3
Why we will change?
Production
•Production is the process of combining units
of inputs (man-made and human resources) to
create output
Fabric
(Cutting)
Thread Machinery Manpower
(Workers)
Output
4
1000pcs 200 Cones 35 Machines 40 persons (40x
10) = 400hrs 200 pcs
5
Production
What is SMV ?
• Meaning of the Abbreviation- Standard Minute Value
• It should be expressed always in Minutes
• Time taken by a standard operator to complete any give operation/s
with pre-defined conditions
• BSI 100= 100% performance operator is the standard operator
• SMV = Basic Time + Allowance
Observe Time X Rating
• Basic Time =
Standard Rating
6
How to Calculate SMV?
• We Can Calculate SMV By 03 Way.
• PMTS can be used as a method analysis technique
There are common versions. (Time study).
• MTM1,2,3 [Established in 1940(350codes), 1965 (39 codes),1970 (10
codes)
• GSD (General Sewing Data) Established in 1971- specially designed for
the needle trade work. (36 codes)
7
WHAT IS TARGET?
• Production Target refers to the number of units or the quantity of output
the business is expected to produce in the next financial period.
• Production target defines how much to produce?
• The production target is fixed during the preparation of the production
budget when the man, material, method, money are decided.
• This production target helps the organisation follow a routine production
process and adjust their master schedules when necessary to achieve the
desired target.
8
How to Calculate Target?
TOTAL MANPOWER X WORKING HOURS X 60
• TARGET = X EXPECTED EFFI.%
SMV
(TTL.MP=80) X (WH=10) X 60
TARGET = X 65%
(SMV= 35.80)
9
48000
TARGET = X 65%
35.80
TARGET = 1340.78 X 65%
TARGET = 871.50 PCS.
10
How to Calculate Target?
• Efficiency is the quality of being able to do a task successfully, without
wasting time or energy.
• The comparison of what is actually produced or performed with what
can be achieved with the same consumption of resources (money,
time, labor, etc.). It is an important factor in determination of
productivity. See also effectiveness.
11
WHAT IS EFFICIENCY?
• Production output from the line (Pcs),
• Standard Minute Value (SMV) for garment,
• Total number of operators / Helpers in the line,
• Total working hours.
How to Calculate Efficiency
12
How to Calculate Efficiency
Line Output SMV of the Garment
Total number of Operators /
Helpers
Total Working Hours 60
Total produced Minutes
100
Total Worked Minutes
100
13
WR-254 (4UDBWBY)
800pcs 22.02 minutes
40 10 60
100
800 x 22.02
40 x 10 x 60
100
14
17616 mins
24,000 mins
100
73.40%
Efficiency
15
Reasons for Poor Efficiency
• Not following Individual Targets of Operators / Helpers
• Poor Recording Systems (Not recording WIP / Input / Output)
• Excessive Working Hours without productivity (Extra Overtime)
• Non productive Times (Machine Breakdown / No Input)
• Improper Planning (Not prepare well for next style change)
• Bottlenecks (Due to poor balancing)
• Not follow Bundling Serial Systems
• Operators / Helpers doing non – value added operations / Processes
• Poor cooperation with other departments (Cutting / Store)
• Operator Skills
• Absenteeism
16
Not following Individual Targets of Operators /
Helpers
• Without not knowing the hourly
achievement how can you achieve
daily target
• Not possible to identify where the
problem is
• Finally you can not make decisions
17
Follow Operator Individual Targets Closely
• Record every hour production from the beginning, of style not after
one day
• If you found less than the requirement ask for reasons
• If Operator give any reasons (Good or Bad) check it right or wrong
• If right necessary to give a solution
• If wrong explain them that answer is wrong
• Don’t misbehave or use rough language with them
18
Poor Recording Systems (Not recording WIP / Input /
Output)
Date Front Part Output Back Part Output Total Output
1/4/16 2500 2200 1200
2/4/16 3200 2800 1700
3/4/16 4000 3300 2500
4/4/16 4900 4000 3200
5/4/16 5500 4500 4000
19
500
400
300
600
500
400
200
150
100
Front Back Belt
300 250 200 100 75 60
20
Excessive Working Hours without productivity (Excess
OT)
Hour 1 2 3 4 5 6 7 8 9 10 11 12 13
Output 50 70 75 80 80 85 83 80 85 85 ?? ?? ??
Up to 10 Hours Total Production =773pcs
Up to 13 Hours Total Production = 850pcs
Up to 10 Hours Average Production / Hr =77pcs
Up to 10 Hours Average Production / Hr =65pcs
21
Non productive Times (Machine Breakdown / No
Input)
22
Improper Planning (Not prepare well for next style
change)
• If you have clear details about Input / Output / WIP you know that
when will be finish current style
• Then you can assume when you need new input
23
Bottlenecks
•Bottleneck is a stage in a process that causes the entire process to
slow down or stop.
24
Practical Example
Pocket Seam
Attach – 500pcs
Pocket Overlock
– 500pcs
Pocket Bag
Topstitch – 400pcs
Pocket Attach –
200pcs
• Operator Problem??
• Machine Problem??
• Capacity Problem??
• Defectives??
Or What
• Motivate / Change
Operator
• Change Machine??
• Check Actual Capacity??
• Change the method with
the help of WSE??
25
Not follow Bundling Serial Systems
• If you are not following Bundling Systems
• If Front / Back Parts follow different bundles then can not do
assembly
• Unable to get exact qty’s
• Directly affecting to operator performance as they need to
search for bundles
• Increasing non productive time
• Excessive backlogs due to bundle mistakes
• Affecting Line Cleanliness / arrangements
• Create Unpleasant working environment
26
How We are Doing - Bargain
27
28
How Others are Doing
29
30
31
Operators / Helpers doing non – value added Operations
• What is Non Value Added Operations
• Any process doing by operator / helper and do not allocate SMV in
Operation Breakdown
• Therefore these processes not considering when calculate efficiency
• But those operator / helper working hours added to total working hours
of production line
• Increase Product Cost (Buyer did not pay for extra work)
• What are the Non Value Added Operations
• Matching Parts (Such as Pockets / Front & Back Parts) / Belts)
• Tacking Parts to body (Such as Belt / Belt Loop)
• Excess Markings (Other than the required markings)
• Thread Cutting
• Any other Operator / Helper process which is not included in layout 32
Matching No Serial in Parts (Bargain & Zazu)
33
Knee Marks - Bargain
34
Tack Waist Belt & Loop to Body (909 & Bargain)
35
What we can do to STOP Non Value Adding Operations
• Follow Bundle / Number Serial - No Need Match parts or Tack Parts
to Body
• Remove Excess Markings
• Ask your self actually this is required or not / Check with WSE & Quality
Controller for any other methods or remove marks completely
• Reduce Marking area and It will help to increase production pcs
• Keep Active all Auto Thread Cutting Devises (Wiper / UBT)
• Reduce no of Helper Process as much as you can to increase Efficiency
36
Bundle & No Serial Follow up
37
Reduce Marking Area
38
Reduce Marking Area
Not Clear / Excess
Markings / Not Good
Method = Low Output
Clear & Clean/ Less
Markings / Good Method
= High Output
39
Poor cooperation with other Departments (Cutting / Store)
• Keep good communication channel with Cutting / Stores
• Usually follow up Input figures (Qty) with Input man
• Create a friendly relationship with other departments
40
Work Smarter
41
Operator Skills
• Skill - an ability to do an activity or job well
• Low Skill Caused
• Low Output / Target
• Poor Quality
• Balancing Problems
• Train Low Skill Operators to do other processes with help of WSE
• Train Experienced Helpers to operate machine even a small process
• Change Operators among various operations specially when having new
lay out
• Motivate your team for greater results 42
Absenteeism
• Does Absenteeism Really affecting Efficiency??
• Day Output 300pcs / Workers – 40 x 10hrs = 300/400 x 100 = 75%
• Theoretically it does not
• Day Output 250pcs / Workers – 33x 10hrs = 250/330 x 100 = 75%
• But if you don’t have skilled operators Efficiency will go down because
they are unable to achieve hourly / daily target
• And if you work more hours to recover target still affecting to
Efficiency
• Day Output 250pcs / Workers – 33x 13hrs = 250/429 x 100 = 58%
43
Motivate Your Team
• Meet with your team at least once a week
• Explain goals / targets / Absenteeism
• Hear their difficulties and try hard to solve them
• When new style starts, must have a meeting and explain what
the mistakes we did in previous style, and how to overcome
them in new style
• Well behave with the employees (Need to add more details)
44
Be a Leader
45
46
Team Work
47
Proper Team Work
Zero Feeding Time
New Style Input Previous Style Output
48
Our Factory Actual Situation
Hour 1 2 3 4 5 6 7 8 9 10 11 12 13
Output 20 20 20 20 20 20 20 20 20 20
• Previous Style Last Output = 600pcs / 10Hr
= 60pcs / Hr
• Next Day Output Balance = 200pcs
• How Many Hours Need to Complete = 200/60 = 3.33Hrs
49
Continued…
• New Style Input = 8.00am (25/04/2016)
• New Style Output = 10.00am (26/04/2016)
• Line Feeding Time = 12Hrs
50
• Study the Sample of New Style
• Prepare Input /Pattern Boards / Threads In Advance
• Prepare machinery quickly with the help of Mechanic
• If one machine finish previous style input new style
How Can we reduced Line Feeding Time
51
52
53
THANKS TO ALL…

More Related Content

What's hot

What is Lean Six Sigma - ADDVALUE - Nilesh Arora
What is Lean Six Sigma -  ADDVALUE - Nilesh AroraWhat is Lean Six Sigma -  ADDVALUE - Nilesh Arora
What is Lean Six Sigma - ADDVALUE - Nilesh AroraADD VALUE CONSULTING Inc
 
Machine shop101 rev_l
Machine shop101 rev_lMachine shop101 rev_l
Machine shop101 rev_lJeremy Kermit
 
Seven wastes of lean operations management
Seven wastes of lean operations managementSeven wastes of lean operations management
Seven wastes of lean operations managementHriday Bora
 
Session 8_OM
Session 8_OMSession 8_OM
Session 8_OMthangv
 
Training & Development of Supervisors
Training & Development of SupervisorsTraining & Development of Supervisors
Training & Development of SupervisorsShubham Singh
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...Karina Islam
 
Standard Work And One Piece Flow
Standard Work And One Piece FlowStandard Work And One Piece Flow
Standard Work And One Piece Flowguest399e73
 
Single Minute Exchange of Dies (SMED)
Single Minute Exchange of Dies (SMED)Single Minute Exchange of Dies (SMED)
Single Minute Exchange of Dies (SMED)Pramod A
 
Mba 505 business_processes_operations_productivity_strategy_tutorial1s
Mba 505 business_processes_operations_productivity_strategy_tutorial1sMba 505 business_processes_operations_productivity_strategy_tutorial1s
Mba 505 business_processes_operations_productivity_strategy_tutorial1sChainon
 
How to implement Single minute exchange of die
How to implement Single minute exchange of die How to implement Single minute exchange of die
How to implement Single minute exchange of die Nikunj Rana
 
Modern Terchnological Tool in aid of Lean manufacture in garment unit
Modern Terchnological Tool in aid of Lean manufacture in garment unitModern Terchnological Tool in aid of Lean manufacture in garment unit
Modern Terchnological Tool in aid of Lean manufacture in garment unitIEI GSC
 

What's hot (20)

Line balancing
Line balancingLine balancing
Line balancing
 
How to Improve Productivity
How to Improve ProductivityHow to Improve Productivity
How to Improve Productivity
 
What is Lean Six Sigma - ADDVALUE - Nilesh Arora
What is Lean Six Sigma -  ADDVALUE - Nilesh AroraWhat is Lean Six Sigma -  ADDVALUE - Nilesh Arora
What is Lean Six Sigma - ADDVALUE - Nilesh Arora
 
Machine shop101 rev_l
Machine shop101 rev_lMachine shop101 rev_l
Machine shop101 rev_l
 
Seven wastes of lean operations management
Seven wastes of lean operations managementSeven wastes of lean operations management
Seven wastes of lean operations management
 
The Six Big Losses of OEE
The Six Big Losses of OEEThe Six Big Losses of OEE
The Six Big Losses of OEE
 
Session 8_OM
Session 8_OMSession 8_OM
Session 8_OM
 
Training & Development of Supervisors
Training & Development of SupervisorsTraining & Development of Supervisors
Training & Development of Supervisors
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
 
Standard Work And One Piece Flow
Standard Work And One Piece FlowStandard Work And One Piece Flow
Standard Work And One Piece Flow
 
Single Minute Exchange of Dies (SMED)
Single Minute Exchange of Dies (SMED)Single Minute Exchange of Dies (SMED)
Single Minute Exchange of Dies (SMED)
 
Mba 505 business_processes_operations_productivity_strategy_tutorial1s
Mba 505 business_processes_operations_productivity_strategy_tutorial1sMba 505 business_processes_operations_productivity_strategy_tutorial1s
Mba 505 business_processes_operations_productivity_strategy_tutorial1s
 
How to implement Single minute exchange of die
How to implement Single minute exchange of die How to implement Single minute exchange of die
How to implement Single minute exchange of die
 
Just In Time & Kanban
Just In Time & KanbanJust In Time & Kanban
Just In Time & Kanban
 
7 Types of Muda
7 Types of Muda7 Types of Muda
7 Types of Muda
 
WASTE ELIMINATION
WASTE ELIMINATIONWASTE ELIMINATION
WASTE ELIMINATION
 
FUSION BROCHURE_ENG_Final_20160224_kvz(2)
FUSION BROCHURE_ENG_Final_20160224_kvz(2)FUSION BROCHURE_ENG_Final_20160224_kvz(2)
FUSION BROCHURE_ENG_Final_20160224_kvz(2)
 
Just in Time
Just in TimeJust in Time
Just in Time
 
Modern Terchnological Tool in aid of Lean manufacture in garment unit
Modern Terchnological Tool in aid of Lean manufacture in garment unitModern Terchnological Tool in aid of Lean manufacture in garment unit
Modern Terchnological Tool in aid of Lean manufacture in garment unit
 
All in 1 IE
All in 1 IEAll in 1 IE
All in 1 IE
 

Similar to Olio ie training for all stuff

Standard work training
Standard work trainingStandard work training
Standard work trainingdnachreiner
 
05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf
05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf
05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdfRahbiMalek
 
Industrial engineeering pli
Industrial engineeering   pliIndustrial engineeering   pli
Industrial engineeering pliDhyey Shukla
 
2.IE Presentation.pptx
2.IE Presentation.pptx2.IE Presentation.pptx
2.IE Presentation.pptxVarun Mehrotra
 
SMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping LineSMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping LineParth Patel
 
Smed implementation on manufacturing stamping line
Smed implementation on manufacturing stamping lineSmed implementation on manufacturing stamping line
Smed implementation on manufacturing stamping lineDhruvShah202
 
Autonomous Maintenance (AM)
Autonomous Maintenance (AM)Autonomous Maintenance (AM)
Autonomous Maintenance (AM)Pramod A
 
Operations scheduling
Operations schedulingOperations scheduling
Operations schedulingRajThakuri
 
Cost & management Accounting
Cost & management AccountingCost & management Accounting
Cost & management AccountingJisjissyChandran
 
Top 6 Workforce Management Challenges
Top 6 Workforce Management ChallengesTop 6 Workforce Management Challenges
Top 6 Workforce Management ChallengesAdtech Global
 
Process Selection and Facility layout.ppt
Process Selection and Facility layout.pptProcess Selection and Facility layout.ppt
Process Selection and Facility layout.pptSandipanMaji3
 
Just in time and Lean systems
Just in time and Lean systemsJust in time and Lean systems
Just in time and Lean systemsAyman Aljahdali
 
Line balancing and its formulation
Line balancing and its formulationLine balancing and its formulation
Line balancing and its formulationavijit biswas
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)MohammedLahssaini1
 
SBS - SMED Training (Set Up Reduction)
SBS - SMED Training (Set Up Reduction)SBS - SMED Training (Set Up Reduction)
SBS - SMED Training (Set Up Reduction)Chris Cummins
 

Similar to Olio ie training for all stuff (20)

Standard work training
Standard work trainingStandard work training
Standard work training
 
05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf
05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf
05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf
 
Industrial engineeering pli
Industrial engineeering   pliIndustrial engineeering   pli
Industrial engineeering pli
 
CIM 15ME62 Module-3
CIM 15ME62  Module-3CIM 15ME62  Module-3
CIM 15ME62 Module-3
 
2.IE Presentation.pptx
2.IE Presentation.pptx2.IE Presentation.pptx
2.IE Presentation.pptx
 
SMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping LineSMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping Line
 
Smed implementation on manufacturing stamping line
Smed implementation on manufacturing stamping lineSmed implementation on manufacturing stamping line
Smed implementation on manufacturing stamping line
 
Line balancing
Line balancing Line balancing
Line balancing
 
Autonomous Maintenance (AM)
Autonomous Maintenance (AM)Autonomous Maintenance (AM)
Autonomous Maintenance (AM)
 
Operations scheduling
Operations schedulingOperations scheduling
Operations scheduling
 
Report on apparel internship at orient craft limited
Report on apparel internship at orient craft limitedReport on apparel internship at orient craft limited
Report on apparel internship at orient craft limited
 
Cost & management Accounting
Cost & management AccountingCost & management Accounting
Cost & management Accounting
 
Lean and 5 s
Lean and 5 sLean and 5 s
Lean and 5 s
 
5 Steps to implementing Lean
5  Steps to implementing Lean5  Steps to implementing Lean
5 Steps to implementing Lean
 
Top 6 Workforce Management Challenges
Top 6 Workforce Management ChallengesTop 6 Workforce Management Challenges
Top 6 Workforce Management Challenges
 
Process Selection and Facility layout.ppt
Process Selection and Facility layout.pptProcess Selection and Facility layout.ppt
Process Selection and Facility layout.ppt
 
Just in time and Lean systems
Just in time and Lean systemsJust in time and Lean systems
Just in time and Lean systems
 
Line balancing and its formulation
Line balancing and its formulationLine balancing and its formulation
Line balancing and its formulation
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)
 
SBS - SMED Training (Set Up Reduction)
SBS - SMED Training (Set Up Reduction)SBS - SMED Training (Set Up Reduction)
SBS - SMED Training (Set Up Reduction)
 

Recently uploaded

Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEselvakumar948
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersMairaAshraf6
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadhamedmustafa094
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 

Recently uploaded (20)

Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 

Olio ie training for all stuff

  • 2. Improving Production & Line Efficiency Training for All Stuff 2
  • 3. 3 Why we will change?
  • 4. Production •Production is the process of combining units of inputs (man-made and human resources) to create output Fabric (Cutting) Thread Machinery Manpower (Workers) Output 4
  • 5. 1000pcs 200 Cones 35 Machines 40 persons (40x 10) = 400hrs 200 pcs 5 Production
  • 6. What is SMV ? • Meaning of the Abbreviation- Standard Minute Value • It should be expressed always in Minutes • Time taken by a standard operator to complete any give operation/s with pre-defined conditions • BSI 100= 100% performance operator is the standard operator • SMV = Basic Time + Allowance Observe Time X Rating • Basic Time = Standard Rating 6
  • 7. How to Calculate SMV? • We Can Calculate SMV By 03 Way. • PMTS can be used as a method analysis technique There are common versions. (Time study). • MTM1,2,3 [Established in 1940(350codes), 1965 (39 codes),1970 (10 codes) • GSD (General Sewing Data) Established in 1971- specially designed for the needle trade work. (36 codes) 7
  • 8. WHAT IS TARGET? • Production Target refers to the number of units or the quantity of output the business is expected to produce in the next financial period. • Production target defines how much to produce? • The production target is fixed during the preparation of the production budget when the man, material, method, money are decided. • This production target helps the organisation follow a routine production process and adjust their master schedules when necessary to achieve the desired target. 8
  • 9. How to Calculate Target? TOTAL MANPOWER X WORKING HOURS X 60 • TARGET = X EXPECTED EFFI.% SMV (TTL.MP=80) X (WH=10) X 60 TARGET = X 65% (SMV= 35.80) 9
  • 10. 48000 TARGET = X 65% 35.80 TARGET = 1340.78 X 65% TARGET = 871.50 PCS. 10 How to Calculate Target?
  • 11. • Efficiency is the quality of being able to do a task successfully, without wasting time or energy. • The comparison of what is actually produced or performed with what can be achieved with the same consumption of resources (money, time, labor, etc.). It is an important factor in determination of productivity. See also effectiveness. 11 WHAT IS EFFICIENCY?
  • 12. • Production output from the line (Pcs), • Standard Minute Value (SMV) for garment, • Total number of operators / Helpers in the line, • Total working hours. How to Calculate Efficiency 12
  • 13. How to Calculate Efficiency Line Output SMV of the Garment Total number of Operators / Helpers Total Working Hours 60 Total produced Minutes 100 Total Worked Minutes 100 13
  • 14. WR-254 (4UDBWBY) 800pcs 22.02 minutes 40 10 60 100 800 x 22.02 40 x 10 x 60 100 14
  • 16. Reasons for Poor Efficiency • Not following Individual Targets of Operators / Helpers • Poor Recording Systems (Not recording WIP / Input / Output) • Excessive Working Hours without productivity (Extra Overtime) • Non productive Times (Machine Breakdown / No Input) • Improper Planning (Not prepare well for next style change) • Bottlenecks (Due to poor balancing) • Not follow Bundling Serial Systems • Operators / Helpers doing non – value added operations / Processes • Poor cooperation with other departments (Cutting / Store) • Operator Skills • Absenteeism 16
  • 17. Not following Individual Targets of Operators / Helpers • Without not knowing the hourly achievement how can you achieve daily target • Not possible to identify where the problem is • Finally you can not make decisions 17
  • 18. Follow Operator Individual Targets Closely • Record every hour production from the beginning, of style not after one day • If you found less than the requirement ask for reasons • If Operator give any reasons (Good or Bad) check it right or wrong • If right necessary to give a solution • If wrong explain them that answer is wrong • Don’t misbehave or use rough language with them 18
  • 19. Poor Recording Systems (Not recording WIP / Input / Output) Date Front Part Output Back Part Output Total Output 1/4/16 2500 2200 1200 2/4/16 3200 2800 1700 3/4/16 4000 3300 2500 4/4/16 4900 4000 3200 5/4/16 5500 4500 4000 19
  • 21. Excessive Working Hours without productivity (Excess OT) Hour 1 2 3 4 5 6 7 8 9 10 11 12 13 Output 50 70 75 80 80 85 83 80 85 85 ?? ?? ?? Up to 10 Hours Total Production =773pcs Up to 13 Hours Total Production = 850pcs Up to 10 Hours Average Production / Hr =77pcs Up to 10 Hours Average Production / Hr =65pcs 21
  • 22. Non productive Times (Machine Breakdown / No Input) 22
  • 23. Improper Planning (Not prepare well for next style change) • If you have clear details about Input / Output / WIP you know that when will be finish current style • Then you can assume when you need new input 23
  • 24. Bottlenecks •Bottleneck is a stage in a process that causes the entire process to slow down or stop. 24
  • 25. Practical Example Pocket Seam Attach – 500pcs Pocket Overlock – 500pcs Pocket Bag Topstitch – 400pcs Pocket Attach – 200pcs • Operator Problem?? • Machine Problem?? • Capacity Problem?? • Defectives?? Or What • Motivate / Change Operator • Change Machine?? • Check Actual Capacity?? • Change the method with the help of WSE?? 25
  • 26. Not follow Bundling Serial Systems • If you are not following Bundling Systems • If Front / Back Parts follow different bundles then can not do assembly • Unable to get exact qty’s • Directly affecting to operator performance as they need to search for bundles • Increasing non productive time • Excessive backlogs due to bundle mistakes • Affecting Line Cleanliness / arrangements • Create Unpleasant working environment 26
  • 27. How We are Doing - Bargain 27
  • 28. 28
  • 29. How Others are Doing 29
  • 30. 30
  • 31. 31
  • 32. Operators / Helpers doing non – value added Operations • What is Non Value Added Operations • Any process doing by operator / helper and do not allocate SMV in Operation Breakdown • Therefore these processes not considering when calculate efficiency • But those operator / helper working hours added to total working hours of production line • Increase Product Cost (Buyer did not pay for extra work) • What are the Non Value Added Operations • Matching Parts (Such as Pockets / Front & Back Parts) / Belts) • Tacking Parts to body (Such as Belt / Belt Loop) • Excess Markings (Other than the required markings) • Thread Cutting • Any other Operator / Helper process which is not included in layout 32
  • 33. Matching No Serial in Parts (Bargain & Zazu) 33
  • 34. Knee Marks - Bargain 34
  • 35. Tack Waist Belt & Loop to Body (909 & Bargain) 35
  • 36. What we can do to STOP Non Value Adding Operations • Follow Bundle / Number Serial - No Need Match parts or Tack Parts to Body • Remove Excess Markings • Ask your self actually this is required or not / Check with WSE & Quality Controller for any other methods or remove marks completely • Reduce Marking area and It will help to increase production pcs • Keep Active all Auto Thread Cutting Devises (Wiper / UBT) • Reduce no of Helper Process as much as you can to increase Efficiency 36
  • 37. Bundle & No Serial Follow up 37
  • 39. Reduce Marking Area Not Clear / Excess Markings / Not Good Method = Low Output Clear & Clean/ Less Markings / Good Method = High Output 39
  • 40. Poor cooperation with other Departments (Cutting / Store) • Keep good communication channel with Cutting / Stores • Usually follow up Input figures (Qty) with Input man • Create a friendly relationship with other departments 40
  • 42. Operator Skills • Skill - an ability to do an activity or job well • Low Skill Caused • Low Output / Target • Poor Quality • Balancing Problems • Train Low Skill Operators to do other processes with help of WSE • Train Experienced Helpers to operate machine even a small process • Change Operators among various operations specially when having new lay out • Motivate your team for greater results 42
  • 43. Absenteeism • Does Absenteeism Really affecting Efficiency?? • Day Output 300pcs / Workers – 40 x 10hrs = 300/400 x 100 = 75% • Theoretically it does not • Day Output 250pcs / Workers – 33x 10hrs = 250/330 x 100 = 75% • But if you don’t have skilled operators Efficiency will go down because they are unable to achieve hourly / daily target • And if you work more hours to recover target still affecting to Efficiency • Day Output 250pcs / Workers – 33x 13hrs = 250/429 x 100 = 58% 43
  • 44. Motivate Your Team • Meet with your team at least once a week • Explain goals / targets / Absenteeism • Hear their difficulties and try hard to solve them • When new style starts, must have a meeting and explain what the mistakes we did in previous style, and how to overcome them in new style • Well behave with the employees (Need to add more details) 44
  • 48. Zero Feeding Time New Style Input Previous Style Output 48
  • 49. Our Factory Actual Situation Hour 1 2 3 4 5 6 7 8 9 10 11 12 13 Output 20 20 20 20 20 20 20 20 20 20 • Previous Style Last Output = 600pcs / 10Hr = 60pcs / Hr • Next Day Output Balance = 200pcs • How Many Hours Need to Complete = 200/60 = 3.33Hrs 49
  • 50. Continued… • New Style Input = 8.00am (25/04/2016) • New Style Output = 10.00am (26/04/2016) • Line Feeding Time = 12Hrs 50
  • 51. • Study the Sample of New Style • Prepare Input /Pattern Boards / Threads In Advance • Prepare machinery quickly with the help of Mechanic • If one machine finish previous style input new style How Can we reduced Line Feeding Time 51
  • 52. 52