SlideShare a Scribd company logo
1 of 21
The Road to
Resilience
14th Annual
The Quarterback’s Dilemma
Successfully managing the development and invocation of a Business
Continuity Plan
When uncertainty prevails….
Planning, Practice and Risk Management can
lead to success
Goal is known - “Win!”
But…
• What it takes to “win” is constantly changing, not just
between plays, but within plays
• Strategy for winning is dynamic
• Resources are constrained, and their behavior uncertain
• Obstacles and impediments interfere with strategy and plans
• Many individual outcomes are uncertain
The Quarterback’s Dilemma
Sound familiar?
Just like developing a Business
Continuity Plan, or invoking one?
Developing and Invoking a Business Continuity Plan
both share common complexities
• Scope and goals
• Organizational structure, roles and responsibilities
• Resources
• Ongoing organizational and operational dynamics and
change
• Both are programs – or a “project of many projects”.
• Business Continuity Management may also be a continuous
program of projects in order to maintain and validate a plan
Business Continuity Projects are Complex
Structural Multiplicity: The need to manage and keep track of
huge numbers of different interconnected tasks and activities
Technical Interdependence: Dependencies between the
processes, technology, and/or resources engaged in the
project.
Novelty: The uniqueness of the project/process/technology
within the organization.
• Often, the organization has no relevant organizational or
technical precedents or experiences.
Directional Diversity: Uncertainty and ambiguity arising from
multiple interpretations of goals and objectives
Business Strategy Changes: M&A activity, regulatory actions
and other external factors may significantly alter the scope and
objectives of the project
What Makes a Project Complex?
Is Your Project Complex?
Keys to Managing Complex Projects
Context
• A “bet your business” project is underway
• The Senior Leader is meeting with the 12 project teams
• The following dialogue ensues with each of the 12 teams
• The Senior Leader concludes “you each reported a 50/50
chance of being on time, therefore the project has a 50/50
chance of being on time”
Case Study 1: Failing to Manage Risk
Senior Project Leader Response from Each of 12 Team Leaders
“What is your status?”
“Generally on plan, but we have
identified some issues”
“What actions have you taken?”
“We have assessed the risk and
developed a remediation plan for each
issue, and are tracking each”
“From 1-5, if 5 is will complete on-time
and 1 is will not complete on-time, what
is your timeliness assessment?
“3 50/50”
Issues:
• Each team leader identified that risks existed in their
projects, but no specific risks were described or shared
• Neither the Senior Project Leader nor any team leader knew
how risks identified by others might impact their project
• The consequences of risks cascade through the project
• When risks are not effectively known, ignorance cascades through
the project
• No one on the project could influence the outcome of the
risks encountered by other teams, though each may have
been impacted by those risks
• The chance of being on time was not 50/50 or 50%, but
0.0244% or 1/2048th of the assumed likelihood
Outcome:
• Project over-budget and behind schedule by “100’s of %”
Case Study 1: Failing to Manage Risk
Adding Value by Managing Risk
 Effective Risk Management preempts challenges
and identifies new opportunities
• Risks are not adjunct to project tasks and goals – they are
an intrinsic part of each
• Continuously identify new risks and dependencies,
reassess old ones, and develop and update response plans
• Identify previously
unknown opportunities
to increase the business
value of the solution
Organizational changes make projects more
complex, and risk management more difficult
Legacy Projects
(Business Continuity)
Project Manager
Team 1 Team 2 Team 3
User
Liaison
Today’s Projects
14th Annual Continuity Insights Management Conference:
The Road to Resilience
11
(Business Continuity)
Project Office
(BC, IT, User, etc…)
TalentTeam 1 Legal
Corp
Comms
QA
Security
Multiple
Organizational
Leaders
Executive
Sponsors
Awareness of Risk diminishes as information moves
upwards in the organization
• Risk Management skills may be inadequate
• Ownership and awareness of risk is diffused
• Organizational biases may diminish risk recognition
Senior leadership becomes aware of risks too late
Projects Without Active Risk Management
Quality & Risk Management - QRM
 Business Continuity Projects have many risks. And
many of those risks are significant
 QRM helps to Identify, Assess and Control those risks.
Context:
• Project has an ironclad due date
• A critical milestone is about to be missed
• The task is simple, but requires modest effort from 6
distinct business units
• For two months, all business units have ignored requests
to perform their related work
• The project team is to report to the C-Suite in two weeks
• The project sponsor identifies the milestone status as
“green” – we’ll get it done next week (this has been the
status for the past 8 weeks)
Challenge:
• The project sponsor is not assessing the risk properly
• The project will mis-report to the C-Suite, and then fail
Case Study 2: Quantifying a Risk View
Knowns and Assumptions:
• No calendar slippage is allowed
• If any one of the 6 business units fails to deliver, then the
project slips at least one week
• Combinations of failures will lead to slippages >= 1 week
What is the probability of the project slipping at least
1 week?
Outcome: Project sponsor understood the risk and
got the 6 business units to complete work on time
Case Study 2: Quantifying a Risk View
Chance of Each of 6 Tasks
Completing On-Time
Chance of Success - No
Slippage
Chance of Failiure -
Slipping at Least 1 Week
90% 53% 47%
80% 26% 74%
70% 12% 88%
60% 5% 95%
50% 2% 98%
Centralize the responsibility for addressing project
risks in the Business Continuity Management team
• Risk Management is elevated to the same level as Project
and Financial metrics and milestones
• Risk management reports join the key project deliverables that are
shared by the project team and by leadership
• Risks to developing the program and to invoking it are both
identified and addressed by a core team of project leaders
and sponsors
• Additional professionals and experienced Risk Management
staff may be added to the Business Continuity Management
team.
Empowering the BCM to Manage Risk
Risk Governance is transformed from a task distributed
and diffused throughout the project team to one
shared by the project team and their leadership.
Develop a “risk view” of the Business Continuity
Project.
• The risk view supplements the typical “process view” (e.g.:
Gantt charts, task list, milestones, etc...) and the “financial
view” (i.e., budgets) commonly used to manage projects,
allowing the project team and the project’s sponsors to
understand and address risks effectively.
• Conflicts and uncertainties that impact the Business
Continuity program are more readily identified and become
more visible. This allows for the preparation for a wider
range of contingencies.
Empowering the BCM to Manage Risk
Risk identification, management and
mitigation becomes a core competency of the
entire project and leadership team, with
appropriate resources, skills and accountability
Organizing a Project to Manage Risk
Task Risk
How much risk (uncertainty) to
success is inherent in the task to be
performed?
Status Risk
How much risk (uncertainty) to
success is inherent in the current
status
Case Study 3: A Risk View of a Project
Characteristic Risk Characteristic
Project depends on new
technology; Staff has no experience
and needs 2 weeks of training
High
Deployment scheduled during the
middle of a major datacenter
relocation
A product issue has been identified.
Vendor has proposed a work-
around.
Elevated
A key person is scheduled for
vacation during a critical period
Not High, Elevated or Low Normal Not High, Elevated or Low
A repetitive task that has been
successfully performed routinely
throughout the project needs to be
performed a few times more
Low
Small/simple task, not on the
critical path, and fully resourced
Case Study 3: A Risk View of a Project
Task Owner
Current
Week
Prior
Week Comment
Current
Week
Prior
Week Comment
A.1 Ensure readiness of SiteA
and SiteB
Tom Task:G Task:G
All new technology validated and initial
installs complete
Status:Y Status:Y
WAN circuit upgrade delayed by telco;
Generator install delayed by contractor
A.2 Implement DR for VPN and
remote-access security
software
Dick Done Done
System implemented with auto-failover
across independent hardened
datacenters
Done Done Complete
A.4: Deploy High-Availability
Email/Archive/GOOD-Access
Harry Done Done
All installation/dev/testing complete;
Fully operational and failover routinely
tested in production
Done Status:G
Mailbox moves in process, but do not
affect overall deployment schedule.
Mostly complete. No residual risks
A.6 Deploy DR for Sharepoint
portal sites and applications
Betty Task:G Task:G
Proof of concept validated. No technical
risk at this time
Status:Y Status:Y
Work being scheduled and expected to
complete on time
A.8 Develop BCP/DR plans for
SiteA and SiteB
Jane Task:A Task:Y
New user requirement to automate
recovery workflows. This new
technology adds an undimensioned risk
Status:R Status:R
Ability to meet schedule requirements
cannot be assessed until need
technology is assessed and validated
C.1 Implement DR for Payroll
and HR IS systems
Mary Task:G Task:G
Will be migrated from in-house
technology to proven 3d party service
provider
Status:Y Status:Y Implementation to be scheduled
C.3: Implement PC Provisioning
for DR
TBD Task:Y Task:G
Business process and accounting issues
continue to impact agreement on
strategy
Status:Y Status:Y
Business process and accounting issues
continue to delay resolution
Task Risk Status Risk
Q & A

More Related Content

What's hot

Project Success Assessment
Project Success AssessmentProject Success Assessment
Project Success AssessmentGlen Alleman
 
Pressman ch-21-project-management-concepts
Pressman ch-21-project-management-conceptsPressman ch-21-project-management-concepts
Pressman ch-21-project-management-conceptsseethaveera
 
Introduction to risk management
Introduction to risk managementIntroduction to risk management
Introduction to risk managements. Akhlaque
 
Project Risk Management - Introduction 2011
Project Risk Management - Introduction 2011Project Risk Management - Introduction 2011
Project Risk Management - Introduction 2011Sasha Lazarevic
 
Project risk management
Project risk managementProject risk management
Project risk managementDewang Agrawal
 
Paradigm of agile project management
Paradigm of agile project managementParadigm of agile project management
Paradigm of agile project managementGlen Alleman
 
Information Technology Risk Management
Information Technology Risk ManagementInformation Technology Risk Management
Information Technology Risk ManagementGlen Alleman
 
Top Five Ideas for Project Management
Top Five Ideas for Project ManagementTop Five Ideas for Project Management
Top Five Ideas for Project ManagementJohn Goodpasture
 
Risk Management Guidance
Risk Management GuidanceRisk Management Guidance
Risk Management GuidanceGlen Alleman
 
John marinaro pm_process
John marinaro pm_processJohn marinaro pm_process
John marinaro pm_processNASAPMC
 
Dealing With Troubled Projects in 8 Simple Steps
Dealing With Troubled Projects in 8 Simple StepsDealing With Troubled Projects in 8 Simple Steps
Dealing With Troubled Projects in 8 Simple StepsDoug Ziemke
 
Why Do So Many Software Projects Fail?
Why Do So Many Software Projects Fail?Why Do So Many Software Projects Fail?
Why Do So Many Software Projects Fail?Phil Comelio
 
Immutable principles of project management (utah pmi)(v1)(no exercise)
Immutable principles of project management (utah pmi)(v1)(no exercise)Immutable principles of project management (utah pmi)(v1)(no exercise)
Immutable principles of project management (utah pmi)(v1)(no exercise)Glen Alleman
 
PMP selected topics and ideas
PMP selected topics and ideasPMP selected topics and ideas
PMP selected topics and ideasAhmad Hamid
 
Nine best practices of project management
Nine best practices of project managementNine best practices of project management
Nine best practices of project managementGlen Alleman
 
Identifying and Recovering Troubled Projects
Identifying and Recovering Troubled ProjectsIdentifying and Recovering Troubled Projects
Identifying and Recovering Troubled ProjectsRicardo Viana Vargas
 

What's hot (20)

Project Success Assessment
Project Success AssessmentProject Success Assessment
Project Success Assessment
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Pressman ch-21-project-management-concepts
Pressman ch-21-project-management-conceptsPressman ch-21-project-management-concepts
Pressman ch-21-project-management-concepts
 
Introduction to risk management
Introduction to risk managementIntroduction to risk management
Introduction to risk management
 
Project Risk Management - Introduction 2011
Project Risk Management - Introduction 2011Project Risk Management - Introduction 2011
Project Risk Management - Introduction 2011
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
R1
R1R1
R1
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Paradigm of agile project management
Paradigm of agile project managementParadigm of agile project management
Paradigm of agile project management
 
Information Technology Risk Management
Information Technology Risk ManagementInformation Technology Risk Management
Information Technology Risk Management
 
Top Five Ideas for Project Management
Top Five Ideas for Project ManagementTop Five Ideas for Project Management
Top Five Ideas for Project Management
 
Risk Management Guidance
Risk Management GuidanceRisk Management Guidance
Risk Management Guidance
 
John marinaro pm_process
John marinaro pm_processJohn marinaro pm_process
John marinaro pm_process
 
Dealing With Troubled Projects in 8 Simple Steps
Dealing With Troubled Projects in 8 Simple StepsDealing With Troubled Projects in 8 Simple Steps
Dealing With Troubled Projects in 8 Simple Steps
 
Project governance
Project governanceProject governance
Project governance
 
Why Do So Many Software Projects Fail?
Why Do So Many Software Projects Fail?Why Do So Many Software Projects Fail?
Why Do So Many Software Projects Fail?
 
Immutable principles of project management (utah pmi)(v1)(no exercise)
Immutable principles of project management (utah pmi)(v1)(no exercise)Immutable principles of project management (utah pmi)(v1)(no exercise)
Immutable principles of project management (utah pmi)(v1)(no exercise)
 
PMP selected topics and ideas
PMP selected topics and ideasPMP selected topics and ideas
PMP selected topics and ideas
 
Nine best practices of project management
Nine best practices of project managementNine best practices of project management
Nine best practices of project management
 
Identifying and Recovering Troubled Projects
Identifying and Recovering Troubled ProjectsIdentifying and Recovering Troubled Projects
Identifying and Recovering Troubled Projects
 

Viewers also liked

Redwoods advance pte ltd singapore at the asian convention
Redwoods advance pte ltd singapore at the asian conventionRedwoods advance pte ltd singapore at the asian convention
Redwoods advance pte ltd singapore at the asian conventionRedwoods Advance
 
Redwoods Advance Telematch - at West Coast Park, Singapore
Redwoods Advance Telematch - at West Coast Park, SingaporeRedwoods Advance Telematch - at West Coast Park, Singapore
Redwoods Advance Telematch - at West Coast Park, SingaporeRedwoods Advance
 
Face to-face marketing relatively a simple solution
Face to-face marketing relatively a simple solutionFace to-face marketing relatively a simple solution
Face to-face marketing relatively a simple solutionRedwoods Advance
 
Making the business case for investing in technology
Making the business case for investing in technologyMaking the business case for investing in technology
Making the business case for investing in technologyAllan Cytryn
 
Project value risk management achieving the wow factor on your projects
Project value risk management   achieving the wow factor on your projectsProject value risk management   achieving the wow factor on your projects
Project value risk management achieving the wow factor on your projectsAllan Cytryn
 

Viewers also liked (12)

Redwoods Advance Reviews
Redwoods Advance ReviewsRedwoods Advance Reviews
Redwoods Advance Reviews
 
M1 01
M1 01M1 01
M1 01
 
El tinajon frozen goods
El tinajon frozen goodsEl tinajon frozen goods
El tinajon frozen goods
 
Ccl
CclCcl
Ccl
 
Product Presentation
Product PresentationProduct Presentation
Product Presentation
 
Redwoods advance pte ltd singapore at the asian convention
Redwoods advance pte ltd singapore at the asian conventionRedwoods advance pte ltd singapore at the asian convention
Redwoods advance pte ltd singapore at the asian convention
 
Redwoods Advance Telematch - at West Coast Park, Singapore
Redwoods Advance Telematch - at West Coast Park, SingaporeRedwoods Advance Telematch - at West Coast Park, Singapore
Redwoods Advance Telematch - at West Coast Park, Singapore
 
Face to-face marketing relatively a simple solution
Face to-face marketing relatively a simple solutionFace to-face marketing relatively a simple solution
Face to-face marketing relatively a simple solution
 
Processing Plant in Costa Rica
Processing Plant in Costa RicaProcessing Plant in Costa Rica
Processing Plant in Costa Rica
 
Making the business case for investing in technology
Making the business case for investing in technologyMaking the business case for investing in technology
Making the business case for investing in technology
 
Project value risk management achieving the wow factor on your projects
Project value risk management   achieving the wow factor on your projectsProject value risk management   achieving the wow factor on your projects
Project value risk management achieving the wow factor on your projects
 
Capacitors
CapacitorsCapacitors
Capacitors
 

Similar to The Quarterbacks Dilemma

Challenging Aspects of Modern Project Management
Challenging Aspects of Modern Project ManagementChallenging Aspects of Modern Project Management
Challenging Aspects of Modern Project ManagementYamanta Raj Niroula, PMP
 
Project management 02112009
Project management 02112009Project management 02112009
Project management 02112009Manish Chaurasia
 
Project assurance - make sure your projects delivers as expected
Project assurance - make sure your projects delivers as expectedProject assurance - make sure your projects delivers as expected
Project assurance - make sure your projects delivers as expectedTerje Sæbø
 
Project Manager Primer
Project Manager PrimerProject Manager Primer
Project Manager PrimerTom Cremins
 
Managing Risk in Agile Development: It Isn’t Magic
Managing Risk in Agile Development: It Isn’t MagicManaging Risk in Agile Development: It Isn’t Magic
Managing Risk in Agile Development: It Isn’t MagicTechWell
 
PMEC Study Material.pdf
PMEC Study Material.pdfPMEC Study Material.pdf
PMEC Study Material.pdfMrUmairKhan1
 
Risk Management Plan
Risk Management PlanRisk Management Plan
Risk Management PlanRavi Nakulan
 
Work shop project management
Work shop project managementWork shop project management
Work shop project managementrakeshsatpathy07
 
PMO Manual v2.0 June-18.pptx
PMO Manual v2.0 June-18.pptxPMO Manual v2.0 June-18.pptx
PMO Manual v2.0 June-18.pptxAshfaq Ahmad
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementKris Kimmerle
 
A Gentle Introduction to Deliverables Based Planning
A Gentle Introduction to Deliverables Based PlanningA Gentle Introduction to Deliverables Based Planning
A Gentle Introduction to Deliverables Based PlanningGlen Alleman
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycleSAJID ALI RUK
 
Getting the basics right
Getting the basics rightGetting the basics right
Getting the basics rightThomas Cream
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Dhamo daran
 

Similar to The Quarterbacks Dilemma (20)

Challenging Aspects of Modern Project Management
Challenging Aspects of Modern Project ManagementChallenging Aspects of Modern Project Management
Challenging Aspects of Modern Project Management
 
Project management 02112009
Project management 02112009Project management 02112009
Project management 02112009
 
Project assurance - make sure your projects delivers as expected
Project assurance - make sure your projects delivers as expectedProject assurance - make sure your projects delivers as expected
Project assurance - make sure your projects delivers as expected
 
A Framework for Managing Project Risk
A Framework for Managing Project RiskA Framework for Managing Project Risk
A Framework for Managing Project Risk
 
Project Manager Primer
Project Manager PrimerProject Manager Primer
Project Manager Primer
 
Managing Risk in Agile Development: It Isn’t Magic
Managing Risk in Agile Development: It Isn’t MagicManaging Risk in Agile Development: It Isn’t Magic
Managing Risk in Agile Development: It Isn’t Magic
 
INTRO.pptx
INTRO.pptxINTRO.pptx
INTRO.pptx
 
PMEC Study Material.pdf
PMEC Study Material.pdfPMEC Study Material.pdf
PMEC Study Material.pdf
 
Risk Management Plan
Risk Management PlanRisk Management Plan
Risk Management Plan
 
Work shop project management
Work shop project managementWork shop project management
Work shop project management
 
PMO Manual v2.0 June-18.pptx
PMO Manual v2.0 June-18.pptxPMO Manual v2.0 June-18.pptx
PMO Manual v2.0 June-18.pptx
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Unit 1.pptx
Unit 1.pptxUnit 1.pptx
Unit 1.pptx
 
A Gentle Introduction to Deliverables Based Planning
A Gentle Introduction to Deliverables Based PlanningA Gentle Introduction to Deliverables Based Planning
A Gentle Introduction to Deliverables Based Planning
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
 
Getting the basics right
Getting the basics rightGetting the basics right
Getting the basics right
 
PRESTO @ SUPSI
PRESTO @ SUPSIPRESTO @ SUPSI
PRESTO @ SUPSI
 
IT projects
IT projectsIT projects
IT projects
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5
 
PART- 1 Engineering Project Management
PART- 1 Engineering Project Management PART- 1 Engineering Project Management
PART- 1 Engineering Project Management
 

Recently uploaded

VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 
Risk management in surgery (bailey and love).pptx
Risk management in surgery (bailey and love).pptxRisk management in surgery (bailey and love).pptx
Risk management in surgery (bailey and love).pptxSaujanya Jung Pandey
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
LPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System PresentationLPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System Presentationthomas851723
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
 
Training Methods and Training Objectives
Training Methods and Training ObjectivesTraining Methods and Training Objectives
Training Methods and Training Objectivesmintusiprd
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
LPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering PresentationLPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering Presentationthomas851723
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 

Recently uploaded (20)

VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 
Risk management in surgery (bailey and love).pptx
Risk management in surgery (bailey and love).pptxRisk management in surgery (bailey and love).pptx
Risk management in surgery (bailey and love).pptx
 
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
LPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System PresentationLPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System Presentation
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
 
Training Methods and Training Objectives
Training Methods and Training ObjectivesTraining Methods and Training Objectives
Training Methods and Training Objectives
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
LPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering PresentationLPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering Presentation
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 

The Quarterbacks Dilemma

  • 1. The Road to Resilience 14th Annual The Quarterback’s Dilemma Successfully managing the development and invocation of a Business Continuity Plan
  • 2. When uncertainty prevails…. Planning, Practice and Risk Management can lead to success
  • 3. Goal is known - “Win!” But… • What it takes to “win” is constantly changing, not just between plays, but within plays • Strategy for winning is dynamic • Resources are constrained, and their behavior uncertain • Obstacles and impediments interfere with strategy and plans • Many individual outcomes are uncertain The Quarterback’s Dilemma Sound familiar? Just like developing a Business Continuity Plan, or invoking one?
  • 4. Developing and Invoking a Business Continuity Plan both share common complexities • Scope and goals • Organizational structure, roles and responsibilities • Resources • Ongoing organizational and operational dynamics and change • Both are programs – or a “project of many projects”. • Business Continuity Management may also be a continuous program of projects in order to maintain and validate a plan Business Continuity Projects are Complex
  • 5. Structural Multiplicity: The need to manage and keep track of huge numbers of different interconnected tasks and activities Technical Interdependence: Dependencies between the processes, technology, and/or resources engaged in the project. Novelty: The uniqueness of the project/process/technology within the organization. • Often, the organization has no relevant organizational or technical precedents or experiences. Directional Diversity: Uncertainty and ambiguity arising from multiple interpretations of goals and objectives Business Strategy Changes: M&A activity, regulatory actions and other external factors may significantly alter the scope and objectives of the project What Makes a Project Complex?
  • 6. Is Your Project Complex?
  • 7. Keys to Managing Complex Projects
  • 8. Context • A “bet your business” project is underway • The Senior Leader is meeting with the 12 project teams • The following dialogue ensues with each of the 12 teams • The Senior Leader concludes “you each reported a 50/50 chance of being on time, therefore the project has a 50/50 chance of being on time” Case Study 1: Failing to Manage Risk Senior Project Leader Response from Each of 12 Team Leaders “What is your status?” “Generally on plan, but we have identified some issues” “What actions have you taken?” “We have assessed the risk and developed a remediation plan for each issue, and are tracking each” “From 1-5, if 5 is will complete on-time and 1 is will not complete on-time, what is your timeliness assessment? “3 50/50”
  • 9. Issues: • Each team leader identified that risks existed in their projects, but no specific risks were described or shared • Neither the Senior Project Leader nor any team leader knew how risks identified by others might impact their project • The consequences of risks cascade through the project • When risks are not effectively known, ignorance cascades through the project • No one on the project could influence the outcome of the risks encountered by other teams, though each may have been impacted by those risks • The chance of being on time was not 50/50 or 50%, but 0.0244% or 1/2048th of the assumed likelihood Outcome: • Project over-budget and behind schedule by “100’s of %” Case Study 1: Failing to Manage Risk
  • 10. Adding Value by Managing Risk  Effective Risk Management preempts challenges and identifies new opportunities • Risks are not adjunct to project tasks and goals – they are an intrinsic part of each • Continuously identify new risks and dependencies, reassess old ones, and develop and update response plans • Identify previously unknown opportunities to increase the business value of the solution
  • 11. Organizational changes make projects more complex, and risk management more difficult Legacy Projects (Business Continuity) Project Manager Team 1 Team 2 Team 3 User Liaison Today’s Projects 14th Annual Continuity Insights Management Conference: The Road to Resilience 11 (Business Continuity) Project Office (BC, IT, User, etc…) TalentTeam 1 Legal Corp Comms QA Security Multiple Organizational Leaders Executive Sponsors
  • 12. Awareness of Risk diminishes as information moves upwards in the organization • Risk Management skills may be inadequate • Ownership and awareness of risk is diffused • Organizational biases may diminish risk recognition Senior leadership becomes aware of risks too late Projects Without Active Risk Management
  • 13. Quality & Risk Management - QRM  Business Continuity Projects have many risks. And many of those risks are significant  QRM helps to Identify, Assess and Control those risks.
  • 14. Context: • Project has an ironclad due date • A critical milestone is about to be missed • The task is simple, but requires modest effort from 6 distinct business units • For two months, all business units have ignored requests to perform their related work • The project team is to report to the C-Suite in two weeks • The project sponsor identifies the milestone status as “green” – we’ll get it done next week (this has been the status for the past 8 weeks) Challenge: • The project sponsor is not assessing the risk properly • The project will mis-report to the C-Suite, and then fail Case Study 2: Quantifying a Risk View
  • 15. Knowns and Assumptions: • No calendar slippage is allowed • If any one of the 6 business units fails to deliver, then the project slips at least one week • Combinations of failures will lead to slippages >= 1 week What is the probability of the project slipping at least 1 week? Outcome: Project sponsor understood the risk and got the 6 business units to complete work on time Case Study 2: Quantifying a Risk View Chance of Each of 6 Tasks Completing On-Time Chance of Success - No Slippage Chance of Failiure - Slipping at Least 1 Week 90% 53% 47% 80% 26% 74% 70% 12% 88% 60% 5% 95% 50% 2% 98%
  • 16. Centralize the responsibility for addressing project risks in the Business Continuity Management team • Risk Management is elevated to the same level as Project and Financial metrics and milestones • Risk management reports join the key project deliverables that are shared by the project team and by leadership • Risks to developing the program and to invoking it are both identified and addressed by a core team of project leaders and sponsors • Additional professionals and experienced Risk Management staff may be added to the Business Continuity Management team. Empowering the BCM to Manage Risk Risk Governance is transformed from a task distributed and diffused throughout the project team to one shared by the project team and their leadership.
  • 17. Develop a “risk view” of the Business Continuity Project. • The risk view supplements the typical “process view” (e.g.: Gantt charts, task list, milestones, etc...) and the “financial view” (i.e., budgets) commonly used to manage projects, allowing the project team and the project’s sponsors to understand and address risks effectively. • Conflicts and uncertainties that impact the Business Continuity program are more readily identified and become more visible. This allows for the preparation for a wider range of contingencies. Empowering the BCM to Manage Risk Risk identification, management and mitigation becomes a core competency of the entire project and leadership team, with appropriate resources, skills and accountability
  • 18. Organizing a Project to Manage Risk
  • 19. Task Risk How much risk (uncertainty) to success is inherent in the task to be performed? Status Risk How much risk (uncertainty) to success is inherent in the current status Case Study 3: A Risk View of a Project Characteristic Risk Characteristic Project depends on new technology; Staff has no experience and needs 2 weeks of training High Deployment scheduled during the middle of a major datacenter relocation A product issue has been identified. Vendor has proposed a work- around. Elevated A key person is scheduled for vacation during a critical period Not High, Elevated or Low Normal Not High, Elevated or Low A repetitive task that has been successfully performed routinely throughout the project needs to be performed a few times more Low Small/simple task, not on the critical path, and fully resourced
  • 20. Case Study 3: A Risk View of a Project Task Owner Current Week Prior Week Comment Current Week Prior Week Comment A.1 Ensure readiness of SiteA and SiteB Tom Task:G Task:G All new technology validated and initial installs complete Status:Y Status:Y WAN circuit upgrade delayed by telco; Generator install delayed by contractor A.2 Implement DR for VPN and remote-access security software Dick Done Done System implemented with auto-failover across independent hardened datacenters Done Done Complete A.4: Deploy High-Availability Email/Archive/GOOD-Access Harry Done Done All installation/dev/testing complete; Fully operational and failover routinely tested in production Done Status:G Mailbox moves in process, but do not affect overall deployment schedule. Mostly complete. No residual risks A.6 Deploy DR for Sharepoint portal sites and applications Betty Task:G Task:G Proof of concept validated. No technical risk at this time Status:Y Status:Y Work being scheduled and expected to complete on time A.8 Develop BCP/DR plans for SiteA and SiteB Jane Task:A Task:Y New user requirement to automate recovery workflows. This new technology adds an undimensioned risk Status:R Status:R Ability to meet schedule requirements cannot be assessed until need technology is assessed and validated C.1 Implement DR for Payroll and HR IS systems Mary Task:G Task:G Will be migrated from in-house technology to proven 3d party service provider Status:Y Status:Y Implementation to be scheduled C.3: Implement PC Provisioning for DR TBD Task:Y Task:G Business process and accounting issues continue to impact agreement on strategy Status:Y Status:Y Business process and accounting issues continue to delay resolution Task Risk Status Risk
  • 21. Q & A