SlideShare a Scribd company logo
1 of 1
Download to read offline
Property of ClearCost Consulting US
IT Project Life Cycle Process Flow Chart
Preliminary
Evaluation
Initiation & Risk
Assessment
Requirements Project Build
QA &
Testing
Are
Any Changes to
Design Plan
Required?
Documentation
& Training
Implementation IntegrationDesign
Discovery Design Build Run
Submit
Preliminary Plan
to Manager
Preliminary Project
Plan & Include
Project Benefits
Complete
Project Summary
Is project
OVER 50,000
in local
currency?
Complete the
Investment
Request Template
Complete the
Project Financials
Template
Have Meeting with
Management
for the Go-Ahead
No
Determine the
Approval Path
for required
Management
Is Project
Evaluation
Approved?
No
Alternative
Plan
or
File Project
Yes
Put together
Project Team (X)
Requirements &
Recommendations
Put together
Project
Management Plan
Put together
Project Team (“X”)
Requirements &
Recommendations
Put together
Project
Management Plan
Put Together
Task Plan
For Projects
UNDER 50,000,
use the Project
Summary
Template for
Approval
Signatures
Scan Original
Signatures
(Signature
Page Only)
Approval
For Projects
OVER 50,000, use
the Investment
Request Template
for Approval
Signatures
Prepare All
Documents for the
Approval Process
Next
Phase
Evaluation
Review
Regional
Signatures
Global Mgmt.
Signatures
Regional
CEO / CFO
Signature
Global
CEO / CFO
Signature
Board of
Directors
Approvals
Required
Required
Required
Next
Phase
> 1 Million
X
X
X
X
X
Board of
Directors
X
Global
CEO
XX
Regional
CEO
XXX
Global IT
Management
XXXX
Regional
Management
> 500,000> 50,000< 50,000< 25,000
Approval Signature Requirements
Decommission
Develop a
Microsoft
Project Plan
Create a
Requirements Doc
with Success
Criteria
Define &
Document Test
Lab Requirements
(if Required)
Acquire
Approvals for
Requirements
Document
Were
Requirements
Approved?
No
Yes
Create a Technical
Approach Doc
(if Required)
Acquire
Approval for
Technical
Approach
Was Tech
Approach
Approved?
No
Document All
Inter-project
Dependencies
Yes
Acquire
Approval for
Lab
Requirements
Were
Requirements
Approved?
No
Required
Not
Required
Not
Required
Yes
Yes
Not
Required
Provide
Business Case
Documents
to Routing
Administrator
Create a Solution
Design Document
(if Required)
Acquire
Approval for
Solution
Design
No
Yes
Were
Requirements
Approved?
Not
Required
Document Any
Issues for
Inter-project
Dependencies
Schedule a
Meeting Regarding
Inter-project
Dependencies doc
Establish a Game
Plan for All
Inter-project
Dependencies
Develop
a Detailed
QA / Test Plan
Acquire
Approval for
QA /
Test Plan
Was
QA / Test Plan
Approved?
No
Not
Required
Next
Phase
Meeting w/ Project
Team to Review
& Discuss
Project Build Doc‟s
Make Necessary
Revisions to
Project Build Plan
or Design
Follow the Process
According to the
Project Build
& Design Plan
Is a Project
Team or Status
Meeting Beneficial
at this Time?
Yes
No
Yes
Not
Required
Is the
Project Build
Completed?
Meeting w/ Project
Team to Review
Project Status &
Implementation
Progress
No
Meeting w/ Project
Team to Approve
QA / Testing
Strategy
Is the
Project Build
Approved for
Testing?
Meeting w/ Project
Team to Complete
Testing & Start
Documentation
Yes
No
Meeting w/ Pilot
Group to Discuss
QA & Testing
Procedures
Yes
Follow the Process
According to the
QA & Testing Plan
Define Testing
Group and
Requirements for
a Test Success
Move
Forward Without
Additional
Testing?
Are the
QA / Test Results
Satisfactory?
No
Yes
Move
Forward
with the Project
Testing?
Make Necessary
Improvements or
Changes to
Testing Plan
Yes
No
Yes
Prepare Team for
Implementation
Phase
Revised 02-10-05
Scan Original
Signatures Master
(Signature Page
Only)
Supplemental
Regional
Signatures
Global Mgmt.
Signatures
Regional
CEO / CFO
Signature
Global CEO
Signature
Board of
Directors
Approvals
Review All
Documents for
Original
Signatures
Required
Required
Required
Not
Required
Provide Revised
Business Case
Documents
to Routing
Administrator
Did the
Cost of the Project
Increase?
Next
Phase
No Cost
Increase
Create an
Addendum to
the Inv. Request
w/Financials
Yes
Next
Phase
Is a
End User Manual
Required?
Is a
Process Flowchart
Document
Required?
Yes
Make Necessary
Revisions to
Project Build
Requirements
Next
Phase
Decommission
Completion
Y Z
Y Z
I M Y Z
Y Z
Y Z
Y Z
Y Z
Y Z
Y Z
Meeting w/
Project Team to
Review & Discuss
Implementation
Strategy
Not
Required
Required
Are any
Change Requests
Required?
Are any
Status Reports
Required?
B Y Z
Y Z
Y Z
Y Z
Y Z
Y Z
Y Z
A B C D F I O
M R S X Y Z
Y Z
F I M Y Z
Y Z
Y Z
Y Z
Q Y Z
B F I M
P Q R
B F I
M Q
E M Q
E M Q
G Q
Review
Risk & ROI
Cost & Benefits
with Management
Does the
Preliminary Plan
Justify Moving
Ahead?
Yes
No
Document
Risk & ROI
Cost & Benefits
Summary
Review
All Project
Documentation
with Team
Members
Yes
Review Final
Project Documents
& Financials
with Management
Team
Q Y Z
Y Z
Y Z
Y Z
X Y Z
A C D I
O X Y Z
A B C D F I M
O S T X Y Z
Y Z
B I M D O
T X Y Z
B I M D O
S T X Y Z
B D F I M O
S T X Y Z
B D I M O
S T X Y Z
P X Y Z
B D I M O
T X Y Z
A C D I O
X Y Z
B D I M O
S T X Y Z
D O T
X Y Z
X Y Z
X Y ZI X Y Z
O D T
X Y Z
X Y Z
T X Y Z
X Y Z
B F I M
R X Y Z
B X Y Z
Q X Y Z
B F I
M P Q
B F I
M Q
E M R
E M Q
G Q
Y Z
Y Z
Y Z
A B C D F I
S O X Y Z
D O T X Z
D O
X Y Z
X Y Z
D O
X Y Z
A C D F I
O R S X Y Z
B I M D T
X Y Z
D O T
X Y Z
A D O S
T U X Y Z
D O T U X
D I O T X
D F I O
T X Y Z
T X Y Z
X Y Z
X Y Z
A B C D I
O S X Y Z
I O P
X Y Z
X Y Z
D C O T
X Y Z
Level
1
Level
2
Level
3
Level
4
Level
5
Level
6
Level
7
Level
8
Level
9
Level
10
Level
11
Level
12
Level
13
Level
14
Level
15
Level
16
Level
17
Level
18
Level
15
Level
10
Level
9
Level
8
Level
7
Level
6
Level
5
Level
4
Level
3
Level
2
Level
1
Individual or Group Dependencies
A Architecture Team P Purchasing Group
B Business Owner Q Routing Administrator
C Consulting Team R Risk Management
D Development Team S Security Team
E Executive Management (Non - IT) T Testing Team
F Finance Group (IT) U Pilot Testing Group
G Board of Directors V Training Group
I IT Department Team W Project Architect
L Legal Department X Project Team
M Management (Business) Y Project Principle
O Operations Group Z Project Manager
Required
Required
Is the
Implementation
Process
Complete?
Not
Required
Follow the Process
According to the
Implementation
Plan
Implementation
Evaluation
(Every 2 to 4
Weeks)
Not
Required
No
Yes
Meeting w/
Project Team to
Review & Discuss
Integration
Strategy
Meeting w/
Project Team to
Review & Discuss
Project Completion
Follow Process
According to the
Integration
Strategy
Are any
Change Requests
Required?
Status Reports Due:
1. Schedules
2. Transition Plan
3. Project Mgmt. Plan
4. Implement Plan
5. In-Pro Dependencies
Are any
Status Reports
Required?
Required
Required
Is the
Transition Process
Complete?
Not
Required
Transition
Evaluation
(Every 1 to 4
Weeks)
Change Requests:
1. Schedules
2. Transition Plan
3. Project Mgmt. Plan
4. Implement Plan
5. In-Pro Dependencies
Not
Required
Sign-Off on the
Procedures for
Project Transition
Yes
Are any
User Acceptance
Sign-Off‟s
Required?
Reports Sign-Off:
1. Time & Materials
2. Total Cost Report
3. Business Case
4. Resources Used
5. Project Design Doc‟s
Are any
Report Sign-Off‟s
Required?
Required
Required
Not
Required
User Acceptance
Sign-Off
1. Administrators
2. Support Team
3. Power Users
4. Remote Locations
5. Management Team
6. Security Team Not
Required
Was
the Project
Approved by the
Executive
Team?
Yes
A1
A C D F I O
S T X Y Z
D I O
X Y Z
D I O
X Y Z
D I O
X Y Z
D I O
X Y Z
B D I O
X Y Z
Was
the Project
Approved by the
Executive
Team?
A1 No
Yes
D I O
X Y Z
A B C D F I
M O S U X Y Z
D I O
X Y Z
D X Y Z
B D I O
X Y Z
Not
Required
Not
Required
Level
11
Status Reports Due:
1. Schedules
2. Solution Plan
3. Cost Controls
4. Project Mgmt. Plan
5. Implement Plan
6. In-Pro Dependencies
7. Risk Mgmt. Plan
B D I M
O X Y Z
D X Y Z
5% 10% 15% 20% 30% 35% 40% 50% 60% 70% 80% 90% 100%
Review All
Documents for
Original
Signatures
Legal Review
& Contract
Execution
Any
Contracts or
Agreements
Required for
Legal?
Is there
New HW / SW
Required?
No
B1
Did All
Contracts &
Agreements
Receive
Approval?
Required
Yes
No
F I R Y Z
F L I
M Y Z
Start the
Legal Review
& Contract
Procedures
B F I M
L Y Z
No
Project Success
Meeting with
Discussions &
Lessons Learned
Document
Lessons Learned
and Send Copies
to Team
Level
14
Level
13
Level
12
A B C D F I
M O S X Y Z
X Y Z
X Y Z
D X Y Z
D X Y Z
Meeting w/
Project Team to
Discuss Parallel
Processing &
Decommission
Follow the
Parallel Process
Decommission
According to the
Transition Plan
Status Reports Due:
1. Schedules
2. Transition Plan
3. In-Pro Dependencies
Are any
Status Reports
Required?
Required
Is the
Decommission
Process
Complete?
Not
Required
Decommission
Evaluation
(Every 1 to 4
Weeks)
D I M O
X Y Z
D I M O
X Y Z
X Y Z
D I M O
X Y Z
D X Y Z
No
Any Legacy
Applications or
Parallel Procedures
Required?
Yes
Not
Required
Yes
Process
Complete
IFS
File All Documents
in Project Folder
IFS
File All Project
Documents
IFS
Enter Project into
IT PM Register
IFS
File Scanned
Signatures Copy
IFS
Update IT PM
Register for
Project Approval
IFS
File All Documents
in Project Folder
IFS
Update New
Changes in
Project Folder
IFS
Update IT PM
Register to Include
Supplemental
Approval
IFS
Update IT PM
Register & Project
Folder
IFS
Update IT PM
Register
Validate the
User Manuals
& Technical
Documentation
IFS
File All User
Manuals & Tech
Documentation
IFS
File Acceptance
Sign-Off
Documents
IFS
Update All Final
Documents &
Lessons Learned
IFS
Update the
Project Folder
110%
C1
A2
B2
C2
No
Not
Required
IFS
File Signatures
Scanned Copy
IFS
Update the
IT PM Register
Is the
QA & Testing Plan
Ready for a Pilot
Group?
IFS
Include All Testing
Results in the
Project Folder
IFS
Document Status
Reports & File
IFS
Document Change
Requests & File
D X Y Z
IFS
Document Change
Requests & File
IFS
Update the
IT PM Register
IFS
Locate Required
Business Case
Documents
IFS
Locate Required
Business Case
Documents
IFS
Create a Project
Folder
Develop
Implementation
Plan w/ Design
Requirements
Work with
Procurement
Dept to Price
Required
HW / SW
Complete the
HW and / or SW
Requisition Form
IFS
File All Documents
in Project Folder
Q Y Z
Review &
Update the
QA / Testing
Process
E1
E2
D O T X Z
D O T X Z
A B C D I
O S X Y Z
A B C D F I
M O S X Y Z
B D I O
X Y Z
IFS
Document Status
Reports & File
D X Y Z
D I O
X Y Z
D I O
X Y Z
A B C D F I
M O F X Y Z
IFS
File Reports
Sign-Off
Documents
A B C D F I
M O U X Y Z
Sign-Off
Procedures for
Project Completion
A B C D F I
M O F X Y Z
Meeting w/ Project
Team to
Determine
the Required
Documents
A B C D F I M
O R S X Y Z
I
Complete
Project Summary
I
II
III
IV
IV
V
V
VI
VII
VIII
IX
X
XI
XIII
XIV
XV
XVI
XVII
Start Technical
Documentation
(Version,
Support, etc…)
Start the
End User Manual
Documentation
(„How To‟)
Process or
Engineering Flow
(Step-by-step
Procedures)
Business Case Documents
Document Description
Preliminary
Project Plan
Legal Review
Contract Proced.
Project
Summary
Investment
Request
Team
Requirements
This is a basic document that is the starting point or feasibility
study that will determine if the project should be initiated.
A document that contains the procedures and sigh-off by an
officer of the company for software / hardware licenses or legal
contracts associated with the project.
Mandatory for all projects. High level document required for the
approval process and used as a project cover page.
Required for project over 50,000. This primary document includes
the project details that are important during the approval process.
Document of all team members and the duties, authorities and
responsibilities for each.
Project
Management Plan
Using Microsoft Project, lay out the important events on a Gant
chart for documenting the tasks for the project.
Required for project over 50,000. This documents includes the
project financial & ROI details that are important during the
approval process.
Project
Financials
A
#
B
I
II
III
IV
V
Acquire
Approval for
Migration
Strategy
Was
Migration
Strategy
Approved?
B C D I M
O X Y Z
Yes
A B C D I
M O X Y Z
A B C D I
M O X Y Z
B I M D T
X Y Z
IFS
Revise All Initial
Business Case &
Project Budgets
XII
XV
XIII
XII
D I T O
X Y Z
Set up the
Development,
Test and
Production
Environments
Approval
Process
Supplemental
Approval
Process
Order New
HW / SW for
the Solution
(If Required)
Configure &
Implement
HW / SW the
Solution
Turn Over
HW / SW to the
Project Team
I O P
A I O
A I O
Required
Not
Required
T X Y Z
Testing
Evaluation
(Every 1 to 2
Weeks)
Order New
HW / SW for
Solution
(If Required)
Configure &
Implement
HW / SW the
Solution
Turn Over
HW / SW to the
Project Team
A I O
A I O
Start to Create the
Disaster Recovery
Plan
Is a Disaster
Recovery Plan
Required?
Required
Not
Required
Notify Team when
QA & Testing is
Completed
Are All
Legal Documents
& Contracts Still
Valid?
D2
No
D1 Yes
D I O
X Y Z
A C D I
O X Y Z
Start to Create an
Implementation
Roadmap
Meeting with
Training Groups
to Discuss
Training Process
Follow the Process
According to the
Training Plan
Are the
Training Results
Satisfactory?
B C D I M
O V X Y Z
Training
Evaluation
(Every 1 to 2
Weeks)
B C D I M
O V X Y Z
B C D I M
O V X Y Z
No
Yes
Complete the
End User Manual
IFS
Place a Users
Manual in
Project Folder
Document Benefit
Returns Predicted
in the Business
Case Documents
Key Financial Indicators:
1. Project Cost
2. Net Present Value
3. IRR / ROI
4. Payback Period
5. Resources Used
6. Value & Risk
IFS
Update
Documents in
Project Folder
D X Y Z
A1
B1
C1
Review with
Management &
Determine if Any
Project Changes
will Help
Meet with Project
Team to Make
Changes or
Improvements to
Project
Cut Costs to
Project Spending
to Improve RIO &
KPI‟s
Update All
Documentation to
Submit for
Approval
F I B
X Y Z
D O P
R X Y Z
F B
X Y Z
X Y Z
Review with
Management &
Determine if Any
Contract Changes
will Help
Meet with Project
Team to Make
Changes or
Improvements to
Contracts
Cut Costs to
Contracts to
Improve RIO &
KPI‟s
Update All
Contracts to
Submit for
Approval
B F I R
X Y Z
F X Y Z
B F O R
X Y Z
F X Y Z
Review with
Management the
Reasons for
Testing Failure
Meet with Project
Team to Discuss
Proposed
Changes to
Project Build
Review with
Management for
Approval of New
Project Build
Specifications
Update All Design
& Implementation
Documentation
B F I R
X Y Z
D O P R
X Y Z
B F I
X Y Z
X Y Z
X Y Z
X Y Z
X Y Z
A2
B2
C2
Off Chart Modification & Sub-Processes
IFS
Save Revised
Documents
IFS
Save Revised
Documents
IFS
Save Revised
Documents
D1
Review with
Management
Reasons for
Contract Changes
Meet with Project
Team to Discuss
Proposed
Changes to
Contracts
Review with
Management for
Approval of New
Contract Changes
Update All
Contract
Documentation
B F I R
X Y Z
D O P R
X Y Z
B F I
X Y Z
X Y Z X Y Z
D2
IFS
Save Revised
Documents
E1
Review with
Management
Reasons for
Project Issues
Meet with Project
Team to Discuss
Proposed
Changes to
Build Design
Review with
Management for
Approval of New
Build Design
Update All Project
Build
Documentation
A B C D F I
M O S X Y Z
D I X Y Z X Y Z
E2
IFS
Save Revised
Documents
A C D I
O S X Y Z
A B C D F I
M O S X Y Z
Level
17
Level
18
Level
16
Create a Training
Plan & Define the
Training Groups
Meet with
Operations Group
to Formulate
Design Plan
Change Requests:
1. Schedules
2. Solution Plan
3. Cost Controls
4. Project Mgmt. Plan
5. Implement Plan
6. In-Pro Dependencies
No
Determine &
Document the
Dev, Test and
Production
Requirements
Develop
a Migration
Strategy
XII
> 1 Million
X
X
X
X
X
Task
Plan
Optional Optional X X X
XXOptionalOptional
Team
Requirements
XXXOptional
Project
Mgmt. Plan
XXOptionalOptional
Project
Financials
XXOptionalOptional
Investment
Request
XXXX
Project
Summary
> 500,000> 50,000< 50,000< 25,000
Business Case Requirements
Perform a Security
Architecture
Review / Audit
if Required
Required
A C I O S
X Y Z
Acquire
Approvals for
Risk Mgmt
Plan
A B C D F I M
O S T X Y Z
Update the MS
Project Plan to
Reflect Any
Requirements
Changes
Level
19
Yes
No
Meeting w/ Project
Team to Approve
Build Design
A C D F I O
S T X Y Z
Yes
Y Z
Y Z
Yes
Project Design Documents
Document Description
Microsoft
Project Plan
Requirements
Document
Lab
Requirements
A detailed plan that shows the technical approach from a systems
architecture and application view point.
Using Microsoft Project, lay out the important events on a Gant
chart for documenting the tasks for the project.
A detailed document that lists the Project Requirements with a
scope to include a set of deliverables and project success criteria.
A detailed document that lists all the lab Requirements for the
Operations Group and Security Team.
A detailed document that provides the solution architecture,
system design, application dependencies and s.
A reference document of all the current projects & applications
that are associated to the proposed project ...
A formal detailed document that provides the implementation
schedules, personnel responsibilities, deliverables, milestones,
system design and simulations.
Form required for all software or hardware purchases related to
the project.
Technical
Approach
Inter-Project
Dependencies
Solution
Design
Detailed
Implementation
SW / HW
Requisition
Detailed
QA / Test Plan
A detailed test plan includes; quality assumptions, production
requirements, BAU acceptance, timelines, and testing success
scorecards.
Weekly, Bi-Monthly, or Monthly reports related to the status of a
project. May include the progress related to the original Pro.
Mgmt. Plan
Status
Reports
#
VII
VIII
IX
X
XI
XIII
XIV
XV
XVI
Project Folder
in IFS
All projects require a project folder in IFS where all project related
documents are kept.
IT PM
Register
Project spreadsheet for recording all project financial information
found in IFS under IT PM / Register.
A detailed document that provides a Migration Strategy for the
Dev, Testing and Production environments.
Migration
Strategy
XII
Risk Management
Plan
The objective of the risk management plan is to minimize any
unexpected but not unforseen events migrating to become project
issues and having a residual impact on the project.
XVII
Create a Risk
Management Plan
XVII
Not
Required
A C I O
S X Y Z
Review Risk
Management Plan
and Security
Issues
Acquire
Approval for
Risk
Management
Plan
R S X Y Z
Level
20
Index
Requires Signature / Approval Multiple Files or Documents
Review or Approval Required
Process Step
Document Procedure
Direction to the Next Step
“Yes” or “No” Direction
Dependencies Code (see chart)
Off Chart Modification
Sub-Processes
Process Level within a Section
Decision Step Required
Process Group or Predefined
Phase Kick Off Meetings Enter Data in the IFS Directory
NO YES
T X Y Z
A1
Level
16
IFS
To understand how to properly use this template, please refer to the IT Project Life Cycle Process Manual
The manual will help explain how to effectively utilize this template tool when running or managing a
medium, large or enterprise IT projects.
Does
the Project Require
Contracts or Legal
Reviews?
Complete
Legal Review &
Contract
Procedures Doc
Required
Y Z
Y Z
Not
Required
A
Complete the
Application /
Infrastructure
Operations
Handover Doc.
B
Task Plan
A document to list the chronological events that are broken into
individual tasks that ties to the implementation plan.
Supplemental
Addendum
All documents that are additions to the original Investment request
or Project Financial worksheets for receiving second approval.
VI
XVII

More Related Content

What's hot

The Quarterbacks Dilemma
The Quarterbacks Dilemma The Quarterbacks Dilemma
The Quarterbacks Dilemma Allan Cytryn
 
Project management basics
Project management basicsProject management basics
Project management basicsPlanning School
 
Sami Zahran Quality Gates
Sami Zahran Quality GatesSami Zahran Quality Gates
Sami Zahran Quality GatesDr. Sami Zahran
 
Managing Projects with Intelligence
Managing Projects with IntelligenceManaging Projects with Intelligence
Managing Projects with IntelligencePaul Gerrard
 
Project Management Presentation
Project Management PresentationProject Management Presentation
Project Management PresentationAlejandra Vicuna
 
5 pasos exitosos para menejo proyectos
5 pasos exitosos para menejo proyectos5 pasos exitosos para menejo proyectos
5 pasos exitosos para menejo proyectosduniat
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycleSAJID ALI RUK
 
Project Initiation and Scoping
Project Initiation and ScopingProject Initiation and Scoping
Project Initiation and ScopingCiprian Rusen
 
A Short Workshop on Project Management
A Short Workshop on Project ManagementA Short Workshop on Project Management
A Short Workshop on Project ManagementNicole Fronda
 
Project risk management
Project risk managementProject risk management
Project risk managementBarnatuCoffee
 
Presentation Project managment
Presentation Project managmentPresentation Project managment
Presentation Project managmentMalan Bothma
 
Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1Mena M. Eissa
 
Project management Critical Success Factor
Project management Critical Success FactorProject management Critical Success Factor
Project management Critical Success FactorVenture Advisors
 
Project Management Tools
Project Management ToolsProject Management Tools
Project Management Toolsostephens
 
Project audit and closure
Project audit and closureProject audit and closure
Project audit and closureVelita Furtado
 
Introduce Project Management
Introduce Project ManagementIntroduce Project Management
Introduce Project Managementguest90bddb
 

What's hot (20)

GAFM Academy - THE ESSENTIALS OF PLANNING AND SCOPING A PROJECT
GAFM Academy - THE ESSENTIALS OF PLANNING AND SCOPING A PROJECTGAFM Academy - THE ESSENTIALS OF PLANNING AND SCOPING A PROJECT
GAFM Academy - THE ESSENTIALS OF PLANNING AND SCOPING A PROJECT
 
Section 1: introduction
Section 1: introductionSection 1: introduction
Section 1: introduction
 
The Quarterbacks Dilemma
The Quarterbacks Dilemma The Quarterbacks Dilemma
The Quarterbacks Dilemma
 
Project management basics
Project management basicsProject management basics
Project management basics
 
Sami Zahran Quality Gates
Sami Zahran Quality GatesSami Zahran Quality Gates
Sami Zahran Quality Gates
 
Managing Projects with Intelligence
Managing Projects with IntelligenceManaging Projects with Intelligence
Managing Projects with Intelligence
 
Self test engine PSP-PMI-SP
Self test engine PSP-PMI-SPSelf test engine PSP-PMI-SP
Self test engine PSP-PMI-SP
 
Project Management Presentation
Project Management PresentationProject Management Presentation
Project Management Presentation
 
5 pasos exitosos para menejo proyectos
5 pasos exitosos para menejo proyectos5 pasos exitosos para menejo proyectos
5 pasos exitosos para menejo proyectos
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
 
Project Initiation and Scoping
Project Initiation and ScopingProject Initiation and Scoping
Project Initiation and Scoping
 
A Short Workshop on Project Management
A Short Workshop on Project ManagementA Short Workshop on Project Management
A Short Workshop on Project Management
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Presentation Project managment
Presentation Project managmentPresentation Project managment
Presentation Project managment
 
Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1
 
Project management Critical Success Factor
Project management Critical Success FactorProject management Critical Success Factor
Project management Critical Success Factor
 
Project Management Tools
Project Management ToolsProject Management Tools
Project Management Tools
 
Project audit and closure
Project audit and closureProject audit and closure
Project audit and closure
 
Vol. VII Quality Gates
Vol. VII Quality GatesVol. VII Quality Gates
Vol. VII Quality Gates
 
Introduce Project Management
Introduce Project ManagementIntroduce Project Management
Introduce Project Management
 

Similar to IT Project Life Cycle Process Flow

LavaCon Best Practices For Multiple Technical Projects V1R2
LavaCon Best Practices For Multiple Technical Projects V1R2LavaCon Best Practices For Multiple Technical Projects V1R2
LavaCon Best Practices For Multiple Technical Projects V1R2Jose Figueroa
 
IC-RACI-Model-11448_PowerPoint.pptx
IC-RACI-Model-11448_PowerPoint.pptxIC-RACI-Model-11448_PowerPoint.pptx
IC-RACI-Model-11448_PowerPoint.pptxDoraDora58
 
Integration ManagementChapter 4Overall ViewWhat is Int
Integration ManagementChapter 4Overall ViewWhat is IntIntegration ManagementChapter 4Overall ViewWhat is Int
Integration ManagementChapter 4Overall ViewWhat is IntMerrileeDelvalle969
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its PhasesGaurav Sukhija
 
Project management - Stakeholders and project success - Overcoming project f...
Project management - Stakeholders and project success  - Overcoming project f...Project management - Stakeholders and project success  - Overcoming project f...
Project management - Stakeholders and project success - Overcoming project f...ILX Group
 
General Manager Or Plant manager prescreening questionnaire
General Manager Or Plant manager prescreening questionnaireGeneral Manager Or Plant manager prescreening questionnaire
General Manager Or Plant manager prescreening questionnaireJames Baker, SPHR Retired, MAS
 
change management with agility
change management with agilitychange management with agility
change management with agilityitSMF Belgium
 
timesaverpptjk-140526132859-phpapp02.pptx
timesaverpptjk-140526132859-phpapp02.pptxtimesaverpptjk-140526132859-phpapp02.pptx
timesaverpptjk-140526132859-phpapp02.pptxAmeya Patekar
 
Agile Team Performance Appraisal
Agile Team Performance AppraisalAgile Team Performance Appraisal
Agile Team Performance AppraisalAshutosh Rai
 
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...Chandrasen Sharma
 
Agile adoption julen c. mohanty
Agile adoption   julen c. mohantyAgile adoption   julen c. mohanty
Agile adoption julen c. mohantyJulen Mohanty
 
Best Practices
Best PracticesBest Practices
Best Practicesjspet5
 
D09 Recognize and Overcome Resistance
D09 Recognize and Overcome ResistanceD09 Recognize and Overcome Resistance
D09 Recognize and Overcome ResistanceLeanleaders.org
 
D09 Recognize and Overcome Resistance
D09 Recognize and Overcome ResistanceD09 Recognize and Overcome Resistance
D09 Recognize and Overcome ResistanceLeanleaders.org
 
How to become a Successful Project Manager
How to become a Successful Project ManagerHow to become a Successful Project Manager
How to become a Successful Project ManagerSaviNaitame1
 
Odoo Implementation Methodology
Odoo Implementation MethodologyOdoo Implementation Methodology
Odoo Implementation MethodologyOdoo
 
Global slit lamps market2020 industry research report gives adva
Global slit lamps market2020 industry research report gives advaGlobal slit lamps market2020 industry research report gives adva
Global slit lamps market2020 industry research report gives advassuser47f0be
 

Similar to IT Project Life Cycle Process Flow (20)

LavaCon Best Practices For Multiple Technical Projects V1R2
LavaCon Best Practices For Multiple Technical Projects V1R2LavaCon Best Practices For Multiple Technical Projects V1R2
LavaCon Best Practices For Multiple Technical Projects V1R2
 
IC-RACI-Model-11448_PowerPoint.pptx
IC-RACI-Model-11448_PowerPoint.pptxIC-RACI-Model-11448_PowerPoint.pptx
IC-RACI-Model-11448_PowerPoint.pptx
 
Integration ManagementChapter 4Overall ViewWhat is Int
Integration ManagementChapter 4Overall ViewWhat is IntIntegration ManagementChapter 4Overall ViewWhat is Int
Integration ManagementChapter 4Overall ViewWhat is Int
 
Project Management Quick Connects
Project Management Quick ConnectsProject Management Quick Connects
Project Management Quick Connects
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its Phases
 
Project management - Stakeholders and project success - Overcoming project f...
Project management - Stakeholders and project success  - Overcoming project f...Project management - Stakeholders and project success  - Overcoming project f...
Project management - Stakeholders and project success - Overcoming project f...
 
General Manager Or Plant manager prescreening questionnaire
General Manager Or Plant manager prescreening questionnaireGeneral Manager Or Plant manager prescreening questionnaire
General Manager Or Plant manager prescreening questionnaire
 
change management with agility
change management with agilitychange management with agility
change management with agility
 
Pro Membership
Pro MembershipPro Membership
Pro Membership
 
PMP Exam Q & A
PMP Exam Q & APMP Exam Q & A
PMP Exam Q & A
 
timesaverpptjk-140526132859-phpapp02.pptx
timesaverpptjk-140526132859-phpapp02.pptxtimesaverpptjk-140526132859-phpapp02.pptx
timesaverpptjk-140526132859-phpapp02.pptx
 
Agile Team Performance Appraisal
Agile Team Performance AppraisalAgile Team Performance Appraisal
Agile Team Performance Appraisal
 
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
 
Agile adoption julen c. mohanty
Agile adoption   julen c. mohantyAgile adoption   julen c. mohanty
Agile adoption julen c. mohanty
 
Best Practices
Best PracticesBest Practices
Best Practices
 
D09 Recognize and Overcome Resistance
D09 Recognize and Overcome ResistanceD09 Recognize and Overcome Resistance
D09 Recognize and Overcome Resistance
 
D09 Recognize and Overcome Resistance
D09 Recognize and Overcome ResistanceD09 Recognize and Overcome Resistance
D09 Recognize and Overcome Resistance
 
How to become a Successful Project Manager
How to become a Successful Project ManagerHow to become a Successful Project Manager
How to become a Successful Project Manager
 
Odoo Implementation Methodology
Odoo Implementation MethodologyOdoo Implementation Methodology
Odoo Implementation Methodology
 
Global slit lamps market2020 industry research report gives adva
Global slit lamps market2020 industry research report gives advaGlobal slit lamps market2020 industry research report gives adva
Global slit lamps market2020 industry research report gives adva
 

More from Mark S. Mahre

Technology Alignment Framework
Technology Alignment FrameworkTechnology Alignment Framework
Technology Alignment FrameworkMark S. Mahre
 
Technology Assessment Framework
Technology Assessment FrameworkTechnology Assessment Framework
Technology Assessment FrameworkMark S. Mahre
 
Aprio Consulting Services - Cloud, ITFM, Compliance, Innovation, Technology
Aprio Consulting Services - Cloud, ITFM, Compliance, Innovation, TechnologyAprio Consulting Services - Cloud, ITFM, Compliance, Innovation, Technology
Aprio Consulting Services - Cloud, ITFM, Compliance, Innovation, TechnologyMark S. Mahre
 
Governance - Project Management Office Professional Services
Governance - Project Management Office Professional ServicesGovernance - Project Management Office Professional Services
Governance - Project Management Office Professional ServicesMark S. Mahre
 
SOC-2 Compliance Status Report sample v10.0
SOC-2 Compliance Status Report   sample v10.0SOC-2 Compliance Status Report   sample v10.0
SOC-2 Compliance Status Report sample v10.0Mark S. Mahre
 
SOC Certification Runbook Template
SOC Certification Runbook TemplateSOC Certification Runbook Template
SOC Certification Runbook TemplateMark S. Mahre
 
SOC-2 Framework - Plan, Budget, Design, Integrate & Audit Security Controls
SOC-2 Framework - Plan, Budget, Design, Integrate & Audit Security ControlsSOC-2 Framework - Plan, Budget, Design, Integrate & Audit Security Controls
SOC-2 Framework - Plan, Budget, Design, Integrate & Audit Security ControlsMark S. Mahre
 
US State Government Case Study
US State Government Case StudyUS State Government Case Study
US State Government Case StudyMark S. Mahre
 
ClearCost License & Implementation under $50K
ClearCost License & Implementation under $50KClearCost License & Implementation under $50K
ClearCost License & Implementation under $50KMark S. Mahre
 
VP Reference Letter_Oct2015
VP Reference Letter_Oct2015VP Reference Letter_Oct2015
VP Reference Letter_Oct2015Mark S. Mahre
 
CFO Reference Letter_Sept2015
CFO Reference Letter_Sept2015CFO Reference Letter_Sept2015
CFO Reference Letter_Sept2015Mark S. Mahre
 
ClearCost Introduction 2015
ClearCost Introduction 2015ClearCost Introduction 2015
ClearCost Introduction 2015Mark S. Mahre
 
Mark S Mahre - Info-Tech final
Mark S Mahre - Info-Tech finalMark S Mahre - Info-Tech final
Mark S Mahre - Info-Tech finalMark S. Mahre
 
Spending Request Example V4
Spending Request Example V4Spending Request Example V4
Spending Request Example V4Mark S. Mahre
 
IT Dashboard User Manual V2.2
IT Dashboard User Manual V2.2IT Dashboard User Manual V2.2
IT Dashboard User Manual V2.2Mark S. Mahre
 
Capacity Management Process Handbook
Capacity Management Process HandbookCapacity Management Process Handbook
Capacity Management Process HandbookMark S. Mahre
 
PMO Framework Corus360 V2B
PMO Framework Corus360 V2BPMO Framework Corus360 V2B
PMO Framework Corus360 V2BMark S. Mahre
 
Data Migrations Framework V33
Data Migrations Framework V33Data Migrations Framework V33
Data Migrations Framework V33Mark S. Mahre
 
FundFlow V3.6 Overview (Printable) 08-18-03
FundFlow V3.6 Overview (Printable) 08-18-03FundFlow V3.6 Overview (Printable) 08-18-03
FundFlow V3.6 Overview (Printable) 08-18-03Mark S. Mahre
 

More from Mark S. Mahre (20)

Technology Alignment Framework
Technology Alignment FrameworkTechnology Alignment Framework
Technology Alignment Framework
 
Technology Assessment Framework
Technology Assessment FrameworkTechnology Assessment Framework
Technology Assessment Framework
 
Aprio Consulting Services - Cloud, ITFM, Compliance, Innovation, Technology
Aprio Consulting Services - Cloud, ITFM, Compliance, Innovation, TechnologyAprio Consulting Services - Cloud, ITFM, Compliance, Innovation, Technology
Aprio Consulting Services - Cloud, ITFM, Compliance, Innovation, Technology
 
Governance - Project Management Office Professional Services
Governance - Project Management Office Professional ServicesGovernance - Project Management Office Professional Services
Governance - Project Management Office Professional Services
 
SOC-2 Compliance Status Report sample v10.0
SOC-2 Compliance Status Report   sample v10.0SOC-2 Compliance Status Report   sample v10.0
SOC-2 Compliance Status Report sample v10.0
 
SOC Certification Runbook Template
SOC Certification Runbook TemplateSOC Certification Runbook Template
SOC Certification Runbook Template
 
SOC-2 Framework - Plan, Budget, Design, Integrate & Audit Security Controls
SOC-2 Framework - Plan, Budget, Design, Integrate & Audit Security ControlsSOC-2 Framework - Plan, Budget, Design, Integrate & Audit Security Controls
SOC-2 Framework - Plan, Budget, Design, Integrate & Audit Security Controls
 
US State Government Case Study
US State Government Case StudyUS State Government Case Study
US State Government Case Study
 
ClearCost License & Implementation under $50K
ClearCost License & Implementation under $50KClearCost License & Implementation under $50K
ClearCost License & Implementation under $50K
 
ClearCost
ClearCostClearCost
ClearCost
 
VP Reference Letter_Oct2015
VP Reference Letter_Oct2015VP Reference Letter_Oct2015
VP Reference Letter_Oct2015
 
CFO Reference Letter_Sept2015
CFO Reference Letter_Sept2015CFO Reference Letter_Sept2015
CFO Reference Letter_Sept2015
 
ClearCost Introduction 2015
ClearCost Introduction 2015ClearCost Introduction 2015
ClearCost Introduction 2015
 
Mark S Mahre - Info-Tech final
Mark S Mahre - Info-Tech finalMark S Mahre - Info-Tech final
Mark S Mahre - Info-Tech final
 
Spending Request Example V4
Spending Request Example V4Spending Request Example V4
Spending Request Example V4
 
IT Dashboard User Manual V2.2
IT Dashboard User Manual V2.2IT Dashboard User Manual V2.2
IT Dashboard User Manual V2.2
 
Capacity Management Process Handbook
Capacity Management Process HandbookCapacity Management Process Handbook
Capacity Management Process Handbook
 
PMO Framework Corus360 V2B
PMO Framework Corus360 V2BPMO Framework Corus360 V2B
PMO Framework Corus360 V2B
 
Data Migrations Framework V33
Data Migrations Framework V33Data Migrations Framework V33
Data Migrations Framework V33
 
FundFlow V3.6 Overview (Printable) 08-18-03
FundFlow V3.6 Overview (Printable) 08-18-03FundFlow V3.6 Overview (Printable) 08-18-03
FundFlow V3.6 Overview (Printable) 08-18-03
 

IT Project Life Cycle Process Flow

  • 1. Property of ClearCost Consulting US IT Project Life Cycle Process Flow Chart Preliminary Evaluation Initiation & Risk Assessment Requirements Project Build QA & Testing Are Any Changes to Design Plan Required? Documentation & Training Implementation IntegrationDesign Discovery Design Build Run Submit Preliminary Plan to Manager Preliminary Project Plan & Include Project Benefits Complete Project Summary Is project OVER 50,000 in local currency? Complete the Investment Request Template Complete the Project Financials Template Have Meeting with Management for the Go-Ahead No Determine the Approval Path for required Management Is Project Evaluation Approved? No Alternative Plan or File Project Yes Put together Project Team (X) Requirements & Recommendations Put together Project Management Plan Put together Project Team (“X”) Requirements & Recommendations Put together Project Management Plan Put Together Task Plan For Projects UNDER 50,000, use the Project Summary Template for Approval Signatures Scan Original Signatures (Signature Page Only) Approval For Projects OVER 50,000, use the Investment Request Template for Approval Signatures Prepare All Documents for the Approval Process Next Phase Evaluation Review Regional Signatures Global Mgmt. Signatures Regional CEO / CFO Signature Global CEO / CFO Signature Board of Directors Approvals Required Required Required Next Phase > 1 Million X X X X X Board of Directors X Global CEO XX Regional CEO XXX Global IT Management XXXX Regional Management > 500,000> 50,000< 50,000< 25,000 Approval Signature Requirements Decommission Develop a Microsoft Project Plan Create a Requirements Doc with Success Criteria Define & Document Test Lab Requirements (if Required) Acquire Approvals for Requirements Document Were Requirements Approved? No Yes Create a Technical Approach Doc (if Required) Acquire Approval for Technical Approach Was Tech Approach Approved? No Document All Inter-project Dependencies Yes Acquire Approval for Lab Requirements Were Requirements Approved? No Required Not Required Not Required Yes Yes Not Required Provide Business Case Documents to Routing Administrator Create a Solution Design Document (if Required) Acquire Approval for Solution Design No Yes Were Requirements Approved? Not Required Document Any Issues for Inter-project Dependencies Schedule a Meeting Regarding Inter-project Dependencies doc Establish a Game Plan for All Inter-project Dependencies Develop a Detailed QA / Test Plan Acquire Approval for QA / Test Plan Was QA / Test Plan Approved? No Not Required Next Phase Meeting w/ Project Team to Review & Discuss Project Build Doc‟s Make Necessary Revisions to Project Build Plan or Design Follow the Process According to the Project Build & Design Plan Is a Project Team or Status Meeting Beneficial at this Time? Yes No Yes Not Required Is the Project Build Completed? Meeting w/ Project Team to Review Project Status & Implementation Progress No Meeting w/ Project Team to Approve QA / Testing Strategy Is the Project Build Approved for Testing? Meeting w/ Project Team to Complete Testing & Start Documentation Yes No Meeting w/ Pilot Group to Discuss QA & Testing Procedures Yes Follow the Process According to the QA & Testing Plan Define Testing Group and Requirements for a Test Success Move Forward Without Additional Testing? Are the QA / Test Results Satisfactory? No Yes Move Forward with the Project Testing? Make Necessary Improvements or Changes to Testing Plan Yes No Yes Prepare Team for Implementation Phase Revised 02-10-05 Scan Original Signatures Master (Signature Page Only) Supplemental Regional Signatures Global Mgmt. Signatures Regional CEO / CFO Signature Global CEO Signature Board of Directors Approvals Review All Documents for Original Signatures Required Required Required Not Required Provide Revised Business Case Documents to Routing Administrator Did the Cost of the Project Increase? Next Phase No Cost Increase Create an Addendum to the Inv. Request w/Financials Yes Next Phase Is a End User Manual Required? Is a Process Flowchart Document Required? Yes Make Necessary Revisions to Project Build Requirements Next Phase Decommission Completion Y Z Y Z I M Y Z Y Z Y Z Y Z Y Z Y Z Y Z Meeting w/ Project Team to Review & Discuss Implementation Strategy Not Required Required Are any Change Requests Required? Are any Status Reports Required? B Y Z Y Z Y Z Y Z Y Z Y Z Y Z A B C D F I O M R S X Y Z Y Z F I M Y Z Y Z Y Z Y Z Q Y Z B F I M P Q R B F I M Q E M Q E M Q G Q Review Risk & ROI Cost & Benefits with Management Does the Preliminary Plan Justify Moving Ahead? Yes No Document Risk & ROI Cost & Benefits Summary Review All Project Documentation with Team Members Yes Review Final Project Documents & Financials with Management Team Q Y Z Y Z Y Z Y Z X Y Z A C D I O X Y Z A B C D F I M O S T X Y Z Y Z B I M D O T X Y Z B I M D O S T X Y Z B D F I M O S T X Y Z B D I M O S T X Y Z P X Y Z B D I M O T X Y Z A C D I O X Y Z B D I M O S T X Y Z D O T X Y Z X Y Z X Y ZI X Y Z O D T X Y Z X Y Z T X Y Z X Y Z B F I M R X Y Z B X Y Z Q X Y Z B F I M P Q B F I M Q E M R E M Q G Q Y Z Y Z Y Z A B C D F I S O X Y Z D O T X Z D O X Y Z X Y Z D O X Y Z A C D F I O R S X Y Z B I M D T X Y Z D O T X Y Z A D O S T U X Y Z D O T U X D I O T X D F I O T X Y Z T X Y Z X Y Z X Y Z A B C D I O S X Y Z I O P X Y Z X Y Z D C O T X Y Z Level 1 Level 2 Level 3 Level 4 Level 5 Level 6 Level 7 Level 8 Level 9 Level 10 Level 11 Level 12 Level 13 Level 14 Level 15 Level 16 Level 17 Level 18 Level 15 Level 10 Level 9 Level 8 Level 7 Level 6 Level 5 Level 4 Level 3 Level 2 Level 1 Individual or Group Dependencies A Architecture Team P Purchasing Group B Business Owner Q Routing Administrator C Consulting Team R Risk Management D Development Team S Security Team E Executive Management (Non - IT) T Testing Team F Finance Group (IT) U Pilot Testing Group G Board of Directors V Training Group I IT Department Team W Project Architect L Legal Department X Project Team M Management (Business) Y Project Principle O Operations Group Z Project Manager Required Required Is the Implementation Process Complete? Not Required Follow the Process According to the Implementation Plan Implementation Evaluation (Every 2 to 4 Weeks) Not Required No Yes Meeting w/ Project Team to Review & Discuss Integration Strategy Meeting w/ Project Team to Review & Discuss Project Completion Follow Process According to the Integration Strategy Are any Change Requests Required? Status Reports Due: 1. Schedules 2. Transition Plan 3. Project Mgmt. Plan 4. Implement Plan 5. In-Pro Dependencies Are any Status Reports Required? Required Required Is the Transition Process Complete? Not Required Transition Evaluation (Every 1 to 4 Weeks) Change Requests: 1. Schedules 2. Transition Plan 3. Project Mgmt. Plan 4. Implement Plan 5. In-Pro Dependencies Not Required Sign-Off on the Procedures for Project Transition Yes Are any User Acceptance Sign-Off‟s Required? Reports Sign-Off: 1. Time & Materials 2. Total Cost Report 3. Business Case 4. Resources Used 5. Project Design Doc‟s Are any Report Sign-Off‟s Required? Required Required Not Required User Acceptance Sign-Off 1. Administrators 2. Support Team 3. Power Users 4. Remote Locations 5. Management Team 6. Security Team Not Required Was the Project Approved by the Executive Team? Yes A1 A C D F I O S T X Y Z D I O X Y Z D I O X Y Z D I O X Y Z D I O X Y Z B D I O X Y Z Was the Project Approved by the Executive Team? A1 No Yes D I O X Y Z A B C D F I M O S U X Y Z D I O X Y Z D X Y Z B D I O X Y Z Not Required Not Required Level 11 Status Reports Due: 1. Schedules 2. Solution Plan 3. Cost Controls 4. Project Mgmt. Plan 5. Implement Plan 6. In-Pro Dependencies 7. Risk Mgmt. Plan B D I M O X Y Z D X Y Z 5% 10% 15% 20% 30% 35% 40% 50% 60% 70% 80% 90% 100% Review All Documents for Original Signatures Legal Review & Contract Execution Any Contracts or Agreements Required for Legal? Is there New HW / SW Required? No B1 Did All Contracts & Agreements Receive Approval? Required Yes No F I R Y Z F L I M Y Z Start the Legal Review & Contract Procedures B F I M L Y Z No Project Success Meeting with Discussions & Lessons Learned Document Lessons Learned and Send Copies to Team Level 14 Level 13 Level 12 A B C D F I M O S X Y Z X Y Z X Y Z D X Y Z D X Y Z Meeting w/ Project Team to Discuss Parallel Processing & Decommission Follow the Parallel Process Decommission According to the Transition Plan Status Reports Due: 1. Schedules 2. Transition Plan 3. In-Pro Dependencies Are any Status Reports Required? Required Is the Decommission Process Complete? Not Required Decommission Evaluation (Every 1 to 4 Weeks) D I M O X Y Z D I M O X Y Z X Y Z D I M O X Y Z D X Y Z No Any Legacy Applications or Parallel Procedures Required? Yes Not Required Yes Process Complete IFS File All Documents in Project Folder IFS File All Project Documents IFS Enter Project into IT PM Register IFS File Scanned Signatures Copy IFS Update IT PM Register for Project Approval IFS File All Documents in Project Folder IFS Update New Changes in Project Folder IFS Update IT PM Register to Include Supplemental Approval IFS Update IT PM Register & Project Folder IFS Update IT PM Register Validate the User Manuals & Technical Documentation IFS File All User Manuals & Tech Documentation IFS File Acceptance Sign-Off Documents IFS Update All Final Documents & Lessons Learned IFS Update the Project Folder 110% C1 A2 B2 C2 No Not Required IFS File Signatures Scanned Copy IFS Update the IT PM Register Is the QA & Testing Plan Ready for a Pilot Group? IFS Include All Testing Results in the Project Folder IFS Document Status Reports & File IFS Document Change Requests & File D X Y Z IFS Document Change Requests & File IFS Update the IT PM Register IFS Locate Required Business Case Documents IFS Locate Required Business Case Documents IFS Create a Project Folder Develop Implementation Plan w/ Design Requirements Work with Procurement Dept to Price Required HW / SW Complete the HW and / or SW Requisition Form IFS File All Documents in Project Folder Q Y Z Review & Update the QA / Testing Process E1 E2 D O T X Z D O T X Z A B C D I O S X Y Z A B C D F I M O S X Y Z B D I O X Y Z IFS Document Status Reports & File D X Y Z D I O X Y Z D I O X Y Z A B C D F I M O F X Y Z IFS File Reports Sign-Off Documents A B C D F I M O U X Y Z Sign-Off Procedures for Project Completion A B C D F I M O F X Y Z Meeting w/ Project Team to Determine the Required Documents A B C D F I M O R S X Y Z I Complete Project Summary I II III IV IV V V VI VII VIII IX X XI XIII XIV XV XVI XVII Start Technical Documentation (Version, Support, etc…) Start the End User Manual Documentation („How To‟) Process or Engineering Flow (Step-by-step Procedures) Business Case Documents Document Description Preliminary Project Plan Legal Review Contract Proced. Project Summary Investment Request Team Requirements This is a basic document that is the starting point or feasibility study that will determine if the project should be initiated. A document that contains the procedures and sigh-off by an officer of the company for software / hardware licenses or legal contracts associated with the project. Mandatory for all projects. High level document required for the approval process and used as a project cover page. Required for project over 50,000. This primary document includes the project details that are important during the approval process. Document of all team members and the duties, authorities and responsibilities for each. Project Management Plan Using Microsoft Project, lay out the important events on a Gant chart for documenting the tasks for the project. Required for project over 50,000. This documents includes the project financial & ROI details that are important during the approval process. Project Financials A # B I II III IV V Acquire Approval for Migration Strategy Was Migration Strategy Approved? B C D I M O X Y Z Yes A B C D I M O X Y Z A B C D I M O X Y Z B I M D T X Y Z IFS Revise All Initial Business Case & Project Budgets XII XV XIII XII D I T O X Y Z Set up the Development, Test and Production Environments Approval Process Supplemental Approval Process Order New HW / SW for the Solution (If Required) Configure & Implement HW / SW the Solution Turn Over HW / SW to the Project Team I O P A I O A I O Required Not Required T X Y Z Testing Evaluation (Every 1 to 2 Weeks) Order New HW / SW for Solution (If Required) Configure & Implement HW / SW the Solution Turn Over HW / SW to the Project Team A I O A I O Start to Create the Disaster Recovery Plan Is a Disaster Recovery Plan Required? Required Not Required Notify Team when QA & Testing is Completed Are All Legal Documents & Contracts Still Valid? D2 No D1 Yes D I O X Y Z A C D I O X Y Z Start to Create an Implementation Roadmap Meeting with Training Groups to Discuss Training Process Follow the Process According to the Training Plan Are the Training Results Satisfactory? B C D I M O V X Y Z Training Evaluation (Every 1 to 2 Weeks) B C D I M O V X Y Z B C D I M O V X Y Z No Yes Complete the End User Manual IFS Place a Users Manual in Project Folder Document Benefit Returns Predicted in the Business Case Documents Key Financial Indicators: 1. Project Cost 2. Net Present Value 3. IRR / ROI 4. Payback Period 5. Resources Used 6. Value & Risk IFS Update Documents in Project Folder D X Y Z A1 B1 C1 Review with Management & Determine if Any Project Changes will Help Meet with Project Team to Make Changes or Improvements to Project Cut Costs to Project Spending to Improve RIO & KPI‟s Update All Documentation to Submit for Approval F I B X Y Z D O P R X Y Z F B X Y Z X Y Z Review with Management & Determine if Any Contract Changes will Help Meet with Project Team to Make Changes or Improvements to Contracts Cut Costs to Contracts to Improve RIO & KPI‟s Update All Contracts to Submit for Approval B F I R X Y Z F X Y Z B F O R X Y Z F X Y Z Review with Management the Reasons for Testing Failure Meet with Project Team to Discuss Proposed Changes to Project Build Review with Management for Approval of New Project Build Specifications Update All Design & Implementation Documentation B F I R X Y Z D O P R X Y Z B F I X Y Z X Y Z X Y Z X Y Z X Y Z A2 B2 C2 Off Chart Modification & Sub-Processes IFS Save Revised Documents IFS Save Revised Documents IFS Save Revised Documents D1 Review with Management Reasons for Contract Changes Meet with Project Team to Discuss Proposed Changes to Contracts Review with Management for Approval of New Contract Changes Update All Contract Documentation B F I R X Y Z D O P R X Y Z B F I X Y Z X Y Z X Y Z D2 IFS Save Revised Documents E1 Review with Management Reasons for Project Issues Meet with Project Team to Discuss Proposed Changes to Build Design Review with Management for Approval of New Build Design Update All Project Build Documentation A B C D F I M O S X Y Z D I X Y Z X Y Z E2 IFS Save Revised Documents A C D I O S X Y Z A B C D F I M O S X Y Z Level 17 Level 18 Level 16 Create a Training Plan & Define the Training Groups Meet with Operations Group to Formulate Design Plan Change Requests: 1. Schedules 2. Solution Plan 3. Cost Controls 4. Project Mgmt. Plan 5. Implement Plan 6. In-Pro Dependencies No Determine & Document the Dev, Test and Production Requirements Develop a Migration Strategy XII > 1 Million X X X X X Task Plan Optional Optional X X X XXOptionalOptional Team Requirements XXXOptional Project Mgmt. Plan XXOptionalOptional Project Financials XXOptionalOptional Investment Request XXXX Project Summary > 500,000> 50,000< 50,000< 25,000 Business Case Requirements Perform a Security Architecture Review / Audit if Required Required A C I O S X Y Z Acquire Approvals for Risk Mgmt Plan A B C D F I M O S T X Y Z Update the MS Project Plan to Reflect Any Requirements Changes Level 19 Yes No Meeting w/ Project Team to Approve Build Design A C D F I O S T X Y Z Yes Y Z Y Z Yes Project Design Documents Document Description Microsoft Project Plan Requirements Document Lab Requirements A detailed plan that shows the technical approach from a systems architecture and application view point. Using Microsoft Project, lay out the important events on a Gant chart for documenting the tasks for the project. A detailed document that lists the Project Requirements with a scope to include a set of deliverables and project success criteria. A detailed document that lists all the lab Requirements for the Operations Group and Security Team. A detailed document that provides the solution architecture, system design, application dependencies and s. A reference document of all the current projects & applications that are associated to the proposed project ... A formal detailed document that provides the implementation schedules, personnel responsibilities, deliverables, milestones, system design and simulations. Form required for all software or hardware purchases related to the project. Technical Approach Inter-Project Dependencies Solution Design Detailed Implementation SW / HW Requisition Detailed QA / Test Plan A detailed test plan includes; quality assumptions, production requirements, BAU acceptance, timelines, and testing success scorecards. Weekly, Bi-Monthly, or Monthly reports related to the status of a project. May include the progress related to the original Pro. Mgmt. Plan Status Reports # VII VIII IX X XI XIII XIV XV XVI Project Folder in IFS All projects require a project folder in IFS where all project related documents are kept. IT PM Register Project spreadsheet for recording all project financial information found in IFS under IT PM / Register. A detailed document that provides a Migration Strategy for the Dev, Testing and Production environments. Migration Strategy XII Risk Management Plan The objective of the risk management plan is to minimize any unexpected but not unforseen events migrating to become project issues and having a residual impact on the project. XVII Create a Risk Management Plan XVII Not Required A C I O S X Y Z Review Risk Management Plan and Security Issues Acquire Approval for Risk Management Plan R S X Y Z Level 20 Index Requires Signature / Approval Multiple Files or Documents Review or Approval Required Process Step Document Procedure Direction to the Next Step “Yes” or “No” Direction Dependencies Code (see chart) Off Chart Modification Sub-Processes Process Level within a Section Decision Step Required Process Group or Predefined Phase Kick Off Meetings Enter Data in the IFS Directory NO YES T X Y Z A1 Level 16 IFS To understand how to properly use this template, please refer to the IT Project Life Cycle Process Manual The manual will help explain how to effectively utilize this template tool when running or managing a medium, large or enterprise IT projects. Does the Project Require Contracts or Legal Reviews? Complete Legal Review & Contract Procedures Doc Required Y Z Y Z Not Required A Complete the Application / Infrastructure Operations Handover Doc. B Task Plan A document to list the chronological events that are broken into individual tasks that ties to the implementation plan. Supplemental Addendum All documents that are additions to the original Investment request or Project Financial worksheets for receiving second approval. VI XVII