SlideShare a Scribd company logo
1 of 2
Download to read offline
MARGARET COURT ARENA PROJECT:
PLEATED ROOF THE CROWNING FEATURE
TheMargaretCourtArenaprojectseesthetransformationofanexisting,
under-utilised outdoor tennis court into a year round entertainment
venue according to Aurecon Project Director Mark Sheldon. The arena
is the final element in the first stage of the $366 million Melbourne
Park upgrade.
On completion the 7,500 seat arena will be suitable for tennis, basketball, netball,
concert events and will be fully air-conditioned. The crowning feature and most visual
component of the venue is a sleek, copper penny coloured roof structure which is
acoustically lined, and can be opened or closed in under five minutes.
To produce the “pleated” roof structure, the shape of the major trusses represent a
series of interlocking props and ties, and give the appearance that the top chord of
the truss has been omitted. The trusses are fabricated from 610mm dia and 508mm
dia CHS members, typically ranging in thicknesses from 12.7mm up to 50.1mm.
Utilising the pleated shape of the roof, the operable roof panels consist of a series of
folded plates which work as trusses that “lean” on each other, with external members
added to accommodate the out-of-balance loads at the perimeter.
Pictured: The major fixed roof truss (below)
featuring the “Pleated” top chord, and the
Operable Panel leading edge truss during roof
construction.
© Copyright 2014
IMPORTANT INFORMATION This publication has been prepared by OneSteel (OneSteel Manufacturing Pty Limited ABN 42
004 651 325, trading as OneSteel Market Mills). The information contained in this publication is subject to change without
notice and to ensure accuracy, OneSteel recommends you seek your own professional advice in relation to the matters
covered by this publication to satisfy yourself and not to rely on the information without first doing so. Unless required by law
thecompanycannotacceptanyresponsibilityforanyloss,damageorconsequenceresultingfromtheuseofthispublication.
Photographs shown are representative only of typical applications, current at March 2014.
Collaboration between Aurecon, Lend Lease and GVP
Fabricatorswasthekeyindevelopingtheerectionmethodology
for the main roof elements. Each step was sequentially planned
and agreed, so that pre-cambers and pre-sets for the various
elements could be built in, allowing the structure to take its
correct geometry after all loads were added.
In a first for Australia, the operable panels are driven by bogies
featuring a single rail rack & pinion system for accurate control
of the roof positioning. The bogies were supported on 53kg and
86kg rail supplied by OneSteel’s EMRAIL business unit.
Steelwork has been used as the main structural solution for
many elements of this difficult project, including a steel framed
composite slab for the northern concourse extension, and
additional seating tiers built up off the existing concourse (with
the addition of steel strengthening beams under the existing
slab), and the unique ‘folded plate’ roof.
The concept for Margaret Court Arena by the Joint Venture
Architects, NH Architecture + Populous, was that the new
buildingshouldsitcomfortablyalongsidetheexistingRodLaver
Arena, which it abuts. It needed to demonstrate that it was a
separate building and that it had a more intimate capacity. The
desire was to develop a building which sits below the Rod Laver
Arena roof and which also has a tennis “high ball” line; a sleek
roof profile was required.
The solution was to allow the trailing edge of the roof panels
to be supported by the fixed roof via a series of seven mini
bogies for each of the two operable panels, which measure
approximately 57m x 32m. The concept then allowed a straight-
line dimension of only 1.25m between the top of the operable
roof panel and the fixed roof. To achieve such a tight dimension,
a single downturned major truss across the leading edge of
each operable roof panel supported by the drive bogies, which
park at the edge of the fixed roof when in the open position,
completes the structure. These leading edge trusses span 48.6
metres, are approximately 4.6 metres deep, and are typically
fabricated from 406dia x 9.5 CHS members, with a 500WC228
(300PLUS) top chord member. Supporting the leading edge of
the fixed roof, which in turn supports the trailing edge of the
operable roof panels, are the two interlocking prop/tie trusses
which span approximately 65 metres.
Preparatory work commenced on site in March 2012, including
extensions to the concourse and back-of-house areas, with
major construction works undertaken immediately after the
2013 Australian Open, including the addition of a fixed roof and
enclosure wall, prior to “handover” back to the Melbourne and
OlympicParksTrustforthehostingofthe2014AustralianOpen.
The fully completed arena will be handed over in November
2014, ready for the 2015 Australian Open.
Above:Thephotosdepicttheroofpanels
pre-assembly jigsdesignedandassembled
by GVPfollowedby theerection ofthe
individualroofpanelsafely positionedand
fixedonthemovingroofs.
Left:OperableRoofTrailingEdge“MiniBogie”

More Related Content

What's hot

Visual Dictionary 2- Conrete
Visual Dictionary 2- ConreteVisual Dictionary 2- Conrete
Visual Dictionary 2- Conreteconcrete
 
Power bike
Power bikePower bike
Power bikezebratwo
 
Mite Cycle
Mite CycleMite Cycle
Mite Cyclezebratwo
 
2532778 wartime-scooter
2532778 wartime-scooter2532778 wartime-scooter
2532778 wartime-scooterzebratwo
 
Portal frames final
Portal frames finalPortal frames final
Portal frames finalWen Crystal
 
Fat Tire Mini bike
Fat Tire Mini bikeFat Tire Mini bike
Fat Tire Mini bikezebratwo
 
Roof trusses
Roof trussesRoof trusses
Roof trussesRavi Pa
 
38720563 vintage-go-kart-mini-bike-plans-1950s
38720563 vintage-go-kart-mini-bike-plans-1950s38720563 vintage-go-kart-mini-bike-plans-1950s
38720563 vintage-go-kart-mini-bike-plans-1950szebratwo
 
2535613 king-midget-article
2535613 king-midget-article2535613 king-midget-article
2535613 king-midget-articlezebratwo
 
Construction Techniques Of framed Industrial Building by Shabaz Khan
Construction Techniques Of framed Industrial Building by Shabaz KhanConstruction Techniques Of framed Industrial Building by Shabaz Khan
Construction Techniques Of framed Industrial Building by Shabaz KhanShabaz Khan
 
2926577 midget-sports-car
2926577 midget-sports-car2926577 midget-sports-car
2926577 midget-sports-carzebratwo
 
Design of industrial storage shed and analysis of stresses produced on failur...
Design of industrial storage shed and analysis of stresses produced on failur...Design of industrial storage shed and analysis of stresses produced on failur...
Design of industrial storage shed and analysis of stresses produced on failur...IAEME Publication
 
What are the types of structural steel framing
What are the types of structural steel framingWhat are the types of structural steel framing
What are the types of structural steel framingnajeeb muhamed
 
2917143 plywood-scooter
2917143 plywood-scooter2917143 plywood-scooter
2917143 plywood-scooterzebratwo
 
Helicast Brochure REV 2. 1ST JUNE 2014
Helicast  Brochure REV 2. 1ST JUNE 2014Helicast  Brochure REV 2. 1ST JUNE 2014
Helicast Brochure REV 2. 1ST JUNE 2014Carol Ferrari
 
Presentation Teodor Caragioiu
Presentation Teodor CaragioiuPresentation Teodor Caragioiu
Presentation Teodor CaragioiuTeodor Caragioiu
 

What's hot (20)

Visual Dictionary 2- Conrete
Visual Dictionary 2- ConreteVisual Dictionary 2- Conrete
Visual Dictionary 2- Conrete
 
Trulift presentation
Trulift presentationTrulift presentation
Trulift presentation
 
Taipei 101
Taipei 101Taipei 101
Taipei 101
 
Mini dump
Mini dumpMini dump
Mini dump
 
Power bike
Power bikePower bike
Power bike
 
Mite Cycle
Mite CycleMite Cycle
Mite Cycle
 
2532778 wartime-scooter
2532778 wartime-scooter2532778 wartime-scooter
2532778 wartime-scooter
 
Portal frames final
Portal frames finalPortal frames final
Portal frames final
 
Fat Tire Mini bike
Fat Tire Mini bikeFat Tire Mini bike
Fat Tire Mini bike
 
B.cons ii (3)
B.cons ii (3)B.cons ii (3)
B.cons ii (3)
 
Roof trusses
Roof trussesRoof trusses
Roof trusses
 
38720563 vintage-go-kart-mini-bike-plans-1950s
38720563 vintage-go-kart-mini-bike-plans-1950s38720563 vintage-go-kart-mini-bike-plans-1950s
38720563 vintage-go-kart-mini-bike-plans-1950s
 
2535613 king-midget-article
2535613 king-midget-article2535613 king-midget-article
2535613 king-midget-article
 
Construction Techniques Of framed Industrial Building by Shabaz Khan
Construction Techniques Of framed Industrial Building by Shabaz KhanConstruction Techniques Of framed Industrial Building by Shabaz Khan
Construction Techniques Of framed Industrial Building by Shabaz Khan
 
2926577 midget-sports-car
2926577 midget-sports-car2926577 midget-sports-car
2926577 midget-sports-car
 
Design of industrial storage shed and analysis of stresses produced on failur...
Design of industrial storage shed and analysis of stresses produced on failur...Design of industrial storage shed and analysis of stresses produced on failur...
Design of industrial storage shed and analysis of stresses produced on failur...
 
What are the types of structural steel framing
What are the types of structural steel framingWhat are the types of structural steel framing
What are the types of structural steel framing
 
2917143 plywood-scooter
2917143 plywood-scooter2917143 plywood-scooter
2917143 plywood-scooter
 
Helicast Brochure REV 2. 1ST JUNE 2014
Helicast  Brochure REV 2. 1ST JUNE 2014Helicast  Brochure REV 2. 1ST JUNE 2014
Helicast Brochure REV 2. 1ST JUNE 2014
 
Presentation Teodor Caragioiu
Presentation Teodor CaragioiuPresentation Teodor Caragioiu
Presentation Teodor Caragioiu
 

Similar to Onesteel MCourt Arena_0314

Building construction-2 project-2
Building construction-2 project-2Building construction-2 project-2
Building construction-2 project-2kerneng
 
2003v12 building tension
2003v12 building tension2003v12 building tension
2003v12 building tensionHugoCopire1
 
Design Appraisal report
Design Appraisal reportDesign Appraisal report
Design Appraisal reportConor Meaney
 
Long span structures case study.pptx
Long span structures case study.pptxLong span structures case study.pptx
Long span structures case study.pptxPrituJadhav1
 
115659118 pre-engineered-buildings (1)
115659118 pre-engineered-buildings (1)115659118 pre-engineered-buildings (1)
115659118 pre-engineered-buildings (1)hlksd
 
115659118 pre-engineered-buildings
115659118 pre-engineered-buildings115659118 pre-engineered-buildings
115659118 pre-engineered-buildingshlksd
 
O2 Arena Booklet
O2 Arena BookletO2 Arena Booklet
O2 Arena Bookleteileen_0692
 
08 - Portal Frame.pptx
08 - Portal Frame.pptx08 - Portal Frame.pptx
08 - Portal Frame.pptx2022786965
 
2013-08-29 econogrid WEB
2013-08-29 econogrid WEB2013-08-29 econogrid WEB
2013-08-29 econogrid WEBJanine Course
 
Lincoln arc welding article183
Lincoln arc welding article183Lincoln arc welding article183
Lincoln arc welding article183Miklos Peller, Sr.
 
The space frame structure
The space frame structureThe space frame structure
The space frame structurebadekarbhavana
 

Similar to Onesteel MCourt Arena_0314 (20)

Building construction-2 project-2
Building construction-2 project-2Building construction-2 project-2
Building construction-2 project-2
 
2003v12 building tension
2003v12 building tension2003v12 building tension
2003v12 building tension
 
Design Appraisal report
Design Appraisal reportDesign Appraisal report
Design Appraisal report
 
Wcee2012 4617
Wcee2012 4617Wcee2012 4617
Wcee2012 4617
 
Long span structures case study.pptx
Long span structures case study.pptxLong span structures case study.pptx
Long span structures case study.pptx
 
ASHTECH
ASHTECHASHTECH
ASHTECH
 
Retractable systems
Retractable systemsRetractable systems
Retractable systems
 
115659118 pre-engineered-buildings (1)
115659118 pre-engineered-buildings (1)115659118 pre-engineered-buildings (1)
115659118 pre-engineered-buildings (1)
 
115659118 pre-engineered-buildings
115659118 pre-engineered-buildings115659118 pre-engineered-buildings
115659118 pre-engineered-buildings
 
IABSE 2002
IABSE 2002IABSE 2002
IABSE 2002
 
O2 booklet
O2 bookletO2 booklet
O2 booklet
 
O2 Arena Booklet
O2 Arena BookletO2 Arena Booklet
O2 Arena Booklet
 
O2 booklet
O2 bookletO2 booklet
O2 booklet
 
08 - Portal Frame.pptx
08 - Portal Frame.pptx08 - Portal Frame.pptx
08 - Portal Frame.pptx
 
2013-08-29 econogrid WEB
2013-08-29 econogrid WEB2013-08-29 econogrid WEB
2013-08-29 econogrid WEB
 
ASHJACK
ASHJACKASHJACK
ASHJACK
 
Lincoln arc welding article183
Lincoln arc welding article183Lincoln arc welding article183
Lincoln arc welding article183
 
CONFORTO
CONFORTOCONFORTO
CONFORTO
 
The space frame structure
The space frame structureThe space frame structure
The space frame structure
 
Space frame - Intro
Space frame -  IntroSpace frame -  Intro
Space frame - Intro
 

More from Mark Sheldon

Structural Dynamics in Tennis Courts
Structural Dynamics in Tennis CourtsStructural Dynamics in Tennis Courts
Structural Dynamics in Tennis CourtsMark Sheldon
 
Presentation to Interior Designers
Presentation to Interior DesignersPresentation to Interior Designers
Presentation to Interior DesignersMark Sheldon
 
Steel Compliance from the Consulting Engineer's Perspective
Steel Compliance from the Consulting Engineer's PerspectiveSteel Compliance from the Consulting Engineer's Perspective
Steel Compliance from the Consulting Engineer's PerspectiveMark Sheldon
 
Concrete 2015 - Dynamics at Tennis Centre- Sheldon Delaney
Concrete 2015 - Dynamics at Tennis Centre- Sheldon DelaneyConcrete 2015 - Dynamics at Tennis Centre- Sheldon Delaney
Concrete 2015 - Dynamics at Tennis Centre- Sheldon DelaneyMark Sheldon
 
Civil Engineers Aust - Margaret Court Arena April 2014
Civil Engineers Aust - Margaret Court Arena April 2014Civil Engineers Aust - Margaret Court Arena April 2014
Civil Engineers Aust - Margaret Court Arena April 2014Mark Sheldon
 
TEDA ACSE magazine Sept 05
TEDA ACSE magazine Sept 05TEDA ACSE magazine Sept 05
TEDA ACSE magazine Sept 05Mark Sheldon
 
MCG Concrete 2005 050725
MCG Concrete 2005 050725MCG Concrete 2005 050725
MCG Concrete 2005 050725Mark Sheldon
 

More from Mark Sheldon (10)

Structural Dynamics in Tennis Courts
Structural Dynamics in Tennis CourtsStructural Dynamics in Tennis Courts
Structural Dynamics in Tennis Courts
 
Presentation to Interior Designers
Presentation to Interior DesignersPresentation to Interior Designers
Presentation to Interior Designers
 
Steel Compliance from the Consulting Engineer's Perspective
Steel Compliance from the Consulting Engineer's PerspectiveSteel Compliance from the Consulting Engineer's Perspective
Steel Compliance from the Consulting Engineer's Perspective
 
Concrete 2015 - Dynamics at Tennis Centre- Sheldon Delaney
Concrete 2015 - Dynamics at Tennis Centre- Sheldon DelaneyConcrete 2015 - Dynamics at Tennis Centre- Sheldon Delaney
Concrete 2015 - Dynamics at Tennis Centre- Sheldon Delaney
 
Civil Engineers Aust - Margaret Court Arena April 2014
Civil Engineers Aust - Margaret Court Arena April 2014Civil Engineers Aust - Margaret Court Arena April 2014
Civil Engineers Aust - Margaret Court Arena April 2014
 
TEDA ACSE magazine Sept 05
TEDA ACSE magazine Sept 05TEDA ACSE magazine Sept 05
TEDA ACSE magazine Sept 05
 
SEI 2002
SEI 2002SEI 2002
SEI 2002
 
MCG Concrete 2005 050725
MCG Concrete 2005 050725MCG Concrete 2005 050725
MCG Concrete 2005 050725
 
CEI 2000
CEI 2000CEI 2000
CEI 2000
 
AISC 1999
AISC 1999AISC 1999
AISC 1999
 

Onesteel MCourt Arena_0314

  • 1. MARGARET COURT ARENA PROJECT: PLEATED ROOF THE CROWNING FEATURE TheMargaretCourtArenaprojectseesthetransformationofanexisting, under-utilised outdoor tennis court into a year round entertainment venue according to Aurecon Project Director Mark Sheldon. The arena is the final element in the first stage of the $366 million Melbourne Park upgrade. On completion the 7,500 seat arena will be suitable for tennis, basketball, netball, concert events and will be fully air-conditioned. The crowning feature and most visual component of the venue is a sleek, copper penny coloured roof structure which is acoustically lined, and can be opened or closed in under five minutes. To produce the “pleated” roof structure, the shape of the major trusses represent a series of interlocking props and ties, and give the appearance that the top chord of the truss has been omitted. The trusses are fabricated from 610mm dia and 508mm dia CHS members, typically ranging in thicknesses from 12.7mm up to 50.1mm. Utilising the pleated shape of the roof, the operable roof panels consist of a series of folded plates which work as trusses that “lean” on each other, with external members added to accommodate the out-of-balance loads at the perimeter. Pictured: The major fixed roof truss (below) featuring the “Pleated” top chord, and the Operable Panel leading edge truss during roof construction.
  • 2. © Copyright 2014 IMPORTANT INFORMATION This publication has been prepared by OneSteel (OneSteel Manufacturing Pty Limited ABN 42 004 651 325, trading as OneSteel Market Mills). The information contained in this publication is subject to change without notice and to ensure accuracy, OneSteel recommends you seek your own professional advice in relation to the matters covered by this publication to satisfy yourself and not to rely on the information without first doing so. Unless required by law thecompanycannotacceptanyresponsibilityforanyloss,damageorconsequenceresultingfromtheuseofthispublication. Photographs shown are representative only of typical applications, current at March 2014. Collaboration between Aurecon, Lend Lease and GVP Fabricatorswasthekeyindevelopingtheerectionmethodology for the main roof elements. Each step was sequentially planned and agreed, so that pre-cambers and pre-sets for the various elements could be built in, allowing the structure to take its correct geometry after all loads were added. In a first for Australia, the operable panels are driven by bogies featuring a single rail rack & pinion system for accurate control of the roof positioning. The bogies were supported on 53kg and 86kg rail supplied by OneSteel’s EMRAIL business unit. Steelwork has been used as the main structural solution for many elements of this difficult project, including a steel framed composite slab for the northern concourse extension, and additional seating tiers built up off the existing concourse (with the addition of steel strengthening beams under the existing slab), and the unique ‘folded plate’ roof. The concept for Margaret Court Arena by the Joint Venture Architects, NH Architecture + Populous, was that the new buildingshouldsitcomfortablyalongsidetheexistingRodLaver Arena, which it abuts. It needed to demonstrate that it was a separate building and that it had a more intimate capacity. The desire was to develop a building which sits below the Rod Laver Arena roof and which also has a tennis “high ball” line; a sleek roof profile was required. The solution was to allow the trailing edge of the roof panels to be supported by the fixed roof via a series of seven mini bogies for each of the two operable panels, which measure approximately 57m x 32m. The concept then allowed a straight- line dimension of only 1.25m between the top of the operable roof panel and the fixed roof. To achieve such a tight dimension, a single downturned major truss across the leading edge of each operable roof panel supported by the drive bogies, which park at the edge of the fixed roof when in the open position, completes the structure. These leading edge trusses span 48.6 metres, are approximately 4.6 metres deep, and are typically fabricated from 406dia x 9.5 CHS members, with a 500WC228 (300PLUS) top chord member. Supporting the leading edge of the fixed roof, which in turn supports the trailing edge of the operable roof panels, are the two interlocking prop/tie trusses which span approximately 65 metres. Preparatory work commenced on site in March 2012, including extensions to the concourse and back-of-house areas, with major construction works undertaken immediately after the 2013 Australian Open, including the addition of a fixed roof and enclosure wall, prior to “handover” back to the Melbourne and OlympicParksTrustforthehostingofthe2014AustralianOpen. The fully completed arena will be handed over in November 2014, ready for the 2015 Australian Open. Above:Thephotosdepicttheroofpanels pre-assembly jigsdesignedandassembled by GVPfollowedby theerection ofthe individualroofpanelsafely positionedand fixedonthemovingroofs. Left:OperableRoofTrailingEdge“MiniBogie”