleviate the lack of parking space in urban areas and today, along with the underground transit systems (metros, etc.), can be characterised as the most typical form of underground development (Kaliampakos D., 2003). The advantages that such facilities offer are significant and their use is widespread. In particular, they contribute to the environmental protection, as valuable surface space can be preserved and the visual annoyance is minimal, assisting in the improvement of the quality of the city life, and at the same time they can provide a safe environment with high availability since their construction could take place almost anywhere (Tareau, J.P., 1995). Nevertheless, underground car parks have to deal with a high construction and service cost, in relation to aboveground solutions, because of the increased need for support, lightning and ventilation. That issue puts forth the necessity to further investigate solutions capable of offering lower costs without on the same time affecting the efficiency of underground car parks.
  • 2. 2. UNDERGROUND CAR PARKS - “CUT-AND-COVER” METHOD 2.1. General outline – Cases examined This method, which is commonly used for the construction of underground parking areas, is quite flexible and it requires simple mechanical equipment. For the support of the cutting perimetric walls, steel strands or reinforced concrete, or tensile anchors are used. Cut and cover is easily adapted on the loose soil of top layers while in exceptional cases also in hard soil. In recent years a booming in the development of underground car parks following this method was experienced in Greece and in Athens in particular. In Table 1 the characteristics of three underground garages are presented, (J.&P., 2002) namely the stations of Paidon Hospital square (Fig. 1a), Rizari street, and finally Kanigos Square (Fig 1b). These car parks are located under public squares, having a total capacity ranging from 500 to 650 parking places, covering a surface of about 17,000 m2 allocated in 4-5 floors. Parking Station Surface (m2 ) Volume (m3 ) Floors Capacity (cars) Paidon Hospital Square 17,433 54,764 5 576 Rizari Street 18,997 56,339 4 664 Kaniggos Square 15,401 49,283 4 491 Table 1. Characteristics of underground car parks constructed following the cut-and-cover method. Fig. 1. Underground car stations in Athens. (a) Vehicle entry point of the Paidon Hospital Square car park; (b) Ground plan of the car station developed under the Kanjgos Square. 2.2. Cost Analysis – Key issues The cost analysis of the underground car parks are based on the as-build cost data and concern the cost of individual construction phases of the Paidon Hospital Square and Rizari Street stations, as well as the total construction cost of the three stations. Therefore the comparison is aiming not only at providing general cost assumptions but also at identifying key factors which affect the construction process and differentiate the project’s cost. Parking Station Total Cost (x103 €) Cost/parking place (€) Cost/m2 (€) Paidon Hospital Square 5,283 9,170 303 Rizari Street 4,830 7,275 254 Kaniggos Square 9,856 20,075 640 Table 2. Cost data of the cut-and-cover underground car stations in Athens.
  • 3. Even though there are differentiations between the examined “cut-and-cover” projects, and each car park has unique design features, the expenditure allocation of the construction costs are distributed roughly at the same cost components. Thus, the cost of the concrete works is the most important one, reaching almost to the 30% of the total cost, followed by the electrical and mechanical works (20%). Also, the required support amounts approximately to 10%, whereas the excavation and waterproofing is almost 9% and 5% of the total cost, respectively. In Fig. 2 the major cost components of the examined projects are presented. 0 5 10 15 20 25 30 35 40 D esign Studies Support Excavation C oncrete W aterproofing Pavem ents C oatings Landscaping/decoration Electrical& M echanical ParallelworksG eneralexpences As-buildCost(%) Paidon Square station Rizari street station Fig. 2. Analysis of the major cost components in the construction of cut-and-cover parking facilities. Based on the examined data, the factors that play an important role to the total cost are:  local conditions in the construction area  geological background and  excavation depth The siting of an underground car parking facility has a great effect not only to its utilisation but is also of major importance to its construction cost. As the cut-and-cover method requires the excavation to start from the top and gradually reach to the target depth, in the early stages, it is possible to have reprecautions to the city life. Thus, the proximity of the construction site to other buildings, nodal points in the city, etc. mandate the establishment of additional measures to alleviate possible consequences. On the other hand, after the construction period a series of parallel work are required to redevelop the original forms or even improve the prevailing conditions. In the examined cases, the most characteristic examples are the car parks constructed under Kaniggos Square and the Paidon Hospital Square. In the first case, the construction took place in the heart of Athens centre, under both the homonymous square and Akadimias avenue. Thus, a number of parallel works, rerouting of the traffic, pedestrian passages, rearrangement of utility networks, etc. were required along with a complete renovation and landscaping after the construction period. Moreover, in order to minimise the impacts it was decided to divide the construction in many phases, element that affected both the project’s budget and its construction period. Another important factor is the need for additional support measures so as to ensure that the safety of the surrounding buildings and ensure that ground deformations will be kept at a minimum level. Thus, the design of the support system (piles, diaphragm walls, cable support, etc.) should include the additional loadings, while the installation of steel braces and other support types at the topmost level should be made parallel or before the actual start of the excavation. This was the case in the Paidon Hospital Square car park and is reflected to the extra cost spending in support and concrete works, compared to the case of the Rizari street garage where the structure was built under a public garden.
  • 4. The geological structure is also of importance, as it affects the excavation and support cost. If the rock has increased strength, more recourses should be allocated in the excavation stage, while the support can be simpler and more economical. The geological background of the Paidon Hospital square is constituted by hard red clay, loose soil, conglomerate and gravel, rocks, of low to medium strength and cohesiveness while in the Rizari Street car park, the Athenian Schist prevails as it is characterized by higher strength and cohesiveness, and consists a rocky formation. Hence, the underground parking area of the Paidon Hospital square presents lower excavation cost in relation to the Rizari Street’s case. This happens not only because of the smaller volume of the first but also because of the fact that the subsoil is constituted by loose soil, low stiffness and cohesion, contrary to the rocky formation of the second region, that is extracted more difficultly. As with support, the opposite stands. The support required for the Rizari Street car park is lighter and of lower cost, whereas in the Paidon square’s case, more material, personnel and labour hours are required. Finally, the excavation depth is in proportion to the support and the excavation costs. As it increases more difficulties are to be encountered as the mucking of the materials becomes an important cost centre and the support used should be capable of overcoming increased lateral pressures. This has been also the case for the Paidon Square Hospital car park as increased expenses were required to the support system. 3. UNDERGROUND CAR PARKS – “ROOM AND PILLAR” METHOD 3.1. General outline – Cases examined The room-and-pillar is a typical “open stope” mining method, where only part of the ore/rock is extracted while the rest remains in place in the form of pillars so as to provide natural support of the overburden. The method can be used in horizontal or slightly inclined formations, located in low to medium depth and are characterised of high to medium strength. The approach of this method for the creation of void space is different than mining. More specifically, instead of designing the exploitation scheme with a view to extract as much rock as possible and achieve the highest recovery ratio, the project’s design aims at providing adequate space to serve the needs of a typical parking facility, without compromising the safety of the site. The data provided regarding the construction cost of the underground parking places is relied on three specific cases (Table 3), the construction of which is proposed to take place by using the principles of the room-and-pillar method (Kaliampakos et al, 2003).. Parking Station Surface (m2 ) Volume (m3 ) Floors Capacity (cars) Agia Paraskevi 13,248 66,240 1 360 Tourkovounia 11,319 45,276 1 346 Katehaki Bus depot 59,917 479,336 1 284 (buses) Table 3. Characteristics of underground car parking stations designed with the room and pillar method. The first two car parks have a capacity of around 360 parking places, while the third is designed to host the depot of the public bus company of Athens, with a capacity of 284 busses. All of those facilities are designed within limestone formations of good to medium strength and the rock will be extracted using blasting agents. Moreover, the facilities are developed in a single floor space. 3.2. Cost Analysis In the cost analysis of the selected projects, two major cost components can be discerned; the excavation cost and the development cost. The first incorporates all the necessary operations for the creation of the void space (excavation, mucking, support, etc.), while the second includes all the
  • 5. required works to develop and transform the site into a fully working underground car parking facility (mechanical installations, waterproofing, pavements, etc.). The cost data is presented in Table 4. Parking Station Total Cost (x103 €) Cost/parking place (€) Cost/m2 (€) Agia Paraskevi 1,353 3,760 102 Tourkovounia 3,067 8,865 297 Katehaki Bus depot 3,667 12,910 61 Table 2. Cost data of the room-and-pillar underground car stations in Athens. It should also be noted that the excavation cost takes into account the income gained from the sale of the extracted raw materials which could be used as aggregates. The impact of such decision is of extreme importance, as for example, with a no sale option, the cost for the Agia Paraskevi case would be approximately at 170 €/m2 . To understand the differentiation in the cost figures, the case of the Agia Paraskevi car park will be used as a base example. This garage is constructed in a hilly environment allowing for the minimisation of the access tunnels. The Tourkovounia car park has almost the same characteristics, nevertheless its siting requires a number of parallel works to be completed so as to become attractive to the end users. Thus, a series of access tunnels is required, along with the construction of an inclined shaft, in which a shuttle funicular lift will allow easy passage to the city’s centre. Nevertheless, the total cost of these works is extremely high, estimated at approximately 2 million €, increasing the total cost per parking place from 2,900 € to 8,865 €. Another issue that plays an important role is the size of the garage itself and more specifically the height. This can be shown by examining the Katehaki bus depot case, the main difference of which lies on its preferred dimensions. As it should facilitate buses, its dimensions are increased allowing for the creation of economies of scale. Furthermore, it allows for the development of a bench type operation where the excavation of the lower part could be made using vertical blastholes, and thus achieving higher productivity rates, which are reflected to the decrease of the construction cost. 4. DISCUSSION – CONCLUSIONS The development of car parks underground is an efficient method of overcoming surface space constrains and provide at the same time an efficient way to facilitate the parking needs in modern cities. Each one of the construction method that was examined in this paper has its own unique features and characteristics. The cut-and-cover method is most efficient in soils or soft ground conditions and when multi level structures are to be constructed, whereas the room and pillar method presents significant advantages in cases of rock formations and suitable geomorphologic setting. The cost analysis however indicates that the room and pillar method offers a considerable reduction in the total cost (Fig. 3). Agia Paraskevi 102 Τourkovounia 297 Paidon Hospital Square 303 Rizari Street 254 Kaniggos Square 640 Katehaki Bus Depot 61 0 150 300 450 600 750 Totalcost(€/m2) Hospital Paidon Square Rizari Street Kaniggos Square Agia Paraskevi Thermal Bus Company Τourkovounia Figure 3. Comparison of total construction cost (€/m2 ) of underground car parks constructed with the “cut-and- cover” and “room-and-pillar” methods.
  • 6. The cost per square meter is at least 3 times lower in the room and pillar cases than of the cut-and- cover ones. This differentiation in the total cost is due to two main reasons; the revenues from the aggregate sales and the absence of major support systems and concrete works in the very form of the room and pillar facility, as the pillars themselves constitute the structural elements that offer the natural support. Consequently, the selection of the room-and-pillar construction scheme can be proved most efficient in terms of financial results and can become the standard construction method, particularly in cases of special projects and where the feasibility of creating an underground car park is marginal or questioned. REFERENCES Christopoulos, C., 2003. Construction of underground car parking station with the room-and pillar-method in Agia Paraskevi, Diploma thesis Lab of Mining & Environmental Technology-NTUA, Greece. J&P ,2002. As built cost report for Paidon Hospital Square underground car parking station . J&P, 2002. As built cost report for Rizari Street underground car parking station . J&P, 2002. As built cost report for Kaniggos Square underground car parking station . Dimitroukas, A, Tolis T., 2003. Construction of underground car parking station with the room-and pillar-method in Tourkovounia, Diploma thesis, Lab of Mining & Environmental Technology- NTUA, Greece. ITA Working Group No.13, 1995. Direct and Indirect Advantages of Underground Structures, Tunnelling and Underground Space Technology, vol.10, no 3, pp.321-341. Kaliampakos, D., Mavrikos, A., 2003. Underground Development in Greece: History, Current Situation and Trends”, Proceedings of the 1st International Conference Sustainable Development and Management of the Subsurface, 5-7 November, Utrecht. Kaliampakos, D., Manaras, S. Orfanos, C., Mavrikos, A., 2005. Underground bus depot in Athens: A novel design approach. 10th ACUUS International Conference Underground Space: Economy and Environment, pp. 94-98, 24-28 January, Moscow. Kaliampakos, D., 2003. Notes for the course “Underground works”, Lab of Mining & Environmental Technology-NTUA, Greece. Sterling, R., 1997. Underground Technologies for Livable Cities, Tunnelling and Underground Space Technology, vol.12, no 4, pp. 479-490. Sterling, R., Godard, J-P., 2001. Geoengineering considerations in the optimum use of underground space, ITA-AITES Position Papers, 2001. Tareau, J.P., 1995. Underground Car Parks", Tunneling and Underground Space Technology, vol.10, no 3, pp.299-309.