1. Gantt Chart – IMOCA 60 RC
27 July 3 Aug 10 Aug 17 Aug 24 Aug 31 Aug
1.1.1 IMOCA 60
Design Acquired
1.1.2 Design
Adjusted
1.1.3 Final Design
Completed
1.2.1 Materials
Designed
1.2.2 Materials
Procured
1.2.3 Frames
Completed
1.2.4 Hull & Deck
Laminated
1.2.5 Cosmetics
1.3.1 Components
Decided & Procured
1.3.2 Components
Installed
1.3.3 Components
Tested
Title
m t w t f m t w t f m t w t f m t w t f m t w t f m t w t f m