SlideShare a Scribd company logo
1 of 18
Download to read offline
Delays and Disputes
Members:
1. Jacquelyn Vanessa Tee
2. Lee Lin Hui
3. Jason Teo Chun Chen
Questions
Q1: As a Consultant assessing an extension of time application by
the Contractor, what are the initial checklist and the principles to be
applied?
Q2: What are the purpose of an extension of time clause in most
standard contract and its implications? What is the implications of a
Certificate of Non-Completion? What is the difference between
general damages and liquidated damages?
Q3: What are concurrent delays? Is the Contractor entitled to
extension of time and loss and expense if there are concurrent
delays by Employer and Contractor?
“Q1: As a Consultant assessing an extension of time application by the
Contractor, what are the initial checklist and the principles to be applied?
Elements that needs to be clearly identified and present in the Contractor’s claims
are:
▣ The Relevant Event [Clause 23.8(a) - 23.8(x)]
- Related to Clause 23.1.
▣ Liability for the Relevant Event
- Proving the Contractor did not contribute towards the event which is stated
in the Conditions of Contract as being one which entitles the Contractor to
an EOT.
▣ Contractual Entitlement
- Contractor needs to state which clause or sub-clause under the PAM Contract
he considers he is entitled to.
▣ Clause 23.1 - If the Contractor is of the opinion that the completion of the Works is or
will be delayed beyond the Completion Date by any of the Relevant Events stated in
Clause 23.8, he may apply for an extension of time provided always that:
Sub-Clause 23.1(a) of the PAM Conditions
states that the Contractor shall give written
notice to the Architect of his intention to
claim for an extension of time and that such
notice must be given within twenty-eight
(28) Days from the date of the Architects
Instruction or the commencement date of the
Relevant Event, whichever is the earlier and
the giving of such a written notice shall be a
condition precedent to an entitlement to an
extension of time.
Sub-Clause 23.1(b) within twenty eight (28)
days of the end of the cause of delay, the
Contractor shall send to the Architect his final
claim for extension of time duly supported
with all particulars to enable the Architect to
assess any EOT to be granted. If the
Contractor fails to submit such particulars
within the state time (or within such longer
period as may be agreed in writing by the
Architect), it shall be deemed that the
Contractor has assessed that such Relevant
Event will not delay the completion of the
Works beyond the Completion Date.
▣ Cause and Effect
- Prepare facts describing the effects of the relevant event upon the Works.
Should include details of the works that were affected and the status of the
work.
▣ Substantiation
- Contractor should provide copies of documentary evidence (eg. progress
report and photos, minutes of meetings, programmes and schedules)
“Q2: What are the purpose of an extension of time clause in most standard
contract and its implications? What is the implications of a Certificate of
Non-Completion? What is the difference between general damages and
liquidated damages?
Construction contracts generally allow the construction period to be extended
where there is a delay that is not the contractor's fault. This is described as an
extension of time (EOT).
When it becomes reasonably apparent that there is, or that there is likely to be, a
delay that could merit an extension of time, the contractor gives written notice to
the contract administrator identifying the relevant event that has caused the
delay.
The purpose of an extension of time clause in the contract is to preserve
liquidated damages and prevent the contract from being frustrated. The main
beneficiary of the extension of time clause is the employer.
What are the purpose of an extension of time clause in most
standard contract and its implications?
It is not uncommon for delays to cause the completion date to be missed, that is,
the works are not complete, and so a certificate of practical completion cannot be
issued by the date for completion.
Employer will issues the contractor with a certificate of non-completion
(sometimes referred to as a ‘non-completion certificate’ or ‘non-completion
notice') as a prerequisite to claiming liquidated and ascertained damages. The
certificate of non-completion gives formal written notice to the contractor that
they have failed to complete the works described in the contract by the
completion date that was last agreed (the original completion date may have been
adjusted during the course of the works).
● Clause 22.1, 22.2
What is the implications of a Certificate of Non-Completion?
Liquidated damages (sometimes referred to as agreed damages) are a fixed sum of
money which has been agreed in advance of a contract breach to compensate the
‘innocent party’ for a breach of contract such as delay in completion of a project.
Clause 22.2: The Liquidated Damages stated in the Appendix is a genuine
pre-estimate of the loss and/or damage which the Employer will suffer in the
event that the Contractor is in the breach of Clause 21.0 and 22.0. The parties
agree that by entering into the Contract, the Contractor shall pay to the Employer
the said amount, if the same becomes due without the need for the Employer to
prove his loss and/or damages unless the contrary is proved by the Contractor.
General damages are to be assessed by the court at a hearing of the matter, and
could be for any amount from $1 up to an unlimited amount.
What is the difference between general damages and
liquidated damages?
“Q3: What are concurrent delays? Is the Contractor entitled to extension of time
and loss and expense if there are concurrent delays by Employer and
Contractor?
Concurrent delays can easily be defined as “Two or more delay events occurring
within the same time, each independently affecting the Completion Date of a
project.”
As it is rare for events to happen at the same time, not all of those events enable
the contractor to claim an extension of time or to claim loss and expense. Yet, it is
difficult in determining whether concurrent delays are allow an extension of time
and loss and expense claims.
➔ Employer Delay + No Contractor Delay = EOT & Cost
➔ Employer Delay + Contractor Delay = Depends on the case, Possibly only EOT no Cost.
➔ No Employer Delay + Contractor Delay = Liquidated Damages
Is the Contractor entitled to extension of time and loss and expense if there
are concurrent delays by Employer and Contractor?
➢ Depends how the contract has been amended and agreed
➢ Find out the cause of delays by both parties, to be view and determine for
extension of time and loss and expense
➢ Contractor is entitled to extension of time and loss and expense if the
dominant delays are caused by Employer
Case Study: City Inn v Shepherd Construction Ltd (2010)
The Facts:
The dispute was about late completion of a hotel in Bristol. The parties had entered into an
amended JCT standard form of building contract, 1980 edition. The contractor (Shepherd) had been
awarded a 4-week extension of time by the architect and was given an additional 5 weeks by an
adjudicator.
City Inn was unhappy with the adjudicator’s decision, and raised proceedings in the Court of
Session seeking various orders, including a declaration that the contractor was not entitled to a
single day by way of extension of time. Shepherd counterclaimed, seeking 11 weeks extension of
time and payment of associated loss and expense.
The Decision:
The Scottish Appeal Court decided that apportioning delay was appropriate & concluded that:
- The relevant event must delay or be likely to delay the works.
- If a dominant cause can be identified, this must be the relevant event.
- If no dominant cause can be identified, an apportionment should be made in a fair and
reasonable way.
Questions:
1. Will Contractor be automatically entitled to compensation due to
prolongation when EOT is granted to him?
Answer:
No. Entitlement to an EOT does not automatically lead to entitlement to
compensation.
Contractor will only be entitled to compensation if EOT is granted because of the
delay is caused by the Employer.
The Contractor will not be entitled to compensation if the EOT is granted due to
neutral events.
Questions:
2. If the Contractor is in the situation whereby his Works are affected
or bound to be affected by a heavy thunderstorm for a whole month,
under which clause under Relevant Events shall he apply EOT & what
are the particulars he should provide to support it?
▣ Answer:
23.8 (b) Exceptionally inclement weather
Eg. Let’s say it rains for the whole month in December and the
Completion Date is a few months after that, it would definitely
affect the Works. In some cases, Works can’t even be carried out
such as concrete works.
Therefore, Contractor needs to provide statistics of the weather
for the month of December from the past years for proof that it is
a month that is prone to thunderstorm.

More Related Content

What's hot

A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in WorksDr K M SONI
 
Commercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesCommercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesAMILA GAYAN
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explainedclaimsconsultancy
 
clause 51.0 and 53.0 - contract
clause 51.0 and 53.0 - contractclause 51.0 and 53.0 - contract
clause 51.0 and 53.0 - contractPavitrah Segaran
 
Construction claims management + project documentation seminar
Construction claims management + project documentation seminarConstruction claims management + project documentation seminar
Construction claims management + project documentation seminarKegler Brown Hill + Ritter
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"Abhishek Shah
 
Drafting Construction Contracts
Drafting Construction ContractsDrafting Construction Contracts
Drafting Construction ContractsMelissa Brumback
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industryKheng Hoe Advocates
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyFIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyKhalil Hasan
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011Tahir B Mirza
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byseenyeeyong
 

What's hot (20)

A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
 
Commercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesCommercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and Penalties
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explained
 
clause 51.0 and 53.0 - contract
clause 51.0 and 53.0 - contractclause 51.0 and 53.0 - contract
clause 51.0 and 53.0 - contract
 
Construction claims management + project documentation seminar
Construction claims management + project documentation seminarConstruction claims management + project documentation seminar
Construction claims management + project documentation seminar
 
Liquadated damages
Liquadated damagesLiquadated damages
Liquadated damages
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
FIDIC intro author eng. mohammed fadlalla
FIDIC intro  author eng. mohammed fadlallaFIDIC intro  author eng. mohammed fadlalla
FIDIC intro author eng. mohammed fadlalla
 
Drafting Construction Contracts
Drafting Construction ContractsDrafting Construction Contracts
Drafting Construction Contracts
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
 
Cl compilation
Cl compilationCl compilation
Cl compilation
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyFIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Liquidated damages
Liquidated damagesLiquidated damages
Liquidated damages
 
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-by
 

Similar to PP2 - Seminar Presentation

Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsEversheds Sutherland
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & AssociatesCerasela Angelescu
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
Cl compilation updated
Cl compilation updatedCl compilation updated
Cl compilation updatedYong Sy
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
2 claims under new fidic
2 claims under new fidic2 claims under new fidic
2 claims under new fidicAhmetArslan47
 
Dispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptxDispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptxPujanNeupane6
 
Construction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aConstruction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aColin Tomlinson
 
Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2Colin Tomlinson
 
Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015Colin Tomlinson
 
Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7ashleyyeap
 
Law relating-to-payment
Law relating-to-paymentLaw relating-to-payment
Law relating-to-paymentArthur Wilson
 
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدالمحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدEgyptian Engineers Association
 
Preserving Your Bottom Line
Preserving Your Bottom LinePreserving Your Bottom Line
Preserving Your Bottom LineCallPM
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Melvin Lim
 
ICM.pptx
ICM.pptxICM.pptx
ICM.pptxKoul5
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014SHKLaw
 

Similar to PP2 - Seminar Presentation (20)

Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contracts
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & Associates
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Cl compilation updated
Cl compilation updatedCl compilation updated
Cl compilation updated
 
Pp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyangPp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyang
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
2 claims under new fidic
2 claims under new fidic2 claims under new fidic
2 claims under new fidic
 
Dispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptxDispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptx
 
Construction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aConstruction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 a
 
Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2
 
Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015
 
Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7
 
Law relating-to-payment
Law relating-to-paymentLaw relating-to-payment
Law relating-to-payment
 
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدالمحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
 
Preserving Your Bottom Line
Preserving Your Bottom LinePreserving Your Bottom Line
Preserving Your Bottom Line
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
 
ICM.pptx
ICM.pptxICM.pptx
ICM.pptx
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 

More from Lin Hui

Financial Management
Financial ManagementFinancial Management
Financial ManagementLin Hui
 
Building Economics Presentation
Building Economics PresentationBuilding Economics Presentation
Building Economics PresentationLin Hui
 
Building Economics Report
Building Economics Report Building Economics Report
Building Economics Report Lin Hui
 
PP2 - Group Assignment
PP2 - Group AssignmentPP2 - Group Assignment
PP2 - Group AssignmentLin Hui
 
Measurement 4 presentation
Measurement 4 presentationMeasurement 4 presentation
Measurement 4 presentationLin Hui
 
Assignment - software application for qs
Assignment - software application for qs Assignment - software application for qs
Assignment - software application for qs Lin Hui
 
Software application report
Software application report Software application report
Software application report Lin Hui
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lin Hui
 
Estimating
Estimating Estimating
Estimating Lin Hui
 
Management science
Management scienceManagement science
Management scienceLin Hui
 
Biodiversity Presentation - Conservation on Tapir
Biodiversity Presentation - Conservation on Tapir  Biodiversity Presentation - Conservation on Tapir
Biodiversity Presentation - Conservation on Tapir Lin Hui
 
Building Services 2
Building Services 2 Building Services 2
Building Services 2 Lin Hui
 
Prefabricated timber framing systems
Prefabricated timber framing  systemsPrefabricated timber framing  systems
Prefabricated timber framing systemsLin Hui
 
Water treatment-for-domestic-water-supply - Report
Water treatment-for-domestic-water-supply - ReportWater treatment-for-domestic-water-supply - Report
Water treatment-for-domestic-water-supply - ReportLin Hui
 
Bs1 assignment semester 2016 august
Bs1 assignment   semester 2016 augustBs1 assignment   semester 2016 august
Bs1 assignment semester 2016 augustLin Hui
 
Water treatment-for-domestic-water-supply - Slides
Water treatment-for-domestic-water-supply - Slides Water treatment-for-domestic-water-supply - Slides
Water treatment-for-domestic-water-supply - Slides Lin Hui
 
M2 project assignment aug 2016
M2 project assignment aug 2016M2 project assignment aug 2016
M2 project assignment aug 2016Lin Hui
 
Ipoh railway station - Scientific Poster
Ipoh railway station - Scientific Poster Ipoh railway station - Scientific Poster
Ipoh railway station - Scientific Poster Lin Hui
 
Ms ct-bm
Ms ct-bmMs ct-bm
Ms ct-bmLin Hui
 
Integrated assignment m1 ct1 and bm mac 2016
Integrated assignment m1 ct1 and bm mac 2016Integrated assignment m1 ct1 and bm mac 2016
Integrated assignment m1 ct1 and bm mac 2016Lin Hui
 

More from Lin Hui (20)

Financial Management
Financial ManagementFinancial Management
Financial Management
 
Building Economics Presentation
Building Economics PresentationBuilding Economics Presentation
Building Economics Presentation
 
Building Economics Report
Building Economics Report Building Economics Report
Building Economics Report
 
PP2 - Group Assignment
PP2 - Group AssignmentPP2 - Group Assignment
PP2 - Group Assignment
 
Measurement 4 presentation
Measurement 4 presentationMeasurement 4 presentation
Measurement 4 presentation
 
Assignment - software application for qs
Assignment - software application for qs Assignment - software application for qs
Assignment - software application for qs
 
Software application report
Software application report Software application report
Software application report
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Estimating
Estimating Estimating
Estimating
 
Management science
Management scienceManagement science
Management science
 
Biodiversity Presentation - Conservation on Tapir
Biodiversity Presentation - Conservation on Tapir  Biodiversity Presentation - Conservation on Tapir
Biodiversity Presentation - Conservation on Tapir
 
Building Services 2
Building Services 2 Building Services 2
Building Services 2
 
Prefabricated timber framing systems
Prefabricated timber framing  systemsPrefabricated timber framing  systems
Prefabricated timber framing systems
 
Water treatment-for-domestic-water-supply - Report
Water treatment-for-domestic-water-supply - ReportWater treatment-for-domestic-water-supply - Report
Water treatment-for-domestic-water-supply - Report
 
Bs1 assignment semester 2016 august
Bs1 assignment   semester 2016 augustBs1 assignment   semester 2016 august
Bs1 assignment semester 2016 august
 
Water treatment-for-domestic-water-supply - Slides
Water treatment-for-domestic-water-supply - Slides Water treatment-for-domestic-water-supply - Slides
Water treatment-for-domestic-water-supply - Slides
 
M2 project assignment aug 2016
M2 project assignment aug 2016M2 project assignment aug 2016
M2 project assignment aug 2016
 
Ipoh railway station - Scientific Poster
Ipoh railway station - Scientific Poster Ipoh railway station - Scientific Poster
Ipoh railway station - Scientific Poster
 
Ms ct-bm
Ms ct-bmMs ct-bm
Ms ct-bm
 
Integrated assignment m1 ct1 and bm mac 2016
Integrated assignment m1 ct1 and bm mac 2016Integrated assignment m1 ct1 and bm mac 2016
Integrated assignment m1 ct1 and bm mac 2016
 

Recently uploaded

Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Salam Al-Karadaghi
 
Event 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxEvent 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxaryanv1753
 
Anne Frank A Beacon of Hope amidst darkness ppt.pptx
Anne Frank A Beacon of Hope amidst darkness ppt.pptxAnne Frank A Beacon of Hope amidst darkness ppt.pptx
Anne Frank A Beacon of Hope amidst darkness ppt.pptxnoorehahmad
 
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...NETWAYS
 
Dutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
Dutch Power - 26 maart 2024 - Henk Kras - Circular PlasticsDutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
Dutch Power - 26 maart 2024 - Henk Kras - Circular PlasticsDutch Power
 
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSimulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSebastiano Panichella
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Krijn Poppe
 
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
miladyskindiseases-200705210221 2.!!pptx
miladyskindiseases-200705210221 2.!!pptxmiladyskindiseases-200705210221 2.!!pptx
miladyskindiseases-200705210221 2.!!pptxCarrieButtitta
 
Work Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxWork Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxmavinoikein
 
The Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism PresentationThe Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism PresentationNathan Young
 
PHYSICS PROJECT BY MSC - NANOTECHNOLOGY
PHYSICS PROJECT BY MSC  - NANOTECHNOLOGYPHYSICS PROJECT BY MSC  - NANOTECHNOLOGY
PHYSICS PROJECT BY MSC - NANOTECHNOLOGYpruthirajnayak525
 
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfOpen Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfhenrik385807
 
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...NETWAYS
 
James Joyce, Dubliners and Ulysses.ppt !
James Joyce, Dubliners and Ulysses.ppt !James Joyce, Dubliners and Ulysses.ppt !
James Joyce, Dubliners and Ulysses.ppt !risocarla2016
 
Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170Escort Service
 
Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...
Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...
Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...marjmae69
 
Mathan flower ppt.pptx slide orchids ✨🌸
Mathan flower ppt.pptx slide orchids ✨🌸Mathan flower ppt.pptx slide orchids ✨🌸
Mathan flower ppt.pptx slide orchids ✨🌸mathanramanathan2005
 
Philippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptPhilippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptssuser319dad
 
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...NETWAYS
 

Recently uploaded (20)

Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
 
Event 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxEvent 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptx
 
Anne Frank A Beacon of Hope amidst darkness ppt.pptx
Anne Frank A Beacon of Hope amidst darkness ppt.pptxAnne Frank A Beacon of Hope amidst darkness ppt.pptx
Anne Frank A Beacon of Hope amidst darkness ppt.pptx
 
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
 
Dutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
Dutch Power - 26 maart 2024 - Henk Kras - Circular PlasticsDutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
Dutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
 
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSimulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
 
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
 
miladyskindiseases-200705210221 2.!!pptx
miladyskindiseases-200705210221 2.!!pptxmiladyskindiseases-200705210221 2.!!pptx
miladyskindiseases-200705210221 2.!!pptx
 
Work Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxWork Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptx
 
The Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism PresentationThe Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism Presentation
 
PHYSICS PROJECT BY MSC - NANOTECHNOLOGY
PHYSICS PROJECT BY MSC  - NANOTECHNOLOGYPHYSICS PROJECT BY MSC  - NANOTECHNOLOGY
PHYSICS PROJECT BY MSC - NANOTECHNOLOGY
 
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfOpen Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
 
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
 
James Joyce, Dubliners and Ulysses.ppt !
James Joyce, Dubliners and Ulysses.ppt !James Joyce, Dubliners and Ulysses.ppt !
James Joyce, Dubliners and Ulysses.ppt !
 
Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170
 
Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...
Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...
Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...
 
Mathan flower ppt.pptx slide orchids ✨🌸
Mathan flower ppt.pptx slide orchids ✨🌸Mathan flower ppt.pptx slide orchids ✨🌸
Mathan flower ppt.pptx slide orchids ✨🌸
 
Philippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptPhilippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.ppt
 
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
 

PP2 - Seminar Presentation

  • 1. Delays and Disputes Members: 1. Jacquelyn Vanessa Tee 2. Lee Lin Hui 3. Jason Teo Chun Chen
  • 2. Questions Q1: As a Consultant assessing an extension of time application by the Contractor, what are the initial checklist and the principles to be applied? Q2: What are the purpose of an extension of time clause in most standard contract and its implications? What is the implications of a Certificate of Non-Completion? What is the difference between general damages and liquidated damages? Q3: What are concurrent delays? Is the Contractor entitled to extension of time and loss and expense if there are concurrent delays by Employer and Contractor?
  • 3. “Q1: As a Consultant assessing an extension of time application by the Contractor, what are the initial checklist and the principles to be applied?
  • 4. Elements that needs to be clearly identified and present in the Contractor’s claims are: ▣ The Relevant Event [Clause 23.8(a) - 23.8(x)] - Related to Clause 23.1. ▣ Liability for the Relevant Event - Proving the Contractor did not contribute towards the event which is stated in the Conditions of Contract as being one which entitles the Contractor to an EOT. ▣ Contractual Entitlement - Contractor needs to state which clause or sub-clause under the PAM Contract he considers he is entitled to.
  • 5. ▣ Clause 23.1 - If the Contractor is of the opinion that the completion of the Works is or will be delayed beyond the Completion Date by any of the Relevant Events stated in Clause 23.8, he may apply for an extension of time provided always that: Sub-Clause 23.1(a) of the PAM Conditions states that the Contractor shall give written notice to the Architect of his intention to claim for an extension of time and that such notice must be given within twenty-eight (28) Days from the date of the Architects Instruction or the commencement date of the Relevant Event, whichever is the earlier and the giving of such a written notice shall be a condition precedent to an entitlement to an extension of time. Sub-Clause 23.1(b) within twenty eight (28) days of the end of the cause of delay, the Contractor shall send to the Architect his final claim for extension of time duly supported with all particulars to enable the Architect to assess any EOT to be granted. If the Contractor fails to submit such particulars within the state time (or within such longer period as may be agreed in writing by the Architect), it shall be deemed that the Contractor has assessed that such Relevant Event will not delay the completion of the Works beyond the Completion Date.
  • 6. ▣ Cause and Effect - Prepare facts describing the effects of the relevant event upon the Works. Should include details of the works that were affected and the status of the work. ▣ Substantiation - Contractor should provide copies of documentary evidence (eg. progress report and photos, minutes of meetings, programmes and schedules)
  • 7. “Q2: What are the purpose of an extension of time clause in most standard contract and its implications? What is the implications of a Certificate of Non-Completion? What is the difference between general damages and liquidated damages?
  • 8. Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor's fault. This is described as an extension of time (EOT). When it becomes reasonably apparent that there is, or that there is likely to be, a delay that could merit an extension of time, the contractor gives written notice to the contract administrator identifying the relevant event that has caused the delay. The purpose of an extension of time clause in the contract is to preserve liquidated damages and prevent the contract from being frustrated. The main beneficiary of the extension of time clause is the employer. What are the purpose of an extension of time clause in most standard contract and its implications?
  • 9. It is not uncommon for delays to cause the completion date to be missed, that is, the works are not complete, and so a certificate of practical completion cannot be issued by the date for completion. Employer will issues the contractor with a certificate of non-completion (sometimes referred to as a ‘non-completion certificate’ or ‘non-completion notice') as a prerequisite to claiming liquidated and ascertained damages. The certificate of non-completion gives formal written notice to the contractor that they have failed to complete the works described in the contract by the completion date that was last agreed (the original completion date may have been adjusted during the course of the works). ● Clause 22.1, 22.2 What is the implications of a Certificate of Non-Completion?
  • 10. Liquidated damages (sometimes referred to as agreed damages) are a fixed sum of money which has been agreed in advance of a contract breach to compensate the ‘innocent party’ for a breach of contract such as delay in completion of a project. Clause 22.2: The Liquidated Damages stated in the Appendix is a genuine pre-estimate of the loss and/or damage which the Employer will suffer in the event that the Contractor is in the breach of Clause 21.0 and 22.0. The parties agree that by entering into the Contract, the Contractor shall pay to the Employer the said amount, if the same becomes due without the need for the Employer to prove his loss and/or damages unless the contrary is proved by the Contractor. General damages are to be assessed by the court at a hearing of the matter, and could be for any amount from $1 up to an unlimited amount. What is the difference between general damages and liquidated damages?
  • 11. “Q3: What are concurrent delays? Is the Contractor entitled to extension of time and loss and expense if there are concurrent delays by Employer and Contractor?
  • 12. Concurrent delays can easily be defined as “Two or more delay events occurring within the same time, each independently affecting the Completion Date of a project.” As it is rare for events to happen at the same time, not all of those events enable the contractor to claim an extension of time or to claim loss and expense. Yet, it is difficult in determining whether concurrent delays are allow an extension of time and loss and expense claims. ➔ Employer Delay + No Contractor Delay = EOT & Cost ➔ Employer Delay + Contractor Delay = Depends on the case, Possibly only EOT no Cost. ➔ No Employer Delay + Contractor Delay = Liquidated Damages
  • 13. Is the Contractor entitled to extension of time and loss and expense if there are concurrent delays by Employer and Contractor? ➢ Depends how the contract has been amended and agreed ➢ Find out the cause of delays by both parties, to be view and determine for extension of time and loss and expense ➢ Contractor is entitled to extension of time and loss and expense if the dominant delays are caused by Employer
  • 14. Case Study: City Inn v Shepherd Construction Ltd (2010) The Facts: The dispute was about late completion of a hotel in Bristol. The parties had entered into an amended JCT standard form of building contract, 1980 edition. The contractor (Shepherd) had been awarded a 4-week extension of time by the architect and was given an additional 5 weeks by an adjudicator. City Inn was unhappy with the adjudicator’s decision, and raised proceedings in the Court of Session seeking various orders, including a declaration that the contractor was not entitled to a single day by way of extension of time. Shepherd counterclaimed, seeking 11 weeks extension of time and payment of associated loss and expense. The Decision: The Scottish Appeal Court decided that apportioning delay was appropriate & concluded that: - The relevant event must delay or be likely to delay the works. - If a dominant cause can be identified, this must be the relevant event. - If no dominant cause can be identified, an apportionment should be made in a fair and reasonable way.
  • 15.
  • 16. Questions: 1. Will Contractor be automatically entitled to compensation due to prolongation when EOT is granted to him? Answer: No. Entitlement to an EOT does not automatically lead to entitlement to compensation. Contractor will only be entitled to compensation if EOT is granted because of the delay is caused by the Employer. The Contractor will not be entitled to compensation if the EOT is granted due to neutral events.
  • 17. Questions: 2. If the Contractor is in the situation whereby his Works are affected or bound to be affected by a heavy thunderstorm for a whole month, under which clause under Relevant Events shall he apply EOT & what are the particulars he should provide to support it?
  • 18. ▣ Answer: 23.8 (b) Exceptionally inclement weather Eg. Let’s say it rains for the whole month in December and the Completion Date is a few months after that, it would definitely affect the Works. In some cases, Works can’t even be carried out such as concrete works. Therefore, Contractor needs to provide statistics of the weather for the month of December from the past years for proof that it is a month that is prone to thunderstorm.