SlideShare a Scribd company logo
1 of 4
Download to read offline
Building Tension
Martin Simpson and Mike King
Although the Commonwealth
Games were highly successful, the
41,000-seat stadium could never be vi-
able as a track-and-field venue alone.
The key to its ongoing success was its
permanent role as a world-class soccer
venue for Manchester City Football
Club, with a temporary role mid-con-
struction as the focal point of the Com-
monwealth Games. The legacy it leaves
is a landmark building of iconic architec-
ture and a stimulus for the gentrification
of an underdeveloped sector of the city.
Immediately after the Common-
wealth Games finished, work began in
earnest to convert the track and field
venue to a soccer stadium. This in-
volved excavating the area of the ath-
letic track to 6 m below ground level,
building another level of terraces at the
new, lower field level, and constructing
the entire north stand.
Soccer fields have different dimen-
sions from track venues, and spectators
have different perspectives in the
sports’ respective stadiums. Modern
soccer stadiums require spectators to be
seated as close to the field as possible to
maximize the atmosphere and provide
the best possible views. A track is much
larger than a soccer field, so if the Man-
chester Stadium were to remain a duel-
use venue, then soccer spectators
would be seated far from the field. Per-
manent, dual-purpose facilities have
been adopted in a number of stadiums
in Europe, but quality as a soccer sta-
dium is compromised heavily.
STRUCTURE
The stadium is formed from several
structural systems, each chosen to
achieve the structural performance,
architectural quality and cost effi-
ciency. Concrete frame and precast ter-
race units form the bowl structure,
while the roof was formed from struc-
tural steel rafters suspended from an
innovative cable-net structure. This ar-
ticle discusses the steel roof in more
detail.
The most visible features of the sta-
dium are the 12 perimeter masts that
rise as high as 70 m (230’) into the air.
Each of these masts is supported at the
base by either a concrete plant tower
linked back to the bowl structure, or
from a plinth at ground level.
These masts support the cable net,
which is formed from forestay cables to
the roof and backstay cables to the
ground. The forestay cables are
grouped together in fans of either five
or seven cables, and formed from a sin-
gle, spiral-strand cable, which in turn
supports an individual rafter.
Modern Steel Construction • December 2003
© Dennis GilbertVIEW
The City of Manchester Stadium in the United Kingdom was built for two purposes:
to provide both the centerpiece track and field venue for the XVII Commonwealth
Games, and a world-class stadium for the Manchester Football Club.
December 2003 • Modern Steel Construction
At each mast head, the tension
forces of a forestay group are trans-
ferred into compression in the masts
and tension in a pair of backstays. Each
of the backstays in the pair comprise
four, grade 460 N/mm2 (67 ksi)
“Macalloy” rods anchored to the
ground with multi-strand ground an-
chors pre-compressing concrete piles.
The cigar-shaped masts take the re-
solved compression force from the
forestay and backstay cable tensions.
They are fabricated from curved steel
plate. The cigar profile is achieved by
constructing each mast of a cylindrical
central piece and two conical end
pieces. The central sections range in di-
ameter from 1500 mm (59”) for the four
side masts and 1300 mm (51”) for the
four end masts and four corner masts.
All masts taper to 750 mm (30”) diame-
ter at the lower ends and 650 mm (26”)
diameter at the mast heads, with wall
thicknesses between 20 mm and 30 mm
(0.8” and 1.2”).
ROOF UPLIFT
As with all lightweight roofs, wind-
induced uplift was one of the most sig-
nificant design criteria. There are sev-
eral solutions for maintaining tension
in cables under uplift, including in-
creasing the mass of the roof by addi-
tional ballast or using opposing cables
with tension and compression rings.
Program and budget constraints forced
the designers to explore an alternative
solution.
The stadium uses a method called
“the grounded tension ring,” an inno-
vative adaptation of the opposing cable
solution. A “catenary cable” links all
the forestays together. At each corner of
the stadium this catenary cable is tied
back to the ground by four “corner tie
cables.” By pulling down at the four
corners a tensile force can be induced
into the entire cable net. The geometry
of the cable net was defined in such a
way that this pretension force was ex-
actly equal to the force induced in the
forestay cables under the worst-case
wind-uplift condition. Therefore the
cables do not go slack under any wind-
Three of the permanent stands were constructed in a horseshoe arrangement along with their associated roofs for the stadium’s mid-con-
struction role in the Commonwealth Games. Photo © Dennis GilbertVIEW
The most visible features of the stadium are the 12 support masts (shown in blue, above).Tensile forces are maintained in the cable net under
all loading conditions.
uplift situation. The software used for
the structural analysis of the roof, in-
cluding the form-finding and non-lin-
ear analysis (static P-delta and
dynamic relaxation) was Oasys GSA.
Oasys GSA is written by Arup for in-
ternal use, but is also available exter-
nally as commercial software.
The geometry of the cable net used
for the stadium is such that it can form
an independent, statically determinate
structure under pre-stress, with just the
cables and the masts. As a result, it
could be erected independently of the
rafters. The use of the grounded ten-
sion-ring cable net meant the roof
could be installed in two distinct
phases. For the Commonwealth
Games, three of the permanent stands
were constructed in a horseshoe
arrangement along with their associ-
ated roofs. These gave a homogeneous
look to the stadium even though it was
only partially complete. The final per-
manent stand and the final portion of
the roof were erected during phase two
for the soccer conversion.
ROOF GRAVITY LOADS
The load path for downwards loads
can be idealized as a standard triangu-
lated system, with most loads apart
from self weight applied directly to the
cladding. There are two distinct types
of cladding:
● Standing-seam aluminium cladding
(Kalzip) to the majority of the roof.
● Transparent polycarbonate to the
leading edge. This transparent zone
increased the amount of natural
light entering the bowl, which im-
proved the environment in the sta-
dium for players, spectators and
television coverage, in addition to
assisting grass growth of the natural
field.
The standing-seam cladding is sup-
ported directly from structural liner
trays that span approximately 4 m (13’)
between wide-flange purlins. The
purlins in turn span between the 76
rafters that run in a radial pattern. The
rafters are fabricated steel box sections,
900 mm deep by 300 mm wide (35” by
12”), tapering to 450 mm deep (18”) at
the leading end and rear end. The
flanges of the box sections vary be-
tween 12 mm and 55 mm (0.5” and
2.2”) and are optimized to provide
greatest efficiency. The webs of the box
section are constant at 6 mm (1
/4”) thick.
Each rafter is supported at two
points:
● At the rear of the stadium, each
rafter is supported from the con-
crete bowl by an integral “V strut”
formed by two inclined struts of cir-
cular HSS.
● Towards the leading edge, the rafter
is effectively hung from the cable
net by means of the “Forestay-
strut.”
The maximum rafter cantilever is
15 m (49’), and the back span of a rafter
is 37 m (121’). This ratio was derived to
equate the back-span and cantilever
moments for the longest rafter under a
variety of load cases, and to optimize
the rafter design. The geometry of back
span to cantilever for other rafters then
was dictated by the geometry of the
cable net.
DESIGN OF ROOF PLATE
The roof has a saddle profile due to
the constraints of the bowl geometry. A
roof with a curving profile can be sub-
jected to arching in the roof plate. For
the stadium, the occurrence of arching
was not desired as it tries to short-cir-
cuit the primary load paths through the
cable net. This secondary load path
was also a problem for thermal expan-
sion and would have required a signif-
icant increase in the size of the purlins
to facilitate it. One solution would be to
allow movement joints at the four cor-
ners to coincide with the major thermal
joints in the concrete bowl. However,
waterproofing details at movement
joints are notoriously difficult and ex-
pensive, so the design team adopted a
solution of regular but much smaller
movement joints throughout the roof.
These joints were incorporated every
other bay through simple slotted holes
in the purlins and shoulder bolts. The
movements at each joint were in the
order of 25 mm (1”), which the stan-
dard cladding and flashing details
could accommodate. The lateral stabil-
ity of the rafter was provided by cross-
bracing every other bay.
Lateral-torsional stability and
minor-axis buckling of the rafter was
also a key factor in the design, espe-
cially under wind-uplift conditions
where effective restraint from the
purlins could not be provided. The so-
lution was to use U-frame stability,
more commonly associated with
bridge design. By using internal di-
aphragms within the box-section
rafters at the purlin positions, the
bending resistance of the purlin could
restrain the bottom flange of the rafter.
DESIGN OF THE STADIUM
ROOF UNDER SERVICE
CONDITIONS
The assessment of the roof in service
was one of the most complex elements
of the roof design. At the time of the as-
sessment into behavior of the roof
under service conditions, it was still the
intention to use laminated glass as the
cladding to the leading edge in place of
polycarbonate cladding. The use of
glass in such a roof imposed strict lim-
its as to acceptable deformations. The
behavior of the roof was assessed for
the following criteria:
Drainage Slope—The only gutter is
located at the rear edge of the roof. All
water should flow to the outside of the
stadium to prevent ponding or water
running off the leading edge. Each
rafter and cladding panel was assessed
to ensure that there was always a posi-
tive fall of 1.5° under all service-load
conditions.
Visual Deformation—The visual
performance of the rafters was main-
tained at 1:100 for the cantilever and
1:200 for the back spans. However the
overall total deflection was controlled
by the deflection of the cable net, which
was also limited to 1:100.
Shear Strain and Warping—The
shear strain was measured as the
change in angle at the four corners of a
cladding panel, and the warping was
measured as the mean change in dis-
tance out of plane at each of the four
corners. These criteria were assessed
for every cladding panel.
Movement—The length of slots cut
in the purlins to allow movement was
assessed for various load cases and
studies were carried out to determine
the effect of the movement joints seiz-
ing up.
Though each of the rafters are sup-
ported by a forestay, the forestays
themselves are grouped together in
‘fans’ supported by single masts. De-
flection in the rafters is controlled
largely by rigid body rotation caused
by extension of the backstays and rota-
tion of the masts and rafters. If an indi-
vidual rafter is loaded heavily then the
subsequent rotation of the mast also
will lower all the rafters attached to
Modern Steel Construction • December 2003
that mast. Therefore the forestay cable
fans act as load-sharing devices with
respect to relative displacement be-
tween rafters.
DESIGNING FOR ROBUSTNESS
Blast protection is important for sta-
diums, where roofs cover thousands of
spectators. The robustness require-
ments of this stadium were investi-
gated thoroughly leading to the use of
multiple cables for highly sensitive
load paths.
● Each backstay is made from four el-
ements, which in turn are attached
to two discrete foundation plinths.
● Each catenary cable and corner tie is
made from four cables.
● Non-linear studies were carried out
to investigate the results of losses of
elements ranging from forestay ca-
bles to entire towers.
Under extreme emergency-load
cases, stability of the four cable ele-
ments is maintained with any three re-
maining cables from the group of four.
In addition, the primary connections
involving multiple cables, i.e. the mast
heads, were designed taking into ac-
count the eccentricities caused by los-
ing one or more forestay or backstay
cables. The conclusion was that there is
a sufficient degree of redundancy in
the load paths, which will avoid dis-
proportionate collapse under most con-
ceivable extreme-loading conditions.
Fire protection is provided inher-
ently to the bowl, due to the use of re-
inforced concrete. The roof structure is
not fire-protected, as there is negligible
combustible material in the terrace
area. Most importantly, the roof is not
required for the stability of the stadium
bowl.
ROOF CONSTRUCTION
SEQUENCE
Arup’s original erection proposal
took advantage of the mast and cable-
net structure’s independence from the
roof steel structure by erecting and pre-
tensioning the cable-net prior to the
lifting and attachment of rafter and
purlin braced pairs. Due to program
constraints, it was decided to bring for-
ward the erection of roof plane steel-
work so that it could be erected in
parallel with the lifting of masts and as-
sembly and stressing of the cable-net.
The end result was a framework of
temporary steel props erected to sup-
port the leading edge of the rafters.
The revised erection scheme created
a platform at roof level on which the
cable-net could be laid out prior to final
assembly and stressing. Once erection
of the masts and assembly of the cable-
net was complete, the cable-net was
made taut by pulling down on the
backstays and connecting them to their
pinned bases. The final tension was ac-
complished by jacking the four corner
ties at the top of the corner-tie frames.
Upon completion of the stressing
phase, individual rafters were lifted off
their props and connected to the cable-
net, after which the temporary props
were removed.
During the conversion of the sta-
dium for soccer use, the roof of the
north stand was completed as origi-
nally intended. The cable net was in
place from phase one and each roof
panel was lifted into position and sup-
ported from the rear of the bowl and
hung from the cable net. This phase of
the works was carried out successfully
to a very tight schedule.
CONCLUSION
The successful design of the cable-
stayed roof for the City of Manchester
Stadium can largely be attributed to the
teamwork between the structural engi-
neers, architects and steelwork fabrica-
tors. The roof is a ground-breaking
structure, incorporating many innova-
tive features that are sure to be re-
peated on future stadium projects
around the world, especially the first
use of the grounded tension ring phi-
losophy.
REFERENCE
Simpson, M. “The Analysis and Design
of the City of Manchester Stadium.”
Proceedings of the Fifth International
Conference on Space Structures, Sur-
rey, 2003, pp 827-836.
OWNER
Manchester City Council
OPERATOR
Manchester City Football Club
ARCHITECT AND
STRUCTURAL ENGINEERS
Arup Associates, London
CONSTRUCTION MANAGER
Laing O’Rourke, Kent, UK
ENGINEERING SOFTWARE
Oasys GSA
The Manchester Stadium in its final configuration as a soccer venue. Photo courtesy Lee Jordan.
December 2003 • Modern Steel Construction

More Related Content

What's hot

Cable stayed bridges of prestressed concrete.
Cable stayed bridges of prestressed concrete.Cable stayed bridges of prestressed concrete.
Cable stayed bridges of prestressed concrete.Franco Bontempi
 
PPT ON DESIGN OF COLUMN BRACES
PPT ON DESIGN OF COLUMN BRACESPPT ON DESIGN OF COLUMN BRACES
PPT ON DESIGN OF COLUMN BRACESsrinivas cnu
 
6 portal frames
6 portal frames6 portal frames
6 portal framesPrabhu mk
 
Lecture 11 s.s.iii Design of Steel Structures - Faculty of Civil Engineering ...
Lecture 11 s.s.iii Design of Steel Structures - Faculty of Civil Engineering ...Lecture 11 s.s.iii Design of Steel Structures - Faculty of Civil Engineering ...
Lecture 11 s.s.iii Design of Steel Structures - Faculty of Civil Engineering ...Ursachi Răzvan
 
Lecture 8 s.s.iii Steel Structures
Lecture 8  s.s.iii Steel Structures Lecture 8  s.s.iii Steel Structures
Lecture 8 s.s.iii Steel Structures Ursachi Răzvan
 
IRJET- Analysis and Design of Segmental Box Girder Bridge
IRJET- Analysis and Design of Segmental Box Girder BridgeIRJET- Analysis and Design of Segmental Box Girder Bridge
IRJET- Analysis and Design of Segmental Box Girder BridgeIRJET Journal
 
Comparative analysis and design of box girder bridge sub structure with two di
Comparative analysis and design of box girder bridge sub structure with two diComparative analysis and design of box girder bridge sub structure with two di
Comparative analysis and design of box girder bridge sub structure with two diIAEME Publication
 
Seismic protection of cable stayed bridge using supplemental devices
Seismic protection of cable stayed bridge using supplemental devicesSeismic protection of cable stayed bridge using supplemental devices
Seismic protection of cable stayed bridge using supplemental devicesManish Mall
 
Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering IaşiLecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering IaşiUrsachi Răzvan
 
Analyze and design of suspension bridge using sap2000
Analyze and design of suspension bridge using sap2000Analyze and design of suspension bridge using sap2000
Analyze and design of suspension bridge using sap2000vivatechijri
 
Cable stayed ppt acp
Cable stayed ppt acpCable stayed ppt acp
Cable stayed ppt acpJigar Shah
 
STUDY ON VARIATION OF JOINT FORCES IN STIFFENING TRUSS OF CABLE-STAYED BRIDGE
STUDY ON VARIATION OF JOINT FORCES IN STIFFENING TRUSS OF CABLE-STAYED BRIDGESTUDY ON VARIATION OF JOINT FORCES IN STIFFENING TRUSS OF CABLE-STAYED BRIDGE
STUDY ON VARIATION OF JOINT FORCES IN STIFFENING TRUSS OF CABLE-STAYED BRIDGEAELC
 
Lecture 2 s. s. iii Design of Steel Structures - Faculty of Civil Engineering...
Lecture 2 s. s. iii Design of Steel Structures - Faculty of Civil Engineering...Lecture 2 s. s. iii Design of Steel Structures - Faculty of Civil Engineering...
Lecture 2 s. s. iii Design of Steel Structures - Faculty of Civil Engineering...Ursachi Răzvan
 
Design of column base plates anchor bolt
Design of column base plates anchor boltDesign of column base plates anchor bolt
Design of column base plates anchor boltKhaled Eid
 
Ppt polyvalent hall romania(cluj napoca)
Ppt polyvalent hall  romania(cluj napoca)Ppt polyvalent hall  romania(cluj napoca)
Ppt polyvalent hall romania(cluj napoca)akhil madhani
 
Lecture 1 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 1 s.s.iii Design of Steel Structures - Faculty of Civil Engineering IaşiLecture 1 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 1 s.s.iii Design of Steel Structures - Faculty of Civil Engineering IaşiUrsachi Răzvan
 

What's hot (20)

EC3 design
EC3 designEC3 design
EC3 design
 
Cable stayed bridges of prestressed concrete.
Cable stayed bridges of prestressed concrete.Cable stayed bridges of prestressed concrete.
Cable stayed bridges of prestressed concrete.
 
PPT ON DESIGN OF COLUMN BRACES
PPT ON DESIGN OF COLUMN BRACESPPT ON DESIGN OF COLUMN BRACES
PPT ON DESIGN OF COLUMN BRACES
 
6 portal frames
6 portal frames6 portal frames
6 portal frames
 
Lecture 11 s.s.iii Design of Steel Structures - Faculty of Civil Engineering ...
Lecture 11 s.s.iii Design of Steel Structures - Faculty of Civil Engineering ...Lecture 11 s.s.iii Design of Steel Structures - Faculty of Civil Engineering ...
Lecture 11 s.s.iii Design of Steel Structures - Faculty of Civil Engineering ...
 
Lecture 8 s.s.iii Steel Structures
Lecture 8  s.s.iii Steel Structures Lecture 8  s.s.iii Steel Structures
Lecture 8 s.s.iii Steel Structures
 
IRJET- Analysis and Design of Segmental Box Girder Bridge
IRJET- Analysis and Design of Segmental Box Girder BridgeIRJET- Analysis and Design of Segmental Box Girder Bridge
IRJET- Analysis and Design of Segmental Box Girder Bridge
 
Comparative analysis and design of box girder bridge sub structure with two di
Comparative analysis and design of box girder bridge sub structure with two diComparative analysis and design of box girder bridge sub structure with two di
Comparative analysis and design of box girder bridge sub structure with two di
 
Seismic protection of cable stayed bridge using supplemental devices
Seismic protection of cable stayed bridge using supplemental devicesSeismic protection of cable stayed bridge using supplemental devices
Seismic protection of cable stayed bridge using supplemental devices
 
Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering IaşiLecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
 
Analyze and design of suspension bridge using sap2000
Analyze and design of suspension bridge using sap2000Analyze and design of suspension bridge using sap2000
Analyze and design of suspension bridge using sap2000
 
Cable stayed ppt acp
Cable stayed ppt acpCable stayed ppt acp
Cable stayed ppt acp
 
STUDY ON VARIATION OF JOINT FORCES IN STIFFENING TRUSS OF CABLE-STAYED BRIDGE
STUDY ON VARIATION OF JOINT FORCES IN STIFFENING TRUSS OF CABLE-STAYED BRIDGESTUDY ON VARIATION OF JOINT FORCES IN STIFFENING TRUSS OF CABLE-STAYED BRIDGE
STUDY ON VARIATION OF JOINT FORCES IN STIFFENING TRUSS OF CABLE-STAYED BRIDGE
 
Lecture 2 s. s. iii Design of Steel Structures - Faculty of Civil Engineering...
Lecture 2 s. s. iii Design of Steel Structures - Faculty of Civil Engineering...Lecture 2 s. s. iii Design of Steel Structures - Faculty of Civil Engineering...
Lecture 2 s. s. iii Design of Steel Structures - Faculty of Civil Engineering...
 
Design of column base plates anchor bolt
Design of column base plates anchor boltDesign of column base plates anchor bolt
Design of column base plates anchor bolt
 
Ppt polyvalent hall romania(cluj napoca)
Ppt polyvalent hall  romania(cluj napoca)Ppt polyvalent hall  romania(cluj napoca)
Ppt polyvalent hall romania(cluj napoca)
 
Lecture 1 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 1 s.s.iii Design of Steel Structures - Faculty of Civil Engineering IaşiLecture 1 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 1 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
 
Rail bridge and composite girder bridge analysis
Rail bridge and composite girder bridge analysisRail bridge and composite girder bridge analysis
Rail bridge and composite girder bridge analysis
 
Steel structures
Steel structuresSteel structures
Steel structures
 
Steel structures failure
Steel structures failureSteel structures failure
Steel structures failure
 

Similar to 2003v12 building tension

Lincoln arc welding article183
Lincoln arc welding article183Lincoln arc welding article183
Lincoln arc welding article183Miklos Peller, Sr.
 
Shaft sinking
Shaft sinking Shaft sinking
Shaft sinking OmKaitade
 
Onesteel MCourt Arena_0314
Onesteel MCourt Arena_0314Onesteel MCourt Arena_0314
Onesteel MCourt Arena_0314Mark Sheldon
 
Radial gates psc ancho
Radial gates psc anchoRadial gates psc ancho
Radial gates psc anchoBhanu Prasad
 
Long span structures case study.pptx
Long span structures case study.pptxLong span structures case study.pptx
Long span structures case study.pptxPrituJadhav1
 
Earthquake Resistant Structures Taipei 101
Earthquake Resistant Structures   Taipei 101Earthquake Resistant Structures   Taipei 101
Earthquake Resistant Structures Taipei 101Khushboo Sood
 
The space frame structure
The space frame structureThe space frame structure
The space frame structurebadekarbhavana
 
IRJET- Sandwich Plate System in Bridge Deck – A Review
IRJET-  	  Sandwich Plate System in Bridge Deck – A ReviewIRJET-  	  Sandwich Plate System in Bridge Deck – A Review
IRJET- Sandwich Plate System in Bridge Deck – A ReviewIRJET Journal
 
Cast in situ bridge superstracture
Cast in situ bridge superstractureCast in situ bridge superstracture
Cast in situ bridge superstracturekhushal tadas
 
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Hossam Shafiq II
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeMohammed Abdelkawy
 
Calculation Note Final
Calculation Note FinalCalculation Note Final
Calculation Note FinalMohamed Elfike
 
Olympiapark, munich
Olympiapark, munichOlympiapark, munich
Olympiapark, munichjigarramani1
 
Experimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabExperimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabIRJET Journal
 

Similar to 2003v12 building tension (20)

Lincoln arc welding article183
Lincoln arc welding article183Lincoln arc welding article183
Lincoln arc welding article183
 
Guida ARBED edifici alti
Guida ARBED edifici altiGuida ARBED edifici alti
Guida ARBED edifici alti
 
Shaft sinking
Shaft sinking Shaft sinking
Shaft sinking
 
Onesteel MCourt Arena_0314
Onesteel MCourt Arena_0314Onesteel MCourt Arena_0314
Onesteel MCourt Arena_0314
 
Radial gates psc ancho
Radial gates psc anchoRadial gates psc ancho
Radial gates psc ancho
 
Long span structures case study.pptx
Long span structures case study.pptxLong span structures case study.pptx
Long span structures case study.pptx
 
Earthquake Resistant Structures Taipei 101
Earthquake Resistant Structures   Taipei 101Earthquake Resistant Structures   Taipei 101
Earthquake Resistant Structures Taipei 101
 
Shell structure
Shell structureShell structure
Shell structure
 
The space frame structure
The space frame structureThe space frame structure
The space frame structure
 
Form Active system
Form Active systemForm Active system
Form Active system
 
IRJET- Sandwich Plate System in Bridge Deck – A Review
IRJET-  	  Sandwich Plate System in Bridge Deck – A ReviewIRJET-  	  Sandwich Plate System in Bridge Deck – A Review
IRJET- Sandwich Plate System in Bridge Deck – A Review
 
Cast in situ bridge superstracture
Cast in situ bridge superstractureCast in situ bridge superstracture
Cast in situ bridge superstracture
 
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridge
 
Cable stayed bridge
Cable stayed bridgeCable stayed bridge
Cable stayed bridge
 
c&w project work
c&w project workc&w project work
c&w project work
 
Calculation Note Final
Calculation Note FinalCalculation Note Final
Calculation Note Final
 
Olympiapark, munich
Olympiapark, munichOlympiapark, munich
Olympiapark, munich
 
Experimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabExperimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor Slab
 
competition equipment
competition equipmentcompetition equipment
competition equipment
 

More from HugoCopire1

Educational tour report
Educational tour reportEducational tour report
Educational tour reportHugoCopire1
 
Creating excellent-primary-schools 2
Creating excellent-primary-schools 2Creating excellent-primary-schools 2
Creating excellent-primary-schools 2HugoCopire1
 
dispensary theory
dispensary theory dispensary theory
dispensary theory HugoCopire1
 
Tormax united-kingdom i-motion-2401_specifications_barrier-free-building
Tormax united-kingdom i-motion-2401_specifications_barrier-free-buildingTormax united-kingdom i-motion-2401_specifications_barrier-free-building
Tormax united-kingdom i-motion-2401_specifications_barrier-free-buildingHugoCopire1
 
CLIMATIC ZONES a4
CLIMATIC ZONES a4CLIMATIC ZONES a4
CLIMATIC ZONES a4HugoCopire1
 
CLIMATIC ZONES OF INDIA
CLIMATIC ZONES OF INDIACLIMATIC ZONES OF INDIA
CLIMATIC ZONES OF INDIAHugoCopire1
 

More from HugoCopire1 (10)

smart house.pdf
smart house.pdfsmart house.pdf
smart house.pdf
 
AR.UC JAIN.pdf
AR.UC JAIN.pdfAR.UC JAIN.pdf
AR.UC JAIN.pdf
 
Educational tour report
Educational tour reportEducational tour report
Educational tour report
 
Shape geo game
Shape geo gameShape geo game
Shape geo game
 
Creating excellent-primary-schools 2
Creating excellent-primary-schools 2Creating excellent-primary-schools 2
Creating excellent-primary-schools 2
 
Cube house
Cube houseCube house
Cube house
 
dispensary theory
dispensary theory dispensary theory
dispensary theory
 
Tormax united-kingdom i-motion-2401_specifications_barrier-free-building
Tormax united-kingdom i-motion-2401_specifications_barrier-free-buildingTormax united-kingdom i-motion-2401_specifications_barrier-free-building
Tormax united-kingdom i-motion-2401_specifications_barrier-free-building
 
CLIMATIC ZONES a4
CLIMATIC ZONES a4CLIMATIC ZONES a4
CLIMATIC ZONES a4
 
CLIMATIC ZONES OF INDIA
CLIMATIC ZONES OF INDIACLIMATIC ZONES OF INDIA
CLIMATIC ZONES OF INDIA
 

Recently uploaded

Cosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable BricksCosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable Bricksabhishekparmar618
 
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一F La
 
Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full NightCall Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full Nightssuser7cb4ff
 
How to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our SiteHow to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our Sitegalleryaagency
 
SCRIP Lua HTTP PROGRACMACION PLC WECON CA
SCRIP Lua HTTP PROGRACMACION PLC  WECON CASCRIP Lua HTTP PROGRACMACION PLC  WECON CA
SCRIP Lua HTTP PROGRACMACION PLC WECON CANestorGamez6
 
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一F dds
 
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
PORTAFOLIO   2024_  ANASTASIYA  KUDINOVAPORTAFOLIO   2024_  ANASTASIYA  KUDINOVA
PORTAFOLIO 2024_ ANASTASIYA KUDINOVAAnastasiya Kudinova
 
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024CristobalHeraud
 
Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,
Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,
Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,bhuyansuprit
 
Design Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William VickeryDesign Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William VickeryWilliamVickery6
 
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...babafaisel
 
Passbook project document_april_21__.pdf
Passbook project document_april_21__.pdfPassbook project document_april_21__.pdf
Passbook project document_april_21__.pdfvaibhavkanaujia
 
NATA 2024 SYLLABUS, full syllabus explained in detail
NATA 2024 SYLLABUS, full syllabus explained in detailNATA 2024 SYLLABUS, full syllabus explained in detail
NATA 2024 SYLLABUS, full syllabus explained in detailDesigntroIntroducing
 
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts ServiceCall Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Servicejennyeacort
 
3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdfSwaraliBorhade
 
Call Girls Satellite 7397865700 Ridhima Hire Me Full Night
Call Girls Satellite 7397865700 Ridhima Hire Me Full NightCall Girls Satellite 7397865700 Ridhima Hire Me Full Night
Call Girls Satellite 7397865700 Ridhima Hire Me Full Nightssuser7cb4ff
 
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130Suhani Kapoor
 
Introduction-to-Canva-and-Graphic-Design-Basics.pptx
Introduction-to-Canva-and-Graphic-Design-Basics.pptxIntroduction-to-Canva-and-Graphic-Design-Basics.pptx
Introduction-to-Canva-and-Graphic-Design-Basics.pptxnewslab143
 

Recently uploaded (20)

Cosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable BricksCosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable Bricks
 
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
 
Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full NightCall Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
 
How to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our SiteHow to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our Site
 
SCRIP Lua HTTP PROGRACMACION PLC WECON CA
SCRIP Lua HTTP PROGRACMACION PLC  WECON CASCRIP Lua HTTP PROGRACMACION PLC  WECON CA
SCRIP Lua HTTP PROGRACMACION PLC WECON CA
 
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
 
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
PORTAFOLIO   2024_  ANASTASIYA  KUDINOVAPORTAFOLIO   2024_  ANASTASIYA  KUDINOVA
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
 
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
 
Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,
Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,
Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,
 
Design Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William VickeryDesign Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William Vickery
 
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...
 
Passbook project document_april_21__.pdf
Passbook project document_april_21__.pdfPassbook project document_april_21__.pdf
Passbook project document_april_21__.pdf
 
NATA 2024 SYLLABUS, full syllabus explained in detail
NATA 2024 SYLLABUS, full syllabus explained in detailNATA 2024 SYLLABUS, full syllabus explained in detail
NATA 2024 SYLLABUS, full syllabus explained in detail
 
Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...
Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
 
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts ServiceCall Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
 
3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf
 
Call Girls Satellite 7397865700 Ridhima Hire Me Full Night
Call Girls Satellite 7397865700 Ridhima Hire Me Full NightCall Girls Satellite 7397865700 Ridhima Hire Me Full Night
Call Girls Satellite 7397865700 Ridhima Hire Me Full Night
 
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
 
Introduction-to-Canva-and-Graphic-Design-Basics.pptx
Introduction-to-Canva-and-Graphic-Design-Basics.pptxIntroduction-to-Canva-and-Graphic-Design-Basics.pptx
Introduction-to-Canva-and-Graphic-Design-Basics.pptx
 
young call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Service
young call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Service
young call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Service
 

2003v12 building tension

  • 1. Building Tension Martin Simpson and Mike King Although the Commonwealth Games were highly successful, the 41,000-seat stadium could never be vi- able as a track-and-field venue alone. The key to its ongoing success was its permanent role as a world-class soccer venue for Manchester City Football Club, with a temporary role mid-con- struction as the focal point of the Com- monwealth Games. The legacy it leaves is a landmark building of iconic architec- ture and a stimulus for the gentrification of an underdeveloped sector of the city. Immediately after the Common- wealth Games finished, work began in earnest to convert the track and field venue to a soccer stadium. This in- volved excavating the area of the ath- letic track to 6 m below ground level, building another level of terraces at the new, lower field level, and constructing the entire north stand. Soccer fields have different dimen- sions from track venues, and spectators have different perspectives in the sports’ respective stadiums. Modern soccer stadiums require spectators to be seated as close to the field as possible to maximize the atmosphere and provide the best possible views. A track is much larger than a soccer field, so if the Man- chester Stadium were to remain a duel- use venue, then soccer spectators would be seated far from the field. Per- manent, dual-purpose facilities have been adopted in a number of stadiums in Europe, but quality as a soccer sta- dium is compromised heavily. STRUCTURE The stadium is formed from several structural systems, each chosen to achieve the structural performance, architectural quality and cost effi- ciency. Concrete frame and precast ter- race units form the bowl structure, while the roof was formed from struc- tural steel rafters suspended from an innovative cable-net structure. This ar- ticle discusses the steel roof in more detail. The most visible features of the sta- dium are the 12 perimeter masts that rise as high as 70 m (230’) into the air. Each of these masts is supported at the base by either a concrete plant tower linked back to the bowl structure, or from a plinth at ground level. These masts support the cable net, which is formed from forestay cables to the roof and backstay cables to the ground. The forestay cables are grouped together in fans of either five or seven cables, and formed from a sin- gle, spiral-strand cable, which in turn supports an individual rafter. Modern Steel Construction • December 2003 © Dennis GilbertVIEW The City of Manchester Stadium in the United Kingdom was built for two purposes: to provide both the centerpiece track and field venue for the XVII Commonwealth Games, and a world-class stadium for the Manchester Football Club.
  • 2. December 2003 • Modern Steel Construction At each mast head, the tension forces of a forestay group are trans- ferred into compression in the masts and tension in a pair of backstays. Each of the backstays in the pair comprise four, grade 460 N/mm2 (67 ksi) “Macalloy” rods anchored to the ground with multi-strand ground an- chors pre-compressing concrete piles. The cigar-shaped masts take the re- solved compression force from the forestay and backstay cable tensions. They are fabricated from curved steel plate. The cigar profile is achieved by constructing each mast of a cylindrical central piece and two conical end pieces. The central sections range in di- ameter from 1500 mm (59”) for the four side masts and 1300 mm (51”) for the four end masts and four corner masts. All masts taper to 750 mm (30”) diame- ter at the lower ends and 650 mm (26”) diameter at the mast heads, with wall thicknesses between 20 mm and 30 mm (0.8” and 1.2”). ROOF UPLIFT As with all lightweight roofs, wind- induced uplift was one of the most sig- nificant design criteria. There are sev- eral solutions for maintaining tension in cables under uplift, including in- creasing the mass of the roof by addi- tional ballast or using opposing cables with tension and compression rings. Program and budget constraints forced the designers to explore an alternative solution. The stadium uses a method called “the grounded tension ring,” an inno- vative adaptation of the opposing cable solution. A “catenary cable” links all the forestays together. At each corner of the stadium this catenary cable is tied back to the ground by four “corner tie cables.” By pulling down at the four corners a tensile force can be induced into the entire cable net. The geometry of the cable net was defined in such a way that this pretension force was ex- actly equal to the force induced in the forestay cables under the worst-case wind-uplift condition. Therefore the cables do not go slack under any wind- Three of the permanent stands were constructed in a horseshoe arrangement along with their associated roofs for the stadium’s mid-con- struction role in the Commonwealth Games. Photo © Dennis GilbertVIEW The most visible features of the stadium are the 12 support masts (shown in blue, above).Tensile forces are maintained in the cable net under all loading conditions.
  • 3. uplift situation. The software used for the structural analysis of the roof, in- cluding the form-finding and non-lin- ear analysis (static P-delta and dynamic relaxation) was Oasys GSA. Oasys GSA is written by Arup for in- ternal use, but is also available exter- nally as commercial software. The geometry of the cable net used for the stadium is such that it can form an independent, statically determinate structure under pre-stress, with just the cables and the masts. As a result, it could be erected independently of the rafters. The use of the grounded ten- sion-ring cable net meant the roof could be installed in two distinct phases. For the Commonwealth Games, three of the permanent stands were constructed in a horseshoe arrangement along with their associ- ated roofs. These gave a homogeneous look to the stadium even though it was only partially complete. The final per- manent stand and the final portion of the roof were erected during phase two for the soccer conversion. ROOF GRAVITY LOADS The load path for downwards loads can be idealized as a standard triangu- lated system, with most loads apart from self weight applied directly to the cladding. There are two distinct types of cladding: ● Standing-seam aluminium cladding (Kalzip) to the majority of the roof. ● Transparent polycarbonate to the leading edge. This transparent zone increased the amount of natural light entering the bowl, which im- proved the environment in the sta- dium for players, spectators and television coverage, in addition to assisting grass growth of the natural field. The standing-seam cladding is sup- ported directly from structural liner trays that span approximately 4 m (13’) between wide-flange purlins. The purlins in turn span between the 76 rafters that run in a radial pattern. The rafters are fabricated steel box sections, 900 mm deep by 300 mm wide (35” by 12”), tapering to 450 mm deep (18”) at the leading end and rear end. The flanges of the box sections vary be- tween 12 mm and 55 mm (0.5” and 2.2”) and are optimized to provide greatest efficiency. The webs of the box section are constant at 6 mm (1 /4”) thick. Each rafter is supported at two points: ● At the rear of the stadium, each rafter is supported from the con- crete bowl by an integral “V strut” formed by two inclined struts of cir- cular HSS. ● Towards the leading edge, the rafter is effectively hung from the cable net by means of the “Forestay- strut.” The maximum rafter cantilever is 15 m (49’), and the back span of a rafter is 37 m (121’). This ratio was derived to equate the back-span and cantilever moments for the longest rafter under a variety of load cases, and to optimize the rafter design. The geometry of back span to cantilever for other rafters then was dictated by the geometry of the cable net. DESIGN OF ROOF PLATE The roof has a saddle profile due to the constraints of the bowl geometry. A roof with a curving profile can be sub- jected to arching in the roof plate. For the stadium, the occurrence of arching was not desired as it tries to short-cir- cuit the primary load paths through the cable net. This secondary load path was also a problem for thermal expan- sion and would have required a signif- icant increase in the size of the purlins to facilitate it. One solution would be to allow movement joints at the four cor- ners to coincide with the major thermal joints in the concrete bowl. However, waterproofing details at movement joints are notoriously difficult and ex- pensive, so the design team adopted a solution of regular but much smaller movement joints throughout the roof. These joints were incorporated every other bay through simple slotted holes in the purlins and shoulder bolts. The movements at each joint were in the order of 25 mm (1”), which the stan- dard cladding and flashing details could accommodate. The lateral stabil- ity of the rafter was provided by cross- bracing every other bay. Lateral-torsional stability and minor-axis buckling of the rafter was also a key factor in the design, espe- cially under wind-uplift conditions where effective restraint from the purlins could not be provided. The so- lution was to use U-frame stability, more commonly associated with bridge design. By using internal di- aphragms within the box-section rafters at the purlin positions, the bending resistance of the purlin could restrain the bottom flange of the rafter. DESIGN OF THE STADIUM ROOF UNDER SERVICE CONDITIONS The assessment of the roof in service was one of the most complex elements of the roof design. At the time of the as- sessment into behavior of the roof under service conditions, it was still the intention to use laminated glass as the cladding to the leading edge in place of polycarbonate cladding. The use of glass in such a roof imposed strict lim- its as to acceptable deformations. The behavior of the roof was assessed for the following criteria: Drainage Slope—The only gutter is located at the rear edge of the roof. All water should flow to the outside of the stadium to prevent ponding or water running off the leading edge. Each rafter and cladding panel was assessed to ensure that there was always a posi- tive fall of 1.5° under all service-load conditions. Visual Deformation—The visual performance of the rafters was main- tained at 1:100 for the cantilever and 1:200 for the back spans. However the overall total deflection was controlled by the deflection of the cable net, which was also limited to 1:100. Shear Strain and Warping—The shear strain was measured as the change in angle at the four corners of a cladding panel, and the warping was measured as the mean change in dis- tance out of plane at each of the four corners. These criteria were assessed for every cladding panel. Movement—The length of slots cut in the purlins to allow movement was assessed for various load cases and studies were carried out to determine the effect of the movement joints seiz- ing up. Though each of the rafters are sup- ported by a forestay, the forestays themselves are grouped together in ‘fans’ supported by single masts. De- flection in the rafters is controlled largely by rigid body rotation caused by extension of the backstays and rota- tion of the masts and rafters. If an indi- vidual rafter is loaded heavily then the subsequent rotation of the mast also will lower all the rafters attached to Modern Steel Construction • December 2003
  • 4. that mast. Therefore the forestay cable fans act as load-sharing devices with respect to relative displacement be- tween rafters. DESIGNING FOR ROBUSTNESS Blast protection is important for sta- diums, where roofs cover thousands of spectators. The robustness require- ments of this stadium were investi- gated thoroughly leading to the use of multiple cables for highly sensitive load paths. ● Each backstay is made from four el- ements, which in turn are attached to two discrete foundation plinths. ● Each catenary cable and corner tie is made from four cables. ● Non-linear studies were carried out to investigate the results of losses of elements ranging from forestay ca- bles to entire towers. Under extreme emergency-load cases, stability of the four cable ele- ments is maintained with any three re- maining cables from the group of four. In addition, the primary connections involving multiple cables, i.e. the mast heads, were designed taking into ac- count the eccentricities caused by los- ing one or more forestay or backstay cables. The conclusion was that there is a sufficient degree of redundancy in the load paths, which will avoid dis- proportionate collapse under most con- ceivable extreme-loading conditions. Fire protection is provided inher- ently to the bowl, due to the use of re- inforced concrete. The roof structure is not fire-protected, as there is negligible combustible material in the terrace area. Most importantly, the roof is not required for the stability of the stadium bowl. ROOF CONSTRUCTION SEQUENCE Arup’s original erection proposal took advantage of the mast and cable- net structure’s independence from the roof steel structure by erecting and pre- tensioning the cable-net prior to the lifting and attachment of rafter and purlin braced pairs. Due to program constraints, it was decided to bring for- ward the erection of roof plane steel- work so that it could be erected in parallel with the lifting of masts and as- sembly and stressing of the cable-net. The end result was a framework of temporary steel props erected to sup- port the leading edge of the rafters. The revised erection scheme created a platform at roof level on which the cable-net could be laid out prior to final assembly and stressing. Once erection of the masts and assembly of the cable- net was complete, the cable-net was made taut by pulling down on the backstays and connecting them to their pinned bases. The final tension was ac- complished by jacking the four corner ties at the top of the corner-tie frames. Upon completion of the stressing phase, individual rafters were lifted off their props and connected to the cable- net, after which the temporary props were removed. During the conversion of the sta- dium for soccer use, the roof of the north stand was completed as origi- nally intended. The cable net was in place from phase one and each roof panel was lifted into position and sup- ported from the rear of the bowl and hung from the cable net. This phase of the works was carried out successfully to a very tight schedule. CONCLUSION The successful design of the cable- stayed roof for the City of Manchester Stadium can largely be attributed to the teamwork between the structural engi- neers, architects and steelwork fabrica- tors. The roof is a ground-breaking structure, incorporating many innova- tive features that are sure to be re- peated on future stadium projects around the world, especially the first use of the grounded tension ring phi- losophy. REFERENCE Simpson, M. “The Analysis and Design of the City of Manchester Stadium.” Proceedings of the Fifth International Conference on Space Structures, Sur- rey, 2003, pp 827-836. OWNER Manchester City Council OPERATOR Manchester City Football Club ARCHITECT AND STRUCTURAL ENGINEERS Arup Associates, London CONSTRUCTION MANAGER Laing O’Rourke, Kent, UK ENGINEERING SOFTWARE Oasys GSA The Manchester Stadium in its final configuration as a soccer venue. Photo courtesy Lee Jordan. December 2003 • Modern Steel Construction